Beruflich Dokumente
Kultur Dokumente
Project Zephyr
Progress Report 8
Vallabi Vallaban
Kelly Crocker
Noah Wong
Objective:
This time was spent determining the Mylar and valve configurations and testing the solar panels.
Previous Objective:
The focus of this time was finishing the support diagram and designing the payload container
cross-section of the blimp were conducted in an effort to determine the length of Mylar
the blimp.
Figure 3: The decided Mylar configuration for the blimp consists of two sheets of Mylar
wrapping around the body of the blimp with two nosepieces joining the ends at either point.
PROJECT ZEPHYR PROGRESS REPORT 8 4
Figure 4: This is the nosecone design for the blimp as based upon other models.
One of the major focuses during this time was coming to a decision about how the Mylar
would be oriented around the blimp frame. The team opted to have a basic design with two
sheets of Mylar, each roughly 5.3 m long, wrapping around the belly of the blimp and forming a
seam around the circumference of the blimp. The length of Mylar needed was calculated by the
equations shown in Figures 1 and 2 to find the circumference of the blimp. This will take up
roughly one roll of Mylar leaving the other one to be used for repairs, seams around the rudder,
payload container, and valve, as well as nosecone pieces. A nosecone is meant to gather all the
loose, jagged ends of the two main sheets of Mylar around the ends of the blimp and provide a
surface to heat seal them all together and maintain an airtight pocket within the blimp.
PROJECT ZEPHYR PROGRESS REPORT 8 5
Figure 5: This Inventor sketch shows the configuration of the payload container to house the
The payload container was completed in Inventor with a lid, or rather, removable bottom,
added to the design to allow for the insertion of the electronic devices while keeping an airtight
seal with the air pocket. The container itself will not be airtight, as the sensors need access to the
atmosphere in order to give accurate readings. Also, the design allows for air holes to be drilled
through the walls of the payload container for cooling purposes, as the electronics are in a plastic
box and the team would like to keep everything from melting. The design was submitted for 3D
While the payload container was being designed and sent off for printing, the epoxy and
foam board to make the actual frame of the blimp were ordered and are expected to arrive within
PROJECT ZEPHYR PROGRESS REPORT 8 6
the near future. Two 8ft by 4ft by 0.75in sheets of foam board will be used to construct the struts
In addition to the Mylar, payload container, and supports, the team investigated the
necessary connection to transfer helium from an industrial tank and into the blimp. It was
discovered that the general connection on an inert gas industrial tank is a CGA-580 connection.
However, there is a possibility that the tank the team will order will not have this connection, so
an adaptor has not been bought at this time. Despite this uncertainty, the team has a plan in place
with which to insert helium into the blimp. An adaptor will be purchased to connect the tank to
an air hose. This air hose will deliver helium into the blimp through a small fortified flap that
Overall 21.164
Average
Figure 6: Data from the experiment performed on 21 February 2017, to discover the average
The main experimental aspect of this time came from the testing of the solar panels to
determine their average output voltage. The panels, stored in boxes labeled with their letter, were
laid on the concrete half wall outside of Discovery Hall on the George Mason campus at
Innovation Park. They were arranged in alphabetical order and positioned on top of their
respective boxes in order to avoid any shadows. The voltage reading was taken with a multimeter
seven times over the course of fifteen minutes starting at 9:40 am. The procedure of one trial was
to take the reading from Panel A, then move on to Panel B about 25 seconds later. When Panel D
had been tested, a new trial was immediately begun starting again with a reading from Panel A.
PROJECT ZEPHYR PROGRESS REPORT 8 8
As shown in Figure 7 below, the outputs were relatively consistent taking into account
minute shifts in the weather and the cloud cover that moved in about 3 minutes into the
experiment. This conclusion is supported by the higher voltages output during Trial 1 when there
was a lack of cloud cover. The average voltage of 21.16 supports the need for a step down
converter to bridge the gap between the solar charge converter and Raspberry Pi, which runs on
5V.
Figure 7: This graph shows the output of each solar panel according to trial number.
PROJECT ZEPHYR PROGRESS REPORT 8 9
Resources
Freudenrich, P. C. (2001, February 26). How Blimps Work. Retrieved February 22, 2017, from
http://science.howstuffworks.com/transport/flight/modern/blimp1.htm.
GAS CONNECTION ASSIGNMENT TABLE . (1999, March). Retrieved February 22, 2017,
from http://mfc.engr.arizona.edu/documents/gas%20finttings%20connections.htm.