1 2 New, and opening date in the past SAP has created a new requisition and
scheduled it appropriately based on the demand, however, given the lead
time of the material the Purchase Order should have already been issued to
the supplier. High potential that this order will need to be expedited!
Critical
2 3 New, and start date in the past The order or requisition is scheduled to
start in the past. High potential that this order will
need to be expedited or that the demand can not be supplied! Critical
3 4 New, and finish date in the past The order or requisition is scheduled to
finish in the past. High potential that this order will
need to be expedited or that the demand can not be supplied! Critical
5 50 No BOM exists SAP was unable to find a valid Bill Of Material for the
item. Check the BOM, Production Version & Selection Method. Error
5 52 No BOM selected SAP was unable to find a valid Bill Of Material for the
item. Check the BOM, Production Version & Selection Method. Error
5 55 Phantom assembly not exploded SAP was unable to find a valid Bill
Of Material for the phantom material. Check the BOM or contact the
Helpdesk for assistance with this error. Error
6 96 Stock fallen below safety stock level Supply plan insufficient to cover
safety stock requirement. Review and adjust if appropriate. Important