Beruflich Dokumente
Kultur Dokumente
VOLUME - I
ANALYSIS FOR SCHEDULE OF RATES 2009
(VOLUME I)
CONTENTS
Chapter No. Name of Sub-head Page No.
I Labour Basic Rates 1 to 4
II Materials for buildings and roads 5 to 86
III Hire Charges of Plants 87 to 90
IV Mortars 91 to 108
V Loading and Unloading 109 to 120
VI Carriage by :-
1) Manual Labour 121 to 129
2) Mechanical Transport 130 to 139
3) Animal Transport 140 to 153
VII Earth Work 154 to 186
VIII Form Work 187 to 258
IX Concrete 259 to 358
CHAPTER I
LABOUR
BASIC RATES
Notes : -
(1) These rates are exclusive of contractors profit and overheads and do not take into account
one days paid holiday after six working days. (The rates adopted in rate-analysis are 7/6th of
these basic rates so as to include the effect on one holiday after every six working days).
(2) For employment of departmental labour on muster-rolls, the rates given below may be
considered as maximum rates upto which an Executive Engineer can authorise employment
of labour. If in a certain locality, prevailing conditions necessitate payment of higher rates of
wages, the Superintending Engineer shall increase the rates suitably for a specified period,
not exceeding 3 months after which the rates should be reviewed again and revised
downwards if the conditions so warrant.
CHAPTER -I
Notes : -
(1) All the rates in this chapter are for the materials ex-P.W.D. Store except where specified
otherwise.
(2) These rates are exclusive of carriage, contractors profit and overheads but include Octroi,
Toll-tax, Malkana, Royalty, Sales Tax etc. wherever applicable.
(3) The rates are for the purpose of analysing the rates of items of work are not for obtaining
supplies from open market. Supplies shall be obtained either through Controller of Stores,
H.P. or after calling tender or quotations as may be required under rules and order in force.
(4) The rates shall not be used for issuing materials from Government Stores.
CHAPTER -II
MORTARS
Chapter IV
MORTARS
Notes : -
1. These rates are exclusive of contractors profit and overheads but include octroi, royalty etc.
2. Water charges have been allowed on the cost of the Mortar under basic rates but this has
been allowed in the Analysis of complete item in which these Mortars are used.
3. The Analysis of rates containing lime are based on the use of lime in form of putty; where
dry hydrated lime is used, the analysis shall be suitably modified as per relevant
specifications.
CHAPTER-IV
Mortar
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
0401 lime mortar1:1
(1 lime putty :1 sand )
Detail of cost for 1 cum
MATERIAL :
lime: qtl. 4.510 500.00 2255.00
sand cu.m 0.712 300.00 213.60
CARRIAGE :
Lime
1 KM BY MECH. TRANSPORT 1 Cum. 0.580 92.45 53.62
100 MTRS BY HEAD LOAD 1 cum 0.580 43.48 25.22
Sand
1 KM BY MECH. TRANSPORT 1 Cum. 0.713 110.95 79.11
100 MTRS BY HEAD LOAD 1 cum 0.713 54.35 38.75
LABOUR :
Beldar each 2.500 116.67 291.68
Bhishti each 0.450 116.67 52.50
SUNDRIES : 14.00
COST PER cu.m 3023.47 say 3023.45
LABOUR PER cu.m 358.18
LABOUR RATE :
ACTUAL LABOUR: 344.18
SUNDRIES : 14.00
LABOUR PER cu.m 358.18
MATERIAL :
lime: qtl. 3.010 500.00 1505.00
sand cu.m 0.950 300.00 285.00
CARRIAGE :
Lime
1 KM BY MECH. TRANSPORT 1 Cum. 0.390 92.45 36.06
100 MTRS BY HEAD LOAD 1 cum 0.390 43.48 16.96
Sand
1 KM BY MECH. TRANSPORT 1 Cum. 0.950 110.95 105.40
100 MTRS BY HEAD LOAD 1 cum 0.950 54.35 51.63
LABOUR :
Beldar each 2.500 116.67 291.68
Bhishti each 0.450 116.67 52.50
SUNDRIES : 14.00
COST PER cum. 2358.20
LABOUR PER cum. 358.15
LABOUR RATE :
ACTUAL LABOUR: 344.18
SUNDRIES : 14.00
Mortar
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR PER cum. 358.15
MATERIAL :
lime: qtl. 2.260 500.00 1130.00
sand cu.m 1.070 300.00 321.00
CARRIAGE :
Lime
1 KM BY MECH. TRANSPORT 1 Cum. 0.290 92.45 26.81
100 MTRS BY HEAD LOAD 1 cum 0.290 43.48 12.61
Sand
1 KM BY MECH. TRANSPORT 1 Cum. 1.070 110.95 118.72
100 MTRS BY HEAD LOAD 1 cum 1.070 54.35 58.15
LABOUR :
Beldar each 2.500 116.67 291.68
Bhishti each 0.450 116.67 52.50
SUNDRIES : 14.00
COST PER cum. 2025.45
LABOUR PER cum. 358.15
LABOUR RATE :
ACTUAL LABOUR: 344.18
SUNDRIES : 14.00
LABOUR PER cum. 358.15
MATERIAL :
lime: qtl. 4.510 500.00 2255.00
Stone.(Surkhi) cu.m 0.712 420.00 299.04
CARRIAGE :
Lime
1 KM BY MECH. TRANSPORT 1 Cum. 0.580 92.45 53.62
100 MTRS BY HEAD LOAD 1 cum 0.580 43.48 25.22
Surkhi
1 KM BY MECH. TRANSPORT 1 cum 0.712 92.45 65.82
100 MTRS BY HEAD LOAD 1 cum 0.712 43.48 30.96
LABOUR :
Beldar each 2.500 116.67 291.68
Bhishti each 0.450 116.67 52.50
SUNDRIES : 14.00
COST PER cum. 3087.80
Mortar
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR PER cum. 358.15
LABOUR RATE :
ACTUAL LABOUR: 344.18
SUNDRIES : 14.00
LABOUR PER cum. 358.15
MATERIAL :
lime: qtl. 3.010 500.00 1505.00
Stone.(Surkhi) cu.m 0.950 420.00 399.00
CARRIAGE :
Lime
1 KM BY MECH. TRANSPORT 1 Cum. 0.390 92.45 36.06
100 MTRS BY HEAD LOAD 1 cum 0.390 43.48 16.96
Surkhi
1 KM BY MECH. TRANSPORT 1 cum 0.950 92.45 87.83
100 MTRS BY HEAD LOAD 1 cum 0.950 43.48 41.31
LABOUR :
Beldar each 2.500 116.67 291.68
Bhishti each 0.450 116.67 52.50
SUNDRIES : 14.00
COST PER cum. 2444.30
LABOUR PER cum. 358.15
LABOUR RATE :
ACTUAL LABOUR: 344.18
SUNDRIES : 14.00
LABOUR PER cum. 358.15
MATERIAL :
lime: qtl. 2.260 500.00 1130.00
Stone.(Surkhi) cu.m 1.070 420.00 449.40
CARRIAGE :
Lime
1 KM BY MECH. TRANSPORT 1 Cum. 0.290 92.45 26.81
100 MTRS BY HEAD LOAD 1 cum 0.290 43.48 12.61
Surkhi
1 KM BY MECH. TRANSPORT 1 cum 1.070 92.45 98.92
100 MTRS BY HEAD LOAD 1 cum 1.070 43.48 46.52
LABOUR :
Mortar
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Beldar each 2.500 116.67 291.68
Bhishti each 0.450 116.67 52.50
SUNDRIES : 14.00
COST PER cum. 2122.42
LABOUR PER cum. 358.15
LABOUR RATE :
ACTUAL LABOUR: 344.18
SUNDRIES : 14.00
LABOUR PER cum. 358.15
MATERIAL :
lime: qtl. 2.260 500.00 1130.00
Stone.(Surkhi) cu.m 0.357 420.00 149.94
sand cu.m 0.714 300.00 214.20
CARRIAGE :
Mortar
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Lime
1 KM BY MECH. TRANSPORT 1 Cum. 0.290 92.45 26.81
100 MTRS BY HEAD LOAD 1 cum 0.290 43.48 12.61
Surkhi
1 KM BY MECH. TRANSPORT 1 cum 0.357 92.45 33.00
100 MTRS BY HEAD LOAD 1 cum 0.357 43.48 15.52
Sand
1 KM BY MECH. TRANSPORT 1 Cum. 0.714 110.95 79.22
100 MTRS BY HEAD LOAD 1 cum 0.714 54.35 38.81
LABOUR :
Beldar each 2.500 116.67 291.68
Bhishti each 0.450 116.67 52.50
SUNDRIES : 14.00
COST PER cum. 2058.25
LABOUR PER cum. 358.15
LABOUR RATE :
ACTUAL LABOUR: 344.18
SUNDRIES : 14.00
LABOUR PER cum. 358.15
MATERIAL :
Cement : tonne 1.020 4900.00 4998.00
sand cu.m 0.712 300.00 213.00
CARRIAGE :
Cement
1 KM BY MECH. TRANSPORT 1 Tonne. 1.020 73.95 75.43
MATERIAL :
Cement : tonne 0.680 4900.00 3332.00
sand cu.m 0.950 300.00 285.00
CARRIAGE :
Cement
1 KM BY MECH. TRANSPORT 1 Tonne. 0.680 73.95 50.29
Cemen
100 MTRS BY HEAD LOAD 1 Tonne 0.680 31.20 21.22
Sand
1 KM BY MECH. TRANSPORT 1 Cum. 0.950 110.95 105.40
100 MTRS BY HEAD LOAD 1 cum 0.950 54.35 51.63
LABOUR :
Beldar each 0.900 116.67 105.00
Bhishti each 0.080 116.67 9.33
SUNDRIES : 14.00
COST PER cum. 3973.85
LABOUR PER cum. 128.35
LABOUR RATE :
ACTUAL LABOUR: 114.34
SUNDRIES : 14.00
LABOUR PER cum. 128.35
MATERIAL :
Cement : tonne 0.510 4900.00 2499.00
sand cu.m 1.070 300.00 321.00
CARRIAGE :
Cement
1 KM BY MECH. TRANSPORT 1 Tonne. 0.510 73.95 37.71
Cemen
100 MTRS BY HEAD LOAD 1 Tonne 0.510 31.20 15.91
Sand
1 KM BY MECH. TRANSPORT 1 Cum. 1.070 110.95 118.72
100 MTRS BY HEAD LOAD 1 cum 1.070 54.35 58.15
LABOUR :
Beldar each 0.900 116.67 105.00
Bhishti each 0.080 116.67 9.33
SUNDRIES : 14.00
COST PER cum. 3178.80
LABOUR PER cum. 128.35
LABOUR RATE :
ACTUAL LABOUR: 114.34
Mortar
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
SUNDRIES : 14.00
LABOUR PER cum. 128.35
MATERIAL :
Cement : tonne 0.380 4900.00 1862.00
sand cu.m 1.070 300.00 321.00
CARRIAGE :
Cement
1 KM BY MECH. TRANSPORT 1 Tonne. 0.380 73.95 28.10
Cemen
100 MTRS BY HEAD LOAD 1 Tonne 0.380 31.20 11.86
Sand
1 KM BY MECH. TRANSPORT 1 Cum. 1.070 110.95 118.72
100 MTRS BY HEAD LOAD 1 cum 1.070 54.35 58.15
LABOUR :
Beldar each 0.900 116.67 105.00
Bhishti each 0.080 116.67 9.33
SUNDRIES : 14.00
COST PER cum. 2528.15
LABOUR PER cum. 128.35
LABOUR RATE :
ACTUAL LABOUR: 114.34
SUNDRIES : 14.00
LABOUR PER cum. 128.35
MATERIAL :
Cement : tonne 0.310 4900.00 1519.00
sand cu.m 1.070 300.00 321.00
CARRIAGE :
Cement
1 KM BY MECH. TRANSPORT 1 Tonne. 0.310 73.95 22.92
Cemen
100 MTRS BY HEAD LOAD 1 Tonne 0.310 31.20 9.67
Sand
1 KM BY MECH. TRANSPORT 1 Cum. 1.070 110.95 118.72
100 MTRS BY HEAD LOAD 1 cum 1.070 54.35 58.15
LABOUR :
Beldar each 0.900 116.67 105.00
Mortar
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Bhishti each 0.080 116.67 9.33
SUNDRIES : 14.00
COST PER cum. 2177.80
LABOUR PER cum. 128.34
LABOUR RATE :
ACTUAL LABOUR: 114.34
SUNDRIES : 14.00
LABOUR PER cum. 128.35
MATERIAL :
Cement : tonne 0.250 4900.00 1225.00
sand cu.m 1.070 300.00 321.00
CARRIAGE :
Cement
1 KM BY MECH. TRANSPORT 1 Tonne. 0.250 73.95 18.49
Cemen
100 MTRS BY HEAD LOAD 1 Tonne 0.250 31.20 7.80
Sand
1 KM BY MECH. TRANSPORT 1 Cum. 1.070 110.95 118.72
100 MTRS BY HEAD LOAD 1 cum 1.070 54.35 58.15
LABOUR :
Beldar each 0.900 116.67 105.00
Bhishti each 0.080 116.67 9.33
SUNDRIES : 14.00
COST PER cum. 1877.50
LABOUR PER cum. 128.35
LABOUR RATE :
ACTUAL LABOUR: 114.34
SUNDRIES : 14.00
LABOUR PER cum. 128.35
MATERIAL :
Cement : tonne 0.220 4900.00 1078.00
sand cu.m 1.070 300.00 321.00
CARRIAGE :
Cement
Mortar
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
1 KM BY MECH. TRANSPORT 1 Tonne. 0.220 73.95 16.27
Cemen
100 MTRS BY HEAD LOAD 1 Tonne 0.220 31.20 6.86
Sand
1 KM BY MECH. TRANSPORT 1 Cum. 1.070 110.95 118.72
100 MTRS BY HEAD LOAD 1 cum 1.070 54.35 58.15
LABOUR :
Beldar each 0.900 116.67 105.00
Bhishti each 0.080 116.67 9.33
SUNDRIES : 14.00
COST PER cum. 1727.35
LABOUR PER cum. 128.35
LABOUR RATE :
ACTUAL LABOUR: 114.34
SUNDRIES : 14.00
LABOUR PER cum. 128.35
MATERIAL :
Cement : tonne 0.190 4900.00 931.00
sand cu.m 1.070 300.00 321.00
CARRIAGE :
Cement
1 KM BY MECH. TRANSPORT 1 Tonne. 0.190 73.95 14.05
Cemen
100 MTRS BY HEAD LOAD 1 Tonne 0.190 31.20 5.93
Sand
1 KM BY MECH. TRANSPORT 1 Cum. 1.070 110.95 118.72
100 MTRS BY HEAD LOAD 1 cum 1.070 54.35 58.15
LABOUR :
Beldar each 0.900 116.67 105.00
Bhishti each 0.080 116.67 9.33
SUNDRIES : 14.00
COST PER cum. 1577.20
LABOUR PER cum. 128.35
LABOUR RATE :
ACTUAL LABOUR: 114.34
SUNDRIES : 14.00
LABOUR PER cum. 128.35
MATERIAL :
Cement : tonne 0.380 4900.00 1862.00
lime: qtl. 1.700 500.00 850.00
sand cu.m 1.070 300.00 321.00
CARRIAGE :
Cement
1 KM BY MECH. TRANSPORT 1 Tonne. 0.380 73.95 28.10
Cemen
100 MTRS BY HEAD LOAD 1 Tonne 0.380 31.20 11.86
Lime
1 KM BY MECH. TRANSPORT 1 Cum. 0.220 92.45 20.34
100 MTRS BY HEAD LOAD 1 cum 0.220 43.48 9.57
Sand
1 KM BY MECH. TRANSPORT 1 Cum. 1.070 110.95 118.72
100 MTRS BY HEAD LOAD 1 cum 1.070 54.35 58.15
LABOUR :
Beldar each 2.500 116.67 291.68
Mortar
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Bhishti each 0.450 116.67 52.50
SUNDRIES : 14.00
COST PER cum. 3637.90
LABOUR PER cum. 358.15
LABOUR RATE :
ACTUAL LABOUR: 344.18
SUNDRIES : 14.00
358.15
MATERIAL :
Cement : tonne 0.310 4900.00 1519.00
lime: qtl. 1.350 500.00 675.00
sand cu.m 1.070 300.00 321.00
CARRIAGE :
Cement
1 KM BY MECH. TRANSPORT 1 Tonne. 0.310 73.95 22.92
Cemen
100 MTRS BY HEAD LOAD 1 Tonne 0.310 31.20 9.67
Lime
1 KM BY MECH. TRANSPORT 1 Cum. 0.174 92.45 16.08
100 MTRS BY HEAD LOAD 1 cum 0.174 43.48 7.56
Sand
1 KM BY MECH. TRANSPORT 1 Cum. 1.070 110.95 118.72
100 MTRS BY HEAD LOAD 1 cum 1.070 54.35 58.15
LABOUR :
Beldar each 2.500 116.67 291.67
Bhishti each 0.450 116.67 52.50
SUNDRIES : 14.00
COST PER cum. 3106.25
LABOUR PER cum. 358.15
LABOUR RATE :
ACTUAL LABOUR: 344.17
SUNDRIES : 14.00
LABOUR PER cum. 358.15
MATERIAL :
Cement : tonne 0.250 4900.00 1225.00
lime: qtl. 1.130 500.00 565.00
Mortar
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
sand cu.m 1.070 300.00 321.00
CARRIAGE :
Cement
1 KM BY MECH. TRANSPORT 1 Tonne. 0.250 73.95 18.49
Cemen
100 MTRS BY HEAD LOAD 1 Tonne 0.250 31.20 7.80
Lime
1 KM BY MECH. TRANSPORT 1 Cum. 0.150 92.45 13.87
100 MTRS BY HEAD LOAD 1 cum 0.150 43.48 6.52
Sand
1 KM BY MECH. TRANSPORT 1 Cum. 1.070 110.95 118.72
100 MTRS BY HEAD LOAD 1 cum 1.070 54.35 58.15
LABOUR :
Beldar each 2.500 116.67 291.68
Bhishti each 0.450 116.67 52.50
SUNDRIES : 14.00
COST PER cum. 2692.70
LABOUR PER cum. 358.15
LABOUR RATE :
ACTUAL LABOUR: 344.18
SUNDRIES : 14.00
LABOUR PER cum. 358.15
MATERIAL :
Cement : tonne 0.220 4900.00 1078.00
lime: qtl. 0.970 500.00 485.00
sand cu.m 1.070 300.00 321.00
CARRIAGE :
Cement
1 KM BY MECH. TRANSPORT 1 Tonne. 0.220 73.95 16.26
Cemen
100 MTRS BY HEAD LOAD 1 Tonne 0.220 31.20 6.86
Lime
1 KM BY MECH. TRANSPORT 1 Cum. 0.130 92.45 12.00
100 MTRS BY HEAD LOAD 1 cum 0.130 43.48 5.65
Sand
1 KM BY MECH. TRANSPORT 1 Cum. 1.070 110.95 118.71
100 MTRS BY HEAD LOAD 1 cum 1.070 54.35 58.15
LABOUR :
Beldar each 2.500 116.67 291.67
Bhishti each 0.450 116.67 52.50
SUNDRIES : 14.00
COST PER cum. 2459.80
LABOUR PER cum. 358.15
Mortar
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR: 344.17
SUNDRIES : 14.00
LABOUR PER cum. 358.15
MATERIAL :
Cement : tonne 0.190 4900.00 931.00
lime: qtl. 0.840 500.00 420.00
sand cu.m 1.070 300.00 321.00
CARRIAGE :
Cement
1 KM BY MECH. TRANSPORT 1 Tonne. 0.190 73.95 14.05
Cement
100 MTRS BY HEAD LOAD 1 Tonne 0.190 31.20 5.93
Lime
1 KM BY MECH. TRANSPORT 1 Cum. 0.110 92.45 10.17
100 MTRS BY HEAD LOAD 1 cum 0.110 43.48 4.78
Sand
1 KM BY MECH. TRANSPORT 1 Cum. 1.070 110.95 118.72
100 MTRS BY HEAD LOAD 1 cum 1.070 54.35 58.15
LABOUR :
Beldar each 2.500 116.67 291.68
Bhishti each 0.450 116.67 52.50
SUNDRIES : 14.00
COST PER cum. 2241.95
LABOUR PER cum. 358.15
LABOUR RATE :
ACTUAL LABOUR: 344.18
SUNDRIES : 14.00
LABOUR PER cum. 358.15
MATERIAL :
Cement : tonne 0.150 4900.00 735.00
lime: qtl. 0.670 500.00 335.00
sand cu.m 1.070 300.00 321.00
CARRIAGE :
Cement
1 KM BY MECH. TRANSPORT 1 Tonne. 0.150 73.95 11.09
Cemen
100 MTRS BY HEAD LOAD 1 Tonne 0.150 31.20 4.68
Lime
1 KM BY MECH. TRANSPORT 1 Cum. 0.090 92.45 8.32
100 MTRS BY HEAD LOAD 1 cum 0.090 43.48 3.91
Sand
1 KM BY MECH. TRANSPORT 1 Cum. 1.070 110.95 118.72
100 MTRS BY HEAD LOAD 1 cum 1.070 54.35 58.15
LABOUR :
Beldar each 2.500 116.67 291.68
Bhishti each 0.450 116.67 52.50
SUNDRIES : 14.00
COST PER cum. 1954.05
LABOUR PER cum. 358.15
LABOUR RATE :
ACTUAL LABOUR: 344.18
SUNDRIES : 14.00
LABOUR PER cum. 358.15
Mortar
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
Cement : tonne 0.170 4900.00 833.00
lime: qtl. 1.510 500.00 755.00
sand cu.m 1.070 300.00 321.00
CARRIAGE :
Cement
1 KM BY MECH. TRANSPORT 1 Tonne. 0.170 73.95 12.57
Cemen
100 MTRS BY HEAD LOAD 1 Tonne 0.170 31.20 5.30
Lime
1 KM BY MECH. TRANSPORT 1 Cum. 0.200 92.45 18.49
100 MTRS BY HEAD LOAD 1 cum 0.200 43.48 8.70
Sand
1 KM BY MECH. TRANSPORT 1 Cum. 1.070 110.95 118.72
100 MTRS BY HEAD LOAD 1 cum 1.070 54.35 58.15
LABOUR :
Beldar each 2.500 116.67 291.68
Bhishti each 0.450 116.67 52.50
SUNDRIES : 14.00
COST PER cum. 2489.10
LABOUR PER cum. 358.15
LABOUR RATE :
ACTUAL LABOUR: 344.18
SUNDRIES : 14.00
LABOUR PER cum. 358.15
MATERIAL :
Cement : tonne 0.130 4900.00 637.00
lime: qtl. 1.700 500.00 850.00
sand cu.m 1.070 300.00 321.00
CARRIAGE :
Cement
1 KM BY MECH. TRANSPORT 1 Tonne. 0.130 73.95 9.61
Cemen
100 MTRS BY HEAD LOAD 1 Tonne 0.130 31.20 4.06
Lime
Mortar
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
1 KM BY MECH. TRANSPORT 1 Cum. 0.220 92.45 20.34
100 MTRS BY HEAD LOAD 1 cum 0.220 43.48 9.57
Sand
1 KM BY MECH. TRANSPORT 1 Cum. 1.070 110.95 118.72
100 MTRS BY HEAD LOAD 1 cum 1.070 54.35 58.15
LABOUR :
Beldar each 2.500 116.67 291.68
Bhishti each 0.450 116.67 52.50
SUNDRIES : 14.00
COST PER cum. 2386.60
LABOUR PER cum. 358.15
LABOUR RATE :
ACTUAL LABOUR: 344.18
SUNDRIES : 14.00
LABOUR PER cum. 358.15
MATERIAL :
Good earth cu.m. 1.200 75.00 90.00
CARRIAGE :
Mud dr
1 KM BY MECH. TRANSPORT 1 cum 1.200 92.45 110.94
100 MTRS BY HEAD LOAD 1 cum 1.200 43.48 52.18
LABOUR :
Beldar each 0.700 116.67 81.67
Bhishti each 0.350 116.67 40.83
SUNDRIES : 5.00
COST PER cum. 380.60
LABOUR PER cum. 127.50
LABOUR RATE :
ACTUAL LABOUR: 122.50
SUNDRIES : 5.00
LABOUR PER cum. 127.50
CHAPTER V
Notes : -
1. The rates given below have been worked out for loading/un-loading of materials by
engaging Departmental labour. The rates are applicable for loading/un-loading of
materials from non- tipping trucks/railway wagons. As for as possible, the Engineer-In-
Charge should ensure that unloading of wagons is carried out by Departmental labour.
However, where effective utilization of the Departmental labour is not possible and
further the exigencies of a particular situation demand the un-loading of materials from
railways wagons at inconvenient the Engineer-In-Charge is authorised to get the un-
loading done at the market rates.
2. The rates on un-loading the materials, like sand, stone blast etc. from tipping trucks shall
be reduced by 50%. There shall however be no reduction in rates for loading.
3. Where the lead for loading and un-loading is more than the lead specified in the rates,
this shall be paid at the carriage rates worked out on the basis of the most economic mode
of transport and paid at the carriage rates applicable.
4. The rates include the loading of materials in truck in such a way so that no harm accures
to the loaded materials and further there is full utilization of the available space in the
truck/wagon.
5. The rates do not include the stacking of the un-loaded materials except where specified.
The rates for stacking shall be paid for the various materials as enumerated in items Nos.
0514U to 0518U.
6. The rate do not account for any special arrangement such as provision of mechanical
equipment for loading/un-loading purposes. The un-loading of heavy machinery or
consignments requiring. Crane work or any other special arrangement will be done
departmentally or paid for on the merits of the individual case.
7. The unit rates are applicable for net quantity of the materials loaded/un-loaded.
8. The contractors profit and overhead charges have not been allowed on these rates but the
same has been allowed in the analysis of complete items where it containing these
charges.
CHAPTER V
3.95
COST FOR 1 qtl.
0506L loading in the wagons/Non-tipping trucks
within 20 mtrs.lead.
structural steel G.I,C.C.,R.C.C.
pipes upto 500 mm diametre and
special,C.I.manholes,cover,steps other
casting and ancilary items like
lead,hamps,rope etc.
Loading and Unloading
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
CODE
Detail of cost for oneTonne.
Beldar 0.530 EACH 116.67 61.84
61.85
COST FOR 1 Tonne
0506u unloading from wagons/non-tipping trucks
within 20 metre lead.
structural steel G.I,C.I.,C.C.,R.c.c.pipes
upto 500
mm.diameter and
special,C.I.manholes,covers,steps,
other casting and ancillary items
like lead,hemp,rope etc.
Detail of cost for oneTonne.
Beldar 0.350 EACH 116.67 40.83
40.85
COST FOR 1 Tonne
0507l loading in the wagons/npn-tipping
trucks within 20 mtrs.lead.
Timber sleeper (standard size)
Detail of cost for 100 Nos.
Beldar 1.750 EACH 116.67 204.17
CARRIAGE OF MATERIAL
Chapter VI
Notes : -
1. (a) The distance shall be measured in units of 50 meters upto 1 km. and in units of 1/2 km.
for distance beyond 1 km.
(b)The units of distance more than 25 meters but less than 50 meters shall be taken as 50
meters (upto a total distance of 1 km.) and the distance less than 20 meters shall be
ignored. Similarly the units of distance more than 1/2 km. but less than 1 km. shall be
taken as 1 km. and the distance less than 1/2 km. shall be ignored for distance more than
1 km.
2. Unless otherwise stated, the carriage rates include loading and un-loading.
3. The payment shall be made on the basis of length of route most practicable and most
economical. This shall be decided by the Engineer-in-charge as per site conditions.
4. The unit rates are applicable to net quantities.
CARRIAGE BY MANUAL LABOUR (Contd.)
LIGHT MATERIAL
DATA SHEET FOR ANALYSIS OF RATES
Remarks
The following labour work for 8 hour a day will carry materials upto a 1st to 50 meters as given
below:
Beldar :- 7.67 Nos. @116.67 per day = 894.86. Quantity of materials carried in 50 meters
lead including loading and unloading :-
Note : 3.84 extra labour (Beldar) will be required for every additional lead of 50 meters.
3.84116.67 = 448.00
Cost for 50 meter = 894.86+(894.861.40) = 1073.82
2 2
Note: coefficient 1.40 i.e. 40% increase has been made from consistantial of plum.
Lead in meters Cost per 8 hour day Increase in cost for every 50 meters.
50m
Rs. 894.86 Rs. 448.00
The following labour working for 8 hours a day will carry materials as given below :-
Beldar each @ 9.2 Nos.@ 116.67 = 1073.36
Quantity of materials is carried in 50 meters lead including loading and unloading:-
1. (Stone blocks G.I.C.I. pipes below 100 mm dia and other 46 Tonne
heavy materials
2. Cement 57 Tonne
3. Steel including C.C.I. and Asbestos sheets 27 Tonne
4. Timber 42 Cu.m
5. Tar Bitumen etc. 46 Tonne
6. S.W. pipes:
(i) 80mm / 100mm dia 2298 Meters
(ii) 150mm dia 1398 Meters
(iii) 200mm dia 999 Meters
(iv) 200mm dia 780 Meters
(v) 250mm dia 600 Meters
(vi) 300mm dia 420 Meters
(vii) 350mm dia 300 Meters
(viii) 400mm dia 240 Meters
(ix) 450mm dia 198 Meters
(x) 500mm dia 162 Meters
(xi) 600mm dia 132 Meters
7. Concrete, RCC Hume Steel C.I. Pipes:-
(i) 100mm dia 1702 Meters
(ii) 125mm dia 1391 Meters
(iii) 150mm dia 1208 Meters
(iv) 200mm dia 805 Meters
(v) 250mm dia 458 Meters
(vi) 300mm dia 366 Meters
(vii) 350mm dia 256 Meters
(viii) 400mm dia 220 Meters
(ix) 450mm dia, 500mm dia 165 Meters
(x) 600mm dia, 700mm dia, 750mm dia and 800mm dia 150 Meters
(xi) 900mm dia, 1000mm dia, 1100mm dia and 1200mm dia 125 Meters
8. Asbestos Cement Pipes:-
(i) 50mm dia 10064 Meters
(ii) 80mm dia 3660 Meters
(iii) 100mm dia 2562 Meters
(iv) 125mm dia 2200 Meters
(v) 150mm dia 1830 Meters
(vi) 200mm dia 1600 Meters
(vii) 250mm dia 1400 Meters
(viii) 300mm dia 1200 Meters
Note :- 50% extra beldar will be required for every additional lead of 50 meters :-
9.2 Beldars @ 116.67 = 1073.36
50% of Rs. 1073.36 = 536.68
Lead in Meter Cost per 8 hour day Increase in cost for every 50 meter
50 meter 1073.36 536.68
Half the cost has been taken for loading/unloading and half for actual carriage.
CHAPTER VI
CARRIAGE OF MATERIALS BY MANUAL LABOUR INCLUDING LOADING/UNLOADING AND STACKING LIGHT MATERIALS-DATA
SHEETS FOR ANALYSISIS OF RATES
Code Materials Capacity Net Qty to be Unit Cost of 8 hours Cost of carriage including loading and
Paid after stacking
deduction for
voids
For 1st 50 For every add. For 100 For 1 k.m. Beyond 1
mtrs lead of 50 mtrs or mrts. k.m. per
part there of every 1/2
beyond 50 mtrs km.
upto 0.50 k.m.
7.67 Beldar 50% for loading
@ 116.67 = & unloading 50%
894.86 for carriage Rs.
894.86/2+(894.8 50% of col. No.4 6+7 18xcol.no. 50%of col.
6x 1.40)/2 i.e. 50% of Rs. 7+col.no.8 No. 9
=1073.82 448.00
1 2 3 4 5 6 7 8 9 10
0601010101 Lime. 35 Cum 35 cum 1 cum 30.68 12.80 43.48 273.88 136.94
0601010102 Moorum 35 Cum 35 cum 1 cum 30.68 12.80 43.48 273.88 136.94
0601010103 Building 35 Cum 35 cum 1 cum 30.68 12.80 43.48 273.88 136.94
rubbish
0601010104 Surkhi 35 Cum 35 cum 1 cum 30.68 12.80 43.48 273.88 136.94
0601010105 Mud dry 35 Cum 35 cum 1 cum 30.68 12.80 43.48 273.88 136.94
0601010200 Earth work 35 Cum 28 cum 1 cum 38.35 16.00 54.35 342.35 171.18
0601010300 Manure of 35 Cum 32.20 cum 1 cum 33.35 13.91 47.26 297.64 148.82
sludge
0601010400 Excavated 35 Cum 17.50 cum 1 cum 61.36 25.60 86.96 547.76 273.88
rock
1 2 3 4 5 6 7 8 9 10
0601020100 Sand, stone 28 Cum 28 cum 1 cum 38.35 16.00 54.35 342.35 171.18
aggregate
below 40mm
nominal size
0601020200 stone 28 Cum 25.90 cum 1 cum 41.46 17.30 58.75 370.16 185.08
aggregate
40mm
nominal size
and above
building
0601020300 Soling stone, 28 cum 28 cum 1 cum 38.35 16.00 54.35 342.35 171.18
stone for filling
crates
0602000000 Bricks 15000 15000 Nos. 1000 71.59 29.87 101.45 639.12 319.56
Nos. Nos.
0603000000 Brick Tiles 24000 24000 Nos. 1000 44.74 18.67 63.41 399.47 199.74
Nos. Nos.
0604000000 Steam coal 30 30 Tonne 1 Tonne 35.79 14.93 50.72 319.46 159.73
Tonne
0605000000 States 80000 80000 Nos. 1000 13.42 5.60 19.02 119.82 59.91
Nos. Nos.
0606000000 Terrazo Tiles 15000 15000 Nos. 1000 71.59 29.87 101.46 639.12 319.56
Nos. Nos.
1 2 3 4 5 6 7 8 9 10
0607000000 Stone Blocks, 46 46 Tonne 1 Tonne 23.34 9.74 33.08 208.40 104.20
G.I,CC. Pipes Tonne
below 100mm
dia & other
heavy
material
0608000000 Cement 57 57 Tonne 1 Tonne 23.34 7.86 31.20 172.68 86.34
Tonne
0609000000 Steel 27 27 Tonne 1 Tonne 39.77 18.07 57.85 383.10 191.55
including Tonne
C.G.I. and
absestos
sheets.
0610000000 Timber 42 cum 42 cum 1 cum 25.57 10.67 36.25 228.30 114.15
0611000000 Tar, Bitumen 46 46 Tonne 1 Tonne 23.34 9.74 33.08 208.40 104.20
etc. Tonne
0612010000 S.W. pipes 2298m. 2298m. 100 m. 46.73 19.50 66.23 417.23 208.62
80mm to 100
mm dia
0612020000 150mm 1398m. 1398m. 100m. 76.81 32.05 108.86 685.76 342.88
0612030000 200mm dia 999m. 999m. 100m. 107.49 44.84 152.33 959.45 479.73
0612040000 230mm dia 780m. 780m. 100m. 137.67 57.44 195.11 1229.03 614.52
0612050000 250mm dia 600m. 600m. 100m. 178.97 74.67 253.64 1597.70 798.85
0612060000 300mm dia 420m. 420m. 100m. 255.67 106.67 362.34 2282.40 1141.20
0612070000 350mm dia 300m. 300m. 100m. 357.94 149.33 507.27 3195.21 1597.61
0612080000 400mm dia. 240m. 240m 100m. 447.43 186.67 634.10 3994.16 1997.08
0612090000 450mm dia. 198m. 198m. 100m. 542.33 226.26 768.59 4841.27 2420.64
1 2 3 4 5 6 7 8 9 10
0512100000 500mm dia. 162m. 162m. 100m. 662.85 276.54 939.39 5917.11 2958.55
0612110000 600mm dia 132m. 132m. 100m. 813.50 339.39 1152.89 6922.52 3461.26
0613101000 Concrete 1702m. 1702m. 100m. 63.09 26.32 89.41 563.17 281.59
RCC
Hume,steel
pipe 100mm
dia
0613020000 125mm dia 1391m. 1391m. 100m. 77.20 32.21 109.41 689.19 344.60
0613030000 150mm dia. 1208m. 1208m. 100m. 88.89 37.09 125.98 793.60 396.80
0613040000 200mm dia 805m. 805m. 100m. 133.39 55.65 189.04 1190.74 595.37
0613050000 250mm dia 458m. 458m. 100m. 234.46 97.82 332.28 2093.04 1046.52
0613060000 300mm dia. 366m. 366m. 100m. 293.39 122.40 415.79 2618.99 1309.50
0613070000 350 mm dia 256m. 256m. 100m. 419.46 175.00 594.46 3744.46 1872.23
0613080000 400mm dia 220m. 220m. 100m. 488.10 203.64 691.74 4357.26 2178.63
0613090000 450mm,500m 165m. 165m. 100m. 650.80 271.52 922.32 5809.68 2904.84
m dia
0613100000 600mm, 150m. 150m. 100m. 715.88 298.67 1014.55 6390.61 3195.31
700mm,
750mm and
800mm
0613110000 900mm, 125m. 125m. 100m. 859.06 358.40 1217.46 7668.66 3834.33
1000mm,
1100mm and
1200mm dia
0614010000 Asbestos 10064m 10064m 100m 10.67 4.45 15.12 95.22 47.61
cement pipes
50mm dia
(5032 pipe 2
m length
0614020000 80mm dia 3660m. 3660m. 100m. 29.34 12.24 41.58 261.90 130.95
(1630 pipes
2m length)
1 2 3 4 5 6 7 8 9 10
0614030000 100mm. Dia 2562m. 2562m. 100m. 41.91 17.49 59.40 374.22 187.11
(1281 pipes
2m length
0614040000 125mm dia 2200m. 2200m. 100m. 48.81 20.36 69.17 435.65 217.83
(1100 pipes
2m length)
0614050000 150mm dia 1830m. 1830m. 100m. 58.68 24.48 83.16 523.80 261.90
(915 pipes 2m
length)
0614060000 200mm dia 1600m. 1600m. 100m. 67.11 28.00 95.11 599.11 299.56
(800 pipes
2mlength)
0614070000 250mm dia 1400m. 1400m. 100m. 76.70 32.00 108.70 684.70 342.35
(700 pipes 2m
length)
0614080000 300mm dia 1200m. 1200m. 100m. 89.49 37.33 126.82 798.76 399.38
(600 pipes 2m
length)
CHAPTER VI (II)
NOTES :
1. (a) The distance less than 1 Km shall be assumed as 1 Km for the first kilometre, all
other distances shall be rounded off to the nearest kilometre.
(b) Unless otherwise stated, the carriage rates include loading, unloading and stacking
with in a lead of 10 metres for the purposes of measurement.
2. The rates are applicable for carriage on metalled roads.
3. For carriage of material on katcha roads, 20% extra on the basis rate of the Km/Kms
concerned should be paid.
4. For carriage of length above 6 metres of heavy steel sections like Rolled steel joists,
rails, channels etc, which can not be easily bent, the carriage rates shall be increased
by 50%.
5. The mode of carriage whether by manual labour, Animal Transport or Mechanical
Transport shall be decided on the basis of economy and expediency and on the merits
of individual case by the Engineer-in-charge after taking into consideration all the
factors. The carriage of materials by private contractors / agencies can be got done by
the Engineer-in-charge only after approval by the Superintending Engineer. The rates
should in no case be more than the rates laid down by Himachal Road Transport
Corporation.
6. The rates are applicable for net quantities i.c. quantities after deduction of voids
where ever applicable.
II CARRIAGE OF MATERIAL BY MECHANICAL TRANSPORT.
Sr. Averag (n) No No of Liters Cost of Litres Cost of Cost of 6 Hire Total Cost Cost Per Increase Average
no. e of Km or of charges in cost cost per
per km Km
over after 5
previous km.
km
Lead Speed Trips Done Diesel Diesel m.oil m.oil@ Beldar @ @ 6+8+9+10 trip
in km/ 8/ @ 120.00 116.67 2200.00
km
Hr/(s) (21/s (2nl+6) Cons 36 per Cons Per ltr. Per day Per/day
+1.25 umed ltr. umed
)
1 2 3 4 5 6 7 8 9 10 11 12 13 14
1. 12.00 5.65 11.30 5.77 207.72 0.22 26.40 700.00 2200.00 3134.12 554.71
2. 12.75 5.12 26.48 8.82 317.52 0.33 39.60 700.00 2200.00 3257.12 636.15 81.44
3. 13.12 4.69 34.14 11.38 409.68 0.43 51.60 700.00 2200.00 3361.28 716.69 80.54
4. 13.50 4.34 40.72 13.58 488.88 0.51 61.20 700.00 2200.00 3450.08 794.95 78.26
5. 13.88 4.06 46.60 15.53 559.08 0.58 69.60 700.00 2200.00 3528.68 86.13 74.18
6. 14.25 3.82 51.84 17.28 622.08 0.65 78.00 700.00 2200.00 3600.08 942.43 73.30
7. 14.63 3.62 56.68 18.89 680.04 0.71 85.20 700.00 2200.00 3665.24 1012.50 70.07
8. 15.10 3.45 61.20 20.40 734.40 0.77 92.40 700.00 2200.00 3726.80 1080.23 67.73 68.38
9. 15.38 3.31 65.58 21.86 786.96 0.82 98.40 700.00 2200.00 3785.36 1143.61 63.38
10. 15.75 3.17 69.40 23.14 833.04 0.87 104.40 700.00 2200.00 3837.44 1210.55 66.94
11. 16.13 3.06 73.32 24.44 879.84 0.92 110.40 700.00 2200.00 3890.24 1271.32 60.77 56.15
12. 16.50 2.96 77.04 25.68 924.48 0.96 115.20 700.00 2200.00 3939.68 1330.97 59.65
13. 16.88 2.87 80.62 26.87 967.32 1.01 121.20 700.00 2200.00 3988.52 1389.73 58.76
14. 17.25 2.78 83.64 27.95 1006.20 1.05 126.00 700.00 2200.00 4032.20 1450.43 60.70
15. 17.63 2.71 87.30 29.10 1047.60 1.09 130.80 700.00 2200.00 4078.40 1504.94 54.51
16. 18.00 2.64 90.48 30.16 1085.76 1.13 135.60 700.00 2200.00 4121.36 1561.12 56.18
17. 18.38 2.59 94.05 31.35 1128.60 1.18 141.60 700.00 2200.00 4170.20 1610.12 49.00
18. 18.75 2.52 96.72 32.24 1160.64 1.21 145.20 700.00 2200.00 4205.84 1668.98 58.86
19. 19.13 2.47 99.86 33.29 1198.44 1.25 150.00 700.00 2200.00 4248.44 1720.02 51.04
20. 19.50 2.42 102.80 34.27 1233.72 1.29 154.80 700.00 2200.00 4288.52 1772.12 52.10
21. 19.88 2.38 105.96 35.32 1271.52 1.32 158.40 700.00 2200.00 4329.92 1819.29 47.17
22. 20.25 2.34 108.96 36.32 1307.52 1.36 163.20 700.00 2200.00 4370.72 1867.83 48.54
23. 20.63 2.30 111.80 37.27 1341.72 1.40 168.00 700.00 2200.00 4409.72 1917.27 49.44
24. 21.00 2.26 114.48 38.16 1373.76 1.43 11.60 700.00 2200.00 4445.36 1966.97 49.70
25. 21.38 2.24 118.00 39.33 1415.88 1.48 177.60 700.00 2200.00 4493.48 2006.02 39.05
46.40
26. 21.75 2.20 120.40 40.13 1444.68 1.51 181.20 700.00 2200.00 4525.88 2057.22 51.20
27. 22.13 2.17 123.18 41.06 1478.16 1.54 184.80 700.00 2200.00 4562.96 2102.75 45.53
28. 22.50 2.14 125.84 41.95 1510.20 1.57 188.40 700.00 2200.00 4598.60 2148.88 46.13
29. 22.88 2.11 128.38 42.79 1540.44 1.60 192.00 700.00 2200.00 4632.44 2195.47 46.59
30. 23.25 2.09 131.41 43.80 1576.80 1.64 196.80 700.00 2200.00 4673.60 2236.17 40.70
Note :-1) Number of trips in working day of 8 hours=N=(8/2L+1.25) where L=lead in km. per
Hour. One hour is allowed for loading and unloading.
2) Consumption of diesel taken at 3 Kms. Per Litre.
3) Consumption of Mobile oil taken at 80 Kms. Per Litre.
4) In column 4 of km. Done an allowances of 6 km. Has been made for movement of truck
from parking place to duty and back.
5) (I) Cost of diesel @ 36 per litre.
(II) Cost of Mobile oil @ 120.00 per Litre.
(III) Hire charges of truck @ Rs. 2200.00 for a day of 8 hours.
CHAPTER VI
II-CARRIAGE OF MATERIALS BY MECHANICAL TRANSPORT INCLUDING LOADING AND UNLOADING AND STACKING
Code Materials Capaci Net qty Unit of Cost 1 km 2 km 3km 4 km 5 km Beyond Beyond Beyond
ty per payable rates per 5 km 10 km 20 km
trip after trip upto 10 upto 20 per
deductio km per km per addition
n of km km al 1 km.
voids.
1 2 3 4 5 6 7 8 9 10 11 12 13 14
0601010101 Lime. 6 cum 6 cum 1 cum 92.45 106.00 119.45 132.50 144.85 11.40 9.35 7.75
0601010102 Moorum 6 cum 6 cum 1 cum 92.45 106.00 119.45 132.50 144.85 11.40 9.35 7.75
0601010103 Building 6 cum 6 cum 1 cum 92.45 106.00 119.45 132.50 144.85 11.40 9.35 7.75
rubbish
0601010104 Surkhi 6 cum 6 cum 1 cum 92.45 106.00 119.45 132.50 144.85 11.40 9.35 7.75
0601010105 Mud dry 6 cum 6 cum 1 cum 92.45 106.00 119.45 132.50 144.85 11.40 9.35 7.75
0601010200 Earth 6 4.80 1 cum 115.55 132.55 149.30 165.60 181.05 14.25 11.70 9.65
work cum cum
0601010300 Manure 6 5.52 1 cum 100.50 115.25 129.85 144.00 157.45 12.35 10.15 8.40
of cum cum
sludge
0601010400 Excavat 6cum 3 cum 1 cum 184.90 212.05 238.90 264.95 289.70 22.75 18.70 15.45
ed rock
0601020101 Sand 5 5 cum 1 cum 110.95 127.25 143.35 158.95 173.85 13.65 11.25 9.30
cum
0601020102 stone 5 5 cum 1 cum 110.95 127.25 143.35 158.95 173.85 13.65 11.25 9.30
aggrega cum
te below
40mm
nominal
size
0601020201 Stone 5 4.62 1 cum 120.05 137.70 155.15 172.05 188.10 14.80 12.15 10.05
aggrega cum cum
te above
40mm.
0601020202 Building 5 4.62 1 cum 120.05 137.70 155.15 172.05 188.10 14.80 12.15 10.05
stones cum cum
0601020300 Soling 5 4.25 1 cum 130.50 149.70 168.65 187.00 204.50 16.10 13.20 10.90
stone cum cum
and
filling
crate
0602000000 Bricks 2000 2000 1000 277.35 318.10 358.35 397.45 434.55 34.15 28.10 23.20
Nos. Nos. Nos.
0603010000 Bricks 3200 3200 1000 173.35 198.80 223.95 248.40 271.60 21.35 17.55 14.50
tiles Nos. Nos. Nos.
0603020000 Terrazo 2500 2500 1000 221.90 254.45 286.70 317.95 347.65 27.30 22.45 18.55
tiles Nos. Nos. Nos.
0604000000 Cement, 7.50 7.50 1 73.95 84.80 95.55 106.00 115.90 9.10 7.50 6.20
G.I., C.I, Tonne Tonne Tonne
A.C.
C.C.
Pipe
and
other
heavy
material
0605000000 Steel, 7.50 7.50 1 73.95 84.80 95.55 106.00 115.90 9.10 7.50 6.20
C.G.I. & Tonne Tonne Tonne
Asbesto
s
sheets.
0606000000 States. 14450 14450 1000 38.40 44.00 49.60 55.00 60.15 4.75 3.90 3.20
Nos. Nos. Nos.
0607000000 Timber. 5 5 cum 1 cum 110.95 127.25 143.35 158.95 173.85 13.65 11.25 9.30
cum
0608000000 Tar 4.50 4.50 1 123.25 141.35 159.25 176.65 193.15 15.20 12.50 10.30
Bitumen tonne Tonne Tonne
0609000000 Steam 5.50 5.50 1 100.85 115.65 130.30 144.50 158.00 12.40 10.20 8.45
coal Tonn Tonne Tonne
e
0610010000 S.W. 720 720 100 77.05 88.35 99.95 110.40 120.70 9.50 7.80 6.45
pipes mtrs. mtrs. mtrs.
(1) 80
mm dia
0610020000 S.W. 480 480 100 115.55 132.55 149.30 165.60 181.05 14.25 11.70 9.65
pipes mtrs. mtrs. Mtrs.
100 mm
dia.
0610030000 S.W. 240 240 100 231.15 265.05 298.60 331.20 362.15 28.45 23.40 19.35
pipes
150 mm mrts. mtrs. mtrs.
dia
0610040000 S.W. 135 135 100 410.90 471.20 530.90 588.80 643.80 50.60 41.60 34.35
pipes Mtrs. Mtrs. Mtrs.
200 mm
dia
0610050000 S.W. 105 105 100 528.30 605.85 682.55 757.00 827.75 65.05 53.50 44.20
pipes mtrs. mtrs. mtrs.
230 mm
dia
0610060000 S.W. 84 84 100 660.35 757.30 853.20 946.25 1034.65 81.30 66.85 55.25
pipes mtrs. mtrs. Mtrs.
250 mm
dia
0610070000 S.W. 66 66 100 840.45 963.85 1085.90 1204.30 1316.85 103.50 85.05 70.30
pipes Mtrs. Mtrs. Mtrs.
300 mm
dia
0610080000 S.W. 48 48 100 1155.60 1325.30 1493.10 1655.95 1810.70 142.30 117.00 96.65
pipes mtrs. Mtrs. Mtrs.
350mm
dia
0610090000 S.W. 33 33 100 1680.90 1927.70 2171.80 2408.60 2633.70 206.95 170.15 140.60
pipes mtrs. Mtrs. Mtrs.
400 mm
dia
0610100000 S.W. 27 27 100 2054.45 2356.10 2654.40 2943.90 3219.00 252.95 207.95 171.85
pipes mtrs. mtrs. mtrs.
450 mm
dia
0610110000 S.W. 24 24 100 2311.30 2650.65 2986.15 3311.90 3621.40 280.40 233.95 193.35
pipes mtrs. mtrs. mts.
500mm
dia
0610120000 S.W. 18 18 100 3081.70 3534.15 3981.60 4415.85 4828.50 379.45 311.95 257.80
pipes mtrs. mtrs. mtrs.
600mm
dia
0611010000 R.C.C,A 329.40 329.40 100 168.40 193.10 217.55 241.30 263.85 20.75 17.05 14.10
.C. mtr. mtr. mtrs.
Hume &
steel
pipes 80
mm dia
0611020000 RCC,AC 292.80 292.80 100 189.45 217.25 244.75 271.45 296.85 23.35 19.20 15.85
& Steel mtr. mtr. mtrs.
pipe
100mm
dia
0611030000 RCC,AC 219.60 219.60 100 252.60 289.70 326.35 361.95 395.80 31.10 25.55 21.15
& Steel mtrs Mtrs. mtrs.
pipe 125
mm dia
0611040000 RCC, 183 183 100 303.10 347.60 391.65 434.35 474.95 37.30 30.70 25.35
AC & mtrs. mtrs. Mtrs.
Steel
pipe
150mm
dia
0611050000 RCC, 109.80 109.80 100 505.20 579.35 652.70 723.90 791.55 62.20 51.15 42.25
AC & mtr. mtr. mtrs.
Steel
pipe
200mm
dia
0611060000 RCC, 80.52 80.52 100 688.90 790.05 890.10 987.15 1079.40 84.80 69.75 57.65
AC & mtrs. mtrs. mtrs.
steel
pipe 250
mm dia
0611070000 RCC,AC 62.22 62.22 100 891.55 1022.40 1151.85 1277.50 1396.85 109.75 90.25 74.55
, Hume mtrs. mtrs. Mtrs.
pipe &
steel
pipes
300mm
dia
0611080000 RCC, 43.92 43.92 100 1263.00 1448.45 1631.80 1809.80 1978.90 155.50 127.85 105.65
AC, mtrs. Mtrs. mtrs.
Hume &
Steel
pipes
350 mm
dia
0611090000 RCC, 32.94 32.94 100 1684.00 1931.25 2175.75 2413.00 2638.50 207.35 170.45 140.85
AC, mtrs. mtrs. mtrs.
Hume &
Steel
pipes
400mm
dia
06111000000 450/500 25.62 25.62 100 2165.15 2483.00 2797.40 3102.45 3392.40 266.60 219.15 181.10
mm dia mtrs. mtrs. mtrs.
0611110000 600, 18.30 18.30 100 3031.20 3476.25 3916.35 4343.45 4749.35 373.20 306.85 253.55
700, mtrs. Mtrs. Mtrs.
750, &
800 mm
dia
0611120000 900, 11.00 11.00 100 5042.30 5783.20 6515.35 7225.90 7901.20 620.90 510.45 421.80
1000, mtrs mtrs. mtrs.
1100
and
1200
mm dia
CHAPTER-VI
CARRIAGE OF MATERIALS BY ANIMAL TRANSPORT (BY MULES)
Notes : -
1. The carriage by Animal transport shall be restored to only where it is not possible to
use manual labour/mechanical transport. It may be further ensured that the cheapest
mode of transport by Animal transport is used depending upon the topographical
features and the availability of animals.
2. The rates are applicable for net quantities after deduction of voids where applicable.
CHAPTER-VI
Note:
1) The carriage by animal transport shall be resorted only where it is not possible to use
manual labour/mechanical transport. It may be further ensured that the economical
mode of transport by animal transport is used depending upon the toporaphical
features and availability of animals.
II) The rates are applicable for not quantities i.e. quantities after deduction of voids
wherever applicable.
III) The rates calculated are exclusive of contractors profit and over head charges.
0601010102 Moorum. 0.084 0.084 1 Cum. 242.25 429.75 618.45 805.95 991.65 187.50
cum Cum.
0601010103 Building 0.084 0.084 cum 1 cum. 242.25 429.75 618.45 805.95 991.65 187.50
rubish. cum
0601010104 Surkhi 0.084 0.084 cum 1 cum. 242.25 429.75 618.45 805.95 991.65 187.50
cum
0601010200 Earth. 0.069 0.059 cum 1 cum 344.90 611.85 880.50 1147.45 1411.85 266.95
cum
0301010300 Manure 0.052 0.048 1 cum 423.95 752.10 1082.30 1410.40 1735.40 328.15
or cum cum.
sludge.
0601010400 Excavat 0.042 0.021 cum 1 cum 969.05 1719.0 2473.80 3223.80 3966.65 750.00
ed rock. cum 5
0601020101 Sand 0.042 0.042 cum 1 cum 484.50 859.50 1236.90 1611.90 1983.35 375.00
cum
0601020102 Stone 0.042 0.042 cum 1 cum 484.50 859.50 1236.90 1611.90 1983.35 375.00
aggregat cum
e below
40 mm
nominal
size
0601020201 Stone 0.042 0.039 cum 1 cum 521.80 925.65 1332.05 1735.90 2135.90 403.85
aggregat cum.
e 40mm
nominal
size
0601020202 Building 0.042 0.039 cum 1 cum 521.80 925.65 1332.05 1735.90 2135.90 403.85
stone. cum
0601020300 Soling 0.042 0.036 cum 1 cum 565.28 1002.80 1443.30 1880.55 2323.90 437.50
stone. cum
0602000000 Cement, 0.10 0.10 1 203.50 361.00 519.50 677.00 833.00 157.50
stone Tonne Tonne Tonne
blocks
CI,AC &
CC
pipes &
other
heavy
material
s.
0603000000 Steel 0.10 0.10 1 cum 203.50 361.00 519.50 677.00 833.00 157.50
(10% Tonne Tonne
extra on
the
above
rate)
0604000000 Wheat, 0.10 0.10 1 203.50 361.00 519.50 677.00 833.00 157.50
rice and Tonne Tonne Tonne
wheat
atta etc.
CHAPTER-VI
CARRIAGE OF MATERIALS BY ANIMAL TRANSPORT. (By donkey)
Notes:-
1. The carriage by Animal transport shall be restored to only where it is not possible to
use manual labour/mechanical transport. It may be further ensured that the cheapest
mode of transport by Animal transport is used depending upon the topographical
features and the availability of animals.
2. The rates are applicable for net quantities after deduction of voids where applicable.
CARRIAGE OF MATERIALS BY ANIMAL TRANSPORT (INCLUDING
LOADING/UNLOADING)
(BY DONKEY)
Note : Donkey charges Rs. 137.75 per day for 8 hours + Beldar Charges
(One beldar will handle 5 donkeys)
Hence Labour charges for each = 116.67/5 =23.35
Total donkey charges per day = (137.75+23.35) = Rs. 161.10 each
Note :- Rate has been increased 96.08% on previous rate of HPSR 1999 for Donkey charges.
CHAPTER VI
II-CARRIAGE OF MATERIALS BY ANIMAL TRANSPORT (BY DONKEY) INCLUDING LOADING AND UNLOADING
0601010102 Moorum. 0.042 0.042 1 Cum. 445.25 810.70 1176.20 1540.50 1908.35 364.30
cum Cum.
0601010103 Building 0.042 0.042 1 Cum. 445.25 810.70 1176.20 1540.50 1908.35 364.30
rubish. cum Cum.
0601010200 Earth 0.035 0.030 1 cum. 623.35 1135.00 1646.65 2156.65 2671.65 510.00
cum cum
0601010300 Manure 0.026 0.024 1 cum 779.15 1418.75 2058.35 2695.85 3339.60 637.50
or cum cum
sludge.
0601010400 Excavat 0.021 0.011 1 cum 1700.00 3095.45 4490.90 5881.80 7286.35 1390.90
ed rock cum cum
0601010501 Sand 0.021 0.021 1 cum 890.50 1621.45 2352.40 3080.95 3816.65 728.55
cum cum
0601010502 Stone 0.021 0.021 1 cum 890.50 1621.45 2352.40 3080.95 3816.65 728.55
aggregat cum cum
e (below
40mm)
0601010503 Soling 0.021 0.021 1 cum 890.50 1621.45 2352.40 3080.95 3816.65 728.55
stone cum cum
(below
40mm)
0601010601 Stone 0.021 0.021 1 cum 890.50 1621.45 2352.40 3080.95 3816.65 728.55
aggregat cum cum
e 40mm
nominal
size and
above.
0601010602 Building 0.021 0.021 1 cum 890.50 1621.45 2352.40 3080.95 3816.65 728.55
stones. cum cum
0601010700 Soling 0.021 0.018 1 cum 1038.90 1891.65 2744.45 3594.45 4452.75 850.00
stone. cum cum
0601020000 Cement 0.05 0.05 1 374.00 681.00 988.00 1294.00 1603.00 306.00
stone Tonne Tonne Tonne
block,
GI,
CI,AC &
CC
pipes &
other
heavy
material
0603000000 Steel. 0.05 0.05 1 374.00 681.00 988.00 1294.00 1603.00 306.00
Tonne Tonne Tonne
0604000000 Wheat, 0.05 0.05 1 374.00 681.00 988.00 1294.00 1603.00 306.00
rice & Tonne Tonne Tonne
wheat
Atta etc.
CHAPTER-VI
CARRIAGE OF MATERIALS BY ANIMAL TRANSPORT (BY COATS)
Notes :-
1. The carriage by Animal transport shall be resorted to only where it is not possible to
use manual labour/mechanical transport. It may be further ensured that the cheapest
mode of transport by Animal transport is used depending upon the topographical
features and the availability of animals.
2. The rates are applicable for net quantities i.e. quantities after deduction of voids where
applicable.
CARRIAGE OF MATERIALS BY ANIMAL TRANSPORT INCLUDING
LOADING AND UNLOADING
(BY COAT)
Note : Goat charges Rs. 55.10 per day + Beldar Charges 6 hours
(One beldar will handle 20 goats)
Hence Labour charges for each = 116.67/20 =5.85
Hence Total charges per day per goat Rs. = (55.10+5.85) = Rs. 60.95 each
Note :- Rate has been increased 96.08% on previous rate of HPSR 1999 for Goat charges.
CHAPTER VI
II-CARRIAGE OF MATERIALS BY ANIMAL TRANSPORT (BY GOAT) INCLUDING LOADING AND UNLOADING
0601010102 Moorum. 0.00252 0.00252 1 Cum. 3928.55 7519.85 11091.30 18313.50 18913.50 3571.45
Cum Cum.
0601010103 Building 0.00252 0.00252 1 Cum. 3928.55 7519.85 11091.30 18313.50 18913.50 3571.45
rubish. Cum Cum.
0601010200 Earth 0.0021 0.0018 1 cum 5500.00 9023.80 15527.80 20527.80 25638.90 5000.00
cum cum
0601010300 Manure of 0.00056 0.00144 1 cum 6875.00 13159.70 19409.70 25659.70 32048.60 6250.00
sludge. cum cum
0601010400 Excavated 0.00126 0.00066 1 cum 15000.00 28712.10 42348.50 55984.85 69924.25 13636.35
rock. cum cum
0601020101 Sand 0.00126 0.00126 1 cum 7857.15 15039.70 22182.55 29325.40 36627.00 7142.85
cum cum
0601020102 Stone 0.00126 0.00126 1 cum 7857.15 15039.70 22182.55 29325.40 36627.00 7142.85
aggregate cum cum
40mm
nominal size
and below.
0601020201 Stone 0.00126 0.00114 1 cum 8684.20 16622.80 24517.55 32412.30 40482.45 7894.75
aggregate cum cum
40mm
nominal size
and above.
0601020202 Building 0.00126 0.00114 1 cum 8684.20 16622.80 24517.55 32412.30 40482.45 7894.75
stone ( Ded. cum cum
For voids
9.52%)
0601020300 Soling stone 0.00126 0.00108 1 cum 9166.65 17546.30 25879.65 34212.95 42731.50 8333.35
(Ded. Voids cum cum
14.2%
0601020000 Cement, 0.005 0.005 1Tonne 1980.00 3790.00 5590.00 7390.00 9230.00 1800.00
stone blocks, Tonne Tonne
GI, CI & AC
pipes & other
heavy
material
0603000000 Steel 0.005 0.005 1 Tonne 1980.00 3790.00 5590.00 7390.00 9230.00 1800.00
Tonne Tonne
0604000000 Wheat, rice 0.005 0.005 1 Tonne 1980.00 3790.00 5590.00 7390.00 9230.00 1800.00
& wheat Atta Tonne Tonne
etc.
CHAPTER VII
EARTH WORK
CHAPTER VII
EARTH WORK
Notes. Measurement of Lead and Lift.
1. These shall be measured from the centre of gravity of the excavated earth to that
of the placed earth. For such measurements, the earthwork proposed to be worked
upon shall be demarcated in sections economically for placement of excavated
earth. The mean lead and lift shall be calculated separately for such sections.
When earth has to be carried over a spoil bank and dumped beyond it, the mean
lift would be the difference in level between the centre of gravity of the excavated
earth and top of the spoil bank omitting the dowel.
The rate provided for additional leads are valid for distances upto 300 meters for
disposals done manually. However, the most economical mode i.e. manual
(including the use of wheel barrows), animal transport or mechanical transport
shall be decided by the Engineer-in-Charge and paid as such according to relevant
schedule of rates for manual, animal or mechanical transport.
2. These rates do not include the cost of pumping out of water which shall normally
be done departmentally. Whenever work is to be got done by contract, the rate
shall be settled before execution on the individual case.
4. The classification of earth work shall be done by the Engineer-in-Charge and the
intermediate classification like P.J/J.B/P.J.B., etc. shall be paid proportionately.
CHAPTER-VII
EARTH WORK
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
CODE
07010000 Cutting in earth work and disposal
of excavated earth upto a lead of
20 metres:-
TOTAL : 388.51
ADD FOR CONTRACTOR'S PROFIT @10 % 38.85
ADD FOR OVERHEAD CHARGES @5 % 19.43
COST FOR 10.00 cum 446.79
COST PER cum 44.68
Say Rs. 44.70
07010200 Pick Work:-
Detail of cost for 10 cubic metre.
Labour :
Beldar EACH 5.000 116.67 583.35
TOTAL : 583.35
ADD FOR CONTRACTOR'S PROFIT @10 % 58.34
ADD FOR OVERHEAD CHARGES @5 % 29.17
COST FOR 10.00 cum 670.85
COST PER cum 67.09
Say Rs. 67.10
07010300 Jumper Work:-
Detail of cost for 10 cubic metre.
MATERIAL :
Special Gelatine (80%). KG 2.520 75.00 189.00
Detonators(ordinary) 100 NO. 12.000 300.00 36.00
Safety fuse wire(Coil 10Mtr Length COIL 1.000 30.00 30.00
Labour :
Hole Driller EACH 0.540 116.67 63.00
Blaster EACH 0.360 148.16 53.34
Beldar EACH 6.670 116.67 778.19
TOTAL : 1797.53
ADD FOR CONTRACTOR'S PROFIT @10 % 179.75
ADD FOR CONTRACTOR'S PROFIT @5 % 89.88
COST FOR 10.00 cum 2067.16
COST PER cum 206.70
Labour Rate :
Actual Labour 894.53
ADD FOR CONTRACTOR'S PROFIT @10 % 89.45
ADD FOR OVERHEAD CHARGES @5 % 44.73
LABOUR FOR 10.00 cum 1028.71
LABOUR PER cum 102.85
MATERIAL :
Special Gelatine(80%). KG 3.920 75.00 294.00
Detonators (ordinary) 100 NOS 14.000 300.00 42.00
Safety fuse wire(Coil 10Mtr Length COIL 1.250 30.00 37.50
Labour :
Hole Driller EACH 0.840 116.67 98.00
Blaster EACH 0.560 148.16 82.97
Beldar EACH 8.330 116.67 971.86
TOTAL : 2534.33
ADD FOR CONTRACTOR'S PROFIT @10 % 253.43
ADD FOR CONTRACTOR'S PROFIT @5 % 126.72
COST FOR 10.00 cum 2914.48
COST PER cum 291.45
Labour Rate :
Actual Labour 1152.83
ADD FOR CONTRACTOR'S PROFIT @10 % 115.28
ADD FOR OVERHEAD CHARGES @5 % 57.64
LABOUR FOR 10.00 cum 1325.76
LABOUR PER cum 132.55
EARTH WORK
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
CODE
TOTAL : 2790.19
ADD FOR CONTRACTOR'S PROFIT @10 % 279.02
ADD FOR OVERHEAD CHARGES @5 % 139.51
COST FOR 10.00 cum 3208.72
COST PER cum 320.85
TOTAL : 4186.03
ADD FOR CONTRACTOR'S PROFIT @10 % 418.60
ADD FOR OVERHEAD CHARGES @5 % 209.30
COST FOR 10.00 cum 4813.94
COST PER cum 481.40
TOTAL :
ADD FOR CONTRACTOR'S PROFIT @10 % 478.35
ADD FOR OVERHEAD CHARGES @5 % 47.83
COST FOR 10.00 cum 23.92
COST PER cum 550.10
55.00
MATERIAL :
Special Gelatine (80%) KG 0.630 75.00 47.25
Detonators (ordinary) 100 NO 3.000 300.00 9.00
Safety fuse wire(Coil 10Mtr Length COIL 0.250 30.00 7.50
Labour :
Hole Driller EACH 0.135 116.67 15.75
Blaster EACH 0.090 148.16 13.33
Beldar EACH 12.000 116.67 1400.04
TOTAL : 1654.87
ADD FOR CONTRACTOR'S PROFIT @10 % 165.49
ADD FOR CONTRACTOR'S PROFIT @5 % 82.74
COST FOR 10.00 cum 1903.11
COST PER cum 190.30
Labour Rate :
Actual Labour 1429.12
ADD FOR CONTRACTOR'S PROFIT @10 % 142.91
ADD FOR OVERHEAD CHARGES @5 % 71.46
LABOUR FOR 10.00 cum 1643.49
LABOUR PER cum 164.35
MATERIAL :
Special Gelatine (80%) KG 2.520 75.00 189.00
Detonators (ordinary) 100 NOS 12.000 300.00 36.00
Safety fuse wire (Coil 10Mtr
Length). COIL 1.000 30.00 30.00
Labour :
Hole Driller EACH 0.540 116.67 63.00
Blaster EACH 0.360 148.16 53.34
Beldar EACH 8.670 116.67 1011.53
TOTAL : 2030.87
ADD FOR CONTRACTOR'S PROFIT @10 % 203.09
ADD FOR CONTRACTOR'S PROFIT @5 % 101.54
COST FOR 10.00 cum 2335.50
EARTH WORK
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
CODE
COST PER cum 233.55
Labour Rate :
Actual Labour 1127.87
ADD FOR CONTRACTOR'S PROFIT @10 % 112.79
ADD FOR OVERHEAD CHARGES @5 % 56.39
LABOUR FOR 10.00 cum 1297.05
LABOUR PER cum 129.70
MATERIAL :
Special Gelatine (80%). KG 3.920 75.00 294.00
Detonators (ordinary). 100 NOS 14.000 300.00 42.00
Safety fuse wire(Coil 10 Mtr
Length). COIL 1.250 30.00 37.50
Labour :
Hole Driller EACH 0.840 116.67 98.00
Blaster EACH 0.560 148.16 82.97
Beldar EACH 11.333 116.67 1322.22
TOTAL : 2884.69
ADD FOR CONTRACTOR'S PROFIT @10 % 288.47
ADD FOR CONTRACTOR'S PROFIT @5 % 144.23
COST FOR 10.00 cum 3317.40
COST PER cum 331.70
Labour Rate :
Actual Labour 1503.19
ADD FOR CONTRACTOR'S PROFIT @10 % 150.32
ADD FOR OVERHEAD CHARGES @5 % 75.16
LABOUR FOR 10.00 cum 1728.67
LABOUR PER cum 172.85
TOTAL : 3023.53
ADD FOR CONTRACTOR'S PROFIT @10 % 302.35
ADD FOR OVERHEAD CHARGES @5 % 151.18
COST FOR 10.00 cum 3477.06
COST PER cum 347.70
EARTH WORK
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
CODE
07020502 Hard Rock.
Detail of cost for 10 cubic metre.
Labour :
Stone Chiseller EACH 23.420 116.67 2732.41
Beldar EACH 14.710 116.67 1716.22
Black Smith 2nd Class EACH 0.590 148.16 87.41
TOTAL : 4536.04
ADD FOR CONTRACTOR'S PROFIT @10 % 453.60
ADD FOR OVERHEAD CHARGES @5 % 226.80
COST FOR 10.00 cum 5216.45
COST PER cum 521.65
TOTAL : 522.68
ADD FOR CONTRACTOR'S PROFIT @10 % 52.27
ADD FOR OVERHEAD CHARGES @5 % 26.13
COST FOR 10.00 cum 601.08
COST PER cum 60.10
07030200 Pick Work
Detail of cost for 10 cu.metres.
Labour :
Beldar EACH 6.370 116.67 743.19
TOTAL : 743.19
ADD FOR CONTRACTOR'S PROFIT @10 % 74.32
ADD FOR OVERHEAD CHARGES @5 % 37.16
COST FOR 10.00 cum 854.67
COST PER cum 85.45
EXCAVATION FOR FOUNDATIONS,DRAINS,CHANNELS,PIPES & CABLES
07040000 Excavation in foundations, trenches
etc., in earth work, lift upto 1.50
Metres stacking the eacavated soil
not more than 3 metres clear from
the edge of the excavation and then
returning the stacked soil in 15cm.
layers, when required in to plinths
sides of foundations etc.,
consolidating each deposited layer
EARTH WORK
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
CODE
by ramming and watering and then
disposing of all surplus excavated
earth as directed with in a lead of
20 metres.
TOTAL : 807.36
ADD FOR WATER CHARGES @1.5% 12.10
TOTAL : 819.45
ADD FOR CONTRACTOR'S PROFIT @10 % 81.95
ADD FOR OVERHEAD CHARGES @5 % 40.97
COST FOR 10.00 cum 942.37
COST PER cum 94.25
TOTAL : 1003.36
ADD FOR WATER CHARGES @1.5% 15.05
1018.41
ADD FOR CONTRACTOR'S PROFIT @10 % 101.84
ADD FOR OVERHEAD CHARGES @5 % 50.92
COST FOR 10.00 cum 1171.17
COST PER cum 117.10
07040300 Jumper Work:
Detail of cost for 10 cu.metres.
MATERIAL :
Special Gelatine (80%) KG 0.630 75.00 47.25
Detonators (ordinary). 100 NOS 3.000 300.00 9.00
Safety fuse wire (Coil 10 Metre
Length). COIL 0.250 30.00 7.50
Labour :
Hole Driller EACH 0.135 116.67 15.75
Blaster EACH 0.090 148.16 13.33
Beldar EACH 16.000 116.67 1866.72
TOTAL : 2121.55
ADD FOR CONTRACTOR'S PROFIT @10 % 212.16
ADD FOR CONTRACTOR'S PROFIT @5 % 106.08
COST FOR 10.00 cum 2439.79
COST PER cum 244.00
Labour Rate :
EARTH WORK
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
CODE
Actual Labour 1895.80
ADD FOR CONTRACTOR'S PROFIT @10 % 189.58
ADD FOR OVERHEAD CHARGES @5 % 94.79
LABOUR FOR 10.00 cum 2180.18
LABOUR PER cum 218.00
07040400 Blasting Work.
MATERIAL :
Special Gelatine (80%). KG 3.330 75.00 249.75
Detonators (ordinary). 100 NOS 12.000 300.00 36.00
Safety fuse wire (Coil 10 Metre
Length). COIL 1.000 30.00 30.00
Labour :
Hole Driller EACH 0.540 116.67 63.00
Blaster EACH 0.360 148.16 53.34
Beldar EACH 11.670 116.67 1361.54
TOTAL : 2441.63
ADD FOR CONTRACTOR'S PROFIT @10 % 244.16
ADD FOR CONTRACTOR'S PROFIT @5 % 122.08
COST FOR 10.00 cum 2807.87
COST PER cum 280.80
Labour Rate :
Actual Labour 1477.88
ADD FOR CONTRACTOR'S PROFIT @10 % 147.79
ADD FOR OVERHEAD CHARGES @5 % 73.89
LABOUR FOR 10.00 cum 1699.56
LABOUR PER cum 169.95
07040402 Hard Rock.
Detail of cost for 10 cu.metres.
MATERIAL :
Special Gelatine (80%). KG 5.350 75.00 401.25
Detonators (ordinary). 100 NO 14.000 300.00 42.00
Safety fuse wire(Coil 10 Metre
Length). COIL 1.250 30.00 37.50
Labour :
Hole Driller EACH 0.840 116.67 98.00
Blaster EACH 0.560 148.16 82.97
Beldar EACH 14.580 116.67 1701.05
TOTAL : 3370.77
ADD FOR CONTRACTOR'S PROFIT @10 % 337.08
ADD FOR CONTRACTOR'S PROFIT @5 % 168.54
COST FOR 10.00 cum 3876.39
COST PER cum 387.65
Labour Rate :
Actual Labour 1882.02
ADD FOR CONTRACTOR'S PROFIT @10 % 188.20
ADD FOR OVERHEAD CHARGES @5 % 94.10
EARTH WORK
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
CODE
LABOUR FOR 10.00 cum 2164.32
LABOUR PER cum 216.45
TOTAL : 4430.57
ADD FOR CONTRACTOR'S PROFIT @10 % 443.06
ADD FOR OVERHEAD CHARGES @5 % 221.53
COST FOR 10.00 cum 5095.16
COST PER cum 509.50
07040502 Hard Rock :
------------
Detail of cost for 10 cubic metres
:
Labour :
Stone Chiseller EACH 37.470 116.67 4371.62
Beldar EACH 18.740 116.67 2186.40
Black Smith 2nd Class EACH 0.590 148.16 87.41
TOTAL : 6645.44
ADD FOR CONTRACTOR'S PROFIT @10 % 664.54
ADD FOR OVERHEAD CHARGES @5 % 332.27
COST FOR 10.00 cum 7642.25
COST PER cum 764.20
07050000 Excavation in drains and channels
etc. in earth work including
dressing of side and bed and
disposing of excavated earth upto a
lead of 20 metres and lift upto
1.50 metres disposed earth to be
levelled and neatly dressed:
TOTAL : 646.35
ADD FOR WATER CHARGES @1.5% 9.70
656.05
ADD FOR CONTRACTOR'S PROFIT @10 % 65.60
ADD FOR OVERHEAD CHARGES @5 % 32.80
EARTH WORK
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
CODE
COST FOR 10.00 cum 754.45
COST PER cum 75.45
Labour :
Beldar EACH 6.660 116.67 777.02
Bhishti EACH 0.220 116.67 25.67
TOTAL : 802.68
ADD FOR WATER CHARGES @1.5% 12.04
TOTAL : 81.48
ADD FOR CONTRACTOR'S PROFIT @10 % 40.74
ADD FOR OVERHEAD CHARGES @5 % 936.94
COST FOR 10.00 cum 93.70
07050300 COST PER cum
Jumper Work.
Detail of cost for 10 cu.metres.
DAY 0.045 3600.00 162.00
Drilling Equipment :
MATERIAL :
Special gelatine (80%). KG 5.350 75.00 401.25
Detonators (ordinary). 100 NOS 14.000 300.00 42.00
Safety fuse wire (Coil 10 Metre
Length). COIL 1.250 30.00 37.50
Labour :
Hole Driller EACH 0.840 116.67 98.00
Blaster EACH 0.560 148.16 82.97
Beldar EACH 11.660 116.67 1360.37
TOTAL : 3030.09
ADD FOR CONTRACTOR'S PROFIT @10 % 303.01
ADD FOR CONTRACTOR'S PROFIT @5 % 151.50
COST FOR 10.00 cum 3484.61
COST PER cum 348.45
Labour Rate :
Actual Labour 1541.34
ADD FOR CONTRACTOR'S PROFIT @10 % 154.13
ADD FOR OVERHEAD CHARGES @5 % 77.07
LABOUR FOR 10.00 cum 1772.55
LABOUR PER cum 177.25
07050500 Chiselling/wedging out of rock
(where blasting is prohibited).
TOTAL : 5859.08
ADD FOR CONTRACTOR'S PROFIT @10 % 585.91
ADD FOR OVERHEAD CHARGES @5 % 292.95
COST FOR 10.00 cum 6737.94
COST PER cum 673.80
FILLING EXCAVATED EARTH IN FOUNDATION TRENCHES AND
PLINTH UNDER FLOOR AND SAND FILLING IN PLINTH
07060000 Excavation in earth work and
filling in 15 cm. layers in
foundation and plinths including
ramming, watering and consolidating
upto a lead of 20 metres and lift
upto a 1.5 metres.
TOTAL : 688.35
ADD FOR WATER CHARGES @1.5% 10.32
TOTAL : 698.65
ADD FOR CONTRACTOR'S PROFIT @10 % 69.87
ADD FOR OVERHEAD CHARGES @5 % 34.93
COST FOR 10.00 cum 803.47
COST PER cum 80.35
07060200 Pick Work.
Detail of cost for 10 cu.metres.
Labour :
Beldar EACH 6.110 116.67 712.85
Bhishti EACH 0.290 116.67 33.83
TOTAL : 746.69
ADD FOR WATER CHARGES @1.5% 11.20
TOTAL : 757.89
ADD FOR CONTRACTOR'S PROFIT @10 % 75.79
ADD FOR OVERHEAD CHARGES @5 % 37.89
COST FOR 10.00 cum 871.57
EARTH WORK
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
CODE
COST PER cum 87.15
MATERIAL :
Sand. cum 10.000 300.00 3000.00
CARRIAGE :
Sand
1 KM BY MECH. TRANSPORT 1 cum 10.000 110.95 1109.50
Labour :
Beldar Each 2.280 116.67 266.01
Bhishti Each 0.480 116.67 56.00
TOTAL : 4975.01
ADD FOR WATER CHARGES @1.5% 74.62
TOTAL : 5049.63
ADD FOR CONTRACTOR'S PROFIT @10 % 504.96
ADD FOR OVERHEAD CHARGES @5 % 252.48
COST FOR 10.00 cum 5807.07
COST PER cum 580.70
Labour Rate :
Actual Labour 322.01
ADD FOR WATER CHARGES @1.5% 74.62
TOTAL : 396.63
ADD FOR CONTRACTOR'S PROFIT @10 % 39.66
ADD FOR OVERHEAD CHARGES @5 % 19.83
LABOUR FOR 10.00 cum 456.12
LABOUR PER cum 45.60
LEAD
07080000 Lead:
Extra for a head of 20 metres or
part thereof for.
TOTAL : 52.50
ADD FOR CONTRACTOR'S PROFIT @10 % 5.25
EARTH WORK
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
CODE
ADD FOR OVERHEAD CHARGES @5 % 2.63
COST FOR 10.00 cum 60.38
COST PER cum 6.05
TOTAL : 58.34
ADD FOR CONTRACTOR'S PROFIT @10 % 5.83
ADD FOR OVERHEAD CHARGES @5 % 2.92
COST FOR 10.00 cum 67.09
COST PER cum 6.70
07080300 Jumper Work:
Labour :
Beldar EACH 0.540 116.67 63.00
TOTAL : 63.00
ADD FOR CONTRACTOR'S PROFIT @10 % 6.30
ADD FOR OVERHEAD CHARGES @5 % 3.15
COST FOR 10.00 cum 72.45
COST PER cum 7.25
07080400 Blasting Work.
TOTAL : 67.67
ADD FOR CONTRACTOR'S PROFIT @10 % 6.77
ADD FOR OVERHEAD CHARGES @5 % 3.38
COST FOR 10.00 cum 77.82
COST PER cum 7.80
07080402 Hard Work:
----------
Labour :
Beldar EACH 0.730 116.67 85.17
TOTAL : 85.17
ADD FOR CONTRACTOR'S PROFIT @10 % 8.52
ADD FOR OVERHEAD CHARGES @5 % 4.26
COST FOR 10.00 cum 97.94
COST PER cum 9.80
07080500 Chiselling/wedging out of rock
(where blasting is prohibited)
TOTAL : 67.67
ADD FOR CONTRACTOR'S PROFIT @10 % 6.77
ADD FOR OVERHEAD CHARGES @5 % 3.38
COST FOR 10.00 cum 77.82
COST PER cum 7.80
07080502 Hard Rock.
----------
Detail of cost for 10 cu.metres.
Labour :
Beldar EACH 0.730 116.67 85.17
TOTAL : 85.17
ADD FOR CONTRACTOR'S PROFIT @10 % 8.52
ADD FOR OVERHEAD CHARGES @5 % 4.26
COST FOR 10.00 cum 97.94
COST PER cum 9.80
LIFT
07090000 Extra for every additional lift of
1.50 metre or part thereof for:
TOTAL : 58.34
ADD FOR CONTRACTOR'S PROFIT @10 % 5.83
ADD FOR OVERHEAD CHARGES @5 % 2.92
COST FOR 10.00 cum 67.09
COST PER cum 6.70
07090200 Pick Work:
----------
Detail of cost for 10 cu.metres.
Labour :
Beldar EACH 0.550 116.67 64.17
TOTAL : 64.17
ADD FOR CONTRACTOR'S PROFIT @10 % 6.42
ADD FOR OVERHEAD CHARGES @5 % 3.21
COST FOR 10.00 cum 73.79
COST PER cum 7.40
07090300 Jumper Work:
------------
Detail of cost for 10 cu.metres.
Labour :
Beldar EACH 0.900 116.67 105.00
TOTAL : 105.00
ADD FOR CONTRACTOR'S PROFIT @10 % 10.50
ADD FOR OVERHEAD CHARGES @5 % 5.25
COST FOR 10.00 cum 120.75
EARTH WORK
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
CODE
COST PER cum 12.05
TOTAL : 100.34
ADD FOR CONTRACTOR'S PROFIT @10 % 10.03
ADD FOR OVERHEAD CHARGES @5 % 5.02
COST FOR 10.00 cum 115.39
COST PER cum 11.55
07090402 Hard Rock:
----------
Detail of cost for 10 cu.metres.
Labour :
Beldar EACH 1.080 116.67 126.00
TOTAL : 126.00
ADD FOR CONTRACTOR'S PROFIT @10 % 12.60
ADD FOR OVERHEAD CHARGES @5 % 6.30
COST FOR 10.00 cum 144.90
COST PER cum 14.50
07090500 Chieselling/Wedging out of rock
(where blasting is prohibited).
TOTAL : 100.34
ADD FOR CONTRACTOR'S PROFIT @10 % 10.03
ADD FOR OVERHEAD CHARGES @5 % 5.02
COST FOR 10.00 cum 115.39
COST PER cum 11.55
07090502 Hard Rock:
----------
Detail of cost for 10 cu. metres.
Labour :
Beldar EACH 1.080 116.67 126.00
TOTAL : 126.00
ADD FOR CONTRACTOR'S PROFIT @10 % 12.60
ADD FOR OVERHEAD CHARGES @5 % 6.30
COST FOR 10.00 cum 144.90
COST PER cum 14.50
EARTH WORK
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
CODE
DRESSING
07100000 Dressing the ground including
cutting and filling upto 15 cm.
07100100
-----------
Detail of cost for 1000 sqft.
Labour :
Beldar EACH 1.500 116.67 175.01
Coolie EACH 1.000 116.67 116.67
TOTAL : 291.68
ADD FOR CONTRACTOR'S PROFIT @10 % 29.17
ADD FOR OVERHEAD CHARGES @5 % 14.58
COST FOR 1000 sqft. 335.43
COST 10.00 sqft. 36.10
TOTAL : 378.01
ADD FOR CONTRACTOR'S PROFIT @10 % 37.80
ADD FOR OVERHEAD CHARGES @5 % 18.90
COST FOR 100.00 sq.m 434.71
COST PER sq.m 4.35
07110200 Felling trees of the girth
(measured at a height of 1 metre
above ground level) including
cuttng of trunks and branches
removing the roots and stacking of
serviceable material and disposal
of unserviceable materials.
07110201 Beyond 30 cm. girth and upto and
including 60 cm. girth.
Detail of cost for tree of 15cm. in
diametre.
Labour :
Beldar EACH 0.600 116.67 70.00
SUNDRIES : 1.80
TOTAL : 71.80
ADD FOR CONTRACTOR'S PROFIT @10 % 7.18
ADD FOR OVERHEAD CHARGES @5 % 3.59
EARTH WORK
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
CODE
COST FOR 1.00 TREE 82.57
COST PER TREE 82.60
07110202 Beyond 60 cm girth and upto and
including 120 cm. girth
Detail of cost of a tree of average
Girth of avarage diametre 0.90 mtr
and lenght 0.30 mtr.
Labour :
Beldar EACH 2.700 116.67 315.01
SUNDRIES : 3.60
TOTAL : 318.61
ADD FOR CONTRACTOR'S PROFIT @10 % 31.86
ADD FOR OVERHEAD CHARGES @5 % 15.93
COST FOR 1.00 TREE 366.40
COST PER TREE 366.40
07110203 Beyond 120 cm. girth and upto and
including 240 cm girth.
Detail of cost for a tree:Av. girth
180 cms and avarage length 7.0 mtr.
Labour :
Beldar EACH 12.600 116.67 1470.04
SUNDRIES : 5.40
TOTAL : 1475.44
ADD FOR CONTRACTOR'S PROFIT @10 % 147.54
ADD FOR OVERHEAD CHARGES @5 % 73.77
COST FOR 1.00 TREE 1696.76
COST PER TREE 1696.80
07110204 Above 240cm girth.
Detail of cost for a tree of
average 800 cm. Girth and length 10
metres.
Labour :
Beldar EACH 25.200 116.67 2940.08
SUNDRIES : 18.30
TOTAL : 2958.38
ADD FOR CONTRACTOR'S PROFIT @10 % 295.84
ADD FOR OVERHEAD CHARGES @5 % 147.92
COST FOR 1.00 Tree 3402.14
COST PER Tree 3402.10
PLANKING AND STRUTTING FOR EARTH WORK IN EXCAVATION
MATERIAL :
Second class kail wood planks
(polling board). Cum 1.140 40605.00 46289.70
Walling (Second class kail wood
scantling). Cum 1.200 39390.00 47268.00
Ballies. R.M. 51.000 230.00 11730.00
CARRIAGE :
Timber
1 KM BY MECH. TRANSPORT 1 cum 2.966 110.95 329.08
TOTAL : 105724.29
DEDUCT CREDIT FOR
MATERIAL AFTER USE as
75% OF THE COST
OF MATERIALS 3/4xY Each 3/4 th 105287.70 (-) 78765.77
TOTAL : 26958.52
THIS CAN BE USED
FOUR TIMES ON THE
SAME WORK THEREFORE
COST FOR USING ONCE Each 0.2500 26958.52 6739.63
Labour :
SUNDRIES : 12.50
TOTAL : 6857.12
ADD FOR CONTRACTOR'S PROFIT @10 % 685.71
ADD FOR CONTRACTOR'S PROFIT @5 % 342.86
COST FOR 90.00 sqm 7885.69
COST PER sqm 87.60
Labour Rate :
Actual Labour 105.00
SUNDRIES : 12.50
TOTAL : 117.50
ADD FOR CONTRACTOR'S PROFIT @10 % 11.75
ADD FOR OVERHEAD CHARGES @5 % 5.88
LABOUR FOR 90.00 sqm 135.13
LABOUR PER sqm 1.50
EARTH WORK
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
CODE
MATERIAL :
Second class kail wood planks
(polling board). Cum 1.140 40605.00 46289.70
Walling (Second class kail wood
scantling). Cum 1.200 39390.00 47268.00
Ballies. R.M. 51.000 230.00 11730.00
CARRIAGE :
Timber
1 KM BY MECH. TRANSPORT 1 cum 2.966 110.95 329.08
TOTAL : 105724.29
DEDUCT CREDIT FOR
MATERIAL AFTER USE as
75% OF THE COST
OF MATERIALS 3/4xY Each 3/4 th 105287.70 (-) 78765.77
TOTAL : 26958.52
THIS CAN BE USED
FOUR TIMES ON THE
SAME WORK THEREFORE
COST FOR USING ONCE Each 0.2500 26958.52 6739.63
Labour :
SUNDRIES : 20.00
TOTAL : 6969.63
ADD FOR CONTRACTOR'S PROFIT @10 % 696.96
ADD FOR CONTRACTOR'S PROFIT @5 % 348.48
COST FOR 90.00 sqm 8015.07
COST PER sqm 89.06
Labour Rate :
Actual Labour 210.00
SUNDRIES : 20.00
TOTAL : 230.00
ADD FOR CONTRACTOR'S PROFIT @10 % 23.00
ADD FOR OVERHEAD CHARGES @5 % 11.50
EARTH WORK
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
CODE
LABOUR FOR 90.00 sqm 264.50
LABOUR PER sqm 2.95
MATERIAL :
Second class kail wood planks
(polling board). Cum 1.140 40605.00 46289.70
Walling (Second class kail wood
scantling). Cum 1.200 39390.00 47268.00
Ballies. R.M. 51.000 230.00 11730.00
CARRIAGE :
Timber
1 KM BY MECH. TRANSPORT 1 cum 2.966 110.95 329.08
TOTAL : 105724.29
DEDUCT CREDIT FOR
MATERIAL AFTER USE as
75% OF THE COST
OF MATERIALS 3/4xY Each 3/4 th 105287.70 (-) 78765.77
TOTAL : 26958.52
THIS CAN BE USED
FOUR TIMES ON THE
SAME WORK THEREFORE
COST FOR USING ONCE Each 0.2500 26958.52 6739.63
Labour :
SUNDRIES : 30.00
TOTAL : 7160.47
ADD FOR CONTRACTOR'S PROFIT @10 % 716.05
ADD FOR CONTRACTOR'S PROFIT @5 % 358.02
COST FOR 90.00 sqm 8234.54
COST PER sqm 91.50
Labour Rate :
Actual Labour 390.84
SUNDRIES : 30.00
TOTAL : 420.84
EARTH WORK
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
CODE
ADD FOR CONTRACTOR'S PROFIT @10 % 42.08
ADD FOR OVERHEAD CHARGES @5 % 21.04
LABOUR FOR 90.00 sqm 483.97
LABOUR PER sqm 5.40
MATERIAL :
Second class kail wood planks
(polling board). Cum 1.710 40605.00 69434.55
Walling (Second class kail wood
scantling). Cum 0.300 39390.00 11817.00
Ballies. R.M. 25.500 230.00 5865.00
CARRIAGE :
Timber
1 KM BY MECH. TRANSPORT 1 cum 3.323 110.95 368.69
TOTAL : 87906.68
DEDUCT CREDIT FOR
MATERIAL AFTER USE as
75% OF THE COST
OF MATERIALS 3/4xY Each 3/4 th 87116.55 (-) 65337.41
TOTAL : 22268.27
THIS CAN BE USED
FOUR TIMES ON THE
SAME WORK THEREFORE
COST FOR USING ONCE Each 0.2500 22268.27 5567.07
Labour :
SUNDRIES : 17.50
TOTAL : 5689.56
ADD FOR CONTRACTOR'S PROFIT @10 % 568.96
ADD FOR CONTRACTOR'S PROFIT @5 % 284.48
COST FOR 45.00 sqm 6542.99
COST PER sqm 145.40
Labour Rate :
Actual Labour 105.00
SUNDRIES : 17.50
TOTAL : 122.50
ADD FOR CONTRACTOR'S PROFIT @10 % 12.25
ADD FOR OVERHEAD CHARGES @5 % 6.13
LABOUR FOR 45.00 sqm 140.88
LABOUR PER sqm 3.15
MATERIAL :
Second class kail wood planks
(polling board). Cum 1.710 40605.00 69434.55
Walling (Second class kail wood
scantling). Cum 0.300 39390.00 11817.00
Ballies. R.M. 25.500 230.00 5865.00
CARRIAGE :
Timber
1 KM BY MECH. TRANSPORT 1 cum 3.323 110.95 368.69
TOTAL : 87906.68
DEDUCT CREDIT FOR
MATERIAL AFTER USE as
75% OF THE COST
OF MATERIALS 3/4xY Each 3/4 th 87116.55 (-) 65337.41
TOTAL : 22268.27
THIS CAN BE USED
FOUR TIMES ON THE
SAME WORK THEREFORE
COST FOR USING ONCE Each 0.2500 22268.27 5567.07
Labour :
SUNDRIES : 19.00
TOTAL : 5796.06
ADD FOR CONTRACTOR'S PROFIT @10 % 579.61
ADD FOR CONTRACTOR'S PROFIT @5 % 289.80
COST FOR 45.00 sqm 6665.47
COST PER sqm 148.10
Labour Rate :
Actual Labour 210.00
SUNDRIES : 19.00
TOTAL : 229.00
ADD FOR CONTRACTOR'S PROFIT @10 % 22.90
ADD FOR OVERHEAD CHARGES @5 % 11.45
LABOUR FOR 45.00 sqm 263.35
LABOUR PER sqm 5.85
MATERIAL :
Second class kail wood planks
(polling board). Cum 1.710 40605.00 69434.55
Walling (Second class kail wood
scantling). Cum 0.300 39390.00 11817.00
Ballies. R.M. 25.500 230.00 5865.00
CARRIAGE :
Timber
1 KM BY MECH. TRANSPORT 1 cum 3.323 110.95 368.69
TOTAL : 87906.68
DEDUCT CREDIT FOR
MATERIAL AFTER USE as
75% OF THE COST
OF MATERIALS 3/4xY Each 3/4 th 87116.55 (-) 65337.41
TOTAL : 22268.27
THIS CAN BE USED
FOUR TIMES ON THE
SAME WORK THEREFORE
COST FOR USING ONCE Each 0.2500 22268.27 5567.07
EARTH WORK
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
CODE
Labour :
SUNDRIES : 26.50
TOTAL : 5908.56
ADD FOR CONTRACTOR'S PROFIT @10 % 590.86
ADD FOR CONTRACTOR'S PROFIT @5 % 295.43
COST FOR 45.00 sqm 6794.84
COST PER sqm 151.00
Labour Rate :
Actual Labour 315.00
SUNDRIES : 26.50
TOTAL : 341.50
ADD FOR CONTRACTOR'S PROFIT @10 % 34.15
ADD FOR OVERHEAD CHARGES @5 % 17.08
LABOUR FOR 45.00 sqm 392.73
LABOUR PER sqm 8.70
MATERIAL :
Special Gelatine (80%). KG 2.520 75.00 189.00
TOTAL : 933.36
ADD EXTRA FOR DEWATERING @ 20% OF LABOUR : 186.67
ADD EXTRA FOR SHORING AND SHUTTERING @ 5% OF LABOUR 46.67
TOTAL : 1166.70
ADD FOR CONTRACTOR'S PROFIT @10 % 116.67
ADD FOR OVERHEAD CHARGES @5 % 58.34
COST FOR 10.00 Cum. 1341.68
COST PER Cum. 134.15
TOTAL : 1108.37
EARTH WORK
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
CODE
ADD EXTRA FOR DEWATERING @ 20% OF LABOUR : 221.67
ADD EXTRA FOR SHORING AND SHUTTERING @ 10% OF LABOUR 110.84
TOTAL : 1440.87
ADD FOR CONTRACTOR'S PROFIT @10 % 144.09
ADD FOR OVERHEAD CHARGES @5 % 72.04
COST FOR 10.00 Cum. 1656.95
COST PER Cum. 165.70
TOTAL : 1382.54
ADD EXTRA FOR DEWATERING @ 20% OF LABOUR : 276.51
ADD EXTRA FOR SHORING AND SHUTTERING @ 15% OF LABOUR 207.38
TOTAL : 1866.43
ADD FOR CONTRACTOR'S PROFIT @10 % 186.64
ADD FOR OVERHEAD CHARGES @5 % 93.32
COST FOR 10.00 Cum. 2146.36
COST PER Cum. 214.65
07170200 Hard Soil.
TOTAL : 1283.37
ADD EXTRA FOR DEWATERING @ 20% OF LABOUR : 256.67
TOTAL : 1540.04
ADD FOR CONTRACTOR'S PROFIT @10 % 154.00
ADD FOR OVERHEAD CHARGES @5 % 77.00
COST FOR 10.00 Cum. 1771.03
COST PER Cum. 177.10
EARTH WORK
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
CODE
TOTAL : 1575.05
ADD EXTRA FOR DEWATERING @ 20% OF LABOUR : 315.01
ADD EXTRA FOR SHORING AND SHUTTERING @ 5% OF LABOUR 78.75
TOTAL : 1968.81
ADD FOR CONTRACTOR'S PROFIT @10 % 196.88
ADD FOR OVERHEAD CHARGES @5 % 98.44
COST FOR 10.00 Cum. 2264.11
COST PER Cum. 226.40
TOTAL : 1849.22
ADD EXTRA FOR DEWATERING @ 20% OF LABOUR : 369.84
ADD EXTRA FOR SHORING AND SHUTTERING @ 10% OF LABOUR 184.92
TOTAL : 2403.99
ADD FOR CONTRACTOR'S PROFIT @10 % 240.40
ADD FOR OVERHEAD CHARGES @5 % 120.20
COST FOR 10.00 Cum. 2764.56
COST PER Cum. 276.45
MATERIAL :
Special gelatine 80 % 1 KG 3.350 75.00 251.25
Detonator 100 NOS 13.000 300.00 39.00
Safty fusewire 1 COIL 1.000 30.00 30.00
Labour :
Hole Driller EACH 0.540 116.67 63.00
Blaster EACH 0.540 148.16 80.01
Beldar EACH 11.670 116.67 1361.54
TOTAL : 2472.80
ADD EXTRA FOR SUNDRIES @ 1% OF LABOUR 24.72
TOTAL : 2497.50
ADD FOR CONTRACTOR'S PROFIT @10 % 249.75
ADD FOR CONTRACTOR'S PROFIT @5 % 124.88
COST FOR 10.00 Cum 2872.13
COST PER Cum 287.20
Labour Rate :
Actual Labour 1504.55
ADD EXTRA FOR SUNDRIES @ 1% OF LABOUR 15.04
TOTAL : 1519.57
ADD FOR CONTRACTOR'S PROFIT @10 % 151.95
ADD FOR OVERHEAD CHARGES @5 % 75.97
LABOUR FOR 10.00 Cum 1747.49
LABOUR PER Cum 174.75
TOTAL : 4430.58
ADD EXTRA FOR SUNDRIES @ 1% OF LABOUR 44.30
TOTAL : 4474.88
ADD FOR CONTRACTOR'S PROFIT @10 % 447.49
ADD FOR OVERHEAD CHARGES @5 % 223.74
COST FOR 10.00 Cum. 5146.11
COST PER Cum. 514.60
MATERIAL :
Special Gelatine 80% 1 KG 5.350 75.00 401.25
Detonator 100 NOS 14.000 300.00 42.00
Safety fusewire 1 COIL 1.250 30.00 37.50
EARTH WORK
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
CODE
Labour :
Hole Driller EACH 0.840 116.67 98.00
Blaster EACH 0.840 148.16 124.45
Beldar EACH 16.000 116.67 1866.72
TOTAL : 3577.93
ADD EXTRA FOR SUNDRIES @ 1% OF LABOUR 35.77
TOTAL : 3612.69
ADD FOR CONTRACTOR'S PROFIT @10 % 361.27
ADD FOR CONTRACTOR'S PROFIT @5 % 180.63
COST FOR 10.00 Cum 4154.59
COST PER Cum 415.45
Labour Rate :
Actual Labour 2089.18
ADD EXTRA FOR SUNDRIES @ 1% OF LABOUR 20.89
TOTAL : 2110.06
ADD FOR CONTRACTOR'S PROFIT @10 % 211.00
ADD FOR OVERHEAD CHARGES @5 % 105.50
LABOUR FOR 10.00 Cum 2426.56
LABOUR PER Cum 242.65
07170500 Hard rock (blasting prohibited).
Detail of cost for 10 Cum.
Labour :
Stone Chiseller EACH 37.470 116.67 4371.62
Beldar EACH 18.740 116.67 2186.40
Black Smith 2nd Class EACH 0.590 148.16 87.41
TOTAL : 6645.43
ADD EXTRA FOR SUNDRIES @ 1% OF LABOUR 66.45
TOTAL : 6711.88
ADD FOR CONTRACTOR'S PROFIT @10 % 671.19
ADD FOR OVERHEAD CHARGES @5 % 335.59
COST FOR 10.00 Cum. 7718.66
COST PER Cum. 771.85
CHAPTER VIII
FORM WORK
CHAPTER VIII
FORM WORK
Notes.-
1. Unless otherwise stated, the labour rates include handling of all materials within 100meters.
2. These rates are applicable for form work comprised of ordinary timber planking unplanned so as
to give a rough finish. In case the planks are planed so as to give a medium smooth finish, the
labour rates shall be increased by 3% and through rates shall also be increased corresponding to
this increase in the labour rates. In case the timber planking having special lining is used so as to
give the exposed concrete work the textured or decorative even surface for architectural
purposeds, the labour and through rates shall be increased by 5%.
3. The rates are applicable to all conditions of working and at all floors. Nothing extra shall be
payable on account of extra lift of materials involved. The rates shall include the cost of materials
and labour for various operations involved such as:-
(a) Splayed edging and notching, allowances for overlaps and passing at angles, centering,
shuttering, strutting, propping, bolting, nailing, wedging, easing, striking and removal.
(b) Filleting.
(c) Dressing with oil
(d) Raking or circular cutting.
4. (a) The rate are applicable for four meters height of propping and centering below supporting
floor. For heights between 4 meters to 7 meters extra rates as shown below shall be paid.
These extra rates are exclusive of the cost of supporting brick/stone/C.C. pillars if
required at site in case, these are used additional rates for these shall be paid after
recovering the cost of salvaged material.
(b) For heights beyond 7 meters the additional wood work shall be paid as only 1/16th of the
total cost of wood work involved and cost of supporting brick/stone C.C. pillars (if
required at site) shall be paid after recovering the cost of salvaged material.
(c) The design of supporting structures for additional heights be evolved suitably by the
Engineer-in-Charge. In case of centering and shuttering required for bridge works, the
cost of special measures, if any, for diversion of river water for protecting the supporting
structure shall be paid for separately.
CHAPTER-VIII
FORM WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
0801000000 Providing from work of ordinary
timber plankings so as to give a
rough finish including
centring,shuttering, strutting and
propping etc. height of propping
and centring below supporting floor
to ceililng not exceeding 4 metres
and removal of the same for insitu
reinforced concrete and plain
concrete work in:-
0801010000 Foundations,footings,bases of
columns etc. and mass concrete.
Detail of cost for 10 Square metres
and area of contact with concrete
(2.5mx2.5mx1m high).
MATERIAL :
Carriage of timber:
Planks = 0.4051 Cum
Ballies:12.6x22/7x1/4(.125m2)
= 0.1546 Cum
Battens: 0.0630 Cum.
-------------------
Total: 0.6227 Cum.
FORM WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
1 KM BY MECH. TRANSPORT cu.m 0.62200 110.95 69.01
100 MTRS BY HEAD LOAD 1 Cum 0.62200 36.25 22.55
Total : 21920.21
Assuming that Timber shall become
unserviceable after being used
16 times.Hence cost for using once Each 1/16 21920.21 1370.00
Add 5% wastage for usage 1096.00
repetedly :
Total : 2466.00
LABOUR :
Carpenter 2nd Class Each 1.30000 186.67 242.67
Beldar Each 1.30000 116.67 151.67
SUNDRIES : 20.00
TOTAL : 2880.34
ADD FOR CONTRACTORS PROFIT 10% 288.03
MATERIAL :
Total : 35477.48
Assuming that Timber shall become
unserviceable after being used
16 times.Hence cost for using once Each 1/16 35477.48 2217.34
Add 5% wastage for usage 1773.85
repetedly :
Total : 3991.19
LABOUR :
Carpenter 2nd Class Each 2.52000 186.67 470.41
Beldar Each 2.52000 116.67 294.01
SUNDRIES : 39.00
TOTAL : 4794.59
ADD FOR CONTRACTORS PROFIT 10% 479.45
MATERIAL :
Soft wood centring Battens
75mmx100mm(second class kail wood
or equivalent local soft
FORM WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
wood)6x4mx0.075mx0.10m=0.180cum
Add wastage 5%=0.009 cum
Total =0.189 cum.
cu.m 0.18900 39390.00 7444.71
Total : 70724.30
Assuming that Timber shall become
unserviceable after being used
16 times.Hence cost for using once Each 1/16 70724.30 4420.27
Add 5% wastage for usage 3536.20
repetedly :
Total : 7956.45
LABOUR :
Carpenter 2nd Class Each 4.48000 186.67 836.28
Beldar Each 4.48000 116.67 522.68
SUNDRIES : 69.50
TOTAL : 9384.91
ADD FOR CONTRACTORS PROFIT 10% 938.49
MATERIAL :
Battens 75mmx50mm
2x13x0.075x0.050=0.098 cu.m.
Add Wastage 5% =0.004 cu.m.
Total =0.102 Cu.m.
Total : 71798.10
FORM WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Assuming that Timber shall become
unserviceable after being used
16 times.Hence cost for using once Each 1/16 71798.10 4487.38
Add 5% wastage for usage 3589.92
repetedly :
Total : 8077.30
LABOUR :
Carpenter 2nd Class Each 7.50000 186.67 1400.03
Beldar Each 6.00000 116.67 700.02
SUNDRIES : 100.00
TOTAL : 10277.34
ADD FOR CONTRACTORS PROFIT 10% 1027.73
MATERIAL :
Total : 27812.00
Assuming that Timber shall become
unserviceable after being used
16 times.Hence cost for using once Each 1/16 27812.00 1738.25
MATERIAL :
Battens 75mmx100mm
9x3x0.075x0.1=0.202 cu.m.
75% battens for top surface
=0.151cu.m.
Total =0.353 Cum.
Add wastage 5% =0.017 Cum.
Total = = 0.370 Cu.m.
Cum. 0.37000 39390.00 14574.30
Planks(lower side)
4x3x1.76x0.038=0.802 cu.m.
Upper side
Assuming that the 75% of the area
will be provided
Shuttring with 30mm thick
planks,volume =0.475cum
Total =1.277cum
Add wastage 5% =0.064cum
Total =1.341 cu.m.
cu.m 1.34100 40605.00 54451.31
Total : 108916.44
Assuming that Timber shall become
unserviceable after being used
16 times.Hence cost for using once Each 1/16 108916.44 6807.28
Add 5% wastage for usage
repetedly : 5445.83
Total : 12253.11
LABOUR :
Carpenter 2nd Class Each 12.00000 186.67 2240.04
Beldar each 10.50000 116.67 1225.04
SUNDRIES : 150.00
TOTAL : 15868.19
ADD FOR CONTRACTORS PROFIT 10% 1586.82
LABOUR RATE :
ACTUAL RATE+SUNDRIES 3615.08
TOTAL : 3615.08
ADD FOR CONTRACTORS PROFIT @10% : 361.51
ADD FOR OVER HEAD CHARGES @5% : 180.75
LABOUR FOR 21.125 sq.m 4157.34
LABOUR PER sq.m 196.80
0801050000 Arches:-
0801050100 Arches upto 6 metres span.
Detail of cost for a semi-circular
arch 3.6m clear span and 3.6m long .
Area of Centring.
22/7x1.8x3.6=20.37 sq.m. .
MATERIAL :
CARRIAGE :
Carriage of timber:
Battens: = 1.792 Cum
Planks : = 0.929 Cum.
Ballies:-123.50x22/7x1/4(0.125m2)
. = 1.519 Cum
-----------------------
Total: 4.240 Cum.
Total : 137338.05
Assuming that Timber shall become
unserviceable after being used
8 times.Hence cost for using once Each 1/8 137338.05 17167.26
Add 5% wastage for usage
repetedly : 6866.85
Total : 24034.11
LABOUR :
Carpenter 2nd Class Each 16.00000 186.67 2986.72
Beldar each 13.00000 116.67 1516.71
SUNDRIES : 200.00
TOTAL : 28737.54
ADD FOR CONTRACTORS PROFIT 10% 2873.75
LABOUR RATE :
ACTUAL RATE+SUNDRIES 4703.43
TOTAL : 4703.43
ADD FOR CONTRACTORS PROFIT @10% : 470.34
ADD FOR OVER HEAD CHARGES @5% : 235.17
LABOUR FOR 20.370 sq.m 5408.94
LABOUR PER sq.m 265.50
MATERIAL :
CARRIAGE :
Carriage of timber.
Total : 310822.37
Assuming that Timber shall become
unserviceable after being used
8 times.Hence cost for using once Each 1/8 310822.37 38852.80
Add 5% wastage for usage
repetedly : 15541.12
Total : 54393.92
LABOUR :
Carpenter 2nd Class Each 28.00000 186.67 5226.76
Beldar Each 24.00000 116.67 2800.08
SUNDRIES 70.00
Total 62490.76
ADD FOR CONTRACTORS PROFIT @10% : 6249.08
LABOUR RATE :
ACTUAL RATE+SUNDRIES 8096.84
TOTAL : 8096.84
ADD FOR CONTRACTORS PROFIT @10% : 809.68
ADD FOR OVER HEAD CHARGES @5% : 404.84
LABOUR FOR 33.310 sq.m 9311.37
LABOUR PER sq.m 279.50
MATERIAL :
Carriage of timber:
Planks: =0.218 Cum
Ballies:-15.96x22/7x1/4(0.125m2)
=0.196 Cum
-------------------
Total: 0.414 Cum.
Total : 12583.63
Assuming that Timber shall become
unserviceable after being used
16 times.Hence cost for using once Each 1/16 12583.63 786.48
Add 5% wastage for usage
repetedly : 629.10
Total : 1415.58
LABOUR :
Carpenter 2nd Class Each 1.47000 186.67 274.40
Beldar each 1.47000 116.67 171.50
SUNDRIES : 23.00
TOTAL : 1884.49
ADD FOR CONTRACTORS PROFIT @10% : 188.45
MATERIAL :
Templates(Battens)
Vertical
4x3.5x0.060x0.050=0.035 Cum.
Add 5% wastage =0.002 Cum.
Total =0.037 cum.
Total : 14017.09
Assuming that Timber shall become
unserviceable after being used
16 times.Hence cost for using once Each 1/16 14017.09 876.07
Add 5% wastage for usage
repetedly : 700.85
Total : 1576.92
LABOUR :
Carpenter 2nd Class each 1.46000 186.67 272.54
Beldar Each 1.46000 116.67 170.34
SUNDRIES : 22.50
TOTAL : 2042.30
ADD FOR CONTRACTORS PROFIT @10% : 204.23
MATERIAL :
Total : 23056.08
Assuming that Timber shall become
unserviceable after being used
16 times.Hence cost for using once Each 1/16 23056.08 1441.00
Add 5% wastage for usage
repetedly : 1152.80
Total : 2593.80
LABOUR :
Carpenter 2nd Class each 2.86000 186.67 533.88
Beldar each 2.86000 116.67 333.68
SUNDRIES : 44.00
TOTAL : 3505.35
ADD FOR CONTRACTORS PROFIT @10% : 350.54
MATERIAL :
Planks 38 mm thick
Second class kail wood
1x15x0.476 = 7.140Sqm
2x16x1.2 =38.400SQM.
2x1.238x0.476 = 1.179Sqm.
FORM WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Total =46.719 Sq.m.
Extra & wastage 5%=2.335 Sqm.
Total =49.854 sq.m.
Cubic contents:
49.854 x 0.038 =1.864 cum.
cum. 1.86400 40605.00 75687.72
Total : 125679.61
Assuming that Timber shall become
unserviceable after being used
16 times.Hence cost for using once Each 1/16 125679.61 7854.98
Add 5% wastage for usage
repetedly : 6283.95
Total : 14138.93
LABOUR :
Carpenter 2nd Class each 15.10000 186.67 2818.72
Beldar Each 15.10000 116.67 1761.72
SUNDRIES : 200.00
TOTAL : 18919.36
FORM WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR CONTRACTORS PROFIT @10% : 1891.94
MATERIAL :
Total : 7502.25
Assuming that Timber shall become
unserviceable after being used
16 times.Hence cost for using once Each 1/16 7502.25 468.89
FORM WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Add 5% wastage for usage
repetedly : 375.10
Total : 843.99
LABOUR :
Carpenter 2nd Class each 0.75000 186.67 140.00
Beldar each 0.56000 116.67 65.34
SUNDRIES : 10.00
TOTAL : 1059.33
ADD FOR CONTRACTORS PROFIT @10% : 105.93
LABOUR RATE :
ACTUAL RATE+SUNDRIES 215.34
TOTAL : 215.34
ADD FOR CONTRACTORS PROFIT @10% : 21.53
ADD FOR OVER HEAD CHARGES @5% : 10.77
LABOUR FOR 12.000 Rmt. 247.64
LABOUR PER Rmt. 20.60
MATERIAL :
Battens:
6x2x0.6x0.075x0.100=0.054
6x2x1.5x0.075x0.100=0.113
Total =0.167
Add wastage 5% =0.008
Total =0.175 Cu.m.
Total : 13439.36
Assuming that Timber shall become
unserviceable after being used
16 times.Hence cost for using once Each 1/16 13439.36 839.96
Add 5% wastage for usage
repetedly : 671.95
Total : 1511.91
LABOUR :
Carpenter 2nd Class each 1.00000 186.67 186.67
Beldar each 0.75000 116.67 87.50
SUNDRIES : 14.00
TOTAL : 1800.08
ADD FOR CONTRACTORS PROFIT @10% : 180.01
MATERIAL :
CARRIAGE :
Planks : =0.182 Cum
Battens: =0.228 Cum
Ballies:-25.20x22/7x1/4(0.125m2)
=0.310 Cum.
-----------------
Total: 0.720 Cum.
Total : 22273.01
Assuming that Timber shall become
unserviceable after being used
16 times.Hence cost for using once Each 1/16 22273.01 1392.06
Add 5% wastage for usage
repetedly : 1113.65
Total : 2505.71
LABOUR :
Carpenter 2nd Class each 0.63000 186.67 117.60
Beldar each 0.63000 116.67 73.50
SUNDRIES : 10.00
TOTAL : 2706.81
ADD FOR CONTRACTORS PROFIT @10% : 270.68
MATERIAL :
Battens:
Horizontal
2x0.75x0.05x0.075=0.0056cum
slant fixed to column
4x0.15x0.05x0.075=0.0023cum.
=0.0135cum
Add wastage 5% 0.0006cum.
Total =0.0141 cum.
Total : 2954.00
Assuming that Timber shall become
unserviceable after being used
16 times.Hence cost for using once Each 1/16 2954.00 184.62
Add 5% wastage for usage
repetedly : 147.70
Total : 332.32
LABOUR :
Carpenter 2nd Class each 0.10000 186.67 18.67
Beldar each 0.10000 116.67 11.67
SUNDRIES : 1.50
TOTAL : 364.15
ADD FOR CONTRACTORS PROFIT @10% : 36.42
MATERIAL :
Battens:
End with bearing centre.
2x0.60x0.075x0.10 =0.009cum.
1x0.45x0.075x0.10 =0.003cum.
Total =0.012 cum
Add 5% wastage =0.001 cum
Total =0.013 cum
Total : 3401.74
FORM WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Assuming that Timber shall become
unserviceable after being used
16 times.Hence cost for using once Each 1/16 3401.74 212.61
Add 5% wastage for usage
repetedly : 170.05
Total : 382.66
LABOUR :
Carpenter 2nd Class each 0.25000 186.67 46.67
Beldar each 0.25000 116.67 29.17
SUNDRIES : 4.00
TOTAL : 462.50
ADD FOR CONTRACTORS PROFIT @10% : 46.25
MATERIAL :
Carriage of timber:
Planks : 0.231 Cum
Battens: 0.041 Cum
Ballies:-6.72x22/7x1/4(0.125m2)
0.082 Cum.
------------------
Total: 0.354 Cum.
Total : 12592.45
Assuming that Timber shall become
unserviceable after being used
16 times.Hence cost for using once Each 1/16 12592.45 787.03
Add 5% wastage for usage
repetedly : 629.63
Total : 1416.66
LABOUR :
Carpenter 2nd Class Each 2.43000 186.67 453.61
Beldar Each 1.51000 110.67 167.11
SUNDRIES : 33.00
TOTAL : 2070.38
ADD FOR CONTRACTORS PROFIT @10% : 207.04
MATERIAL :
LABOUR :
Labour Rate as per item no 0801070100 Sq.m 1.40000 124.80 174.72
Labour Rate as per item no 0801030000 Sq.m 3.22000 84.30 271.45
Labour Rate as per item no 0801060100 Sq.m 1.66000 128.40 213.14
MATERIAL :
Carriage of timber:
Planks : =20.2702 Cum.
Battens: = 0.1586 Cum
Ballies:-53.00x22/7x1/4(0.125m2)
= 0.1626 Cum
---------------------
Total: 20.591 cum.
Total : 844539.72
Assuming that Timber shall become
unserviceable after being used
16 times.Hence cost for using once Each 1/16 844539.72 52783.73
Add 5% wastage for usage
repetedly : 42226.95
Total : 95010.68
LABOUR :
Carpenter 2nd Class each 163.50000 186.67 30520.55
Beldar Each 163.50000 116.67 19075.55
SUNDRIES : 200.00
TOTAL : 144806.77
ADD FOR CONTRACTORS PROFIT @10% : 14480.68
MATERIAL :
MATERIAL :
Total : 5062.94
Assuming that Timber shall become
unserviceable after being used
16 times.Hence cost for using once Each 1/16 5062.94 316.43
Add 5% wastage for usage
repetedly : 253.15
Total : 569.58
LABOUR :
Carpenter 2nd Class Each 0.25000 186.67 46.67
Beldar Each 0.25000 116.67 29.17
SUNDRIES : 4.00
TOTAL : 649.42
ADD FOR CONTRACTORS PROFIT @10% : 64.94
MATERIAL :
Total :
Assuming that Timber shall become
unserviceable after being used
FORM WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
16 times.Hence cost for using once Each 1/16 16508.69 1031.79
Add 5% wastage for usage 825.45
repetedly : 1857.24
Total :
080301000 Cost of Commercial ply wood 4 mm
thick (shuttering) 3 ply including
wastage
MATERIAL :
LABOUR :
Carpenter 2nd Class Each 0.25000 186.67 46.67
Beldar Each 0.25000 116.67 29.17
SUNDRIES : 3.00
TOTAL : 319.67
ADD FOR CONTRACTORS PROFIT @10% : 31.97
MATERIAL :
Battens
Total : 69277.46
Assuming that Timber shall become
unserviceable after being used
16 times.Hence cost for using once Each 1/16 69277.46 4329.84
Add 5% wastage for usage
repetedly : 3463.87
Total : 7793.71
080304020b Cost of Commercial ply wood 4 mm
thick (shuttering) 3 ply including
wastage
MATERIAL :
LABOUR :
Carpenter 2nd Class Each 1.00000 186.67 186.67
Beldar Each 1.00000 116.67 116.67
TOTAL : 1733.69
ADD FOR CONTRACTORS PROFIT @10% : 173.37
MATERIAL :
Total : 2322.88
Assuming that Timber shall become
unserviceable after being used
16 times.Hence cost for using once Each 0.06250 2322.88 145.18
Add 5% wastage for usage
repetedly : 116.15
Total : 261.33
080307010b Cost of commercial ply 4mm thick
MATERIAL :
TOTAL : 74.72
ADD FOR CONTRACTORS PROFIT @10% : 7.47
MATERIAL :
Total : 7416.90
Assuming that Timber shall become
unserviceable after being used
16 times.Hence cost for using once Each 1/16 7416.90 463.56
Add 5% wastage for usage
repetedly : 370.84
Total : 834.40
080308000b Cost of Commercial ply wood 4 mm
thick (shuttering) 3 ply including
wastage
MATERIAL :
LABOUR :
Carpenter 2nd Class Each 0.30000 186.67 56.00
Beldar Each 0.30000 116.67 35.00
TOTAL : 276.49
ADD FOR CONTRACTORS PROFIT @10% : 27.65
MATERIAL :
Carriage of timber.
Total : 10049.48
Assuming that Timber shall become
unserviceable after being used
16 times.Hence cost for using once Each 1/16 10049.48 628.09
Total :
FORM WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR :
Carpenter 2nd Class each 0.60000 186.67 112.00
Beldar Each 0.60000 116.67 70.00
SUNDRIES : 9.00
TOTAL : 819.09
ADD FOR CONTRACTORS PROFIT @10% : 81.91
MATERIAL :
Total : 38718.81
Assuming that Timber shall become
unserviceable after being used
16 times.Hence cost for using once Each 1/16 38718.81 2419.93
Total :
LABOUR :
Carpenter 2nd Class Each 2.50000 186.67 466.68
Beldar Each 2.50000 116.67 291.68
SUNDRIES : 38.00
TOTAL : 3216.28
FORM WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR CONTRACTORS PROFIT @10% : 321.63
MATERIAL :
Total : 9262.14
Assuming that Timber shall become
unserviceable after being used
16 times.Hence cost for using once Each 1/16 9262.14 578.88
Total :
LABOUR :
Carpenter 2nd Class Each 2.50000 186.67 466.68
Beldar Each 2.50000 116.67 291.68
SUNDRIES : 38.00
TOTAL : 1375.23
ADD FOR CONTRACTORS PROFIT @10% : 137.52
MATERIAL :
FORM WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Total : 2081.17
Assuming that Timber shall become
unserviceable after being used
16 times.Hence cost for using once Each 1/16 2081.17 130.07
Total :
LABOUR :
Carpenter 2nd Class Each 0.12000 186.67 22.40
Beldar Each 0.12000 116.67 14.00
SUNDRIES : 2.00
TOTAL : 168.47
ADD FOR CONTRACTORS PROFIT @10% : 16.85
MATERIAL :
Total : 2095.01
Assuming that Timber shall become
unserviceable after being used
16 times.Hence cost for using once Each 1/16 2095.01 130.94
Total :
LABOUR :
Carpenter 2nd Class Each 0.40000 186.67 74.67
Beldar Each 0.40000 116.67 46.67
SUNDRIES : 6.00
TOTAL : 258.28
ADD FOR CONTRACTORS PROFIT @10% : 25.83
MATERIAL :
CARRIAGE :
Carriage of M.S.Plate and angles.
M.S.Plate : 0.140 Qtl.
Angle iron: 0.0683Qtl.
------------------
Total : 0.2093Qtl.or
or 0.02093 Tonne.
Total :
LABOUR :
Black Smith 1st Class Each 0.06600 186.67 12.32
Bandhani Each 0.06600 116.67 7.70
Beldar Each 0.15400 116.67 17.97
SUNDRIES :
Welding charges by Electric plant 1 cm. 300.00 2.00 600.00
Total : 1583.46
Add for water charges @1.5% : 23.75
Total : 1607.21
Less credit for scrap value after full (-) 94.85
use of plate when become unserviceablt
10 % as reserve price941.85x10% =94.85
Total : 1512.36
COST FOR 0.540 Sqm. 1512.36
FORM WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
COST PER Sqm. 2800.00
MATERIAL :
Total :
Assuming that Steel Plates will become
unserviceable after being used
100 times.Hence cost for using once Each 1/100 28425.60 284.26
Add 1% for using repeatedly
i/c repairs,removal of dents
cleaning concrete deposits &
applying oiling & greasings
Assuming that Timber shall become 284.25
unserviceable after being used
16 times.Hence cost for using once Each 1/16 2725.81 170.36
Add 5% wastage for usage
repetedly : 136.50
Total : 875.15
LABOUR :
For assembling errection & dismentling
carpenter taken of item no 0801000000
has been reduced to 60 %
Carpenter 2nd Class Each 0.52000 186.67 97.07
FORM WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Beldar Each 1.30000 116.67 151.67
SUNDRIES(Taking 10% of cost of labour) : 24.00
TOTAL : 1147.88
ADD FOR CONTRACTORS PROFIT @10% : 114.79
MATERIAL :
MATERIAL :
Total : 63604.77
Assuming that Steel Plates will become
unserviceable after being used
100 times.Hence cost for using once Each 1/100 44800.00 448.00
Add 1% for using repeatedly
i/c repairs,removal of dents
cleaning concrete deposits &
applying oiling & greasings Each 1/100 44800.00 448.00
Assuming that Timber shall become
unserviceable after being used
16 times.Hence cost for using once Each 1/16 18804.77 1175.30
Add 5% wastage for usage
repetedly : 940.24
Total : 3011.54
LABOUR :
For assembling errection & dismentling
carpenter taken of item no 0801000000
has been reduced to 60 %
Carpenter 2nd class Each 1.78000 186.67 332.27
Beldar Each 4.48000 116.67 522.68
MATERIAL :
Total : 93816.58
Assuming that Steel Plates will become
unserviceable after being used
100 times.Hence cost for using once Each 1/100 84000.00 840.00
Add 1% for using repeatedly
i/c repairs,removal of dents
cleaning concrete deposits &
applying oiling & greasings 840.00
Assuming that Timber shall become
unserviceable after being used
16 times.Hence cost for using once Each 1/16 9816.58 613.54
Add 5% wastage for usage
repetedly : 490.80
Total : 2784.34
LABOUR :
For assembling errection & dismentling
carpenter taken of item no 0801000000
has been reduced to 60 %
Carpenter 2nd Class Each 3.00000 186.67 560.01
Beldar Each 6.00000 116.67 700.02
SUNDRIES(Taking 10% of cost of labour): 100.00
TOTAL : 4144.37
ADD FOR CONTRACTORS PROFIT @10% : 414.43
MATERIAL :
Total : 16753.25
MATERIAL :
Total : 14313.10
Assuming that Steel Plates will become
unserviceable after being used
100 times.Hence cost for using once Each 1/100 10472.00 104.72
Add 1% for using repeatedly
i/c repairs,removal of dents
cleaning concrete deposits &
applying oiling & greasings 104.72
Assuming that Timber shall become
unserviceable after being used
16 times.Hence cost for using once Each 1/16 3841.10 240.07
Add 5% wastage for usage
repetedly : 192.05
Total : 641.54
LABOUR :
For assembling errection & dismentling
carpenter taken of item no 0801000000
has been reduced to 60 %
Carpenter 2nd Class Each 0.58000 186.67 108.27
Beldar Each 1.46000 116.67 170.34
SUNDRIES(Taking 10% of cost of labour 26.00
TOTAL : 946.12
ADD FOR CONTRACTORS PROFIT @10% : 94.61
MATERIAL :
Total :
Assuming that Steel Plates will become
unserviceable after being used
100 times.Hence cost for using once Each 1/100 16212.00 162.12
Add 1% for using repeatedly
i/c repairs,removal of dents
cleaning concrete deposits &
applying oiling & greasings 162.00
Assuming that Timber shall become
unserviceable after being used
16 times.Hence cost for using once Each 1/16 2237.90 139.87
Add 5% wastage for usage
repetedly : 111.90
Total : 576.00
LABOUR :
For assembling errection & dismentling
carpenter taken of item no 0801000000
has been reduced to 60 %
Carpenter 2nd Class Each 0.97000 186.67 181.07
FORM WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Beldar Each 1.51000 116.67 176.17
SUNDRIES(Taking 10% of cost of labour 32.50
TOTAL : 965.73
ADD FOR CONTRACTORS PROFIT @10% : 96.57
MATERIAL :
Ballies.
1 Metre 12.60000 90.00 1134.00
CARRIAGE :
Carriage of timber:
ballies : 0.273 Cum.
Total : 29089.49
Assuming that Steel Plates will become
unserviceable after being used
100 times.Hence cost for using once Each 1/100 25930.80 259.31
Add 1% for using repeatedly
i/c repairs,removal of dents
cleaning concrete deposits &
applying oiling & greasings 259.30
Assuming that Timber shall become
unserviceable after being used
16 times.Hence cost for using once Each 1/16 3158.68 197.42
Add 5% wastage for usage
FORM WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
repetedly : 157.93
Total : 873.96
LABOUR :
For assembling errection & dismentling
carpenter taken of item no 0801000000
has been reduced to 60 %
Carpenter 2nd Class Each 1.14000 186.67 212.80
Beldar Each 2.86000 116.67 333.68
SUNDRIES(Taking 10% of cost of labour 50.00
TOTAL : 1470.44
ADD FOR CONTRACTORS PROFIT @10% : 147.04
MATERIAL :
Total : 159362.70
Assuming that Steel Plates will become
unserviceable after being used
100 times.Hence cost for using once Each 1/100 130813.20 1308.13
Add 1% for using repeatedly
i/c repairs,removal of dents
cleaning concrete deposits &
applying oiling & greasings 1308.13
Assuming that Timber shall become
unserviceable after being used
16 times.Hence cost for using once Each 1/16 28549.50 1784.34
Add 5% wastage for usage
repetedly : 1427.47
Total : 5828.07
LABOUR :
For assembling errection & dismentling
carpenter taken of item no 0801000000
has been reduced to 60 %
Carpenter 2nd Class Each 6.04000 186.67 1127.49
Beldar Each 15.10000 116.67 1761.72
SUNDRIES(Taking 10% of cost of labour 200.00
TOTAL : 8917.27
ADD FOR CONTRACTORS PROFIT @10% : 891.73
MATERIAL :
Total : 10219.38
Assuming that Steel Plates will become
unserviceable after being used
100 times.Hence cost for using once Each 1/100 5040.00 50.40
Add 1% for using repeatedly
i/c repairs,removal of dents
cleaning concrete deposits &
applying oiling & greasings 50.40
Assuming that Timber shall become
unserviceable after being used
16 times.Hence cost for using once Each 1/16 5179.38 323.71
Add 5% wastage for usage
repetedly : 258.95
Total : 683.46
LABOUR :
For assembling errection & dismentling
carpenter taken of item no 0801000000
has been reduced to 60 %
Carpenter 2nd Class Each 0.30000 186.67 56.00
Beldar Each 0.56000 116.67 65.34
SUNDRIES(Taking 10% of cost of labour 11.00
TOTAL : 815.80
ADD FOR CONTRACTORS PROFIT @10% : 81.58
MATERIAL :
Total : 18119.04
Assuming that Steel Plates will become
unserviceable after being used
100 times.Hence cost for using once Each 1/100 11200.00 112.00
Add 1% for using repeatedly
i/c repairs,removal of dents
cleaning concrete deposits &
applying oiling & greasings 112.00
Assuming that Timber shall become
unserviceable after being used
16 times.Hence cost for using once Each 1/16 6919.04 432.44
Add 5% wastage for usage
repetedly : 345.95
Total : 1002.39
LABOUR :
For assembling errection & dismentling
carpenter taken of item no 0801000000
has been reduced to 60 %
Carpenter 2nd class Each 0.40000 186.67 74.67
Beldar Each 0.75000 116.67 87.50
SUNDRIES(Taking 10% of cost of labour 13.00
TOTAL : 1177.56
ADD FOR CONTRACTORS PROFIT @10% : 117.76
MATERIAL :
FORM WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Rate as per item no 080500000D 1 Sqm 9.33000 2800.00 26124.00
Ballies 125mm.dia.
12x3.902m = 46.82 Rmt.
Braces : 9x1.200m = 10.80 Rmt.
------------------
Total : = 57.62 Rmt.
Add wastage @ 5 % = 2.58 Rmt.
------------------
Total : = 60.50 Rmt.
1 Metre 60.50000 90.00 5445.00
CARRIAGE :
Carriage of timber:
ballies: 60.60x22/7x1/4(.125)2
=0.745 Cum
Battens : =0.097 Cum
------------------
Total : =0.842 Cum.
Total :
Assuming that Steel Plates will become
unserviceable after being used
100 times.Hence cost for using once Each 1/100 26124.00 261.24
Add 1% for using repeatedly
i/c repairs,removal of dents
cleaning concrete deposits &
applying oiling & greasings 261.24
Assuming that Timber shall become
unserviceable after being used
16 times.Hence cost for using once Each 1/16 9389.76 586.86
Add 5% wastage for usage
repetedly : 469.48
Total : 1578.82
LABOUR :
For assembling errection & dismentling
carpenter taken of item no 0801000000
has been reduced to 60 %
Carpenter 2nd Class Each 1.26000 186.67 235.20
Beldar Each 2.80000 116.67 326.68
SUNDRIES(Taking 10% of cost of labour 52.00
TOTAL : 2192.70
ADD FOR CONTRACTORS PROFIT @10% : 219.27
MATERIAL :
Ballies :
2x4x3.50m = 28.00 Rmt.
2x4x4.75m = 57.00 Rmt.
3x4x4.125m = 49.50 Rmt.
--------------------
Total : =134.50 Rmt.
Add wastage @5%= 6.72 Rmt.
---------------------
Total : 141.22 Rmt.
Say 141.20 Rmt.
1 Metre 141.20000 90.00 12708.00
CARRIAGE :
Carriage of timber:
Ballies : 141.20x22/7x1/4(.125)2
=1.733 Cum.
Battens : =0.370 Cum.
-------------------
Total : 2.103 Cum.
Total : 131079.85
Assuming that Steel Plates will become
unserviceable after being used
100 times.Hence cost for using once Each 1/100 103488.00 1034.88
Add 1% for using repeatedly
i/c repairs,removal of dents
cleaning concrete deposits &
applying oiling & greasings 1034.88
FORM WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Assuming that Timber shall become
unserviceable after being used
16 times.Hence cost for using once Each 1/16 27591.85 1724.49
Add 5% wastage for usage
repetedly : 1379.60
Total : 5173.85
LABOUR :
For assembling errection & dismentling
carpenter taken of item no 0801000000
has been reduced to 60 %
Carpenter 2nd Class Each 4.80000 186.67 896.02
Beldar Each 10.50000 116.67 1225.04
SUNDRIES(Taking 10% of cost of labour 200.00
TOTAL : 7494.90
ADD FOR CONTRACTORS PROFIT @10% : 749.49
MATERIAL :
Total : 22528.11
Assuming that Steel Plates will become
FORM WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
unserviceable after being used
100 times.Hence cost for using once Each 1/100 11200.00 112.00
Add 1% for using repeatedly
i/c repairs,removal of dents
cleaning concrete deposits &
applying oiling & greasings 112.00
Assuming that Timber shall become
unserviceable after being used
16 times.Hence cost for using once Each 1/16 11328.11 708.01
Add 5% wastage for usage
repetedly : 566.40
Total : 1498.41
LABOUR :
For assembling errection & dismentling
carpenter taken of item no 0801000000
has been reduced to 60 %
Carpenter 2nd Class Each 0.25000 186.67 46.67
Beldar Each 0.63000 116.67 73.50
SUNDRIES(Taking 10% of cost of labour 10.00
TOTAL : 1628.58
ADD FOR CONTRACTORS PROFIT @10% : 162.86
MATERIAL :
Carriage of timber:
Ballies : 5.25x22/7x1/4(.125)2
= 0.064 Cum.
Battens : = 0.013 Cum
-----------------
FORM WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Total : 0.077 Cum.
Total :
Assuming that Steel Plates will become
unserviceable after being used
100 times.Hence cost for using once Each 1/100 2900.00 29.00
Add 1% for using repeatedly
i/c repairs,removal of dents
cleaning concrete deposits &
applying oiling & greasings 29.00
Assuming that Timber shall become
unserviceable after being used
16 times.Hence cost for using once Each 1/16 995.91 62.24
Add 5% wastage for usage
repetedly : 49.80
Total : 170.04
LABOUR :
For assembling errection & dismentling
carpenter taken of item no 0801000000
has been reduced to 60 %
Carpenter 2nd Class Each 0.10000 186.67 18.67
Beldar Each 0.25000 116.67 29.17
SUNDRIES(Taking 10% of cost of labour 4.50
TOTAL : 222.37
ADD FOR CONTRACTORS PROFIT @10% : 22.24
MATERIAL :
Total : 1255720.49
Assuming that Steel Plates will become
unserviceable after being used
100 times.Hence cost for using once Each 1/100 1244656.00 12446.56
Add 1% for using repeatedly
i/c repairs,removal of dents
cleaning concrete deposits &
applying oiling & greasings 12446.56
Assuming that Timber shall become
unserviceable after being used
16 times.Hence cost for using once Each 1/16 11064.49 691.53
Add 5% wastage for usage
repetedly : 553.22
Total : 26137.87
LABOUR :
For assembling errection & dismentling
carpenter taken of item no 0801000000
has been reduced to 60 %
Carpenter 2nd Class Each 65.40000 186.67 12208.22
Beldar Each 163.50000 116.67 19075.55
SUNDRIES(Taking 10% of cost of labour 2935.00
TOTAL : 60356.63
ADD FOR CONTRACTORS PROFIT @10% : 6035.66
MATERIAL :
Total :
Assuming that Steel Plates will become
unserviceable after being used
100 times.Hence cost for using once Each 1/100 63336.00 633.36
Add 1% for using repeatedly
i/c repairs,removal of dents
cleaning concrete deposits &
applying oiling & greasings 633.36
Assuming that Timber shall become
unserviceable after being used
16 times.Hence cost for using once Each 1/16 5561.56 347.60
Add 5% wastage for usage
repetedly : 278.08
Total : 1892.40
LABOUR :
For assembling errection & dismentling
carpenter taken of item no 0801000000
has been reduced to 60 %
Carpenter 2nd Class Each 3.60000 186.67 672.01
Beldar Each 9.0000 116.67 1050.03
SUNDRIES(Taking 10% of cost of labour 150.00
TOTAL : 3764.44
ADD FOR CONTRACTORS PROFIT @10% : 376.44
CONCRETE
CHAPTER IX
CONCRETE
Notes.-
1. Unless otherwise stated, the labour rates include the re-handling charges of all
materials within 100meters.
2. The labour and through rates include the cost of water. Where water is supplied free
by the Department the rates shall be decreased accordingly.
3. The labour as well as through rates of concrete include the cost of curing. Wherever
curing is got done departmentally and not through contractors, the rates shall be
reduced accordingly.
4. The rates given below are for hand-mixed concrete. In case mechanical mixer is
employed the labour as well as through rates shall be increased by Rs. 25.00 per cubic
meter.
5. The rates give below are for non-vibrated concrete. In case vibrator is used for
compacting the concrete, the corresponding through rates for concrete shall be
increased by Rs. 25.00 per cubic meter.
6. The rates give below are for a height upto floor level two. The maximum storey
height shall be taken as 3 meters. For additional heights, the rates, shall be increased
as given in various items. In case structures like retaining walls/breast walls height of
4meters above ground level in case of piers, abutments, etc.
7. The rates give below are for both cast in-situ and precast work, the precast work
include, the cost of hoisting and fixing in position.
8. The labour rates given in the Chapter include the cost of water, tools and plants,
scaffolding and cost of good earth for mud mortar wherever required.
9. All rates for cement concrete/reinforced cement concrete have been worked out suing
crushed stone aggregate. In case water borne aggregate is used in cement concrete
work, reduction may be made as per the rates worked out under various items of sub-
head cement concrete.
10. The through rates include the cost of carriage of all materials for 100 meters by head
load and one kilometer by mechanical transport.
CHAPTER-IX
CONCRETE
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
0901000A Mud-concrete:
Providing and laying in foundations mud
concrete with graded Stone aggregate 40mm
nominal size excluding.
Cost of Form work.
Detail of cost for 1 Cubic Metre.
MATERIAL :
CARRIAGE :
Stone aggregate above 40mm.
1 KM BY MECH. TRANSPORT 1 Cum. 0.69000 120.05 82.83
100 MTRS BY HEAD LOAD 1 cum 0.69000 58.75 40.54
Stone aggregate below 40mm.
1 KM BY MECH. TRANSPORT 1 Cum. 0.25000 110.95 27.74
100 MTRS BY HEAD LOAD 1 cum 0.25000 54.35 13.59
LABOUR :
Mason 1st class Each 0.02000 211.16 4.22
Mason 2nd Class Each 0.02000 158.67 3.17
Beldar Each 1.06000 116.67 123.67
Bhishti Each 0.08000 116.67 9.33
SUNDRIES : L.S 15.00
TOTAL : 890.94
Add for water charges @1.5% : 13.35
TOTAL : 904.29
ADD FOR CONTRACTORS PROFIT @10% 90.43
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 155.40
Labour for mud mortar: 51.00
TOTAL : 206.40
CONCRETE
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
Stone aggregate 40 mm
Cum. 0.69000 440.00 303.60
Stone aggregate 20 mm
Cum. 0.25000 460.00 115.00
Water borne aggregate 40 mm
Cum. 0.69000 330.00 227.70
Water borne aggregate 20 mm
Cum. 0.25000 350.00 87.50
Difference between stone aggregate
and water borne aggregate : 103.40
ADD FOR CONTRACTORS PROFIT @10% : 10.34
ADD FOR OVER HEAD CHARGES @5% : 5.17
COST FOR 1.000 Cum. 118.91
COST PER Cum. 118.90
MATERIAL :
LABOUR :
Beldar Each 1.96000 116.67 228.67
Bhishti Each 0.27000 116.67 31.50
Mason 1st class Each 0.05000 211.16 10.56
Mason 2nd Class Each 0.05000 158.67 7.93
Mate Each 0.04000 116.67 4.67
Beldar (For extra ramming) Each 0.25000 116.67 29.17
SUNDRIES : L.S 15.00
TOTAL : 1873.10
Add for water charges @1.5% : 28.10
TOTAL : 1901.20
ADD FOR CONTRACTORS PROFIT @10% 190.12
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 327.50
Labour for lime surkhi mortar 1:1:1 143.26
TOTAL : 470.76
Add for water charges : 28.10
TOTAL : 498.86
ADD FOR CONTRACTORS PROFIT @10% : 49.89
ADD FOR OVER HEAD CHARGES @5% : 24.94
LABOUR FOR 1.000 Cum. 573.69
LABOUR PER Cum. 573.70
0902000B Difference of cost using water borne
aggregate/Cum.
MATERIAL :
Stone aggregat 40 mm
Cum. 0.69000 440.00 303.60
Stone aggregate 20 mm
Cum. 0.25000 460.00 115.00
Water borne aggregate 40 mm
MATERIAL :
LABOUR :
Rate as per item no. : 0902000A 312.48
SUNDRIES : L.S 15.00
TOTAL : 1854.06
Add for water charges @1.5% : 27.81
TOTAL : 1881.87
ADD FOR CONTRACTORS PROFIT @10% 188.19
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 327.48
Labour for lime mortar 1:2 143.26
TOTAL : 470.74
Add for water charges : 27.81
TOTAL : 498.55
ADD FOR CONTRACTORS PROFIT @10% : 49.86
ADD FOR OVER HEAD CHARGES @5% : 24.93
LABOUR FOR 1.000 Cum. 573.33
LABOUR PER Cum. 573.30
MATERIAL :
LABOUR :
Rate as per item no. : 0902000A 312.48
SUNDRIES : L.S 15.00
TOTAL : 1720.96
Add for water charges @1.5% : 25.80
TOTAL : 1746.76
ADD FOR CONTRACTORS PROFIT @10% 174.68
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 327.48
Labour for lime mortar1:3 143.26
TOTAL : 470.74
Add for water charges : 25.80
TOTAL : 496.54
ADD FOR CONTRACTORS PROFIT @10% : 49.65
ADD FOR OVER HEAD CHARGES @5% : 24.83
LABOUR FOR 1.000 Cum. 571.02
LABOUR PER Cum. 571.00
MATERIAL :
LABOUR :
Rate as per item no. : 0902000A 312.48
SUNDRIES : L.S 15.00
TOTAL : 1888.50
Add for water charges @1.5% : 28.33
TOTAL : 1916.83
CONCRETE
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 327.48
Labour for lime surkhi mortar 1:2 143.26
TOTAL : 470.74
Add for water charges : 28.33
TOTAL : 499.07
ADD FOR CONTRACTORS PROFIT @10% : 49.91
ADD FOR OVER HEAD CHARGES @5% : 24.95
LABOUR FOR 1.000 Cum. 573.93
LABOUR PER Cum. 573.90
MATERIAL :
LABOUR :
Beldar Each 1.96000 116.67 228.67
Bhishti Each 0.27000 116.67 31.50
Mason 1st class Each 0.05000 211.16 10.56
Mason 2nd Class Each 0.05000 158.67 7.93
Mate Each 0.04000 116.67 4.67
CONCRETE
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 327.50
Labour for lime surkhi mortar 1:2 179.07
TOTAL : 506.57
Add for water charges : 30.97
TOTAL : 537.54
ADD FOR CONTRACTORS PROFIT @10% : 53.75
ADD FOR OVER HEAD CHARGES @5% : 26.88
LABOUR FOR 1.000 Cum. 618.17
LABOUR PER Cum. 618.15
MATERIAL :
MATERIAL :
MATERIAL :
MATERIAL :
CONCRETE
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
MATERIAL :
CONCRETE
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR :
Beldar Each 2.09000 116.67 243.84
Bhishti Each 0.27000 116.67 31.50
Mason 1st class Each 0.05000 211.16 10.56
Mason 2nd Class Each 0.05000 158.67 7.93
Mate Each 0.04000 116.67 4.67
Beldar (For extra ramming) Each 0.25000 116.67 29.17
SUNDRIES : L.S 15.00
TOTAL : 2681.70
Add for water charges @1.5% : 40.22
TOTAL : 2721.92
ADD FOR CONTRACTORS PROFIT @10% 272.19
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 342.67
TOTAL : 342.67
CONCRETE
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
MATERIAL :
Rate as per item no. : 0911010A 2084.30
CARRIAGE :
Rate as per item no. : 0911010A 254.71
LABOUR :
Beldar Each 2.09000 116.67 243.84
Bhishti Each 0.28000 116.67 32.67
Mason 1st class Each 0.06000 211.16 12.67
Mason 2nd Class Each 0.06000 158.67 9.52
Mate Each 0.04000 116.67 4.67
Beldar (For extra ramming) Each 0.25000 116.67 29.17
CONCRETE
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 385.53
TOTAL : 385.53
Add for water charges : 40.86
TOTAL : 426.39
ADD FOR CONTRACTORS PROFIT @10% : 42.64
ADD FOR OVER HEAD CHARGES @5% : 21.32
LABOUR FOR 1.000 Cum. 490.35
LABOUR PER Cum. 490.35
09110300 Independent piers columns and pillars upto
floor two level:
Detail of cost for 1 cubic metre.
MATERIAL :
Rate as per item no. : 0911010A 2084.30
CARRIAGE :
Rate as per item no. : 0911010A 254.71
LABOUR :
Beldar Each 3.59000 116.67 418.85
Bhishti Each 0.29000 116.67 33.83
Mason 1st class Each 0.10000 211.16 21.12
Mason 2nd Class Each 0.10000 158.67 15.87
Mate Each 0.04000 116.67 4.67
Beldar (For extra ramming) Each 0.25000 116.67 29.17
SUNDRIES : L.S 15.00
Scaffolding L.S 38.00
TOTAL : 2915.51
Add for water charges @1.5% : 43.73
TOTAL : 2959.24
ADD FOR CONTRACTORS PROFIT @10% 295.92
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 576.50
TOTAL : 576.50
Add for water charges : 43.73
TOTAL : 620.23
ADD FOR CONTRACTORS PROFIT @10% : 62.02
ADD FOR OVER HEAD CHARGES @5% : 31.01
LABOUR FOR 1.000 Cum. 713.26
LABOUR PER Cum. 713.25
09120000 Providing and laying cement concrete 1:3:6 (1
cement:3 sand:6 graded stone aggregate 40mm
nominal size) excluding cost of centring and
shuttering in:
0912010A Foundations and plinth:
Detail of cost for 1 cubic metre.
MATERIAL :
LABOUR :
Rate as per item no. : 0911010A 327.65
SUNDRIES : L.S 15.00
TOTAL : 2214.77
CONCRETE
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 342.65
TOTAL : 342.65
Add for water charges : 33.22
TOTAL : 375.87
ADD FOR CONTRACTORS PROFIT @10% : 37.59
ADD FOR OVER HEAD CHARGES @5% : 18.79
LABOUR FOR 1.000 Cu.M. 432.25
LABOUR PER Cu.M. 432.25
0912010B Difference in cost for using water borne
aggregate/cum.
MATERIAL :
MATERIAL :
Stone aggregate 20 mm
Cum. 0.24000 460.00 110.40
Sand
Cum. 0.47000 300.00 141.00
Cement(0.15674 cu.m.)or 0.22 tonne
Tonne 0.22000 4900.00 1078.00
CARRIAGE :
Stone aggregate above 40mm.
1 KM BY MECH. TRANSPORT 1 Cum. 0.65000 120.05 78.03
100 MTRS BY HEAD LOAD 1 cum 0.65000 58.75 38.19
Stone aggregate below 40mm.
1 KM BY MECH. TRANSPORT 1 Cum. 0.24000 110.95 26.63
100 MTRS BY HEAD LOAD 1 cum 0.24000 54.35 13.04
100 MTRS BY HEAD LOAD 0.47000 110.95 52.15
100 MTRS BY HEAD LOAD 1 cum 0.47000 54.35 25.54
Cement
1 KM BY MECH. TRANSPORT 1 Tonne 0.22000 73.95 16.27
100 MTRS BY HEAD LOAD 1 cum 0.22000 31.20 6.86
LABOUR :
Rate as per item no. : 09110200 332.50
SUNDRIES : L.S 15.00
Scaffolding L.S 38.00
TOTAL : 2257.62
Add for water charges @1.5% : 33.86
TOTAL : 2291.48
ADD FOR CONTRACTORS PROFIT @10% 229.15
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 385.50
TOTAL : 385.50
Add for water charges : 33.86
TOTAL : 419.36
ADD FOR CONTRACTORS PROFIT @10% : 41.94
ADD FOR OVER HEAD CHARGES @5% : 20.97
LABOUR FOR 1.000 Cum. 482.26
LABOUR PER Cum. 482.25
09120300 Independent piers columns and pillars upto
floor two level.
Detail of cost for 1 cu.m. .
MATERIAL :
CONCRETE
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR :
Rate as per item no. : 09110300 523.47
SUNDRIES : L.S 15.00
Scaffolding L.S 38.00
TOTAL : 2448.59
Add for water charges @1.5% : 36.72
TOTAL : 2485.31
ADD FOR CONTRACTORS PROFIT @10% 248.53
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 576.47
TOTAL : 576.47
Add for water charges : 36.72
TOTAL : 613.19
ADD FOR CONTRACTORS PROFIT @10% : 61.32
ADD FOR OVER HEAD CHARGES @5% : 30.66
LABOUR FOR 1.000 Cum. 705.17
LABOUR PER Cum. 705.20
CONCRETE
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
LABOUR :
Beldar Each 2.09000 116.67 243.84
Bhishti Each 0.27000 116.67 31.50
Mason 1st class Each 0.05000 211.16 10.56
Mason 2nd Class Each 0.05000 158.67 7.93
Mate Each 0.04000 116.67 4.67
Beldar (For extra ramming) Each 0.25000 116.67 29.17
SUNDRIES : L.S 15.00
TOTAL : 1964.53
Add for water charges @1.5% : 29.46
TOTAL : 1993.99
ADD FOR CONTRACTORS PROFIT @10% 199.40
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 342.67
TOTAL : 342.67
Add for water charges : 29.46
TOTAL : 372.13
ADD FOR CONTRACTORS PROFIT @10% : 37.21
ADD FOR OVER HEAD CHARGES @5% : 18.61
LABOUR FOR 1.000 Cum. 427.95
LABOUR PER Cum. 427.95
09130200 Walls including attached buttresses pilasters
and their caps and bases and string courses
etc. upto floor two level.
Detail of cost for 1 cubic metre.
MATERIAL :
LABOUR :
Beldar Each 2.09000 116.67 243.84
Bhishti Each 0.29000 116.67 33.83
Mason 1st class Each 0.06000 211.16 12.67
Mason 2nd Class Each 0.06000 158.67 9.52
Mate Each 0.04000 116.67 4.67
CONCRETE
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 386.70
TOTAL : 386.70
Add for water charges : 30.12
TOTAL : 416.82
ADD FOR CONTRACTORS PROFIT @10% : 41.68
ADD FOR OVER HEAD CHARGES @5% : 20.84
LABOUR FOR 1.000 Cum. 479.34
LABOUR PER Cum. 479.30
09140000 Providing and laying cement concrete 1:4:8 (1
cement : 4 sand : 8 Graded stone aggregate
25mm nominal size) and curing complete
excluding cost of form work in foundation and
plinth in breast and retaining walls etc.
Detail of cost for 1 cubic metre.
MATERIAL :
LABOUR :
Beldar Each 2.09000 116.67 243.84
Bhishti Each 0.27000 116.67 31.50
Mason 1st class Each 0.05000 211.16 10.56
Mason 2nd Class Each 0.05000 158.67 7.93
Mate Each 0.04000 116.67 4.67
Beldar (For extra ramming) Each 0.25000 116.67 29.17
SUNDRIES : L.S 15.00
TOTAL : 1971.03
Add for water charges @1.5% : 29.56
TOTAL : 2000.59
ADD FOR CONTRACTORS PROFIT @10% 200.06
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 342.67
TOTAL : 342.67
Add for water charges : 29.56
TOTAL : 372.23
ADD FOR CONTRACTORS PROFIT @10% : 37.22
ADD FOR OVER HEAD CHARGES @5% : 18.61
LABOUR FOR 1.000 Cum. 428.06
LABOUR PER Cum. 428.05
MATERIAL :
LABOUR :
Beldar Each 2.09000 116.67 243.84
Bhishti Each 0.27000 116.67 31.50
Mason 1st class Each 0.05000 211.16 10.56
Mason 2nd Class Each 0.05000 158.67 7.93
Mate Each 0.04000 116.67 4.67
Beldar (For extra ramming) Each 0.25000 116.67 29.17
SUNDRIES : L.S 15.00
TOTAL : 1768.52
Add for water charges @1.5% : 26.52
TOTAL : 1795.04
ADD FOR CONTRACTORS PROFIT @10% 179.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 342.67
TOTAL : 342.67
Add for water charges : 26.52
TOTAL : 367.16
ADD FOR CONTRACTORS PROFIT @10% : 36.72
ADD FOR OVER HEAD CHARGES @5% : 18.36
LABOUR FOR 1.000 Cum. 422.24
LABOUR PER Cum. 422.20
CONCRETE
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
Rate as per item no. : 09150100 1174.40
CARRIAGE :
Rate as per item no. : 09150100 251.44
LABOUR :
Rate as per item no. : 09130200 333.67
SUNDRIES : L.S 15.00
Scaffolding L.S 38.00
TOTAL : 1812.51
Add for water charges @1.5% : 27.18
TOTAL : 1839.69
ADD FOR CONTRACTORS PROFIT @10% 183.97
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 386.67
TOTAL : 386.67
Add for water charges : 27.18
TOTAL : 413.85
ADD FOR CONTRACTORS PROFIT @10% : 41.39
ADD FOR OVER HEAD CHARGES @5% : 20.69
LABOUR FOR 1.000 Cum. 475.93
LABOUR PER Cum. 475.90
MATERIAL :
LABOUR :
Rate as per item no. : 0911010A 327.65
SUNDRIES : L.S 15.00
TOTAL : 1664.18
Add for water charges @1.5% : 24.96
TOTAL : 1689.14
ADD FOR CONTRACTORS PROFIT @10% 168.91
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 342.65
TOTAL : 342.65
Add for water charges : 24.96
TOTAL : 367.61
ADD FOR CONTRACTORS PROFIT @10% : 36.76
ADD FOR OVER HEAD CHARGES @5% : 18.38
LABOUR FOR 1.000 Cum. 422.75
LABOUR PER Cum. 422.75
CONCRETE
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
Rate as per item no. : 09160100 1076.40
CARRIAGE :
Rate as per item no. : 09160100 245.13
LABOUR :
Rate as per item no. : 09110200 332.50
SUNDRIES : L.S 15.00
Scaffolding L.S 38.00
TOTAL : 1707.03
Add for water charges @1.5% : 25.60
TOTAL : 1732.63
ADD FOR CONTRACTORS PROFIT @10% 173.26
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 385.50
TOTAL : 385.50
Add for water charges : 25.60
TOTAL : 411.10
ADD FOR CONTRACTORS PROFIT @10% : 41.11
ADD FOR OVER HEAD CHARGES @5% : 20.56
LABOUR FOR 1.000 Cum. 472.77
LABOUR PER Cum. 472.75
MATERIAL :
Stone aggregate 20 mm
Cum. 0.58000 460.00 266.80
CONCRETE
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Stone aggregate 10 mm
Cum. 0.20000 480.00 96.00
Sand
Cum. 0.39000 300.00 117.00
Cement(0.393cu.m )or0.56 tonne.
Tonne 0.56000 4900.00 2744.00
CARRIAGE :
Stone aggregate below 40mm.
1 KM BY MECH. TRANSPORT 1 Cum. 0.78000 110.95 86.54
100 MTRS BY HEAD LOAD 1 cum 0.78000 54.35 42.39
Sand
1 KM BY MECH. TRANSPORT 1 Cum. 0.39000 110.95 43.27
100 MTRS BY HEAD LOAD 1 cum 0.39000 54.35 21.20
Cement
1 KM BY MECH. TRANSPORT 1 Tonne 0.56000 73.95 41.41
100 MTRS BY HEAD LOAD 1 Tonne 0.56000 31.20 17.47
LABOUR :
Rate as per item no. : 0911010A 327.65
SUNDRIES : L.S 15.00
TOTAL : 3818.73
Add for water charges @1.5% : 57.28
TOTAL : 3876.01
ADD FOR CONTRACTORS PROFIT @10% 387.60
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 342.65
TOTAL : 342.65
Add for water charges : 57.28
TOTAL : 399.93
ADD FOR CONTRACTORS PROFIT @10% : 39.99
ADD FOR OVER HEAD CHARGES @5% : 20.00
LABOUR FOR 1.000 Cum. 459.92
LABOUR PER Cum. 459.20
MATERIAL :
Stone aggregate 20 mm
CONCRETE
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
Rate as per item no. : 0917010A 3223.80
CARRIAGE :
Rate as per item no. : 0917010A 252.28
LABOUR :
Rate as per item no. : 09110200 332.50
SUNDRIES : L.S 15.00
Scaffolding L.S 38.00
TOTAL : 3861.58
Add for water charges @1.5% : 57.92
TOTAL : 3919.50
ADD FOR CONTRACTORS PROFIT @10% 391.95
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 385.50
TOTAL : 385.50
Add for water charges : 57.92
TOTAL : 443.42
ADD FOR CONTRACTORS PROFIT @10% : 44.34
ADD FOR OVER HEAD CHARGES @5% : 22.17
LABOUR FOR 1.000 Cum. 509.93
CONCRETE
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
Rate as per item no. : 0917010A 3223.80
CARRIAGE :
Rate as per item no. : 0917010A 252.28
LABOUR :
Rate as per item no. : 09110300 523.47
SUNDRIES : L.S 15.00
Scaffolding L.S 38.00
TOTAL : 4052.55
Add for water charges @1.5% : 60.78
TOTAL : 4113.33
ADD FOR CONTRACTORS PROFIT @10% 411.33
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 576.47
TOTAL : 576.47
Add for water charges : 60.78
TOTAL : 637.25
ADD FOR CONTRACTORS PROFIT @10% : 63.73
ADD FOR OVER HEAD CHARGES @5% : 31.86
LABOUR FOR 1.000 Cum. 732.84
LABOUR PER Cum. 732.80
09180000 Providing and laying cement concrete 1:1.1/2 :3
(1 cement :1.1/2 Sand : 3 graded stone aggregate
20 mm nominal size and curing complete
excluding cost of form work.
0918010A Foundation and plinth :
Details of cost for 1 cubic metre.
MATERIAL :
20 mm Stone aggregate
Cum. 0.57000 460.00 262.20
10 mm Stone aggregate
CONCRETE
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR :
Beldar Each 2.09000 116.67 243.84
Bhishti Each 0.27000 116.67 31.50
Mason 1st class Each 0.05000 211.16 10.56
Mason 2nd Class Each 0.05000 158.67 7.93
Mate Each 0.04000 116.67 4.67
Beldar (For extra ramming) Each 0.25000 116.67 29.17
SUNDRIES : L.S 15.00
TOTAL : 3079.55
Add for water charges @1.5% : 46.20
TOTAL : 3125.75
ADD FOR CONTRACTORS PROFIT @10% 312.58
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 342.64
TOTAL : 342.64
Add for water charges : 46.20
TOTAL : 388.84
ADD FOR CONTRACTORS PROFIT @10% : 38.88
ADD FOR OVER HEAD CHARGES @5% : 19.44
LABOUR FOR 1.000 Cum. 447.17
LABOUR PER Cum. 447.15
MATERIAL :
CONCRETE
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Stone aggregate 20 mm
Cum. 0.57000 460.00 262.20
stone aggregate 10 mm
Cum. 0.28000 480.00 134.40
Water borne aggregate 20 mm
Cum. 0.57000 350.00 199.50
Water borne aggregate 10 mm
Cum. 0.28000 360.00 100.80
Difference between stone aggregate
and water borne aggregate : 96.30
ADD FOR CONTRACTORS PROFIT @10% : 9.63
ADD FOR OVER HEAD CHARGES @5% : 4.82
COST FOR 1.000 Cum. 110.75
COST PER Cum. 110.75
MATERIAL :
Rate as per item no. : 0918010A 2484.10
CARRIAGE :
Rate as per item no. : 0918010A 252.81
LABOUR :
Beldar Each 2.09000 116.67 243.84
Bhishti Each 0.28000 116.67 32.67
Mason 1st class Each 0.06000 211.16 12.67
Mason 2nd Class Each 0.06000 158.67 9.52
Mate Each 0.04000 116.67 4.67
Beldar (For extra ramming) Each 0.25000 116.67 29.17
SUNDRIES : L.S 15.00
Scaffolding L.S 38.00
TOTAL : 3122.41
Add for water charges @1.5% : 46.81
TOTAL : 3169.25
ADD FOR CONTRACTORS PROFIT @10% 316.93
LABOUR RATE :
CONCRETE
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
Rate as per item no. : 0918010A 2484.10
CARRIAGE :
Rate as per item no. : 0918010A 252.81
LABOUR :
Beldar Each 3.59000 116.67 418.85
Bhishti Each 0.29000 116.67 33.83
Mason 1st class Each 0.10000 211.16 21.12
Mason 2nd Class Each 0.10000 158.67 15.87
Mate Each 0.04000 116.67 4.67
Beldar (For extra ramming) Each 0.25000 116.67 29.17
SUNDRIES : L.S 15.00
Scaffolding L.S 38.00
TOTAL : 331.39
Add for water charges @1.5% : 49.70
TOTAL : 3363.09
ADD FOR CONTRACTORS PROFIT @10% 336.31
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 576.48
TOTAL : 576.48
Add for water charges : 49.70
TOTAL : 626.18
ADD FOR CONTRACTORS PROFIT @10% : 62.62
ADD FOR OVER HEAD CHARGES @5% : 31.31
LABOUR FOR 1.000 Cum. 720.11
LABOUR PER Cum. 720.10
09190000 Providing and laying cement concrete
CONCRETE
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
20 mm stone aggregate
Cum. 0.64000 460.00 294.40
10 mm Stone aggregate
Cum. 0.22000 480.00 105.60
Sand
Cum. 0.43000 300.00 129.00
Cement (0.26875 cum) or0.38 tonne.
Tonne 0.38000 4900.00 1862.00
CARRIAGE :
Stone aggregate below 40mm.
1 KM BY MECH. TRANSPORT 1 Cum. 0.86000 110.95 95.42
100 MTRS BY HEAD LOAD 1 cum 0.86000 54.35 46.74
Sand
1 KM BY MECH. TRANSPORT 1 Cum. 0.43000 110.95 47.71
100 MTRS BY HEAD LOAD 1 cum 0.43000 54.35 23.37
Cement
1 KM BY MECH. TRANSPORT 1 Tonne 0.38000 73.95 28.10
100 MTRS BY HEAD LOAD 1 Tonne 0.38000 31.20 11.86
LABOUR :
Beldar Each 2.09000 116.67 243.84
Bhishti Each 0.27000 116.67 31.50
Mason 1st class Each 0.05000 211.16 10.56
Mason 2nd Class Each 0.05000 158.67 7.93
Mate Each 0.04000 116.67 4.67
Beldar (For extra ramming) Each 0.25000 116.67 29.17
SUNDRIES : L.S 15.00
TOTAL : 2986.82
Add for water charges @1.5% : 44.80
TOTAL : 3031.62
ADD FOR CONTRACTORS PROFIT @10% 303.16
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 342.64
CONCRETE
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 342.64
Add for water charges : 44.80
TOTAL : 387.44
ADD FOR CONTRACTORS PROFIT @10% : 38.74
ADD FOR OVER HEAD CHARGES @5% : 19.37
LABOUR FOR 1.000 Cum. 445.56
LABOUR PER Cum. 445.55
MATERIAL :
Stone aggregate 20 mm
Cum. 0.64000 460.00 294.40
Stone aggregate 10 mm
Cum. 0.22000 480.00 105.60
Water borne aggregate 20 mm
Cum. 0.64000 350.00 224.00
Water borne aggregate 10 mm
Cum. 0.22000 360.00 79.20
Difference between stone aggregate
and water borne aggregate : 96.80
ADD FOR CONTRACTORS PROFIT @10% : 9.68
ADD FOR OVER HEAD CHARGES @5% : 4.84
COST FOR 1.000 Cum. 111.32
COST PER Cum. 111.30
MATERIAL :
Rate as per item no. : 0919010A 2391.00
CARRIAGE :
Rate as per item no. : 0919010A 253.18
LABOUR :
Beldar Each 2.09000 116.67 243.84
Bhishti Each 0.28000 116.67 32.67
Mason 1st class Each 0.06000 211.16 12.67
Mason 2nd Class Each 0.06000 158.67 9.52
Mate Each 0.04000 116.67 4.67
Beldar (For extra ramming) Each 0.25000 116.67 29.17
SUNDRIES : L.S 15.00
CONCRETE
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
Rate as per item no. : 0919010A 2391.00
CARRIAGE :
Rate as per item no. : 0919010A 253.18
LABOUR :
Beldar Each 3.59000 116.67 418.85
Bhishti Each 0.29000 116.67 33.83
Mason 1st class Each 0.10000 211.16 21.12
Mason 2nd Class Each 0.10000 158.67 15.87
Mate Each 0.04000 116.67 4.67
Beldar (For extra ramming) Each 0.25000 116.67 29.17
SUNDRIES : L.S 15.00
Scaffolding L.S 38.00
TOTAL : 3220.68
Add for water charges @1.5% : 48.31
TOTAL : 3268.99
ADD FOR CONTRACTORS PROFIT @10% 326.90
MATERIAL :
20 mm stone aggregate
Cum. 0.67000 460.00 308.20
10 mm stone aggregate
Cum. 0.22000 480.00 105.60
Sand
Cum. 0.44500 300.00 133.50
Cement(0.2225 cum.)or 0.32 tonne
Tonne 0.32000 4900.00 1568.00
CARRIAGE :
Stone aggregate below 40mm.
1 KM BY MECH. TRANSPORT 1 Cum. 0.89000 110.95 98.75
100 MTRS BY HEAD LOAD 1 cum 0.89000 54.35 48.37
Sand
1 KM BY MECH. TRANSPORT 1 Cum. 0.44500 110.95 49.37
100 MTRS BY HEAD LOAD 1 cum 0.44500 54.35 24.19
Cement
1 KM BY MECH. TRANSPORT 1 Tonne 0.32000 73.95 23.66
100 MTRS BY HEAD LOAD 1 Tonne 0.32000 31.20 9.98
LABOUR :
Beldar Each 2.09000 116.67 243.84
Bhishti Each 0.27000 116.67 31.50
Mason 1st class Each 0.05000 211.16 10.56
Mason 2nd Class Each 0.05000 158.67 7.93
Mate Each 0.04000 116.67 4.67
Beldar (For extra ramming) Each 0.25000 116.67 29.17
SUNDRIES : L.S 15.00
TOTAL : 2712.29
CONCRETE
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 342.67
TOTAL : 342.67
Add for water charges : 40.68
TOTAL : 383.35
ADD FOR CONTRACTORS PROFIT @10% : 38.34
ADD FOR OVER HEAD CHARGES @5% : 19.17
LABOUR FOR 1.000 Cum. 440.85
LABOUR PER Cum. 440.85
MATERIAL :
Stone aggregate 20 mm
Cum. 0.67000 460.00 308.20
Stone aggregate 10 mm
Cum. 0.22000 480.00 105.60
Water borne aggregate 20 mm
Cum. 0.67000 350.00 234.50
Water borne aggregate 10 mm
Cum. 0.22000 360.00 79.20
Difference between stone aggregate
and water borne aggregate : 100.10
ADD FOR CONTRACTORS PROFIT @10% : 10.01
ADD FOR OVER HEAD CHARGES @5% : 5.01
COST FOR 1.000 Cum. 115.12
COST PER Cum. 115.10
MATERIAL :
Rate as per item no. : 0920010A 2115.30
CARRIAGE :
CONCRETE
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR :
Beldar Each 2.09000 116.67 243.84
Bhishti Each 0.28000 116.67 32.67
Mason 1st class Each 0.06000 211.16 12.67
Mason 2nd Class Each 0.06000 158.67 9.52
Mate Each 0.04000 116.67 4.67
Beldar (For extra ramming) Each 0.25000 116.67 29.17
SUNDRIES : L.S 15.00
Scaffolding L.S 38.00
TOTAL : 2768.23
Add for water charges @1.5% : 41.52
TOTAL : 2809.76
ADD FOR CONTRACTORS PROFIT @10% 280.98
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 385.53
TOTAL : 385.53
Add for water charges : 41.52
TOTAL : 427.06
ADD FOR CONTRACTORS PROFIT @10% : 42.71
ADD FOR OVER HEAD CHARGES @5% : 21.35
LABOUR FOR 1.000 Cum. 491.11
LABOUR PER Cum. 491.10
MATERIAL :
Rate as per item no. : 0920010A 2115.30
CARRIAGE :
Rate as per item no. : 0920010A 267.40
LABOUR :
Beldar Each 3.59000 116.67 418.85
Bhishti Each 0.29000 116.67 33.83
Mason 1st class Each 0.10000 211.16 21.12
Mason 2nd Class Each 0.10000 158.67 15.87
Mate Each 0.04000 116.67 4.67
CONCRETE
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 576.50
TOTAL : 576.50
Add for water charges : 44.39
TOTAL : 620.88
ADD FOR CONTRACTORS PROFIT @10% : 62.09
ADD FOR OVER HEAD CHARGES @5% : 31.04
LABOUR FOR 1.000 Cum. 714.02
LABOUR PER Cum. 714.00
MATERIAL :
20 mm stone aggregate
Cum. 0.70000 460.00 322.00
10 mm stone aggregate
Cum. 0.24000 480.00 115.20
Sand
Cum. 0.47000 300.00 141.00
Cement(0.1567 cum.)or 0.22 tonne
Tonne 0.22000 4900.00 1078.00
CARRIAGE :
Stone aggregate below 40mm.
1 KM BY MECH. TRANSPORT 1 Cum. 0.94000 110.95 104.29
100 MTRS BY HEAD LOAD 1 cum 0.94000 54.35 51.09
Sand
1 KM BY MECH. TRANSPORT 1 Cum. 0.47000 110.95 52.15
100 MTRS BY HEAD LOAD 1 cum 0.47000 54.35 25.54
Cement
CONCRETE
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR :
Beldar Each 2.09000 116.67 243.84
Bhishti Each 0.27000 116.67 31.50
Mason 1st class Each 0.05000 211.16 10.56
Mason 2nd Class Each 0.05000 158.67 7.93
Mate Each 0.04000 116.67 4.67
Beldar (For extra ramming) Each 0.25000 116.67 29.17
SUNDRIES : L.S 15.00
TOTAL : 2255.07
Add for water charges @1.5% : 33.83
TOTAL : 2288.90
ADD FOR CONTRACTORS PROFIT @10% 228.89
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 342.67
TOTAL : 342.67
Add for water charges : 33.83
TOTAL : 376.49
ADD FOR CONTRACTORS PROFIT @10% : 37.65
ADD FOR OVER HEAD CHARGES @5% : 18.82
LABOUR FOR 1.000 Cum. 432.97
LABOUR PER Cum. 432.95
MATERIAL :
Stone aggregate 20 mm
Cum. 0.70000 460.00 322.00
Stone aggregate 10 mm
Cum. 0.24000 480.00 115.20
Water borne aggregate 10 mm
Cum. 0.70000 350.00 245.00
Water borne aggregate 10 mm
Cum. 0.24000 360.00 86.40
Difference between stone aggregate
and water borne aggregate : 105.80
ADD FOR CONTRACTORS PROFIT @10% : 10.58
CONCRETE
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
Rate as per item no. : 0921010A 1656.20
CARRIAGE :
Rate as per item no. : 0921010A 256.17
LABOUR :
Beldar Each 2.09000 116.67 243.84
Bhishti Each 0.28000 116.67 32.67
Mason 1st class Each 0.06000 211.16 12.67
Mason 2nd Class Each 0.06000 158.67 9.52
Mate Each 0.04000 116.67 4.67
Beldar (For extra ramming) Each 0.25000 116.67 29.17
SUNDRIES : L.S 15.00
Scaffolding L.S 38.00
TOTAL : 2297.90
Add for water charges @1.5% : 34.47
TOTAL : 2332.37
ADD FOR CONTRACTORS PROFIT @10% 233.24
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 385.53
TOTAL : 385.53
Add for water charges @ 1.5% 34.47
TOTAL : 420.00
ADD FOR CONTRACTORS PROFIT @10% : 42.00
ADD FOR OVER HEAD CHARGES @5% : 21.00
LABOUR FOR 1.000 Cum. 483.00
LABOUR PER Cum. 483.00
MATERIAL :
Rate as per item no. : 0921010A 1656.20
CARRIAGE :
Rate as per item no. : 0921010A 256.17
LABOUR :
Beldar Each 3.59000 116.67 418.85
Bhishti Each 0.29000 116.67 33.83
Mason 1st Class Each 0.10000 211.16 21.12
Mason 2nd Class Each 0.10000 158.67 15.87
Mate Each 0.04000 116.67 4.67
Beldar (For extra ramming) Each 0.25000 116.67 29.17
SUNDRIES : L.S 15.00
Scaffolding L.S 38.00
TOTAL : 2488.87
Add for water charges @1.5% : 37.33
TOTAL : 2526.20
ADD FOR CONTRACTORS PROFIT @10% 252.62
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 576.50
TOTAL : 576.50
Add for water charges : 37.33
TOTAL : 613.83
ADD FOR CONTRACTORS PROFIT @10% : 61.38
ADD FOR OVER HEAD CHARGES @5% : 30.69
LABOUR FOR 1.000 Cum. 705.90
LABOUR PER Cum. 705.90
09220000 Providing and laying upto floor two level
cement concrete 1:2:4 (1 cement : 2 Sand :4
graded stone aggregate 20mm nominal size) and
curing complete including form work in :
0922010A Kerbs,Steps and the like
Detail of cost for a kerb 100m.long 20cm.
deep and 30cm. wide=100x0.30x0.20=6 cu.m.
MATERIAL :
Form Work:
Rate as per item no.0801010000 of form work
100(0.20+0.20)=40 sqm.
Sqm. 331.25 13250.00
TOTAL : 32336.90
COST FOR 6.000 Cum. 32336.90
COST PER Cum. 5389.50
LABOUR RATE:
Rate as per item no 0920010A Cum. 6.00000 441.00 2646.00
Rate as per item no 0801010000 Sqm. 40.0000 47.65 1906.00
TOTAL : 4552.00
LABOUR FOR 6.000 Cum. 4552.00
LABOUR PER Cum. 758.65
0922010B Difference in cost using water borne
aggregate/cum.
MATERIAL :
Stone aggregate 20 mm
Cum. 0.67000 460.00 308.20
Stone aggregate 10 mm
Cum. 0.22000 480.00 105.60
Water borne aggregate 20 mm
Cum. 0.67000 350.00 234.50
Water borne aggregate 10 mm
Cum. 0.22000 360.00 79.20
Difference between stone aggregate
and water borne aggregate : 100.10
ADD FOR CONTRACTORS PROFIT @10% : 10.01
ADD FOR OVER HEAD CHARGES @5% : 5.01
COST FOR 1.000 cum. 115.12
COST PER cum. 115.10
MATERIAL :
TOTAL : 216.19
COST FOR 0.030 Cum. 216.19
COST PER Cum. 7206.60
LABOUR RATE:
Rate as per item no 09200200 Cum. 0.03000 468.10 14.04
Rate as per item no 0801010000 Sqm. 0.36000 47.65 17.15
TOTAL : 31.19
LABOUR FOR 0.030 Cum. 31.20
LABOUR PER Cum. 1040.00
09220300 Small arched lintels not exceeding
1.5 clear span over sailing, coping and the
like requiring form work to suspended
portions.
Detail of cost for 1 lintel 1.50m. clear
span.
(20cm wide & 15cm deep 1.8x0.20x0.15=0.054
cum).
MATERIAL :
TOTAL : 472.60
COST FOR 0.054 Cum. 472.60
COST PER Cum. 8751.85
LABOUR RATE:
Rate as per item no 09200200 1 Cum. 0.05400 468.10 25.28
Rate as per item no 0801010000 1 sqm 0.90000 47.65 42.89
TOTAL : 68.15
LABOUR FOR 0.054 Cum. 68.15
LABOUR PER Cum. 1262.00
09220400 Mouldings as in cornices, window sills etc.
Exceeding 15cm. in girth.
MATERIAL :
Total : 7603.09
Add for water charges @1.5% Except on (-I-) 5.95
Total : 7609.04
ADD FOR CONTRACTORS PROFIT @10% @10% Except on (-I-): 40.24
ADD FOR OVER HEAD CHARGES @5% Except on (-I-) 20.12
COST FOR 1.000 Cum. 7669.40
COST PER Cum. 7669.40
LABOUR RATE :
ADDITION LABOUR FOR FINISHING : 396.49
Labour As per item no :09220200 1040.00 (-a-):
TOTAL : 1436.49
Add for water charges : 5.95
TOTAL : 1442.44
ADD FOR CONTRACTORS PROFIT @10% @10% EXCEPT ON (-a-) : 40.24
ADD FOR OVER HEAD CHARGES @5% EXCEPT ON (-a-) : 20.12
LABOUR FOR 1.000 Cum. 1502.80
LABOUR PER Cum. 1502.80
MATERIAL :
Total : 7636.37
Add for water charges @1.5% Except on (-I-) 6.45
Total : 7642.82
ADD FOR CONTRACTORS PROFIT @10% @10% Except on (-I-): 43.62
ADD FOR OVER HEAD CHARGES @5% Except on (-I-): 21.81
COST FOR 1.000 Cum. 7708.25
COST PER Cum. 7708.25
LABOUR RATE :
CONCRETE
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
Rate as per item no. 0922010A
Cum. 1.00000 5389.50 5389.50
Deduct for difference of rate in cement
concrete 1:2:4 and 1:3:6
i.e.rate of item no 0920010A(-)0921010A
Total : 549.00
COST FOR 1.000 Cum. 4840.50
COST PER Cum. 4840.50
LABOUR RATE :
Rate same as per item no 0922010A 758.65
0923010B Difference in cost using water borne
aggregate/Cum.
MATERIAL :
MATERIAL :
LABOUR RATE :
Rate same as per item no 09220200 1040.00
09230300 Small arched lintels not exceeding 1.5m clear
span over sailing copings and requiring form
work to suspended position.
Detail of cost for 1 cubic metre.
MATERIAL :
LABOUR RATE :
Rate same as per item no 09220300 1262.00
09230400 Mouldings as in cornices window sills etc.
exceeding 15cm in girth.
Detail of cost for per cubic metre.
MATERIAL :
LABOUR RATE :
Rate same as per item no 09220400 1502.80
09230500 Mouldings as in cornices,window sills
etc.,not exceeding 15cm. in girth.
Detail of cost for 1 Cubic Metre.
MATERIAL :
LABOUR RATE :
Rate same as per item no 09220500 1541.65
09240000 Extra for additional lift over rates upto
floor two level for all concrete work above
floor two level.
Detail of cost for per Floor (i.e.above 3
metre height.)
Extra for every additional height of 0.3 m or
part there of over floor two level .
Taking each floor to be of average 3 metres
height extra per floor i.e. 10% of the rate
of concrete work from plinth to floor two
level
TOTAL : 466.68
Add for water charges @1.5% : 7.00
CONCRETE
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 473.68
ADD FOR CONTRACTORS PROFIT @10% : 47.37
ADD FOR OVER HEAD CHARGES @5% : 23.68
COST FOR 0.300 mtr. 544.73
COST PER mtr. 1815.75
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 466.68
TOTAL : 466.68
Add for water charges : 7.00
TOTAL : 473.68
ADD FOR CONTRACTORS PROFIT @10% : 47.37
ADD FOR OVER HEAD CHARGES @5% : 23.68
LABOUR FOR 0.300 mtr. 544.73
LABOUR PER mtr. 1815.75
09250200 In or under liquid mud including cost of
removing slush etc. complete same as per item
No.092401
LABOUR :
Beldar Each 4.00000 116.67 466.68
TOTAL : 466.68
Add for water charges @1.5% : 7.00
TOTAL : 473.68
ADD FOR CONTRACTORS PROFIT @10% : 47.37
ADD FOR OVER HEAD CHARGES @5% : 23.68
COST FOR 0.300 mtr 544.73
COST PER mtr 1815.75
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 466.68
TOTAL : 466.68
Add for water charges : 7.00
TOTAL : 473.68
ADD FOR CONTRACTORS PROFIT @10% : 47.37
ADD FOR OVER HEAD CHARGES @5% : 23.68
LABOUR FOR 0.300 mtr 544.73
LABOUR PER mtr 1815.75
09250300 In or under foul condition.
Detail of cost for 1 cubic metre.
LABOUR :
Mason 1st class EACH 0.02000 211.16 4.22
Mason 2nd Class Each 0.02000 158.67 3.17
Beldar Each 0.40000 116.67 46.67
TOTAL : 54.06
Add for water charges @1.5% : 0.81
TOTAL : 54.88
ADD FOR CONTRACTORS PROFIT @10% : 5.49
CONCRETE
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 54.06
TOTAL : 54.06
Add for water charges : 0.81
TOTAL : 54.88
ADD FOR CONTRACTORS PROFIT @10% : 5.49
ADD FOR OVER HEAD CHARGES @5% : 2.74
LABOUR FOR 1.000 Cum. 63.11
LABOUR PER Cum. 63.10
MATERIAL :
LABOUR RATE :
ADDITION LABOUR FOR FINISHING : 336.59
Labour As per item no :0920010A 110.25 (-a-)
TOTAL : 446.84
Add for water charges : 5.04
TOTAL : 451.88
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a-): 34.16
ADD FOR OVER HEAD CHARGES @5% EXCEPT ON (-a-) : 17.08
LABOUR FOR 10.000 sqm 503.12
LABOUR PER sqm 50.30
0926000B Difference in cost for using water borne
aggregate.
MATERIAL :
MATERIAL :
LABOUR RATE :
ADDITION LABOUR FOR FINISHING : 335.80
Labour As per item no :0920010A 167.58 (-a-)
TOTAL : 502.38
Add for water charges : 5.03
TOTAL : 507.41
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a-): 34.08
ADD FOR OVER HEAD CHARGES @5% EXCEPT ON (-a-) 17.04
LABOUR FOR 10.000 sqm. 558.53
LABOUR PER sqm. 55.85
MATERIAL :
MATERIAL :
CONCRETE
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ADDITION LABOUR FOR FINISHING : 333.25
Labour As per item no :0920010A 220.50 (-a-)
TOTAL : 553.75
Add for water charges : 5.00
TOTAL : 558.75
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a-): 33.82
ADD FOR OVER HEAD CHARGES @5% EXCEPT ON (-a-) 16.91
LABOUR FOR 10.000 Sqm. 609.48
LABOUR PER Sqm. 60.95
MATERIAL :
Stone aggregate 20 mm
Cum. 0.50000 460.00 230.00
Water borne aggregate 20 mm
Cum. 0.50000 350.00 175.00
Difference between stone aggregate
and water borne aggregate : 55.00
ADD FOR CONTRACTORS PROFIT @10% : 5.50
ADD FOR OVER HEAD CHARGES @5% : 2.75
COST FOR 10.000 Sqm. 63.25
COST PER Sqm. 6.30
MATERIAL :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 51.30
Labour for cement mortar 1:2 22.07
TOTAL : 73.37
Add for water charges : 11.02
TOTAL : 84.39
ADD FOR CONTRACTORS PROFIT @10% : 8.44
ADD FOR OVER HEAD CHARGES @5% : 4.22
LABOUR FOR 10.000 Sqm. 97.05
LABOUR PER Sqm. 9.70
09290200 20 mm thick.
Detail of cost for 10 square metre.
MATERIAL :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 51.33
Labour for cement mortar 1:2 28.75
TOTAL : 80.08
Add for water charges : 14.12
TOTAL : 94.20
ADD FOR CONTRACTORS PROFIT @10% : 9.42
ADD FOR OVER HEAD CHARGES @5% : 4.71
LABOUR FOR 10.000 Sqm. 108.32
LABOUR PER Sqm. 10.80
09300000 Applying a coat of hot bitumen (mexphalt
80/100 or equivalent) using 1.70 kg. per
square metre on damp proof course after
cleaning the surface with a piece of cloth
lightly soaked with kerosene.
Detail of cost for 10 square metre.
MATERIAL :
Mexphalt 80/100
Tonne 0.01700 43940.00 746.98
Kerosene oil
Litre 1.35000 20.00 27.00
Fuel for heating L.S 11.00
CARRIAGE :
Tar Bitumen.
1 KM BY MECH. TRANSPORT 1 Tonne 0.01700 123.25 2.10
100 MTRS BY HEAD LOAD 1 Tonne 0.01700 33.08 0.56
LABOUR :
Beldar Each 0.22000 116.67 25.67
Painter 1st Class Each 0.18000 148.16 26.67
SUNDRIES : L.S 3.00
TOTAL : 842.97
ADD FOR CONTRACTORS PROFIT @10% 84.30
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 55.34
TOTAL : 55.34
ADD FOR CONTRACTORS PROFIT @10% : 5.53
ADD FOR OVER HEAD CHARGES @5% : 2.77
LABOUR FOR 10.000 Sqm. 63.64
LABOUR PER Sqm. 6.35
MATERIAL :
Total : 3235.58
Add for water charges @1.5% Except on (-I-) 0.82
Total : 3236.40
ADD FOR CONTRACTORS PROFIT @10% Except on (-I-): 5.52
ADD FOR OVER HEAD CHARGES @5% Except on (-I-): 2.76
COST FOR 1.000 Cum. 3244.68
COST PER Cum. 3244.70
LABOUR RATE :
ADDITION LABOUR FOR LAYING C.C IN RCC WORK 54.43
Labour As per item no :0920010A 441.00 (-a-)
TOTAL : 495.43
Add for water charges : 0.82
TOTAL : 496.25
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a-) 5.53
ADD FOR OVER HEAD CHARGES @5% EXCEPT ON (-a-) 2.76
LABOUR FOR 1.000 Cum. 504.54
CONCRETE
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
Base:-1x6.0x1.5x0.2=1.80 cu.m.
HEEL:-1X6X0.3X0.2 = 0.36 cum.
1x6x0.3x0.3 = 0.54 cu.m.
Stem:-1x6x4.3x0.2 = 5.16 cu.m.
Irregular counter Forts:-
2x1/2x4.4x1.5x0.2=1.32 cu.m.
--------------
Total : = 9.18 Cum.
(Rate as per item no. 9200200)
1 Cum. 9.18000 3231.20 29662.42 (-I-)
LABOUR (EXTRA FOR LAYING C.C IN RCC WORK):
Rate as per item no 09310100 1 Cum. 9.18000 54.43 499.67
Total : 30162.08
Add for water charges @1.5% Except on (-I-) : 7.50
Total : 30169.58
ADD FOR CONTRACTORS PROFIT @10% Except on (-I-): 50.71
ADD FOR OVER HEAD CHARGES @5% Except on (-I-) : 25.35
COST FOR 9.180 Cum. 30245.64
COST PER Cum. 3294.70
LABOUR RATE :
ADDITION LABOUR FOR LAYING C.C IN RCC WORK 499.66
Labour As per item no :09200200 4297.15 (-a-)
TOTAL : 4796.81
Add for water charges : 7.50
TOTAL : 4807.31
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a-): 50.71
ADD FOR OVER HEAD CHARGES @5% EXCEPT ON (-a-) : 25.35
LABOUR FOR 9.180 Cum. 4880.37
LABOUR PER Cum. 531.60
CONCRETE
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
Total : 3255.42
Add for water charges @1.5% Except on (-I-) : 1.10
Total : 3256.52
ADD FOR CONTRACTORS PROFIT @10% Except on (-I-) : 7.53
ADD FOR OVER HEAD CHARGES @5% Except on (-I-) : 3.76
COST FOR 1.000 CUM 3267.81
COST PER CUM 3267.80
LABOUR RATE :
ADDITION LABOUR FOR LAYING C.C IN RCC WORK 74.27
Labour As per item no :0920010A 441.00 (-a-)
TOTAL : 515.27
Add for water charges : 1.10
TOTAL : 516.37
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a-) : 7.53
ADD FOR OVER HEAD CHARGES @5% EXCEPT ON (-a-) : 3.76
LABOUR FOR 1.000 CUM 527.66
LABOUR PER CUM 527.65
MATERIAL :
Total : 3528.37
Add for water charges @1.5% Except on (-I-) : 1.10
Total : 3529.47
ADD FOR CONTRACTORS PROFIT @10% Except on (-I-): 7.53
ADD FOR OVER HEAD CHARGES @5% Except on (-I-) : 3.76
COST FOR 1.000 Cum. 3540.76
COST PER Cum. 3540.75
LABOUR RATE :
ADDITION LABOUR FOR LAYING C.C IN RCC WORK 74.27
Labour As per item no :09200300 714.00 (-a-)
TOTAL : 788.27
Add for water charges : 1.10
TOTAL : 789.37
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a-): 7.53
ADD FOR OVER HEAD CHARGES @5% EXCEPT ON (-a-) : 3.76
LABOUR FOR 1.000 Cum. 800.66
LABOUR PER Cum. 800.65
09310500 Stair cases (except spiral stair cases)
excluding landing but including preparing of
the surface and finishing of nosing upto
floor two level.
Detail of cost for a flight of 3.40 m clear
span including 1 metre landing (cost of
landing excluded)
MATERIAL :
Total : 2760.85
Add for water charges @1.5% Except on (-I-) 3.72
Total : 2764.57
ADD FOR CONTRACTORS PROFIT @10% Except on (-I-) : 25.14
ADD FOR OVER HEAD CHARGES @5% Except on (-I-) : 12.57
COST FOR 0.790 cum. 2802.28
COST PER cum. 3547.20
LABOUR RATE :
ADDITION LABOUR FOR LAYING C.C IN RCC WORK AND
EXTRA LABOUR FOR FINISHING 247.75
Labour As per item no :0920010A 348.39 (-a-)
TOTAL : 596.14
Add for water charges : 3.72
TOTAL : 599.86
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a-): 25.14
ADD FOR OVER HEAD CHARGES @5% EXCEPT ON (-a-) : 12.57
LABOUR FOR 0.790 cum. 637.57
LABOUR PER cum. 807.00
09310600 Spiral stair cases including landings etc.
upto floor two level.
Detail of cost for ten steps:
MATERIAL :
LABOUR RATE :
ADDITION LABOUR FOR LAYING C.C IN RCC WORK AND
EXTRA LABOUR FOR FINISHING 151.06
Labour As per item no :0920010A 105.84 (-a-)
TOTAL : 256.90
Add for water charges : 2.26
TOTAL : 259.16
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a-): 15.33
ADD FOR OVER HEAD CHARGES @5% EXCEPT ON (-a-): 7.66
LABOUR FOR 0.240 CUM 282.15
LABOUR PER CUM 1175.60
09310700 Arches upto floor two level.
MATERIAL :
Total : 89030.38
Add for water charges @1.5% Except on (-I-) : 59.97
Total : 89090.35
ADD FOR CONTRACTORS PROFIT @10% Except on (-I-) : 405.82
ADD FOR OVER HEAD CHARGES @5% Except on (-I-) : 202.91
COST FOR 26.730 Cum. 89699.08
COST PER Cum. 3355.75
LABOUR RATE :
ADDITION LABOUR FOR LAYING C.C IN RCC WORK AND
EXTRA LABOUR FOR LAYING CONCRETE OVER CURVED S URFAC 3E998.24
Labour As per item no :0920010A 11787.93 (-a-)
TOTAL : 15786.17
Add for water charges : 59.97
TOTAL : 15846.14
CONCRETE
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
Total : 3314.54
Add for water charges @1.5% Except on (-I-) : 0.30
Total : 3314.84
ADD FOR CONTRACTORS PROFIT @10% Except on (-I-) : 2.01
ADD FOR OVER HEAD CHARGES @5% Except on (-I-) : 1.00
COST FOR 1.000 Cum. 3317.85
COST PER Cum. 3317.85
LABOUR RATE :
LABOUR (EXTRA FOR LIFTING MATERIAL) 19.84
Labour As per item no :09310200 531.60 (-a-)
TOTAL : 551.44
Add for water charges : 0.30
TOTAL : 551.74
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a-): 2.01
ADD FOR OVER HEAD CHARGES @5% EXCEPT ON (-a-) : 1.00
LABOUR FOR 1.000 Cum. 554.75
LABOUR PER Cum. 554.75
MATERIAL :
Total : 3304.03
Add for water charges @1.5% Except on (-I-) 0.15
Total : 3304.18
ADD FOR CONTRACTORS PROFIT @10% Except on (-I-) : 0.95
CONCRETE
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
LABOUR (EXTRA INVOLVED) 9.33
Labour As per item no :09310200 531.60 (-a-)
TOTAL : 540.93
Add for water charges : 0.15
TOTAL : 541.08
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a-) : 0.95
ADD FOR OVER HEAD CHARGES @5% EXCEPT ON (-a-) : 0.47
LABOUR FOR 1.000 Cum. 542.50
LABOUR PER Cum. 542.50
09311000 Vertical and horizontal (thickness not more
than 0.10 m) individually or forming box
louvers and projected band upto floor two
level :
Detail of cost for 4 vertical R.C.C. fins 4m
height and at 1 metre centre with two
horizontal fins all projecting 60cms from
face of wall and 5 cm. thick. = 0.66
Cu.M.
MATERIAL :
Total : 2197.11
Add for water charges @1.5% Except on (-I-) : 1.46
Total : 2198.57
ADD FOR CONTRACTORS PROFIT @10% Except on (-I-) : 9.90
ADD FOR OVER HEAD CHARGES @5% Except on (-I-) : 4.95
COST FOR 0.660 cum. 2213.42
COST PER cum. 3353.65
CONCRETE
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
LABOUR (EXTRA FOR LIFTING MATERIAL) AND
(EXTRA LABOUR FOR RESTRICTED WORK IN FINS): 97.56
Labour As per item no :0920010A 291.06 (-a-)
TOTAL : 388.62
Add for water charges : 1.46
TOTAL : 390.08
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a-) : 9.90
ADD FOR OVER HEAD CHARGES @5% EXCEPT ON (-a-) : 4.95
LABOUR FOR 0.660 cum. 404.93
LABOUR PER cum. 613.50
09320000 Providing and laying cement concrete work
1:1.1/2:3 (1 cement :
1.1/2 sand :3 graded stone aggregate 20mm
nominal size) and curing complete excluding
cost of form work and reinforcement for
reinforced concrete work in :
09320100 Wall (any thickness but not less than 0.1 m
thickness) attached pilasters, buttresses,
plinth and string courses etc. from top of
foundation level upto floor two level :
Detail of cost for a counterfort retaining
wall 4.5 m. height and 6 metre long :
MATERIAL :
Total : 33957.08
Add for water charges @1.5% Except on (-I-)
: 7.50
Total : 33964.58
ADD FOR CONTRACTORS PROFIT @10% Except on (-I-) : 50.71
ADD FOR OVER HEAD CHARGES @5% Except on (-I-) : 25.35
COST FOR 9.180 Cum. 34040.6
COST PER Cum. 3708.15
LABOUR RATE :
ADDITION LABOUR FOR LAYING C.C IN RCC WORK 499.66
Labour As per item no :09180200 (9.18 x 497.20) 4564.30 (-a-)
TOTAL : 5063.96
Add for water charges : 7.50
CONCRETE
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 5071.46
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a-) : 50.71
ADD FOR OVER HEAD CHARGES @5% EXCEPT ON (-a-) : 25.35
LABOUR FOR 9.180 Cum. 5147.52
LABOUR PER Cum. 560.70
09320200 Lintels, beams girders bressumers and
cantilevers upto floor two level :
Detail of cost for 1 cu.m. .
MATERIAL :
Total : 3668.87
Add for water charges @1.5% Except on (-I-) : 1.10
Total : 3669.97
ADD FOR CONTRACTORS PROFIT @10% Except on (-I-) : 7.53
ADD FOR OVER HEAD CHARGES @5% Except on (-I-) : 3.76
COST FOR 1.000 Cum. 3681.26
COST PER Cum. 3681.25
LABOUR RATE :
ADDITION LABOUR FOR LAYING C.C IN RCC WORK AND
LABOUR (EXTRA FOR LIFTING MATERIAL) : 74.27
Labour As per item no :0918010A 447.15 (-a-)
TOTAL : 521.42
Add for water charges : 1.10
TOTAL : 522.52
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a-) : 7.53
ADD FOR OVER HEAD CHARGES @5% EXCEPT ON (-a-) : 3.76
LABOUR FOR 1.000 Cum. 533.80
LABOUR PER Cum. 533.80
09320300 Column, pillars, posts and struts upto floor
two level :
Detail of cost for 1 cu.m. .
MATERIAL :
Total : 3941.82
Add for water charges @1.5% Except on (-I-) : 1.10
Total : 3942.92
ADD FOR CONTRACTORS PROFIT @10% Except on (-I-) : 7.53
ADD FOR OVER HEAD CHARGES @5% Except on (-I-) : 3.76
COST FOR 1.000 Cum. 3954.21
COST PER Cum. 3954.20
LABOUR RATE :
ADDITION LABOUR FOR LAYING C.C IN RCC WORK AND
LABOUR (EXTRA FOR LIFTING MATERIAL) : 74.27
Labour As per item no :09180300 720.10 (-a-)
TOTAL : 794.37
Add for water charges : 1.10
TOTAL : 795.47
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a-) : 7.53
ADD FOR OVER HEAD CHARGES @5% EXCEPT ON (-a-) : 3.76
LABOUR FOR 1.000 Cum. 806.76
LABOUR PER Cum. 806.75
09330000 Providing and laying cement concrete 1:1:2 (1
cement : 1 sand :2 graded stone aggregate
20mm nominal size) and curing complete
excluding cost of form work and reinforcement
in reinforced concrete work in :
09330100 Walls (any thickness but not exceeding 0.1
metre thickness) including attached
pilasters, buttersses, plinth and string.
Concrete etc. from top of foundation level
upto floor two level.
Detail of cost of counterfort retaining walls
4.5 metres high, 6 metres long=9.18 cu.m.
MATERIAL :
Total : 41938.87
ADD FOR CONTRACTORS PROFIT @10% Except on (-I-) : 56.10
ADD FOR OVER HEAD CHARGES @5% Except on (-I-) : 28.05
COST FOR 9.180 Cum. 42023.02
COST PER Cum. 4577.65
LABOUR RATE :
ADDITION LABOUR FOR LAYING C.C IN RCC WORK + SUNDRIES : 522.66
Labour As per item no :09170200 4681.80 (-a-)
TOTAL : 5204.46
Add for water charges : 8.28
TOTAL : 5212.74
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a-) : 56.10
ADD FOR OVER HEAD CHARGES @5% EXCEPT ON (-a-) : 28.05
LABOUR FOR 9.180 Cum. 5296.89
LABOUR PER Cum. 577.00
09330200 Lintels beams, girders, brassumers and
cantilevers upto floor two level etc.
Detail of cost for 1 cubic metre.
MATERIAL :
LABOUR RATE :
ADDITION LABOUR FOR LAYING C.C IN RCC WORK AND
LABOUR (EXTRA FOR LIFTING MATERIAL) + SUNDRIES 89.27
Labour As per item no :0917010A 459.90 (-a-)
TOTAL : 549.17
Add for water charges : 1.34
TOTAL : 550.51
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a-) : 9.06
CONCRETE
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
LABOUR RATE :
ADDITION LABOUR FOR LAYING C.C IN RCC WORK AND
LABOUR (EXTRA FOR LIFTING MATERIAL) + SUNDRIES : 111.27
MATERIAL :
Total : 20825.98
Add for water charges @1.5% Except on (-I-) 1.75
Total : 20827.73
ADD FOR CONTRACTORS PROFIT @10% Except on (-I-) : 11.86
ADD FOR OVER HEAD CHARGES @5% Except on (-I-) : 5.93
COST FOR 1.440 cum. 20845.53
COST PER cum. 14476.00
LABOUR RATE :
ADDITION LABOUR FOR LAYING C.C IN RCC WORK AND
LABOUR (EXTRA FOR LIFTING MATERIAL) : 116.88
Labour As per item no :0920010A 635.04 (-a-)
Labour As per item no :0801020100 2350.68 (-a-)
Labour As per item no :17044010 1123.20
TOTAL : 4225.80
Add for water charges : 1.75
TOTAL : 4227.55
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a-) : 11.86
CONCRETE
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
Total : 18727.42
Add for water charges @1.5% Except on (-I-) 1.75
Total : 18729.17
ADD FOR CONTRACTORS PROFIT @10% Except on (-I-) : 11.86
ADD FOR OVER HEAD CHARGES @5% Except on (-I-) : 5.93
COST FOR 1.440 cum. 18746.97
COST PER cum. 13018.70
LABOUR RATE :
ADDITION LABOUR FOR LAYING C.C IN RCC WORK AND
LABOUR (EXTRA FOR LIFTING MATERIAL) : 116.88
CONCRETE
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 3102.60
Add for water charges : 1.75
TOTAL : 3104.35
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a-) : 11.86
ADD FOR OVER HEAD CHARGES @5% EXCEPT ON (-a-) : 5.93
LABOUR FOR 1.440 cum. 3122.15
LABOUR PER cum. 2168.15
MATERIAL :
TOTAL : 5443.93
Add for water charges : 0.82
TOTAL : 5444.75
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-I-) : 5.44
ADD FOR OVER HEAD CHARGES @5% EXCEPT ON (-I-) : 2.76
COST FOR 1.000 cum. 5452.95
COST PER cum. 5453.00
LABOUR RATE :
ADDITION LABOUR FOR LAYING C.C IN RCC WORK 54.43
MATERIAL :
Total : 7261.03
Add for water charges @1.5% Except on (-I-) 0.82
Total : 7261.85
ADD FOR CONTRACTORS PROFIT @10% Except on (-I-) : 5.52
ADD FOR OVER HEAD CHARGES @5% Except on (-I-) : 2.76
COST FOR 1.000 cum. 7270.13
COST PER cum. 7270.10
LABOUR RATE :
ADDITION LABOUR FOR LAYING C.C IN RCC WORK 54.43
Labour As per item no :09220200 1040.00 (-a-)
TOTAL : 1094.43
Add for water charges : 0.82
TOTAL : 1095.25
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a-) : 5.52
ADD FOR OVER HEAD CHARGES @5% EXCEPT ON (-a-) : 2.76
LABOUR FOR 1.000 cum. 1103.53
LABOUR PER cum. 1103.50
09360300 Small Arched lintels not exceeding 1.5m clear
span over a sailings, copings and the like.
Detail of cost for 1 cu.m.
MATERIAL :
Total : 8806.28
Add for water charges @1.5% Except on (-I-) 0.82
Total : 8807.10
ADD FOR CONTRACTORS PROFIT @10% Except on (-I-) : 5.52
ADD FOR OVER HEAD CHARGES @5% Except on (-I-) : 2.76
COST FOR 1.000 cum. 8815.38
CONCRETE
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ADDITION LABOUR FOR LAYING C.C IN RCC WORK 54.43
Labour As per item no :09220200 1262.00 (-a-)
TOTAL : 1316.43
Add for water charges : 0.82
TOTAL : 1317.25
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a-) : 5.52
ADD FOR OVER HEAD CHARGES @5% EXCEPT ON (-a-) : 2.76
LABOUR FOR 1.000 cum. 1325.53
LABOUR PER cum. 1325.50
MATERIAL :
Total : 7723.83
Add for water charges @1.5% Except on (-I-) 0.82
Total : 7724.65
ADD FOR CONTRACTORS PROFIT @10% Except on (-I-) : 5.52
ADD FOR OVER HEAD CHARGES @5% Except on (-I-) : 2.76
COST FOR 1.000 cum. 7732.93
COST PER cum. 7732.90
LABOUR RATE :
ADDITION LABOUR FOR LAYING C.C IN RCC WORK 54.43
Labour As per item no :09220400 1502.80 (-a-)
TOTAL : 1557.23
Add for water charges : 0.82
TOTAL : 1558.05
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a-) : 5.52
ADD FOR OVER HEAD CHARGES @5% EXCEPT ON (-a-) : 2.76
LABOUR FOR 1.000 cum. 1566.33
LABOUR PER cum. 1566.30
MATERIAL :
CONCRETE
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Total : 7762.68
Add for water charges @1.5% Except on (-I-) 0.82
Total : 7763.50
ADD FOR CONTRACTORS PROFIT @10% Except on (-I-) : 5.52
ADD FOR OVER HEAD CHARGES @5% Except on (-I-) : 2.76
COST FOR 1.000 cum. 7771.78
COST PER cum. 7771.80
LABOUR RATE :
ADDITION LABOUR FOR LAYING C.C IN RCC WORK 54.43
Labour As per item no :09220500 1541.65 (-a-)
TOTAL : 1596.10
Add for water charges : 0.82
TOTAL : 1596.92
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a-) : 5.52
ADD FOR OVER HEAD CHARGES @5% EXCEPT ON (-a-) : 2.76
LABOUR FOR 1.000 cum. 1605.20
LABOUR PER cum. 1605.20
MATERIAL :
Total : 5443.93
Add for water charges @1.5% Except on (-I-) 0.82
Total : 5444.75
ADD FOR CONTRACTORS PROFIT @10% Except on (-I-) : 5.52
CONCRETE
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ADDITION LABOUR FOR LAYING C.C IN RCC WORK 54.43
Labour As per item no :0922010A 758.65 (-a-)
TOTAL : 813.08
Add for water charges : 0.82
TOTAL : 813.90
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a-) : 5.52
ADD FOR OVER HEAD CHARGES @5% EXCEPT ON (-a-) : 2.76
LABOUR FOR 1.000 cum. 822.18
LABOUR PER cum. 822.20
MATERIAL :
Total : 6712.03
Add for water charges @1.5% Except on (-I-) 0.82
Total : 6712.85
ADD FOR CONTRACTORS PROFIT @10% Except on (-I-) : 5.52
ADD FOR OVER HEAD CHARGES @5% Except on (-I-) : 2.76
COST FOR 1.000 cum. 6721.13
COST PER cum. 6721.10
LABOUR RATE :
ADDITION LABOUR FOR LAYING C.C IN RCC WORK 54.43
Labour As per item no :09230200 1040.00 (-a-)
TOTAL : 1094.43
Add for water charges : 0.82
TOTAL : 1095.25
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a-) : 5.52
ADD FOR OVER HEAD CHARGES @5% EXCEPT ON (-a-) : 2.76
LABOUR FOR 1.000 cum. 1103.53
LABOUR PER cum. 1103.50
MATERIAL :
Total : 8257.28
Add for water charges @1.5% Except on (-I-) 0.82
Total : 8258.10
ADD FOR CONTRACTORS PROFIT @10% Except on (-I-) : 5.52
ADD FOR OVER HEAD CHARGES @5% Except on (-I-) : 2.76
COST FOR 1.000 cum. 8266.38
COST PER cum. 8266.40
LABOUR RATE :
ADDITION LABOUR FOR LAYING C.C IN RCC WORK 54.43
Labour As per item no :09230300 1262.00 (-a-)
TOTAL : 1316.43
Add for water charges : 0.82
TOTAL : 1317.25
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a-) : 5.52
ADD FOR OVER HEAD CHARGES @5% EXCEPT ON (-a-) : 2.76
LABOUR FOR 1.000 cum. 1325.53
LABOUR PER cum. 1325.50
MATERIAL :
Total : 7174.83
Add for water charges @1.5% Except on (-I-) 0.82
Total : 7175.65
ADD FOR CONTRACTORS PROFIT @10% Except on (-I-) : 5.52
ADD FOR OVER HEAD CHARGES @5% Except on (-I-) : 2.76
COST FOR 1.000 cum. 7183.93
CONCRETE
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ADDITION LABOUR FOR LAYING C.C IN RCC WORK 54.43
Labour As per item no :09230400 1502.80 (-a-)
TOTAL : 1557.23
Add for water charges : 0.82
TOTAL : 1558.05
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a-) : 5.52
ADD FOR OVER HEAD CHARGES @5% EXCEPT ON (-a-) : 2.76
LABOUR FOR 1.000 cum. 1566.33
LABOUR PER cum. 1566.30
MATERIAL :
Total : 7213.68
Add for water charges @1.5% Except on (-I-) 0.82
Total : 7214.50
ADD FOR CONTRACTORS PROFIT @10% Except on (-I-) : 5.52
ADD FOR OVER HEAD CHARGES @5% Except on (-I-) : 2.76
COST FOR 1.000 cum. 7222.78
COST PER cum. 7222.80
LABOUR RATE :
ADDITION LABOUR FOR LAYING C.C IN RCC WORK 54.43
Labour As per item no :09230500 1541.65 (-a-)
TOTAL : 1596.08
Add for water charges : 0.82
TOTAL : 1596.90
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a-) : 5.52
ADD FOR OVER HEAD CHARGES @5% EXCEPT ON (-a-) : 2.76
LABOUR FOR 1.000 cum. 1605.18
LABOUR PER cum. 1605.20
MATERIAL :
LABOUR RATE :
ADDITION LABOUR FOR LAYING C.C IN RCC WORK AND
CONCRETE
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
Concrete work
4.93x0.43x0.20=0.424 cu.m.
(Rate as per item no. 0920010A)
Cum. 0.42400 3181.15 1348.81 (-I-)
Add for difference between 20 mm &
12.5 mm size =0.67 cum.x(rate of code
020101080000(-)020101070000)
Cum. 0.42400 6.70 2.84
Form works
4.93x0.83 girth= 4.09 sq.m.
Rate as per item no.0801010000.
Sqm. 4.09000 331.25 1354.81 (-I-)
LABOUR (EXTRA FOR LAYING C.C IN RCC WORK):
Rate as per item no 09310100 Cum. 0.42400 54.43 23.08
SUNDRIES : L.S 18.00
Total : 2747.54
Add for water charges @1.5% Except on (-I-) 0.65
Total : 2748.19
ADD FOR CONTRACTORS PROFIT @10% Except on (-I-) : 4.45
ADD FOR OVER HEAD CHARGES @5% Except on (-I-) : 2.23
COST FOR 0.4240 Cum. 2754.87
COST PER Cum. 6497.30
CONCRETE
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ADDITION LABOUR FOR LAYING C.C IN RCC WORK AND
EXTRA LABOUR FOR FORM WORK + SUNDRIES +
EXTRA LABOUR FOR POURING CONCRETE : 41.07
Labour As per item no :0920010A 186.98 (-a-)
Labour As per item no :0801010000 194.88 (-a-)
TOTAL : 422.93
Add for water charges : 0.65
TOTAL : 423.58
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a-) : 4.17
ADD FOR OVER HEAD CHARGES @5% EXCEPT ON (-a-) : 2.08
LABOUR FOR 0.424 Cum. 429.83
LABOUR PER CUM 1013.75
MATERIAL :
Total : 44355.43
Add for water charges @1.5% Except on (-I-) 11.23
Total : 44366.66
ADD FOR CONTRACTORS PROFIT @10% Except on (-I-) : 76.00
ADD FOR OVER HEAD CHARGES @5% Except on (-I-) : 38.00
COST FOR 12.250 Cum. 44480.66
COST PER Cum. 3631.00
CONCRETE
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ADDITION LABOUR FOR LAYING C.C IN RCC WORK AND
EXTRA LABOUR FOR FORM WORK + SUNDRIES +
EXTRA LABOUR FOR POURING CONCRETE : 666.76
Labour As per item no :0920010A 5402.25 (-a-)
Labour As per item no :0801010000 667.1 (-a-)
TOTAL : 6736.11
Add for water charges : 11.23
TOTAL : 6747.34
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a-) : 67.80
ADD FOR OVER HEAD CHARGES @5% EXCEPT ON (-a-) : 33.90
LABOUR FOR 12.250 Cum. 6849.04
LABOUR PER CUM 559.10
MATERIAL :
LABOUR :
Black Smith 1st Class Each 1.00000 186.67 186.67
Beldar Each 1.00000 116.67 116.67
SUNDRIES : L.S 50.00
Total : 4829.68
Add for water charges @1.5% Except on (-I-) 72.45
Total : 4902.13
ADD FOR CONTRACTORS PROFIT @10% 490.21
ADD FOR OVER HEAD CHARGES @5% 245.10
COST FOR 100.000 kg 5637.44
COST PER kg 56.40
LABOUR RATE :
CONCRETE
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
CARRIAGE :
Steel,C.G.I.& Asbestos sheets.
1 KM BY MECH. TRANSPORT 1 Tonne 0.10500 73.95 7.76
100 MTRS BY HEAD LOAD 1 Tonne 0.10500 57.85 6.07
LABOUR :
Black Smith 1st Class Each 1.00000 186.67 186.67
Beldar Each 1.00000 116.67 116.67
SUNDRIES : L.S 50.00
Total : 5092.17
Add for water charges @1.5% Except on (-I-) 76.38
Total : 5168.55
ADD FOR CONTRACTORS PROFIT @10% 516.85
ADD FOR OVER HEAD CHARGES @5% 258.42
COST FOR 100.000 kg 5943.82
COST PER kg 59.40
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 353.34
TOTAL : 353.34
Add for water charges : 76.38
TOTAL : 429.72
ADD FOR CONTRACTORS PROFIT @10% : 42.97
ADD FOR OVER HEAD CHARGES @5% : 21.48
LABOUR FOR 100.000 kg 494.17
LABOUR PER kg 4.95
MATERIAL :
CARRIAGE :
Cement
1 KM BY MECH. TRANSPORT 1 Tonne 0.02100 73.95 1.55
100 MTRS BY HEAD LOAD 1 Tonne 0.02100 31.20 0.66
Sand
1 KM BY MECH. TRANSPORT 1 Cum. 0.15000 110.95 16.64
100 MTRS BY HEAD LOAD 1 cum 0.15000 54.35 8.15
LABOUR :
Mason 1st class Each 0.20000 211.16 42.23
Mason 2nd Class Each 0.20000 158.67 31.73
Beldar Each 0.25000 116.67 29.17
SUNDRIES : L.S 15.00
CONCRETE
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 423.69
Add for water charges @1.5% : 6.35
TOTAL : 430.04
ADD FOR CONTRACTORS PROFIT @10% 43.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 118.12
Labour for cement mortar 1:2 3.85
TOTAL : 121.97
Add for water charges : 6.35
TOTAL : 128.32
ADD FOR CONTRACTORS PROFIT @10% : 12.83
ADD FOR OVER HEAD CHARGES @5% : 6.41
LABOUR FOR 10.000 Sqm. 147.56
LABOUR PER Sqm. 14.75
MATERIAL :
LABOUR :
Beldar Each 0.25000 116.67 29.17
TOTAL : 166.75
Add for water charges @1.5% : 2.50
TOTAL : 169.25
ADD FOR CONTRACTORS PROFIT @10% 16.92
CONCRETE
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 29.16
TOTAL : 29.16
Add for water charges : 2.50
TOTAL : 31.66
ADD FOR CONTRACTORS PROFIT @10% : 3.16
ADD FOR OVER HEAD CHARGES @5% : 1.58
LABOUR FOR 10.000 Sqm. 36.40
LABOUR PER Sqm. 3.65
MATERIAL :
TOTAL : 513.21
Add for water charges @1.5% : 7.70
TOTAL : 520.91
ADD FOR CONTRACTORS PROFIT @10% : 52.09
ADD FOR OVER HEAD CHARGES @5% : 26.05
COST FOR 10.000 Sqm. 599.05
COST PER Sqm. 59.90
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 284.34
Labour for cement mortar 1:3 9.25
TOTAL : 293.59
Add for water charges : 4.40
TOTAL : 297.99
CONCRETE
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 350.09
TOTAL : 350.09
Add for water charges : 5.25
TOTAL : 355.34
ADD FOR CONTRACTORS PROFIT @10% : 35.53
ADD FOR OVER HEAD CHARGES @5% : 17.76
LABOUR FOR 31.200 mtr. 408.63
LABOUR PER mtr. 13.10
09470000 Providing and filling in position bitumen mix
filler of proportion 80 kg. of hot bitumen 1
kg. of cement and 0.25 cu.m. of sand for
expension joints.
Details of cost for a joint 2.5 cm wide 15cm
deep and 300mm length :
Cubical contents of joints
300x0.15x0.025=1.125 cu.m.
MATERIAL :
or 0.303 tonne.
Tonne 0.30300 43940.00 13313.82
Steam coal for heating of bitumen 2 quintal
per tonne of bitumen i.e. 0.303x2=0.606
quintal
Qtl. 0.60600 510.00 309.06
Cement 1/8x288.34=3.61kg
or 0.0036 tonne.
Tonne 0.00360 4900.00 17.64
Sand :- 1/4 of the quantity of cement
=3.60/4=0.9 cu.m.
Cum. 0.90000 300.00 270.00
CARRIAGE :
Tar Bitumen.
1 KM BY MECH. TRANSPORT 1 Tonne 0.30300 123.25 37.34
100 MTRS BY HEAD LOAD 1 Tonne 0.30300 33.08 10.02
Steam Coal.
1 KM BY MECH. TRANSPORT 1 Tonne 0.06100 100.85 6.15
100 MTRS BY HEAD LOAD 1 Tonne 0.06100 50.72 3.09
Cement
1 KM BY MECH. TRANSPORT 1 Tonne 0.00400 73.95 0.30
100 MTRS BY HEAD LOAD 1 Tonne 0.00400 31.20 0.12
Sand
1 KM BY MECH. TRANSPORT 1 Cum. 0.90000 110.95 99.86
100 MTRS BY HEAD LOAD 1 cum 0.90000 54.35 48.92
LABOUR :
TOTAL : 26428.23
Add for water charges @1.5% : 396.42
TOTAL : 26824.65
ADD FOR CONTRACTORS PROFIT @10% 2682.46
COST FOR 300 mtr length 2.5cm wide & 15 cm deep 30848.35
COST PER 100 mtr length 1 cm wide & 1 cm deep 274.20
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 12311.91
TOTAL : 12311.91
Add for water charges : 396.42
CONCRETE
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 12708.33
ADD FOR CONTRACTORS PROFIT @10% : 1270.83
ADD FOR OVER HEAD CHARGES @5% : 635.41
LABOUR FOR 300 mtr length 2.5cm wide & 15 cm deep 14614.57
LABOUR PER 100 mtr length 1 cm wide & 1 cm deep 129.90
09480000 Providing and filling in position blown
bitumen in expension joints.
Details of cost for a joint 2.5 cm wide 15 cm
deep and 300 mm in length :
Cubical contents of joint.
300x0.025x0.150=1.125 cu.m.
MATERIAL :
LABOUR :
Mason 2nd Class Each 34.8800 158.67 5534.41
Beldar Each 58.2000 116.67 6790.19
Total 72100.80
COST FOR 300 mtr length 2.5cm wide & 15 cm deep 84159.65
COST PER 100 mtr length 1 cm wide & 1 cm deep 748.00
LABOUR RATE :
CONCRETE
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
TOTAL : 7613.54
Add for water charges @1.5% : 114.20
TOTAL : 7727.74
ADD FOR CONTRACTORS PROFIT @10% : 772.77
ADD FOR OVER HEAD CHARGES @5% : 386.39
COST FOR 100 mtr length 12mm thick& 10 cm deep 8886.90
COST FOR 100 mtr length 12mm thick& 1 cm deep 888.70
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 73.54
TOTAL : 73.54
Add for water charges : 114.20
TOTAL : 187.74
ADD FOR CONTRACTORS PROFIT @10% : 18.77
ADD FOR OVER HEAD CHARGES @5% : 9.39
LABOUR FOR 100 mtr length 12mm thick& 10 cm deep 215.90
CONCRETE
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
CARRIAGE :
Stone aggregate below 40mm.
1 KM BY MECH. TRANSPORT 1 Cum. 0.89000 110.95 98.75
100 MTRS BY HEAD LOAD 1 cum 0.89000 54.35 48.37
Sand
1 KM BY MECH. TRANSPORT 1 Cum. 0.44500 110.95 49.37
100 MTRS BY HEAD LOAD 1 cum 0.44500 54.35 24.19
Cement
1 KM BY MECH. TRANSPORT 1 Tonne 0.08800 73.95 6.51
100 MTRS BY HEAD LOAD 1 Tonne 0.08800 31.20 2.75
LABOUR :
Beldar Each 2.09000 116.67 243.84
Bhishti Each 0.27000 116.67 31.50
Mason 1st class Each 0.05000 211.16 10.56
Mason 2nd Class Each 0.05000 158.67 7.93
Mate Each 0.04000 116.67 4.67
Beldar (For extra ramming) Each 0.25000 116.67 29.17
SUNDRIES : L.S 15.00
TOTAL : 1553.02
Add for water charges @1.5% : 23.30
TOTAL : 1576.32
ADD FOR CONTRACTORS PROFIT @10% 157.63
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 342.64
TOTAL : 342.64
Add for water charges : 23.30
TOTAL : 365.94
ADD FOR CONTRACTORS PROFIT @10% : 36.59
ADD FOR OVER HEAD CHARGES @5% : 18.30
LABOUR FOR 1.000 Cum. 420.83
LABOUR PER Cum. 420.80
09510000 Providing and laying cement concrete 1:5:10
(1cement :5sand :10 graded stone aggregate
40mm. nominal size) with 15 % plum and curing
complete excluding cost of form work in
retaining walls/ Breast walls, the size of
plums shall usually be 150mm. to 300mm. as
per H.P.P.W.D.Specification.
Detail of cost for one Cum.
MATERIAL :
Cement
1 KM BY MECH. TRANSPORT 1 Tonne 0.12000 73.95 8.87
100 MTRS BY HEAD LOAD 1 Tonne 0.12000 31.20 3.74
CONCRETE
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR :
Beldar Each 1.07000 116.67 124.84
Beldar (For extra ramming) Each 0.98000 116.67 114.34
Bhishti (For extra ramming) Each 0.25000 116.67 29.17
Mason 1st class Each 0.17000 211.16 35.90
SUNDRIES : L.S 25.00
TOTAL : 1708.60
Add for water charges @1.5% : 25.62
TOTAL : 1734.22
ADD FOR CONTRACTORS PROFIT @10% 173.42
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 329.24
TOTAL : 329.24
Add for water charges : 25.62
TOTAL : 354.86
ADD FOR CONTRACTORS PROFIT @10% : 35.48
ADD FOR OVER HEAD CHARGES @5% : 17.74
LABOUR FOR 1.000 Cum 408.18
LABOUR PER Cum 408.20
MATERIAL :
LABOUR :
Extra labour for laying CC in RCC work
Beldar Each 0.10000 116.67 11.66
Bhishti Each 0.20000 116.67 23.33
Mason 1st class Each 0.04000 211.16 8.44
Mason 2nd class Each 0.04000 158.67 6.34
Mate Each 0.04000 116.67 4.66
TOTAL : 3649.03
Add for water charges @1.5% Except on (-I-) : 0.82
TOTAL : 3649.85
ADD FOR CONTRACTORS PROFIT @10% Except on (-I-) : 5.52
LABOUR RATE :
Labour as per item No. 0918010A 447.15 (-a-)
Extra labour for laying C.C. in RCC 54.43
501.58
Add for water charges : 0.82
TOTAL : 502.40
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-) : 5.52
ADD FOR OVER HEAD CHARGES @5% Except on (-a-) : 2.76
LABOUR FOR 1.000 Cum 510.68
LABOUR PER Cum 510.70
MATERIAL :
LABOUR :
Extra labour for laying CC in RCC work
Rate as per item No. 09310100 54.43
TOTAL : 3668.87
Add for water charges @1.5% Except on (-I-) : 1.11
TOTAL : 3669.98
ADD FOR CONTRACTORS PROFIT @10% Except on (-I-) : 7.54
LABOUR RATE :
Labour as per item No. 0918010A 447.15 (-a-)
Extra labour for laying C.C. in RCC & lifting/finishng 74.27
TOTAL : 521.42
Add for water charges : 1.11
TOTAL : 522.53
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-) : 7.54
ADD FOR OVER HEAD CHARGES @5% Except on (-a-) : 3.77
LABOUR FOR 1.00 Cum 533.84
LABOUR Rate PER Cum 533.85
MATERIAL :
LABOUR :
Extra labour for laying CC in RCC work
Rate as per item No. 09310100
Cum 0.79000 54.53 43.00
Extra labour for finishing
Mason 1st class Each 0.50000 211.16 105.58
Mason 2nd class Each 0.50000 158.67 79.34
CONCRETE
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 3087.48
Add for water charges @1.5% Except on (-I-) : 3.72
TOTAL : 3091.20
ADD FOR CONTRACTORS PROFIT @10% Except on (-I-) : 25.14
LABOUR RATE :
Labour as per item No. 0918010A 353.25 (-a-)
Extra labour for laying C.C. in RCC & lifting/finishng 247.75
601.00
Add for water charges : 3.72
TOTAL : 604.72
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-) : 25.14
ADD FOR OVER HEAD CHARGES @5% Except on (-a-) : 12.57
LABOUR FOR 0.79 Cum 642.43
LABOUR Rate PER Cum 813.20
MATERIAL :
LABOUR :
Extra labour for laying CC in RCC work
Rate as per item No. 09310100
Cum 0.24000 54.53 13.06
TOTAL : 1013.76
Add for water charges @1.5% Except on (-I-) : 2.26
TOTAL : 1016.02
ADD FOR CONTRACTORS PROFIT @10% Except on (-I-) : 15.33
LABOUR RATE :
Labour as per item No. 0918010A 107.32 (-a-)
Extra labour for laying C.C. in RCC & lifting/finishing 151.06
TOTAL : 258.38
Add for water charges : 2.26
TOTAL : 260.64
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-) : 15.33
ADD FOR OVER HEAD CHARGES @5% Except on (-a-) : 7.66
LABOUR FOR 0.24 Cum 283.63
LABOUR Rate PER Cum 1181.80
MATERIAL :
LABOUR :
Extra labour for laying CC in RCC work
Rate as per item No. 09310100
Cum 26.73000 54.53 1454.91
TOTAL : 101536.80
Add for water charges @1.5% Except on (-I-) : 81.80
TOTAL : 101618.60
ADD FOR CONTRACTORS PROFIT @10% Except on (-I-) : 553.50
LABOUR RATE :
Labour as per item No. 0918010A 11952.31 (-a-)
Extra labour for laying CC in RCC &
laying CC in curred surface 5453.15
TOTAL : 17405.46
Add for water charges : 81.80
TOTAL : 17487.26
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-) : 553.50
ADD FOR OVER HEAD CHARGES @5% Except on (-a-) : 276.75
LABOUR FOR 26.73 Cum 18317.51
LABOUR Rate PER Cum 685.30
MATERIAL :
LABOUR :
Extra labour for laying CC in wall staining
TOTAL : 3717.48
Add for water charges @1.5% Except on (-I-) : 0.15
TOTAL : 3717.63
ADD FOR CONTRACTORS PROFIT @10% Except on (-I-) : 0.95
LABOUR RATE :
Labour as per item No. 09320100 560.70 (-a-)
Extra labour for laying CC in RCC wall
staining 9.33
TOTAL : 570.03
Add for water charges : 0.15
TOTAL : 570.18
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-) : 0.95
ADD FOR OVER HEAD CHARGES @5% Except on (-a-) : 0.47
Labour Cost for 1 cum 571.60
LABOUR Rate PER Cum 571.60
MATERIAL :
LABOUR :
Labour as per item No. 0918010A cum 0.66000 54.43 35.92
Extra labour lifting of material
Beldar Each 0.12000 116.67 14.00
Mason 1st class Each 0.05000 211.16 10.55
Mason 2nd class Each 0.05000 158.67 7.93
Beldar (for extra ramming Each 0.10000 116.67 11.66
Bhisti (for extra ramming Each 0.15000 116.67 17.50
TOTAL : 2470.00
Add for water charges @1.5% Except on (-I-) : 1.46
TOTAL : 2471.46
ADD FOR CONTRACTORS PROFIT @10% Except on (-I-) : 9.90
CONCRETE
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
Labour as per item No. 0918010A 295.10 (-a-)
Extra labour for ramming 97.56
TOTAL : 392.66
Add for water charges : 1.46
TOTAL : 394.12
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-) : 9.90
ADD FOR OVER HEAD CHARGES @5% Except on (-a-) : 4.95
Labour Cost for 0.66 cum 408.97
LABOUR Rate PER sqm 619.70
MATERIAL :
Carriage :-
Carriage & labour for mixing LS 5.00
Total 43.50
Add for water charges @1.5% 0.65
TOTAL : 44.15
ADD FOR CONTRACTORS PROFIT @10% 4.42
VOLUME - II
ANALYSIS FOR SCHEDULE OF RATES 2009
(VOLUME II)
CONTENTS
Chapter No. Name of Sub-head Page No.
X Brick Work 359 to 534
XI Stone Masonry, Precast Concrete Block 535 to 682
CHAPTER X
BRICK WORK
Chapter X
1 Unless otherwise stated , the labour rates include the cost of re handling of materials
within 100 meters.
2 The labour rates as well as through rates include the cost of water, is supplied free by
Department , the rates will be reduced accordingly.
3 The labour rates include the cost of water, tools and plants, scaffolding (labour and
material) and cost of good earth for mud mortar.
4 The through rates include the carriage of all materials for 100 mtrs on had load and one
kilometer by mechanical Transport .
5 The rates are applicable for conventional bricks with sizes in stated F.P.S Units. These
rates are not applicable for modular bricks.
6 The rates are applicable for laying of brick in foundations and plinth/ floor level two .
The plinth level shall be taken as 1.5 meters above ground level. The maximum story-
height shall be taken as 3 meters. In case of structure like retaining walls / breast walls,
height of 4 mtrs above ground level shall be reckoned as floor level two. This height shall
be 6 meters above ground level in case piers and abutments. Similar procedure for
demarcation of demarcation of works done in basement of works done in basement shall
be adopted for increase of rates.
BRICK WORK (CONTD.)
Bricks used shall be of the specified class and size. The nominal and actual size of different
categories of bricks and brick tiles shall be as under
S. No. Type of Bricks Nominal Size Actual Size
1 Modular bricks 20cm10cm 10cm 19cm9cm9cm
7.873.94 3.94 7.48 3.54 3.54
2 Modular bricks tiles 20cm10cm 10cm 19cm9cm4cm
7.87 3.941.97 7.48 3.541.57
3 Conventional FPS 22.86cm11.43cm7.62cm 22.68cm11.43cm6.99cm
brick 9.00 43 9.00 42
4 Conventional FPS 22.86cm11.43cm5.08cm 22.68cm11.43cm4.45cm
brick tiles 9.00 42 9.00 41
5. FPS large size 25.40cm12.70cm7.62cm 25.40cm12.53cm7.62cm
bricks 10.00 5.003.00 10.00 43.00
6. FPS large size 25.40cm12.70cm5.08cm 25.40cm12.53cm5.08cm
bricks tiles 10.00 5.002.00 10.00 42.00
7. Machine make 20.00cm10.00cm10.00cm 19.00cm9.00cm9.00cm
bricks
Where the sizes of bricks \ brick tiles are not specifically mentioned it shall be taken to mean
either conventional F.P.S large sizes according as is commonly available in the area. The
permitted tolerance in sizes for bricks of sub-class A is 3% and that for bricks of sub-class B
is 8%.
CHAPTER-X
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
CODE
10010100 Brick work using common burnt clay
building bricks in foundation and
plinth in :-
MATERIAL :
CARRIAGE :
Bricks.
1 KM BY MECH. TRANSPORT 1000 Nos. 475.0000 277.35 131.74
LABOUR :
Mason 1st class Each 0.5000 211.16 105.58
Mason 2nd Class Each 0.5000 158.67 79.34
Beldar Each 1.8000 116.67 210.01
Bhishti Each 0.2000 116.67 23.33
SUNDRIES : 22.50
TOTAL : 2624.07
ADD FOR WATER CHARGES @ 1.5% : 39.36
TOTAL : 2663.43
ADD FOR CONTRACTORS PROFIT @ 10% 266.34
ADD FOR OVER HEAD CHARGES @5% : 133.17
COST FOR 1.000 cum 3062.94
COST PER cum 3062.95
LABOUR PER cum 647.10
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 440.76
Labour for lime surkhi mortar 1:1:1 82.60
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 523.36
WATER CHARGES @ 1.5% : 39.36
TOTAL : 562.72
ADD FOR CONTRACTORS PROFIT @10% : 56.27
ADD FOR OVER HEAD CHARGES @5% : 28.14
LABOUR FOR 1.000 cum 647.12
LABOUR PER cum 647.10
MATERIAL :
CARRIAGE :
Bricks.
1 KM BY MECH. TRANSPORT 1000 Nos. 475.0000 277.35 131.74
LABOUR :
Mason 1st class Each 0.5000 211.16 105.58
Mason 2nd Class Each 0.5000 158.67 79.34
Beldar Each 1.8000 116.67 210.01
Bhishti Each 0.2000 116.67 23.33
SUNDRIES : 22.50
TOTAL : 2528.07
ADD FOR WATER CHARGES @ 1.5% : 37.92
TOTAL : 2565.99
ADD FOR CONTRACTORS PROFIT @ 10% 256.60
ADD FOR OVER HEAD CHARGES @5% : 128.30
COST FOR 1.000 cum 2950.88
COST PER cum 2950.90
LABOUR PER cum 645.50
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 440.76
Labour for lime surkhi mortar 1:1:1 82.60
TOTAL : 523.36
WATER CHARGES @ 1.5% : 37.92
TOTAL : 561.28
ADD FOR CONTRACTORS PROFIT @10% : 56.13
ADD FOR OVER HEAD CHARGES @5% : 28.06
LABOUR FOR 1.000 cum 645.47
LABOUR PER cum 645.50
MATERIAL :
CARRIAGE :
Bricks.
1 KM BY MECH. TRANSPORT 1000 Nos. 475.0000 277.35 131.74
LABOUR :
Mason 1st class Each 0.5000 211.16 105.58
Mason 2nd Class Each 0.5000 158.67 79.34
Beldar Each 1.8000 116.67 210.01
Bhishti Each 0.2000 116.67 23.33
SUNDRIES : 22.50
TOTAL : 2691.93
ADD FOR WATER CHARGES @ 1.5% : 40.38
TOTAL : 2732.31
ADD FOR CONTRACTORS PROFIT @ 10% 273.23
ADD FOR OVER HEAD CHARGES @5% : 136.62
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
COST FOR 1.000 cum 3142.16
COST PER cum 3142.15
LABOUR PER cum 648.30
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 440.76
Labour for lime surkhi mortar 1:1:1 82.60
TOTAL : 523.36
WATER CHARGES @ 1.5% : 40.38
TOTAL : 563.73
ADD FOR CONTRACTORS PROFIT @10% : 56.37
ADD FOR OVER HEAD CHARGES @5% : 28.19
LABOUR FOR 1.000 cum 648.29
LABOUR PER cum 648.30
MATERIAL :
CARRIAGE :
Bricks.
1 KM BY MECH. TRANSPORT 1000 Nos. 475.0000 277.35 131.74
LABOUR :
Mason 1st class Each 0.5000 211.16 105.58
Mason 2nd Class Each 0.5000 158.67 79.34
Beldar Each 1.8000 116.67 210.01
Bhishti Each 0.2000 116.67 23.33
SUNDRIES : 22.50
TOTAL : 2596.93
ADD FOR WATER CHARGES @ 1.5% : 38.95
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 2635.89
ADD FOR CONTRACTORS PROFIT @ 10% 263.59
ADD FOR OVER HEAD CHARGES @5% : 131.79
COST FOR 1.000 cum 3031.27
COST PER cum 3031.25
LABOUR PER cum 646.65
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 440.76
Labour for lime surkhi mortar 1:1:1 82.60
TOTAL : 523.36
WATER CHARGES @ 1.5% : 38.95
TOTAL : 562.31
ADD FOR CONTRACTORS PROFIT @10% : 56.23
ADD FOR OVER HEAD CHARGES @5% : 28.12
LABOUR FOR 1.000 cum 646.66
LABOUR PER cum 646.65
MATERIAL :
CARRIAGE :
Bricks.
1 KM BY MECH. TRANSPORT 1000 Nos. 475.0000 277.35 131.74
LABOUR :
Mason 1st class Each 0.5000 211.16 105.58
Mason 2nd Class Each 0.5000 158.67 79.34
Beldar Each 1.8000 116.67 210.01
Bhishti Each 0.2000 116.67 23.33
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
SUNDRIES : 22.50
TOTAL : 2636.04
ADD FOR WATER CHARGES @ 1.5% : 39.54
TOTAL : 2675.58
ADD FOR CONTRACTORS PROFIT @ 10% 267.56
ADD FOR OVER HEAD CHARGES @5% : 133.78
COST FOR 1.000 cum 3076.91
COST PER cum 3076.90
LABOUR PER cum 647.35
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 440.76
Labour for lime surkhi mortar 1:1:1 82.60
TOTAL : 523.36
WATER CHARGES @ 1.5% : 39.54
TOTAL : 562.90
ADD FOR CONTRACTORS PROFIT @10% : 56.29
ADD FOR OVER HEAD CHARGES @5% : 28.14
LABOUR FOR 1.000 cum 647.33
LABOUR PER cum 647.35
MATERIAL :
CARRIAGE :
Bricks.
1 KM BY MECH. TRANSPORT 1000 Nos. 475.0000 277.35 131.74
LABOUR :
Mason 1st class Each 0.5000 211.16 105.58
Mason 2nd Class Each 0.5000 158.67 79.34
Beldar Each 1.8000 116.67 210.01
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
Bhishti Each 0.2000 116.67 23.33
SUNDRIES : 22.50
TOTAL : 2541.04
ADD FOR WATER CHARGES @ 1.5% : 38.12
TOTAL : 2579.15
ADD FOR CONTRACTORS PROFIT @ 10% 257.92
ADD FOR OVER HEAD CHARGES @5% : 128.96
COST FOR 1.000 cum 2966.02
COST PER cum 2966.00
LABOUR PER cum 645.70
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 440.76
Labour for lime surkhi mortar 1:1:1 82.60
TOTAL : 523.36
WATER CHARGES @ 1.5% : 38.12
TOTAL : 561.47
ADD FOR CONTRACTORS PROFIT @10% : 56.15
ADD FOR OVER HEAD CHARGES @5% : 28.07
LABOUR FOR 1.000 cum 645.69
LABOUR PER cum 645.70
MATERIAL :
CARRIAGE :
Bricks.
1 KM BY MECH. TRANSPORT 1000 Nos. 475.0000 277.35 131.74
LABOUR :
Mason 1st class Each 0.5000 211.16 105.58
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
Mason 2nd Class Each 0.5000 158.67 79.34
Beldar Each 1.8000 116.67 210.01
Bhishti Each 0.2000 116.67 23.33
SUNDRIES : 22.50
TOTAL : 2583.76
ADD FOR WATER CHARGES @ 1.5% : 38.76
TOTAL : 2622.51
ADD FOR CONTRACTORS PROFIT @ 10% 262.25
ADD FOR OVER HEAD CHARGES @5% : 131.13
COST FOR 1.000 cum 3015.89
COST PER cum 3015.90
LABOUR PER cum 646.45
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 440.76
Labour for lime surkhi mortar 1:1:1 82.60
TOTAL : 523.36
WATER CHARGES @ 1.5% : 38.76
TOTAL : 562.11
ADD FOR CONTRACTORS PROFIT @10% : 56.21
ADD FOR OVER HEAD CHARGES @5% : 28.11
LABOUR FOR 1.000 cum 646.43
LABOUR PER cum 646.45
MATERIAL :
CARRIAGE :
Bricks.
1 KM BY MECH. TRANSPORT 1000 Nos. 475.0000 277.35 131.74
SUNDRIES : 22.50
TOTAL : 2488.76
ADD FOR WATER CHARGES @ 1.5% : 37.33
TOTAL : 2526.09
ADD FOR CONTRACTORS PROFIT @ 10% 252.61
ADD FOR OVER HEAD CHARGES @5% : 126.30
COST FOR 1.000 cum 2905.00
COST PER cum 2905.00
LABOUR PER cum 644.80
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 440.76
Labour for lime surkhi mortar 1:1:1 82.60
TOTAL : 523.36
WATER CHARGES @ 1.5% : 37.33
TOTAL : 560.69
ADD FOR CONTRACTORS PROFIT @10% : 56.07
ADD FOR OVER HEAD CHARGES @5% : 28.03
LABOUR FOR 1.000 cum 644.79
LABOUR PER cum 644.80
MATERIAL :
CARRIAGE :
Bricks.
1 KM BY MECH. TRANSPORT 1000 Nos. 475.0000 277.35 131.74
LABOUR :
Mason 1st class Each 0.5000 211.16 105.58
Mason 2nd Class Each 0.5000 158.67 79.34
Beldar Each 1.8000 116.67 210.01
Bhishti Each 0.2000 116.67 23.33
SUNDRIES : 22.50
TOTAL : 2548.29
ADD FOR WATER CHARGES @ 1.5% : 38.22
TOTAL : 2586.51
ADD FOR CONTRACTORS PROFIT @ 10% 258.65
ADD FOR OVER HEAD CHARGES @5% : 129.33
COST FOR 1.000 cum 2974.49
COST PER cum 2974.50
LABOUR PER cum 645.80
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 440.76
Labour for lime surkhi mortar 1:1:1 82.60
TOTAL : 523.36
WATER CHARGES @ 1.5% : 38.22
TOTAL : 561.58
ADD FOR CONTRACTORS PROFIT @10% : 56.16
ADD FOR OVER HEAD CHARGES @5% : 28.08
LABOUR FOR 1.000 cum 645.82
LABOUR PER cum 645.80
MATERIAL :
CARRIAGE :
Bricks.
1 KM BY MECH. TRANSPORT 1000 Nos. 475.0000 277.35 131.74
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR :
Mason 1st class Each 0.5000 211.16 105.58
Mason 2nd Class Each 0.5000 158.67 79.34
Beldar Each 1.8000 116.67 210.01
Bhishti Each 0.2000 116.67 23.33
SUNDRIES : 22.50
TOTAL : 2453.29
ADD FOR WATER CHARGES @ 1.5% : 36.80
TOTAL : 2490.08
ADD FOR CONTRACTORS PROFIT @ 10% 249.01
ADD FOR OVER HEAD CHARGES @5% : 124.50
COST FOR 1.000 cum 2863.60
COST PER cum 2863.60
LABOUR PER cum 644.20
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 440.76
Labour for lime surkhi mortar 1:1:1 82.60
TOTAL : 523.36
WATER CHARGES @ 1.5% : 36.80
TOTAL : 560.15
ADD FOR CONTRACTORS PROFIT @10% : 56.02
ADD FOR OVER HEAD CHARGES @5% : 28.01
LABOUR FOR 1.000 cum 644.18
LABOUR PER cum 644.20
MATERIAL :
CARRIAGE :
Bricks.
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
1 KM BY MECH. TRANSPORT 1000 Nos. 475.0000 277.35 131.74
LABOUR :
Mason 1st class Each 0.5000 211.16 105.58
Mason 2nd Class Each 0.5000 158.67 79.34
Beldar Each 1.8000 116.67 210.01
Bhishti Each 0.2000 116.67 23.33
SUNDRIES : 22.50
TOTAL : 2808.60
ADD FOR WATER CHARGES @ 1.5% : 42.13
TOTAL : 2850.72
ADD FOR CONTRACTORS PROFIT @ 10% 285.07
ADD FOR OVER HEAD CHARGES @5% : 142.54
COST FOR 1.000 cum 3278.33
COST PER cum 3278.30
LABOUR PER cum 586.90
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 440.76
Labour for lime surkhi mortar 1:1:1 27.44
TOTAL : 468.20
WATER CHARGES @ 1.5% : 42.13
TOTAL : 510.32
ADD FOR CONTRACTORS PROFIT @10% : 51.03
ADD FOR OVER HEAD CHARGES @5% : 25.52
LABOUR FOR 1.000 cum 586.87
LABOUR PER cum 586.90
MATERIAL :
CARRIAGE :
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
Bricks.
1 KM BY MECH. TRANSPORT 1000 Nos. 475.0000 277.35 131.74
LABOUR :
Mason 1st class Each 0.5000 211.16 105.58
Mason 2nd Class Each 0.5000 158.67 79.34
Beldar Each 1.8000 116.67 210.01
Bhishti Each 0.2000 116.67 23.33
SUNDRIES : 22.50
TOTAL : 2713.60
ADD FOR WATER CHARGES @ 1.5% : 40.70
TOTAL : 2754.30
ADD FOR CONTRACTORS PROFIT @ 10% 275.43
ADD FOR OVER HEAD CHARGES @5% : 137.71
COST FOR 1.000 cum 3167.44
COST PER cum 3167.45
LABOUR PER cum 585.25
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 440.76
Labour for lime surkhi mortar 1:1:1 27.44
TOTAL : 468.20
WATER CHARGES @ 1.5% : 40.70
TOTAL : 508.90
ADD FOR CONTRACTORS PROFIT @10% : 50.89
ADD FOR OVER HEAD CHARGES @5% : 25.44
LABOUR FOR 1.000 cum 585.23
LABOUR PER cum 585.25
MATERIAL :
Bricks.
1 KM BY MECH. TRANSPORT 1000 Nos. 475.0000 277.35 131.74
LABOUR :
Mason 1st class Each 0.5000 211.16 105.58
Mason 2nd Class Each 0.5000 158.67 79.34
Beldar Each 1.8000 116.67 210.01
Bhishti Each 0.2000 116.67 23.33
SUNDRIES : 22.50
TOTAL : 2652.45
ADD FOR WATER CHARGES @ 1.5% : 39.79
TOTAL : 2692.23
ADD FOR CONTRACTORS PROFIT @ 10% 269.22
ADD FOR OVER HEAD CHARGES @5% : 134.61
COST FOR 1.000 cum 3096.07
COST PER cum 3096.05
LABOUR PER cum 584.20
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 440.76
Labour for lime surkhi mortar 1:1:1 27.44
TOTAL : 468.20
WATER CHARGES @ 1.5% : 39.79
TOTAL : 507.98
ADD FOR CONTRACTORS PROFIT @10% : 50.80
ADD FOR OVER HEAD CHARGES @5% : 25.40
LABOUR FOR 1.000 cum 584.18
LABOUR PER cum 584.20
MATERIAL :
CARRIAGE :
Bricks.
1 KM BY MECH. TRANSPORT 1000 Nos. 475.0000 277.35 131.74
LABOUR :
Mason 1st class Each 0.5000 211.16 105.58
Mason 2nd Class Each 0.5000 158.67 79.34
Beldar Each 1.8000 116.67 210.01
Bhishti Each 0.2000 116.67 23.33
SUNDRIES : 22.50
TOTAL : 2557.45
ADD FOR WATER CHARGES @ 1.5% : 38.36
TOTAL : 2595.81
ADD FOR CONTRACTORS PROFIT @ 10% 259.58
ADD FOR OVER HEAD CHARGES @5% : 129.79
COST FOR 1.000 cum 2985.18
COST PER cum 2985.15
LABOUR PER cum 582.55
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 440.76
Labour for lime surkhi mortar 1:1:1 27.44
TOTAL : 468.20
WATER CHARGES @ 1.5% : 38.36
TOTAL : 506.56
ADD FOR CONTRACTORS PROFIT @10% : 50.66
ADD FOR OVER HEAD CHARGES @5% : 25.33
LABOUR FOR 1.000 cum 582.54
LABOUR PER cum 582.55
MATERIAL :
CARRIAGE :
Bricks.
1 KM BY MECH. TRANSPORT 1000 Nos. 475.0000 277.35 131.74
LABOUR :
Mason 1st class Each 0.5000 211.16 105.58
Mason 2nd Class Each 0.5000 158.67 79.34
Beldar Each 1.8000 116.67 210.01
Bhishti Each 0.2000 116.67 23.33
SUNDRIES : 22.50
TOTAL : 2568.36
ADD FOR WATER CHARGES @ 1.5% : 38.53
TOTAL : 2606.88
ADD FOR CONTRACTORS PROFIT @ 10% 260.69
ADD FOR OVER HEAD CHARGES @5% : 130.34
COST FOR 1.000 cum 2997.91
COST PER cum 2997.90
LABOUR PER cum 582.75
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 440.76
Labour for lime surkhi mortar 1:1:1 27.44
TOTAL : 468.20
WATER CHARGES @ 1.5% : 38.53
TOTAL : 506.72
ADD FOR CONTRACTORS PROFIT @10% : 50.67
ADD FOR OVER HEAD CHARGES @5% : 25.34
LABOUR FOR 1.000 cum 582.73
LABOUR PER cum 582.75
MATERIAL :
CARRIAGE :
Bricks.
1 KM BY MECH. TRANSPORT 1000 Nos. 475.0000 277.35 131.74
LABOUR :
Mason 1st class Each 0.5000 211.16 105.58
Mason 2nd Class Each 0.5000 158.67 79.34
Beldar Each 1.8000 116.67 210.01
Bhishti Each 0.2000 116.67 23.33
SUNDRIES : 22.50
TOTAL : 2473.36
ADD FOR WATER CHARGES @ 1.5% : 37.10
TOTAL : 2510.46
ADD FOR CONTRACTORS PROFIT @ 10% 251.05
ADD FOR OVER HEAD CHARGES @5% : 125.52
COST FOR 1.000 cum 2887.02
COST PER cum 2887.00
LABOUR PER cum 581.10
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 440.76
Labour for lime surkhi mortar 1:1:1 27.44
TOTAL : 468.20
WATER CHARGES @ 1.5% : 37.10
TOTAL : 505.30
ADD FOR CONTRACTORS PROFIT @10% : 50.53
ADD FOR OVER HEAD CHARGES @5% : 25.26
LABOUR FOR 1.000 cum 581.09
LABOUR PER cum 581.10
MATERIAL :
CARRIAGE :
Bricks.
1 KM BY MECH. TRANSPORT 1000 Nos. 475.0000 277.35 131.74
LABOUR :
Mason 1st class Each 0.5000 211.16 105.58
Mason 2nd Class Each 0.5000 158.67 79.34
Beldar Each 1.8000 116.67 210.01
Bhishti Each 0.2000 116.67 23.33
SUNDRIES : 22.50
TOTAL : 2496.29
ADD FOR WATER CHARGES @ 1.5% : 37.44
TOTAL : 2533.73
ADD FOR CONTRACTORS PROFIT @ 10% 253.37
ADD FOR OVER HEAD CHARGES @5% : 126.69
COST FOR 1.000 cum 2913.79
COST PER cum 2913.80
LABOUR PER cum 581.45
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 440.76
Labour for lime surkhi mortar 1:1:1 27.44
TOTAL : 468.20
WATER CHARGES @ 1.5% : 37.44
TOTAL : 505.64
ADD FOR CONTRACTORS PROFIT @10% : 50.56
ADD FOR OVER HEAD CHARGES @5% : 25.28
LABOUR FOR 1.000 cum 581.49
LABOUR PER cum 581.45
MATERIAL :
CARRIAGE :
Bricks.
1 KM BY MECH. TRANSPORT 1000 Nos. 475.0000 277.35 131.74
LABOUR :
Mason 1st class Each 0.5000 211.16 105.58
Mason 2nd Class Each 0.5000 158.67 79.34
Beldar Each 1.8000 116.67 210.01
Bhishti Each 0.2000 116.67 23.33
SUNDRIES : 22.50
TOTAL : 2401.29
ADD FOR WATER CHARGES @ 1.5% : 36.02
TOTAL : 2437.30
ADD FOR CONTRACTORS PROFIT @ 10% 243.73
ADD FOR OVER HEAD CHARGES @5% : 121.87
COST FOR 1.000 cum 2802.90
COST PER cum 2802.90
LABOUR PER cum 579.85
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 440.76
Labour for lime surkhi mortar 1:1:1 27.44
TOTAL : 468.20
WATER CHARGES @ 1.5% : 36.02
TOTAL : 504.21
ADD FOR CONTRACTORS PROFIT @10% : 50.42
ADD FOR OVER HEAD CHARGES @5% : 25.21
LABOUR FOR 1.000 cum 579.85
LABOUR PER cum 579.85
MATERIAL :
CARRIAGE :
Bricks.
1 KM BY MECH. TRANSPORT 1000 Nos. 475.0000 277.35 131.74
LABOUR :
Mason 1st class Each 0.5000 211.16 105.58
Mason 2nd Class Each 0.5000 158.67 79.34
Beldar Each 1.8000 116.67 210.01
Bhishti Each 0.2000 116.67 23.33
SUNDRIES : 22.50
TOTAL : 2130.61
ADD FOR WATER CHARGES @ 1.5% : 31.96
TOTAL : 2162.56
ADD FOR CONTRACTORS PROFIT @ 10% 216.26
ADD FOR OVER HEAD CHARGES @5% : 108.13
COST FOR 1.000 cum 2486.95
COST PER cum 2486.95
LABOUR PER cum 577.40
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 440.76
Labour for lime surkhi mortar 1:1:1 29.39
TOTAL : 470.15
WATER CHARGES @ 1.5% : 31.96
TOTAL : 502.10
ADD FOR CONTRACTORS PROFIT @10% : 50.21
ADD FOR OVER HEAD CHARGES @5% : 25.11
LABOUR FOR 1.000 cum 577.42
LABOUR PER cum 577.40
MATERIAL :
CARRIAGE :
Bricks.
1 KM BY MECH. TRANSPORT 1000 Nos. 475.0000 277.35 131.74
LABOUR :
Mason 1st class Each 0.5000 211.16 105.58
Mason 2nd Class Each 0.5000 158.67 79.34
Beldar Each 1.8000 116.67 210.01
Bhishti Each 0.2000 116.67 23.33
SUNDRIES : 22.50
TOTAL : 2035.61
ADD FOR WATER CHARGES @ 1.5% : 30.53
TOTAL : 2066.14
ADD FOR CONTRACTORS PROFIT @ 10% 206.61
ADD FOR OVER HEAD CHARGES @5% : 103.31
COST FOR 1.000 cum 2376.06
COST PER cum 2376.05
LABOUR PER cum 575.80
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 440.76
Labour for lime surkhi mortar 1:1:1 29.39
TOTAL : 470.15
WATER CHARGES @ 1.5% : 30.53
TOTAL : 500.68
ADD FOR CONTRACTORS PROFIT @10% : 50.07
ADD FOR OVER HEAD CHARGES @5% : 25.03
LABOUR FOR 1.000 cum 575.78
LABOUR PER cum 575.80
LABOUR :
Mason 1st class Each 0.0800 211.16 16.89
Mason 2nd Class Each 0.0800 158.67 12.69
Beldar Each 0.3300 116.67 38.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 79.09
TOTAL : 79.09
WATER CHARGES @ 1.5% : 1.19
TOTAL : 80.27
ADD FOR CONTRACTORS PROFIT @10% : 8.03
ADD FOR OVER HEAD CHARGES @5% : 4.01
LABOUR FOR 1.000 cum 92.31
LABOUR PER cum 92.30
LABOUR :
Mason 1st class Each 0.0800 211.16 16.89
Mason 2nd Class Each 0.0800 158.67 12.69
Beldar Each 0.3300 116.67 38.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 79.09
TOTAL : 79.09
WATER CHARGES @ 1.5% : 1.19
TOTAL : 80.27
ADD FOR CONTRACTORS PROFIT @10% : 8.03
ADD FOR OVER HEAD CHARGES @5% : 4.01
LABOUR FOR 1.000 cum 92.31
LABOUR PER cum 92.30
LABOUR :
Mason 1st class Each 0.2700 211.16 57.01
Mason 2nd Class Each 0.2700 158.67 42.84
Beldar Each 0.2700 116.67 31.50
TOTAL : 131.36
ADD FOR WATER CHARGES @ 1.5% : 1.97
TOTAL : 133.33
ADD FOR CONTRACTORS PROFIT @ 10% 13.33
ADD FOR OVER HEAD CHARGES @5% : 6.67
COST FOR 1.000 cum 153.32
COST PER cum 153.30
LABOUR PER cum 153.30
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 131.36
TOTAL : 131.36
WATER CHARGES @ 1.5% : 1.97
TOTAL : 133.33
ADD FOR CONTRACTORS PROFIT @10% : 13.33
ADD FOR OVER HEAD CHARGES @5% : 6.67
LABOUR FOR 1.000 cum 153.32
LABOUR PER cum 153.30
LABOUR :
Mason 1st class Each 0.2700 211.16 57.01
Mason 2nd Class Each 0.2700 158.67 42.84
Beldar Each 0.2700 116.67 31.50
TOTAL : 131.36
ADD FOR WATER CHARGES @ 1.5% : 1.97
TOTAL : 133.33
ADD FOR CONTRACTORS PROFIT @ 10% 13.33
ADD FOR OVER HEAD CHARGES @5% : 6.67
COST FOR 1.000 cum 153.32
COST PER cum 153.30
LABOUR PER cum 153.30
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 131.36
TOTAL : 131.36
WATER CHARGES @ 1.5% : 1.97
TOTAL : 133.33
ADD FOR CONTRACTORS PROFIT @10% : 13.33
ADD FOR OVER HEAD CHARGES @5% : 6.67
LABOUR FOR 1.000 cum 153.32
LABOUR PER cum 153.30
MATERIAL :
CARRIAGE :
Bricks.
1 KM BY MECH. TRANSPORT 1000 Nos. 141.0000 277.35 39.11
LABOUR :
Mason 1st class Each 0.7100 211.16 149.92
Mason 2nd Class Each 0.7100 158.67 112.66
Beldar Each 0.3500 116.67 40.83
TOTAL : 779.82
ADD FOR WATER CHARGES @ 1.5% : 11.70
TOTAL : 791.52
ADD FOR CONTRACTORS PROFIT @ 10% 79.15
ADD FOR OVER HEAD CHARGES @5% : 39.58
COST FOR 1.000 cum 910.25
COST PER cum 910.25
LABOUR PER cum 362.40
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 303.41
TOTAL : 303.41
WATER CHARGES @ 1.5% : 11.70
TOTAL : 315.11
ADD FOR CONTRACTORS PROFIT @10% : 31.51
ADD FOR OVER HEAD CHARGES @5% : 15.76
LABOUR FOR 1.000 cum 362.38
LABOUR PER cum 362.40
MATERIAL :
CARRIAGE :
Bricks.
1 KM BY MECH. TRANSPORT 1000 Nos. 141.0000 277.35 39.11
LABOUR :
Mason 1st class Each 0.7100 211.16 149.92
Mason 2nd Class Each 0.7100 158.67 112.66
Beldar Each 0.3500 116.67 40.83
TOTAL : 751.62
ADD FOR WATER CHARGES @ 1.5% : 11.27
TOTAL : 762.90
ADD FOR CONTRACTORS PROFIT @ 10% 76.29
ADD FOR OVER HEAD CHARGES @5% : 38.14
COST FOR 1.000 cum 877.33
COST PER cum 877.30
LABOUR PER cum 361.90
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 303.41
TOTAL : 303.41
WATER CHARGES @ 1.5% : 11.27
TOTAL : 314.69
ADD FOR CONTRACTORS PROFIT @10% : 31.47
ADD FOR OVER HEAD CHARGES @5% : 15.73
LABOUR FOR 1.000 cum 361.89
LABOUR PER cum 361.90
MATERIAL :
CARRIAGE :
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
Bricks.
1 KM BY MECH. TRANSPORT 1000 Nos. 36.0000 277.35 9.98
LABOUR :
Mason 1st class Each 0.1300 211.16 27.45
Mason 2nd Class Each 0.1300 158.67 20.63
Beldar Each 0.5300 116.67 61.84
TOTAL : 231.54
ADD FOR WATER CHARGES @ 1.5% : 3.47
TOTAL : 235.02
ADD FOR CONTRACTORS PROFIT @ 10% 23.50
ADD FOR OVER HEAD CHARGES @5% : 11.75
COST FOR 1.000 cum 270.27
COST PER cum 270.25
LABOUR PER cum 130.40
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 109.91
TOTAL : 109.91
WATER CHARGES @ 1.5% : 3.47
TOTAL : 113.39
ADD FOR CONTRACTORS PROFIT @10% : 11.34
ADD FOR OVER HEAD CHARGES @5% : 5.67
LABOUR FOR 1.000 cum 130.39
LABOUR PER cum 130.40
MATERIAL :
CARRIAGE :
Bricks.
1 KM BY MECH. TRANSPORT 1000 Nos. 36.0000 277.35 9.98
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR :
Mason 1st class Each 0.1300 211.16 27.45
Mason 2nd Class Each 0.1300 158.67 20.63
Beldar Each 0.5300 116.67 61.84
TOTAL : 224.34
ADD FOR WATER CHARGES @ 1.5% : 3.37
TOTAL : 227.71
ADD FOR CONTRACTORS PROFIT @ 10% 22.77
ADD FOR OVER HEAD CHARGES @5% : 11.39
COST FOR 1.000 cum 261.86
COST PER cum 261.90
LABOUR PER cum 130.30
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 109.91
TOTAL : 109.91
WATER CHARGES @ 1.5% : 3.37
TOTAL : 113.28
ADD FOR CONTRACTORS PROFIT @10% : 11.33
ADD FOR OVER HEAD CHARGES @5% : 5.66
LABOUR FOR 1.000 cum 130.27
LABOUR PER cum 130.30
MATERIAL :
CARRIAGE :
Bricks.
1 KM BY MECH. TRANSPORT 1000 Nos. 178.0000 277.35 49.37
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR :
Mason 1st class Each 1.2500 211.16 263.95
Mason 2nd Class Each 1.2500 158.67 198.34
Beldar Each 2.0000 116.67 233.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 736.13
TOTAL : 736.13
WATER CHARGES @ 1.5% : 20.06
TOTAL : 756.19
ADD FOR CONTRACTORS PROFIT @10% : 75.62
ADD FOR OVER HEAD CHARGES @5% : 37.81
LABOUR FOR 9.300 sqm 869.62
LABOUR PER sqm. 93.50
MATERIAL :
Bricks.
1 KM BY MECH. TRANSPORT 1000 Nos. 178.0000 277.35 49.37
LABOUR :
Mason 1st class Each 1.2500 211.16 263.95
Mason 2nd Class Each 1.2500 158.67 198.34
Beldar Each 2.0000 116.67 233.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 736.13
TOTAL : 736.13
WATER CHARGES @ 1.5% : 19.53
TOTAL : 755.66
ADD FOR CONTRACTORS PROFIT @10% : 75.57
ADD FOR OVER HEAD CHARGES @5% : 37.78
LABOUR FOR 9.300 sqm 869.01
LABOUR Per sqm 93.45
MATERIAL :
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
Common burnt clay building bricks
of class designation 350/300
250/200/175/150/125/100/75/50 sub
class A/B 1000 Nos 494.0000 3000.00 1482.00
CARRIAGE :
Bricks.
1 KM BY MECH. TRANSPORT 1000 Nos. 494.0000 277.35 137.01
LABOUR :
Mason 1st class Each 0.6200 211.16 130.92
Mason 2nd Class Each 0.6200 158.67 98.38
Beldar Each 2.2900 116.67 267.17
Bhishi Each 0.2000 116.67 23.33
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 562.30
Labour for cement mortar 1:4 28.58
Labour for centreing and shuttering 2.25x265.50 597.37 (-a-)
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 1188.25
WATER CHARGES @ 1.5% : 97.71
TOTAL : 1285.96
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-) : 68.86
ADD FOR OVER HEAD CHARGES @5% Except on (-a-) : 34.43
LABOUR FOR 1 cum 1389.25
LABOUR Per cum 1389.25
MATERIAL :
CARRIAGE :
Bricks.
1 KM BY MECH. TRANSPORT 1000 Nos. 494.0000 277.35 137.01
LABOUR :
Mason 1st class Each 0.6200 211.16 130.92
Mason 2nd Class Each 0.6200 158.67 98.38
Beldar Each 2.2900 116.67 267.17
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
Bhishi Each 0.2000 116.67 23.33
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 562.30
Labour for cement mortar 1:4 28.58
Labour for centreing and shuttering 2.25x265.50 597.37 (-a-)
TOTAL : 1188.25
WATER CHARGES @ 1.5% : 96.22
TOTAL : 1284.47
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-) : 68.71
ADD FOR OVER HEAD CHARGES @5% Except on (-a-) : 34.36
LABOUR FOR 1 cum 1387.54
LABOUR Per cum 1387.55
MATERIAL :
CARRIAGE :
Bricks.
1 KM BY MECH. TRANSPORT 1000 Nos. 538.0000 277.35 149.21
LABOUR :
Mason 1st class Each 1.3300 211.16 280.84
Mason 2nd Class Each 1.3300 158.67 211.03
Beldar Each 4.4200 116.67 515.68
Bhisti Each 0.2000 116.67 23.33
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1101.39
Labour for cement mortar 1:4 28.58
Labour for centreing and shuttering 2.25x265.50 597.37 (-a-)
TOTAL : 1727.34
WATER CHARGES @ 1.5% : 108.02
TOTAL : 1835.36
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-) : 123.80
ADD FOR OVER HEAD CHARGES @5% Except on (-a-) : 61.90
LABOUR FOR 1 cum 2021.06
LABOUR Per cum 2021.05
MATERIAL :
CARRIAGE :
Bricks.
1 KM BY MECH. TRANSPORT 1000 Nos. 538.0000 277.35 149.21
LABOUR :
Mason 1st class Each 1.3300 211.16 280.84
Mason 2nd Class Each 1.3300 158.67 211.03
Beldar Each 4.4200 116.67 515.68
Bhisti Each 0.2000 116.67 23.33
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1101.39
Labour for cement mortar 1:4 28.58
Labour for centreing and shuttering 2.25x265.50 597.37 (-a-)
TOTAL : 1727.34
WATER CHARGES @ 1.5% : 106.41
TOTAL : 1833.75
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-) : 123.64
ADD FOR OVER HEAD CHARGES @5% Except on (-a-) : 61.82
LABOUR FOR 1 cum 2019.21
LABOUR Per cum 2019.20
MATERIAL :
CARRIAGE :
Bricks.
1 KM BY MECH. TRANSPORT 1000 Nos. 565.0000 277.35 156.70
LABOUR :
Mason 1st class Each 1.2000 211.16 253.39
Beldar Each 2.0000 116.67 233.34
Beldar Each 0.4000 116.67 46.67
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 562.40
Labour for cement lime mortar 1:1:6 96.37
TOTAL : 658.77
WATER CHARGES @ 1.5% : 48.38
TOTAL : 707.15
ADD FOR CONTRACTORS PROFIT @10% : 70.72
ADD FOR OVER HEAD CHARGES @5% : 35.36
LABOUR FOR 10.00 sqm 813.22
LABOUR Per sqm 81.30
MATERIAL :
CARRIAGE :
Bricks.
1 KM BY MECH. TRANSPORT 1000 Nos. 565.0000 277.35 156.70
LABOUR :
Mason 1st class Each 1.2000 211.16 253.39
Beldar Each 2.0000 116.67 233.34
Beldar Each 0.4000 116.67 46.67
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 562.40
Labour for cement lime mortar 1:1:6 96.37
TOTAL : 658.77
WATER CHARGES @ 1.5% : 46.69
TOTAL : 705.46
ADD FOR CONTRACTORS PROFIT @10% : 70.55
ADD FOR OVER HEAD CHARGES @5% : 35.27
LABOUR FOR 10.00 sqm 811.27
LABOUR Per sqm 81.15
MATERIAL :
CARRIAGE :
Bricks.
1 KM BY MECH. TRANSPORT 1000 Nos. 565.0000 277.35 156.70
LABOUR :
Mason 1st class Each 1.2000 211.16 253.39
Beldar Each 2.0000 116.67 233.34
Bhisti Each 0.4000 116.67 46.67
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 562.40
Labour for cement lime mortar 1:1:6 32.01
TOTAL : 594.41
WATER CHARGES @ 1.5% : 50.42
TOTAL : 644.83
ADD FOR CONTRACTORS PROFIT @10% : 64.48
ADD FOR OVER HEAD CHARGES @5% : 32.24
LABOUR FOR 10.00 sqm 741.56
LABOUR Per sqm 74.15
MATERIAL :
CARRIAGE :
Bricks.
1 KM BY MECH. TRANSPORT 1000 Nos. 565.0000 277.35 156.70
LABOUR :
Mason 1st class Each 1.2000 211.16 253.39
Beldar Each 2.0000 116.67 233.34
Bhisti Each 0.4000 116.67 46.67
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 562.40
Labour for cement lime mortar 1:1:6 32.01
TOTAL : 594.41
WATER CHARGES @ 1.5% : 48.73
TOTAL : 643.14
ADD FOR CONTRACTORS PROFIT @10% : 64.31
ADD FOR OVER HEAD CHARGES @5% : 32.16
LABOUR FOR 10.00 sqm 739.61
LABOUR Per sqm 73.95
MATERIAL :
CARRIAGE :
Bricks.
1 KM BY MECH. TRANSPORT 1000 Nos. 565.0000 277.35 156.70
LABOUR :
Mason 1st class Each 1.2000 211.16 253.39
Beldar Each 2.0000 116.67 233.34
Bhisti Each 0.4000 116.67 46.67
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 562.40
Labour for cement lime mortar 1:1:6 32.01
TOTAL : 594.41
WATER CHARGES @ 1.5% : 47.69
TOTAL : 642.10
ADD FOR CONTRACTORS PROFIT @10% : 64.21
ADD FOR OVER HEAD CHARGES @5% : 32.10
LABOUR FOR 10.00 sqm 738.41
LABOUR Per sqm 73.85
MATERIAL :
CARRIAGE :
Bricks.
1 KM BY MECH. TRANSPORT 1000 Nos. 565.0000 277.35 156.70
LABOUR :
Mason 1st class Each 1.2000 211.16 253.39
Beldar Each 2.0000 116.67 233.34
Bhisti Each 0.4000 116.67 46.67
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
SUNDRIES : L.S. 29.00
TOTAL : 3066.30
ADD FOR WATER CHARGES @ 1.5% : 45.99
TOTAL : 3112.29
ADD FOR CONTRACTORS PROFIT @ 10% 311.23
ADD FOR OVER HEAD CHARGES @5% : 155.61
COST FOR 10.00 sqm 3579.14
COST PER Sqm. 357.90
LABOUR PER sqm. 73.65
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 562.40
Labour for cement lime mortar 1:1:6 32.01
TOTAL : 594.41
WATER CHARGES @ 1.5% : 45.99
TOTAL : 640.40
ADD FOR CONTRACTORS PROFIT @10% : 64.04
ADD FOR OVER HEAD CHARGES @5% : 32.02
LABOUR FOR 10.00 sqm 736.47
LABOUR Per sqm 73.65
MATERIAL :
Hoop iron
25 mmx1.6mm=30m @0.32 kg/m=096
quintal 1 qtl 0.0960 4500.00 432.00
CARRIAGE :
Bricks.
1 KM BY MECH. TRANSPORT 1000 Nos. 565.0000 277.35 156.70
Hoop Iron
1 KM BY MECH. TRANSPORT 1 Tonne 0.0960 73.95 7.10
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR :
Mason 1st class Each 1.2000 211.16 253.39
Beldar Each 2.0000 116.67 233.34
Bhisti Each 0.4000 116.67 46.67
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 562.40
Labour for cement lime mortar 1:1:6 32.01
TOTAL : 594.41
WATER CHARGES @ 1.5% : 57.09
TOTAL : 651.50
ADD FOR CONTRACTORS PROFIT @10% : 65.15
ADD FOR OVER HEAD CHARGES @5% : 32.58
LABOUR FOR 10.00 sqm 749.23
LABOUR Per sqm 74.90
MATERIAL :
Hoop iron
25mmx1.6mm=30m @0.32kg/m=096
quintal. 1 qtl 0.0960 4500.00 432.00
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
CARRIAGE :
Bricks.
1 KM BY MECH. TRANSPORT 1000 Nos. 565.0000 277.35 156.70
Hoop Iron
1 KM BY MECH. TRANSPORT 1 Tonne 0.0960 73.95 7.10
LABOUR :
Mason 1st class Each 1.2000 211.16 253.39
Beldar Each 2.0000 116.67 233.34
Bhisti Each 0.4000 116.67 46.67
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 562.40
Labour for cement lime mortar 1:1:6 32.01
TOTAL : 594.41
WATER CHARGES @ 1.5% : 55.40
TOTAL : 649.81
ADD FOR CONTRACTORS PROFIT @10% : 64.98
ADD FOR OVER HEAD CHARGES @5% : 32.49
LABOUR FOR 10.00 sqm 747.28
LABOUR Per sqm 74.75
LABOUR :
Mason 1st class Each 0.2200 211.16 46.46
Mason 2nd Class Each 0.2200 158.67 34.91
Beldar Each 0.5000 116.67 58.34
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 150.70
ADD FOR WATER CHARGES @ 1.5% : 2.26
TOTAL : 152.96
ADD FOR CONTRACTORS PROFIT @ 10% 15.30
ADD FOR OVER HEAD CHARGES @5% : 7.65
COST FOR 10.00 sqm 175.90
COST PER Sqm. 17.59
LABOUR PER sqm. 17.60
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 150.70
TOTAL : 150.70
WATER CHARGES @ 1.5% : 2.26
TOTAL : 152.96
ADD FOR CONTRACTORS PROFIT @10% : 15.30
ADD FOR OVER HEAD CHARGES @5% : 7.65
LABOUR FOR 10.00 sqm 175.90
LABOUR Per sqm 17.60
LABOUR :
Mason 1st class Each 0.2500 211.16 52.79
Mason 2nd Class Each 0.2500 158.67 39.67
Beldar Each 0.0800 116.67 9.33
TOTAL : 108.29
ADD FOR WATER CHARGES @ 1.5% : 1.62
TOTAL : 109.92
ADD FOR CONTRACTORS PROFIT @ 10% 10.99
ADD FOR OVER HEAD CHARGES @5% : 5.50
COST FOR 10.00 sqm 126.40
COST PER Sqm. 12.64
LABOUR PER sqm. 12.65
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 108.29
TOTAL : 108.29
WATER CHARGES @ 1.5% : 1.62
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 109.92
ADD FOR CONTRACTORS PROFIT @10% : 10.99
ADD FOR OVER HEAD CHARGES @5% : 5.50
LABOUR FOR 10.00 sqm 126.40
LABOUR Per sqm 12.65
MATERIAL :
Brick masonry in CM 1:4
Rate as per item no.10010701. 1 cum 0.0690 3096.05 213.63 (-I-)
Extra for super-structure
Rate as per item no.10020100. 1 cum 0.0690 92.30 6.37 (-I-)
Extra for delay (labour) L.S 18.00
TOTAL : 238.00
ADD FOR WATER CHARGES @ 1.5% : 0.27
TOTAL : 238.27
ADD FOR CONTRACTORS PROFIT @ 10% Except on (-I-) : 1.83
ADD FOR OVER HEAD CHARGES @5% Except on (-I-) : 0.92
COST FOR 1.00 sqm 241.02
COST PER sqm 241.00
LABOUR PER sqm 67.65
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 18.00
Labour for 10010701 40.30 (-a-)
Labour for 10020101 6.35 (-a-)
TOTAL : 64.65
WATER CHARGES @ 1.5% : 0.27
TOTAL : 64.92
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-) : 1.83
ADD FOR OVER HEAD CHARGES @5% Except on (-a-) : 0.92
LABOUR FOR 1 sqm 67.67
LABOUR Per sqm 67.65
MATERIAL :
Brick masonry in CM 1:4
Rate as per item no.10010701. 1 cum 0.0690 3096.05 213.63 (-I-)
Extra for super-structure
Rate as per item no. 10020100. 1 cum 0.0690 92.30 6.37 (-I-)
Extra for delay labour L.S 18.00
TOTAL : 238.00
ADD FOR WATER CHARGES @ 1.5% : 0.27
TOTAL : 238.27
ADD FOR CONTRACTORS PROFIT @ 10% Except on (-I-) : 1.83
ADD FOR OVER HEAD CHARGES @5% Except on (-I-) : 0.92
COST FOR 1.00 sqm 241.02
COST PER sqm 241.00
LABOUR PER sqm 67.65
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 18.00
Labour for 10010701 40.30 (-a-)
Labour for 10020101 6.35 (-a-)
TOTAL : 64.65
WATER CHARGES @ 1.5% : 0.27
TOTAL : 64.92
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-) : 1.83
ADD FOR OVER HEAD CHARGES @5% Except on (-a-) : 0.92
LABOUR FOR 1 sqm 67.67
LABOUR Per sqm 67.65
MATERIAL :
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
CARRIAGE :
LABOUR :
For keeping the cavity clear and fixing
wall tiles & delay caused
Mason 1st class Each 0.3700 211.16 78.13
Mason 2nd Class Each 0.3700 158.67 57.71
Beldar Each 0.9200 116.67 107.34
TOTAL : 502.84
ADD FOR WATER CHARGES @ 1.5% : 7.54
TOTAL : 510.38
ADD FOR CONTRACTORS PROFIT @ 10% 51.04
ADD FOR OVER HEAD CHARGES @5% : 25.52
COST FOR 10.00 sqm 586.94
COST PER Sqm. 58.70
LABOUR PER sqm. 28.95
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 244.18
TOTAL : 244.18
WATER CHARGES @ 1.5% : 7.54
TOTAL : 251.72
ADD FOR CONTRACTORS PROFIT @10% : 25.17
ADD FOR OVER HEAD CHARGES @5% : 12.59
LABOUR FOR 10.00 sqm 289.48
LABOUR Per sqm 28.95
MATERIAL :
Mild steel
25mmx3mmx30cmx30Nos.=9mtr.
.@0.6 kg per metre=5.4 kg.
Painting the steel with bitumen 1 qtl 0.0540 4500.00 243.00
CARRIAGE :
LABOUR :
For keeping the cavity clear and fixing
wall tiles & delay caused
Mason 1st class Each 0.3700 211.16 78.13
Mason 2nd Class Each 0.3700 158.67 58.71
Beldar Each 0.9200 116.67 107.34
TOTAL : 502.84
ADD FOR WATER CHARGES @ 1.5% : 7.54
TOTAL : 510.38
ADD FOR CONTRACTORS PROFIT @ 10% 51.04
ADD FOR OVER HEAD CHARGES @5% : 25.52
COST FOR 10.00 sqm 586.94
COST PER Sqm. 58.70
LABOUR PER sqm. 28.95
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 244.18
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 244.18
WATER CHARGES @ 1.5% : 7.54
TOTAL : 251.72
ADD FOR CONTRACTORS PROFIT @10% : 25.17
ADD FOR OVER HEAD CHARGES @5% : 12.59
LABOUR FOR 10.00 sqm 289.48
LABOUR Per sqm 28.95
MATERIAL :
LABOUR :
Mason 1st class Each 0.1200 211.16 25.34
Mason 2nd Class Each 0.1200 158.67 19.04
Beldar Each 0.0600 116.67 7.00
TOTAL : 1194.73
ADD FOR WATER CHARGES @ 1.5% : 2.03
TOTAL : 1196.76
ADD FOR CONTRACTORS PROFIT @ 10% Except on (-I-) : 13.74
ADD FOR OVER HEAD CHARGES @5% Except on (-I-) : 6.87
COST FOR 10.00 metre 1217.37
COST PER metre 121.75
LABOUR PER metre 26.15
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 51.38
Labour for 10040201 200.20 (-a-)
TOTAL : 251.58
WATER CHARGES @ 1.5% : 2.03
TOTAL : 253.61
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-) : 5.34
ADD FOR OVER HEAD CHARGES @5% Except on (-a-) : 2.67
LABOUR FOR 10.00 metre 261.62
LABOUR Per metre 26.15
MATERIAL :
LABOUR :
Mason 1st class Each 0.1200 211.16 25.34
Mason 2nd Class Each 0.1200 158.67 19.04
Beldar Each 0.0600 116.67 7.00
TOTAL : 1159.22
ADD FOR WATER CHARGES @ 1.5% : 2.03
TOTAL : 1161.25
ADD FOR CONTRACTORS PROFIT @ 10% Except on (-I-) : 13.74
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR OVER HEAD CHARGES @5% Except on (-I-) : 6.87
COST FOR 10.00 metre 1181.86
COST PER metre 118.20
LABOUR PER metre 26.10
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 51.38
Labour for 10040201 199.67 (-a-)
TOTAL : 251.05
WATER CHARGES @ 1.5% : 2.03
TOTAL : 253.08
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-) : 5.34
ADD FOR OVER HEAD CHARGES @5% Except on (-a-) : 2.67
LABOUR FOR 10.00 metre 261.09
LABOUR Per metre 26.10
MATERIAL :
TOTAL : 397.64
COST FOR 0.540 sq.m. 397.64
COST PER sq.m. 736.35
LABOUR PER sq.m. 200.00
LABOUR RATE :
Labour for 07020200 12.36
Labour for 09150200 37.60
Labour for 10010701 36.22
Labour for 17125010 21.82
LABOUR FOR 0.540 sq.m. 108.00
LABOUR PER sq.m. 200.00
MATERIAL :
TOTAL : 390.76
COST FOR 0.540 sq.m. 390.76
COST PER sq.m. 723.60
LABOUR PER sq.m. 199.80
LABOUR RATE :
Labour for 07020200 12.36
Labour for 09150200 37.60
Labour for 10010702 36.12
Labour for 17125010 21.82
LABOUR FOR 0.540 sq.m. 107.90
LABOUR PER sq.m. 199.80
MATERIAL :
Rate as per item no. 10010701. 1 cum 0.0450 3096.05 139.32 -I-
Rate as per item no. 10020100 1 cum 0.0450 92.30 4.15 -I-
LABOUR :
Mason 1st class Each 0.1800 211.16 38.01
Mason 2nd Class Each 0.1800 158.67 28.56
Beldar Each 0.1800 116.67 21.00
TOTAL : 231.04
ADD FOR WATER CHARGES @ 1.5% : 1.31
TOTAL : 232.35
ADD FOR CONTRACTORS PROFIT @ 10% Except on (-I-) : 8.89
ADD FOR OVER HEAD CHARGES @5% Except on (-I-) : 4.45
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
COST FOR 1.8000 sq,m 245.69
COST PER sq,m 136.50
LABOUR PER sq,m 73.70
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 87.56
Labour for 10010701 26.29 (-a-)
Labour for 10020101 4.15 (-a-)
TOTAL : 118.00
WATER CHARGES @ 1.5% : 1.31
TOTAL : 119.31
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-) : 8.89
ADD FOR OVER HEAD CHARGES @5% Except on (-a-) : 4.45
LABOUR FOR 1.800 sq,m 132.65
LABOUR Per sqm 73.70
MATERIAL :
Rate as per item no. 10010702 1 cum 0.0450 2985.15 134.33 -I-
LABOUR :
Mason 1st class Each 0.1800 211.16 38.01
Mason 2nd Class Each 0.1800 158.67 28.56
Beldar Each 0.1800 116.67 21.00
TOTAL : 226.05
ADD FOR WATER CHARGES @ 1.5% : 1.31
TOTAL : 227.36
ADD FOR CONTRACTORS PROFIT @ 10% Except on (-I-) : 8.89
ADD FOR OVER HEAD CHARGES @5% Except on (-I-) : 4.45
COST FOR 1.8000 sq,m 240.70
COST PER sq,m 133.70
LABOUR PER sq,m 73.65
LABOUR RATE :
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
ACTUAL LABOUR+SUNDRIES 87.56
Labour for 10010702 26.21 (-a-)
Labour for 10020101 4.15 (-a-)
TOTAL : 117.92
WATER CHARGES @ 1.5% : 1.31
TOTAL : 119.23
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-) : 8.89
ADD FOR OVER HEAD CHARGES @5% Except on (-a-) : 4.45
LABOUR FOR 1.800 sq,m 132.57
LABOUR Per sqm 73.65
MATERIAL :
Rate as per item no. 10010701 1 cum 0.0870 3096.05 269.36 -I-
TOTAL : 312.39
ADD FOR WATER CHARGES @ 1.5% : 0.53
TOTAL : 312.92
ADD FOR CONTRACTORS PROFIT @ 10% Except on (-I-) : 3.55
ADD FOR OVER HEAD CHARGES @5% Except on (-I-) : 1.78
COST FOR 10.00 metre 318.25
COST PER metre 31.85
LABOUR PER metre 10.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 35.00
Labour for 10010701 50.83 (-a-)
Labour for 10020101 8.03 (-a-)
TOTAL : 93.86
WATER CHARGES @ 1.5% : 0.53
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 94.39
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-) : 3.55
ADD FOR OVER HEAD CHARGES @5% Except on (-a-) : 1.78
LABOUR FOR 10.00 metre 99.72
LABOUR Per metre 10.00
MATERIAL :
Rate as per item no. 10010702 1 cum 0.0870 2985.15 259.71 -I-
Rate as per item no. 10020100 1 cum 0.0870 92.30 8.03 -I-
Extra for spc. molded brk L.S 35.00
TOTAL : 302.74
ADD FOR WATER CHARGES @ 1.5% : 0.53
TOTAL : 303.27
ADD FOR CONTRACTORS PROFIT @ 10% Except on (-I-) : 3.55
ADD FOR OVER HEAD CHARGES @5% Except on (-I-) : 1.78
COST FOR 10.00 metre 308.60
COST PER metre 30.85
LABOUR PER metre 9.95
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 35.00
Labour for 10010702 50.68 (-a-)
Labour for 10020101 8.03 (-a-)
TOTAL : 93.71
WATER CHARGES @ 1.5% : 0.53
TOTAL : 94.24
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-) : 3.55
ADD FOR OVER HEAD CHARGES @5% Except on (-a-) : 1.78
LABOUR FOR 10.00 metre 99.57
LABOUR Per metre 9.95
MATERIAL :
Rate as per item no. 10010901 1 cum 0.0870 2913.80 253.50 -I-
TOTAL : 296.53
ADD FOR WATER CHARGES @ 1.5% : 0.53
TOTAL : 297.06
ADD FOR CONTRACTORS PROFIT @ 10% Except on (-I-) : 3.55
ADD FOR OVER HEAD CHARGES @5% Except on (-I-) : 1.78
COST FOR 10.00 metre 302.39
COST PER metre 30.25
LABOUR PER metre 9.95
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 35.00
Labour for 10010901 50.59 (-a-)
Labour for 10020101 8.03 (-a-)
TOTAL : 93.62
WATER CHARGES @ 1.5% : 0.53
TOTAL : 94.15
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-) : 3.55
ADD FOR OVER HEAD CHARGES @5% Except on (-a-) : 1.78
LABOUR FOR 10.00 metre 99.48
LABOUR Per metre 9.95
Rate as per item no. 10010902 1 cum 0.0870 2802.90 243.85 -I-
Rate as per item no. 10020100 1 cum 0.0870 92.30 8.03 -I-
Extra for spc. molded brk L.S 35.00
TOTAL : 286.88
ADD FOR WATER CHARGES @ 1.5% : 0.53
TOTAL : 287.41
ADD FOR CONTRACTORS PROFIT @ 10% Except on (-I-) : 3.55
ADD FOR OVER HEAD CHARGES @5% Except on (-I-) : 1.78
COST FOR 10.00 metre 292.74
COST PER metre 29.25
LABOUR PER metre 9.95
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 35.00
Labour for 10010902 50.45 (-a-)
Labour for 10020101 8.03 (-a-)
TOTAL : 93.62
WATER CHARGES @ 1.5% : 0.53
TOTAL : 94.15
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-) : 3.55
ADD FOR OVER HEAD CHARGES @5% Except on (-a-) : 1.78
LABOUR FOR 10.00 metre 99.48
LABOUR Per metre 9.95
MATERIAL :
Rate as per item no. 10010701 1 cum 0.1700 3096.05 526.33 -I-
Rate as per item no. 17047010 1 sq.m 4.5700 105.00 479.85 -I-
LABOUR :
Mason 1st class Each 0.3300 211.16 69.68
Mason 2nd Class Each 0.3300 158.67 52.36
TOTAL : 1143.91
ADD FOR CONTRACTORS PROFIT @ 10% Except on (-I-) : 12.20
ADD FOR OVER HEAD CHARGES @5% Except on (-I-) : 6.10
COST FOR 10 metre 10 cm projection 20 cm depth 1162.21
COST FOR 1 metre 1 cm projection 1 cm depth 0.60
LABOUR FOR 1 metre 1 cm projection 1 cm depth 0.20
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 122.04
Labour for 10010701 99.31 (-a-)
Labour for 10020101 15.69 (-a-)
Labour for 17047010 202.91 (-a-)
TOTAL : 439.95
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-) : 12.20
ADD FOR OVER HEAD CHARGES @5% Except on (-a-) : 6.10
LABOUR FOR 10 metre 10 cm projection 20 cm depth 458.25
LABOUR FOR 1 metre 1 cm projection 1 cm depth 0.20
MATERIAL :
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
Rate as per item no. 10010702 cum 0.17 2985.15 507.47 (-I-)
Rate as per item no. 10020101 cum 0.17 92.30 15.69 (-I-)
Rate as per item no. 17047010 sq.m. 4.57 105.00 479.95 (-I-)
LABOUR :
Mason 1st class Each 0.33 211.16 69.68
Mason 2nd Class Each 0.33 158.67 52.36
TOTAL : 1125.05
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 122.04
Labour for 10010702 99.03 (-a-)
Labour for 10020101 15.69 (-a-)
Labour for 17047010 202.91 (-a-)
TOTAL : 439.67
MATERIAL :
Rate as per item no. 10010701 1 cum 0.05000 3096.05 154.80 -I-
Rate as per item no. 10020100 1 cum 0.05000 92.30 4.62 -I-
LABOUR :
Mason 1st class Each 0.02000 211.16 4.22
Mason 2nd Class Each 0.02000 158.67 3.17
TOTAL : 168.81
ADD FOR WATER CHARGES @ 1.5% : 0.14
TOTAL : 168.95
ADD FOR CONTRACTORS PROFIT @ 10% Except on (-I-) : 0.95
ADD FOR OVER HEAD CHARGES @5% Except on (-I-) : 0.48
COST FOR 10.00 metre 170.38
COST PER metre 17.05
LABOUR PER metre 4.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 9.39
Labour for 10010701 29.21 (-a-)
Labour for 10020101 4.62 (-a-)
TOTAL : 43.22
WATER CHARGES @ 1.5% : 0.14
TOTAL : 43.36
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-) : 0.95
ADD FOR OVER HEAD CHARGES @5% Except on (-a-) : 0.48
LABOUR FOR 10.00 metre 44.79
LABOUR Per metre 4.50
MATERIAL :
Rate as per item no. 10010702 1 cum 0.05000 2985.15 149.26 -I-
Rate as per item no. 10020100 1 cum 0.05000 92.30 4.62 -I-
LABOUR :
Mason 1st class Each 0.02000 211.16 4.22
Mason 2nd Class Each 0.02000 158.67 3.17
TOTAL : 163.27
ADD FOR WATER CHARGES @ 1.5% : 0.14
TOTAL : 163.41
ADD FOR CONTRACTORS PROFIT @ 10% Except on (-I-) : 0.95
ADD FOR OVER HEAD CHARGES @5% Except on (-I-) : 0.48
COST FOR 10.00 metre 164.84
COST PER metre 16.50
LABOUR PER metre 4.45
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 9.39
Labour for 10010701 29.21 (-a-)
Labour for 10020101 4.62 (-a-)
TOTAL : 43.14
WATER CHARGES @ 1.5% : 0.14
TOTAL : 43.28
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-) : 0.95
ADD FOR OVER HEAD CHARGES @5% Except on (-a-) : 0.48
LABOUR FOR 10.00 metre 44.71
LABOUR Per metre 4.45
LABOUR :
Extra labour due to slow progress
Beldar Each 4.00000 116.67 466.68
TOTAL : 466.68
ADD FOR WATER CHARGES @ 1.5% : 7.00
TOTAL : 473.68
ADD FOR CONTRACTORS PROFIT @10% : 47.37
ADD FOR OVER HEAD CHARGES @5% : 23.69
COST FOR 14 cum per 0.3 metre depth 544.74
COST FOR 1 cum per metre depth 129.70
LABOUR FOR 1 cum per metre depth 129.70
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 466.68
TOTAL : 466.68
WATER CHARGES @ 1.5% : 7.00
TOTAL : 473.68
ADD FOR CONTRACTORS PROFIT @10% : 47.37
ADD FOR OVER HEAD CHARGES @5% : 23.69
LABOUR FOR 14 cum per 0.3 metre depth 544.74
LABOUR FOR 1 cum per metre depth 129.70
LABOUR :
Extra labour due to slow progress
Beldar Each 4.00000 116.67 466.68
TOTAL : 466.68
ADD FOR WATER CHARGES @ 1.5% : 7.00
TOTAL : 473.68
ADD FOR CONTRACTORS PROFIT @10% : 47.37
ADD FOR OVER HEAD CHARGES @5% : 23.69
COST FOR 14 cum per 0.3 metre depth 544.74
COST FOR 1 cum per metre depth 129.70
LABOUR FOR 1 cum per metre depth 129.70
LABOUR RATE :
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
ACTUAL LABOUR+SUNDRIES 466.68
TOTAL : 466.68
WATER CHARGES @ 1.5% : 7.00
TOTAL : 473.68
ADD FOR CONTRACTORS PROFIT @10% : 47.37
ADD FOR OVER HEAD CHARGES @5% : 23.69
LABOUR FOR 14 cum per 0.3 metre depth 544.74
LABOUR FOR 1 cum per metre depth 129.70
10150200 Brick work in or under foul
positions :
LABOUR :
Extra labour due to slow progress
Mason 1st class Each 0.02 211.16 4.22
Mason 2nd Class Each 0.02 158.67 3.17
Beldar Each 0.25 116.67 29.17
Bhishti Each 0.15 116.67 17.50
SUNDRIES : 2.50
TOTAL : 56.56
ADD FOR WATER CHARGES @ 1.5% : 0.85
TOTAL : 57.41
ADD FOR CONTRACTORS PROFIT @10% : 5.74
ADD FOR OVER HEAD CHARGES @5% : 2.87
COST FOR 1.000 cum 66.02
COST PER cum 66.00
LABOUR PER cum 66.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 56.56
TOTAL : 56.56
WATER CHARGES @ 1.5% : 0.85
TOTAL : 57.41
ADD FOR CONTRACTORS PROFIT @10% : 5.74
ADD FOR OVER HEAD CHARGES @5% : 2.87
LABOUR FOR 1.000 cum 66.02
LABOUR PER cum 66.00
10150202 SECOND CLASS BRICKS :
Detail of cost for 1 cubic metre.
LABOUR :
Extra labour due to slow progress
Mason 1st class Each 0.02 211.16 4.22
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
Mason 2nd Class Each 0.02 158.67 3.17
Beldar Each 0.25 116.67 29.17
Bhishti Each 0.15 116.67 17.50
SUNDRIES : 2.50
TOTAL : 56.56
ADD FOR WATER CHARGES @ 1.5% : 0.85
TOTAL : 66.00
ADD FOR CONTRACTORS PROFIT @10% : 57.41
ADD FOR OVER HEAD CHARGES @5% : 5.74
COST FOR 1.000 cum 2.87
COST PER cum 66.02
LABOUR PER cum 66.00
66.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES
TOTAL : 56.56
WATER CHARGES @ 1.5% : 56.56
TOTAL : 0.85
ADD FOR CONTRACTORS PROFIT @10% : 57.41
ADD FOR OVER HEAD CHARGES @5% : 5.74
LABOUR FOR 1.000 cum 2.87
LABOUR PER cum 66.02
66.00
MATERIAL :
CARRIAGE :
Bricks.
1 KM BY MECH. TRANSPORT 1000 Nos. 377.0000 277.35 104.56
LABOUR :
Mason 1st class Each 0.9000 211.16 190.04
Mason 2nd Class Each 0.9000 158.67 142.80
Beldar Each 2.0000 116.67 233.34
Bhishti Each 0.3600 116.67 42.00
SUNDRIES : 34.00
TOTAL : 2491.35
ADD FOR WATER CHARGES @ 1.5% : 37.37
TOTAL : 2528.72
ADD FOR CONTRACTORS PROFIT @10% : 252.87
ADD FOR OVER HEAD CHARGES @5% : 126.44
COST FOR 10.000 sqm 2908.03
COST PER sqm 290.80
LABOUR PER sqm 80.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 642.18
Labour for cement mortar 1:3 20.69
TOTAL : 662.87
WATER CHARGES @ 1.5% : 37.37
TOTAL : 700.24
ADD FOR CONTRACTORS PROFIT @10% : 70.02
ADD FOR OVER HEAD CHARGES @5% : 35.01
LABOUR FOR 10.00 sqm. 805.27
LABOUR PER sqm 80.50
MATERIAL :
CARRIAGE :
Bricks.
1 KM BY MECH. TRANSPORT 1000 Nos. 377.0000 277.35 104.56
LABOUR :
Mason 1st class Each 0.9000 211.16 190.04
Mason 2nd Class Each 0.9000 158.67 142.80
Beldar Each 2.0000 116.67 233.34
Bhishti Each 0.3600 116.67 42.00
SUNDRIES : 34.00
TOTAL : 2415.95
ADD FOR WATER CHARGES @ 1.5% : 36.24
TOTAL : 2452.19
ADD FOR CONTRACTORS PROFIT @10% : 245.22
ADD FOR OVER HEAD CHARGES @5% : 122.61
COST FOR 10.000 sqm 2820.02
COST PER sqm 282.00
LABOUR PER sqm 80.40
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 642.18
Labour for cement mortar 1:3 20.69
TOTAL : 662.87
WATER CHARGES @ 1.5% : 36.24
TOTAL : 699.11
ADD FOR CONTRACTORS PROFIT @10% : 69.91
ADD FOR OVER HEAD CHARGES @5% : 34.96
LABOUR FOR 10.00 sqm. 803.98
LABOUR PER sqm 80.40
MATERIAL :
CARRIAGE :
TOTAL : 3327.69
ADD FOR WATER CHARGES @ 1.5% : 6.30
TOTAL : 3333.99
ADD FOR CONTRACTORS PROFIT 10% 42.60
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1.19
Labour for 10160101 805.27 -a-
TOTAL : 806.46
WATER CHARGES @ 1.5% : 6.30
TOTAL : 812.76
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a-): 0.75
ADD FOR OVER HEAD CHARGES @5% EXCEPT ON (-a-): 0.38
LABOUR FOR 10.000 sq.m. 813.89
LABOUR PER sq.m. 81.40
MATERIAL :
TOTAL : 3239.69
ADD FOR WATER CHARGES @ 1.5% : 6.30
TOTAL : 3245.99
ADD FOR CONTRACTORS PROFIT 10% 42.60
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1.19
Labour for 10160102 803.98 -a-
TOTAL : 805.17
WATER CHARGES @ 1.5% : 6.30
TOTAL : 811.47
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a-): 0.75
ADD FOR OVER HEAD CHARGES @5% EXCEPT ON (-a-): 0.38
LABOUR FOR 10.000 sq.m. 812.60
LABOUR PER sq.m. 81.25
LABOUR :
Mason 1st class Each 1.1300 211.16 238.61
Mason 2nd Class Each 1.1300 158.67 179.30
Beldar Each 2.5000 116.67 291.68
Bhishti Each 1.45000 116.67 169.17
TOTAL : 912.75
WATER CHARGES @ 1.5% : 13.69
TOTAL : 926.45
ADD FOR CONTRACTORS PROFIT @10% : 92.64
ADD FOR OVER HEAD CHARGES @5% : 46.32
LABOUR FOR 10.00 sqm 1065.41
LABOUR PER sqm. 106.55
LABOUR :
Mason 1st class Each 1.1300 211.16 238.61
Mason 2nd Class Each 1.1300 158.67 179.30
Beldar Each 2.5000 116.67 291.68
Bhishti Each 1.45000 116.67 169.17
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 912.75
TOTAL : 912.75
WATER CHARGES @ 1.5% : 13.69
TOTAL : 926.45
ADD FOR CONTRACTORS PROFIT @10% : 92.65
ADD FOR OVER HEAD CHARGES @5% : 46.33
LABOUR FOR 10.00 sqm 1065.43
LABOUR PER sqm. 106.55
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
CARRIAGE :
Bricks tiles.
1 KM BY MECH. TRANSPORT 1000 Nos. 777.0000 173.55 134.85
LABOUR :
Mason 1st class Each 0.8500 211.16 179.49
Mason 2nd Class Each 0.8500 158.67 134.87
Beldar Each 1.6500 116.67 192.51
Bhishti Each 0.22000 116.67 25.67
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 562.53
Labour for lime surkhi mortar 1:1:1 137.67
TOTAL : 700.20
WATER CHARGES @ 1.5% : 60.60
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 760.80
ADD FOR CONTRACTORS PROFIT @10% : 76.08
ADD FOR OVER HEAD CHARGES @5% : 38.04
LABOUR FOR 1.00 cum 874.92
LABOUR PER cum 874.95
MATERIAL :
CARRIAGE :
Bricks tiles.
1 KM BY MECH. TRANSPORT 1000 Nos. 777.0000 173.55 134.85
LABOUR :
Mason 1st class Each 0.8500 211.16 179.49
Mason 2nd Class Each 0.8500 158.67 134.87
Beldar Each 1.6500 116.67 192.51
Bhishti Each 0.22000 116.67 25.67
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 562.53
Labour for lime surkhi mortar 1:1:1 137.67
TOTAL : 700.20
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
WATER CHARGES @ 1.5% : 63.32
TOTAL : 763.52
ADD FOR CONTRACTORS PROFIT @10% : 76.35
ADD FOR OVER HEAD CHARGES @5% : 38.18
LABOUR FOR 1.00 cum 878.05
LABOUR PER cum 878.05
MATERIAL :
Common burnt clay brick tiles 1000 Nos 777.0000 3000.00 2331.00
CARRIAGE :
Bricks tiles.
1 KM BY MECH. TRANSPORT 1000 Nos. 777.0000 173.55 134.85
LABOUR :
Mason 1st class Each 0.8500 211.16 179.49
Mason 2nd Class Each 0.8500 158.67 134.87
Beldar Each 1.6500 116.67 192.51
Bhishti Each 0.22000 116.67 25.67
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 562.53
Labour for cement mortar 1:4 45.73
TOTAL : 608.26
WATER CHARGES @ 1.5% : 61.33
TOTAL : 669.59
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR CONTRACTORS PROFIT @10% : 66.96
ADD FOR OVER HEAD CHARGES @5% : 33.48
LABOUR FOR 1.00 cum 770.03
LABOUR PER cum 770.05
MATERIAL :
CARRIAGE :
Bricks tiles.
1 KM BY MECH. TRANSPORT 1000 Nos. 777.0000 173.55 134.85
LABOUR :
Mason 1st class Each 0.8500 211.16 179.49
Mason 2nd Class Each 0.8500 158.67 134.87
Beldar Each 1.6500 116.67 192.51
Bhishti Each 0.22000 116.67 25.67
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 562.53
Labour for cement mortar 1:6 45.73
TOTAL : 608.26
WATER CHARGES @ 1.5% : 57.43
TOTAL : 665.69
ADD FOR CONTRACTORS PROFIT @10% : 66.57
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR OVER HEAD CHARGES @5% : 33.28
LABOUR FOR 1.00 cum 765.54
LABOUR PER cum 765.55
LABOUR :
Mason 1st class Each 0.1300 211.16 27.45
Mason 2nd Class Each 0.1300 158.67 20.63
Beldar Each 0.3300 116.67 38.50
SUNDRIES : 11.00
TOTAL : 97.58
ADD FOR WATER CHARGES @ 1.5% : 1.46
TOTAL : 99.04
ADD FOR CONTRACTORS PROFIT @10% : 9.90
ADD FOR OVER HEAD CHARGES @5% : 4.95
COST FOR 1.000 cum 113.89
COST PER cum 113.90
LABOUR PER cum 113.90
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 97.58
TOTAL : 97.58
WATER CHARGES @ 1.5% : 1.46
TOTAL : 99.04
ADD FOR CONTRACTORS PROFIT @10% : 9.90
ADD FOR OVER HEAD CHARGES @5% : 4.95
LABOUR FOR 1.000 cum 113.89
LABOUR PER cum 113.90
LABOUR :
Mason 1st class Each 0.4000 211.16 84.46
Mason 2nd Class Each 0.4000 158.67 63.47
Beldar Each 0.3500 116.67 40.83
TOTAL : 188.77
ADD FOR WATER CHARGES @ 1.5% : 2.83
TOTAL : 191.60
ADD FOR CONTRACTORS PROFIT @ 10% 19.16
ADD FOR OVER HEAD CHARGES @5% : 9.58
COST FOR 1.000 cum 220.34
COST PER cum 220.35
LABOUR PER cum 220.35
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 188.77
TOTAL : 188.77
WATER CHARGES @ 1.5% : 2.83
TOTAL : 191.60
ADD FOR CONTRACTORS PROFIT @10% : 19.16
ADD FOR OVER HEAD CHARGES @5% : 9.58
LABOUR FOR 1.000 cum 220.34
LABOUR PER cum 220.35
CARRIAGE :
Bricks tiles.
1 KM BY MECH. TRANSPORT 1000 Nos. 55.0000 173.55 9.55
LABOUR :
Mason 1st class Each 0.2000 211.16 42.23
Mason 2nd Class Each 0.2000 158.67 31.73
Beldar Each 0.8000 116.67 93.34
TOTAL : 345.34
ADD FOR WATER CHARGES @ 1.5% : 5.18
TOTAL : 350.52
ADD FOR CONTRACTORS PROFIT @ 10% 35.05
ADD FOR OVER HEAD CHARGES @5% : 17.53
COST FOR 1.000 cum 403.10
COST PER cum 403.10
LABOUR PER cum 198.35
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 167.30
TOTAL : 167.30
WATER CHARGES @ 1.5% : 5.18
TOTAL : 172.48
ADD FOR CONTRACTORS PROFIT @10% : 17.25
ADD FOR OVER HEAD CHARGES @5% : 8.62
LABOUR FOR 1.000 cum 198.35
LABOUR PER cum 198.35
MATERIAL :
Common burnt clay brick tiles 1000 Nos 777.0000 3000.00 2331.00
CARRIAGE :
Bricks tiles.
1 KM BY MECH. TRANSPORT 1000 Nos. 777.0000 173.55 134.85
LABOUR :
Mason 1st class Each 0.7000 211.16 147.81
Mason 2nd Class Each 0.7000 158.67 111.07
Beldar Each 3.2100 116.67 374.51
Bhishti Each 0.2000 116.67 23.33
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 699.22
Labour for cement mortar 1:4 45.73
Labour for Centreing and shuttering (2.25x265.50) 597.37 (-a-)
TOTAL : 1342.32
WATER CHARGES @ 1.5% : 118.14
TOTAL : 1460.46
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a-): 86.31
ADD FOR OVER HEAD CHARGES @5% EXCEPT ON (-a-): 43.16
LABOUR FOR 1.000 cum 1589.93
LABOUR PER cum 1589.95
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
MODULAR BRICKS
10210000 Brick work using common burnt clay
building bricks in foundation and
plinth in:-
MATERIAL :
CARRIAGE :
Bricks
1 KM BY MECH. TRANSPORT 1000 Nos. 520.0000 277.35 144.22
LABOUR :
Mason 1st class Each 0.4800 211.16 101.36
Mason 2nd Class Each 0.4800 158.67 76.16
Beldar Each 1.6900 116.67 197.17
Bhishti Each 0.2000 116.67 23.33
SUNDRIES : 22.50
TOTAL : 2682.70
ADD FOR WATER CHARGES @ 1.5% : 40.24
TOTAL : 2722.94
ADD FOR CONTRACTORS PROFIT 10% 272.29
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 420.52
Labour for lime surkhi mortar 1:1:1 72.27
TOTAL : 492.79
WATER CHARGES @ 1.5% : 40.24
TOTAL : 533.03
ADD FOR CONTRACTORS PROFIT @10% : 53.30
ADD FOR OVER HEAD CHARGES @5% : 26.65
LABOUR FOR 1.000 cum 612.98
LABOUR PER cum 613.00
MATERIAL :
CARRIAGE :
Bricks
1 KM BY MECH. TRANSPORT 1000 Nos. 520.0000 277.35 144.22
LABOUR :
Mason 1st class Each 0.4800 211.16 101.36
Mason 2nd Class Each 0.4800 158.67 76.16
Beldar Each 1.6900 116.67 197.17
Bhishti Each 0.2000 116.67 23.33
SUNDRIES : 22.50
TOTAL : 2578.70
ADD FOR WATER CHARGES @ 1.5% : 38.68
TOTAL : 2617.38
ADD FOR CONTRACTORS PROFIT 10% 261.74
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 420.52
Labour for lime surkhi mortar 1:1:1 72.27
TOTAL : 492.79
WATER CHARGES @ 1.5% : 38.68
TOTAL : 531.47
ADD FOR CONTRACTORS PROFIT @10% : 53.15
ADD FOR OVER HEAD CHARGES @5% : 26.58
LABOUR FOR 1.000 cum 611.20
LABOUR PER cum 611.20
MATERIAL :
CARRIAGE :
Bricks tiles.
1 KM BY MECH. TRANSPORT 1000 Nos. 520.0000 277.35 144.22
LABOUR :
Mason 1st class Each 0.4800 211.16 101.36
Mason 2nd Class Each 0.4800 158.67 76.16
Beldar Each 1.6900 116.67 197.17
Bhishti Each 0.20000 116.67 23.33
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
SUNDRIES : L.S. 22.50
TOTAL : 2742.96
ADD FOR WATER CHARGES @ 1.5% : 41.14
TOTAL : 2784.11
ADD FOR CONTRACTORS PROFIT @ 10% 278.41
ADD FOR OVER HEAD CHARGES @5% : 139.21
COST FOR 1.00 cum 3201.73
COST PER cum 3201.70
LABOUR PER cum 614.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 420.52
Labour for cement lime mortar 1:1:6 72.27
TOTAL : 492.79
WATER CHARGES @ 1.5% : 41.14
TOTAL : 533.94
ADD FOR CONTRACTORS PROFIT @10% : 53.39
ADD FOR OVER HEAD CHARGES @5% : 26.70
LABOUR FOR 1.00 cum 614.03
LABOUR PER cum 614.00
MATERIAL :
CARRIAGE :
Bricks tiles.
1 KM BY MECH. TRANSPORT 1000 Nos. 520.0000 277.35 144.22
LABOUR :
Mason 1st class Each 0.4800 211.16 101.36
Mason 2nd Class Each 0.4800 158.67 76.16
Beldar Each 1.6900 116.67 197.17
Bhishti Each 0.20000 116.67 23.33
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
SUNDRIES : L.S. 22.50
TOTAL : 2638.96
ADD FOR WATER CHARGES @ 1.5% : 39.58
TOTAL : 2678.55
ADD FOR CONTRACTORS PROFIT @ 10% 267.85
ADD FOR OVER HEAD CHARGES @5% : 133.93
COST FOR 1.00 cum 3080.33
COST PER cum 3080.30
LABOUR PER cum 612.25
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 420.52
Labour for cement lime mortar 1:1:6 72.27
TOTAL : 492.79
WATER CHARGES @ 1.5% : 39.58
TOTAL : 532.38
ADD FOR CONTRACTORS PROFIT @10% : 53.24
ADD FOR OVER HEAD CHARGES @5% : 26.62
LABOUR FOR 1.00 cum 612.24
LABOUR PER cum 612.25
MATERIAL :
CARRIAGE :
Bricks
1 KM BY MECH. TRANSPORT 1000 Nos. 520.0000 277.35 144.22
LABOUR :
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
Mason 1st class Each 0.4800 211.16 101.36
Mason 2nd Class Each 0.4800 158.67 76.16
Beldar Each 1.6900 116.67 197.17
Bhishti Each 0.20000 116.67 23.33
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 420.52
Labour for cement lime mortar 1:1:7 72.27
TOTAL : 492.79
WATER CHARGES @ 1.5% : 40.41
TOTAL : 533.21
ADD FOR CONTRACTORS PROFIT @10% : 53.32
ADD FOR OVER HEAD CHARGES @5% : 26.66
LABOUR FOR 1.00 cum 613.19
LABOUR PER cum 613.20
MATERIAL :
CARRIAGE :
Bricks
1 KM BY MECH. TRANSPORT 1000 Nos. 520.0000 277.35 144.22
LABOUR :
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
Mason 1st class Each 0.4800 211.16 101.36
Mason 2nd Class Each 0.4800 158.67 76.16
Beldar Each 1.6900 116.67 197.17
Bhishti Each 0.20000 116.67 23.33
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 420.52
Labour for cement lime mortar 1:1:7 72.27
TOTAL : 492.79
WATER CHARGES @ 1.5% : 38.85
TOTAL : 531.65
ADD FOR CONTRACTORS PROFIT @10% : 53.16
ADD FOR OVER HEAD CHARGES @5% : 26.58
LABOUR FOR 1.00 cum 611.39
LABOUR PER cum 611.40
MATERIAL :
CARRIAGE :
Bricks
1 KM BY MECH. TRANSPORT 1000 Nos. 520.0000 277.35 144.22
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
100 MTRS BY HEAD LOAD 1000 Nos. 520.0000 101.45 52.75
LABOUR :
Mason 1st class Each 0.4800 211.16 101.36
Mason 2nd Class Each 0.4800 158.67 76.16
Beldar Each 1.6900 116.67 197.17
Bhishti Each 0.20000 116.67 23.33
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 420.52
Labour for cement lime mortar 1:1:8 72.27
TOTAL : 492.79
WATER CHARGES @ 1.5% : 39.72
TOTAL : 532.52
ADD FOR CONTRACTORS PROFIT @10% : 53.25
ADD FOR OVER HEAD CHARGES @5% : 26.63
LABOUR FOR 1.00 cum 612.40
LABOUR PER cum 612.40
MATERIAL :
CARRIAGE :
Bricks
1 KM BY MECH. TRANSPORT 1000 Nos. 520.0000 277.35 144.22
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
100 MTRS BY HEAD LOAD 1000 Nos. 520.0000 101.45 52.75
LABOUR :
Mason 1st class Each 0.4800 211.16 101.36
Mason 2nd Class Each 0.4800 158.67 76.16
Beldar Each 1.6900 116.67 197.17
Bhishti Each 0.20000 116.67 23.33
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 420.52
Labour for cement lime mortar 1:1:8 72.27
TOTAL : 492.79
WATER CHARGES @ 1.5% : 38.16
TOTAL : 530.96
ADD FOR CONTRACTORS PROFIT @10% : 53.10
ADD FOR OVER HEAD CHARGES @5% : 26.55
LABOUR FOR 1.00 cum 610.60
LABOUR PER cum 610.60
MATERIAL :
CARRIAGE :
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
Bricks
1 KM BY MECH. TRANSPORT 1000 Nos. 520.0000 277.35 144.22
LABOUR :
Mason 1st class Each 0.4800 211.16 101.36
Mason 2nd Class Each 0.4800 158.67 76.16
Beldar Each 1.6900 116.67 197.17
Bhishti Each 0.20000 116.67 23.33
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 420.52
Labour for cement lime mortar 1:2:9 72.27
TOTAL : 492.79
WATER CHARGES @ 1.5% : 39.26
TOTAL : 532.05
ADD FOR CONTRACTORS PROFIT @10% : 53.21
ADD FOR OVER HEAD CHARGES @5% : 26.60
LABOUR FOR 1.00 cum 611.86
LABOUR PER cum 611.85
MATERIAL :
CARRIAGE :
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
Bricks
1 KM BY MECH. TRANSPORT 1000 Nos. 520.0000 277.35 144.22
LABOUR :
Mason 1st class Each 0.4800 211.16 101.36
Mason 2nd Class Each 0.4800 158.67 76.16
Beldar Each 1.6900 116.67 197.17
Bhishti Each 0.20000 116.67 23.33
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 420.52
Labour for cement lime mortar 1:2:9 72.27
TOTAL : 492.79
WATER CHARGES @ 1.5% : 37.70
TOTAL : 530.49
ADD FOR CONTRACTORS PROFIT @10% : 53.05
ADD FOR OVER HEAD CHARGES @5% : 26.52
LABOUR FOR 1.00 cum 610.07
LABOUR PER cum 610.05
MATERIAL :
CARRIAGE :
Bricks
1 KM BY MECH. TRANSPORT 1000 Nos. 520.0000 277.35 144.22
LABOUR :
Mason 1st class Each 0.4800 211.16 101.36
Mason 2nd Class Each 0.4800 158.67 76.16
Beldar Each 1.6900 116.67 197.17
Bhishti Each 0.20000 116.67 23.33
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 420.52
Labour for cement mortar 1:3 24.00
TOTAL : 444.52
WATER CHARGES @ 1.5% : 42.68
TOTAL : 487.20
ADD FOR CONTRACTORS PROFIT @10% : 48.72
ADD FOR OVER HEAD CHARGES @5% : 24.36
LABOUR FOR 1.00 cum 560.28
LABOUR PER cum 560.30
MATERIAL :
CARRIAGE :
Bricks
1 KM BY MECH. TRANSPORT 1000 Nos. 520.0000 277.35 144.22
LABOUR :
Mason 1st class Each 0.4800 211.16 101.36
Mason 2nd Class Each 0.4800 158.67 76.16
Beldar Each 1.6900 116.67 197.17
Bhishti Each 0.20000 116.67 23.33
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 420.52
Labour for cement mortar 1:3 24.00
TOTAL : 444.52
WATER CHARGES @ 1.5% : 41.12
TOTAL : 485.64
ADD FOR CONTRACTORS PROFIT @10% : 48.56
ADD FOR OVER HEAD CHARGES @5% : 24.28
LABOUR FOR 1.00 cum 558.49
LABOUR PER cum 558.50
MATERIAL :
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
First class common burnt clay
building bricks. 1000 Nos 520.0000 3000.00 1560.00
CARRIAGE :
Bricks
1 KM BY MECH. TRANSPORT 1000 Nos. 520.0000 277.35 144.22
LABOUR :
Mason 1st class Each 0.4800 211.16 101.36
Mason 2nd Class Each 0.4800 158.67 76.16
Beldar Each 1.6900 116.67 197.17
Bhishti Each 0.20000 116.67 23.33
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 420.52
Labour for cement mortar 1:4 24.00
TOTAL : 444.52
WATER CHARGES @ 1.5% : 40.63
TOTAL : 485.15
ADD FOR CONTRACTORS PROFIT @10% : 48.52
ADD FOR OVER HEAD CHARGES @5% : 24.26
LABOUR FOR 1.00 cum 557.92
LABOUR PER cum 557.95
MATERIAL :
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
Second class common burnt clay
building bricks. 1000 Nos 520.0000 2800.00 1456.00
CARRIAGE :
Bricks
1 KM BY MECH. TRANSPORT 1000 Nos. 520.0000 277.35 144.22
LABOUR :
Mason 1st class Each 0.4800 211.16 101.36
Mason 2nd Class Each 0.4800 158.67 76.16
Beldar Each 1.6900 116.67 197.17
Bhishti Each 0.20000 116.67 23.33
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 420.52
Labour for cement mortar 1:4 24.00
TOTAL : 444.52
WATER CHARGES @ 1.5% : 39.07
TOTAL : 483.59
ADD FOR CONTRACTORS PROFIT @10% : 48.36
ADD FOR OVER HEAD CHARGES @5% : 24.18
LABOUR FOR 1.00 cum 556.13
LABOUR PER cum 556.15
MATERIAL :
CARRIAGE :
Bricks
1 KM BY MECH. TRANSPORT 1000 Nos. 520.0000 277.35 144.22
LABOUR :
Mason 1st class Each 0.4800 211.16 101.36
Mason 2nd Class Each 0.4800 158.67 76.16
Beldar Each 1.6900 116.67 197.17
Bhishti Each 0.20000 116.67 23.33
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 420.52
Labour for cement mortar 1:5 24.00
TOTAL : 444.52
WATER CHARGES @ 1.5% : 39.52
TOTAL : 484.05
ADD FOR CONTRACTORS PROFIT @10% : 48.40
ADD FOR OVER HEAD CHARGES @5% : 24.20
LABOUR FOR 1.00 cum 556.65
LABOUR PER cum 556.65
MATERIAL :
CARRIAGE :
Bricks
1 KM BY MECH. TRANSPORT 1000 Nos. 520.0000 277.35 144.22
LABOUR :
Mason 1st class Each 0.4800 211.16 101.36
Mason 2nd Class Each 0.4800 158.67 76.16
Beldar Each 1.6900 116.67 197.17
Bhishti Each 0.20000 116.67 23.33
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 420.52
Labour for cement mortar 1:5 24.00
TOTAL : 444.52
WATER CHARGES @ 1.5% : 37.96
TOTAL : 482.49
ADD FOR CONTRACTORS PROFIT @10% : 48.25
ADD FOR OVER HEAD CHARGES @5% : 24.12
LABOUR FOR 1.00 cum 554.86
LABOUR PER cum 554.85
MATERIAL :
CARRIAGE :
Bricks
1 KM BY MECH. TRANSPORT 1000 Nos. 520.0000 277.35 144.22
LABOUR :
Mason 1st class Each 0.4800 211.16 101.36
Mason 2nd Class Each 0.4800 158.67 76.16
Beldar Each 1.6900 116.67 197.17
Bhishti Each 0.20000 116.67 23.33
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 420.52
Labour for cement mortar 1:6 24.00
TOTAL : 444.52
WATER CHARGES @ 1.5% : 38.58
TOTAL : 483.10
ADD FOR CONTRACTORS PROFIT @10% : 48.31
ADD FOR OVER HEAD CHARGES @5% : 24.16
LABOUR FOR 1.00 cum 555.57
LABOUR PER cum 555.55
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
CARRIAGE :
Bricks
1 KM BY MECH. TRANSPORT 1000 Nos. 520.0000 277.35 144.22
LABOUR :
Mason 1st class Each 0.4800 211.16 101.36
Mason 2nd Class Each 0.4800 158.67 76.16
Beldar Each 1.6900 116.67 197.17
Bhishti Each 0.20000 116.67 23.33
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 420.52
Labour for cement mortar 1:6 24.00
TOTAL : 444.52
WATER CHARGES @ 1.5% : 37.02
TOTAL : 481.54
ADD FOR CONTRACTORS PROFIT @10% : 48.15
ADD FOR OVER HEAD CHARGES @5% : 24.08
LABOUR FOR 1.00 cum 553.77
LABOUR PER cum 553.75
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
CARRIAGE :
Bricks
1 KM BY MECH. TRANSPORT 1000 Nos. 520.0000 277.35 144.22
LABOUR :
Mason 1st class Each 0.4800 211.16 101.36
Mason 2nd Class Each 0.4800 158.67 76.16
Beldar Each 1.6900 116.67 197.17
Bhishti Each 0.20000 116.67 23.33
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 420.52
Labour for mud mortar 25.71
TOTAL : 446.23
WATER CHARGES @ 1.5% : 33.78
TOTAL : 480.01
ADD FOR CONTRACTORS PROFIT @10% : 48.00
ADD FOR OVER HEAD CHARGES @5% : 24.00
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR FOR 1.00 cum 552.01
LABOUR PER cum 552.00
MATERIAL :
CARRIAGE :
Bricks
1 KM BY MECH. TRANSPORT 1000 Nos. 520.0000 277.35 144.22
LABOUR :
Mason 1st class Each 0.4800 211.16 101.36
Mason 2nd Class Each 0.4800 158.67 76.16
Beldar Each 1.6900 116.67 197.17
Bhishti Each 0.20000 116.67 23.33
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 420.52
Labour for mud mortar 25.71
TOTAL : 446.23
WATER CHARGES @ 1.5% : 32.22
TOTAL : 478.45
ADD FOR CONTRACTORS PROFIT @10% : 47.85
ADD FOR OVER HEAD CHARGES @5% : 23.92
LABOUR FOR 1.00 cum 550.22
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR PER cum 550.25
LABOUR :
Mason 1st class Each 0.0800 211.16 16.89
Mason 2nd Class Each 0.0800 158.67 12.69
Beldar Each 0.3100 116.67 36.17
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 76.75
TOTAL : 76.75
WATER CHARGES @ 1.5% : 1.15
TOTAL : 77.91
ADD FOR CONTRACTORS PROFIT @10% : 7.79
ADD FOR OVER HEAD CHARGES @5% : 3.90
LABOUR FOR 1.00 cum 89.59
LABOUR PER cum 89.60
LABOUR :
Mason 1st class Each 0.0800 211.16 16.89
Mason 2nd Class Each 0.0800 158.67 12.69
Beldar Each 0.3100 116.67 36.17
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 76.75
TOTAL : 76.75
WATER CHARGES @ 1.5% : 1.15
TOTAL : 77.91
ADD FOR CONTRACTORS PROFIT @10% : 7.79
ADD FOR OVER HEAD CHARGES @5% : 3.90
LABOUR FOR 1.00 cum 89.59
LABOUR PER cum 89.60
LABOUR :
Mason 1st class Each 0.2500 211.16 52.79
Mason 2nd Class Each 0.2500 158.67 39.67
Beldar Each 0.2500 116.67 29.17
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 121.63
ADD FOR WATER CHARGES @ 1.5% : 1.82
TOTAL : 123.45
ADD FOR CONTRACTORS PROFIT @ 10% 12.34
ADD FOR OVER HEAD CHARGES @5% : 6.17
COST FOR 1.00 cum 141.97
COST PER cum 141.97
LABOUR PER cum 142.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 121.63
TOTAL : 121.63
WATER CHARGES @ 1.5% : 1.82
TOTAL : 123.45
ADD FOR CONTRACTORS PROFIT @10% : 12.34
ADD FOR OVER HEAD CHARGES @5% : 6.17
LABOUR FOR 1.00 cum 141.97
LABOUR PER cum 142.00
LABOUR :
Mason 1st class Each 0.2500 211.16 52.79
Mason 2nd Class Each 0.2500 158.67 39.67
Beldar Each 0.2500 116.67 29.17
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 121.63
ADD FOR WATER CHARGES @ 1.5% : 1.82
TOTAL : 123.45
ADD FOR CONTRACTORS PROFIT @ 10% 12.34
ADD FOR OVER HEAD CHARGES @5% : 6.17
COST FOR 1.00 cum 141.97
COST PER cum 141.97
LABOUR PER cum 142.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 121.63
TOTAL : 121.63
WATER CHARGES @ 1.5% : 1.82
TOTAL : 123.45
ADD FOR CONTRACTORS PROFIT @10% : 12.34
ADD FOR OVER HEAD CHARGES @5% : 6.17
LABOUR FOR 1.00 cum 141.97
LABOUR PER cum 142.00
MATERIAL :
CARRIAGE :
Bricks
1 KM BY MECH. TRANSPORT 1000 Nos. 142.0000 277.35 39.38
LABOUR :
(For cutting and dressing of bricks)
Mason 1st class Each 0.6500 211.16 137.25
Mason 2nd Class Each 0.6500 158.67 103.14
Beldar Each 0.3300 116.67 38.50
TOTAL : 758.68
ADD FOR WATER CHARGES @ 1.5% : 11.38
TOTAL : 770.06
ADD FOR CONTRACTORS PROFIT @ 10% 77.01
ADD FOR OVER HEAD CHARGES @5% : 38.50
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
COST FOR 1.00 cum 885.57
COST PER cum 885.55
LABOUR PER cum 333.80
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 278.89
TOTAL : 278.89
WATER CHARGES @ 1.5% : 11.38
TOTAL : 290.27
ADD FOR CONTRACTORS PROFIT @10% : 29.03
ADD FOR OVER HEAD CHARGES @5% : 14.51
LABOUR FOR 1.00 cum 333.81
LABOUR PER cum 333.80
MATERIAL :
CARRIAGE :
Bricks
1 KM BY MECH. TRANSPORT 1000 Nos. 142.0000 277.35 39.38
LABOUR :
(For cutting and dressing of bricks)
Mason 1st class Each 0.6500 211.16 137.25
Mason 2nd Class Each 0.6500 158.67 103.14
Beldar Each 0.3300 116.67 38.50
TOTAL : 730.28
ADD FOR WATER CHARGES @ 1.5% : 10.95
TOTAL : 741.23
ADD FOR CONTRACTORS PROFIT @ 10% 74.12
ADD FOR OVER HEAD CHARGES @5% : 37.06
COST FOR 1.00 cum 852.42
COST PER cum 852.40
LABOUR PER cum 333.30
LABOUR RATE :
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
ACTUAL LABOUR+SUNDRIES 278.89
TOTAL : 278.89
WATER CHARGES @ 1.5% : 10.95
TOTAL : 289.84
ADD FOR CONTRACTORS PROFIT @10% : 28.98
ADD FOR OVER HEAD CHARGES @5% : 14.49
LABOUR FOR 1.00 cum 333.32
LABOUR PER cum 333.30
MATERIAL :
CARRIAGE :
Bricks
1 KM BY MECH. TRANSPORT 1000 Nos. 35.0000 277.35 9.71
LABOUR :
TOTAL : 220.97
ADD FOR WATER CHARGES @ 1.5% : 3.31
TOTAL : 224.29
ADD FOR CONTRACTORS PROFIT @ 10% 22.43
ADD FOR OVER HEAD CHARGES @5% : 11.21
COST FOR 1.00 cum 257.93
COST PER cum 257.93
LABOUR PER cum 121.95
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 102.71
TOTAL : 102.71
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
WATER CHARGES @ 1.5% : 3.31
TOTAL : 106.03
ADD FOR CONTRACTORS PROFIT @10% : 10.60
ADD FOR OVER HEAD CHARGES @5% : 5.30
LABOUR FOR 1.00 cum 121.93
LABOUR PER cum 121.95
MATERIAL :
CARRIAGE :
Bricks
1 KM BY MECH. TRANSPORT 1000 Nos. 35.0000 277.35 9.71
LABOUR :
TOTAL : 213.97
ADD FOR WATER CHARGES @ 1.5% : 3.21
TOTAL : 217.18
ADD FOR CONTRACTORS PROFIT @ 10% 21.72
ADD FOR OVER HEAD CHARGES @5% : 10.86
COST FOR 1.00 cum 249.76
COST PER cum 249.75
LABOUR PER cum 121.80
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 102.71
TOTAL : 102.71
WATER CHARGES @ 1.5% : 3.21
TOTAL : 105.92
ADD FOR CONTRACTORS PROFIT @10% : 10.59
ADD FOR OVER HEAD CHARGES @5% : 5.30
LABOUR FOR 1.00 cum 121.81
LABOUR PER cum 121.80
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
CARRIAGE :
Bricks
1 KM BY MECH. TRANSPORT 1000 Nos. 175.0000 277.35 48.54
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 685.34
TOTAL : 685.34
WATER CHARGES @ 1.5% : 19.15
TOTAL : 704.49
ADD FOR CONTRACTORS PROFIT @10% : 70.45
ADD FOR OVER HEAD CHARGES @5% : 35.22
LABOUR FOR 9.300 sqm 810.17
LABOUR PER sqm 87.10
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
10220602 Tapered surface of brick masonry
(Second Class Bricks)
Detail of cost for a tapered well
(slope 1:4) 3 metres high and 3
metres long:
MATERIAL :
CARRIAGE :
Bricks
1 KM BY MECH. TRANSPORT 1000 Nos. 175.0000 277.35 48.54
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 685.34
TOTAL : 685.34
WATER CHARGES @ 1.5% : 18.62
TOTAL : 703.97
ADD FOR CONTRACTORS PROFIT @10% : 70.40
ADD FOR OVER HEAD CHARGES @5% : 35.20
LABOUR FOR 9.300 sqm 809.56
LABOUR PER sqm 87.05
MATERIAL :
CARRIAGE :
Bricks
1 KM BY MECH. TRANSPORT 1000 Nos. 487.0000 277.35 135.07
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 525.34
Labour for cement mortar 1:4 25.15
Labour for Centreing and shuttering 2.25x265.50 597.37 (-a-)
TOTAL : 1147.86
WATER CHARGES @ 1.5% : 95.66
TOTAL : 1243.53
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-) : 64.62
ADD FOR OVER HEAD CHARGES @5% Except on (-a-) : 32.31
LABOUR FOR 1.00 cum 1340.46
LABOUR PER cum 1340.45
MATERIAL :
CARRIAGE :
Bricks
1 KM BY MECH. TRANSPORT 1000 Nos. 487.0000 277.35 135.07
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 525.34
Labour for cement mortar 1:4 25.15
Labour for Centreing and shuttering 2.25x265.50 597.37 (-a-)
TOTAL : 1147.86
WATER CHARGES @ 1.5% : 94.20
TOTAL : 1242.06
ADD FOR CONTRACTORS PROFIT @10% except on (-a-) : 64.47
ADD FOR OVER HEAD CHARGES @5% except on (-a-) : 32.24
LABOUR FOR 1.00 cum 1338.77
LABOUR PER cum 1338.75
MATERIAL :
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
CARRIAGE :
Bricks
1 KM BY MECH. TRANSPORT 1000 Nos. 580.0000 277.35 160.86
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1022.41
Labour for cement mortar 1:4 25.15
Labour for Centreing and shuttering 2.25x265.50 597.37 (-a-)
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 1644.93
WATER CHARGES @ 1.5% : 107.83
TOTAL : 1752.76
ADD FOR CONTRACTORS PROFIT @10% except on (-a-) : 115.54
ADD FOR OVER HEAD CHARGES @5% except on (-a-) : 57.77
LABOUR FOR 1.00 cum 1926.07
LABOUR PER cum 1926.05
MATERIAL :
CARRIAGE :
Bricks
1 KM BY MECH. TRANSPORT 1000 Nos. 580.0000 277.35 160.86
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1022.41
Labour for cement mortar 1:4 25.15
Labour for Centreing and shuttering 2.25x265.50 597.37 (-a-)
TOTAL : 1644.93
WATER CHARGES @ 1.5% : 106.09
TOTAL : 1751.02
ADD FOR CONTRACTORS PROFIT @10% except on (-a-) : 115.36
ADD FOR OVER HEAD CHARGES @5% except on (-a-) : 57.68
LABOUR FOR 1.00 cum 1924.02
LABOUR PER cum 1924.00
MATERIAL :
CARRIAGE :
Bricks
1 KM BY MECH. TRANSPORT 1000 Nos. 550.0000 277.35 152.54
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 541.56
Labour for cement lime mortar 1:1:6 86.04
TOTAL : 627.60
WATER CHARGES @ 1.5% : 46.10
TOTAL : 673.70
ADD FOR CONTRACTORS PROFIT @10% : 67.37
ADD FOR OVER HEAD CHARGES @5% : 33.69
LABOUR FOR 10.00 SQM 774.76
LABOUR PER sqm 77.50
MATERIAL :
CARRIAGE :
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
Bricks
1 KM BY MECH. TRANSPORT 1000 Nos. 550.0000 277.35 152.54
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 541.56
Labour for cement lime mortar 1:1:6 86.04
TOTAL : 627.60
WATER CHARGES @ 1.5% : 44.45
TOTAL : 672.05
ADD FOR CONTRACTORS PROFIT @10% : 67.21
ADD FOR OVER HEAD CHARGES @5% : 33.60
LABOUR FOR 10.00 SQM 772.86
LABOUR PER sqm 77.30
MATERIAL :
CARRIAGE :
Bricks
1 KM BY MECH. TRANSPORT 1000 Nos. 550.0000 277.35 152.54
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 541.56
Labour for cement mortar 1:3 28.58
TOTAL : 570.14
WATER CHARGES @ 1.5% : 47.92
TOTAL : 618.06
ADD FOR CONTRACTORS PROFIT @10% : 61.81
ADD FOR OVER HEAD CHARGES @5% : 30.90
LABOUR FOR 10.00 SQM 710.77
LABOUR PER sqm 71.10
MATERIAL :
CARRIAGE :
Bricks
1 KM BY MECH. TRANSPORT 1000 Nos. 550.0000 277.35 152.54
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 541.56
Labour for cement mortar 1:3 28.58
TOTAL : 570.14
WATER CHARGES @ 1.5% : 46.27
TOTAL : 616.41
ADD FOR CONTRACTORS PROFIT @10% : 61.64
ADD FOR OVER HEAD CHARGES @5% : 30.82
LABOUR FOR 10.00 SQM 708.87
LABOUR PER sqm 70.90
MATERIAL :
CARRIAGE :
Bricks
1 KM BY MECH. TRANSPORT 1000 Nos. 550.0000 277.35 152.54
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 541.56
Labour for cement mortar 1:3 28.58
TOTAL : 570.14
WATER CHARGES @ 1.5% : 45.48
TOTAL : 615.62
ADD FOR CONTRACTORS PROFIT @10% : 61.56
ADD FOR OVER HEAD CHARGES @5% : 30.78
LABOUR FOR 10.00 SQM 707.96
LABOUR PER sqm 70.80
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
CARRIAGE :
Bricks.
1 KM BY MECH. TRANSPORT 1000 Nos. 550.00 277.35 152.54
LABOUR :
Mason 1st class Each 1.14 211.16 240.72
Beldar Each 1.93 116.67 225.17
Bhishti Each 0.40 116.67 46.67
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 541.56
Labour for cement mortar 1:4 28.58
TOTAL : 570.14
WATER CHARGES @ 1.5% : 43.83
TOTAL : 613.97
ADD FOR CONTRACTORS PROFIT @10% : 61.40
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR OVER HEAD CHARGES @5% : 30.70
LABOUR FOR 10.000 sq.m. 706.07
LABOUR PER sq.m. 70.60
MATERIAL :
CARRIAGE :
Bricks
1 KM BY MECH. TRANSPORT 1000 Nos. 550.0000 277.35 152.54
Hoop Iron
1 KM BY MECH. TRANSPORT 1 Tonne 0.096 73.95 7.10
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 541.56
Labour for cement mortar 1:3 28.58
TOTAL : 570.14
WATER CHARGES @ 1.5% : 54.59
TOTAL : 624.73
ADD FOR CONTRACTORS PROFIT @10% : 62.47
ADD FOR OVER HEAD CHARGES @5% : 31.24
LABOUR FOR 10.00 SQM 718.44
LABOUR PER sqm 71.85
MATERIAL :
CARRIAGE :
Bricks
1 KM BY MECH. TRANSPORT 1000 Nos. 550.0000 277.35 152.54
Hoop Iron
1 KM BY MECH. TRANSPORT 1 Tonne 0.096 73.95 7.10
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 541.56
Labour for cement mortar 1:3 28.58
TOTAL : 570.14
WATER CHARGES @ 1.5% : 52.94
TOTAL : 623.08
ADD FOR CONTRACTORS PROFIT @10% : 61.31
ADD FOR OVER HEAD CHARGES @5% : 31.16
LABOUR FOR 10.00 SQM 716.55
LABOUR PER sqm 71.65
LABOUR :
Mason 1st class Each 0.2000 211.16 42.23
Mason 2nd Class Each 0.2000 158.67 31.73
Beldar Each 0.4600 116.67 53.67
TOTAL : 138.63
ADD FOR WATER CHARGES @ 1.5% : 2.08
TOTAL : 140.71
ADD FOR CONTRACTORS PROFIT @ 10% 14.07
ADD FOR OVER HEAD CHARGES @5% : 7.04
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
COST FOR 10.000 sqm 161.82
COST PER sqm 16.18
LABOUR PER sqm 16.20
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 138.63
TOTAL : 138.63
WATER CHARGES @ 1.5% : 2.08
TOTAL : 140.71
ADD FOR CONTRACTORS PROFIT @10% : 14.07
ADD FOR OVER HEAD CHARGES @5% : 7.04
LABOUR FOR 10.00 SQM 161.82
LABOUR PER sqm 16.20
LABOUR :
Mason 1st class Each 0.1200 211.16 25.34
Mason 2nd Class Each 0.1200 158.67 19.04
Beldar Each 0.0800 116.67 9.33
TOTAL : 60.21
ADD FOR WATER CHARGES @ 1.5% : 0.90
TOTAL : 61.12
ADD FOR CONTRACTORS PROFIT @ 10% 6.11
ADD FOR OVER HEAD CHARGES @5% : 3.06
COST FOR 10.000 Rmt. 70.28
COST PER Rmt. 7.03
LABOUR PER Rmt. 7.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 60.21
TOTAL : 60.21
WATER CHARGES @ 1.5% : 0.90
TOTAL : 61.12
ADD FOR CONTRACTORS PROFIT @10% : 6.11
ADD FOR OVER HEAD CHARGES @5% : 3.06
LABOUR FOR 10.00 Rmt. 70.28
LABOUR PER Rmt. 7.00
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
10270100 Half brick thick honey comb brick
work with common burnt clay
building bricks in cement mortar
1:4 (1 cement : 4 sand)
First Class Bricks
Detail of cost for 1 sq.m
MATERIAL :
Brick Masonry
Rate as per item no. 10210701 1 cum 0.0660 3172.90 209.41 (-I-)
Extra for super-structure
Rate as per item no. 10020100 1 cum 0.0660 92.30 6.09 (-I-)
Extra for delay L.S 18.00
TOTAL : 233.50
ADD FOR WATER CHARGES @ 1.5% : 0.27
TOTAL : 233.77
ADD FOR CONTRACTORS PROFIT @ 10% except on (-I-) : 1.83
ADD FOR OVER HEAD CHARGES @5% except on (-I-) : 0.92
COST FOR 1.00 sqm. 236.52
COST PER sqm 236.52
LABOUR PER sqm. 63.95
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 18.00
Labour for 10210701 36.82 (-a-)
Labour for 10020101 6.09 (-a-)
TOTAL : 60.91
WATER CHARGES @ 1.5% : 0.27
TOTAL : 61.18
ADD FOR CONTRACTORS PROFIT @10% except on (-a-) : 1.83
ADD FOR OVER HEAD CHARGES @5% except on (-a-) : 0.92
LABOUR FOR 1.00 sqm 63.93
LABOUR PER Sqm. 63.95
MATERIAL :
Rate as per item no. 10210701 1 cum 0.0660 3040.00 200.64 (-I-)
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
Rate as per item no. 10220101 1 cum 0.0660 89.60 5.91 (-I-)
Extra for delay L.S 18.00
TOTAL : 224.55
ADD FOR WATER CHARGES @ 1.5% : 0.27
TOTAL : 224.82
ADD FOR CONTRACTORS PROFIT @ 10% except on (-I-) : 1.83
ADD FOR OVER HEAD CHARGES @5% except on (-I-) : 0.92
COST FOR 1.00 sqm. 227.57
COST PER sqm 227.55
LABOUR PER sqm. 63.95
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 18.00
Labour for 10210701 36.71 (-a-)
Labour for 10020101 5.91 (-a-)
TOTAL : 60.62
WATER CHARGES @ 1.5% : 0.27
TOTAL : 60.89
ADD FOR CONTRACTORS PROFIT @10% except on (-a-) : 1.83
ADD FOR OVER HEAD CHARGES @5% except on (-a-) : 0.92
LABOUR FOR 1.00 sqm 63.64
LABOUR PER Sqm. 63.95
MATERIAL :
CARRIAGE :
LABOUR :
For keeping the cavity clear and fixing
wall tiles & delay caused
Mason 1st class Each 0.3700 211.16 78.13
Mason 2nd Class Each 0.3700 158.67 58.71
Beldar Each 0.9200 116.67 107.34
TOTAL : 502.40
ADD FOR WATER CHARGES @ 1.5% : 7.54
TOTAL : 510.38
ADD FOR CONTRACTORS PROFIT @ 10% 51.04
ADD FOR OVER HEAD CHARGES @5% : 25.52
COST FOR 10.000 sqm 586.94
COST PER sqm 58.70
LABOUR PER sqm 28.95
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 244.17
TOTAL : 244.17
WATER CHARGES @ 1.5% : 7.54
TOTAL : 251.71
ADD FOR CONTRACTORS PROFIT @10% : 25.17
ADD FOR OVER HEAD CHARGES @5% : 12.59
LABOUR FOR 10.00 SQM 289.48
LABOUR PER sqm 28.95
MATERIAL :
CARRIAGE :
LABOUR :
For keeping the cavity clear and fixing
wall tiles & delay caused
Mason 1st class Each 0.3700 211.16 78.13
Mason 2nd Class Each 0.3700 158.67 58.71
Beldar Each 0.9200 116.67 107.34
TOTAL : 502.84
ADD FOR WATER CHARGES @ 1.5% : 7.54
TOTAL : 510.38
ADD FOR CONTRACTORS PROFIT @ 10% 51.04
ADD FOR OVER HEAD CHARGES @5% : 25.52
COST FOR 10.000 sqm 586.94
COST PER sqm 58.70
LABOUR PER sqm 28.95
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 244.18
TOTAL : 244.18
Add. WATER CHARGES @ 1.5% : 7.54
TOTAL : 251.72
ADD FOR CONTRACTORS PROFIT @10% : 25.17
ADD FOR OVER HEAD CHARGES @5% : 12.59
LABOUR FOR 10.00 SQM 289.48
LABOUR PER sqm 28.95
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
LABOUR :
TOTAL : 1142.21
ADD FOR WATER CHARGES @ 1.5% : 2.03
TOTAL : 1144.24
ADD FOR CONTRACTORS PROFIT @ 10% except on (-I-) : 13.74
ADD FOR OVER HEAD CHARGES @5% except on (-I-) : 6.87
COST FOR 10.00 metre. 1164.85
COST PER metre 116.50
LABOUR PER metre 25.35
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 51.38
Labour for 10240201 191.97 (-a-)
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 243.35
WATER CHARGES @ 1.5% : 2.03
TOTAL : 245.38
ADD FOR CONTRACTORS PROFIT @10% except on (-a-) : 5.34
ADD FOR OVER HEAD CHARGES @5% except on (-a-) : 2.67
LABOUR FOR 10.00 metre 253.39
LABOUR PER metre 25.35
MATERIAL :
LABOUR :
TOTAL : 1107.52
ADD FOR WATER CHARGES @ 1.5% : 2.03
TOTAL : 1109.55
ADD FOR CONTRACTORS PROFIT @ 10% except on (-I-) : 13.74
ADD FOR OVER HEAD CHARGES @5% except on (-I-) : 6.87
COST FOR 10.00 metre. 1130.16
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
COST PER metre 113.00
LABOUR PER metre 25.30
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 51.38
Labour for 10240201 191.43 (-a-)
TOTAL : 242.81
WATER CHARGES @ 1.5% : 2.03
TOTAL : 244.84
ADD FOR CONTRACTORS PROFIT @10% except on (-a-) : 5.34
ADD FOR OVER HEAD CHARGES @5% except on (-a-) : 2.67
LABOUR FOR 10.00 metre 252.85
LABOUR PER metre 25.30
MATERIAL :
TOTAL : 377.51
COST FOR 0.540 sq.m. 377.51
COST PER sq.m. 699.10
LABOUR PER sq.m. 192.20
LABOUR RATE :
Labour for 07020200 12.35
Labour for 09150200 37.60
Labour for 10210701 30.13
Labour for 17119010 23.70
LABOUR FOR 0.540 sq.m. 103.78
LABOUR PER sq.m. 192.20
MATERIAL :
Cement concrete1:5:10105x75x10cm
x0.079 (Rate as per item no.
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
09150200 of concrete work. 1 cum 0.0790 2115.60 167.13 (-I-)
TOTAL :
COST FOR 0.540 sq.m. 370.33
COST PER sq.m. 370.33
LABOUR PER sq.m. 685.80
192.00
LABOUR RATE :
Labour for 07020200
Labour for 09150200 12.35
Labour for 10210702 37.60
Labour for 17119010 30.03
LABOUR FOR 0.540 sq.m. 23.70
LABOUR PER sq.m. 103.68
192.00
MATERIAL :
Rate as per item no. 10220100 1 CUM 0.0450 89.60 4.03 (-I-)
LABOUR :
Cutting grooves 5cm. deep in
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
alternate course of old work
Mason 1st class Each 0.1800 211.16 38.00
Mason 2nd Class Each 0.1800 158.67 58.56
Beldar Each 0.1800 116.67 21.00
TOTAL : 234.37
ADD FOR WATER CHARGES @ 1.5% : 1.31
TOTAL : 235.68
ADD FOR CONTRACTORS PROFIT 8.89
10 % EXCEPT (-I-) :
ADD FOR OVER HEAD CHARGES @5% : 4.45
EXCEPT (-I-)
COST FOR 1.800 sq.m. 249.02
COST PER sq.m. 138.35
LABOUR PER sq.m. 72.95
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 87.56
Labour for 10210701 25.11 (-a-)
Labour for 10220101 4.03 (-a-)
TOTAL : 116.70
WATER CHARGES @ 1.5% : 1.31
TOTAL : 118.01
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a-): 8.82
ADD FOR OVER HEAD CHARGES @5% EXCEPT ON (-a-): 4.45
LABOUR FOR 1.800 sq.m. 131.35
LABOUR PER sq.m. 72.95
MATERIAL :
Rate as per item no. 10220101 1 CUM 0.0450 89.60 4.03 (-I-)
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR :
TOTAL : 228.39
ADD FOR WATER CHARGES @ 1.5% : 1.31
TOTAL : 229.70
ADD FOR CONTRACTORS PROFIT 8.89
10 % EXCEPT (-I-) :
ADD FOR OVER HEAD CHARGES @5% : 4.45
EXCEPT (-I-)
COST FOR 1.800 sq.m. 243.04
COST PER sq.m. 135.00
LABOUR PER sq.m. 72.75
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 87.56
Labour for 10210702 25.03 (-a-)
Labour for 10220101 4.03 (-a-)
TOTAL : 116.62
WATER CHARGES @ 1.5% : 1.31
TOTAL : 117.93
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a-): 8.89
ADD FOR OVER HEAD CHARGES @5% EXCEPT ON (-a-): 4.45
LABOUR FOR 1.800 sq.m. 131.27
LABOUR PER sq.m. 72.75
MATERIAL :
Rate as per item no. 10220101. 1 CUM 0.1000 89.60 8.96 (-I-)
Extra for spe.molded bric L.S 35.00
TOTAL : 361.25
ADD FOR WATER CHARGES @ 1.5% : 0.53
TOTAL : 361.78
ADD FOR CONTRACTORS PROFIT
10 % EXCEPT (-I-) : 3.55
ADD FOR OVER HEAD CHARGES @5% :
EXCEPT (-I-) 1.78
COST FOR 10.000 metre 367.11
COST PER metre 36.70
LABOUR PER metre 10.55
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 35.00
Labour for 10210701 55.80 (-a-)
Labour for 10220101 8.96 (-a-)
TOTAL : 99.76
WATER CHARGES @ 1.5% : 0.53
TOTAL : 100.29
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a-): 3.55
ADD FOR OVER HEAD CHARGES @5% EXCEPT ON (-a-): 1.78
LABOUR FOR 10.000 metre 105.62
LABOUR PER metre 10.55
MATERIAL :
Rate as per item no. 10220100. 1 CUM 0.1000 89.60 8.96 (-I-)
Extra for spe.molded brick L.S 35.00
TOTAL : 347.96
ADD FOR WATER CHARGES @ 1.5% : 0.53
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 348.49
ADD FOR CONTRACTORS PROFIT
10 % EXCEPT (-I-) : 3.55
ADD FOR OVER HEAD CHARGES @5% :
EXCEPT (-I-) 1.78
COST FOR 10.000 metres 353.82
COST PER metres 35.40
LABOUR PER metres 10.55
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 35.00
Labour for 10210702 55.62 (-a-)
Labour for 10220101 8.96 (-a-)
TOTAL : 99.58
WATER CHARGES @ 1.5% : 0.53
TOTAL : 100.11
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a-): 3.55
ADD FOR OVER HEAD CHARGES @5% EXCEPT ON (-a-): 1.78
LABOUR FOR 10.000 metres 105.62
LABOUR PER metres 10.55
MATERIAL :
Rate as per item no. 10220101. 1 CUM 0.1000 89.60 8.96 (-I-)
Extra for spe.molded brick L.S 35.00
TOTAL : 344.15
ADD FOR WATER CHARGES @ 1.5% : 0.53
TOTAL : 344.68
ADD FOR CONTRACTORS PROFIT
10 % EXCEPT (-I-) : 3.55
ADD FOR OVER HEAD CHARGES @5% :
EXCEPT (-I-) 1.78
COST FOR 10.000 metres 350.01
COST PER metres 35.00
LABOUR PER metres 10.55
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 35.00
Labour for 10210901 55.56 (-a-)
Labour for 10220101 8.96 (-a-)
TOTAL : 99.52
WATER CHARGES @ 1.5% : 0.53
TOTAL : 100.05
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a-): 3.55
ADD FOR OVER HEAD CHARGES @5% EXCEPT ON (-a-): 1.78
LABOUR FOR 10.000 metres 105.38
LABOUR PER metres 10.55
MATERIAL :
MATERIAL :
Rate as per item no. 10220101 1 CUM 0.1300 89.60 11.65 (-I-)
LABOUR :
Mason 1st class Each 0.3100 211.16 65.46
Mason 2nd Class Each 0.3100 158.67 49.19
TOTAL : 958.78
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR CONTRACTORS PROFIT
10 % EXCEPT (-I-) : 11.46
ADD FOR OVER HEAD CHARGES @5% :
EXCEPT (-I-) 5.73
COST FOR 10 metre 10 cm projection 20 cm 975.97
COST FOR 1 metre 1 cm projection 1 cm depth 0.50
LABOUR FOR 1 metre 1 cm projection 1 cm depth 0.20
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 114.65
Labour for 10210701 72.53 (-a-)
Labour for 10220101 11.65 (-a-)
Labour for 17047010 177.60
TOTAL : 376.43
TOTAL : 376.43
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a-): 11.46
ADD FOR OVER HEAD CHARGES @5% EXCEPT ON (-a-): 5.73
LABOUR FOR 10 metre 10 cm projection 20 cm depth 393.62
LABOUR FOR 1 metre 1 cm projection 1 cm depth 0.20
MATERIAL :
Rate as per item no. 10220100 1 CUM 0.1300 89.60 11.65 (-I-)
LABOUR :
Mason 1st class Each 0.3100 211.16 65.46
Mason 2nd Class Each 0.3100 158.67 49.19
TOTAL : 941.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 114.65
Labour for 10210702 72.30 (-a-)
Labour for 10220101 11.65 (-a-)
Labour for 17047010 177.60 (-a-)
TOTAL : 376.20
TOTAL : 376.20
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON 11.46
ADD FOR OVER HEAD CHARGES @5% EXCEPT ON 5.73
LABOUR FOR 10 metre 10 cm projection 20 cm depth 393.39
LABOUR FOR 1 metre 1 cm projection 1 cm depth 0.20
MATERIAL :
Rate as per item no. 10220101. 1 CUM 0.0500 89.60 4.48 (-I-)
LABOUR :
Mason 1st class Each 0.0200 211.16 4.22
Mason 2nd Class Each 0.0200 158.67 3.17
TOTAL : 172.52
ADD FOR WATER CHARGES @ 1.5% : 0.14
TOTAL : 172.66
ADD FOR CONTRACTORS PROFIT
10 % EXCEPT (-I-) : 0.95
ADD FOR OVER HEAD CHARGES @5% :
EXCEPT (-I-) 0.48
COST FOR 10.000 metres 174.09
COST PER metres 17.40
LABOUR PER metres 4.35
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 9.39
Labour for 10210701 27.90 (-a-)
Labour for 10220101 4.48 (-a-)
TOTAL : 41.77
WATER CHARGES @ 1.5% : 0.14
TOTAL : 41.91
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a-): 0.95
ADD FOR OVER HEAD CHARGES @5% EXCEPT ON (-a-): 0.48
LABOUR FOR 10.000 metres 43.34
LABOUR PER metres 4.35
MATERIAL :
Rate as per item no. 10220101. 1 CUM 0.0500 89.60 4.48 (-I-)
LABOUR :
Mason 1st class Each 0.0200 211.16 4.22
Mason 2nd Class Each 0.0200 158.67 3.17
TOTAL : 165.87
ADD FOR WATER CHARGES @ 1.5% : 0.14
TOTAL : 166.01
ADD FOR CONTRACTORS PROFIT
10 % EXCEPT (-I-) : 0.95
ADD FOR OVER HEAD CHARGES @5% :
EXCEPT (-I-) 0.48
COST FOR 10.000 metres 167.44
COST PER metres 16.75
LABOUR PER metres 4.35
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 9.39
Labour for 10210701 27.81 (-a-)
Labour for 10220101 4.48 (-a-)
TOTAL : 41.68
WATER CHARGES @ 1.5% : 0.14
TOTAL : 41.82
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a-): 0.95
ADD FOR OVER HEAD CHARGES @5% EXCEPT ON (-a-): 0.48
LABOUR FOR 10.000 metres 43.25
LABOUR PER metres 4.35
LABOUR :
Beldar Each 4.0000 116.67 466.68
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 466.68
ADD FOR WATER CHARGES @ 1.5% : 7.00
TOTAL : 473.68
ADD FOR CONTRACTORS PROFIT @10% : 47.37
ADD FOR OVER HEAD CHARGES @5% : 23.69
COST FOR 14 CUM per 0.3 metre depth 544.74
COST FOR 1 cum metre per metre depth 129.70
LABOUR FOR 1 metre 1 cm projection 1 cm depth 129.70
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 466.68
TOTAL : 466.68
WATER CHARGES @ 1.5% : 7.00
TOTAL : 473.68
ADD FOR CONTRACTORS PROFIT @10% : 47.37
ADD FOR OVER HEAD CHARGES @5% : 23.69
LABOUR FOR 14 CUM per 0.3 metre depth 544.74
LABOUR FOR 1 CUM metre per metre depth 129.70
LABOUR :
Beldar Each 4.0000 116.67 466.68
TOTAL : 466.68
ADD FOR WATER CHARGES @ 1.5% : 7.00
TOTAL : 473.68
ADD FOR CONTRACTORS PROFIT @10% : 47.37
ADD FOR OVER HEAD CHARGES @5% : 23.69
COST FOR 14 CUM per 0.3 metre depth 544.74
COST FOR 1 cum metre per metre depth 129.70
LABOUR FOR 1 metre 1 cm projection 1 cm depth 129.70
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 466.68
TOTAL : 466.68
WATER CHARGES @ 1.5% : 7.00
TOTAL : 473.68
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR CONTRACTORS PROFIT @10% : 47.37
ADD FOR OVER HEAD CHARGES @5% : 23.69
LABOUR FOR 14 CUM per 0.3 metre depth 544.74
LABOUR FOR 1 CUM metre per metre depth 129.70
LABOUR :
Extra labour due to slow progress
Mason 1st class Each 0.0200 211.16 4.22
Mason 2nd Class Each 0.0200 158.67 3.17
Beldar Each 0.2500 116.67 29.17
Bhishti Each 0.1500 116.67 17.50
SUNDRIES : 2.50
TOTAL : 56.56
ADD FOR WATER CHARGES @ 1.5% : 0.85
TOTAL : 57.41
ADD FOR CONTRACTORS PROFIT @10% : 5.74
ADD FOR OVER HEAD CHARGES @5% : 2.87
COST FOR 1.000 cum 66.02
COST PER cum 66.00
LABOUR PER cum 66.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 56.56
TOTAL : 56.56
WATER CHARGES @ 1.5% : 0.85
TOTAL : 57.41
ADD FOR CONTRACTORS PROFIT @10% : 5.74
ADD FOR OVER HEAD CHARGES @5% : 2.87
LABOUR FOR 1.000 cum 66.02
LABOUR PER cum 66.00
LABOUR :
Extra labour due to slow progress
Mason 1st class Each 0.0200 211.16 4.22
Mason 2nd Class Each 0.0200 158.67 3.17
Beldar Each 0.2500 116.67 29.17
Bhishti Each 0.1500 116.67 17.50
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
SUNDRIES : 2.50
TOTAL : 56.56
ADD FOR WATER CHARGES @ 1.5% : 0.85
TOTAL : 57.41
ADD FOR CONTRACTORS PROFIT @10% : 5.74
ADD FOR OVER HEAD CHARGES @5% : 2.87
COST FOR 1.000 cum 66.02
COST PER cum 66.00
LABOUR PER cum 66.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 56.56
TOTAL : 56.56
WATER CHARGES @ 1.5% : 0.85
TOTAL : 57.41
ADD FOR CONTRACTORS PROFIT @10% : 5.74
ADD FOR OVER HEAD CHARGES @5% : 2.87
LABOUR FOR 1.000 cum 66.02
LABOUR PER cum 66.00
MATERIAL :
CARRIAGE :
Bricks tiles.
1 KM BY MECH. TRANSPORT 1000 Nos. 950.0000 173.55 164.87
LABOUR :
SUNDRIES : 30.00
TOTAL : 4313.63
ADD FOR WATER CHARGES @ 1.5% : 64.70
TOTAL : 4378.33
ADD FOR CONTRACTORS PROFIT @10% : 437.83
ADD FOR OVER HEAD CHARGES @5% : 218.92
COST FOR 1.000 cum 5035.08
COST PER cum 5035.10
LABOUR PER cum 787.45
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 516.79
Labour for lime surkhi mortar 1:1:1 103.25
TOTAL : 620.04
WATER CHARGES @ 1.5% : 64.70
TOTAL : 684.74
ADD FOR CONTRACTORS PROFIT @10% : 68.47
ADD FOR OVER HEAD CHARGES @5% : 34.24
LABOUR FOR 1.000 cum 787.45
LABOUR PER cum 787.45
MATERIAL :
CARRIAGE :
Bricks tiles.
1 KM BY MECH. TRANSPORT 1000 Nos. 950.0000 173.55 164.87
LABOUR :
SUNDRIES : 30.00
TOTAL : 4399.71
ADD FOR WATER CHARGES @ 1.5% : 66.00
TOTAL : 4465.71
ADD FOR CONTRACTORS PROFIT @10% : 44657.00
ADD FOR OVER HEAD CHARGES @5% : 223.29
COST FOR 1.000 cum 5135.57
COST PER cum 5135.55
LABOUR PER cum 788.95
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 516.79
Labour for lime surkhi mortar 1:1:1 103.25
TOTAL : 620.04
WATER CHARGES @ 1.5% : 66.00
TOTAL : 686.04
ADD FOR CONTRACTORS PROFIT @10% : 68.40
ADD FOR OVER HEAD CHARGES @5% : 34.30
LABOUR FOR 1.000 cum 788.94
LABOUR PER cum 788.95
MATERIAL :
Common burnt clay Brick tiles. 1000 Nos 950.0000 3000.00 2850.00
CARRIAGE :
Bricks tiles.
1 KM BY MECH. TRANSPORT 1000 Nos. 950.0000 173.55 164.87
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 516.79
Labour for lime surkhi mortar 1:1:1 34.30
TOTAL : 551.09
WATER CHARGES @ 1.5% : 65.26
TOTAL : 616.35
ADD FOR CONTRACTORS PROFIT @10% : 61.64
ADD FOR OVER HEAD CHARGES @5% : 30.82
LABOUR FOR 1.000 cum 708.81
LABOUR PER cum 708.80
MATERIAL :
Common burnt clay bricks tiles 1000 Nos 950.0000 3000.00 2850.00
CARRIAGE :
Bricks tiles.
1 KM BY MECH. TRANSPORT 1000 Nos. 950.0000 173.55 164.87
LABOUR :
SUNDRIES : 30.00
TOTAL : 4155.15
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR WATER CHARGES @ 1.5% : 62.33
TOTAL : 4217.48
ADD FOR CONTRACTORS PROFIT @10% : 421.75
ADD FOR OVER HEAD CHARGES @5% : 210.88
COST FOR 1.000 cum 4850.11
COST PER cum 4850.10
LABOUR PER cum 705.45
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 516.79
Labour for lime surkhi mortar 1:1:1 34.30
TOTAL : 551.09
WATER CHARGES @ 1.5% : 62.33
TOTAL : 613.42
ADD FOR CONTRACTORS PROFIT @10% : 61.34
ADD FOR OVER HEAD CHARGES @5% : 30.67
LABOUR FOR 1.000 cum 705.43
LABOUR PER cum 705.45
LABOUR :
Mason 1st class Each 0.1200 211.16 25.34
Mason 2nd Class Each 0.1200 158.67 19.04
Beldar Each 0.3100 116.67 36.17
TOTAL : 91.55
ADD FOR WATER CHARGES @ 1.5% : 1.37
TOTAL : 92.92
ADD FOR CONTRACTORS PROFIT @10% : 9.29
ADD FOR OVER HEAD CHARGES @5% : 4.65
COST FOR 1.000 cum 106.86
COST PER cum 106.85
LABOUR PER cum 106.85
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 91.55
TOTAL : 91.55
WATER CHARGES @ 1.5% : 1.37
TOTAL : 92.92
ADD FOR CONTRACTORS PROFIT @10% : 9.29
ADD FOR OVER HEAD CHARGES @5% : 4.65
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR FOR 1.000 cum 106.86
LABOUR PER cum 106.85
LABOUR :
Mason 1st class Each 0.3700 211.16 78.13
Mason 2nd Class Each 0.3700 158.67 58.71
Beldar Each 0.3300 116.67 38.50
TOTAL : 175.34
ADD FOR WATER CHARGES @ 1.5% : 2.63
TOTAL : 177.97
ADD FOR CONTRACTORS PROFIT @10% : 17.80
ADD FOR OVER HEAD CHARGES @5% : 8.90
COST FOR 1.000 cum 204.67
COST PER cum 204.67
LABOUR PER cum 204.65
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 175.34
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 175.34
WATER CHARGES @ 1.5% : 2.63
TOTAL : 177.97
ADD FOR CONTRACTORS PROFIT @10% : 17.80
ADD FOR OVER HEAD CHARGES @5% : 8.90
LABOUR FOR 1.000 cum 204.67
LABOUR PER cum 604.65
MATERIAL :
CARRIAGE :
Bricks tiles.
1 KM BY MECH. TRANSPORT 1000 Nos. 67.0000 173.55 11.63
LABOUR :
TOTAL : 373.49
ADD FOR WATER CHARGES @ 1.5% : 5.60
TOTAL : 379.09
ADD FOR CONTRACTORS PROFIT @10% : 37.91
ADD FOR OVER HEAD CHARGES @5% : 18.96
COST FOR 1.000 cum 435.96
COST PER cum 435.95
LABOUR PER cum 186.55
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 156.61
TOTAL : 156.61
WATER CHARGES @ 1.5% : 5.60
TOTAL : 162.21
ADD FOR CONTRACTORS PROFIT @10% : 16.22
ADD FOR OVER HEAD CHARGES @5% : 8.11
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR FOR 1.000 cum 186.54
LABOUR PER cum 186.55
MATERIAL :
Common burnt clay brick tiles 1000 Nos 950.0000 3000.00 2850.00
CARRIAGE :
Bricks tiles.
1 KM BY MECH. TRANSPORT 1000 Nos. 950.0000 173.55 164.87
LABOUR :
Scaffolding 15.00
SUNDRIES : L.S. 27.50
TOTAL : 8163.95
ADD FOR WATER CHARGES @ 1.5% : 122.46
TOTAL : 8286.41
ADD FOR CONTRACTORS PROFIT @10% : 463.60
ADD FOR OVER HEAD CHARGES @5% : 231.80
COST FOR 1.000 cum 8981.81
COST PER cum 8981.80
LABOUR PER cum 1559.65
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 679.99
MATERIAL :
First Class machine made building bricks.
1000 Nos 520.0000 3500.00 1820.00
CARRIAGE :
Bricks
1 KM BY MECH. TRANSPORT 1000 Nos. 520.0000 277.35 144.22
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 496.77
TOTAL : 517.35
WATER CHARGES @ 1.5% : 46.28
TOTAL : 563.63
ADD FOR CONTRACTORS PROFIT @10% : 56.36
ADD FOR OVER HEAD CHARGES @5% : 28.18
LABOUR FOR 1.000 cum 648.17
LABOUR PER cum 648.20
MATERIAL :
Second Class machine made building 1000
bricks.Nos 520.0000 3200.00 1664.00
CARRIAGE :
Bricks
1 KM BY MECH. TRANSPORT 1000 Nos. 520.0000 277.35 144.22
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 496.77
TOTAL : 517.35
WATER CHARGES @ 1.5% : 43.95
TOTAL : 561.30
ADD FOR CONTRACTORS PROFIT @10% : 56.13
ADD FOR OVER HEAD CHARGES @5% : 28.07
LABOUR FOR 1.000 cum 645.50
LABOUR PER cum 645.50
MATERIAL :
First Class machine made building bricks.
1000 Nos 520.0000 3500.00 1820.00
CARRIAGE :
Bricks
1 KM BY MECH. TRANSPORT 1000 Nos. 520.0000 277.35 144.22
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 496.77
TOTAL : 517.35
WATER CHARGES @ 1.5% : 44.53
TOTAL : 561.88
ADD FOR CONTRACTORS PROFIT @10% : 56.18
ADD FOR OVER HEAD CHARGES @5% : 28.09
LABOUR FOR 1.000 cum 646.15
LABOUR PER cum 646.15
MATERIAL :
Second Class machine made building 1000
bricks.Nos 520.0000 3200.00 1664.00
CARRIAGE :
Bricks
1 KM BY MECH. TRANSPORT 1000 Nos. 520.0000 277.35 144.22
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 496.77
TOTAL : 517.35
WATER CHARGES @ 1.5% : 42.19
TOTAL : 559.54
ADD FOR CONTRACTORS PROFIT @10% : 55.95
ADD FOR OVER HEAD CHARGES @5% : 27.98
LABOUR FOR 1.000 cum 643.47
LABOUR PER cum 643.45
MATERIAL :
First Class machine made building bricks.
1000 Nos 520.0000 3500.00 1820.00
CARRIAGE :
Bricks
1 KM BY MECH. TRANSPORT 1000 Nos. 520.0000 277.35 144.22
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 496.77
TOTAL : 517.35
WATER CHARGES @ 1.5% : 43.58
TOTAL : 560.93
ADD FOR CONTRACTORS PROFIT @10% : 56.09
ADD FOR OVER HEAD CHARGES @5% : 28.05
LABOUR FOR 1.000 cum 645.07
LABOUR PER cum 645.05
MATERIAL :
Second Class machine made building 1000
bricks.Nos 520.0000 3200.00 1664.00
CARRIAGE :
Bricks
1 KM BY MECH. TRANSPORT 1000 Nos. 520.0000 277.35 144.22
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 496.77
TOTAL : 517.35
WATER CHARGES @ 1.5% : 41.24
TOTAL : 558.59
ADD FOR CONTRACTORS PROFIT @10% : 55.86
ADD FOR OVER HEAD CHARGES @5% : 27.93
LABOUR FOR 1.000 cum 642.38
LABOUR PER cum 642.40
MATERIAL :
First Class machine made building bricks.
1000 Nos 520.0000 3500.00 1820.00
CARRIAGE :
Bricks
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
1 KM BY MECH. TRANSPORT 1000 Nos. 520.0000 277.35 144.22
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 496.77
TOTAL : 517.35
WATER CHARGES @ 1.5% : 42.77
TOTAL : 560.12
ADD FOR CONTRACTORS PROFIT @10% : 56.01
ADD FOR OVER HEAD CHARGES @5% : 28.00
LABOUR FOR 1.000 cum 644.13
LABOUR PER cum 644.15
MATERIAL :
Second Class machine made building 1000
bricks.Nos 520.0000 3200.00 1664.00
CARRIAGE :
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
Bricks
1 KM BY MECH. TRANSPORT 1000 Nos. 520.0000 277.35 144.22
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 496.77
TOTAL : 517.35
WATER CHARGES @ 1.5% : 40.43
TOTAL : 557.78
ADD FOR CONTRACTORS PROFIT @10% : 55.78
ADD FOR OVER HEAD CHARGES @5% : 27.89
LABOUR FOR 1.000 cum 641.45
LABOUR PER cum 641.45
LABOUR :
TOTAL : 121.63
ADD FOR WATER CHARGES @ 1.5% : 1.82
TOTAL : 123.45
ADD FOR CONTRACTORS PROFIT @10% : 12.35
ADD FOR OVER HEAD CHARGES @5% : 6.18
COST FOR 1.000 cum 142.98
COST PER cum 142.00
LABOUR PER cum 142.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 121.63
WATER CHARGES @ 1.5% : 1.82
TOTAL : 123.45
ADD FOR CONTRACTORS PROFIT @10% : 12.35
ADD FOR OVER HEAD CHARGES @5% : 6.18
LABOUR FOR 1.000 cum 141.98
LABOUR PER cum 142.00
MATERIAL :
Extra bricks. 1000 Nos 142.0000 3500.00 497.00
CARRIAGE :
Bricks
1 KM BY MECH. TRANSPORT 1000 Nos. 142.0000 277.35 39.38
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
100 MTRS BY HEAD LOAD 1000 Nos 142.0000 101.45 14.41
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 278.89
MATERIAL :
Extra bricks. 1000 Nos 142.0000 3200.00 454.40
CARRIAGE :
Bricks
1 KM BY MECH. TRANSPORT 1000 Nos. 142.0000 277.35 39.38
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 278.89
MATERIAL :
Extra bricks. 1000 Nos 35.0000 3500.00 122.50
CARRIAGE :
Bricks
1 KM BY MECH. TRANSPORT 1000 Nos. 35.0000 277.35 9.71
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 102.72
MATERIAL :
Extra bricks. 1000 Nos 35.0000 3200.00 112.00
CARRIAGE :
Bricks
1 KM BY MECH. TRANSPORT 1000 Nos. 35.0000 277.35 9.71
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 102.72
MATERIAL :
Extra bricks. (Wastage 175 Nos) 1000 Nos 175.0000 3500.00 612.50
CARRIAGE :
Bricks
1 KM BY MECH. TRANSPORT 1000 Nos. 175.0000 277.35 48.54
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 685.35
MATERIAL :
Extra bricks. (Wastage 175 Nos) 1000 Nos 175.0000 3200.00 560.00
CARRIAGE :
Bricks
1 KM BY MECH. TRANSPORT 1000 Nos. 175.0000 277.35 48.54
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 685.35
MATERIAL :
First Class machine made building bricks
1000 Nos 550.0000 3500.00 1925.00
CARRIAGE :
Bricks
1 KM BY MECH. TRANSPORT 1000 Nos. 550.0000 277.35 152.54
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 675.19
Labour for cement mortar 1:3 22.86
TOTAL : 698.05
WATER CHARGES @ 1.5% : 51.66
TOTAL : 749.71
ADD FOR CONTRACTORS PROFIT @10% : 74.97
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR OVER HEAD CHARGES @5% : 37.49
LABOUR FOR 10.00 sqm 862.17
LABOUR PER Sqm 86.20
MATERIAL :
Second Class machine made building 1000
bricksNos 550.0000 3200.00 1760.00
CARRIAGE :
Bricks
1 KM BY MECH. TRANSPORT 1000 Nos. 550.0000 277.35 152.54
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 675.19
Labour for cement mortar 1:3 22.86
TOTAL : 698.05
WATER CHARGES @ 1.5% : 49.19
TOTAL : 747.24
ADD FOR CONTRACTORS PROFIT @10% : 74.72
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR OVER HEAD CHARGES @5% : 37.36
LABOUR FOR 10.00 sqm 859.32
LABOUR PER Sqm 85.90
MATERIAL :
First Class machine made building bricks
1000 Nos 550.0000 3500.00 1925.00
CARRIAGE :
Bricks
1 KM BY MECH. TRANSPORT 1000 Nos. 550.0000 277.35 152.54
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 675.19
Labour for cement mortar 1:4 22.86
TOTAL : 698.05
WATER CHARGES @ 1.5% : 49.71
TOTAL : 747.76
ADD FOR CONTRACTORS PROFIT @10% : 74.78
Brick Work
ITEM DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR OVER HEAD CHARGES @5% : 37.39
LABOUR FOR 10.00 sqm 859.93
LABOUR PER Sqm 86.00
MATERIAL :
Second Class machine made building 1000
bricksNos 550.0000 3200.00 1760.00
CARRIAGE :
Bricks
1 KM BY MECH. TRANSPORT 1000 Nos. 550.0000 277.35 152.54
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 675.19
Labour for cement mortar 1:4 22.86
TOTAL : 698.05
WATER CHARGES @ 1.5% : 47.24
TOTAL : 745.29
ADD FOR CONTRACTORS PROFIT @10% : 74.52
ADD FOR OVER HEAD CHARGES @5% : 37.26
LABOUR FOR 10.00 sqm 857.07
LABOUR PER Sqm 85.70
CHAPTER XI
1 The labour rates and through rates are applicable for the stones quarried in blocks
and un-dressed.
2 The rates include the carriage by head load up to 100 meters and by mechanical
transport up to first kilometer. The carriage rates for additional distance shall be
paid for separately.
3 The labour rates include the cost of water, tools and plants, labor and materials for
scaffolding and centering shuttering, Wherever required and cost of good earth
for mud mortar.
4 Where water is supplied free by the department, the rates shall be decreased
accordingly.
5 The labour rates including the cost of dressing of stones and laying also.
6 The rates are applicable for laying of stone in foundations and plinth \ floor level
two. The plinth level shall be taken as 1.5 meters above ground level. The
maximum story height shall be taken as 3 meters. In case of structures like
retaining walls / breast walls height of 4 meters above ground level shall be
reckoned as floor level two. This height shall be 6 meters above ground level in
case of piers and abutments. Similar procedure for demarcation of works done in
basement shall be adopted for increase of rates.
CHAPTER-XI
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
1101000000 Random rubble masonry/polygonal
rubble masonry (uncoursed/brought
to courses) in walls with hard
stones of approved quality in
foundation and plinth laid dry,well
bonded,faced with selected stones
and built with bond or through
stones evenly placed at the rate of
two per square metre.
Detail of cost for 1 cubic metre.
MATERIAL :
CARRIAGE :
Building stones.
1 KM BY MECH. TRANSPORT 1 Cum. 1.1600 120.05 139.26
LABOUR :
Mason 2nd Class Each 0.4200 158.67 66.64
Beldar Each 0.5800 116.67 99.17
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 174.31
TOTAL : 174.31
ADD FOR CONTRACTORS PROFIT @10% : 17.43
ADD FOR OVER HEAD CHARGES @5% : 8.72
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR FOR 1.000 cum 200.46
LABOUR PER cum 2.00.45
MATERIAL :
CARRIAGE :
Building stones.
1 KM BY MECH. TRANSPORT 1 Cum. 1.1600 120.05 139.26
LABOUR :
Mason 2nd Class Each 0.4200 158.67 66.64
Beldar Each 0.5800 116.67 99.17
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 174.31
TOTAL : 174.31
ADD FOR CONTRACTORS PROFIT @10% : 17.43
ADD FOR OVER HEAD CHARGES @5% : 8.72
LABOUR FOR 1.000 cum 200.46
LABOUR PER cum 2.00.45
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
1103000000 Random rubble masonry/polygonal
rubble uncoursed/brought to courses
with hard stone of approved quality
in foundation and plinth with mud
mortar including leveling up at
plinth level.
Detail of cost for 1 cubic metre.
MATERIAL :
CARRIAGE :
Building stones.
1 KM BY MECH. TRANSPORT 1 Cum. 1.1600 120.05 139.26
LABOUR :
Mason 2nd Class Each 1.7700 158.67 280.85
Beldar Each 2.1200 116.67 247.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 557.29
Labour for mud mortar: 36.75
TOTAL : 594.04
WATER CHARGES @ 1.5% : 20.11
TOTAL : 614.15
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR CONTRACTORS PROFIT @10% : 61.42
ADD FOR OVER HEAD CHARGES @5% : 30.71
LABOUR FOR 1.000 cum 706.28
LABOUR PER cum 706.30
MATERIAL :
CARRIAGE :
Building stone
1 KM BY MECH. TRANSPORT 1000 Nos.1.1600 120.05 139.26
LABOUR :
Mason 2nd Class Each 1.7700 158.67 280.85
Beldar Each 2.1200 116.67 247.34
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Bhishti Each 0.0900 116.67 10.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 568.19
Labour for lime surkhi mortar 1:1:1 113.58
TOTAL : 681.77
WATER CHARGES @ 1.5% : 31.17
TOTAL : 712.94
ADD FOR CONTRACTORS PROFIT @10% : 71.29
ADD FOR OVER HEAD CHARGES @5% : 35.65
LABOUR FOR 1.00 cum 819.88
LABOUR Per cum 819.90
MATERIAL :
CARRIAGE :
Building stone
1 KM BY MECH. TRANSPORT 1000 Nos.1.1600 120.05 139.26
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 568.19
Labour for cement mortar 1:6 37.73
TOTAL : 605.92
WATER CHARGES @ 1.5% : 28.56
TOTAL : 634.47
ADD FOR CONTRACTORS PROFIT @10% : 63.45
ADD FOR OVER HEAD CHARGES @5% : 31.72
LABOUR FOR 1.00 cum 729.64
LABOUR Per cum 729.60
MATERIAL :
CARRIAGE :
Building stone
1 KM BY MECH. TRANSPORT 1000 Nos.1.1600 120.05 139.26
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR :
Mason 2nd Class Each 1.7700 158.67 280.85
Beldar Each 2.1200 116.67 247.34
Bhishti Each 0.0900 116.67 10.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 568.19
Labour for cement lime mortar 1:1:8 113.58
TOTAL : 681.77
WATER CHARGES @ 1.5% : 30.35
TOTAL : 712.12
ADD FOR CONTRACTORS PROFIT @10% : 71.21
ADD FOR OVER HEAD CHARGES @5% : 35.61
LABOUR FOR 1.00 cum 818.93
LABOUR Per cum 818.95
MATERIAL :
CARRIAGE :
Building stone
1 KM BY MECH. TRANSPORT 1 cum 1.1600 120.05 139.26
LABOUR :
Mason 2nd Class Each 1.7700 158.67 280.85
Beldar Each 2.1200 116.67 247.34
Bhishti Each 0.0900 116.67 10.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 568.19
Labour for cement lime mortar 1:1:8 37.73
TOTAL : 605.92
WATER CHARGES @ 1.5% : 27.07
TOTAL : 632.99
ADD FOR CONTRACTORS PROFIT @10% : 63.30
ADD FOR OVER HEAD CHARGES @5% : 31.65
LABOUR FOR 1.00 cum 727.93
LABOUR Per cum 727.90
CARRIAGE :
Building stone
1 KM BY MECH. TRANSPORT 1 cum 1.1600 120.05 139.26
LABOUR :
Mason 2nd Class Each 1.7700 158.67 280.85
Beldar Each 2.1200 116.67 247.34
Bhishti Each 0.0900 116.67 10.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 568.19
Labour for cement lime mortar 1:1:8 37.73
TOTAL : 605.92
WATER CHARGES @ 1.5% : 28.35
TOTAL : 634.27
ADD FOR CONTRACTORS PROFIT @10% : 63.43
ADD FOR OVER HEAD CHARGES @5% : 31.71
LABOUR FOR 1.00 cum 729.41
LABOUR Per cum 729.40
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
1106010000 Extra for random rubble
masonry/polygonal rubble masonry
(uncoursed/brought to courses)
with hard stone of approved
quality in :-
LABOUR :
Mason 2nd Class Each 0.2700 158.67 42.84
Beldar Each 0.3800 116.67 44.33
TOTAL : 109.67
ADD FOR WATER CHARGES @ 1.5% : 1.65
TOTAL : 111.32
ADD FOR CONTRACTORS PROFIT @ 10% 11.13
ADD FOR OVER HEAD CHARGES @5% : 5.57
COST FOR 1.00 cum 128.02
COST PER cum 128.02
LABOUR PER cum 128.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 109.67
TOTAL : 109.67
WATER CHARGES @ 1.5% : 1.65
TOTAL : 111.32
ADD FOR CONTRACTORS PROFIT @10% : 11.13
ADD FOR OVER HEAD CHARGES @5% : 5.57
LABOUR FOR 1.00 cum 128.02
LABOUR Per cum 128.00
LABOUR :
Mason 2nd Class Each 0.5800 158.67 92.03
Beldar Each 0.2700 116.67 31.50
TOTAL : 123.53
ADD FOR WATER CHARGES @ 1.5% : 1.85
TOTAL : 125.38
ADD FOR CONTRACTORS PROFIT @ 10% 12.54
ADD FOR OVER HEAD CHARGES @5% : 6.27
COST FOR 1.00 cum 144.19
COST PER cum 144.19
LABOUR PER cum 144.20
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 123.53
TOTAL : 123.53
WATER CHARGES @ 1.5% : 1.85
TOTAL : 125.38
ADD FOR CONTRACTORS PROFIT @10% : 12.54
ADD FOR OVER HEAD CHARGES @5% : 6.27
LABOUR FOR 1.00 cum 144.19
LABOUR Per cum 144.20
MATERIAL :
CARRIAGE :
Building stone
1 KM BY MECH. TRANSPORT 1 cum 0.2900 120.05 34.81
LABOUR :
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Mason 2nd Class Each 1.4200 158.67 225.31
Beldar Each 0.3500 116.67 40.83
TOTAL : 434.00
ADD FOR WATER CHARGES @ 1.5% : 6.50
TOTAL : 440.50
ADD FOR CONTRACTORS PROFIT @ 10% 44.05
ADD FOR OVER HEAD CHARGES @5% : 22.02
COST FOR 1.00 cum 506.57
COST PER cum 506.55
LABOUR PER cum 313.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 266.15
TOTAL : 266.15
WATER CHARGES @ 1.5% : 6.50
TOTAL : 272.65
ADD FOR CONTRACTORS PROFIT @10% : 27.26
ADD FOR OVER HEAD CHARGES @5% : 13.63
LABOUR FOR 1.00 cum 313.54
LABOUR Per cum 313.50
MATERIAL :
CARRIAGE :
Building stone
1 KM BY MECH. TRANSPORT 1 cum 0.1000 120.05 12.01
LABOUR :
Mason 2nd Class Each 0.2700 158.67 42.84
Beldar Each 0.5300 116.67 61.84
TOTAL : 162.56
ADD FOR WATER CHARGES @ 1.5% : 2.43
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 164.99
ADD FOR CONTRACTORS PROFIT @ 10% 16.50
ADD FOR OVER HEAD CHARGES @5% : 8.25
COST FOR 1.00 cum 189.73
COST PER cum 189.70
LABOUR PER cum 123.20
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 104.68
TOTAL : 104.68
WATER CHARGES @ 1.5% : 2.43
TOTAL : 107.11
ADD FOR CONTRACTORS PROFIT @10% : 10.71
ADD FOR OVER HEAD CHARGES @5% : 5.36
LABOUR FOR 1.00 cum 123.17
LABOUR Per cum 123.20
MATERIAL :
CARRIAGE :
Building stones.
1 KM BY MECH. TRANSPORT 1 Cum. 1.3700 120.05 164.47
LABOUR :
Stone dresser for ordianry Each 2.8300 158.67 449.04
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Mason 1st Class Each 1.0600 211.16 223.83
Mason 2nd Class Each 1.0600 158.67 168.19
Beldar Each 2.6500 116.67 309.18
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1210.73
Labour for mud mortar: 36.75
TOTAL : 1247.48
WATER CHARGES @ 1.5% : 33.55
TOTAL : 1281.03
ADD FOR CONTRACTORS PROFIT @10% : 128.10
ADD FOR OVER HEAD CHARGES @5% : 64.05
LABOUR FOR 1.000 cum 1473.19
LABOUR PER cum 1473.20
MATERIAL :
CARRIAGE :
Building stones.
1 KM BY MECH. TRANSPORT 1 Cum. 1.3700 120.05 164.47
LABOUR :
Stone dresser for ordianry Each 2.8300 158.67 449.04
Mason 1st Class Each 1.0600 211.16 223.83
Mason 2nd Class Each 1.0600 158.67 168.19
Beldar Each 2.6500 116.67 309.18
Bhishti Each 0.0900 116.67 10.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1221.73
Labour for lime surkhi mortar 1:1:1 103.25
TOTAL : 1324.98
WATER CHARGES @ 1.5% : 42.95
TOTAL : 1367.93
ADD FOR CONTRACTORS PROFIT @10% : 136.79
ADD FOR OVER HEAD CHARGES @5% : 68.40
LABOUR FOR 1.000 cum 1573.12
LABOUR PER cum 1573.15
MATERIAL :
CARRIAGE :
Building stones.
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
1 KM BY MECH. TRANSPORT 1 Cum. 1.3700 120.05 164.47
LABOUR :
Stone dresser for ordianry Each 2.8300 158.67 449.04
Mason 1st Class Each 1.0600 211.16 223.83
Mason 2nd Class Each 1.0600 158.67 168.19
Beldar Each 2.6500 116.67 309.18
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1210.73
Labour for cement lime mortar 1:1:8 103.25
TOTAL : 1313.98
WATER CHARGES @ 1.5% : 42.05
TOTAL : 1356.03
ADD FOR CONTRACTORS PROFIT @10% : 135.60
ADD FOR OVER HEAD CHARGES @5% : 67.80
LABOUR FOR 1.000 cum 1559.44
LABOUR PER cum 1559.45
MATERIAL :
CARRIAGE :
Building stones.
1 KM BY MECH. TRANSPORT 1 Cum. 1.3700 120.05 164.47
LABOUR :
Stone dresser for ordianry Each 2.8300 158.67 449.04
Mason 1st Class Each 1.0600 211.16 223.83
Mason 2nd Class Each 1.0600 158.67 168.19
Beldar Each 2.6500 116.67 309.18
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1210.73
Labour for cement lime mortar 1:6 34.30
TOTAL : 1245.03
WATER CHARGES @ 1.5% : 40.41
TOTAL : 1285.44
ADD FOR CONTRACTORS PROFIT @10% : 128.54
ADD FOR OVER HEAD CHARGES @5% : 64.27
LABOUR FOR 1.000 cum 1478.26
LABOUR PER cum 1478.30
MATERIAL :
CARRIAGE :
Building stones.
1 KM BY MECH. TRANSPORT 1 Cum. 1.3700 120.05 164.47
LABOUR :
Stone dresser for ordianry Each 2.8300 158.67 449.04
Mason 1st Class Each 1.0600 211.16 223.83
Mason 2nd Class Each 1.0600 158.67 168.19
Beldar Each 2.6500 116.67 309.18
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1210.73
Labour for cement lime mortar 1:5 34.30
TOTAL : 1245.03
WATER CHARGES @ 1.5% : 41.76
TOTAL : 1286.79
ADD FOR CONTRACTORS PROFIT @10% : 128.68
ADD FOR OVER HEAD CHARGES @5% : 64.34
LABOUR FOR 1.000 cum 1479.81
LABOUR PER cum 1479.80
CARRIAGE :
Building stones.
1 KM BY MECH. TRANSPORT 1 Cum. 1.3700 120.05 164.47
LABOUR :
Stone dresser for ordianry Each 2.8300 158.67 449.04
Mason 1st Class Each 1.0600 211.16 223.83
Mason 2nd Class Each 1.0600 158.67 168.19
Beldar Each 2.6500 116.67 309.18
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1210.73
Labour for cement lime mortar 1:4 34.30
TOTAL : 1245.03
WATER CHARGES @ 1.5% : 43.34
TOTAL : 1288.37
ADD FOR CONTRACTORS PROFIT @10% : 128.84
ADD FOR OVER HEAD CHARGES @5% : 64.42
LABOUR FOR 1.000 cum 1481.63
LABOUR PER cum 1481.65
MATERIAL :
CARRIAGE :
Building stones.
1 KM BY MECH. TRANSPORT 1 Cum. 1.3700 120.05 164.47
LABOUR :
Stone dresser for ordianry Each 2.8300 158.67 449.04
Mason 1st Class Each 1.0600 211.16 223.83
Mason 2nd Class Each 1.0600 158.67 168.19
Beldar Each 2.6500 116.67 309.18
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1210.73
Labour for cement lime mortar 1:3 34.30
TOTAL : 1245.03
WATER CHARGES @ 1.5% : 46.27
TOTAL : 1291.30
ADD FOR CONTRACTORS PROFIT @10% : 129.13
ADD FOR OVER HEAD CHARGES @5% : 64.57
LABOUR FOR 1.000 cum 1485.00
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR PER cum 1485.00
MATERIAL :
CARRIAGE :
Building stones.
1 KM BY MECH. TRANSPORT 1 Cum. 1.3700 120.05 164.47
LABOUR :
Stone dresser for ordianry Each 2.8300 158.67 449.04
Mason 1st Class Each 1.0600 211.16 223.83
Mason 2nd Class Each 1.0600 158.67 168.19
Beldar Each 2.6500 116.67 309.18
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1210.73
Labour for cement lime mortar 1:8 34.30
TOTAL : 1245.03
WATER CHARGES @ 1.5% : 39.06
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 1284.09
ADD FOR CONTRACTORS PROFIT @10% : 128.41
ADD FOR OVER HEAD CHARGES @5% : 64.20
LABOUR FOR 1.000 cum 1476.71
LABOUR PER cum 1476.70
MATERIAL :
CARRIAGE :
Building stones.
1 KM BY MECH. TRANSPORT 1 Cum. 1.3700 120.05 164.47
LABOUR :
Stone dresser for ordianry Each 0.6700 158.67 106.31
Mason 1st Class Each 0.2500 211.16 52.79
Mason 2nd Class Each 0.2500 158.67 39.67
Beldar Each 1.0600 116.67 123.67
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 338.94
TOTAL : 338.94
WATER CHARGES @ 1.5% : 18.88
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 357.82
ADD FOR CONTRACTORS PROFIT @10% : 35.78
ADD FOR OVER HEAD CHARGES @5% : 17.89
LABOUR FOR 1.000 cum 411.49
LABOUR PER cum 411.50
MATERIAL :
CARRIAGE :
Building stones.
1 KM BY MECH. TRANSPORT 1 Cum. 1.3700 120.05 164.47
LABOUR :
Stone dresser for ordianry Each 0.8500 158.67 134.87
Mason 1st Class Each 0.3200 211.16 67.57
Mason 2nd Class Each 0.3200 158.67 50.77
Beldar Each 2.6500 116.67 309.18
Bhishti Each 0.0900 116.67 10.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 633.89
Labour for lime surkhi mortar 1:1:1 103.25
TOTAL : 737.14
WATER CHARGES @ 1.5% : 34.13
TOTAL : 771.27
ADD FOR CONTRACTORS PROFIT @10% : 77.13
ADD FOR OVER HEAD CHARGES @5% : 38.56
LABOUR FOR 1.000 cum 886.96
LABOUR PER cum 886.95
MATERIAL :
CARRIAGE :
Building stones.
1 KM BY MECH. TRANSPORT 1 Cum. 1.3700 120.05 164.47
LABOUR :
Stone dresser for ordianry Each 0.8500 158.67 134.87
Mason 1st Class Each 0.3200 211.16 67.57
Mason 2nd Class Each 0.3200 158.67 50.77
Beldar Each 2.6500 116.67 309.18
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
SUNDRIES : L.S 60.50
TOTAL : 2215.43
ADD FOR WATER CHARGES @ 1.5% 33.23
TOTAL : 2248.66
ADD FOR CONTRACTORS PROFIT 10% 224.87
ADD FOR OVER HEAD CHARGES @5% 112.43
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 622.89
Labour for cement lime mortar 1:1:8 103.25
TOTAL : 726.14
WATER CHARGES @ 1.5% : 33.23
TOTAL : 759.37
ADD FOR CONTRACTORS PROFIT @10% : 75.94
ADD FOR OVER HEAD CHARGES @5% : 37.97
LABOUR FOR 1.000 cum 873.28
LABOUR PER cum 873.30
MATERIAL :
CARRIAGE :
Building stones.
1 KM BY MECH. TRANSPORT 1 Cum. 1.3700 120.05 164.47
LABOUR :
Stone dresser for ordianry Each 0.8500 158.67 134.87
Mason 1st Class Each 0.3200 211.16 67.57
Mason 2nd Class Each 0.3200 158.67 50.77
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Beldar Each 2.6500 116.67 309.18
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 622.89
Labour for cement mortar 1:6 34.30
TOTAL : 657.19
WATER CHARGES @ 1.5% : 31.59
TOTAL : 688.78
ADD FOR CONTRACTORS PROFIT @10% : 68.88
ADD FOR OVER HEAD CHARGES @5% : 34.44
LABOUR FOR 1.000 cum 792.10
LABOUR PER cum 792.10
MATERIAL :
CARRIAGE :
Building stones.
1 KM BY MECH. TRANSPORT 1 Cum. 1.3700 120.05 164.47
LABOUR :
Stone dresser for ordianry Each 0.8500 158.67 134.87
Mason 1st Class Each 0.3200 211.16 67.57
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Mason 2nd Class Each 0.3200 158.67 50.77
Beldar Each 2.6500 116.67 309.18
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 622.89
Labour for cement mortar 1:5 34.30
TOTAL : 657.19
WATER CHARGES @ 1.5% : 32.94
TOTAL : 690.13
ADD FOR CONTRACTORS PROFIT @10% : 69.01
ADD FOR OVER HEAD CHARGES @5% : 34.51
LABOUR FOR 1.000 cum 793.65
LABOUR PER cum 793.65
MATERIAL :
CARRIAGE :
Building stones.
1 KM BY MECH. TRANSPORT 1 Cum. 1.3700 120.05 164.47
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 622.89
Labour for cement mortar 1:4 34.30
TOTAL : 657.19
WATER CHARGES @ 1.5% : 34.52
TOTAL : 691.71
ADD FOR CONTRACTORS PROFIT @10% : 69.17
ADD FOR OVER HEAD CHARGES @5% : 34.59
LABOUR FOR 1.000 cum 795.47
LABOUR PER cum 795.45
MATERIAL :
CARRIAGE :
Building stones.
1 KM BY MECH. TRANSPORT 1 Cum. 1.3700 120.05 164.47
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
100 MTRS BY HEAD LOAD 1 cum 1.3700 58.75 80.49
LABOUR :
Stone dresser for ordianry Each 0.8500 158.67 134.87
Mason 1st Class Each 0.3200 211.16 67.57
Mason 2nd Class Each 0.3200 158.67 50.77
Beldar Each 2.6500 116.67 309.18
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 622.89
Labour for cement mortar 1:3 34.30
TOTAL : 657.19
WATER CHARGES @ 1.5% : 37.45
TOTAL : 694.64
ADD FOR CONTRACTORS PROFIT @10% : 69.46
ADD FOR OVER HEAD CHARGES @5% : 34.73
LABOUR FOR 1.000 cum 798.84
LABOUR PER cum 798.85
MATERIAL :
CARRIAGE :
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Building stones.
1 KM BY MECH. TRANSPORT 1 Cum. 1.3700 120.05 164.47
LABOUR :
Stone dresser for ordianry Each 0.8500 158.67 134.87
Mason 1st Class Each 0.3200 211.16 67.57
Mason 2nd Class Each 0.3200 158.67 50.77
Beldar Each 2.6500 116.67 309.18
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 622.89
Labour for cement mortar 1:8 34.30
TOTAL : 657.19
WATER CHARGES @ 1.5% : 30.24
TOTAL : 687.43
ADD FOR CONTRACTORS PROFIT @10% : 68.74
ADD FOR OVER HEAD CHARGES @5% : 34.37
LABOUR FOR 1.000 cum 790.55
LABOUR PER cum 790.55
MATERIAL :
CARRIAGE :
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Building stones.
1 KM BY MECH. TRANSPORT 1 Cum. 1.3700 120.05 164.47
LABOUR :
Stone dresser for ordianry Each 0.2000 158.67 31.73
Mason 1st Class Each 0.1000 211.16 21.12
Mason 2nd Class Each 0.1000 158.67 15.87
Beldar Each 1.0600 116.67 123.67
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 208.89
TOTAL : 208.89
WATER CHARGES @ 1.5% : 16.93
TOTAL : 225.82
ADD FOR CONTRACTORS PROFIT @10% : 22.58
ADD FOR OVER HEAD CHARGES @5% : 11.29
LABOUR FOR 1.000 cum 259.69
LABOUR PER cum 259.70
LABOUR :
Mason 2nd Class Each 0.2500 158.67 39.67
Beldar Each 0.3500 116.67 40.83
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 103.00
ADD FOR WATER CHARGES @ 1.5% 1.55
TOTAL : 104.55
ADD FOR CONTRACTORS PROFIT 10% 10.45
ADD FOR OVER HEAD CHARGES @5% 5.23
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 103.00
TOTAL : 103.00
WATER CHARGES @ 1.5% : 1.55
TOTAL : 104.55
ADD FOR CONTRACTORS PROFIT @10% : 10.46
ADD FOR OVER HEAD CHARGES @5% : 5.23
LABOUR FOR 1.000 cum 120.23
LABOUR PER cum 120.25
LABOUR :
Mason 2nd Class Each 0.6700 158.67 106.31
Beldar Each 0.2700 116.67 31.50
TOTAL : 137.81
ADD FOR WATER CHARGES @ 1.5% 2.07
TOTAL : 139.88
ADD FOR CONTRACTORS PROFIT 10% 13.99
ADD FOR OVER HEAD CHARGES @5% 6.99
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 137.81
TOTAL : 137.81
WATER CHARGES @ 1.5% : 2.07
TOTAL : 139.88
ADD FOR CONTRACTORS PROFIT @10% : 13.99
ADD FOR OVER HEAD CHARGES @5% : 6.99
LABOUR FOR 1.000 cum 160.86
LABOUR PER cum 160.90
MATERIAL :
CARRIAGE :
Building stones.
1 KM BY MECH. TRANSPORT 1 Cum. 0.3200 120.05 38.42
LABOUR :
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Mason 2nd Class Each 1.6700 158.67 264.98
Beldar Each 0.3500 116.67 40.83
TOTAL : 523.03
ADD FOR WATER CHARGES @ 1.5% 7.85
TOTAL : 530.87
ADD FOR CONTRACTORS PROFIT 10% 53.09
ADD FOR OVER HEAD CHARGES @5% 26.54
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 305.81
TOTAL : 305.81
WATER CHARGES @ 1.5% : 7.85
TOTAL : 313.66
ADD FOR CONTRACTORS PROFIT @10% : 31.37
ADD FOR OVER HEAD CHARGES @5% : 15.68
LABOUR FOR 1.000 cum 360.71
LABOUR PER cum 360.70
MATERIAL :
CARRIAGE :
Building stones.
1 KM BY MECH. TRANSPORT 1 Cum. 0.1100 120.05 13.21
LABOUR :
TOTAL : 188.86
ADD FOR WATER CHARGES @ 1.5% 2.83
TOTAL : 191.70
ADD FOR CONTRACTORS PROFIT @10% 19.17
ADD FOR OVER HEAD CHARGES @5% 9.58
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 114.20
TOTAL : 114.20
WATER CHARGES @ 1.5% : 2.83
TOTAL : 117.03
ADD FOR CONTRACTORS PROFIT @10% : 11.70
ADD FOR OVER HEAD CHARGES @5% : 5.85
LABOUR FOR 1.000 cum 134.58
LABOUR PER cum 134.60
MATERIAL :
CARRIAGE :
LABOUR :
TOTAL : 71.14
ADD FOR WATER CHARGES @ 1.5% 1.07
TOTAL : 72.21
ADD FOR CONTRACTORS PROFIT 10% 7.22
ADD FOR OVER HEAD CHARGES @5% 3.61
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 58.01
TOTAL : 58.01
WATER CHARGES @ 1.5% : 1.07
TOTAL : 59.08
ADD FOR CONTRACTORS PROFIT @10% : 5.91
ADD FOR OVER HEAD CHARGES @5% : 2.95
LABOUR FOR 10.000 cu.dm 67.94
LABOUR PER cum 6795.00
MATERIAL :
CARRIAGE :
LABOUR :
TOTAL : 65.02
ADD FOR WATER CHARGES @ 1.5% 0.98
TOTAL : 65.99
ADD FOR CONTRACTORS PROFIT 10% 6.60
ADD FOR OVER HEAD CHARGES @5% 3.30
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 51.89
TOTAL : 51.89
WATER CHARGES @ 1.5% : 0.97
TOTAL : 52.86
ADD FOR CONTRACTORS PROFIT @10% : 5.29
ADD FOR OVER HEAD CHARGES @5% : 2.64
LABOUR FOR 10.000 cu.dm 60.79
LABOUR PER cum 6078.00
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
TOTAL : 79.00
Add for water charges @1.5% Except on (-I-) : 0.34
Total : 79.34
ADD FOR CONTRACTORS PROFIT @10% Except on (-I-): 2.33
ADD FOR OVER HEAD CHARGES @5% Except on (-I-): 1.17
COST FOR 6.750 cu.dm 82.84
COST PER cum 12272.60
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES
Extra Labour for making cornices : 22.95
Labour As per item no :1109010000 45.87 (-a-)
TOTAL : 68.82
Add for water charges : 0.34
TOTAL : 69.16
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a-): 2.33
ADD FOR OVER HEAD CHARGES @5% EXCEPT ON (-a-): 1.17
LABOUR FOR 6.750 cu.dm 72.66
LABOUR PER cum 10764.45
MATERIAL :
CARRIAGE :
LABOUR :
Dressing charges Rate as per item no. : 111604000 75.40
TOTAL : 110.81
ADD FOR WATER CHARGES @ 1.5% : 1.66
TOTAL : 112.47
ADD FOR CONTRACTORS PROFIT 10% 11.24
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 100.88
TOTAL : 100.88
WATER CHARGES @ 1.5% : 1.66
TOTAL : 102.54
ADD FOR CONTRACTORS PROFIT @10% : 10.25
ADD FOR OVER HEAD CHARGES @5% : 5.13
LABOUR FOR 10.000 cu.dm 117.92
LABOUR PER cum 11792.00
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR :
Rate as per item no. : 0801050200 sq.m 279.50
Two Level.
Taking each floor to be of average
0.1% cost of work 0.1x3/0.3=1%
LABOUR :
Labour charges extra L.S 10.00
TOTAL : 10.00
ADD FOR WATER CHARGES @ 1.5% 0.15
TOTAL : 10.15
ADD FOR CONTRACTORS PROFIT 10% 1.02
ADD FOR OVER HEAD CHARGES @5% 0.51
TOTAL : 10.00
WATER CHARGES @ 1.5% : 0.15
TOTAL : 10.15
ADD FOR CONTRACTORS PROFIT @10% : 1.02
ADD FOR OVER HEAD CHARGES @5% : 0.51
LABOUR FOR 10.000 cu.dm 11.67
LABOUR PER cum 1168.00
LABOUR :
Labour charges L.S 30.50
TOTAL : 30.50
ADD FOR WATER CHARGES @ 1.5% 0.46
TOTAL : 30.96
ADD FOR CONTRACTORS PROFIT 10% 3.10
ADD FOR OVER HEAD CHARGES @5% 1.55
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 30.50
TOTAL : 30.50
WATER CHARGES @ 1.5% : 0.46
TOTAL : 30.96
ADD FOR CONTRACTORS PROFIT @10% : 3.10
ADD FOR OVER HEAD CHARGES @5% : 1.55
LABOUR FOR 10.000 cu.dm 35.60
LABOUR PER cum 3561.00
LABOUR :
labour charges L.S 7.00
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 7.00
ADD FOR WATER CHARGES @ 1.5% 0.11
TOTAL : 7.11
ADD FOR CONTRACTORS PROFIT 10% 0.71
ADD FOR OVER HEAD CHARGES @5% 0.36
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 7.00
TOTAL : 7.00
WATER CHARGES @ 1.5% : 0.11
TOTAL : 7.11
ADD FOR CONTRACTORS PROFIT @10% : 0.71
ADD FOR OVER HEAD CHARGES @5% : 0.36
LABOUR FOR 10.000 cu.dm 8.18
LABOUR PER cum 818.00
LABOUR :
Labour L.S 13.00
TOTAL : 13.00
ADD FOR WATER CHARGES @ 1.5% 0.20
TOTAL : 13.20
ADD FOR CONTRACTORS PROFIT @10% 1.32
ADD FOR OVER HEAD CHARGES @5% 0.66
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 13.00
TOTAL : 13.00
WATER CHARGES @ 1.5% : 0.20
TOTAL : 13.20
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR CONTRACTORS PROFIT @10% : 1.32
ADD FOR OVER HEAD CHARGES @5% : 0.66
LABOUR FOR 10.000 cu.dm 15.18
LABOUR PER cum 1518.00
1115010200 Cornices.
Details of cost for a cornices
30cm. long,60cm. deep and 15cm.
projection:
LABOUR :
Mason 1st class Each 0.500 211.16 105.58
Beldar Each 0.7500 116.67 87.50
TOTAL : 193.08
ADD FOR WATER CHARGES @ 1.5% : 2.90
TOTAL : 195.98
ADD FOR CONTRACTORS PROFIT @10% : 19.60
ADD FOR OVER HEAD CHARGES @5% : 9.80
COST FOR 10.000 cu.dm 225.38
COST PER cm girth per metre 10.00
LABOUR per cm girth per metre 10.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 193.08
TOTAL : 193.08
WATER CHARGES @ 1.5% : 2.90
TOTAL : 195.98
ADD FOR CONTRACTORS PROFIT @10% : 19.60
ADD FOR OVER HEAD CHARGES @5% : 9.80
LABOUR FOR 10.000 cu.dm 225.38
LABOUR PER cm girth per metre 10.00
LABOUR :
Labour L.S 37.00
TOTAL : 37.00
ADD FOR WATER CHARGES @ 1.5% 0.56
TOTAL : 37.56
ADD FOR CONTRACTORS PROFIT 10% 3.76
ADD FOR OVER HEAD CHARGES @5% 1.88
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
COST FOR 10.000 cu.dm 43.20
COST PER cum 4320.00
LABOUR PER cum 4320.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 37.00
TOTAL : 37.00
WATER CHARGES @ 1.5% : 0.56
TOTAL : 37.56
ADD FOR CONTRACTORS PROFIT @10% : 3.76
ADD FOR OVER HEAD CHARGES @5% : 1.88
LABOUR FOR 10.000 cu.dm 43.20
LABOUR PER cum 4320.00
LABOUR :
Stone Dresser For ordinary Each 2.830 158.67 449.04
TOTAL : 449.04
ADD FOR CONTRACTORS PROFIT 10% 44.90
ADD FOR OVER HEAD CHARGES @5% 22.45
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 449.04
TOTAL : 449.04
ADD FOR CONTRACTORS PROFIT @10% : 44.90
ADD FOR OVER HEAD CHARGES @5% : 22.45
LABOUR FOR 1.00 cum 516.39
LABOUR PER cum 516.40
LABOUR :
Mason 1st class Each 0.0880 211.16 18.58
Black smith 1st class Each 0.0060 186.67 1.12
Beldar Each 0.0660 116.67 7.70
Bandhani Each 0.04400 116.67 5.13
TOTAL : 32.54
ADD FOR CONTRACTORS PROFIT @ 10% 3.25
ADD FOR OVER HEAD CHARGES @5% : 1.63
COST FOR 10.00 cu.dm 37.41
COST PER cum 3741.00
LABOUR PER cum 3741.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 32.54
TOTAL : 32.54
ADD FOR CONTRACTORS PROFIT @10% : 3.25
ADD FOR OVER HEAD CHARGES @5% : 1.63
LABOUR FOR 10.00 cu.dm 37.41
LABOUR PER cum 3741.00
LABOUR :
Mason 1st class Each 0.0590 211.16 12.46
Black smith 1st class Each 0.0060 186.67 1.12
Beldar Each 0.0660 116.67 7.70
Bandhani Each 0.04400 116.67 5.13
TOTAL : 26.41
ADD FOR CONTRACTORS PROFIT @ 10% 2.64
ADD FOR OVER HEAD CHARGES @5% : 1.32
COST FOR 10.00 cu.dm 30.37
COST PER cum 3037.00
LABOUR PER cum 3037.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 26.41
TOTAL : 26.41
ADD FOR CONTRACTORS PROFIT @10% : 2.64
ADD FOR OVER HEAD CHARGES @5% : 1.32
LABOUR FOR 10.00 cu.dm 30.37
LABOUR PER cum 3037.00
LABOUR :
Mason 1st class Each 0.2910 211.16 61.45
Black smith 1st class Each 0.0060 186.67 1.12
Beldar Each 0.0660 116.67 7.70
Bandhani Each 0.04400 116.67 5.13
TOTAL : 75.40
ADD FOR CONTRACTORS PROFIT @ 10% 7.54
ADD FOR OVER HEAD CHARGES @5% : 3.77
COST FOR 10.00 cu.dm 86.71
COST PER cum 8671.00
LABOUR PER cum 8671.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 75.40
TOTAL : 75.40
ADD FOR CONTRACTORS PROFIT @10% : 7.54
ADD FOR OVER HEAD CHARGES @5% : 3.77
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR FOR 10.00 cu.dm 86.71
LABOUR PER cum 8671.00
LABOUR :
Mason 1st class Each 0.1760 211.16 37.16
Black smith 1st class Each 0.0060 186.67 1.12
Stone Dresser for Ornamental Each 0.176 186.67 32.85
Beldar Each 0.0660 116.67 7.70
Bandhani Each 0.04400 116.67 5.13
TOTAL : 83.96
ADD FOR CONTRACTORS PROFIT @ 10% 8.40
ADD FOR OVER HEAD CHARGES @5% : 4.20
COST FOR 10.00 cu.dm 96.56
COST PER cum 9656.00
LABOUR PER cum 9656.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 83.96
TOTAL : 83.96
ADD FOR CONTRACTORS PROFIT @10% : 8.40
ADD FOR OVER HEAD CHARGES @5% : 4.20
LABOUR FOR 10.00 cu.dm 96.56
LABOUR PER cum 9656.00
LABOUR :
Mason 1st class Each 0.4850 211.16 102.41
Black smith 1st class Each 0.0060 186.67 1.12
Beldar Each 0.0660 116.67 7.70
Bandhani Each 0.04400 116.67 5.13
TOTAL : 116.36
ADD FOR CONTRACTORS PROFIT @ 10% 11.64
ADD FOR OVER HEAD CHARGES @5% : 5.82
COST FOR 10.00 cu.dm 133.81
COST PER cum 13382.00
LABOUR PER cum 13382.00
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 116.36
TOTAL : 116.36
ADD FOR CONTRACTORS PROFIT @10% : 11.64
ADD FOR OVER HEAD CHARGES @5% : 5.82
LABOUR FOR 10.00 cu.dm 133.82
LABOUR PER cum 13382.00
LABOUR :
TOTAL : 65.51
ADD FOR CONTRACTORS PROFIT @ 10% 6.55
ADD FOR OVER HEAD CHARGES @5% : 3.28
COST FOR 1.00 sqm 75.33
COST PER sqm 75.35
LABOUR PER sqm 75.35
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 65.51
TOTAL : 65.51
ADD FOR CONTRACTORS PROFIT @10% : 6.55
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR OVER HEAD CHARGES @5% : 3.28
LABOUR FOR 1.00 sqm 75.33
LABOUR PER sqm 75.35
LABOUR :
TOTAL : 269.92
ADD FOR CONTRACTORS PROFIT @ 10% 26.99
ADD FOR OVER HEAD CHARGES @5% : 13.50
COST FOR 1.00 sqm 310.41
COST PER sqm 310.40
LABOUR PER sqm 310.40
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 269.92
TOTAL : 269.92
ADD FOR CONTRACTORS PROFIT @10% : 26.99
ADD FOR OVER HEAD CHARGES @5% : 13.50
LABOUR FOR 1.00 sqm 310.41
LABOUR PER sqm 310.40
LABOUR :
TOTAL : 138.08
ADD FOR CONTRACTORS PROFIT @ 10% 13.81
ADD FOR OVER HEAD CHARGES @5% : 6.90
COST FOR 1.00 sqm 158.80
COST PER sqm 158.80
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR PER sqm 158.80
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 138.08
TOTAL : 138.08
ADD FOR CONTRACTORS PROFIT @10% : 13.81
ADD FOR OVER HEAD CHARGES @5% : 6.90
LABOUR FOR 1.00 sqm 158.80
LABOUR PER sqm 158.80
LABOUR :
TOTAL : 54.29
ADD FOR CONTRACTORS PROFIT @ 10% 5.43
ADD FOR OVER HEAD CHARGES @5% : 2.71
COST FOR 1.00 sqm 62.43
COST PER sqm 62.45
LABOUR PER sqm 62.45
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 54.29
TOTAL : 54.29
ADD FOR CONTRACTORS PROFIT @10% : 5.43
ADD FOR OVER HEAD CHARGES @5% : 2.71
LABOUR FOR 1.00 sqm 62.43
LABOUR PER sqm 62.45
LABOUR :
Mason 1st class Each 0.0440 211.16 9.29
Bandhani Each 0.0220 116.67 2.57
Beldar Each 0.04400 116.67 5.13
Black Smith 1st Class Each 0.0060 186.67 1.12
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Bhishti Each 0.0220 116.67 2.57
TOTAL : 25.48
ADD FOR CONTRACTORS PROFIT @ 10% 2.55
ADD FOR OVER HEAD CHARGES @5% : 1.27
COST FOR 10.00 Cu.dm 29.31
COST PER cum 2931.00
LABOUR PER cum 2931.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 25.48
TOTAL : 25.48
ADD FOR CONTRACTORS PROFIT @10% : 2.55
ADD FOR OVER HEAD CHARGES @5% : 1.27
LABOUR FOR 10.00 cu.dm 29.31
LABOUR PER cum 2931.00
LABOUR :
Stone Dresser For ordinary Each 1.3500 158.67 214.20
Black Smith 1st Class Each 0.3200 186.67 59.73
Beldar Each 0.33600 116.67 32.20
Bandhani Each 0.224 116.67 26.13
TOTAL : 332.27
ADD FOR CONTRACTORS PROFIT @ 10% 33.23
ADD FOR OVER HEAD CHARGES @5% : 16.61
COST FOR 1.00 sqm 382.11
COST PER sqm 382.10
LABOUR PER sqm 382.10
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 332.27
TOTAL : 332.27
ADD FOR CONTRACTORS PROFIT @10% : 33.23
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR OVER HEAD CHARGES @5% : 16.61
LABOUR FOR 1.00 sqm 382.11
LABOUR PER sqm 382.10
LABOUR :
Stone Dresser For ordinary Each 0.4480 158.67 71.08
Bandhani Each 0.3360 116.67 39.20
Beldar Each 0.67200 116.67 78.40
Bhishti Each 0.336 116.67 39.20
TOTAL : 311.89
ADD FOR CONTRACTORS PROFIT @ 10% 31.19
ADD FOR OVER HEAD CHARGES @5% : 15.59
COST FOR 1.00 sqm 358.67
COST PER sqm 358.65
LABOUR PER sqm 358.65
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 311.89
TOTAL : 311.89
ADD FOR CONTRACTORS PROFIT @10% : 31.19
ADD FOR OVER HEAD CHARGES @5% : 15.59
LABOUR FOR 1.00 sqm 358.67
LABOUR PER sqm 358.65
MATERIAL :
CARRIAGE :
Cement,G.I.,C.I.,A.C.,C.C.pipe
1 KM BY MECH. TRANSPORT 1 Tonne. 0.031 73.95 2.29
LABOUR :
Dressing charges Rate as per item no. : 1116020000 32.53
TOTAL : 236.13
ADD FOR WATER CHARGES @ 1.5% 3.54
TOTAL : 239.67
ADD FOR CONTRACTORS PROFIT 10% 23.97
ADD FOR OVER HEAD CHARGES @5% 11.98
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 72.91
TOTAL : 72.91
WATER CHARGES @ 1.5% : 3.54
TOTAL : 76.45
ADD FOR CONTRACTORS PROFIT @10% : 7.65
ADD FOR OVER HEAD CHARGES @5% : 3.82
LABOUR FOR 10.000 cu.dm 87.93
LABOUR PER cum 8793.00
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
CARRIAGE :
Cement,G.I.,C.I.,A.C.,C.C.pipe
1 KM BY MECH. TRANSPORT 1 Tonne. 0.031 73.95 2.29
LABOUR :
Dressing charges Rate as per item no. : 1116020000 32.53
TOTAL : 262.79
ADD FOR WATER CHARGES @ 1.5% 3.94
TOTAL : 266.73
ADD FOR CONTRACTORS PROFIT 10% 26.67
ADD FOR OVER HEAD CHARGES @5% 13.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 72.91
TOTAL : 72.91
WATER CHARGES @ 1.5% : 3.94
TOTAL : 76.85
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR CONTRACTORS PROFIT @10% : 7.69
ADD FOR OVER HEAD CHARGES @5% : 3.84
LABOUR FOR 10.000 cu.dm 88.39
LABOUR PER cum 8839.00
MATERIAL :
CARRIAGE :
Cement,G.I.,C.I.,A.C.,C.C.pipe
1 KM BY MECH. TRANSPORT 1 Tonne. 0.031 73.95 2.29
LABOUR :
Dressing charges Rate as per item no. : 1116050000 83.96
TOTAL : 301.06
ADD FOR WATER CHARGES @ 1.5% 4.52
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 305.58
ADD FOR CONTRACTORS PROFIT 10% 30.56
ADD FOR OVER HEAD CHARGES @5% 15.28
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 137.84
TOTAL : 137.84
WATER CHARGES @ 1.5% : 4.52
TOTAL : 142.36
ADD FOR CONTRACTORS PROFIT @10% : 14.24
ADD FOR OVER HEAD CHARGES @5% : 7.12
LABOUR FOR 10.000 cu.dm 163.72
LABOUR PER cum 16372.00
MATERIAL :
CARRIAGE :
Cement,G.I.,C.I.,A.C.,C.C.pipe
1 KM BY MECH. TRANSPORT 1 Tonne. 0.031 73.95 2.29
LABOUR :
Dressing charges Rate as per item no. : 1116040000 75.40
TOTAL : 319.16
ADD FOR WATER CHARGES @ 1.5% 4.79
TOTAL : 323.95
ADD FOR CONTRACTORS PROFIT 10% 32.39
ADD FOR OVER HEAD CHARGES @5% 16.20
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 129.28
TOTAL : 129.28
WATER CHARGES @ 1.5% : 4.79
TOTAL : 134.07
ADD FOR CONTRACTORS PROFIT @10% : 13.41
ADD FOR OVER HEAD CHARGES @5% : 6.70
LABOUR FOR 10.000 cu.dm 154.19
LABOUR PER cum 15419.00
MATERIAL :
CARRIAGE :
Cement,G.I.,C.I.,A.C.,C.C.pipe
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
1 KM BY MECH. TRANSPORT 1 Tonne. 0.123 73.95 9.10
LABOUR :
Dressing charges Rate as per item no. : 1119010000 332.26
TOTAL : 1315.84
ADD FOR WATER CHARGES @ 1.5% 19.74
TOTAL : 1335.58
ADD FOR CONTRACTORS PROFIT 10% 133.56
ADD FOR OVER HEAD CHARGES @5% 66.78
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 662.94
TOTAL : 662.94
WATER CHARGES @ 1.5% : 19.74
TOTAL : 682.68
ADD FOR CONTRACTORS PROFIT @10% : 68.27
ADD FOR OVER HEAD CHARGES @5% : 34.13
LABOUR FOR 1.00 sqm 785.09
LABOUR PER sqm 785.10
MATERIAL :
Cement,G.I.,C.I.,A.C.,C.C.pipe
1 KM BY MECH. TRANSPORT 1 Tonne. 0.123 73.95 9.10
LABOUR :
Dressing charges Rate as per item no. : 1119010000 332.26
TOTAL : 1422.50
ADD FOR WATER CHARGES @ 1.5% 21.34
TOTAL : 1443.84
ADD FOR CONTRACTORS PROFIT 10% 144.38
ADD FOR OVER HEAD CHARGES @5% 72.19
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 662.94
TOTAL : 662.94
WATER CHARGES @ 1.5% : 21.34
TOTAL : 684.28
ADD FOR CONTRACTORS PROFIT @10% : 68.43
ADD FOR OVER HEAD CHARGES @5% : 34.22
LABOUR FOR 1.00 sqm 786.93
LABOUR PER sqm 786.95
MATERIAL :
CARRIAGE :
Cement,G.I.,C.I.,A.C.,C.C.pipe
1 KM BY MECH. TRANSPORT 1 Tonne. 0.153 73.95 11.31
LABOUR :
Dressing charges Rate as per item no. : 1119010000 332.26
TOTAL : 1563.42
ADD FOR WATER CHARGES @ 1.5% 23.45
TOTAL : 1586.87
ADD FOR CONTRACTORS PROFIT 10% 158.69
ADD FOR OVER HEAD CHARGES @5% 79.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 746.94
TOTAL : 746.94
WATER CHARGES @ 1.5% : 23.45
TOTAL : 770.39
ADD FOR CONTRACTORS PROFIT @10% : 77.04
ADD FOR OVER HEAD CHARGES @5% : 38.52
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR FOR 1.00 sqm 885.95
LABOUR PER sqm 885.95
MATERIAL :
CARRIAGE :
Cement,G.I.,C.I.,A.C.,C.C.pipe
1 KM BY MECH. TRANSPORT 1 Tonne. 0.153 73.95 11.31
LABOUR :
Dressing charges Rate as per item no. : 1119010000 332.26
TOTAL : 1696.82
ADD FOR WATER CHARGES @ 1.5% 25.45
TOTAL : 1722.27
ADD FOR CONTRACTORS PROFIT 10% 172.23
ADD FOR OVER HEAD CHARGES @5% 86.11
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 746.94
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 746.94
WATER CHARGES @ 1.5% : 25.45
TOTAL : 772.39
ADD FOR CONTRACTORS PROFIT @10% : 77.24
ADD FOR OVER HEAD CHARGES @5% : 38.62
LABOUR FOR 1.00 sqm 888.25
LABOUR PER sqm 888.25
MATERIAL :
CARRIAGE :
Cement,G.I.,C.I.,A.C.,C.C.pipe
1 KM BY MECH. TRANSPORT 1 Tonne. 0.184 73.95 13.61
LABOUR :
Dressing charges Rate as per item no. : 1119010000 332.26
TOTAL : 1726.29
ADD FOR WATER CHARGES @ 1.5% 25.89
TOTAL : 1752.18
ADD FOR CONTRACTORS PROFIT 10% 175.22
ADD FOR OVER HEAD CHARGES @5% 87.61
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 746.94
TOTAL : 746.94
WATER CHARGES @ 1.5% : 25.89
TOTAL : 772.83
ADD FOR CONTRACTORS PROFIT @10% : 77.28
ADD FOR OVER HEAD CHARGES @5% : 38.64
LABOUR FOR 1.00 sqm 888.75
LABOUR PER sqm 888.75
MATERIAL :
CARRIAGE :
Cement,G.I.,C.I.,A.C.,C.C.pipe
1 KM BY MECH. TRANSPORT 1 Tonne. 0.184 73.95 13.61
LABOUR :
Dressing charges Rate as per item no. : 1119010000 332.26
TOTAL : 1886.29
ADD FOR WATER CHARGES @ 1.5% 28.29
TOTAL : 1914.58
ADD FOR CONTRACTORS PROFIT 10% 191.46
ADD FOR OVER HEAD CHARGES @5% 95.73
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 746.94
TOTAL : 746.94
WATER CHARGES @ 1.5% : 28.29
TOTAL : 775.23
ADD FOR CONTRACTORS PROFIT @10% : 77.52
ADD FOR OVER HEAD CHARGES @5% : 38.76
LABOUR FOR 1.00 sqm 891.51
LABOUR PER sqm 891.50
MATERIAL :
CARRIAGE :
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Cement,G.I.,C.I.,A.C.,C.C.pipe
1 KM BY MECH. TRANSPORT 1 Tonne. 0.215 73.95 15.90
LABOUR :
Dressing charges Rate as per item no. : 1119010000 332.26
TOTAL : 1889.51
ADD FOR WATER CHARGES @ 1.5% 28.34
TOTAL : 1917.85
ADD FOR CONTRACTORS PROFIT 10% 191.79
ADD FOR OVER HEAD CHARGES @5% 95.89
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 746.94
TOTAL : 746.94
WATER CHARGES @ 1.5% : 28.29
TOTAL : 775.28
ADD FOR CONTRACTORS PROFIT @10% : 77.53
ADD FOR OVER HEAD CHARGES @5% : 38.77
LABOUR FOR 1.00 sqm 891.58
LABOUR PER sqm 891.60
MATERIAL :
CARRIAGE :
Cement,G.I.,C.I.,A.C.,C.C.pipe
1 KM BY MECH. TRANSPORT 1 Tonne. 0.215 73.95 15.90
LABOUR :
Dressing charges Rate as per item no. : 1119010000 332.26
TOTAL : 2076.17
ADD FOR WATER CHARGES @ 1.5% 31.14
TOTAL : 2107.31
ADD FOR CONTRACTORS PROFIT 10% 210.73
ADD FOR OVER HEAD CHARGES @5% 105.37
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 746.94
TOTAL : 746.94
WATER CHARGES @ 1.5% : 31.14
TOTAL : 778.08
ADD FOR CONTRACTORS PROFIT @10% : 77.81
ADD FOR OVER HEAD CHARGES @5% : 38.90
LABOUR FOR 1.00 sqm 894.79
LABOUR PER sqm 894.80
LABOUR :
Labour and Material L.S 6.20
TOTAL : 6.20
ADD FOR WATER CHARGES @ 1.5% 0.10
TOTAL : 6.30
ADD FOR CONTRACTORS PROFIT 10% 0.63
ADD FOR OVER HEAD CHARGES @5% 0.32
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.20
TOTAL : 6.20
WATER CHARGES @ 1.5% : 0.10
TOTAL : 6.30
ADD FOR CONTRACTORS PROFIT @10% : 0.63
ADD FOR OVER HEAD CHARGES @5% : 0.32
LABOUR FOR 10.00 Cu.dm 7.25
LABOUR PER cum 725.00
MATERIAL :
LABOUR :
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
labour for fixing cramp L.S 200.00
TOTAL : 248.97
ADD FOR WATER CHARGES @ 1.5% : 3.73
TOTAL : 252.70
ADD FOR CONTRACTORS PROFIT @10% : 25.27
ADD FOR OVER HEAD CHARGES @5% : 12.64
COST FOR 1.000 cramp 290.61
COST PER cramp 290.60
LABOUR PER cramp 234.40
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 200.00
Labour for cement mortar 1:2 0.11
TOTAL : 200.11
WATER CHARGES @ 1.5% : 3.73
TOTAL : 203.84
ADD FOR CONTRACTORS PROFIT @10% : 20.38
ADD FOR OVER HEAD CHARGES @5% : 10.19
LABOUR FOR 1.000 cramp 234.41
LABOUR PER cramp 234.40
MATERIAL :
LABOUR :
labour for fixing cramp L.S 200.00
TOTAL : 228.97
ADD FOR WATER CHARGES @ 1.5% : 3.43
TOTAL : 232.40
ADD FOR CONTRACTORS PROFIT @10% : 23.24
ADD FOR OVER HEAD CHARGES @5% : 11.62
COST FOR 1.000 cramp 267.26
COST PER cramp 267.25
LABOUR PER cramp 234.05
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 200.00
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Labour for cement mortar 1:2 0.11
TOTAL : 200.11
WATER CHARGES @ 1.5% : 3.43
TOTAL : 203.54
ADD FOR CONTRACTORS PROFIT @10% : 20.35
ADD FOR OVER HEAD CHARGES @5% : 10.18
LABOUR FOR 1.000 cramp 234.07
LABOUR PER cramp 234.05
MATERIAL :
LABOUR :
Labour for dressing L.S 3.00
TOTAL : 8.47
ADD FOR WATER CHARGES @ 1.5% : 0.13
TOTAL : 8.60
ADD FOR CONTRACTORS PROFIT @10% : 0.86
ADD FOR OVER HEAD CHARGES @5% : 0.43
COST FOR 1.000 dowel 9.89
COST PER dowel 9.90
LABOUR PER dowel 3.70
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 3.00
Labour for cement mortar 1:2 0.10
TOTAL : 3.10
WATER CHARGES @ 1.5% : 0.13
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 3.23
ADD FOR CONTRACTORS PROFIT @10% : 0.32
ADD FOR OVER HEAD CHARGES @5% : 0.16
LABOUR FOR 1.000 dowel 3.71
LABOUR PER dowel 3.70
MATERIAL :
LABOUR :
labour for fixing L.S 2.00
TOTAL : 30.97
ADD FOR WATER CHARGES @ 1.5% : 0.46
TOTAL : 31.43
ADD FOR CONTRACTORS PROFIT @10% : 3.14
ADD FOR OVER HEAD CHARGES @5% : 1.57
COST FOR 1.000 copper pin 36.14
COST PER copper pin 36.15
LABOUR PER copper pin 2.95
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 2.00
Labour for cement mortar 1:2 0.10
TOTAL : 2.10
WATER CHARGES @ 1.5% : 0.46
TOTAL : 2.56
ADD FOR CONTRACTORS PROFIT @10% : 0.26
ADD FOR OVER HEAD CHARGES @5% : 0.13
LABOUR FOR 1.000 copper pin 2.95
LABOUR PER copper pin 2.95
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
1130000000 Extra for laying stone :
LABOUR :
Beldar Each 4.00000 116.67 466.68
TOTAL : 466.68
ADD FOR CONTRACTORS PROFIT @10% : 46.67
ADD FOR OVER HEAD CHARGES @5% : 23.34
COST FOR 14 cum per 0.3 metre depth 536.69
COST FOR 1 cum per metre depth 127.80
LABOUR FOR 1 cum per metre depth 127.80
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 466.68
TOTAL : 466.68
ADD FOR CONTRACTORS PROFIT @10% : 46.67
ADD FOR OVER HEAD CHARGES @5% : 23.34
LABOUR FOR 14 CUM per 0.3 metre depth 536.69
LABOUR FOR 1 CUM metre per metre depth 127.80
LABOUR :
Mason 2nd Class Each 0.04000 158.67 6.35
Beldar Each 0.40000 116.67 46.67
TOTAL : 53.02
ADD FOR CONTRACTORS PROFIT @10% : 5.30
ADD FOR OVER HEAD CHARGES @5% : 2.65
COST FOR 1 cum per metre depth 60.97
COST PER 1 cum per metre depth 60.95
LABOUR FOR 1 cum per metre depth 60.95
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 53.02
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 53.02
ADD FOR CONTRACTORS PROFIT @10% : 5.30
ADD FOR OVER HEAD CHARGES @5% : 2.65
LABOUR FOR 1 CUM metre per metre depth 60.97
LABOUR PER 1 CUM metre per metre depth 60.95
MATERIAL :
CARRIAGE :
LABOUR :
Beldar Each 0.80000 116.67 93.34
TOTAL : 578.19
ADD FOR CONTRACTORS PROFIT @10% : 57.82
ADD FOR OVER HEAD CHARGES @5% : 28.91
COST FOR 1.000 cum 664.92
COST PER cum 664.90
LABOUR PER cum 107.35
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 93.34
Total 93.34
ADD FOR CONTRACTORS PROFIT @10% : 9.33
ADD FOR OVER HEAD CHARGES @5% : 4.67
LABOUR FOR 1.000 cum 107.34
LABOUR PER cum 107.35
MATERIAL :
CARRIAGE :
LABOUR :
Mason 2nd Class Each 0.90000 158.67 142.80
TOTAL : 1112.50
ADD FOR CONTRACTORS PROFIT @10% : 111.25
ADD FOR OVER HEAD CHARGES @5% : 55.63
COST FOR 2.000 cum 1279.38
COST PER cum 639.70
LABOUR PER cum 82.10
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 142.80
Total 142.80
ADD FOR CONTRACTORS PROFIT @10% : 14.28
ADD FOR OVER HEAD CHARGES @5% : 7.14
LABOUR FOR 2.000 cum 164.22
LABOUR PER cum 82.10
MATERIAL :
LABOUR :
Black Smith 2nd Class Each 1.63000 148.16 241.50
TOTAL : 1582.00
ADD FOR CONTRACTORS PROFIT @10% : 158.20
ADD FOR OVER HEAD CHARGES @5% : 79.10
COST FOR 9.375 sq.m. 1819.30
COST PER sq.m. 194.05
LABOUR PER sq.m. 29.60
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 241.50
Total 241.50
ADD FOR CONTRACTORS PROFIT @10% : 24.15
ADD FOR OVER HEAD CHARGES @5% : 12.08
LABOUR FOR 9.375 sq.m. 277.73
LABOUR PER sq.m. 29.60
MATERIAL :
CARRIAGE :
Carriage of G.I.stone L.S 1.50
LABOUR :
Black Smith 2nd Class Each 1.10000 148.16 162.98
TOTAL : 1210.48
ADD FOR CONTRACTORS PROFIT @10% : 121.05
ADD FOR OVER HEAD CHARGES @5% : 60.53
COST FOR 9.375 sq.m. 1392.06
COST PER sq.m. 148.50
LABOUR PER sq.m. 20.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 162.98
Total 162.98
ADD FOR CONTRACTORS PROFIT @10% : 16.30
ADD FOR OVER HEAD CHARGES @5% : 8.15
LABOUR FOR 9.375 sq.m. 187.43
LABOUR PER sq.m. 20.00
MATERIAL :
CARRIAGE :
Carriage of G.I.wire L.S 3.00
LABOUR :
Black Smith 2nd Class Each 1.63000 148.16 241.50
TOTAL : 2251.00
ADD FOR CONTRACTORS PROFIT @10% : 225.10
ADD FOR OVER HEAD CHARGES @5% : 112.55
COST FOR 9.375 sq.m. 2588.65
COST PER sq.m. 276.10
LABOUR PER sq.m. 29.60
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 241.50
Total 241.50
ADD FOR CONTRACTORS PROFIT @10% : 24.15
ADD FOR OVER HEAD CHARGES @5% : 12.08
LABOUR FOR 9.375 sq.m. 277.73
LABOUR PER sq.m. 29.60
MATERIAL :
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
G.I wire 5mm thick(diagonal
dimension) for one face of crate
length of wire required
(9+9)x1.25m x 2 = 31.70 Rmt.
Add for wastage and
twisting 10% = 3.17 Rmt.
Total: = 34.87 Rmt.
For six sides length of wire
required: 34.87x6= 209.22 Rmt.
Wt.of G.I. wire 5mm thick=0.15 kg.
Therefore total weight
209.22Rmtx0.15kg =31.38 kgs.
0.15 kg.
Total = 31.38 kg. 1 Kg 31.3800 50.00 1569.00
CARRIAGE :
Carriage of G.I.wire L.S 3.00
LABOUR :
Black Smith 2nd Class Each 1.10000 148.16 162.98
TOTAL : 1734.98
ADD FOR CONTRACTORS PROFIT @10% : 173.50
ADD FOR OVER HEAD CHARGES @5% : 86.75
COST FOR 9.375 sq.m. 1995.23
COST PER sq.m. 212.80
LABOUR PER sq.m. 20.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 162.98
Total 162.98
ADD FOR CONTRACTORS PROFIT @10% : 16.30
ADD FOR OVER HEAD CHARGES @5% : 8.15
LABOUR FOR 9.375 sq.m. 187.43
LABOUR PER sq.m. 20.00
MATERIAL :
CARRIAGE :
LABOUR :
Mason 2nd Class Each 0.80000 158.67 126.94
Beldar Each 0.80000 116.67 93.34
TOTAL : 705.13
ADD FOR CONTRACTORS PROFIT @10% : 70.51
ADD FOR OVER HEAD CHARGES @5% : 35.25
COST FOR 1.000 cum 810.89
COST PER cum 810.90
LABOUR PER cum 253.35
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 220.28
Total 220.28
ADD FOR CONTRACTORS PROFIT @10% : 22.03
ADD FOR OVER HEAD CHARGES @5% : 11.02
LABOUR FOR 1.000 cum 253.33
LABOUR PER cum 253.35
MATERIAL :
CARRIAGE :
TOTAL : 693.34
ADD FOR CONTRACTORS PROFIT @10% : 69.33
ADD FOR OVER HEAD CHARGES @5% : 34.67
COST FOR 1.000 cum 797.34
COST PER cum 797.35
LABOUR PER cum 120.75
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 105.00
Total 105.00
ADD FOR CONTRACTORS PROFIT @10% : 10.50
ADD FOR OVER HEAD CHARGES @5% : 5.25
LABOUR FOR 1.000 cum 120.75
LABOUR PER cum 120.75
LABOUR :
Mason 2nd Class Each 0.35000 158.67 55.53
Beldar Each 0.70000 116.67 81.67
TOTAL : 144.20
ADD FOR CONTRACTORS PROFIT @10% : 14.42
ADD FOR OVER HEAD CHARGES @5% : 7.21
COST FOR 1.000 cum 165.83
COST PER cum 165.85
LABOUR PER cum 165.85
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 144.20
Total 144.20
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR CONTRACTORS PROFIT @10% : 14.42
ADD FOR OVER HEAD CHARGES @5% : 7.21
LABOUR FOR 1.000 cum 165.83
LABOUR PER cum 165.85
MATERIAL :
CARRIAGE :
LABOUR :
Mason 2nd Class Each 0.53000 158.67 80.10
Beldar Each 0.53000 116.67 61.84
TOTAL : 379.52
ADD FOR CONTRACTORS PROFIT @10% : 37.95
ADD FOR OVER HEAD CHARGES @5% : 18.98
COST FOR 1.000 cum 436.45
COST PER cum 436.45
LABOUR PER cum 163.25
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 141.94
Total 141.94
ADD FOR CONTRACTORS PROFIT @10% : 14.19
ADD FOR OVER HEAD CHARGES @5% : 7.10
LABOUR FOR 1.000 cum 163.23
LABOUR PER cum 163.25
MATERIAL :
CARRIAGE :
LABOUR :
Mason 2nd Class Each 0.10000 158.67 15.87
Beldar Each 0.10000 116.67 11.67
SUNDRIES : L.S. 1.50
TOTAL : 185.16
ADD. FOR WATER CHARGES @ 1.5% 2.78
TOTAL : 187.94
ADD FOR CONTRACTORS PROFIT @10% : 18.79
ADD FOR OVER HEAD CHARGES @5% : 9.40
COST FOR 1.000 cum 216.13
COST PER cum 216.15
LABOUR PER cum 36.60
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 29.04
TOTAL : 29.04
ADD. FOR WATER CHARGES @ 1.5% 2.78
Total 31.82
ADD FOR CONTRACTORS PROFIT @10% : 3.18
ADD FOR OVER HEAD CHARGES @5% : 1.59
LABOUR FOR 1.000 cum 36.59
LABOUR PER cum 36.60
LABOUR :
Mason 2nd Class Each 0.70000 158.67 111.07
Beldar Each 0.70000 116.67 81.67
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 203.74
TOTAL : 203.74
ADD. FOR WATER CHARGES @ 1.5% 3.06
Total 206.80
ADD FOR CONTRACTORS PROFIT @10% : 20.68
ADD FOR OVER HEAD CHARGES @5% : 10.34
LABOUR FOR 1.000 sqm 237.82
LABOUR PER sqm 237.80
MATERIAL :
CARRIAGE :
Building stones.
1 KM BY MECH. TRANSPORT 1 Cum. 0.06000 120.05 7.20
LABOUR :
Mason 2nd Class Each 0.23000 158.67 36.49
Beldar Each 0.11500 116.67 13.42
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 52.91
Labour for mud mortar 3.19
TOTAL : 56.10
ADD. FOR WATER CHARGES @ 1.5% 1.54
Total 57.64
ADD FOR CONTRACTORS PROFIT @10% : 5.76
ADD FOR OVER HEAD CHARGES @5% : 2.88
LABOUR FOR 1.000 Sqm. 66.28
LABOUR PER Sqm. 66.30
MATERIAL :
CARRIAGE :
Building stones.
1 KM BY MECH. TRANSPORT 1 Cum. 0.06000 120.05 7.20
LABOUR :
Mason 2nd Class Each 0.45000 158.67 71.40
Beldar Each 0.24000 116.67 28.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 102.40
Labour for lime mortar1:3 8.95
TOTAL : 111.35
ADD. FOR WATER CHARGES @ 1.5% 2.94
Total 114.29
ADD FOR CONTRACTORS PROFIT @10% : 11.43
ADD FOR OVER HEAD CHARGES @5% : 5.72
LABOUR FOR 1.000 Sqm. 131.44
LABOUR PER Sqm. 131.45
MATERIAL :
CARRIAGE :
Building stones.
LABOUR :
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 136.20
Labour for cement mortar 1:6 2.97
TOTAL : 139.17
WATER CHARGES @ 1.5% : 3.39
TOTAL : 142.56
ADD FOR CONTRACTORS PROFIT @10% : 14.26
ADD FOR OVER HEAD CHARGES @5% : 7.13
LABOUR FOR 1.000 Sq.m. 163.95
LABOUR PER Sq.m. 163.95
MATERIAL :
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 892.52
Labour as per iten no. 0912010A 721.77 (-a-)
Labour for cement mortar 1:6 20.58
TOTAL : 1634.87
WATER CHARGES @ 1.5% : 18.46
TOTAL : 1653.33
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a-) : 93.16
ADD FOR OVER HEAD CHARGES @5% EXCEPT ON (-a-) : 46.58
LABOUR FOR 1.890 cum 1793.07
LABOUR PER cum 948.70
MATERIAL :
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 892.52
Labour as per iten no. 0912010A 721.77 (-a-)
Labour for lime mortar 1:3 61.95
TOTAL : 1676.25
WATER CHARGES @ 1.5% : 18.86
TOTAL : 1695.11
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a-) : 97.33
ADD FOR OVER HEAD CHARGES @5% EXCEPT ON (-a-) : 48.67
LABOUR FOR 1.890 cum 1841.11
LABOUR PER cum 974.15
MATERIAL :
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 892.52
Labour as per iten no. 09150100 705.07 (-a-)
Labour for cement mortar 1:6 20.58
TOTAL : 1618.18
WATER CHARGES @ 1.5% : 18.46
TOTAL : 1636.64
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a-) : 93.16
ADD FOR OVER HEAD CHARGES @5% EXCEPT ON (-a-) : 46.58
LABOUR FOR 1.890 cum 1776.38
LABOUR PER cum 939.90
MATERIAL :
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 892.52
Labour as per iten no. 09150100 705.07 (-a-)
Labour for cement mortar 1:6 61.95
TOTAL : 1659.55
WATER CHARGES @ 1.5% : 18.85
TOTAL : 1678.40
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a-) : 97.33
ADD FOR OVER HEAD CHARGES @5% EXCEPT ON (-a-) : 48.67
LABOUR FOR 1.890 cum 1824.40
LABOUR PER cum 965.30
MATERIAL :
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 493.64
Labour as per iten no. 0912010A 358.73 (-a-)
Labour for cement mortar 1:6 11.43
TOTAL : 863.81
WATER CHARGES @ 1.5% : 10.22
TOTAL : 874.03
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a-) : 51.53
ADD FOR OVER HEAD CHARGES @5% EXCEPT ON (-a-) : 25.77
LABOUR FOR 9.300 Sq.m. 951.33
LABOUR PER Sq.m. 102.30
MATERIAL :
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 463.65
Labour as per iten no. 0912010A 358.73 (-a-)
Labour for cement mortar 1:6 34.42
TOTAL : 886.80
WATER CHARGES @ 1.5% : 10.44
TOTAL : 897.24
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a-) : 53.85
ADD FOR OVER HEAD CHARGES @5% EXCEPT ON (-a-) : 26.93
LABOUR FOR 9.300 Sq.m. 978.02
LABOUR PER Sq.m. 105.15
MATERIAL :
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 493.64
Labour as per iten no. 0912010A 350.43 (-a-)
Labour for cement mortar 1:6 11.43
TOTAL : 855.51
WATER CHARGES @ 1.5% : 10.22
TOTAL : 865.73
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a-) : 51.53
ADD FOR OVER HEAD CHARGES @5% EXCEPT ON (-a-) : 25.77
LABOUR FOR 9.300 Sq.m. 943.03
LABOUR PER Sq.m. 101.40
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 493.64
Labour As per item no :09150100 350.43 (-a-)
Labour for cement mortar 1:3 34.42
TOTAL : 878.50
WATER CHARGES @ 1.5% : 10.44
TOTAL : 888.94
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a-) : 53.85
ADD FOR OVER HEAD CHARGES @5% EXCEPT ON (-a-) : 26.93
LABOUR FOR 9.300 Sq.m. 969.72
LABOUR PER Sq.m. 104.25
LABOUR :
Stone Dresser For ordinary Each 0.3500 158.67 55.53
Black Smith 1st Class Each 0.2000 186.67 37.33
Beldar Each 0.0800 116.67 9.33
Bandhani Each 0.0900 116.67 10.50
Beldar Each 0.0900 116.67 10.50
TOTAL : 123.19
ADD FOR CONTRACTORS PROFIT @10% : 12.32
ADD FOR OVER HEAD CHARGES @5% : 6.16
COST FOR 10.000 cu.dm. 141.67
say Rs. 141.65
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 123.19
TOTAL : 123.19
ADD FOR CONTRACTORS PROFIT @10% : 12.32
ADD FOR OVER HEAD CHARGES @5% : 6.16
LABOUR FOR 10.000 cu.dm. 141.67
say Rs. 141.65
LABOUR :
Stone Dresser For Ornamental Each 0.3500 186.67 65.33
Stone Dresser For ordinary Each 0.3500 158.67 55.53
Black Smith 1st Class Each 0.0200 186.67 3.73
Beldar Each 0.0800 116.67 9.33
Bandhani Each 0.0900 116.67 10.50
Beldar Each 0.2600 116.67 30.33
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 174.75
ADD FOR CONTRACTORS PROFIT @10% : 17.48
ADD FOR OVER HEAD CHARGES @5% : 8.74
COST FOR 10.000 cu.dm. 200.97
say Rs. 200.95
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 174.75
TOTAL : 174.75
ADD FOR CONTRACTORS PROFIT @10% : 17.48
ADD FOR OVER HEAD CHARGES @5% : 8.74
LABOUR FOR 10.000 cu.dm. 200.97
say Rs. 200.95
LABOUR :
Stone Dresser For Ornamental Each 1.2400 186.67 231.47
Black Smith 1st Class Each 0.0200 186.67 3.73
Beldar Each 0.0800 116.67 9.33
Bandhani Each 0.0900 116.67 10.50
Beldar Each 0.5300 116.67 61.84
TOTAL : 316.87
ADD FOR CONTRACTORS PROFIT @10% : 31.69
ADD FOR OVER HEAD CHARGES @5% : 15.85
COST FOR 10.000 cu.dm. 364.41
say Rs. 364.40
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 316.87
TOTAL : 316.87
ADD FOR CONTRACTORS PROFIT @10% : 31.69
ADD FOR OVER HEAD CHARGES @5% : 15.85
LABOUR FOR 10.000 cu.dm. 364.41
say Rs. 364.40
LABOUR :
Stone Dresser For ordinary Each 1.3500 158.67 214.20
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Beldar Each 0.4100 116.67 47.83
Bandhani Each 0.4500 116.67 52.50
Beldar Each 0.4500 116.67 52.50
Black Smith 1st Class Each 0.1100 186.67 20.53
TOTAL : 387.56
ADD FOR CONTRACTORS PROFIT @10% : 38.76
ADD FOR OVER HEAD CHARGES @5% : 19.38
COST FOR 1.000 Sq.m. 445.70
COST PER Sq.m. 445.70
LABOUR PER Sq.m. 445.70
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 387.56
TOTAL : 387.56
ADD FOR CONTRACTORS PROFIT @10% : 38.76
ADD FOR OVER HEAD CHARGES @5% : 19.38
LABOUR FOR 1.000 Sq.m. 445.70
LABOUR PER Sq.m. 445.70
LABOUR :
Stone Dresser For Ornamental Each 0.6700 186.67 125.07
Bandhani Each 0.6700 116.67 78.17
Beldar Each 1.3400 116.67 156.34
Bhishti Each 0.6700 116.67 78.17
Mate Each 0.3300 116.67 38.50
Black Smith 1st Class Each 0.270 186.67 50.40
TOTAL : 545.65
ADD FOR CONTRACTORS PROFIT @10% : 54.57
ADD FOR OVER HEAD CHARGES @5% : 27.29
COST FOR 1.000 Sqm. 627.51
COST PER Sqm. 627.50
LABOUR PER Sqm. 627.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 545.65
TOTAL : 545.65
ADD FOR CONTRACTORS PROFIT @10% : 54.57
ADD FOR OVER HEAD CHARGES @5% : 27.29
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR FOR 1.000 Sqm. 627.51
LABOUR PER Sqm. 627.50
MATERIAL :
White Cement
(0.475 cum. of cement=0.68 Tonne
Cement) 1 Tonne 0.6800 18000.00 12240.00
CARRIAGE :
Cement,G.I.,C.I.,A.C.,C.C.pipe
1 KM BY MECH. TRANSPORT 1 Tonne 0.6800 73.95 50.29
MARBLE DUST
1 KM BY MECH. TRANSPORT 1 Cum. 0.9500 110.95 105.40
LABOUR :
Beldar 1 Cum. 0.6000 116.67 70.00
Bhishti 1 Cum. 0.3000 116.67 35.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 128.70
TOTAL : 128.70
ADD FOR CONTRACTORS PROFIT @10% 12.87
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR OVER HEAD CHARGES @5% 6.44
LABOUR FOR 1.000 Cu.m. 148.01
LABOUR PER Cu.m. 148.00
MATERIAL :
CARRIAGE :
Cement,G.I.,C.I.,A.C.,C.C.pipe
1 KM BY MECH. TRANSPORT 1 Tonne. 0.0320 73.95 2.37
LABOUR :
Fixing Charges :
Stone Dresser For Ornamental Each 0.0900 186.67 16.80
Bandhani Each 0.0700 116.67 8.17
Beldar Each 0.1400 116.67 16.33
Bhishti Each 0.0400 116.67 4.67
Mate Each 0.0400 116.67 4.67
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Black Smith 1st Class Each 0.0100 186.67 1.87
TOTAL : 1087.51
ADD FOR WATER CHARGES @ 1.5% : 16.31
TOTAL : 1103.83
ADD FOR CONTRACTORS PROFIT @ 10% 110.38
ADD FOR OVER HEAD CHARGES @5% : 55.19
COST FOR 10.000 Cu.dm 1269.40
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 177.70
Labour for cement mortar 1:4 0.23
Labour As per item no :1144060000 0.01
TOTAL : 177.94
WATER CHARGES @ 1.5% : 16.31
TOTAL : 194.25
ADD FOR CONTRACTORS PROFIT @10% : 19.43
ADD FOR OVER HEAD CHARGES @5% : 9.72
LABOUR FOR 10.000 Cu.dm 223.40
MATERIAL :
CARRIAGE :
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Cement,G.I.,C.I.,A.C.,C.C.pipe
1 KM BY MECH. TRANSPORT 1 Tonne. 0.0320 73.95 2.37
LABOUR :
Fixing Charges :
Stone Dresser For Ornamental Each 0.0900 186.67 16.80
Bandhani Each 0.0700 116.67 8.17
Beldar Each 0.1400 116.67 16.33
Bhishti Each 0.0400 116.67 4.67
Mate Each 0.0400 116.67 4.67
Black Smith 1st Class Each 0.0100 186.67 1.87
TOTAL : 787.51
ADD FOR WATER CHARGES @ 1.5% : 11.81
TOTAL : 799.33
ADD FOR CONTRACTORS PROFIT @ 10% 79.93
ADD FOR OVER HEAD CHARGES @5% : 39.97
COST FOR 10.000 Cu.dm 919.25
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 177.70
Labour for cement mortar 1:4 0.23
Labour As per item no :1144060000 0.01
TOTAL : 177.94
WATER CHARGES @ 1.5% : 11.81
TOTAL : 189.75
ADD FOR CONTRACTORS PROFIT @10% : 18.98
ADD FOR OVER HEAD CHARGES @5% : 9.49
LABOUR FOR 10.000 Cu.dm 218.22
MATERIAL :
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Finished work =10 cudm.
Add for wastage @ 20 % =2cudm.
Total 12 cudm.
Cost of marble 10 cudm12.0000 425.00 510.00
CARRIAGE :
Cement,G.I.,C.I.,A.C.,C.C.pipe
1 KM BY MECH. TRANSPORT 1 Tonne. 0.0320 73.95 2.37
LABOUR :
Fixing Charges :
Stone Dresser For Ornamental Each 0.0900 186.67 16.80
Bandhani Each 0.0700 116.67 8.17
Beldar Each 0.1400 116.67 16.33
Bhishti Each 0.0400 116.67 4.67
Mate Each 0.0400 116.67 4.67
Black Smith 1st Class Each 0.0100 186.67 1.87
TOTAL : 697.53
ADD FOR WATER CHARGES @ 1.5% : 10.46
TOTAL : 707.99
ADD FOR CONTRACTORS PROFIT @ 10% 70.80
ADD FOR OVER HEAD CHARGES @5% : 35.40
COST FOR 10.000 Cu.dm 814.19
Say Rs. 814.20
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 177.70
Labour for cement mortar 1:4 0.23
Labour As per item no :1144060000 0.01
TOTAL : 177.94
WATER CHARGES @ 1.5% : 10.46
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 188.40
ADD FOR CONTRACTORS PROFIT @10% : 18.84
ADD FOR OVER HEAD CHARGES @5% : 9.42
LABOUR FOR 10.000 Cu.dm 216.66
MATERIAL :
CARRIAGE :
Cement,G.I.,C.I.,A.C.,C.C.pipe
1 KM BY MECH. TRANSPORT 1 Tonne. 0.0320 73.95 2.37
LABOUR :
Fixing Charges :
Stone Dresser For Ornamental Each 0.0900 186.67 16.80
Bandhani Each 0.0700 116.67 8.17
Beldar Each 0.1400 116.67 16.33
Bhishti Each 0.0400 116.67 4.67
Mate Each 0.0400 116.67 4.67
Black Smith 1st Class Each 0.0100 186.67 1.87
TOTAL : 907.53
ADD FOR WATER CHARGES @ 1.5% : 13.62
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 921.15
ADD FOR CONTRACTORS PROFIT @ 10% 92.12
ADD FOR OVER HEAD CHARGES @5% : 46.06
COST FOR 10.000 Cu.dm 1059.33
Say Rs. 1059.35
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 177.70
Labour for cement mortar 1:4 0.23
Labour As per item no :1144060000 0.01
TOTAL : 177.94
WATER CHARGES @ 1.5% : 13.62
TOTAL : 191.56
ADD FOR CONTRACTORS PROFIT @10% : 19.16
ADD FOR OVER HEAD CHARGES @5% : 9.58
LABOUR FOR 10.000 Cu.dm 220.30
MATERIAL :
Cement,G.I.,C.I.,A.C.,C.C.pipe
1 KM BY MECH. TRANSPORT 1 Tonne. 0.0320 73.95 2.37
LABOUR :
Fixing Charges :
Stone Dresser For Ornamental Each 0.0900 186.67 16.80
Bandhani Each 0.0700 116.67 8.17
Beldar Each 0.1400 116.67 16.33
Bhishti Each 0.0400 116.67 4.67
Mate Each 0.0400 116.67 4.67
Black Smith 1st Class Each 0.0100 186.67 1.87
TOTAL : 547.51
ADD FOR WATER CHARGES @ 1.5% : 8.21
TOTAL : 555.73
ADD FOR CONTRACTORS PROFIT @ 10% 55.57
ADD FOR OVER HEAD CHARGES @5% : 27.79
COST FOR 10.000 Cu.dm 639.09
Say Rs. 639.10
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 177.70
Labour for cement mortar 1:4 0.23
Labour As per item no :1144060000 0.01
TOTAL : 177.94
WATER CHARGES @ 1.5% : 8.21
TOTAL : 186.15
ADD FOR CONTRACTORS PROFIT @10% : 18.62
ADD FOR OVER HEAD CHARGES @5% : 9.31
LABOUR FOR 10.000 Cu.dm 214.08
MATERIAL :
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Finished work 10 cu.dm.
Add for wastage @ 20 % =2 cu.dm.
Total =12 cu.dm.
10 Cudm.12.0000 250.00 300.00
CARRIAGE :
Cement,G.I.,C.I.,A.C.,C.C.pipe
1 KM BY MECH. TRANSPORT 1 Tonne. 0.0320 73.95 2.37
LABOUR :
Fixing Charges :
Stone Dresser For Ornamental Each 0.0900 186.67 16.80
Bandhani Each 0.0700 116.67 8.17
Beldar Each 0.1400 116.67 16.33
Bhishti Each 0.0400 116.67 4.67
Mate Each 0.0400 116.67 4.67
Black Smith 1st Class Each 0.0100 186.67 1.87
TOTAL : 487.51
ADD FOR WATER CHARGES @ 1.5% : 7.31
TOTAL : 494.83
ADD FOR CONTRACTORS PROFIT @ 10% 49.48
ADD FOR OVER HEAD CHARGES @5% : 24.74
COST FOR 10.000 Cu.dm 569.05
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 177.70
Labour for cement mortar 1:4 0.23
Labour As per item no :1144060000 0.01
TOTAL : 177.94
WATER CHARGES @ 1.5% : 7.31
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 185.25
ADD FOR CONTRACTORS PROFIT @10% : 18.53
ADD FOR OVER HEAD CHARGES @5% : 9.27
LABOUR FOR 10.000 Cu.dm 213.05
LABOUR :
Dressing charges for plain arches Rate as per item no. 1144020000 174.75
Dressing charges for plain work Rate as per item no. 1144010000 123.19
Difference of rate : 51.56
Total : 70.56
ADD FOR WATER CHARGES @ 1.5% : 1.06
TOTAL : 71.62
ADD FOR CONTRACTORS PROFIT @10% : 7.16
ADD FOR OVER HEAD CHARGES @5% : 3.58
COST FOR 10.000 Cu.dm. 82.36
Say Rs. 82.35
LABOUR :
Dressing charges for plain arches Rate as per item no. 1144020000 174.75
Dressing charges for plain work Rate as per item no. 1144010000 123.19
Difference of rate : 51.66
Total : 51.66
ADD FOR WATER CHARGES @ 1.5% : 0.77
TOTAL : 52.43
ADD FOR CONTRACTORS PROFIT @10% : 5.24
ADD FOR OVER HEAD CHARGES @5% : 2.62
COST FOR 10.000 Cu.dm. 60.29
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Say Rs. 60.30
LABOUR :
Dressing charges for plain arches Rate as per item no. 1144030000 316.87
Dressing charges for plain work Rate as per item no. 1144010000 123.19
Difference of rate : 193.68
Total : 212.68
ADD FOR WATER CHARGES @ 1.5% : 3.19
TOTAL : 215.87
ADD FOR CONTRACTORS PROFIT @10% : 21.59
ADD FOR OVER HEAD CHARGES @5% : 10.80
COST FOR 10.000 Cu.dm. 248.26
Say Rs. 248.25
LABOUR :
Dressing charges for plain arches Rate as per item no. 1144030000 316.87
Dressing charges for plain work Rate as per item no. 1144010000 174.75
Difference of rate :
142.12
Total : 142.12
ADD FOR WATER CHARGES @ 1.5% : 2.13
TOTAL : 144.25
ADD FOR CONTRACTORS PROFIT @10% : 14.43
ADD FOR OVER HEAD CHARGES @5% : 7.22
COST FOR 10.000 Cu.dm. 165.90
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
1150000000 Extra for sunk on moulded work in
circular moulding over :
LABOUR :
Rate as per item no. : 1144030000 316.87
Total : 193.68
ADD FOR WATER CHARGES @ 1.5% : 2.90
TOTAL : 196.58
ADD FOR CONTRACTORS PROFIT @10% : 19.66
ADD FOR OVER HEAD CHARGES @5% : 9.83
COST FOR 10.000 cu.dm. 226.07
Say Rs. 226.05
LABOUR :
Rate as per item no. : 1144030000 316.87
Total : 142.12
ADD FOR WATER CHARGES @ 1.5% : 2.13
TOTAL : 144.25
ADD FOR CONTRACTORS PROFIT @10% : 14.43
ADD FOR OVER HEAD CHARGES @5% : 7.22
COST FOR 10.000 cu.dm. 165.90
MATERIAL :
CARRIAGE :
Cement,G.I.,C.I.,A.C.,C.C.pipe
1 KM BY MECH. TRANSPORT 1 Tonne. 0.0800 73.95 5.92
LABOUR :
TOTAL : 3271.18
ADD FOR WATER CHARGES @ 1.5% : 49.07
TOTAL : 3320.25
ADD FOR CONTRACTORS PROFIT @ 10% 332.02
ADD FOR OVER HEAD CHARGES @5% : 166.01
COST FOR 1.000 sq.m. 3818.29
COST PER sq.m. 3818.30
LABOUR PER sq.m. 1131.85
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 933.21
Labour for cement mortar 1:3 1.60
Labour As per item no :1144060000 0.32
TOTAL : 935.13
WATER CHARGES @ 1.5% : 49.07
TOTAL : 984.20
ADD FOR CONTRACTORS PROFIT @10% : 98.42
ADD FOR OVER HEAD CHARGES @5% : 49.21
LABOUR FOR 1.000 sq.m. 1131.83
LABOUR PER sq.m. 1131.85
MATERIAL :
CARRIAGE :
Cement,G.I.,C.I.,A.C.,C.C.pipe
1 KM BY MECH. TRANSPORT 1 Tonne. 0.0800 73.95 5.92
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 933.21
Labour for cement mortar 1:3 1.60
Labour As per item no :1144060000 0.32
TOTAL : 935.13
WATER CHARGES @ 1.5% : 37.82
TOTAL : 972.95
ADD FOR CONTRACTORS PROFIT @10% : 97.30
ADD FOR OVER HEAD CHARGES @5% : 48.65
LABOUR FOR 1.000 sq.m. 1118.90
LABOUR PER sq.m. 1118.90
MATERIAL :
CARRIAGE :
Cement,G.I.,C.I.,A.C.,C.C.pipe
1 KM BY MECH. TRANSPORT 1 Tonne. 0.0800 73.95 5.92
LABOUR :
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 2296.18
ADD FOR WATER CHARGES @ 1.5% : 34.44
TOTAL : 2330.62
ADD FOR CONTRACTORS PROFIT @ 10% 233.06
ADD FOR OVER HEAD CHARGES @5% : 116.53
COST FOR 1.000 sq.m. 2680.22
COST PER sq.m. 2680.20
LABOUR PER sq.m. 1115.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 933.21
Labour for cement mortar 1:3 1.60
Labour As per item no :1144060000 0.32
TOTAL : 935.13
WATER CHARGES @ 1.5% : 34.44
TOTAL : 969.57
ADD FOR CONTRACTORS PROFIT @10% : 96.96
ADD FOR OVER HEAD CHARGES @5% : 48.48
LABOUR FOR 1.000 sq.m. 1115.01
LABOUR PER sq.m. 1115.00
MATERIAL :
CARRIAGE :
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Cement,G.I.,C.I.,A.C.,C.C.pipe
1 KM BY MECH. TRANSPORT 1 Tonne. 0.0800 73.95 5.92
LABOUR :
TOTAL : 2821.18
ADD FOR WATER CHARGES @ 1.5% : 42.32
TOTAL : 2863.50
ADD FOR CONTRACTORS PROFIT @ 10% 286.35
ADD FOR OVER HEAD CHARGES @5% : 143.17
COST FOR 1.000 sq.m. 3293.04
COST PER sq.m. 3293.05
LABOUR PER sq.m. 1124.10
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 933.21
Labour for cement mortar 1:3 1.60
Labour As per item no :1144060000 0.32
TOTAL : 935.13
WATER CHARGES @ 1.5% : 42.32
TOTAL : 977.45
ADD FOR CONTRACTORS PROFIT @10% : 97.75
ADD FOR OVER HEAD CHARGES @5% : 48.88
LABOUR FOR 1.000 sq.m. 1124.08
LABOUR PER sq.m. 1124.10
MATERIAL :
CARRIAGE :
Cement,G.I.,C.I.,A.C.,C.C.pipe
1 KM BY MECH. TRANSPORT 1 Tonne. 0.0800 73.95 5.92
LABOUR :
TOTAL : 1921.18
ADD FOR WATER CHARGES @ 1.5% : 28.82
TOTAL : 1950.00
ADD FOR CONTRACTORS PROFIT @ 10% 195.00
ADD FOR OVER HEAD CHARGES @5% : 97.50
COST FOR 1.000 sq.m. 2242.50
COST PER sq.m. 2242.50
LABOUR PER sq.m. 1108.55
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 933.21
Labour for cement mortar 1:3 1.60
Labour As per item no :1144060000 0.32
TOTAL : 935.13
WATER CHARGES @ 1.5% : 28.82
TOTAL : 963.95
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR CONTRACTORS PROFIT @10% : 96.40
ADD FOR OVER HEAD CHARGES @5% : 48.20
LABOUR FOR 1.000 sq.m. 1108.55
LABOUR PER sq.m. 1108.55
MATERIAL :
CARRIAGE :
Cement,G.I.,C.I.,A.C.,C.C.pipe
1 KM BY MECH. TRANSPORT 1 Tonne. 0.0800 73.95 5.92
LABOUR :
TOTAL : 1771.18
ADD FOR WATER CHARGES @ 1.5% : 26.58
TOTAL : 1797.76
ADD FOR CONTRACTORS PROFIT @ 10% 179.78
ADD FOR OVER HEAD CHARGES @5% : 89.89
COST FOR 1.000 sq.m. 2067.42
COST PER sq.m. 2067.45
LABOUR PER sq.m. 1105.95
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 933.21
Labour for cement mortar 1:3 1.60
Labour As per item no :1144060000 0.32
TOTAL : 935.13
WATER CHARGES @ 1.5% : 26.57
TOTAL : 961.70
ADD FOR CONTRACTORS PROFIT @10% : 96.17
ADD FOR OVER HEAD CHARGES @5% : 48.09
LABOUR FOR 1.000 sq.m. 1105.96
LABOUR PER sq.m. 1105.95
MATERIAL :
LABOUR :
For dressing/fixing dowel L.S 3.00
TOTAL : 8.47
ADD FOR WATER CHARGES @ 1.5% : 0.13
TOTAL : 8.60
ADD FOR CONTRACTORS PROFIT @ 10% 0.86
ADD FOR OVER HEAD CHARGES @5% : 0.43
COST FOR 1.000 dowel 9.89
COST PER dowel 9.90
LABOUR PER dowel 3.70
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 3.00
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Labour for cement mortar 1:2 0.11
TOTAL : 3.11
WATER CHARGES @ 1.5% : 0.13
TOTAL : 3.24
ADD FOR CONTRACTORS PROFIT @10% : 0.32
ADD FOR OVER HEAD CHARGES @5% : 0.16
LABOUR FOR 1.000 dowel 3.72
LABOUR PER dowel 3.70
MATERIAL :
LABOUR :
Labour for fixing cramp L.S 4.50
TOTAL : 53.47
ADD FOR WATER CHARGES @ 1.5% : 0.80
TOTAL : 54.27
ADD FOR CONTRACTORS PROFIT @ 10% 5.43
ADD FOR OVER HEAD CHARGES @5% : 2.71
COST FOR 1.000 Cramp 62.41
COST PER Cramp 62.40
LABOUR PER Cramp 6.20
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 4.50
Labour for cement mortar 1:2 0.11
TOTAL : 4.61
WATER CHARGES @ 1.5% : 0.80
TOTAL : 5.41
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR CONTRACTORS PROFIT @10% : 0.54
ADD FOR OVER HEAD CHARGES @5% : 0.27
LABOUR FOR 1.000 Cramp 6.22
LABOUR PER Cramp 6.20
MATERIAL :
LABOUR :
Fixing Cramp in position L.S 4.50
TOTAL : 33.47
ADD FOR WATER CHARGES @ 1.5% : 0.50
TOTAL : 33.97
ADD FOR CONTRACTORS PROFIT @ 10% 3.40
ADD FOR OVER HEAD CHARGES @5% : 1.70
COST FOR 1.000 Cramp 39.07
COST PER Cramp 39.05
LABOUR PER Cramp 5.90
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 4.50
Labour for cement mortar 1:2 0.11
TOTAL : 4.61
WATER CHARGES @ 1.5% : 0.50
TOTAL : 5.11
ADD FOR CONTRACTORS PROFIT @10% : 0.51
ADD FOR OVER HEAD CHARGES @5% : 0.26
LABOUR FOR 1.000 Cramp 5.88
LABOUR PER Cramp 5.90
LABOUR :
Labour for fixing L.S 2.00
TOTAL : 30.97
ADD FOR WATER CHARGES @ 1.5% : 0.46
TOTAL : 31.43
ADD FOR CONTRACTORS PROFIT @ 10% 3.14
ADD FOR OVER HEAD CHARGES @5% : 1.57
COST FOR 1.000 copper pin 36.14
COST PER copper pin 36.15
LABOUR PER copper pin 2.95
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 2.00
Labour for cement mortar 1:2 0.10
TOTAL : 2.10
WATER CHARGES @ 1.5% : 0.46
TOTAL : 2.56
ADD FOR CONTRACTORS PROFIT @10% : 0.26
ADD FOR OVER HEAD CHARGES @5% : 0.13
LABOUR FOR 1.000 copper pin 2.95
LABOUR PER copper pin 2.95
MATERIAL :
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Finished work =40 cudm.
Add for wastage @ 20 % =8 cudm
Total =48 cu.dm.
Cost of marble 10 cu.dm48.0000 750.00 3600.00
CARRIAGE :
Cement,G.I.,C.I.,A.C.,C.C.pipe
1 KM BY MECH. TRANSPORT 1 Tonne. 0.1300 73.95 9.61
LABOUR :
Rate as per item no. : 1144040000 387.56
TOTAL : 4645.51
ADD FOR WATER CHARGES @ 1.5% : 69.68
TOTAL : 4715.19
ADD FOR CONTRACTORS PROFIT @ 10% 471.52
ADD FOR OVER HEAD CHARGES @5% : 235.76
COST FOR 1.000 Sqm. 5422.47
COST PER Sqm. 5422.50
LABOUR PER Sqm. 1156.35
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 933.21
Labour for cement mortar 1:3 2.29
Labour As per item no :1144060000 0.32
TOTAL : 935.82
WATER CHARGES @ 1.5% : 69.68
TOTAL : 1005.50
ADD FOR CONTRACTORS PROFIT @10% : 100.55
ADD FOR OVER HEAD CHARGES @5% : 50.28
LABOUR FOR 1.000 Sqm. 1156.33
LABOUR PER Sqm. 1156.35
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
CARRIAGE :
Cement,G.I.,C.I.,A.C.,C.C.pipe
1 KM BY MECH. TRANSPORT 1 Tonne. 0.1300 73.95 9.61
LABOUR :
Rate as per item no. : 1144040000 387.56
TOTAL : 3445.51
ADD FOR WATER CHARGES @ 1.5% : 51.68
TOTAL : 3497.19
ADD FOR CONTRACTORS PROFIT @ 10% 349.72
ADD FOR OVER HEAD CHARGES @5% : 174.86
COST FOR 1.000 Sqm. 4021.77
COST PER Sqm. 4021.80
LABOUR PER Sqm. 1135.65
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 933.21
Labour for cement mortar 1:3 2.29
Labour As per item no :1144060000 0.32
TOTAL : 935.82
WATER CHARGES @ 1.5% : 51.68
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 987.50
ADD FOR CONTRACTORS PROFIT @10% : 98.75
ADD FOR OVER HEAD CHARGES @5% : 49.38
LABOUR FOR 1.000 Sqm. 1135.63
LABOUR PER Sqm. 1135.65
MATERIAL :
CARRIAGE :
Cement,G.I.,C.I.,A.C.,C.C.pipe
1 KM BY MECH. TRANSPORT 1 Tonne. 0.1300 73.95 9.61
LABOUR :
Rate as per item no. : 1144040000 387.56
TOTAL : 3085.51
ADD FOR WATER CHARGES @ 1.5% : 46.28
TOTAL : 3131.79
ADD FOR CONTRACTORS PROFIT @ 10% 313.18
ADD FOR OVER HEAD CHARGES @5% : 156.59
COST FOR 1.000 Sqm. 3601.56
COST PER Sqm. 3601.55
LABOUR PER Sqm. 1129.40
LABOUR RATE :
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ACTUAL LABOUR+SUNDRIES 933.21
Labour for cement mortar 1:3 2.29
Labour As per item no :1144060000 0.32
TOTAL : 935.82
WATER CHARGES @ 1.5% : 46.28
TOTAL : 982.10
ADD FOR CONTRACTORS PROFIT @10% : 98.21
ADD FOR OVER HEAD CHARGES @5% : 49.11
LABOUR FOR 1.000 Sqm. 1129.42
LABOUR PER Sqm. 1129.40
MATERIAL :
CARRIAGE :
Cement,G.I.,C.I.,A.C.,C.C.pipe
1 KM BY MECH. TRANSPORT 1 Tonne. 0.1300 73.95 9.61
LABOUR :
Rate as per item no. : 1144040000 387.56
TOTAL : 3925.51
ADD FOR WATER CHARGES @ 1.5% : 58.88
TOTAL : 3984.39
ADD FOR CONTRACTORS PROFIT @ 10% 398.44
ADD FOR OVER HEAD CHARGES @5% : 199.22
COST FOR 1.000 Sqm. 4582.05
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
COST PER Sqm. 4582.05
LABOUR PER Sqm. 1143.90
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 933.21
Labour for cement mortar 1:3 2.29
Labour As per item no :1144060000 0.32
TOTAL : 935.82
WATER CHARGES @ 1.5% : 58.88
TOTAL : 994.70
ADD FOR CONTRACTORS PROFIT @10% : 99.47
ADD FOR OVER HEAD CHARGES @5% : 49.74
LABOUR FOR 1.000 Sqm. 1143.91
LABOUR PER Sqm. 1143.90
MATERIAL :
CARRIAGE :
Cement,G.I.,C.I.,A.C.,C.C.pipe
1 KM BY MECH. TRANSPORT 1 Tonne. 0.1300 73.95 9.61
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR :
Rate as per item no. : 1144040000 387.56
TOTAL : 2485.51
ADD FOR WATER CHARGES @ 1.5% : 37.28
TOTAL : 2522.79
ADD FOR CONTRACTORS PROFIT @ 10% 252.28
ADD FOR OVER HEAD CHARGES @5% : 126.14
COST FOR 1.000 Sqm. 2901.21
COST PER Sqm. 2901.20
LABOUR PER Sqm. 1119.05
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 933.21
Labour for cement mortar 1:3 2.29
Labour As per item no :1144060000 0.32
TOTAL : 935.82
WATER CHARGES @ 1.5% : 37.28
TOTAL : 973.10
ADD FOR CONTRACTORS PROFIT @10% : 97.31
ADD FOR OVER HEAD CHARGES @5% : 48.66
LABOUR FOR 1.000 Sqm. 1119.07
LABOUR PER Sqm. 1119.05
MATERIAL :
Cement,G.I.,C.I.,A.C.,C.C.pipe
1 KM BY MECH. TRANSPORT 1 Tonne. 0.1300 73.95 9.61
LABOUR :
Rate as per item no. : 1144040000 387.56
TOTAL : 2245.51
ADD FOR WATER CHARGES @ 1.5% : 33.68
TOTAL : 2279.19
ADD FOR CONTRACTORS PROFIT @ 10% 227.92
ADD FOR OVER HEAD CHARGES @5% : 113.96
COST FOR 1.000 Sqm. 2621.07
COST PER Sqm. 2621.10
LABOUR PER Sqm. 1114.95
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 933.21
Labour for cement mortar 1:3 2.29
Labour As per item no :1144060000 0.32
TOTAL : 935.82
WATER CHARGES @ 1.5% : 33.68
TOTAL : 969.50
ADD FOR CONTRACTORS PROFIT @10% : 96.95
ADD FOR OVER HEAD CHARGES @5% : 48.48
LABOUR FOR 1.000 Sqm. 1114.93
LABOUR PER Sqm. 1114.95
MATERIAL :
CARRIAGE :
Cement,G.I.,C.I.,A.C.,C.C.pipe
1 KM BY MECH. TRANSPORT 1 Tonne. 0.1300 73.95 9.61
LABOUR :
Mason for plain marble work Each 16.1600 158.67 2564.11
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 3968.31
Labour As per item no :1144060000 0.64
TOTAL : 3968.95
WATER CHARGES @ 1.5% : 114.78
TOTAL : 4083.73
ADD FOR CONTRACTORS PROFIT @10% : 408.37
ADD FOR OVER HEAD CHARGES @5% : 204.19
LABOUR FOR 1.000 sqm. 4696.29
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR PER sqm. 4696.30
MATERIAL :
CARRIAGE :
Cement,G.I.,C.I.,A.C.,C.C.pipe
1 KM BY MECH. TRANSPORT 1 Tonne. 0.1300 73.95 9.61
LABOUR :
Mason for plain marble work Each 16.1600 158.67 2564.11
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 3968.31
Labour As per item no :1144060000 0.64
TOTAL : 3968.95
WATER CHARGES @ 1.5% : 96.78
TOTAL : 4065.73
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR CONTRACTORS PROFIT @10% : 406.57
ADD FOR OVER HEAD CHARGES @5% : 203.29
LABOUR FOR 1.000 sqm. 4675.59
LABOUR PER sqm. 4675.60
MATERIAL :
CARRIAGE :
Cement,G.I.,C.I.,A.C.,C.C.pipe
1 KM BY MECH. TRANSPORT 1 Tonne. 0.1300 73.95 9.61
LABOUR :
Mason for plain marble work Each 16.1600 158.67 2564.11
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 3968.31
Labour As per item no :1144060000 0.64
TOTAL : 3968.95
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
WATER CHARGES @ 1.5% : 91.38
TOTAL : 4060.33
ADD FOR CONTRACTORS PROFIT @10% : 406.03
ADD FOR OVER HEAD CHARGES @5% : 203.02
LABOUR FOR 1.000 sqm. 4669.38
LABOUR PER sqm. 4669.40
MATERIAL :
CARRIAGE :
Cement,G.I.,C.I.,A.C.,C.C.pipe
1 KM BY MECH. TRANSPORT 1 Tonne. 0.1300 73.95 9.61
LABOUR :
Mason for plain marble work Each 16.1600 158.67 2564.11
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 3968.31
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Labour As per item no :1144060000 0.64
TOTAL : 3968.95
WATER CHARGES @ 1.5% : 103.98
TOTAL : 4072.93
ADD FOR CONTRACTORS PROFIT @10% : 407.29
ADD FOR OVER HEAD CHARGES @5% : 203.65
LABOUR FOR 1.000 sqm. 4683.87
LABOUR PER sqm. 4683.85
MATERIAL :
CARRIAGE :
Cement,G.I.,C.I.,A.C.,C.C.pipe
1 KM BY MECH. TRANSPORT 1 Tonne. 0.1300 73.95 9.61
LABOUR :
Mason for plain marble work Each 16.1600 158.67 2564.11
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 3968.31
Labour As per item no :1144060000 0.64
TOTAL : 3968.95
WATER CHARGES @ 1.5% : 82.38
TOTAL : 4051.33
ADD FOR CONTRACTORS PROFIT @10% : 405.13
ADD FOR OVER HEAD CHARGES @5% : 202.57
LABOUR FOR 1.000 sqm. 4659.03
LABOUR PER sqm. 4659.05
MATERIAL :
CARRIAGE :
Cement,G.I.,C.I.,A.C.,C.C.pipe
1 KM BY MECH. TRANSPORT 1 Tonne. 0.1300 73.95 9.61
LABOUR :
Mason for plain marble work Each 16.1600 158.67 2564.11
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Beldar Each 10.7500 116.67 1254.20
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 3968.31
Labour As per item no :1144060000 0.64
TOTAL : 3968.95
WATER CHARGES @ 1.5% : 78.78
TOTAL : 4047.73
ADD FOR CONTRACTORS PROFIT @10% : 404.77
ADD FOR OVER HEAD CHARGES @5% : 202.39
LABOUR FOR 1.000 sqm. 4654.89
LABOUR PER sqm. 4654.90
(3.11mx3.11m=9.67 sq.m.)
MATERIAL :
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Deodar wood second class
Verticles:
3 Nos.(3.11 metre length)
x0.11x0.11m=0.1129 cum.
Horizontal :
Top and Bottom 2 nos.(2.78 metre
length)x0.11x0.11 metre
Central:
2Nos.(2.78 metre length)x0.05x0.11
Braces:
1.67m + 1.67m. =3.34 metre
6 Nos.(3.34m. length)x0.04mx0.11m
Rate as per item no. 120020200 1 cum. 0.2990 61863.50 18497.19 (-I-)
Salignum painting:
1.39+1.29 + 0.9340 +0.93 =4.64R.M.
1.67+1.67=3.34 R.M x 2.=6.68 R.M.
Total =11.32 R.M.
11.32 R.M. x0.11 M =1.22 sq.m.
1.25 x6 Nos. 7.50 sq.m.
Rate as per item no. 1603800 1 sqm. 7.5000 27.35 205.13 (-I-)
Wire Netting:
Wire netting 12mm -20 mm mesh
Verticles:
3 Nos. (3.11m length) x0.11 m =
1.0263 sq.m.
Horizontal:
Top and Bottom.
2 Nos. (2.78 m length)x0.11=0.6116
sq.m.
Central:
2 Nos.(2.78 m length) x 0.05=0.2780
sq.m.
Braces 6 Nos.(3.34 m length)x 0.04
m = 0.8016 sqm.
total =2.7155 sqm.
2.7155x2(being both side)5.44sq.m.
Add wastage @ 5% 0.27 sq.m.
Total =5.71 sq.m. 1 sqm. 5.7100 60.00 342.60
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR :
Labour L.S 14.20
SUNDRIES : L.S 28.50
TOTAL : 21412.71
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 42.70
MATERIAL :
Solignum painting:-
1.39m+1.39m+0.93m =4.64Rmt.
1.67m+1.67m =3.34x2=6.68Rmt
Total:- 11.32Rmt.
11.32m+0.11mx1.25x6Nos=7.50Sqm.
Rate same as per item no160380000
1 sqm. 7.5000 27.35 205.13 (-I-)
Wire Netting:
Wire netting 12mm -20 mm mesh
Verticles:
3 Nos. (3.11m length) x0.11 m =
1.0263 sq.m.
Horizontal:
Top and Bottom.
2 Nos. (2.78 m length)x0.11=0.6116
sq.m.
Central:
2 Nos.(2.78 m length) x 0.05=0.2780
sq.m.
Braces 6 Nos.(3.34 m length)x 0.04
m = 0.8016 sqm.
total =2.7155 sqm.
2.7155x2(being both side)5.44sq.m.
Add wastage @ 5% 0.27 sq.m.
Total =5.71 sq.m. 1 Sqm. 5.7100 60.00 342.60
LABOUR :
Labour L.S 14.20
SUNDRIES : L.S 28.50
TOTAL : 21084.99
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 42.70
MATERIAL :
Solignum painting:-
1.39m+1.39m+0.93m =4.64Rmt.
1.67m+1.67m =3.34x2=6.68Rmt
Total:- 11.32Rmt.
11.32m+0.11mx1.25x6Nos=7.50Sqm.
Rate same as per item no160380000
1 sqm. 7.5000 27.35 205.13 (-I-)
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Wire Netting:
Wire netting 12mm -20 mm mesh
Verticles:
3 Nos. (3.11m length) x0.11 m =
1.0263 sq.m.
Horizontal:
Top and Bottom.
2 Nos. (2.78 m length)x0.11=0.6116
sq.m.
Central:
2 Nos.(2.78 m length) x 0.05=0.2780
sq.m.
Braces 6 Nos.(3.34 m length)x 0.04
m = 0.8016 sqm.
total =2.7155 sqm.
2.7155x2(being both side)5.44sq.m.
Add wastage @ 5% 0.27 sq.m.
Total =5.71 sq.m. 1 sqm. 5.7100 60.00 342.60
LABOUR :
Labour L.S 14.20
SUNDRIES : L.S 28.50
TOTAL : 15685.48
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 42.70
MATERIAL :
Solignum painting:-
1.39m+1.39m+0.93m =4.64Rmt.
1.67m+1.67m =3.34x2=6.68Rmt
Total:- 11.32Rmt.
11.32m+0.11mx1.25x6Nos=7.50Sqm.
Rate same as per item no160380000
1 Sqm. 7.5000 27.35 205.13 (-I-)
Wire Netting:
Wire netting 12mm -20 mm mesh
Verticles:
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
3 Nos. (3.11m length) x0.11 m =
1.0263 sq.m.
Horizontal:
Top and Bottom.
2 Nos. (2.78 m length)x0.11=0.6116
sq.m.
Central:
2 Nos.(2.78 m length) x 0.05=0.2780
sq.m.
Braces 6 Nos.(3.34 m length)x 0.04
m = 0.8016 sqm.
total =2.7155 sqm.
2.7155x2(being both side)5.44sq.m.
Add wastage @ 5% 0.27 sq.m.
Total =5.71 sq.m. 1 sqm. 5.7100 60.00 342.60
LABOUR :
Labour L.S 14.20
SUNDRIES : L.S 28.50
TOTAL : 16865.95
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 42.70
MATERIAL :
LABOUR :
Extra labour for two line dressing
Rate as per item no 1117030000 1 Sqm 1.0000 158.80 158.80
Extra labour for super structure
Rate as per item no 1108010100 1 Cum 0.1500 120.25 18.04
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 176.84
For square rubble masonary
Labour As per item no :1107010400 221.75
For cement concrete 1:3:6
Labour for 09210200 23.00
For form work with steel plates
Labour for Centreing and shuttering 52.12
LABOUR FOR 1.000 Sq.m. 473.74
LABOUR PER Sq.m. 473.75
Material
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Precast concrete hollow blocks size
40cmx19cmx20cm =0.01482 cum
Total qty. of detail =1.89 cum
Less qty. of cement mortar =0.18 cum
Nett. Qty of blocks = 1.71 cum
Hence total Nos. of blocks
=(1.71/0.01482) =115 Nos.
Each 115.0000 25.00 2875.00
CARRIAGE :
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1021.61
WATER CHARGES @ 1.5% : 64.18
TOTAL : 1085.76
ADD FOR CONTRACTORS PROFIT @10% : 108.58
ADD FOR OVER HEAD CHARGES @5% : 54.29
LABOUR FOR 1.89 cum 1248.65
LABOUR PER Cum 660.65
Stone Masonry Precast Concrete Block Masonry and Marble Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
1163000000 Providing and laying precast cement
concrete hollow block masonry in
wall with cement concrete blocks of
size 40cm x 19cm x20 cm i/c quion
blocks, jamb blocks and closers etc.
made of cement concrete 1:4:8 (1
cement : 4 sand : 8 graded stone
aggregate 25mm nominal size) laid
with cement mortar 1:6 (1 cement :
6 sand) and curing complete in
super structure upto floor two level.
Material
CARRIAGE :
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1021.61
WATER CHARGES @ 1.5% : 55.55
TOTAL : 1077.16
ADD FOR CONTRACTORS PROFIT @10% : 107.71
ADD FOR OVER HEAD CHARGES @5% : 53.85
LABOUR FOR 1.89 cum 1238.72
LABOUR PER Cum 655.40
Confidential
For Office use
VOLUME - III
ANALYSIS FOR SCHEDULE OF RATES 2009
(VOLUME III)
CONTENTS
Chapter No. Name of Sub-head Page No.
XII Wood Work 683 to 1254
CHAPTER XII
WOOD WORK
Chapter XII
WOOD WORK
Notes :-
1 The through rates includes the carriage of all material for 100 meters on head load
and 1 kilometer by mechanical transport .
2 The through rates include all wastage of timber in sawing and cutting and sawing
charges.
3. The labour rates include the cost of tools and plants and scaffolding wherever
required .
CHAPTER-XII
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.03800 110.95 4.21
LABOUR :
Carpenter 1st Class each 0.60000 211.16 126.70
Beldar each 0.30000 116.67 35.00
Mason 2nd Class each 0.03000 158.67 4.76
TOTAL : 3817.58
ADD FOR CONTRACTORS PROFIT 10% 381.75
ADD FOR OVER HEAD CHARGES @5% 190.87
COST FOR 0.036 cum 4390.20
COST PER cum 121959.00
LABOUR PER cum 5317.20
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 166.46
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 166.46
ADD FOR CONTRACTORS PROFIT @10% : 16.64
ADD FOR OVER HEAD CHARGES @5% : 8.32
LABOUR FOR 0.036 cum 191.42
LABOUR PER cum 5317.20
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.03800 110.95 4.21
LABOUR :
Carpenter 1st Class each 0.60000 211.16 126.70
Beldar each 0.30000 116.67 35.00
Mason 2nd Class each 0.03000 158.67 4.76
TOTAL : 3105.27
ADD FOR CONTRACTORS PROFIT 10% 310.52
ADD FOR OVER HEAD CHARGES @5% 155.26
COST FOR 0.036 cum 3571.05
COST PER cum 99195.80
LABOUR PER cum 5317.20
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 166.46
TOTAL : 166.46
ADD FOR CONTRACTORS PROFIT @10% : 16.64
ADD FOR OVER HEAD CHARGES @5% : 8.32
LABOUR FOR 0.036 cum 191.42
LABOUR PER cum 5317.20
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.03800 110.95 4.21
LABOUR :
Carpenter 1st Class each 0.40000 211.16 84.46
Beldar each 0.20000 116.67 23.33
Mason 2nd Class each 0.20000 158.67 3.17
TOTAL : 2110.22
ADD FOR CONTRACTORS PROFIT 10% 211.02
ADD FOR OVER HEAD CHARGES @5% 105.51
COST FOR 0.036 cum 2426.75
COST PER cum 67409.70
LABOUR PER cum 3544.40
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 110.96
TOTAL : 110.96
ADD FOR CONTRACTORS PROFIT @10% : 11.09
ADD FOR OVER HEAD CHARGES @5% : 5.55
LABOUR FOR 0.036 cum 127.60
LABOUR PER cum 3544.40
MATERIAL :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
2nd classdeodar wood.
Qunatity same as in item
no. 1200101000
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.03800 110.95 4.21
LABOUR :
Carpenter 1st Class each 0.40000 211.16 84.46
Beldar each 0.20000 116.67 23.33
Mason 2nd Class each 0.20000 158.67 3.17
TOTAL : 2079.63
ADD FOR CONTRACTORS PROFIT 10% 207.96
ADD FOR OVER HEAD CHARGES @5% 103.98
COST FOR 0.036 cum 2391.57
COST PER cum 66432.50
LABOUR PER cum 3544.40
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 110.46
TOTAL : 110.96
ADD FOR CONTRACTORS PROFIT @10% : 11.09
ADD FOR OVER HEAD CHARGES @5% : 5.55
LABOUR FOR 0.036 cum 127.60
LABOUR PER cum 3544.40
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.03800 110.95 4.21
LABOUR :
Carpenter 1st Class each 0.40000 211.16 84.46
Beldar each 0.20000 116.67 23.33
Mason 2nd Class each 0.20000 158.67 3.17
TOTAL : 2079.63
ADD FOR CONTRACTORS PROFIT 10% 207.96
ADD FOR OVER HEAD CHARGES @5% 103.98
COST FOR 0.036 cum 2391.57
COST PER cum 66432.50
LABOUR PER cum 3544.40
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 110.96
TOTAL : 110.96
ADD FOR CONTRACTORS PROFIT @10% : 11.09
ADD FOR OVER HEAD CHARGES @5% : 5.55
LABOUR FOR 0.036 cum 127.60
LABOUR PER cum 3544.40
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.03800 110.95 4.21
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR :
Carpenter 1st Class each 0.40000 211.16 84.46
Beldar each 0.20000 116.67 23.33
Mason 2nd Class each 0.02000 158.67 3.17
TOTAL : 1613.37
ADD FOR CONTRACTORS PROFIT 10% 161.34
ADD FOR OVER HEAD CHARGES @5% 80.67
COST FOR 0.036 cum 1855.38
COST PER cum 51538.20
LABOUR PER cum 3544.40
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 110.96
TOTAL : 110.96
ADD FOR CONTRACTORS PROFIT @10% : 11.09
ADD FOR OVER HEAD CHARGES @5% : 5.55
LABOUR FOR 0.036 cum 127.60
LABOUR PER cum 3544.40
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.03800 110.95 4.21
LABOUR :
Carpenter 1st Class each 0.40000 211.16 84.46
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Beldar each 0.20000 116.67 23.33
Mason 2nd Class each 0.02000 158.67 3.17
TOTAL : 925.95
ADD FOR CONTRACTORS PROFIT 10% 92.60
ADD FOR OVER HEAD CHARGES @5% 46.30
COST FOR 0.036 cum 1064.85
COST PER cum 29579.20
LABOUR PER cum 3544.40
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 110.96
TOTAL : 110.96
ADD FOR CONTRACTORS PROFIT @10% : 11.09
ADD FOR OVER HEAD CHARGES @5% : 5.55
LABOUR FOR 0.036 cum 127.60
LABOUR PER cum 3544.40
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.03800 110.95 4.21
LABOUR :
Carpenter 1st Class each 0.40000 211.16 84.46
Beldar each 0.20000 116.67 23.33
Mason 2nd Class each 0.02000 158.67 3.17
TOTAL : 825.25
ADD FOR CONTRACTORS PROFIT 10% 82.52
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR OVER HEAD CHARGES @5% 41.26
COST FOR 0.036 cum 949.03
COST PER cum 26361.90
LABOUR PER cum 3544.40
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 110.96
TOTAL : 110.96
ADD FOR CONTRACTORS PROFIT @10% : 11.09
ADD FOR OVER HEAD CHARGES @5% : 5.55
LABOUR FOR 0.036 cum 127.60
LABOUR PER cum 3544.40
MATERIAL :
Sal wood.
Qunatity same as in item
no. 1200101000
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.03800 110.95 4.21
LABOUR :
Carpenter 1st Class each 0.40000 211.16 84.46
Beldar each 0.20000 116.67 23.33
Mason 2nd Class each 0.02000 158.67 3.17
TOTAL : 689.97
ADD FOR CONTRACTORS PROFIT 10% 68.99
ADD FOR OVER HEAD CHARGES @5% 34.50
COST FOR 0.036 cum 793.46
COST PER cum 22040.50
LABOUR PER cum 3544.40
LABOUR RATE :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ACTUAL LABOUR+SUNDRIES 110.96
TOTAL : 110.96
ADD FOR CONTRACTORS PROFIT @10% : 11.09
ADD FOR OVER HEAD CHARGES @5% : 5.55
LABOUR FOR 0.036 cum 127.60
LABOUR PER cum 3357.90
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.16600 110.95 18.41
LABOUR :
Carpenter 2nd Class each 1.01000 186.67 188.54
Beldar each 1.01000 116.67 117.84
SUNDRIES : 23.50
TOTAL : 9063.49
ADD FOR CONTRACTORS PROFIT 10% 906.34
ADD FOR OVER HEAD CHARGES @5% 453.17
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
COST FOR 0.158 cum 10423.00
COST PER cum 65968.30
LABOUR PER cum 2400.30
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 329.88
TOTAL : 329.88
ADD FOR CONTRACTORS PROFIT @10% : 32.98
ADD FOR OVER HEAD CHARGES @5% : 16.49
LABOUR FOR 0.158 cum 379.25
LABOUR PER cum 2400.30
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.16600 110.95 18.41
LABOUR :
Carpenter 2nd Class each 1.01000 186.67 188.54
Beldar each 1.01000 116.67 117.84
SUNDRIES : 23.50
TOTAL : 8929.86
ADD FOR CONTRACTORS PROFIT 10% 892.98
ADD FOR OVER HEAD CHARGES @5% 446.49
COST FOR 0.158 cum 10269.33
COST PER cum 64995.70
LABOUR PER cum 2400.30
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 329.88
TOTAL : 329.88
ADD FOR CONTRACTORS PROFIT @10% : 32.98
ADD FOR OVER HEAD CHARGES @5% : 16.49
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR FOR 0.158 cum 379.25
LABOUR PER cum 2400.30
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.16600 110.95 18.41
LABOUR :
Carpenter 2nd Class each 1.01000 186.67 188.54
Beldar each 1.01000 116.67 117.84
SUNDRIES : 23.50
TOTAL : 8929.86
ADD FOR CONTRACTORS PROFIT 10% 892.98
ADD FOR OVER HEAD CHARGES @5% 446.49
COST FOR 0.158 cum 10269.33
COST PER cum 64995.70
LABOUR PER cum 2400.30
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 329.88
TOTAL : 329.88
ADD FOR CONTRACTORS PROFIT @10% : 32.98
ADD FOR OVER HEAD CHARGES @5% : 16.49
LABOUR FOR 0.158 cum 379.25
LABOUR PER cum 24400.30
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.16600 110.95 18.41
LABOUR :
Carpenter 2nd Class each 1.01000 186.67 188.54
Beldar each 1.01000 116.67 117.84
SUNDRIES : 23.50
TOTAL : 6893.04
ADD FOR CONTRACTORS PROFIT 10% 689.30
ADD FOR OVER HEAD CHARGES @5% 344.65
COST FOR 0.158 cum 7926.99
COST PER cum 50170.80
LABOUR PER cum 2400.30
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 329.88
TOTAL : 329.88
ADD FOR CONTRACTORS PROFIT @10% : 32.98
ADD FOR OVER HEAD CHARGES @5% : 16.49
LABOUR FOR 0.158 cum 379.25
LABOUR PER cum 2400.30
MATERIAL :
CARRIAGE :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.16600 110.95 18.41
LABOUR :
Carpenter 2nd Class each 1.01000 186.67 188.54
Beldar each 1.01000 116.67 117.84
SUNDRIES : 23.50
TOTAL : 3890.10
ADD FOR CONTRACTORS PROFIT 10% 389.00
ADD FOR OVER HEAD CHARGES @5% 194.50
COST FOR 0.158 cum 4473.60
COST PER cum 28313.90
LABOUR PER cum 2400.30
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 329.88
TOTAL : 329.88
ADD FOR CONTRACTORS PROFIT @10% : 32.98
ADD FOR OVER HEAD CHARGES @5% : 16.49
LABOUR FOR 0.158 cum 379.35
LABOUR PER cum 2400.30
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.16600 110.95 18.41
LABOUR :
Carpenter 2nd Class each 1.01000 186.67 188.54
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Beldar each 1.01000 116.67 117.84
SUNDRIES : 23.50
TOTAL : 3450.20
ADD FOR CONTRACTORS PROFIT 10% 345.02
ADD FOR OVER HEAD CHARGES @5% 172.51
COST FOR 0.158 cum 3967.73
COST PER cum 25112.20
LABOUR PER cum 2400.30
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 329.88
TOTAL : 329.88
ADD FOR CONTRACTORS PROFIT @10% : 32.98
ADD FOR OVER HEAD CHARGES @5% : 16.49
LABOUR FOR 0.158 cum 379.35
LABOUR PER cum 2400.30
MATERIAL :
Sal wood
Qunatity same as in item
no. 1200201000 1 cum 0.16600 15090.00 2504.94
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.16600 110.95 18.41
LABOUR :
Carpenter 2nd Class each 1.01000 186.67 188.54
Beldar each 1.01000 116.67 117.84
SUNDRIES : 23.50
TOTAL : 2859.24
ADD FOR CONTRACTORS PROFIT 10% 285.92
ADD FOR OVER HEAD CHARGES @5% 142.96
COST FOR 0.158 cum 3288.12
COST PER cum 20810.90
LABOUR PER cum 2400.30
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 329.88
TOTAL : 329.88
ADD FOR CONTRACTORS PROFIT @10% : 32.98
ADD FOR OVER HEAD CHARGES @5% : 16.49
LABOUR FOR 0.158 cum 379.35
LABOUR PER cum 2400.30
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.04400 110.95 4.88
LABOUR :
Carpenter 1st Class each 0.38000 211.16 80.24
Beldar each 0.46000 116.67 53.67
Mason 2nd Class each 0.02000 158.67 3.17
TOTAL : 2452.02
ADD FOR CONTRACTORS PROFIT 10% 245.20
ADD FOR OVER HEAD CHARGES @5% 122.60
COST FOR 0.042 cum 2819.82
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
COST PER cum 67138.60
LABOUR PER cum 3752.40
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 137.07
TOTAL : 137.07
ADD FOR CONTRACTORS PROFIT @10% : 13.70
ADD FOR OVER HEAD CHARGES @5% : 6.85
LABOUR FOR 0.042 cum 157.62
LABOUR PER cum 3752.40
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.04400 110.95 4.88
LABOUR :
Carpenter 1st Class each 0.38000 211.16 80.24
Beldar each 0.46000 116.67 53.67
Mason 2nd Class each 0.02000 158.67 3.17
TOTAL : 2416.60
ADD FOR CONTRACTORS PROFIT 10% 241.66
ADD FOR OVER HEAD CHARGES @5% 120.83
COST FOR 0.042 cum 2779.09
COST PER cum 66168.80
LABOUR PER cum 3752.40
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 137.07
TOTAL : 137.07
ADD FOR CONTRACTORS PROFIT @10% : 13.70
ADD FOR OVER HEAD CHARGES @5% : 6.85
LABOUR FOR 0.0.42 cum 157.62
LABOUR PER cum 3752.40
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
Sal wood
Qty. same as in item no. 1200301000
1 cum 0.04400 15090.00 663.96
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.04400 110.95 4.88
LABOUR :
Carpenter 1st Class each 0.38000 211.16 80.24
Beldar each 0.46000 116.67 53.67
Mason 2nd Class each 0.02000 158.67 3.17
TOTAL : 807.52
ADD FOR CONTRACTORS PROFIT 10% 80.75
ADD FOR OVER HEAD CHARGES @5% 40.38
COST FOR 0.042 cum 928.65
COST PER cum 22110.70
LABOUR PER cum 3752.40
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 137.07
TOTAL : 137.07
ADD FOR CONTRACTORS PROFIT @10% : 13.70
ADD FOR OVER HEAD CHARGES @5% : 6.85
LABOUR FOR 0.0.42 cum 157.62
LABOUR PER cum 3752.40
MATERIAL :
MATERIAL :
MATERIAL :
MATERIAL :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
MATERIAL :
MATERIAL :
MATERIAL :
MATERIAL :
1200501000 50 mm thick.
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.09000 110.95 9.99
LABOUR :
Carpenter 1st Class each 4.53000 211.16 956.55
Beldar each 1.29000 116.67 150.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1177.05
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 1177.05
ADD FOR CONTRACTORS PROFIT @10% : 117.70
ADD FOR OVER HEAD CHARGES @5% : 58.85
LABOUR FOR 2.160 Sqm 1353.60
LABOUR PER sqm 626.65
MATERIAL :
2ND CLASS Indian Teak wood.
Qty same as in item no. 1200501010 1 cum 0.09000 79390.00 7145.10
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.09000 110.95 9.99
LABOUR :
Carpenter 1st Class each 4.53000 211.16 956.55
Beldar each 1.29000 116.67 150.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1177.05
TOTAL : 1177.05
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR CONTRACTORS PROFIT @10% : 117.70
ADD FOR OVER HEAD CHARGES @5% : 58.85
LABOUR FOR 2.160 Sqm 1353.60
LABOUR PER sqm 626.65
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.09000 110.95 9.99
LABOUR :
Carpenter 1st Class each 3.02000 211.16 637.70
Beldar each 0.86000 116.67 100.34
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.09000 110.95 9.99
LABOUR :
Carpenter 1st Class each 3.02000 211.16 637.70
Beldar each 0.86000 116.67 100.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 783.05
TOTAL : 783.05
ADD FOR CONTRACTORS PROFIT @10% : 78.30
ADD FOR OVER HEAD CHARGES @5% : 39.15
LABOUR FOR 2.160 Sqm 900.50
LABOUR PER sqm 416.90
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.09000 110.95 9.99
LABOUR :
Carpenter 1st Class each 3.02000 211.16 637.70
Beldar each 0.86000 116.67 100.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 783.05
TOTAL : 783.05
ADD FOR CONTRACTORS PROFIT @10% : 78.30
ADD FOR OVER HEAD CHARGES @5% : 39.15
LABOUR FOR 2.160 Sqm 900.50
LABOUR PER sqm 416.90
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.09000 110.95 9.99
LABOUR :
Carpenter 1st Class each 3.02000 211.16 637.70
Beldar each 0.86000 116.67 100.34
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 783.05
TOTAL : 783.05
ADD FOR CONTRACTORS PROFIT @10% : 78.30
ADD FOR OVER HEAD CHARGES @5% : 39.15
LABOUR FOR 2.160 Sqm 900.50
LABOUR PER sqm 416.90
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.09000 110.95 9.99
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 783.05
TOTAL : 783.05
ADD FOR CONTRACTORS PROFIT @10% : 78.30
ADD FOR OVER HEAD CHARGES @5% : 39.15
LABOUR FOR 2.160 Sqm 900.50
LABOUR PER sqm 416.90
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.09000 110.95 9.99
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
100 MTRS BY HEAD LOAD 1 cum 0.09000 36.25 3.26
LABOUR :
Carpenter 1st Class each 3.02000 211.16 637.70
Beldar each 0.86000 116.67 100.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 783.05
TOTAL : 783.05
ADD FOR CONTRACTORS PROFIT @10% : 78.30
ADD FOR OVER HEAD CHARGES @5% : 39.15
LABOUR FOR 2.160 Sqm 900.50
LABOUR PER sqm 416.90
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.08500 110.95 9.43
LABOUR :
Carpenter 1st Class each 4.53000 211.16 956.55
Beldar each 1.29000 116.67 150.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1177.05
TOTAL : 1177.05
ADD FOR CONTRACTORS PROFIT @10% : 117.70
ADD FOR OVER HEAD CHARGES @5% : 58.85
LABOUR FOR 2.160 Sqm 1353.60
LABOUR PER sqm 626.70
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.08500 110.95 9.43
LABOUR :
Carpenter 1st Class each 4.53000 211.16 956.55
Beldar each 1.29000 116.67 150.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1177.05
TOTAL : 1177.05
ADD FOR CONTRACTORS PROFIT @10% : 117.70
ADD FOR OVER HEAD CHARGES @5% : 58.85
LABOUR FOR 2.160 Sqm 1353.60
LABOUR PER sqm 626.70
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.08500 110.95 9.43
LABOUR :
Carpenter 1st Class each 3.02000 211.16 637.70
Beldar each 0.86000 116.67 100.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 783.04
TOTAL : 783.04
ADD FOR CONTRACTORS PROFIT @10% : 78.30
ADD FOR OVER HEAD CHARGES @5% : 39.15
LABOUR FOR 2.160 Sqm 900.50
LABOUR PER sqm 416.90
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
1200502040 2nd Class Deodar wood.
Details of cost for shutters of a
door (half glazed and half
penelled).
200cm x 108 cm = 2.16Sqm.
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.08500 110.95 9.43
LABOUR :
Carpenter 1st Class each 3.02000 211.16 637.70
Beldar each 0.86000 116.67 100.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 783.04
TOTAL : 783.04
ADD FOR CONTRACTORS PROFIT @10% : 78.30
ADD FOR OVER HEAD CHARGES @5% : 39.15
LABOUR FOR 2.160 Sqm 900.50
LABOUR PER sqm 416.90
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.08500 110.95 9.43
LABOUR :
Carpenter 1st Class each 3.02000 211.16 637.70
Beldar each 0.86000 116.67 100.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 783.04
TOTAL : 783.04
ADD FOR CONTRACTORS PROFIT @10% : 78.30
ADD FOR OVER HEAD CHARGES @5% : 39.15
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR FOR 2.160 Sqm 900.50
LABOUR PER sqm 416.90
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.08500 110.95 9.43
LABOUR :
Carpenter 1st Class each 3.02000 211.16 637.70
Beldar each 0.86000 116.67 100.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 783.04
TOTAL : 783.04
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR CONTRACTORS PROFIT @10% : 78.30
ADD FOR OVER HEAD CHARGES @5% : 39.15
LABOUR FOR 2.160 Sqm 900.50
LABOUR PER sqm 416.90
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.08500 110.95 9.43
LABOUR :
Carpenter 1st Class each 3.02000 211.16 637.70
Beldar each 0.86000 116.67 100.34
LABOUR RATE :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ACTUAL LABOUR+SUNDRIES 783.04
TOTAL : 783.04
ADD FOR CONTRACTORS PROFIT @10% : 78.30
ADD FOR OVER HEAD CHARGES @5% : 39.15
LABOUR FOR 2.160 Sqm 900.50
LABOUR PER sqm 416.90
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.08500 110.95 9.43
LABOUR :
Carpenter 1st Class each 3.02000 211.16 637.70
Beldar each 0.86000 116.67 100.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 783.04
TOTAL : 783.04
ADD FOR CONTRACTORS PROFIT @10% : 78.30
ADD FOR OVER HEAD CHARGES @5% : 39.15
LABOUR FOR 2.160 Sqm 900.50
LABOUR PER sqm 416.90
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.07600 110.95 8.43
LABOUR :
Carpenter 1st Class each 4.53000 211.16 956.55
Beldar each 1.29000 116.67 150.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1177.06
TOTAL : 1177.06
ADD FOR CONTRACTORS PROFIT @10% : 117.71
ADD FOR OVER HEAD CHARGES @5% : 58.85
LABOUR FOR 2.160 Sqm 1353.62
LABOUR PER sqm 626.70
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.07600 110.95 8.43
LABOUR :
Carpenter 1st Class each 4.53000 211.16 956.55
Beldar each 1.29000 116.67 150.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1177.06
TOTAL : 1177.06
ADD FOR CONTRACTORS PROFIT @10% : 117.71
ADD FOR OVER HEAD CHARGES @5% : 58.85
LABOUR FOR 2.160 Sqm 1353.62
LABOUR PER sqm 626.70
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.07600 110.95 8.43
LABOUR :
Carpenter 1st Class each 3.02000 211.16 637.70
Beldar each 0.86000 116.67 100.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 783.04
TOTAL : 783.04
ADD FOR CONTRACTORS PROFIT @10% : 78.30
ADD FOR OVER HEAD CHARGES @5% : 39.15
LABOUR FOR 2.160 Sqm 900.50
LABOUR PER sqm 416.90
MATERIAL :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.07600 110.95 8.43
LABOUR :
Carpenter 1st Class each 3.02000 211.16 637.70
Beldar each 0.86000 116.67 100.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 783.04
TOTAL : 783.04
ADD FOR CONTRACTORS PROFIT @10% : 78.30
ADD FOR OVER HEAD CHARGES @5% : 39.15
LABOUR FOR 2.160 Sqm 900.50
LABOUR PER sqm 416.90
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.07600 110.95 8.43
LABOUR :
Carpenter 1st Class each 3.02000 211.16 637.70
Beldar each 0.86000 116.67 100.34
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
SUNDRIES : L.S. 45.00
TOTAL : 5160.95
ADD FOR CONTRACTORS PROFIT 10% 516.09
ADD FOR OVER HEAD CHARGES @5% 258.05
COST FOR 2.160 sqm 5935.09
COST PER Sqm 2747.70
LABOUR PER Sqm 416.90
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 783.04
TOTAL : 783.04
ADD FOR CONTRACTORS PROFIT @10% : 78.30
ADD FOR OVER HEAD CHARGES @5% : 39.15
LABOUR FOR 2.160 Sqm 900.50
LABOUR PER sqm 416.90
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.07600 110.95 8.43
LABOUR :
Carpenter 1st Class each 3.02000 211.16 637.70
Beldar each 0.86000 116.67 100.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 783.04
TOTAL : 783.04
ADD FOR CONTRACTORS PROFIT @10% : 78.30
ADD FOR OVER HEAD CHARGES @5% : 39.15
LABOUR FOR 2.160 Sqm 900.50
LABOUR PER sqm 416.90
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.07600 110.95 8.43
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
100 MTRS BY HEAD LOAD 1 cum 0.07600 36.25 2.76
LABOUR :
Carpenter 1st Class each 3.02000 211.16 637.70
Beldar each 0.86000 116.67 100.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 783.04
TOTAL : 783.04
ADD FOR CONTRACTORS PROFIT @10% : 78.30
ADD FOR OVER HEAD CHARGES @5% : 39.15
LABOUR FOR 2.160 Sqm 900.50
LABOUR PER sqm 416.90
MATERIAL :
CARRIAGE :
Timber.
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
1 KM BY MECH. TRANSPORT 1 cum 0.07600 110.95 8.43
LABOUR :
Carpenter 1st Class each 3.02000 211.16 637.70
Beldar each 0.86000 116.67 100.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 783.04
TOTAL : 783.04
ADD FOR CONTRACTORS PROFIT @10% : 78.30
ADD FOR OVER HEAD CHARGES @5% : 39.15
LABOUR FOR 2.160 Sqm 900.50
LABOUR PER sqm 416.90
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.06800 110.95 7.54
LABOUR :
Carpenter 1st Class each 4.53000 211.16 956.55
Beldar each 1.29000 116.67 150.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1177.06
TOTAL : 1177.06
ADD FOR CONTRACTORS PROFIT @10% : 117.71
ADD FOR OVER HEAD CHARGES @5% : 58.85
LABOUR FOR 2.160 Sqm 1353.62
LABOUR PER sqm 626.70
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.06800 110.95 7.54
LABOUR :
Carpenter 1st Class each 4.53000 211.16 956.55
Beldar each 1.29000 116.67 150.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1177.06
TOTAL : 1177.06
ADD FOR CONTRACTORS PROFIT @10% : 117.71
ADD FOR OVER HEAD CHARGES @5% : 58.85
LABOUR FOR 2.160 Sqm 1353.62
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR PER sqm 626.70
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.06800 110.95 7.54
LABOUR :
Carpenter 1st Class each 3.02000 211.16 637.70
Beldar each 0.86000 116.67 100.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 783.04
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 783.04
ADD FOR CONTRACTORS PROFIT @10% : 78.30
ADD FOR OVER HEAD CHARGES @5% : 39.15
LABOUR FOR 2.160 Sqm 900.50
LABOUR PER sqm 416.90
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.06800 110.95 7.54
LABOUR :
Carpenter 1st Class each 3.02000 211.16 637.70
Beldar each 0.86000 116.67 100.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 783.04
TOTAL : 783.04
ADD FOR CONTRACTORS PROFIT @10% : 78.30
ADD FOR OVER HEAD CHARGES @5% : 39.15
LABOUR FOR 2.160 Sqm 900.50
LABOUR PER sqm 416.90
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.06800 110.95 7.54
LABOUR :
Carpenter 1st Class each 3.02000 211.16 637.70
Beldar each 0.86000 116.67 100.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 783.04
TOTAL : 783.04
ADD FOR CONTRACTORS PROFIT @10% : 78.30
ADD FOR OVER HEAD CHARGES @5% : 39.15
LABOUR FOR 2.160 Sqm 900.50
LABOUR PER sqm 416.90
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.06800 110.95 7.54
LABOUR :
Carpenter 1st Class each 3.02000 211.16 637.70
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Beldar each 0.86000 116.67 100.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 783.04
TOTAL : 783.04
ADD FOR CONTRACTORS PROFIT @10% : 78.30
ADD FOR OVER HEAD CHARGES @5% : 39.15
LABOUR FOR 2.160 Sqm 900.50
LABOUR PER sqm 416.90
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.06800 110.95 7.54
LABOUR :
Carpenter 1st Class each 3.02000 211.16 637.70
Beldar each 0.86000 116.67 100.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 783.04
TOTAL : 783.04
ADD FOR CONTRACTORS PROFIT @10% : 78.30
ADD FOR OVER HEAD CHARGES @5% : 39.15
LABOUR FOR 2.160 Sqm 900.50
LABOUR PER sqm 416.90
MATERIAL :
CARRIAGE :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.06800 110.95 7.54
LABOUR :
Carpenter 1st Class each 3.02000 211.16 637.70
Beldar each 0.86000 116.67 100.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 783.04
TOTAL : 783.04
ADD FOR CONTRACTORS PROFIT @10% : 78.30
ADD FOR OVER HEAD CHARGES @5% : 39.15
LABOUR FOR 2.160 Sqm 900.50
LABOUR PER sqm 416.90
MATERIAL :
Style:-
4x200x9.5x2.5 cm = 0.019 cum.
Rails :
Top Rail
1x110.5x9.5x2.5 cn = 0.003 cum
Lock and botom Rail.
2x110.5x19.7x2.5 cm = 0.018 cum
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Panels :
2x48x41x1.6 cm =0.006 cum.
Sashbars :
2x114x5x3.8x2.5 cm =0.002 cum.
6x114x3.8x2.5 cm =0.003 cum
Beading :
16x92x1.9x1.20 cm =0.03 cum
Total = 0.047 cum
Add for wastage @ 10% =0.004 cum
Total = 0.051 cum
1 cum 0.05100 98625.00 5029.88
Nickel plated bright finish piano hinges1 metre 4.00000 50.00 200.00
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.05100 110.95 5.66
LABOUR :
Carpenter 1st Class each 2.27000 211.16 479.33
Carpenter 2nd' Class each 2.27000 186.67 423.74
Beldar each 1.29000 116.67 150.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1113.58
TOTAL : 1113.58
ADD FOR CONTRACTORS PROFIT @10% : 111.36
ADD FOR OVER HEAD CHARGES @5% : 55.68
LABOUR FOR 2.160 Sqm 1280.62
LABOUR PER sqm 592.90
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
Nickel plated bright finish piano hinges1 metre 4.00000 50.00 200.00
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.05100 110.95 5.66
LABOUR :
Carpenter 1st Class each 2.27000 211.16 479.33
Carpenter 2nd' Class each 2.27000 186.67 423.74
Beldar each 1.29000 116.67 150.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1113.58
TOTAL : 1113.58
ADD FOR CONTRACTORS PROFIT @10% : 111.36
ADD FOR OVER HEAD CHARGES @5% : 55.68
LABOUR FOR 2.160 Sqm 1280.62
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR PER sqm 592.90
MATERIAL :
Nickel plated bright finish piano hinges1 metre 4.00000 50.00 200.00
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.05100 110.95 5.66
LABOUR :
Carpenter 1st Class each 1.51000 211.16 318.85
Carpenter 2nd' Class each 1.51000 186.67 281.87
Beldar each 0.86000 116.67 100.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 741.06
TOTAL : 741.06
ADD FOR CONTRACTORS PROFIT @10% : 74.11
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR OVER HEAD CHARGES @5% : 37.05
LABOUR FOR 2.160 Sqm 852.22
LABOUR PER sqm 394.55
MATERIAL :
Nickel plated bright finish piano hinges1 metre 4.00000 50.00 200.00
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.05100 110.95 5.66
LABOUR :
Carpenter 1st Class each 1.51000 211.16 318.85
Carpenter 2nd' Class each 1.51000 186.67 281.87
Beldar each 0.86000 116.67 100.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 741.06
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 741.06
ADD FOR CONTRACTORS PROFIT @10% : 74.11
ADD FOR OVER HEAD CHARGES @5% : 37.05
LABOUR FOR 2.160 Sqm 852.22
LABOUR PER sqm 394.55
MATERIAL :
Nickel plated bright finish piano hinges1 metre 4.00000 50.00 200.00
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.05100 110.95 5.66
LABOUR :
Carpenter 1st Class each 1.51000 211.16 318.85
Carpenter 2nd' Class each 1.51000 186.67 281.87
Beldar each 0.86000 116.67 100.34
MATERIAL :
Nickel plated bright finish piano hinges1 metre 4.00000 50.00 200.00
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.05100 110.95 5.66
LABOUR :
Carpenter 1st Class each 1.51000 211.16 318.85
Carpenter 2nd' Class each 1.51000 186.67 281.87
Beldar each 0.86000 116.67 100.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 741.06
TOTAL : 741.06
ADD FOR CONTRACTORS PROFIT @10% : 74.11
ADD FOR OVER HEAD CHARGES @5% : 37.05
LABOUR FOR 2.160 Sqm 852.22
LABOUR PER sqm 394.55
MATERIAL :
Nickel plated bright finish piano hinges1 metre 4.00000 50.00 200.00
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.05100 110.95 5.66
LABOUR :
Carpenter 1st Class each 1.51000 211.16 318.85
Carpenter 2nd' Class each 1.51000 186.67 281.87
Beldar each 0.86000 116.67 100.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 741.06
TOTAL : 741.06
ADD FOR CONTRACTORS PROFIT @10% : 74.11
ADD FOR OVER HEAD CHARGES @5% : 37.05
LABOUR FOR 2.160 Sqm 852.22
LABOUR PER sqm 394.55
MATERIAL :
Nickel plated bright finish piano hinges1 metre 4.00000 50.00 200.00
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.05100 110.95 5.66
LABOUR :
Carpenter 1st Class each 1.51000 211.16 318.85
Carpenter 2nd' Class each 1.51000 186.67 281.87
Beldar each 0.86000 116.67 100.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 741.06
TOTAL : 741.06
ADD FOR CONTRACTORS PROFIT @10% : 74.11
ADD FOR OVER HEAD CHARGES @5% : 37.05
LABOUR FOR 2.160 Sqm 852.22
LABOUR PER sqm 394.55
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.05100 110.95 5.66
LABOUR :
Carpenter 1st Class each 2.27000 211.16 479.33
Carpenter 2nd' Class each 2.27000 186.67 423.74
Beldar each 1.29000 116.67 150.50
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
SUNDRIES : L.S. 60.00
TOTAL : 6454.86
ADD FOR CONTRACTORS PROFIT 10% 645.49
ADD FOR OVER HEAD CHARGES @5% 322.74
COST FOR 2.160 sqm 7423.09
COST PER Sqm 3436.60
LABOUR PER Sqm 592.90
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1113.58
TOTAL : 1113.58
ADD FOR CONTRACTORS PROFIT @10% : 111.36
ADD FOR OVER HEAD CHARGES @5% : 55.68
LABOUR FOR 2.160 Sqm 1280.62
LABOUR PER sqm 592.90
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.05100 110.95 5.66
LABOUR :
Carpenter 1st Class each 2.27000 211.16 479.33
Carpenter 2nd' Class each 2.27000 186.67 423.74
Beldar each 1.29000 116.67 150.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1113.58
TOTAL : 1113.58
ADD FOR CONTRACTORS PROFIT @10% : 111.36
ADD FOR OVER HEAD CHARGES @5% : 55.68
LABOUR FOR 2.160 Sqm 1280.62
LABOUR PER sqm 592.90
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.05100 110.95 5.66
LABOUR :
Carpenter 1st Class each 1.51000 211.16 318.85
Carpenter 2nd' Class each 1.51000 186.67 281.87
Beldar each 0.86000 116.67 100.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 741.06
TOTAL : 741.06
ADD FOR CONTRACTORS PROFIT @10% : 74.11
ADD FOR OVER HEAD CHARGES @5% : 37.05
LABOUR FOR 2.160 Sqm 852.22
LABOUR PER sqm 394.55
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.05100 110.95 5.66
LABOUR :
Carpenter 1st Class each 1.51000 211.16 318.85
Carpenter 2nd' Class each 1.51000 186.67 281.87
Beldar each 0.86000 116.67 100.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 741.06
TOTAL : 741.06
ADD FOR CONTRACTORS PROFIT @10% : 74.11
ADD FOR OVER HEAD CHARGES @5% : 37.05
LABOUR FOR 2.160 Sqm 852.22
LABOUR PER sqm 394.55
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.05100 110.95 5.66
LABOUR :
Carpenter 1st Class each 1.51000 211.16 318.85
Carpenter 2nd' Class each 1.51000 186.67 281.87
Beldar each 0.86000 116.67 100.34
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.05100 110.95 5.66
LABOUR :
Carpenter 1st Class each 1.51000 211.16 318.85
Carpenter 2nd' Class each 1.51000 186.67 281.87
Beldar each 0.86000 116.67 100.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 741.06
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 741.06
ADD FOR CONTRACTORS PROFIT @10% : 74.11
ADD FOR OVER HEAD CHARGES @5% : 37.05
LABOUR FOR 2.160 Sqm 852.22
LABOUR PER sqm 394.55
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.05100 110.95 5.66
LABOUR :
Carpenter 1st Class each 1.51000 211.16 318.85
Carpenter 2nd' Class each 1.51000 186.67 281.87
Beldar each 0.86000 116.67 100.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 741.06
TOTAL : 741.06
ADD FOR CONTRACTORS PROFIT @10% : 74.11
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR OVER HEAD CHARGES @5% : 37.05
LABOUR FOR 2.160 Sqm 852.22
LABOUR PER sqm 394.55
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.05100 110.95 5.66
LABOUR :
Carpenter 1st Class each 1.51000 211.16 318.85
Carpenter 2nd' Class each 1.51000 186.67 281.87
Beldar each 0.86000 116.67 100.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 741.06
TOTAL : 741.06
ADD FOR CONTRACTORS PROFIT @10% : 74.11
ADD FOR OVER HEAD CHARGES @5% : 37.05
LABOUR FOR 2.160 Sqm 852.22
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR PER sqm 394.55
MATERIAL :
Total : 107.40
ADD FOR CONTRACTORS PROFIT @10% : 10.74
ADD FOR OVER HEAD CHARGES @5% : 5.37
LABOUR FOR 2.160 Sqm 123.51
LABOUR PER sqm 57.20
MATERIAL :
Total : 76.40
ADD FOR CONTRACTORS PROFIT @10% : 7.64
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR OVER HEAD CHARGES @5% : 3.82
LABOUR FOR 2.160 Sqm 87.86
LABOUR PER sqm 40.70
MATERIAL :
Total : 49.50
ADD FOR CONTRACTORS PROFIT @10% : 4.95
ADD FOR OVER HEAD CHARGES @5% : 2.48
LABOUR FOR 2.160 Sqm 56.93
LABOUR PER sqm 26.35
MATERIAL :
Total : 148.50
ADD FOR CONTRACTORS PROFIT @10% : 14.85
ADD FOR OVER HEAD CHARGES @5% : 7.43
LABOUR FOR 2.160 Sqm 170.78
LABOUR PER sqm 79.00
Total : 49.50
ADD FOR CONTRACTORS PROFIT @10% : 4.95
ADD FOR OVER HEAD CHARGES @5% : 2.48
LABOUR FOR 2.160 Sqm 56.93
LABOUR PER sqm 26.35
MATERIAL :
Cost of Pin head glass 3mm thick 1 sqm. 0.99000 160.00 158.40
Total : 89.10
ADD FOR CONTRACTORS PROFIT @10% : 8.91
ADD FOR OVER HEAD CHARGES @5% : 4.46
LABOUR FOR 2.160 Sqm 102.47
LABOUR PER sqm 47.40
MATERIAL :
Total : 321.75
ADD FOR CONTRACTORS PROFIT @10% : 32.18
ADD FOR OVER HEAD CHARGES @5% : 16.09
LABOUR FOR 2.160 Sqm 370.01
LABOUR PER sqm 171.30
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
CARRIAGE :
carriage of shutter L.S. 20.00
LABOUR :
Carpenter 1st Class each 0.60000 211.16 126.70
Carpenter 2nd' Class each 0.06000 186.67 11.20
Beldar each 0.80000 116.67 93.34
TOTAL : 4300.03
ADD FOR CONTRACTORS PROFIT 10% 430.00
ADD FOR OVER HEAD CHARGES @5% 215.00
COST FOR 2.20 sqm 4945.04
COST PER Sqm 2247.75
LABOUR PER Sqm 120.90
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 231.23
TOTAL : 231.23
ADD FOR CONTRACTORS PROFIT @10% : 23.12
ADD FOR OVER HEAD CHARGES @5% : 11.56
LABOUR FOR 2.20 Sqm 265.92
LABOUR PER sqm 120.90
MATERIAL :
CARRIAGE :
carriage of shutter L.S. 20.00
LABOUR :
Carpenter 1st Class each 0.60000 211.16 126.70
Carpenter 2nd' Class each 0.06000 186.67 11.20
Beldar each 0.80000 116.67 93.34
TOTAL : 3970.03
ADD FOR CONTRACTORS PROFIT 10% 397.00
ADD FOR OVER HEAD CHARGES @5% 198.50
COST FOR 2.20 sqm 4565.54
COST PER Sqm 2075.25
LABOUR PER Sqm 120.90
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 231.23
TOTAL : 231.23
ADD FOR CONTRACTORS PROFIT @10% : 23.12
ADD FOR OVER HEAD CHARGES @5% : 11.56
LABOUR FOR 2.20 Sqm 265.92
LABOUR PER sqm 120.90
MATERIAL :
LABOUR :
Carpenter 1st Class each 0.60000 211.16 126.70
Carpenter 2nd' Class each 0.06000 186.67 11.20
Beldar each 0.80000 116.67 93.34
TOTAL : 3619.03
ADD FOR CONTRACTORS PROFIT 10% 361.90
ADD FOR OVER HEAD CHARGES @5% 180.95
COST FOR 2.20 sqm 4161.89
COST PER Sqm 1891.80
LABOUR PER Sqm 120.90
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 231.23
TOTAL : 231.23
ADD FOR CONTRACTORS PROFIT @10% : 23.12
ADD FOR OVER HEAD CHARGES @5% : 11.56
LABOUR FOR 2.20 Sqm 265.92
LABOUR PER sqm 120.90
MATERIAL :
CARRIAGE :
carriage of shutter L.S. 20.00
LABOUR :
Carpenter 1st Class each 0.50000 211.16 105.58
Carpenter 2nd' Class each 0.07000 186.67 13.07
Beldar each 0.50000 116.67 58.34
TOTAL : 3528.23
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR CONTRACTORS PROFIT 10% 352.82
ADD FOR OVER HEAD CHARGES @5% 176.41
COST FOR 2.20 sqm 4057.46
COST PER Sqm 1844.30
LABOUR PER Sqm 92.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 176.98
TOTAL : 176.98
ADD FOR CONTRACTORS PROFIT @10% : 17.70
ADD FOR OVER HEAD CHARGES @5% : 8.85
LABOUR FOR 2.20 Sqm 203.53
LABOUR PER sqm 92.50
MATERIAL :
CARRIAGE :
carriage of shutter L.S. 20.00
LABOUR :
Carpenter 1st Class each 0.60000 211.16 126.70
Carpenter 2nd' Class each 0.06000 186.67 11.20
Beldar each 0.80000 116.67 93.34
TOTAL : 2892.03
ADD FOR CONTRACTORS PROFIT 10% 289.20
ADD FOR OVER HEAD CHARGES @5% 144.60
COST FOR 2.20 sqm 3325.84
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
COST PER Sqm 1511.75
LABOUR PER Sqm 120.90
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 231.23
TOTAL : 231.23
ADD FOR CONTRACTORS PROFIT @10% : 23.12
ADD FOR OVER HEAD CHARGES @5% : 11.56
LABOUR FOR 2.20 Sqm 265.92
LABOUR PER sqm 120.90
MATERIAL :
CARRIAGE :
carriage of shutter L.S. 20.00
LABOUR :
Carpenter 1st Class each 0.60000 211.16 126.70
Carpenter 2nd' Class each 0.06000 186.67 11.20
Beldar each 0.80000 116.67 93.34
TOTAL : 2650.03
ADD FOR CONTRACTORS PROFIT 10% 265.00
ADD FOR OVER HEAD CHARGES @5% 132.50
COST FOR 2.20 sqm 3047.54
COST PER Sqm 1385.25
LABOUR PER Sqm 120.90
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 231.23
TOTAL : 231.23
ADD FOR CONTRACTORS PROFIT @10% : 23.12
ADD FOR OVER HEAD CHARGES @5% : 11.56
LABOUR FOR 2.20 Sqm 265.92
LABOUR PER sqm 120.90
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
CARRIAGE :
carriage of shutter L.S. 20.00
LABOUR :
Carpenter 1st Class each 0.60000 211.16 126.70
Carpenter 2nd' Class each 0.06000 186.67 11.20
Beldar each 0.80000 116.67 93.34
TOTAL : 2519.03
ADD FOR CONTRACTORS PROFIT 10% 251.90
ADD FOR OVER HEAD CHARGES @5% 125.95
COST FOR 2.20 sqm 2896.89
COST PER Sqm 1316.75
LABOUR PER Sqm 120.90
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 231.23
TOTAL : 231.23
ADD FOR CONTRACTORS PROFIT @10% : 23.12
ADD FOR OVER HEAD CHARGES @5% : 11.56
LABOUR FOR 2.20 Sqm 265.92
LABOUR PER sqm 120.90
MATERIAL :
CARRIAGE :
carriage of shutter L.S. 20.00
LABOUR :
Carpenter 1st Class each 0.50000 211.16 105.58
Carpenter 2nd' Class each 0.07000 186.67 13.07
Beldar each 0.50000 116.67 58.34
TOTAL : 2483.23
ADD FOR CONTRACTORS PROFIT 10% 248.32
ADD FOR OVER HEAD CHARGES @5% 124.16
COST FOR 2.20 sqm 2855.72
COST PER Sqm 1298.05
LABOUR PER Sqm 92.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 176.98
TOTAL : 176.98
ADD FOR CONTRACTORS PROFIT @10% : 17.70
ADD FOR OVER HEAD CHARGES @5% : 8.85
LABOUR FOR 2.20 Sqm 203.53
LABOUR PER sqm 92.50
MATERIAL :
CARRIAGE :
carriage of shutter L.S. 20.00
LABOUR :
Carpenter 1st Class each 0.60000 211.16 126.70
Carpenter 2nd' Class each 0.06000 186.67 11.20
Beldar each 0.80000 116.67 93.34
TOTAL : 3530.03
ADD FOR CONTRACTORS PROFIT 10% 353.00
ADD FOR OVER HEAD CHARGES @5% 176.50
COST FOR 2.20 sqm 4059.54
COST PER Sqm 1845.25
LABOUR PER Sqm 120.90
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 231.23
TOTAL : 231.23
ADD FOR CONTRACTORS PROFIT @10% : 23.12
ADD FOR OVER HEAD CHARGES @5% : 11.56
LABOUR FOR 2.20 Sqm 265.92
LABOUR PER sqm 120.90
MATERIAL :
CARRIAGE :
carriage of shutter L.S. 20.00
LABOUR :
Carpenter 1st Class each 0.60000 211.16 126.70
Carpenter 2nd' Class each 0.06000 186.67 11.20
Beldar each 0.80000 116.67 93.34
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 3354.03
ADD FOR CONTRACTORS PROFIT 10% 335.40
ADD FOR OVER HEAD CHARGES @5% 167.70
COST FOR 2.20 sqm 3857.14
COST PER Sqm 1753.25
LABOUR PER Sqm 120.90
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 231.23
TOTAL : 231.23
ADD FOR CONTRACTORS PROFIT @10% : 23.12
ADD FOR OVER HEAD CHARGES @5% : 11.56
LABOUR FOR 2.20 Sqm 265.92
LABOUR PER sqm 120.90
MATERIAL :
CARRIAGE :
carriage of shutter L.S. 20.00
LABOUR :
Carpenter 1st Class each 0.60000 211.16 126.70
Carpenter 2nd' Class each 0.06000 186.67 11.20
Beldar each 0.80000 116.67 93.34
TOTAL : 3091.03
ADD FOR CONTRACTORS PROFIT 10% 309.10
ADD FOR OVER HEAD CHARGES @5% 154.55
COST FOR 2.20 sqm 3554.69
COST PER Sqm 1615.75
LABOUR PER Sqm 120.90
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 231.23
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 231.23
ADD FOR CONTRACTORS PROFIT @10% : 23.12
ADD FOR OVER HEAD CHARGES @5% : 11.56
LABOUR FOR 2.20 Sqm 265.92
LABOUR PER sqm 120.90
MATERIAL :
CARRIAGE :
carriage of shutter L.S. 20.00
LABOUR :
Carpenter 1st Class each 0.50000 211.16 105.58
Carpenter 2nd' Class each 0.07000 186.67 13.07
Beldar each 0.50000 116.67 58.34
TOTAL : 2813.23
ADD FOR CONTRACTORS PROFIT 10% 281.32
ADD FOR OVER HEAD CHARGES @5% 140.66
COST FOR 2.20 sqm 3235.21
COST PER Sqm 1470.55
LABOUR PER Sqm 92.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 176.98
TOTAL : 176.98
ADD FOR CONTRACTORS PROFIT @10% : 17.70
ADD FOR OVER HEAD CHARGES @5% : 8.85
LABOUR FOR 2.20 Sqm 203.53
LABOUR PER sqm 92.50
MATERIAL :
TOTAL : 88.80
ADD FOR CONTRACTORS PROFIT 10% 8.88
ADD FOR OVER HEAD CHARGES @5% 4.44
COST FOR 2.20 sqm 102.12
COST PER Sqm 46.40
LABOUR PER Sqm
MATERIAL :
TOTAL : 88.80
ADD FOR CONTRACTORS PROFIT 10% 8.88
ADD FOR OVER HEAD CHARGES @5% 4.44
COST FOR 2.20 sqm 102.12
COST PER Sqm 46.40
LABOUR PER Sqm
MATERIAL :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Black enamelled butt hinges
100x58x1.90mm
10 nos. 6.00000 85.00 51.00
TOTAL : 67.80
ADD FOR CONTRACTORS PROFIT 10% 6.78
ADD FOR OVER HEAD CHARGES @5% 3.39
COST FOR 2.20 sqm 77.97
COST PER Sqm 35.45
LABOUR PER Sqm
MATERIAL :
TOTAL : 251.25
ADD FOR CONTRACTORS PROFIT 10% 25.13
ADD FOR OVER HEAD CHARGES @5% 12.56
COST FOR 2.20 sqm 288.94
COST PER Sqm 131.35
LABOUR PER Sqm
MATERIAL :
TOTAL : 65.00
ADD FOR CONTRACTORS PROFIT 10% 6.50
ADD FOR OVER HEAD CHARGES @5% 3.25
COST FOR 1.00 sqm 74.75
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
COST PER Sqm 74.75
MATERIAL :
TOTAL : 65.00
ADD FOR CONTRACTORS PROFIT 10% 6.50
ADD FOR OVER HEAD CHARGES @5% 3.25
COST FOR 1.00 sqm 74.75
COST PER Sqm 74.75
1201402000 Circular
Details of circular panel. (Per sqm. Of door area)
MATERIAL :
TOTAL : 96.00
ADD FOR CONTRACTORS PROFIT 10% 9.60
ADD FOR OVER HEAD CHARGES @5% 4.80
COST FOR 1.00 sqm 110.40
COST PER Sqm 110.40
MATERIAL :
TOTAL : 120.00
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR CONTRACTORS PROFIT 10% 12.00
ADD FOR OVER HEAD CHARGES @5% 6.00
COST FOR 1.00 sqm 138.00
COST PER Sqm 138.00
LABOUR PER sq.m
MATERIAL :
TOTAL : 96.00
ADD FOR CONTRACTORS PROFIT 10% 9.60
ADD FOR OVER HEAD CHARGES @5% 4.80
COST FOR 1.00 sqm 110.40
COST PER Sqm 110.40
LABOUR PER sq.m
MATERIAL :
TOTAL : 20.00
ADD FOR CONTRACTORS PROFIT 10% 2.00
ADD FOR OVER HEAD CHARGES @5% 1.00
COST FOR 1.00 sqm 23.00
COST PER Sqm 23.00
LABOUR PER sq.m
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.05300 110.95 5.88
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 570.51
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 570.51
ADD FOR CONTRACTORS PROFIT @10% : 57.05
ADD FOR OVER HEAD CHARGES @5% : 28.53
LABOUR FOR 1.60 Sqm 656.09
LABOUR PER sqm 410.05
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.05300 110.95 5.88
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 570.51
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 570.51
ADD FOR CONTRACTORS PROFIT @10% : 57.05
ADD FOR OVER HEAD CHARGES @5% : 28.53
LABOUR FOR 1.60 Sqm 656.09
LABOUR PER sqm 410.05
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.05300 110.95 5.88
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 381.67
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 381.67
ADD FOR CONTRACTORS PROFIT @10% : 38.17
ADD FOR OVER HEAD CHARGES @5% : 19.08
LABOUR FOR 1.60 Sqm 438.93
LABOUR PER sqm 274.33
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.05300 110.95 5.88
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 381.67
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 381.67
ADD FOR CONTRACTORS PROFIT @10% : 38.17
ADD FOR OVER HEAD CHARGES @5% : 19.08
LABOUR FOR 1.60 Sqm 438.93
LABOUR PER sqm 274.35
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.05300 110.95 5.88
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 381.67
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 381.67
ADD FOR CONTRACTORS PROFIT @10% : 38.17
ADD FOR OVER HEAD CHARGES @5% : 19.08
LABOUR FOR 1.60 Sqm 438.93
LABOUR PER sqm 274.35
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.05300 110.95 5.88
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 381.67
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 381.67
ADD FOR CONTRACTORS PROFIT @10% : 38.17
ADD FOR OVER HEAD CHARGES @5% : 19.08
LABOUR FOR 1.60 Sqm 438.93
LABOUR PER sqm 274.35
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.05350 110.95 5.94
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 381.67
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 381.67
ADD FOR CONTRACTORS PROFIT @10% : 38.17
ADD FOR OVER HEAD CHARGES @5% : 19.08
LABOUR FOR 1.60 Sqm 438.93
LABOUR PER sqm 274.35
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.05350 110.95 5.94
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 381.67
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 381.67
ADD FOR CONTRACTORS PROFIT @10% : 38.17
ADD FOR OVER HEAD CHARGES @5% : 19.08
LABOUR FOR 1.60 Sqm 438.93
LABOUR PER sqm 274.35
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.04500 110.95 4.99
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 504.98
TOTAL : 504.98
ADD FOR CONTRACTORS PROFIT @10% : 50.50
ADD FOR OVER HEAD CHARGES @5% : 25.25
LABOUR FOR 1.320 Sqm 580.72
LABOUR PER sqm 439.95
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.04500 110.95 4.99
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 504.98
TOTAL : 504.98
ADD FOR CONTRACTORS PROFIT @10% : 50.50
ADD FOR OVER HEAD CHARGES @5% : 25.25
LABOUR FOR 1.320 Sqm 580.72
LABOUR PER sqm 439.95
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.04500 110.95 4.99
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
100 MTRS BY HEAD LOAD 1 cum 0.04500 36.25 1.63
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 333.97
TOTAL : 333.97
ADD FOR CONTRACTORS PROFIT @10% : 33.40
ADD FOR OVER HEAD CHARGES @5% : 16.70
LABOUR FOR 1.320 Sqm 384.07
LABOUR PER sqm 290.95
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.04500 110.95 4.99
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 333.97
TOTAL : 333.97
ADD FOR CONTRACTORS PROFIT @10% : 33.40
ADD FOR OVER HEAD CHARGES @5% : 16.70
LABOUR FOR 1.320 Sqm 384.07
LABOUR PER sqm 290.95
MATERIAL :
CARRIAGE :
Timber.
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
1 KM BY MECH. TRANSPORT 1 cum 0.04500 110.95 4.99
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 333.97
TOTAL : 333.97
ADD FOR CONTRACTORS PROFIT @10% : 33.40
ADD FOR OVER HEAD CHARGES @5% : 16.70
LABOUR FOR 1.320 Sqm 384.07
LABOUR PER sqm 290.95
MATERIAL :
CARRIAGE :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.04500 110.95 4.99
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 333.97
TOTAL : 333.97
ADD FOR CONTRACTORS PROFIT @10% : 33.40
ADD FOR OVER HEAD CHARGES @5% : 16.70
LABOUR FOR 1.320 Sqm 384.07
LABOUR PER sqm 290.95
MATERIAL :
CARRIAGE :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.04500 110.95 4.99
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 333.97
TOTAL : 333.97
ADD FOR CONTRACTORS PROFIT @10% : 33.40
ADD FOR OVER HEAD CHARGES @5% : 16.70
LABOUR FOR 1.320 Sqm 384.07
LABOUR PER sqm 290.95
MATERIAL :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.04500 110.95 4.99
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 333.97
TOTAL : 333.97
ADD FOR CONTRACTORS PROFIT @10% : 33.40
ADD FOR OVER HEAD CHARGES @5% : 16.70
LABOUR FOR 1.320 Sqm 384.07
LABOUR PER sqm 290.95
MATERIAL :
Styles:-
Rails:-
Top rail
1x110.5x6.5x4.00cm=0.004 cum
Lock rail and bottom rail:-
2x110.5x19.7x4.00cm=0.017 cum
Beading:-
(2x3x2+2x150)x1.2x1.2cm = .001cum
Total : =0.052 cum
Add. Wastage @ 10% = 0.005cum
Grand Total: =0.057 cum
1 cum 0.05700 98625.00 5621.62
wire gauge:-
2x160x40cm =1.28sqm.
Add wastage @ 10%=0.13sqm.
Total: =1.41sqm.
1sqm 1.41000 130.00 183.30
Iron hinges:-
100x58x1.90mm
10 nos. 6.00000 85.00 51.00
Iron hinges :-
50x37x1.50mm 10 nos. 2.00000 35.00 7.00
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.05700 110.95 6.32
LABOUR :
Carpenter 1st Class each 1.13000 211.16 238.61
Carpenter 2nd' Class each 1.07000 186.67 199.74
Beldar each 0.86000 116.67 100.34
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
SUNDRIES : L.S. 30.00
TOTAL : 6458.39
ADD FOR CONTRACTORS PROFIT 10% 645.84
ADD FOR OVER HEAD CHARGES @5% 322.92
COST FOR 2.160 sqm 7427.15
COST PER Sqm 3438.50
LABOUR PER Sqm 302.80
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 568.68
TOTAL : 568.68
ADD FOR CONTRACTORS PROFIT @10% : 56.87
ADD FOR OVER HEAD CHARGES @5% : 28.43
LABOUR FOR 2.160 Sqm 653.99
LABOUR PER sqm 302.80
MATERIAL :
wire gauge:-
2x160x40cm =1.28sqm.
Add wastage @ 10%=0.13sqm.
Total: =1.41sqm.
1sqm 1.41000 130.00 183.30
Iron hinges:-
100x58x1.90mm
10 nos. 6.00000 85.00 51.00
Iron hinges :-
50x37x1.50mm 10 nos. 2.00000 35.00 7.00
CARRIAGE :
Timber.
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
1 KM BY MECH. TRANSPORT 1 cum 0.05700 110.95 6.32
LABOUR :
Carpenter 1st Class each 1.13000 211.16 238.61
Carpenter 2nd' Class each 1.07000 186.67 199.74
Beldar each 0.86000 116.67 100.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 568.68
TOTAL : 568.68
ADD FOR CONTRACTORS PROFIT @10% : 56.87
ADD FOR OVER HEAD CHARGES @5% : 28.43
LABOUR FOR 2.160 Sqm 653.99
LABOUR PER sqm 302.80
MATERIAL :
wire gauge:-
2x160x40cm =1.28sqm.
Add wastage @ 10%=0.13sqm.
Total: =1.41sqm.
1sqm 1.41000 130.00 183.30
Iron hinges:-
100x58x1.90mm
10 nos. 6.00000 85.00 51.00
Iron hinges :-
50x37x1.50mm 10 nos. 2.00000 35.00 7.00
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.05700 110.95 6.32
LABOUR :
Carpenter 1st Class each 0.75000 211.16 158.37
Carpenter 2nd' Class each 0.71000 186.67 132.54
Beldar each 0.57000 116.67 66.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 377.41
TOTAL : 377.41
ADD FOR CONTRACTORS PROFIT @10% : 37.74
ADD FOR OVER HEAD CHARGES @5% : 18.87
LABOUR FOR 2.160 Sqm 434.02
LABOUR PER sqm 200.90
MATERIAL :
wire gauge:-
2x160x40cm =1.28sqm.
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Add wastage @ 10%=0.13sqm.
Total: =1.41sqm.
1sqm 1.41000 130.00 183.30
Iron hinges:-
100x58x1.90mm
10 nos. 6.00000 85.00 51.00
Iron hinges :-
50x37x1.50mm 10 nos. 2.00000 35.00 7.00
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.05700 110.95 6.32
LABOUR :
Carpenter 1st Class each 0.75000 211.16 158.37
Carpenter 2nd' Class each 0.71000 186.67 132.54
Beldar each 0.57000 116.67 66.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 377.41
TOTAL : 377.41
ADD FOR CONTRACTORS PROFIT @10% : 37.74
ADD FOR OVER HEAD CHARGES @5% : 18.87
LABOUR FOR 2.160 Sqm 434.02
LABOUR PER sqm 200.90
MATERIAL :
wire gauge:-
2x160x40cm =1.28sqm.
Add wastage @ 10%=0.13sqm.
Total: =1.41sqm.
1sqm 1.41000 130.00 183.30
Iron hinges:-
100x58x1.90mm
10 nos. 6.00000 85.00 51.00
Iron hinges :-
50x37x1.50mm 10 nos. 2.00000 35.00 7.00
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.05700 110.95 6.32
LABOUR :
Carpenter 1st Class each 0.75000 211.16 158.37
Carpenter 2nd' Class each 0.71000 186.67 132.54
Beldar each 0.57000 116.67 66.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 377.41
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 377.41
ADD FOR CONTRACTORS PROFIT @10% : 37.74
ADD FOR OVER HEAD CHARGES @5% : 18.87
LABOUR FOR 2.160 Sqm 434.02
LABOUR PER sqm 200.90
MATERIAL :
wire gauge:-
2x160x40cm =1.28sqm.
Add wastage @ 10%=0.13sqm.
Total: =1.41sqm.
1sqm 1.41000 130.00 183.30
Iron hinges:-
100x58x1.90mm
10 nos. 6.00000 85.00 51.00
Iron hinges :-
50x37x1.50mm 10 nos. 2.00000 35.00 7.00
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.05700 110.95 6.32
LABOUR :
Carpenter 1st Class each 0.75000 211.16 158.37
Carpenter 2nd' Class each 0.71000 186.67 132.54
Beldar each 0.57000 116.67 66.50
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
SUNDRIES : L.S. 20.00
TOTAL : 2959.98
ADD FOR CONTRACTORS PROFIT 10% 296.00
ADD FOR OVER HEAD CHARGES @5% 148.00
COST FOR 2.160 sqm 3403.98
COST PER Sqm 1575.90
LABOUR PER Sqm 200.90
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 377.41
TOTAL : 377.41
ADD FOR CONTRACTORS PROFIT @10% : 37.74
ADD FOR OVER HEAD CHARGES @5% : 18.87
LABOUR FOR 2.160 Sqm 434.02
LABOUR PER sqm 200.90
MATERIAL :
wire gauge:-
2x160x40cm =1.28sqm.
Add wastage @ 10%=0.13sqm.
Total: =1.41sqm.
1sqm 1.41000 130.00 183.30
Iron hinges:-
100x58x1.90mm
10 nos. 6.00000 85.00 51.00
Iron hinges :-
50x37x1.50mm 10 nos. 2.00000 35.00 7.00
CARRIAGE :
Timber.
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
1 KM BY MECH. TRANSPORT 1 cum 0.05700 110.95 6.32
LABOUR :
Carpenter 1st Class each 0.75000 211.16 158.37
Carpenter 2nd' Class each 0.71000 186.67 132.54
Beldar each 0.57000 116.67 66.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 377.41
TOTAL : 377.41
ADD FOR CONTRACTORS PROFIT @10% : 37.74
ADD FOR OVER HEAD CHARGES @5% : 18.87
LABOUR FOR 2.160 Sqm 434.02
LABOUR PER sqm 200.90
MATERIAL :
Rails
Top rails
wire gauge:-
2x160x40cm =1.28sqm.
Add wastage @ 10%=0.13sqm.
Total: =1.41sqm.
1sqm 1.41000 130.00 183.30
Iron hinges:-
100x58x1.90mm
10 nos. 6.00000 85.00 51.00
Iron hinges :-
50x37x1.50mm 10 nos. 2.00000 35.00 7.00
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.04400 110.95 4.88
LABOUR :
Carpenter 1st Class each 0.83000 211.16 175.26
Carpenter 2nd' Class each 0.80000 186.67 149.34
Beldar each 0.68000 116.67 79.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 423.93
TOTAL : 423.93
ADD FOR CONTRACTORS PROFIT @10% : 42.39
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR OVER HEAD CHARGES @5% : 21.20
LABOUR FOR 2.160 Sqm 487.52
LABOUR PER sqm 225.70
MATERIAL :
wire gauge:-
2x160x40cm =1.28sqm.
Add wastage @ 10%=0.13sqm.
Total: =1.41sqm.
1sqm 1.41000 130.00 183.30
Iron hinges:-
100x58x1.90mm
10 nos. 6.00000 85.00 51.00
Iron hinges :-
50x37x1.50mm 10 nos. 2.00000 35.00 7.00
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.04400 110.95 4.88
LABOUR :
Carpenter 1st Class each 0.83000 211.16 175.26
Carpenter 2nd' Class each 0.80000 186.67 149.34
Beldar each 0.68000 116.67 79.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 423.93
TOTAL : 423.93
ADD FOR CONTRACTORS PROFIT @10% : 42.39
ADD FOR OVER HEAD CHARGES @5% : 21.20
LABOUR FOR 2.160 Sqm 487.52
LABOUR PER sqm 225.70
MATERIAL :
wire gauge:-
2x160x40cm =1.28sqm.
Add wastage @ 10%=0.13sqm.
Total: =1.41sqm.
1sqm 1.41000 130.00 183.30
Iron hinges:-
100x58x1.90mm
10 nos. 6.00000 85.00 51.00
Iron hinges :-
50x37x1.50mm 10 nos. 2.00000 35.00 7.00
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.04400 110.95 4.88
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
100 MTRS BY HEAD LOAD 1 cum 0.04400 36.25 1.60
LABOUR :
Carpenter 1st Class each 0.55000 211.16 116.14
Carpenter 2nd' Class each 0.53000 186.67 98.94
Beldar each 0.45000 116.67 52.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 282.57
TOTAL : 282.57
ADD FOR CONTRACTORS PROFIT @10% : 28.26
ADD FOR OVER HEAD CHARGES @5% : 14.13
LABOUR FOR 2.160 Sqm 324.96
LABOUR PER sqm 150.45
MATERIAL :
wire gauge:-
2x160x40cm =1.28sqm.
Add wastage @ 10%=0.13sqm.
Total: =1.41sqm.
1sqm 1.41000 130.00 183.30
Iron hinges:-
100x58x1.90mm
10 nos. 6.00000 85.00 51.00
Iron hinges :-
50x37x1.50mm 10 nos. 2.00000 35.00 7.00
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.04400 110.95 4.88
LABOUR :
Carpenter 1st Class each 0.55000 211.16 116.14
Carpenter 2nd' Class each 0.53000 186.67 98.94
Beldar each 0.45000 116.67 52.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 282.57
TOTAL : 282.57
ADD FOR CONTRACTORS PROFIT @10% : 28.26
ADD FOR OVER HEAD CHARGES @5% : 14.13
LABOUR FOR 2.160 Sqm 324.96
LABOUR PER sqm 150.45
MATERIAL :
wire gauge:-
2x160x40cm =1.28sqm.
Add wastage @ 10%=0.13sqm.
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Total: =1.41sqm.
1sqm 1.41000 130.00 183.30
Iron hinges:-
100x58x1.90mm
10 nos. 6.00000 85.00 51.00
Iron hinges :-
50x37x1.50mm 10 nos. 2.00000 35.00 7.00
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.04400 110.95 4.88
LABOUR :
Carpenter 1st Class each 0.55000 211.16 116.14
Carpenter 2nd' Class each 0.53000 186.67 98.94
Beldar each 0.45000 116.67 52.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 282.57
TOTAL : 282.57
ADD FOR CONTRACTORS PROFIT @10% : 28.26
ADD FOR OVER HEAD CHARGES @5% : 14.13
LABOUR FOR 2.160 Sqm 324.96
LABOUR PER sqm 150.45
MATERIAL :
wire gauge:-
2x160x40cm =1.28sqm.
Add wastage @ 10%=0.13sqm.
Total: =1.41sqm.
1sqm 1.41000 130.00 183.30
Iron hinges:-
100x58x1.90mm
10 nos. 6.00000 85.00 51.00
Iron hinges :-
50x37x1.50mm 10 nos. 2.00000 35.00 7.00
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.04400 110.95 4.88
LABOUR :
Carpenter 1st Class each 0.55000 211.16 116.14
Carpenter 2nd' Class each 0.53000 186.67 98.94
Beldar each 0.45000 116.67 52.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 282.57
TOTAL : 282.57
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR CONTRACTORS PROFIT @10% : 28.26
ADD FOR OVER HEAD CHARGES @5% : 14.13
LABOUR FOR 2.160 Sqm 324.96
LABOUR PER sqm 150.45
MATERIAL :
wire gauge:-
2x160x40cm =1.28sqm.
Add wastage @ 10%=0.13sqm.
Total: =1.41sqm.
1sqm 1.41000 130.00 183.30
Iron hinges:-
100x58x1.90mm
10 nos. 6.00000 85.00 51.00
Iron hinges :-
50x37x1.50mm 10 nos. 2.00000 35.00 7.00
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.04400 110.95 4.88
LABOUR :
Carpenter 1st Class each 0.55000 211.16 116.14
Carpenter 2nd' Class each 0.53000 186.67 98.94
Beldar each 0.45000 116.67 52.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 282.57
TOTAL : 282.57
ADD FOR CONTRACTORS PROFIT @10% : 28.26
ADD FOR OVER HEAD CHARGES @5% : 14.13
LABOUR FOR 2.160 Sqm 324.96
LABOUR PER sqm 150.45
MATERIAL :
wire gauge:-
2x160x40cm =1.28sqm.
Add wastage @ 10%=0.13sqm.
Total: =1.41sqm.
1sqm 1.41000 130.00 183.30
Iron hinges:-
100x58x1.90mm
10 nos. 6.00000 85.00 51.00
Iron hinges :-
50x37x1.50mm 10 nos. 2.00000 35.00 7.00
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.04400 110.95 4.88
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR :
Carpenter 1st Class each 0.55000 211.16 116.14
Carpenter 2nd' Class each 0.53000 186.67 98.94
Beldar each 0.45000 116.67 52.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 282.57
TOTAL : 282.57
ADD FOR CONTRACTORS PROFIT @10% : 28.26
ADD FOR OVER HEAD CHARGES @5% : 14.13
LABOUR FOR 2.160 Sqm 324.96
LABOUR PER sqm 150.45
MATERIAL :
TOTAL : 63.45
ADD FOR CONTRACTORS PROFIT @10% : 6.35
ADD FOR OVER HEAD CHARGES @5% : 3.17
LABOUR FOR 2.160 Sqm 72.97
LABOUR PER sqm 33.80
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.03340 110.95 3.71
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 206.15
TOTAL : 206.15
ADD FOR CONTRACTORS PROFIT @10% : 20.62
ADD FOR OVER HEAD CHARGES @5% : 10.31
LABOUR FOR 0.93 Sqm 237.07
LABOUR PER sqm 254.90
MATERIAL :
Second Class Indian teak wood.
Qty. same as per item no. 1202101000
1 cum 0.03340 79390.00 2651.63
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.03340 110.95 3.71
LABOUR :
Carpenter 1st Class each 0.53000 211.16 111.91
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Carpenter 2nd' Class each 0.12000 186.67 22.40
Beldar each 0.53000 116.67 61.84
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 206.15
TOTAL : 206.15
ADD FOR CONTRACTORS PROFIT @10% : 20.62
ADD FOR OVER HEAD CHARGES @5% : 10.31
LABOUR FOR 0.93 Sqm 237.07
LABOUR PER sqm 254.90
MATERIAL :
1st class Deodar wood
Qty. same as per item no. 1202101000
1 cum 0.03340 54020.00 1804.27
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.03340 110.95 3.71
LABOUR :
Carpenter 1st Class each 0.35000 211.16 73.91
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Carpenter 2nd' Class each 0.12000 186.67 22.40
Beldar each 0.35000 116.67 40.83
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 142.14
TOTAL : 142.14
ADD FOR CONTRACTORS PROFIT @10% : 14.21
ADD FOR OVER HEAD CHARGES @5% : 7.11
LABOUR FOR 0.93 Sqm 163.46
LABOUR PER sqm 175.75
MATERIAL :
2nd class Deodar wood
Qty. same as per item no. 1202101000
1 cum 0.03340 53195.00 1776.71
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.03340 110.95 3.71
LABOUR :
Carpenter 1st Class each 0.35000 211.16 73.91
Carpenter 2nd' Class each 0.12000 186.67 22.40
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Beldar each 0.35000 116.67 40.83
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 142.14
TOTAL : 142.14
ADD FOR CONTRACTORS PROFIT @10% : 14.21
ADD FOR OVER HEAD CHARGES @5% : 7.11
LABOUR FOR 0.93 Sqm 163.46
LABOUR PER sqm 175.75
MATERIAL :
1st class kail wood
Qty. same as per item no. 1202101000
1 cum 0.03340 53195.00 1776.71
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.03340 110.95 3.71
LABOUR :
Carpenter 1st Class each 0.35000 211.16 73.91
Carpenter 2nd' Class each 0.12000 186.67 22.40
Beldar each 0.35000 116.67 40.83
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 142.14
TOTAL : 142.14
ADD FOR CONTRACTORS PROFIT @10% : 14.21
ADD FOR OVER HEAD CHARGES @5% : 7.11
LABOUR FOR 0.93 Sqm 163.46
LABOUR PER sqm 175.75
MATERIAL :
2nd class kail wood
Qty. same as per item no. 1202101000
1 cum 0.03340 40605.00 1356.21
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.03340 110.95 3.71
LABOUR :
Carpenter 1st Class each 0.35000 211.16 73.91
Carpenter 2nd' Class each 0.12000 186.67 22.40
Beldar each 0.35000 116.67 40.83
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
SUNDRIES : L.S. 5.00
TOTAL : 1558.46
ADD FOR CONTRACTORS PROFIT 10% 155.85
ADD FOR OVER HEAD CHARGES @5% 77.92
COST FOR 0.93 sqm 1792.23
COST PER Sqm 1927.10
LABOUR PER Sqm 175.75
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 142.14
TOTAL : 142.14
ADD FOR CONTRACTORS PROFIT @10% : 14.21
ADD FOR OVER HEAD CHARGES @5% : 7.11
LABOUR FOR 0.93 Sqm 163.46
LABOUR PER sqm 175.75
MATERIAL :
1st class chil wood.
Qty. same as per item no. 1202101000
1 cum 0.03340 22045.00 736.30
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.03340 110.95 3.71
LABOUR :
Carpenter 1st Class each 0.35000 211.16 73.91
Carpenter 2nd' Class each 0.12000 186.67 22.40
Beldar each 0.35000 116.67 40.83
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 142.14
TOTAL : 142.14
ADD FOR CONTRACTORS PROFIT @10% : 14.21
ADD FOR OVER HEAD CHARGES @5% : 7.11
LABOUR FOR 0.93 Sqm 163.46
LABOUR PER sqm 175.75
MATERIAL :
2nd class chil wood.
Qty. same as per item no. 1202101000
1 cum 0.03340 19330.00 645.62
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.03340 110.95 3.71
LABOUR :
Carpenter 1st Class each 0.35000 211.16 73.91
Carpenter 2nd' Class each 0.12000 186.67 22.40
Beldar each 0.35000 116.67 40.83
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 142.14
TOTAL : 142.14
ADD FOR CONTRACTORS PROFIT @10% : 14.21
ADD FOR OVER HEAD CHARGES @5% : 7.11
LABOUR FOR 0.93 Sqm 163.46
LABOUR PER sqm 175.75
MATERIAL :
------------------------------------------
Total = 0.0249 cum
Add. For louvered @ 10%=0.0025 cum
Total =0.0274 cum
Add. For wastage @ 10% =0.0027 cum
Total = 0.0301 cum
1 cum 0.03010 98625.00 2968.61
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.03010 110.95 3.34
LABOUR :
Carpenter 1st Class each 0.53000 211.16 111.91
Carpenter 2nd' Class each 0.12000 186.67 22.40
Beldar each 0.53000 116.67 61.84
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 206.15
TOTAL : 206.15
ADD FOR CONTRACTORS PROFIT @10% : 20.62
ADD FOR OVER HEAD CHARGES @5% : 10.31
LABOUR FOR 0.93 Sqm 237.07
LABOUR PER sqm 254.90
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.03010 110.95 3.34
LABOUR :
Carpenter 1st Class each 0.53000 211.16 111.91
Carpenter 2nd' Class each 0.12000 186.67 22.40
Beldar each 0.53000 116.67 61.84
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 206.15
TOTAL : 206.15
ADD FOR CONTRACTORS PROFIT @10% : 20.62
ADD FOR OVER HEAD CHARGES @5% : 10.31
LABOUR FOR 0.93 Sqm 237.07
LABOUR PER sqm 254.90
MATERIAL :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
1st class deodar wood.
Qty. same as per Item No. 1202201000
1 cum 0.03010 54020.00 1626.00
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.03010 110.95 3.34
LABOUR :
Carpenter 1st Class each 0.35000 211.16 73.91
Carpenter 2nd' Class each 0.12000 186.67 22.40
Beldar each 0.35000 116.67 40.83
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 142.14
TOTAL : 142.14
ADD FOR CONTRACTORS PROFIT @10% : 14.21
ADD FOR OVER HEAD CHARGES @5% : 7.11
LABOUR FOR 0.93 Sqm 163.46
LABOUR PER sqm 175.75
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.03010 110.95 3.34
LABOUR :
Carpenter 1st Class each 0.35000 211.16 73.91
Carpenter 2nd' Class each 0.12000 186.67 22.40
Beldar each 0.35000 116.67 40.83
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 142.14
TOTAL : 142.14
ADD FOR CONTRACTORS PROFIT @10% : 14.21
ADD FOR OVER HEAD CHARGES @5% : 7.11
LABOUR FOR 0.93 Sqm 163.46
LABOUR PER sqm 175.75
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.03010 110.95 3.34
LABOUR :
Carpenter 1st Class each 0.35000 211.16 73.91
Carpenter 2nd' Class each 0.12000 186.67 22.40
Beldar each 0.35000 116.67 40.83
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 142.14
TOTAL : 142.14
ADD FOR CONTRACTORS PROFIT @10% : 14.21
ADD FOR OVER HEAD CHARGES @5% : 7.11
LABOUR FOR 0.93 Sqm 163.46
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR PER sqm 175.75
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.03010 110.95 3.34
LABOUR :
Carpenter 1st Class each 0.35000 211.16 73.91
Carpenter 2nd' Class each 0.12000 186.67 22.40
Beldar each 0.35000 116.67 40.83
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 142.14
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 142.14
ADD FOR CONTRACTORS PROFIT @10% : 14.21
ADD FOR OVER HEAD CHARGES @5% : 7.11
LABOUR FOR 0.93 Sqm 163.46
LABOUR PER sqm 175.75
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.03010 110.95 3.34
LABOUR :
Carpenter 1st Class each 0.35000 211.16 73.91
Carpenter 2nd' Class each 0.12000 186.67 22.40
Beldar each 0.35000 116.67 40.83
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 142.14
TOTAL : 142.14
ADD FOR CONTRACTORS PROFIT @10% : 14.21
ADD FOR OVER HEAD CHARGES @5% : 7.11
LABOUR FOR 0.93 Sqm 163.46
LABOUR PER sqm 175.75
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.03010 110.95 3.34
LABOUR :
Carpenter 1st Class each 0.35000 211.16 73.91
Carpenter 2nd' Class each 0.12000 186.67 22.40
Beldar each 0.35000 116.67 40.83
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 142.14
TOTAL : 142.14
ADD FOR CONTRACTORS PROFIT @10% : 14.21
ADD FOR OVER HEAD CHARGES @5% : 7.11
LABOUR FOR 0.93 Sqm 163.46
LABOUR PER sqm 175.75
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.08800 110.95 9.76
LABOUR :
Carpenter 1st Class each 1.53000 211.16 323.07
Carpenter 2nd' Class each 2.33000 186.67 434.94
Beldar each 1.53000 116.67 178.51
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 986.52
TOTAL : 986.52
ADD FOR CONTRACTORS PROFIT @10% : 98.65
ADD FOR OVER HEAD CHARGES @5% : 49.33
LABOUR FOR 5.760 Sqm 1134.50
LABOUR PER sqm 196.95
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.08800 110.95 9.76
LABOUR :
Carpenter 1st Class each 1.53000 211.16 323.07
Carpenter 2nd' Class each 2.33000 186.67 434.94
Beldar each 1.53000 116.67 178.51
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 986.52
TOTAL : 986.52
ADD FOR CONTRACTORS PROFIT @10% : 98.65
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR OVER HEAD CHARGES @5% : 49.33
LABOUR FOR 5.760 Sqm 1134.50
LABOUR PER sqm 196.95
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.08800 110.95 9.76
LABOUR :
Carpenter 1st Class each 1.02000 211.16 215.38
Carpenter 2nd' Class each 1.55000 186.67 289.34
Beldar each 1.02000 116.67 119.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 658.73
TOTAL : 658.73
ADD FOR CONTRACTORS PROFIT @10% : 65.87
ADD FOR OVER HEAD CHARGES @5% : 32.94
LABOUR FOR 5.760 Sqm 757.53
LABOUR PER sqm 131.50
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.08800 110.95 9.76
LABOUR :
Carpenter 1st Class each 1.02000 211.16 215.38
Carpenter 2nd' Class each 1.55000 186.67 289.34
Beldar each 1.02000 116.67 119.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 658.73
TOTAL : 658.73
ADD FOR CONTRACTORS PROFIT @10% : 65.87
ADD FOR OVER HEAD CHARGES @5% : 32.94
LABOUR FOR 5.760 Sqm 757.53
LABOUR PER sqm 131.50
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.08800 110.95 9.76
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 658.73
TOTAL : 658.73
ADD FOR CONTRACTORS PROFIT @10% : 65.87
ADD FOR OVER HEAD CHARGES @5% : 32.94
LABOUR FOR 5.760 Sqm 757.53
LABOUR PER sqm 131.50
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.08800 110.95 9.76
LABOUR :
Carpenter 1st Class each 1.02000 211.16 215.38
Carpenter 2nd' Class each 1.55000 186.67 289.34
Beldar each 1.02000 116.67 119.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 658.73
TOTAL : 658.73
ADD FOR CONTRACTORS PROFIT @10% : 65.87
ADD FOR OVER HEAD CHARGES @5% : 32.94
LABOUR FOR 5.760 Sqm 757.53
LABOUR PER sqm 131.50
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.08800 110.95 9.76
LABOUR :
Carpenter 1st Class each 1.02000 211.16 215.38
Carpenter 2nd' Class each 1.55000 186.67 289.34
Beldar each 1.02000 116.67 119.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 658.73
TOTAL : 658.73
ADD FOR CONTRACTORS PROFIT @10% : 65.87
ADD FOR OVER HEAD CHARGES @5% : 32.94
LABOUR FOR 5.760 Sqm 757.53
LABOUR PER sqm 131.50
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
1202308000 2nd class chil wood.
Details of cost for venetians (of a
windows) 240x240cm=5.76 sqm.
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.08800 110.95 9.76
LABOUR :
Carpenter 1st Class each 1.02000 211.16 215.38
Carpenter 2nd' Class each 1.55000 186.67 289.34
Beldar each 1.02000 116.67 119.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 658.73
TOTAL : 658.73
ADD FOR CONTRACTORS PROFIT @10% : 65.87
ADD FOR OVER HEAD CHARGES @5% : 32.94
LABOUR FOR 5.760 Sqm 757.53
LABOUR PER sqm 131.50
MATERIAL :
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 434.18
TOTAL : 434.18
ADD FOR CONTRACTORS PROFIT @10% : 43.42
ADD FOR OVER HEAD CHARGES @5% : 21.71
LABOUR FOR 5.760 Sqm 499.30
LABOUR PER sqm 86.70
MATERIAL :
LABOUR :
LABOUR RATE :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ACTUAL LABOUR+SUNDRIES 434.18
TOTAL : 434.18
ADD FOR CONTRACTORS PROFIT @10% : 43.42
ADD FOR OVER HEAD CHARGES @5% : 21.71
LABOUR FOR 5.760 Sqm 499.30
LABOUR PER sqm 86.70
MATERIAL :
CARRIAGE :
Timber.
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
1 KM BY MECH. TRANSPORT 1 cum 0.32600 110.95 36.17
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 2004.97
TOTAL : 2004.97
ADD FOR CONTRACTORS PROFIT @10% : 200.50
ADD FOR OVER HEAD CHARGES @5% : 100.25
LABOUR FOR 7.200 Sqm 2305.72
LABOUR PER sqm 320.20
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.32600 110.95 36.17
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1339.36
TOTAL : 1339.36
ADD FOR CONTRACTORS PROFIT @10% : 133.94
ADD FOR OVER HEAD CHARGES @5% : 66.97
LABOUR FOR 7.200 Sqm 1540.26
LABOUR PER sqm 213.90
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.32600 110.95 36.17
LABOUR :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1339.36
TOTAL : 1339.36
ADD FOR CONTRACTORS PROFIT @10% : 133.94
ADD FOR OVER HEAD CHARGES @5% : 66.97
LABOUR FOR 7.200 Sqm 1540.26
LABOUR PER sqm 213.90
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.03700 110.95 4.11
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR :
Carpenter 1st Class each 1.13000 211.16 238.61
Carpenter 2nd' Class each 1.75000 186.67 326.67
Beldar each 0.50000 116.67 58.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 658.62
TOTAL : 658.62
ADD FOR CONTRACTORS PROFIT @10% : 65.86
ADD FOR OVER HEAD CHARGES @5% : 32.93
LABOUR FOR 2.200 Sqm 757.41
LABOUR PER sqm 344.25
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.03700 110.95 4.11
LABOUR :
Carpenter 1st Class each 0.75000 211.16 158.37
Carpenter 2nd' Class each 1.10000 186.67 205.34
Beldar each 0.50000 116.67 58.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 432.04
TOTAL : 432.04
ADD FOR CONTRACTORS PROFIT @10% : 43.20
ADD FOR OVER HEAD CHARGES @5% : 21.60
LABOUR FOR 2.200 Sqm 496.85
LABOUR PER sqm 225.80
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.03700 110.95 4.11
LABOUR :
Carpenter 1st Class each 0.75000 211.16 158.37
Carpenter 2nd' Class each 1.10000 186.67 205.34
Beldar each 0.50000 116.67 58.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 432.04
TOTAL : 432.04
ADD FOR CONTRACTORS PROFIT @10% : 43.20
ADD FOR OVER HEAD CHARGES @5% : 21.60
LABOUR FOR 2.200 Sqm 496.85
LABOUR PER sqm 225.80
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.03700 110.95 4.11
LABOUR :
Carpenter 1st Class each 0.75000 211.16 158.37
Carpenter 2nd' Class each 1.10000 186.67 205.34
Beldar each 0.50000 116.67 58.34
LABOUR RATE :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ACTUAL LABOUR+SUNDRIES 432.04
TOTAL : 432.04
ADD FOR CONTRACTORS PROFIT @10% : 43.20
ADD FOR OVER HEAD CHARGES @5% : 21.60
LABOUR FOR 2.200 Sqm 496.85
LABOUR PER sqm 225.80
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.03700 110.95 4.11
LABOUR :
Carpenter 1st Class each 0.75000 211.16 158.37
Carpenter 2nd' Class each 1.10000 186.67 205.34
Beldar each 0.50000 116.67 58.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 432.04
TOTAL : 432.04
ADD FOR CONTRACTORS PROFIT @10% : 43.20
ADD FOR OVER HEAD CHARGES @5% : 21.60
LABOUR FOR 2.200 Sqm 496.85
LABOUR PER sqm 225.80
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
1202600000 Providing and fixing plain jafri
door and window shutters including
bright finished/black enemelled M.S.
butt hinges with necessary screws,
40mmx12mm
laths placed 40 mm
apart (frame to be paid separately)
including fixing 50 mmx12mm beading
complete with.
MATERIAL :
Styles:-
2x176x7.50x4.00 cm = 0.011 cum.
Rails : 3x86x7.5x4.00 cm = 0.008 cum
CARRIAGE :
LABOUR :
TOTAL : 4645.41
ADD FOR CONTRACTORS PROFIT 10% Except on (-1-) 180.26
ADD FOR OVER HEAD CHARGES @5% Except on (-1-) 90.13
COST FOR 1.510 sqm 4915.80
COST PER Sqm 3255.50
LABOUR RATE :
MATERIAL :
CARRIAGE :
LABOUR :
TOTAL : 3192.90
ADD FOR CONTRACTORS PROFIT 10% Except on (-1-) 127.00
ADD FOR OVER HEAD CHARGES @5% Except on (-1-) 63.50
COST FOR 1.510 sqm 3383.40
COST PER Sqm 2240.65
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 56.00
Labour as per item no. 1202501000 340.95 (-a-)
TOTAL : 396.95
ADD FOR CONTRACTORS PROFIT @10% : Except on (-a-): 5.60
ADD FOR OVER HEAD CHARGES @5% Except on (-a-) : 2.80
LABOUR FOR 1.510 Sqm 405.35
LABOUR PER sqm 268.45
MATERIAL :
CARRIAGE :
LABOUR :
TOTAL : 3151.41
ADD FOR CONTRACTORS PROFIT 10% Except on (-1-) 125.25
ADD FOR OVER HEAD CHARGES @5% Except on (-1-) 62.62
COST FOR 1.510 sqm 3339.28
COST PER Sqm 2211.45
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 56.00
Labour as per item no. 1202501000 340.95 (-a-)
TOTAL : 396.95
ADD FOR CONTRACTORS PROFIT @10% : Except on (-a-): 5.60
ADD FOR OVER HEAD CHARGES @5% Except on (-a-) : 2.80
LABOUR FOR 1.510 Sqm 405.35
LABOUR PER sqm 268.45
MATERIAL :
CARRIAGE :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR :
TOTAL : 3151.41
ADD FOR CONTRACTORS PROFIT 10% Except on (-1-) 125.25
ADD FOR OVER HEAD CHARGES @5% Except on (-1-) 62.62
COST FOR 1.510 sqm 3339.28
COST PER Sqm 2211.45
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 56.00
Labour as per item no. 1202501000 340.95 (-a-)
TOTAL : 396.95
ADD FOR CONTRACTORS PROFIT @10% : Except on (-a-): 5.60
ADD FOR OVER HEAD CHARGES @5% Except on (-a-) : 2.80
LABOUR FOR 1.510 Sqm 405.35
LABOUR PER sqm 268.45
MATERIAL :
CARRIAGE :
LABOUR :
TOTAL : 2519.34
ADD FOR CONTRACTORS PROFIT 10% Except on (-1-) 98.82
ADD FOR OVER HEAD CHARGES @5% Except on (-1-) 49.41
COST FOR 1.510 sqm 2667.57
COST PER Sqm 1766.60
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 56.00
Labour as per item no. 1202501000 340.95 (-a-)
TOTAL : 396.95
ADD FOR CONTRACTORS PROFIT @10% : Except on (-a-): 5.60
ADD FOR OVER HEAD CHARGES @5% Except on (-a-) : 2.80
LABOUR FOR 1.510 Sqm 405.35
LABOUR PER sqm 268.45
1202701010 12 mm thick.
Details of cost for 10 sqm.
MATERIAL :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
First class Indian teak wood
10.00 sq.mt. X 0.0.012m. =0.120 cum
Add for wastage @ 10% =0.012
Total = 0.132 cum 1 cum 0.13200 98625.00 13018.50
Add. Extra rate for selected planks for special work @10% 1301.80
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.13200 110.95 14.65
LABOUR :
SUNDRIES : 55.00
TOTAL : 15824.97
ADD FOR CONTRACTORS PROFIT 10% 1582.50
ADD FOR OVER HEAD CHARGES @5% 791.25
COST FOR 10 sqm 18198.72
COST PER Sqm 1819.85
LABOUR PER sqm. 170.80
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1485.25
TOTAL : 1485.25
ADD FOR CONTRACTORS PROFIT @10% : 148.52
ADD FOR OVER HEAD CHARGES @5% 74.26
LABOUR FOR 10 Sqm 1708.03
LABOUR PER sqm 170.80
1202701020 20 mm thick.
Details of cost for 10 sqm.
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.22000 110.95 24.41
LABOUR :
Carpenter 1st Class each 4.95000 211.16 1045.24
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1485.25
TOTAL : 1485.25
ADD FOR CONTRACTORS PROFIT @10% : 148.53
ADD FOR OVER HEAD CHARGES @5% : 74.26
LABOUR FOR 10 Sqm 1708.04
LABOUR PER sqm 170.80
1202701020 25 mm thick.
Details of cost for 10 sqm.
MATERIAL :
Add. Extra rate for selected planks for special work @10% 2712.19
CARRIAGE :
Timber.
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
1 KM BY MECH. TRANSPORT 1 cum 0.27500 110.95 30.51
LABOUR :
Carpenter 1st Class each 4.95000 211.16 1045.24
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1485.25
TOTAL : 1485.25
ADD FOR CONTRACTORS PROFIT @10% : 148.53
ADD FOR OVER HEAD CHARGES @5% : 74.26
LABOUR FOR 10 Sqm 1708.04
LABOUR PER sqm 170.80
1202702010 12 mm thick
Detail of cost for 10 sqm.
MATERIAL :
Add. Extra rate for selected planks for special work @10% 1047.95
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.13200 110.95 14.65
LABOUR :
Carpenter 1st Class each 4.95000 211.16 1045.24
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1485.25
TOTAL : 1485.25
ADD FOR CONTRACTORS PROFIT @10% : 148.53
ADD FOR OVER HEAD CHARGES @5% : 74.26
LABOUR FOR 10 Sqm 1708.04
LABOUR PER sqm 170.80
1202702020 20 mm thick
Details of cost for 10 sqm.
MATERIAL :
Add. Extra rate for selected planks for special work @10% 1746.58
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.22000 110.95 24.41
LABOUR :
Carpenter 1st Class each 4.95000 211.16 1045.24
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1485.25
TOTAL : 1485.25
ADD FOR CONTRACTORS PROFIT @10% : 148.53
ADD FOR OVER HEAD CHARGES @5% : 74.26
LABOUR FOR 10 Sqm 1708.04
LABOUR PER sqm 170.80
1202702030 25 mm thick
Details of cost for 10 sqm.
MATERIAL :
Add. Extra rate for selected planks for special work @10% 2183.23
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.27500 110.95 30.51
LABOUR :
Carpenter 1st Class each 4.95000 211.16 1045.24
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1485.25
TOTAL : 1485.25
ADD FOR CONTRACTORS PROFIT @10% : 148.53
ADD FOR OVER HEAD CHARGES @5% : 74.26
LABOUR FOR 10 Sqm 1708.04
LABOUR PER sqm 170.80
MATERIAL :
Add. Extra rate for selected planks for special work @10% 713.06
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.13200 110.95 14.65
LABOUR :
Carpenter 1st Class each 3.30000 211.16 696.83
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1008.50
TOTAL : 1008.50
ADD FOR CONTRACTORS PROFIT @10% : 100.85
ADD FOR OVER HEAD CHARGES @5% : 50.43
LABOUR FOR 10 Sqm 1159.78
LABOUR PER sqm 116.00
1202703020 20 mm thick
Details of cost for 10sqm.
MATERIAL :
Add. Extra rate for selected planks for special work @10% 1188.44
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.22000 110.95 24.41
LABOUR :
Carpenter 1st Class each 3.30000 211.16 696.83
1202703030 25 mm thick
Details of cost for 10 sqm.
MATERIAL :
Add. Extra rate for selected planks for special work @10% 1485.55
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.27500 110.95 30.51
LABOUR :
Carpenter 1st Class each 3.30000 211.16 696.83
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1008.50
TOTAL : 1008.50
ADD FOR CONTRACTORS PROFIT @10% : 100.85
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR OVER HEAD CHARGES @5% : 50.43
LABOUR FOR 10 Sqm 1159.78
LABOUR PER sqm 116.00
1202704010 12 mm thick.
Details of cost for 10 sqm.
MATERIAL :
Add. Extra rate for selected planks for special work @10% 702.17
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.13200 110.95 14.65
LABOUR :
Carpenter 1st Class each 3.30000 211.16 696.83
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1008.50
TOTAL : 1008.50
ADD FOR CONTRACTORS PROFIT @10% : 100.85
ADD FOR OVER HEAD CHARGES @5% : 50.43
LABOUR FOR 10 Sqm 1159.78
LABOUR PER sqm 116.00
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
1202704020 20 mm thick
Details of cost for 10 sqm.
MATERIAL :
Add. Extra rate for selected planks for special work @10% 1170.29
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.22000 110.95 24.41
LABOUR :
Carpenter 1st Class each 3.30000 211.16 696.83
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1008.50
TOTAL : 1008.50
ADD FOR CONTRACTORS PROFIT @10% : 100.85
ADD FOR OVER HEAD CHARGES @5% : 50.43
LABOUR FOR 10 Sqm 1159.78
LABOUR PER sqm 116.00
1202704030 25 mm thick
Details of cost for 10 sqm.
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
Add. Extra rate for selected planks for special work @10% 1462.86
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.27500 110.95 30.51
LABOUR :
Carpenter 1st Class each 3.30000 211.16 696.83
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1008.50
TOTAL : 1008.50
ADD FOR CONTRACTORS PROFIT @10% : 100.85
ADD FOR OVER HEAD CHARGES @5% : 50.43
LABOUR FOR 10 Sqm 1159.78
LABOUR PER sqm 116.00
1202705010 12 mm thick.
Details of cost for 10 sqm.
MATERIAL :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Add. Extra rate for selected planks for special work @10% 702.17
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.13200 110.95 14.65
LABOUR :
Carpenter 1st Class each 3.30000 211.16 696.83
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1008.50
TOTAL : 1008.50
ADD FOR CONTRACTORS PROFIT @10% : 100.85
ADD FOR OVER HEAD CHARGES @5% : 50.43
LABOUR FOR 10 Sqm 1159.78
LABOUR PER sqm 116.00
1202705020 20 mm thick.
MATERIAL :
Add. Extra rate for selected planks for special work @10% 1170.29
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.22000 110.95 24.41
LABOUR :
Carpenter 1st Class each 3.30000 211.16 696.83
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1008.50
TOTAL : 1008.50
ADD FOR CONTRACTORS PROFIT @10% : 100.85
ADD FOR OVER HEAD CHARGES @5% : 50.43
LABOUR FOR 10 Sqm 1159.78
LABOUR PER sqm 116.00
1202705030 25 mm thick
Details of cost for 10 sqm.
MATERIAL :
Add. Extra rate for selected planks for special work @10% 1462.86
CARRIAGE :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.27500 110.95 30.51
LABOUR :
Carpenter 1st Class each 3.30000 211.16 696.83
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1008.50
TOTAL : 1008.50
ADD FOR CONTRACTORS PROFIT @10% : 100.85
ADD FOR OVER HEAD CHARGES @5% : 50.43
LABOUR FOR 10 Sqm 1159.78
LABOUR PER sqm 116.00
1202706010 12 mm thick
Details of cost for 10 sqm.
MATERIAL :
Add. Extra rate for selected planks for special work @10% 536.00
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.13200 110.95 14.65
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
100 MTRS BY HEAD LOAD 1 cum 0.13200 36.25 4.79
LABOUR :
Carpenter 1st Class each 3.30000 211.16 696.83
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1008.50
TOTAL : 1008.50
ADD FOR CONTRACTORS PROFIT @10% : 100.85
ADD FOR OVER HEAD CHARGES @5% : 50.43
LABOUR FOR 10 Sqm 1159.78
LABOUR PER sqm 116.00
1202706020 20 mm thick
Details of cost for 10 sqm.
MATERIAL :
Add. Extra rate for selected planks for special work @10% 893.00
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.22000 110.95 24.41
LABOUR :
Carpenter 1st Class each 3.30000 211.16 696.83
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1008.50
TOTAL : 1008.50
ADD FOR CONTRACTORS PROFIT @10% : 100.85
ADD FOR OVER HEAD CHARGES @5% : 50.43
LABOUR FOR 10 Sqm 1159.78
LABOUR PER sqm 116.00
1202706030 25 mm thick.
Details of cost for 10 sqm.
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.27500 110.95 30.51
LABOUR :
Carpenter 1st Class each 3.30000 211.16 696.83
Beldar each 2.20000 116.67 256.67
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
SUNDRIES : L.S 55.00
TOTAL : 13331.99
ADD FOR CONTRACTORS PROFIT 10% 1333.20
ADD FOR OVER HEAD CHARGES @5% 666.60
COST FOR 10.00 sq.m 15331.79
COST PER sq.m 1533.20
LABOUR PER sq.m 116.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1008.50
TOTAL : 1008.50
ADD FOR CONTRACTORS PROFIT @10% : 100.85
ADD FOR OVER HEAD CHARGES @5% : 50.43
LABOUR FOR 10.000 sq.m 1159.78
LABOUR PER sq.m 116.00
1202801010 12 mm thick.
Details of cost for 10 sqm.
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.13200 110.95 14.65
LABOUR :
Carpenter 1st Class each 4.35000 211.16 918.55
Beldar each 2.70000 116.67 315.01
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1288.56
TOTAL : 1288.56
ADD FOR CONTRACTORS PROFIT @10% : 128.86
ADD FOR OVER HEAD CHARGES @5% : 64.43
LABOUR FOR 10.000 sq.m 1481.84
LABOUR PER sq.m 148.20
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.22000 110.95 24.41
LABOUR :
Carpenter 1st Class each 4.35000 211.16 918.55
Beldar each 2.70000 116.67 315.01
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1288.56
TOTAL : 1288.56
ADD FOR CONTRACTORS PROFIT @10% : 128.86
ADD FOR OVER HEAD CHARGES @5% : 64.43
LABOUR FOR 10.000 sq.m 1481.84
LABOUR PER sq.m 148.20
1202801030 25 mm thick.
Details of cost for 10sqm.
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.27500 110.95 30.51
LABOUR :
Carpenter 1st Class each 4.35000 211.16 918.55
Beldar each 2.70000 116.67 315.01
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1288.56
TOTAL : 1288.56
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR CONTRACTORS PROFIT @10% : 128.86
ADD FOR OVER HEAD CHARGES @5% : 64.43
LABOUR FOR 10.000 sq.m 1481.84
LABOUR PER sq.m 148.20
1202802010 12 mm thick.
Details of cost for 10 sqm.
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.13200 110.95 14.65
LABOUR :
Carpenter 1st Class each 4.35000 211.16 918.55
Beldar each 2.70000 116.67 315.01
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1288.56
TOTAL : 1288.56
ADD FOR CONTRACTORS PROFIT @10% : 128.86
ADD FOR OVER HEAD CHARGES @5% : 64.43
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR FOR 10.000 sq.m 1481.84
LABOUR PER sq.m 148.20
1202802020 20 mm thick.
Details of cost for 10 sqm.
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.22000 110.95 24.41
LABOUR :
Carpenter 1st Class each 4.35000 211.16 918.55
Beldar each 2.70000 116.67 315.01
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1288.56
TOTAL : 1288.56
ADD FOR CONTRACTORS PROFIT @10% : 128.86
ADD FOR OVER HEAD CHARGES @5% : 64.43
LABOUR FOR 10.000 sq.m 1481.84
LABOUR PER sq.m 148.20
1202802030 25 mm thick
Details of cost for 10 sqm.
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.27500 110.95 30.51
LABOUR :
Carpenter 1st Class each 4.35000 211.16 918.55
Beldar each 2.70000 116.67 315.01
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1288.56
TOTAL : 1288.56
ADD FOR CONTRACTORS PROFIT @10% : 128.86
ADD FOR OVER HEAD CHARGES @5% : 64.43
LABOUR FOR 10.000 sq.m 1481.84
LABOUR PER sq.m 148.20
1202803010 12 mm thick.
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Details of cost for 10 sqm.
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.13200 110.95 14.65
LABOUR :
Carpenter 1st Class each 2.70000 211.16 570.13
Beldar each 1.60000 116.67 186.67
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 801.80
TOTAL : 801.80
ADD FOR CONTRACTORS PROFIT @10% : 80.18
ADD FOR OVER HEAD CHARGES @5% : 40.09
LABOUR FOR 10.000 sq.m 922.07
LABOUR PER sq.m 92.20
1202803020 20 mm thick.
Details of cost for 10 sqm.
MATERIAL :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
First class Deodar wood.
10.00 sqm x 0.02 = 0.200
Add for wastage at 10% = 0.020 cum
TotAL = 0.220 cum
1 cum 0.22000 54020.00 11884.40
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.22000 110.95 24.41
LABOUR :
Carpenter 1st Class each 2.70000 211.16 570.13
Beldar each 1.60000 116.67 186.67
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 801.80
TOTAL : 801.80
ADD FOR CONTRACTORS PROFIT @10% : 80.18
ADD FOR OVER HEAD CHARGES @5% : 40.09
LABOUR FOR 10.000 sq.m 922.07
LABOUR PER sq.m 92.20
1202803030 25 mm thick.
Details of cost for 10 sqm.
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.27500 110.95 30.51
LABOUR :
Carpenter 1st Class each 2.70000 211.16 570.13
Beldar each 1.60000 116.67 186.67
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 801.80
TOTAL : 801.80
ADD FOR CONTRACTORS PROFIT @10% : 80.18
ADD FOR OVER HEAD CHARGES @5% : 40.09
LABOUR FOR 10.000 sq.m 922.07
LABOUR PER sq.m 92.20
1202804010 12 mm thick
Details of cost for 10 sqm.
MATERIAL :
CARRIAGE :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.13200 110.95 14.65
LABOUR :
Carpenter 1st Class each 2.70000 211.16 570.13
Beldar each 1.60000 116.67 186.67
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 801.80
TOTAL : 801.80
ADD FOR CONTRACTORS PROFIT @10% : 80.18
ADD FOR OVER HEAD CHARGES @5% : 40.09
LABOUR FOR 10.000 sq.m 922.07
LABOUR PER sq.m 92.20
202804020 20 mm thick.
Details of cost for 10 sqm.
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.22000 110.95 24.41
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 801.80
TOTAL : 801.80
ADD FOR CONTRACTORS PROFIT @10% : 80.18
ADD FOR OVER HEAD CHARGES @5% : 40.09
LABOUR FOR 10.000 sq.m 922.07
LABOUR PER sq.m 92.20
1202804030 25 mm thick
Details of cost for 10 sqm.
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.27500 110.95 30.51
LABOUR :
Carpenter 1st Class each 2.70000 211.16 570.13
Beldar each 1.60000 116.67 186.67
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 801.80
TOTAL : 801.80
ADD FOR CONTRACTORS PROFIT @10% : 80.18
ADD FOR OVER HEAD CHARGES @5% : 40.09
LABOUR FOR 10.000 sq.m 922.07
LABOUR PER sq.m 92.20
1202805010 12 mm thick
Details of cost for 10 sqm.
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.13200 110.95 14.65
LABOUR :
Carpenter 1st Class each 2.70000 211.16 570.13
Beldar each 1.60000 116.67 186.67
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 801.80
TOTAL : 801.80
ADD FOR CONTRACTORS PROFIT @10% : 80.18
ADD FOR OVER HEAD CHARGES @5% : 40.09
LABOUR FOR 10.000 sq.m 922.07
LABOUR PER sq.m 92.20
1202805020 20 mm thick.
Details of cost for 10 sqm.
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.22000 110.95 24.41
LABOUR :
Carpenter 1st Class each 2.70000 211.16 570.13
Beldar each 1.60000 116.67 186.67
1202805030 25 mm thick
Details of cost for 10 sqm.
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.27500 110.95 30.51
LABOUR :
Carpenter 1st Class each 2.70000 211.16 570.13
Beldar each 1.60000 116.67 186.67
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 801.80
TOTAL : 801.80
ADD FOR CONTRACTORS PROFIT @10% : 80.18
ADD FOR OVER HEAD CHARGES @5% : 40.09
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR FOR 10.000 sq.m 922.07
LABOUR PER sq.m 92.20
1202806010 12 mm thick
Details of cost for 10 sqm.
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.13200 110.95 14.65
LABOUR :
Carpenter 1st Class each 2.70000 211.16 570.13
Beldar each 1.60000 116.67 186.67
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 801.80
TOTAL : 801.80
ADD FOR CONTRACTORS PROFIT @10% : 80.18
ADD FOR OVER HEAD CHARGES @5% : 40.09
LABOUR FOR 10.000 sq.m 922.07
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR PER sq.m 92.20
1202806020 20 mm thick.
Details of cost for 10 sqm.
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.22000 110.95 24.41
LABOUR :
Carpenter 1st Class each 2.70000 211.16 570.13
Beldar each 1.60000 116.67 186.67
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 801.80
TOTAL : 801.80
ADD FOR CONTRACTORS PROFIT @10% : 80.18
ADD FOR OVER HEAD CHARGES @5% : 40.09
LABOUR FOR 10.000 sq.m 922.07
LABOUR PER sq.m 92.20
1202806030 25 mm thick
Details of cost for 10 sqm.
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.27500 110.95 30.51
LABOUR :
Carpenter 1st Class each 2.70000 211.16 570.13
Beldar each 1.60000 116.67 186.67
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 801.80
TOTAL : 801.80
ADD FOR CONTRACTORS PROFIT @10% : 80.18
ADD FOR OVER HEAD CHARGES @5% : 40.09
LABOUR FOR 10.000 sq.m 922.07
LABOUR PER sq.m 92.21
LABOUR :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Carpenter 1st Class each 0.60000 211.16 126.70
Beldar each 0.60000 116.67 70.00
TOTAL : 196.70
ADD FOR CONTRACTORS PROFIT 10% 19.67
ADD FOR OVER HEAD CHARGES @5% 9.84
COST FOR 10.00 sq.m 226.20
COST PER sq.m 22.60
LABOUR PER sq.m 22.60
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 196.70
TOTAL : 196.70
ADD FOR CONTRACTORS PROFIT @10% : 19.67
ADD FOR OVER HEAD CHARGES @5% : 9.83
LABOUR FOR 10.000 sq.m 226.20
LABOUR PER sq.m 22.60
1203001000 9 mm thick.
Details of cost for 10 sqm.
MATERIAL :
CARRIAGE :
carriage insulation board L.S. 15.00
LABOUR :
Carpenter 1st Class each 0.50000 211.16 105.58
Beldar each 0.50000 116.67 58.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 173.92
TOTAL : 173.92
ADD FOR CONTRACTORS PROFIT @10% : 17.39
ADD FOR OVER HEAD CHARGES @5% : 8.70
LABOUR FOR 10.000 sq.m 200.00
LABOUR PER sq.m 20.00
1203002000 12 mm thick
Details of cost for 10 sqm.
MATERIAL :
CARRIAGE :
carriage insulation board L.S. 15.00
LABOUR :
Carpenter 1st Class each 0.50000 211.16 105.58
Beldar each 0.50000 116.67 58.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 173.92
TOTAL : 173.92
ADD FOR CONTRACTORS PROFIT @10% : 17.39
ADD FOR OVER HEAD CHARGES @5% : 8.70
LABOUR FOR 10.000 sq.m 200.00
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR PER sq.m 20.00
1203003000 18 mm thick
Details of cost for 10 sqm.
MATERIAL :
CARRIAGE :
carriage insulation board L.S. 15.00
LABOUR :
Carpenter 1st Class each 0.50000 211.16 105.58
Beldar each 0.50000 116.67 58.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 173.92
TOTAL : 173.92
ADD FOR CONTRACTORS PROFIT @10% : 17.39
ADD FOR OVER HEAD CHARGES @5% : 8.70
LABOUR FOR 10.000 sq.m 200.00
LABOUR PER sq.m 20.00
1203004000 25 mm thick
Details of cost for 10 sqm.
MATERIAL :
CARRIAGE :
carriage insulation board L.S. 15.00
LABOUR :
Carpenter 1st Class each 0.50000 211.16 105.58
Beldar each 0.50000 116.67 58.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 173.92
TOTAL : 173.92
ADD FOR CONTRACTORS PROFIT @10% : 17.39
ADD FOR OVER HEAD CHARGES @5% : 8.70
LABOUR FOR 10.000 sq.m 200.00
LABOUR PER sq.m 20.00
1203101000 12 mm thick
Details of cost for 10 sqm.
MATERIAL :
CARRIAGE :
carriage particle board L.S. 15.00
LABOUR :
Carpenter 1st Class each 0.50000 211.16 105.58
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Beldar each 0.50000 116.67 58.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 173.92
TOTAL : 173.92
ADD FOR CONTRACTORS PROFIT @10% : 17.39
ADD FOR OVER HEAD CHARGES @5% : 8.70
LABOUR FOR 10.000 sq.m 200.00
LABOUR PER sq.m 20.00
1203102000 19 mm thick
Details of cost for 10 sqm.
MATERIAL :
CARRIAGE :
carriage particle board L.S. 15.00
LABOUR :
Carpenter 1st Class each 0.50000 211.16 105.58
Beldar each 0.50000 116.67 58.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 173.92
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 173.92
ADD FOR CONTRACTORS PROFIT @10% : 17.39
ADD FOR OVER HEAD CHARGES @5% : 8.70
LABOUR FOR 10.000 sq.m 200.00
LABOUR PER sq.m 20.00
1203103000 25 mm thick
Details of cost for 10 sqm.
MATERIAL :
CARRIAGE :
carriage particle board L.S. 15.00
LABOUR :
Carpenter 1st Class each 0.50000 211.16 105.58
Beldar each 0.50000 116.67 58.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 173.92
TOTAL : 173.92
ADD FOR CONTRACTORS PROFIT @10% : 17.39
ADD FOR OVER HEAD CHARGES @5% : 8.70
LABOUR FOR 10.000 sq.m 200.00
LABOUR PER sq.m 20.00
1203201000 3 mm thick.
Details of cost for 10 sqm.
MATERIAL :
CARRIAGE :
carriage hard board sheet L.S. 15.00
LABOUR :
Carpenter 1st Class each 0.50000 211.16 105.58
Beldar each 0.50000 116.67 58.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 173.92
TOTAL : 173.92
ADD FOR CONTRACTORS PROFIT @10% : 17.39
ADD FOR OVER HEAD CHARGES @5% : 8.70
LABOUR FOR 10.000 sq.m 200.00
LABOUR PER sq.m 20.00
MATERIAL :
LABOUR :
Carpenter 1st Class each 0.50000 211.16 105.58
Beldar each 0.50000 116.67 58.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 173.92
TOTAL : 173.92
ADD FOR CONTRACTORS PROFIT @10% : 17.39
ADD FOR OVER HEAD CHARGES @5% : 8.70
LABOUR FOR 10.000 sq.m 200.00
LABOUR PER sq.m 20.00
1203203000 6 mm thick.
Details of cost for 10 sqm.
MATERIAL :
CARRIAGE :
carriage hard board sheet L.S. 15.00
LABOUR :
Carpenter 1st Class each 0.50000 211.16 105.58
Beldar each 0.50000 116.67 58.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 173.92
TOTAL : 173.92
ADD FOR CONTRACTORS PROFIT @10% : 17.39
ADD FOR OVER HEAD CHARGES @5% : 8.70
LABOUR FOR 10.000 sq.m 200.00
LABOUR PER sq.m 20.00
1203204000 9 mm thick.
Details of cost for 10 sqm.
MATERIAL :
CARRIAGE :
carriage hard board sheet L.S. 15.00
LABOUR :
Carpenter 1st Class each 0.50000 211.16 105.58
Beldar each 0.50000 116.67 58.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 173.92
TOTAL : 173.92
ADD FOR CONTRACTORS PROFIT @10% : 17.39
ADD FOR OVER HEAD CHARGES @5% : 8.70
LABOUR FOR 10.000 sq.m 200.00
LABOUR PER sq.m 20.00
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
1203300000 Providing and fixing ply wood
lining with butt jointing and nails
(frame work and coner fillets to be
measured and paid for separately).
1203301000 3 mm thick.
Details of cost for 10 sqm.
MATERIAL :
LABOUR :
Carpenter 1st Class each 0.74000 211.16 156.26
Beldar each 0.74000 116.67 86.34
TOTAL : 1672.59
ADD FOR CONTRACTORS PROFIT 10% 167.26
ADD FOR OVER HEAD CHARGES @5% 83.63
COST FOR 10.00 sq.m 1923.48
COST PER sq.m 192.35
LABOUR PER sq.m 27.90
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 242.59
TOTAL : 242.59
ADD FOR CONTRACTORS PROFIT @10% : 24.26
ADD FOR OVER HEAD CHARGES @5% : 12.13
LABOUR FOR 10.000 sq.m 278.98
LABOUR PER sq.m 27.90
1203302000 4 mm thick.
Details of cost for 10 sqm.
MATERIAL :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
4mm thick ply wood =10.00 sqm
Add for wastage @ 5% =0.50 sqm
Total = 10.50 sqm.1 sqm. 10.50000 160.00 1680.00
LABOUR :
Carpenter 1st Class each 0.74000 211.16 156.26
Beldar each 0.74000 116.67 86.34
TOTAL : 1987.59
ADD FOR CONTRACTORS PROFIT 10% 198.76
ADD FOR OVER HEAD CHARGES @5% 99.38
COST FOR 10.00 sq.m 2285.73
COST PER sq.m 228.60
LABOUR PER sq.m 27.90
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 242.59
TOTAL : 242.59
ADD FOR CONTRACTORS PROFIT @10% : 24.26
ADD FOR OVER HEAD CHARGES @5% : 12.13
LABOUR FOR 10.000 sq.m 278.98
LABOUR PER sq.m 27.90
1203302000 6 mm thick.
Details of cost for 10 sqm.
MATERIAL :
LABOUR :
Carpenter 1st Class each 0.74000 211.16 156.26
Beldar each 0.74000 116.67 86.34
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 2932.59
ADD FOR CONTRACTORS PROFIT 10% 293.26
ADD FOR OVER HEAD CHARGES @5% 146.63
COST FOR 10.00 sq.m 3372.48
COST PER sq.m 337.25
LABOUR PER sq.m 27.90
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 242.59
TOTAL : 242.59
ADD FOR CONTRACTORS PROFIT @10% : 24.26
ADD FOR OVER HEAD CHARGES @5% : 12.13
LABOUR FOR 10.000 sq.m 278.98
LABOUR PER sq.m 27.90
MATERIAL :
LABOUR :
Carpenter 1st Class each 0.74000 211.16 156.26
Beldar each 0.74000 116.67 86.34
TOTAL : 2617.59
ADD FOR CONTRACTORS PROFIT 10% 261.76
ADD FOR OVER HEAD CHARGES @5% 130.88
COST FOR 10.00 sq.m 3010.23
COST PER sq.m 301.00
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR PER sq.m 27.90
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 242.59
TOTAL : 242.59
ADD FOR CONTRACTORS PROFIT @10% : 24.26
ADD FOR OVER HEAD CHARGES @5% : 12.13
LABOUR FOR 10.000 sq.m 278.98
LABOUR PER sq.m 27.90
1203501000 3 mm thick
Details of cost for 10 sqm.
MATERIAL :
LABOUR :
Carpenter 1st Class each 0.54000 211.16 114.03
Beldar each 0.13000 116.67 15.17
Sacffolding L.S 25.00
SUNDRIES : L.S 10.00
TOTAL : 1569.19
ADD FOR CONTRACTORS PROFIT 10% 156.92
ADD FOR OVER HEAD CHARGES @5% 78.46
COST FOR 10.00 sq.m 1804.57
COST PER sq.m 180.45
LABOUR PER sq.m 18.90
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 164.19
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 164.19
ADD FOR CONTRACTORS PROFIT @10% : 16.42
ADD FOR OVER HEAD CHARGES @5% : 8.21
LABOUR FOR 10.000 sq.m 188.82
LABOUR PER sq.m 18.90
1203502000 4 mm thick
Details of cost for 10 sqm.
MATERIAL :
LABOUR :
Carpenter 1st Class each 0.54000 211.16 114.03
Beldar each 0.13000 116.67 15.17
Sacffolding L.S 25.00
SUNDRIES : L.S 10.00
TOTAL : 1884.19
ADD FOR CONTRACTORS PROFIT 10% 188.42
ADD FOR OVER HEAD CHARGES @5% 94.21
COST FOR 10.00 sq.m 2166.82
COST PER sq.m 216.70
LABOUR PER sq.m 18.90
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 164.19
TOTAL : 164.19
ADD FOR CONTRACTORS PROFIT @10% : 16.42
ADD FOR OVER HEAD CHARGES @5% : 8.21
LABOUR FOR 10.000 sq.m 188.82
LABOUR PER sq.m 18.88 say 18.90
1203503000 6 mm thick
Details of cost for 10 sqm.
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
LABOUR :
Carpenter 1st Class each 0.54000 211.16 114.03
Beldar each 0.13000 116.67 15.17
Sacffolding L.S 25.00
SUNDRIES : L.S 10.00
TOTAL : 2829.19
ADD FOR CONTRACTORS PROFIT 10% 282.92
ADD FOR OVER HEAD CHARGES @5% 141.46
COST FOR 10.00 sq.m 3253.57
COST PER sq.m 325.35
LABOUR PER sq.m 18.90
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 164.19
TOTAL : 164.19
ADD FOR CONTRACTORS PROFIT @10% : 16.42
ADD FOR OVER HEAD CHARGES @5% : 8.21
LABOUR FOR 10.000 sq.m 188.82
LABOUR PER sq.m 18.90
MATERIAL :
LABOUR :
Carpenter 1st Class each 0.37000 211.16 78.13
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 103.13
ADD FOR CONTRACTORS PROFIT 10% 10.31
ADD FOR OVER HEAD CHARGES @5% 5.16
COST FOR 10.00 sq.m 118.60
COST PER sq.m 11.85
LABOUR PER sq.m 9.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 78.13
TOTAL : 78.13
ADD FOR CONTRACTORS PROFIT @10% : 7.81
ADD FOR OVER HEAD CHARGES @5% : 3.91
LABOUR FOR 10.000 sq.m 89.85
LABOUR PER sq.m 9.00
MATERIAL :
LABOUR :
Carpenter 1st Class each 0.37000 211.16 78.13
TOTAL : 128.13
ADD FOR CONTRACTORS PROFIT 10% 12.81
ADD FOR OVER HEAD CHARGES @5% 6.41
COST FOR 10.00 sq.m 147.35
COST PER sq.m 14.70
LABOUR PER sq.m 9.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 78.13
TOTAL : 78.13
ADD FOR CONTRACTORS PROFIT @10% : 7.81
ADD FOR OVER HEAD CHARGES @5% : 3.91
LABOUR FOR 10.000 sq.m 89.85
LABOUR PER sq.m 9.00
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
1203801000 4 mm thick.
Details of cost for 10 sqm.
MATERIAL :
LABOUR :
Carpenter 1st Class each 0.80000 211.16 168.93
Beldar each 0.80000 116.67 93.34
Sacffolding L.S 7.00
SUNDRIES : L.S 5.00
TOTAL : 1882.26
ADD FOR CONTRACTORS PROFIT 10% 188.23
ADD FOR OVER HEAD CHARGES @5% 94.11
COST FOR 10.00 sq.m 2164.60
COST PER sq.m 216.45
LABOUR PER sq.m 31.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 274.26
TOTAL : 274.26
ADD FOR CONTRACTORS PROFIT @10% : 27.43
ADD FOR OVER HEAD CHARGES @5% : 13.71
LABOUR FOR 10.000 sq.m 315.40
LABOUR PER sq.m 31.50
1203802000 5 mm thick.
Details of cost for 10 sqm.
MATERIAL :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
5mm thick plain asbestos sheet=10.00 sqm
Add for wastage @ 10% =1.00 sqm
Total = 11.00 sqm.1 sqm. 11.00 150.00 1650.00
Screws 20mm 100 nos. 240.00 20.00 48.00
CARRIAGE :
carriage of asbestos sheet L.S. 20.00
LABOUR :
Carpenter 1st Class each 0.80000 211.16 168.93
Beldar each 0.80000 116.67 93.34
Sacffolding L.S 7.00
SUNDRIES : L.S 5.00
TOTAL : 1992.26
ADD FOR CONTRACTORS PROFIT 10% 199.23
ADD FOR OVER HEAD CHARGES @5% 99.61
COST FOR 10.00 sq.m 2291.10
COST PER sq.m 229.10
LABOUR PER sq.m 31.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 274.26
TOTAL : 274.26
ADD FOR CONTRACTORS PROFIT @10% : 27.43
ADD FOR OVER HEAD CHARGES @5% : 13.71
LABOUR FOR 10.000 sq.m 315.40
LABOUR PER sq.m 31.50
1203901000 4 mm thick
Details of cost for 10 sqm.
MATERIAL :
Asbestos cement sheets 5mm th=10.00 sqm
Add for wastage @ 10% =1.00 sqm
Total = 11.00 sqm.1 sqm. 11.00000 140.00 1540.00
Wood Screws 20mm 100 nos. 260.000 20.00 52.00
CARRIAGE :
Steel, C.G.I. & Asbestos sheets.
1 KM BY MECH. TRANSPORT 1 tonne 0.08800 73.95 6.51
1 KM BY MECH. TRANSPORT 1 tonne 0.08800 57.85 5.09
LABOUR :
Carpenter 1st Class each 0.72000 211.16 152.04
Beldar each 0.36000 116.67 42.00
Sacffolding L.S 25.00
SUNDRIES : L.S 10.00
TOTAL : 1832.63
ADD FOR CONTRACTORS PROFIT 10% 183.26
ADD FOR OVER HEAD CHARGES @5% 91.63
COST FOR 10.00 sq.m 2107.53
COST PER sq.m 210.75
LABOUR PER sq.m 26.35
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 229.04
TOTAL : 229.04
ADD FOR CONTRACTORS PROFIT @10% : 22.90
ADD FOR OVER HEAD CHARGES @5% : 11.45
LABOUR FOR 10.000 sq.m 263.39
LABOUR PER sq.m 26.35
1203902000 5 mm thick
Details of cost for 10 sqm.
MATERIAL :
Asbestos cement sheets 5mm th=10.00 sqm
Add for wastage @ 5% =1.00 sqm
Total = 11.00 sqm.1 sqm. 11.00000 150.00 1650.00
Wood Screws 20mm 100 nos. 260.000 20.00 52.00
CARRIAGE :
LABOUR :
Carpenter 1st Class each 0.72000 211.16 152.04
Beldar each 0.36000 116.67 42.00
Sacffolding L.S 25.00
SUNDRIES : L.S 10.00
TOTAL : 1945.53
ADD FOR CONTRACTORS PROFIT 10% 194.55
ADD FOR OVER HEAD CHARGES @5% 97.28
COST FOR 10.00 sq.m 2237.36
COST PER sq.m 223.75
LABOUR PER sq.m 26.35
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 229.04
TOTAL : 229.04
ADD FOR CONTRACTORS PROFIT @10% : 22.90
ADD FOR OVER HEAD CHARGES @5% : 11.45
LABOUR FOR 10.000 sq.m 263.39
LABOUR PER sq.m 26.35
1203903000 6 mm thick
Details of cost for 10 sqm.
MATERIAL :
CARRIAGE :
LABOUR :
Carpenter 1st Class each 0.72000 211.16 152.04
Beldar each 0.36000 116.67 42.00
Sacffolding L.S 25.00
SUNDRIES : L.S 10.00
TOTAL : 2663.43
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR CONTRACTORS PROFIT 10% 266.34
ADD FOR OVER HEAD CHARGES @5% 133.17
COST FOR 10.00 sq.m 3062.95
COST PER sq.m 306.30
LABOUR PER sq.m 26.35
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 229.04
TOTAL : 229.04
ADD FOR CONTRACTORS PROFIT @10% : 22.90
ADD FOR OVER HEAD CHARGES @5% : 11.45
LABOUR FOR 10.000 sq.m 263.39
LABOUR PER sq.m 26.35
1204001010 12 mm thick
Details of cost for 10 sqm.
MATERIAL :
CARRIAGE :
LABOUR :
Carpenter 1st Class each 2.48000 211.16 523.68
Carpenter 2nd Class each 2.48000 186.67 462.94
Beldar each 3.30000 116.67 385.01
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1426.63
TOTAL : 1426.63
ADD FOR CONTRACTORS PROFIT @10% : 142.66
ADD FOR OVER HEAD CHARGES @5% : 71.33
LABOUR FOR 10.000 sq.m 1640.62
LABOUR PER sq.m 164.05
1204001020 20 mm thick
Details of cost for 10 sqm.
MATERIAL :
CARRIAGE :
LABOUR :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Carpenter 1st Class each 2.48000 211.16 523.68
Carpenter 2nd Class each 2.48000 186.67 462.94
Beldar each 3.30000 116.67 385.01
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1426.63
TOTAL : 1426.63
ADD FOR CONTRACTORS PROFIT @10% : 142.66
ADD FOR OVER HEAD CHARGES @5% : 71.33
LABOUR FOR 10.000 sq.m 1640.62
LABOUR PER sq.m 164.05
1204001030 25 mm thick
Details of cost for 10 sqm.
MATERIAL :
CARRIAGE :
LABOUR :
Carpenter 1st Class each 2.48000 211.16 523.68
Carpenter 2nd Class each 2.48000 186.67 462.94
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Beldar each 3.30000 116.67 385.01
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1426.63
TOTAL : 1426.63
ADD FOR CONTRACTORS PROFIT @10% : 142.66
ADD FOR OVER HEAD CHARGES @5% : 71.33
LABOUR FOR 10.000 sq.m 1640.62
LABOUR PER sq.m 164.05
1204002010 12 mm thick.
Details of cost for 10 sqm.
MATERIAL :
CARRIAGE :
LABOUR :
Carpenter 1st Class each 1.65000 211.16 348.41
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Carpenter 2nd Class each 1.65000 186.67 308.01
Beldar each 2.20000 116.67 256.67
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 968.09
TOTAL : 968.09
ADD FOR CONTRACTORS PROFIT @10% : 96.81
ADD FOR OVER HEAD CHARGES @5% : 48.40
LABOUR FOR 10.000 sq.m 1113.31
LABOUR PER sq.m 111.30
1204002020 20 mm thick
Details of cost for 10 sqm.
MATERIAL :
CARRIAGE :
LABOUR :
Carpenter 1st Class each 1.65000 211.16 348.41
Carpenter 2nd Class each 1.65000 186.67 308.01
Beldar each 2.20000 116.67 256.67
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 968.09
TOTAL : 968.09
ADD FOR CONTRACTORS PROFIT @10% : 96.81
ADD FOR OVER HEAD CHARGES @5% : 48.40
LABOUR FOR 10.000 sq.m 1113.31
LABOUR PER sq.m 111.30
1204002030 25 mm thick
Details of cost for 10 sqm.
MATERIAL :
CARRIAGE :
LABOUR :
Carpenter 1st Class each 1.65000 211.16 348.41
Carpenter 2nd Class each 1.65000 186.67 308.01
Beldar each 2.20000 116.67 256.67
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Scaffolding L.S 35.00
SUNDRIES : L.S 20.00
TOTAL : 15960.07
ADD FOR CONTRACTORS PROFIT 10% 1596.01
ADD FOR OVER HEAD CHARGES @5% 798.00
COST FOR 10.00 sq.m 18354.08
COST PER sq.m 1835.40
LABOUR PER sq.m 111.30
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 968.09
TOTAL : 968.09
ADD FOR CONTRACTORS PROFIT @10% : 96.81
ADD FOR OVER HEAD CHARGES @5% : 48.40
LABOUR FOR 10.000 sq.m 1113.31
LABOUR PER sq.m 111.30
1204003010 12 mm thick
Details of cost for 10 sqm.
MATERIAL :
CARRIAGE :
LABOUR :
Carpenter 1st Class each 1.65000 211.16 348.41
Carpenter 2nd Class each 1.65000 186.67 308.01
Beldar each 2.20000 116.67 256.67
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 968.09
TOTAL : 968.09
ADD FOR CONTRACTORS PROFIT @10% : 96.81
ADD FOR OVER HEAD CHARGES @5% : 48.40
LABOUR FOR 10.000 sq.m 1113.31
LABOUR PER sq.m 111.30
1204003020 20 mm thick
Details of cost for 10 sqm.
MATERIAL :
CARRIAGE :
LABOUR :
Carpenter 1st Class each 1.65000 211.16 348.41
Carpenter 2nd Class each 1.65000 186.67 308.01
Beldar each 2.20000 116.67 256.67
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 968.09
TOTAL : 968.09
ADD FOR CONTRACTORS PROFIT @10% : 96.81
ADD FOR OVER HEAD CHARGES @5% : 48.40
LABOUR FOR 10.000 sq.m 1113.31
LABOUR PER sq.m 111.30
1204003030 25 mm thick
Details of cost for 10 sqm.
MATERIAL :
CARRIAGE :
LABOUR :
Carpenter 1st Class each 1.65000 211.16 348.41
Carpenter 2nd Class each 1.65000 186.67 308.01
Beldar each 2.20000 116.67 256.67
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 968.09
TOTAL : 968.09
ADD FOR CONTRACTORS PROFIT @10% : 96.81
ADD FOR OVER HEAD CHARGES @5% : 48.40
LABOUR FOR 10.000 sq.m 1113.31
LABOUR PER sq.m 111.30
LABOUR :
TOTAL : 196.70
ADD FOR CONTRACTORS PROFIT 10% 19.67
ADD FOR OVER HEAD CHARGES @5% 9.83
COST FOR 10.00 sq.m 226.20
COST PER sq.m 22.60
LABOUR PER sq.m 22.60
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 196.70
TOTAL : 196.70
ADD FOR CONTRACTORS PROFIT @10% : 19.67
ADD FOR OVER HEAD CHARGES @5% : 9.83
LABOUR FOR 10.000 sq.m 226.20
LABOUR PER sq.m 22.60
1204101010 12 mm thick
Details of cost for 10 sqm.
MATERIAL :
CARRIAGE :
LABOUR :
Carpenter 1st Class each 1.15000 211.16 242.83
Carpenter 2nd Class each 1.15000 186.67 214.67
Beldar each 1.55000 116.67 180.84
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 693.34
TOTAL : 693.34
ADD FOR CONTRACTORS PROFIT @10% : 69.33
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR OVER HEAD CHARGES @5% : 34.67
LABOUR FOR 10.000 sq.m 797.34
LABOUR PER sq.m 79.70
1204101020 20 mm thick
Details of cost for 10 sqm.
MATERIAL :
CARRIAGE :
LABOUR :
Carpenter 1st Class each 1.15000 211.16 242.83
Carpenter 2nd Class each 1.15000 186.67 214.67
Beldar each 1.55000 116.67 180.84
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 693.34
TOTAL : 693.34
ADD FOR CONTRACTORS PROFIT @10% : 69.33
ADD FOR OVER HEAD CHARGES @5% : 34.67
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR FOR 10.000 sq.m 797.34
LABOUR PER sq.m 79.70
1204101030 25 mm thick
Details of cost for 10 sqm.
MATERIAL :
CARRIAGE :
LABOUR :
Carpenter 1st Class each 1.15000 211.16 242.83
Carpenter 2nd Class each 1.15000 186.67 214.67
Beldar each 1.55000 116.67 180.84
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 693.34
TOTAL : 693.34
ADD FOR CONTRACTORS PROFIT @10% : 69.33
ADD FOR OVER HEAD CHARGES @5% : 34.67
LABOUR FOR 10.000 sq.m 797.34
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR PER sq.m 79.70
1204102010 12 mm thick
Details of cost for 10 sqm.
MATERIAL :
CARRIAGE :
LABOUR :
Carpenter 1st Class each 1.15000 211.16 242.83
Carpenter 2nd Class each 1.15000 186.67 214.67
Beldar each 1.55000 116.67 180.84
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 693.34
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 693.34
ADD FOR CONTRACTORS PROFIT @10% : 69.33
ADD FOR OVER HEAD CHARGES @5% : 34.67
LABOUR FOR 10.000 sq.m 797.34
LABOUR PER sq.m 79.70
1204102020 20 mm thick
Details of cost for 10 sqm.
MATERIAL :
CARRIAGE :
LABOUR :
Carpenter 1st Class each 1.15000 211.16 242.83
Carpenter 2nd Class each 1.15000 186.67 214.67
Beldar each 1.55000 116.67 180.84
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 693.34
TOTAL : 693.34
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR CONTRACTORS PROFIT @10% : 69.33
ADD FOR OVER HEAD CHARGES @5% : 34.67
LABOUR FOR 10.000 sq.m 797.34
LABOUR PER sq.m 79.70
1204102030 25 mm thick
Details of cost for 10 sqm.
MATERIAL :
CARRIAGE :
LABOUR :
Carpenter 1st Class each 1.15000 211.16 242.83
Carpenter 2nd Class each 1.15000 186.67 214.67
Beldar each 1.55000 116.67 180.84
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 693.34
TOTAL : 693.34
ADD FOR CONTRACTORS PROFIT @10% : 69.33
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR OVER HEAD CHARGES @5% : 34.67
LABOUR FOR 10.000 sq.m 797.34
LABOUR PER sq.m 79.70
LABOUR :
Carpenter 1st Class each 1.00000 211.16 211.16
Carpenter 2nd Class each 1.00000 186.67 186.67
Beldar each 2.00000 116.67 233.34
TOTAL : 631.17
ADD FOR CONTRACTORS PROFIT 10% 63.12
ADD FOR OVER HEAD CHARGES @5% 31.56
COST FOR 10.00 sq.m 725.85
COST PER sq.m 72.60
LABOUR PER sq.m 72.60
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 631.17
TOTAL : 631.17
ADD FOR CONTRACTORS PROFIT @10% : 63.12
ADD FOR OVER HEAD CHARGES @5% : 31.56
LABOUR FOR 10.000 sq.m 725.85
LABOUR PER sq.m 72.60
1204301010 12 mm thick
Details of cost for 10 holes of
0.75m.dia each i.e.
10x22/7x(.75)2=23.57mtr.say23.60mtrs.
MATERIAL :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
First class indian teak wood.
Area (10x22 (0.75) 2) =4.43 sqm
----------------------------------------
7x4
(Rate same as per item no. 1204001010)
1 sqm 4.43000 1668.00 7389.24 (-I-)
LABOUR :
Carpenter 1st Class each 3.75000 211.16 791.85
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1234.36
Labour as per item no. 1204001010 726.74 (-a-)
TOTAL : 1961.10
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-): 123.43
ADD FOR OVER HEAD CHARGES @5% Except on (-a-): 61.71
LABOUR FOR 23.600 Metre 2146.24
LABOUR PER Metre 90.90
1204301020 20 mm thick
Details of cost for 10 holes of
0.75 metres diametre each i.e
10x22/7x0.75=23.57(say)23.60mtrs.
MATERIAL :
LABOUR :
Carpenter 1st Class each 3.75000 211.16 791.85
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Beldar each 3.75000 116.67 437.51
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1234.36
Labour as per item no. 1204001010 726.74 (-a-)
TOTAL : 1961.10
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-): 123.43
ADD FOR OVER HEAD CHARGES @5% Except on (-a-): 61.71
LABOUR FOR 23.600 Metre 2146.24
LABOUR PER Metre 90.90
1204301030 25 mm thick
Details of cost for 10 holes of
0.75 metres diametre each i.e
10x22/7x0.75=23.57(say)23.60mtrs.
MATERIAL :
LABOUR :
Carpenter 1st Class each 3.75000 211.16 791.85
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1234.36
Labour as per item no. 1204001010 726.74 (-a-)
TOTAL : 1961.10
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-): 123.43
ADD FOR OVER HEAD CHARGES @5% Except on (-a-): 61.71
LABOUR FOR 23.600 Metre 2146.24
LABOUR PER Metre 90.90
1204302010 12 mm thick.
Details of cost for 10 holes of
0.75m.diametre each i.e.
10x22/7x0.75m=23.57mtrs or23.60mtr
MATERIAL :
LABOUR :
Carpenter 1st Class each 2.50000 211.16 527.90
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 824.58
Labour as per item no. 1204001010 493.05 (-a-)
TOTAL : 1317.62
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-): 82.45
ADD FOR OVER HEAD CHARGES @5% Except on (-a-): 41.22
LABOUR FOR 23.600 Metre 1441.29
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR PER Metre 61.05
1204302020 20 mm thick
Details of cost for 10 holes of
0.75m diametre each
i.e.(10x22x0.75)=23.57 meters
________________
7 say 23.60 meters
MATERIAL :
LABOUR :
Carpenter 1st Class each 2.50000 211.16 527.90
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 824.58
Labour as per item no. 1204002020 493.05 (-a-)
TOTAL : 1317.62
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-): 82.45
ADD FOR OVER HEAD CHARGES @5% Except on (-a-): 41.22
LABOUR FOR 23.600 Metre 1441.29
LABOUR PER Metre 61.05
1204302030 25 mm thick
Details of cost for 10 holes of
0.75m diametre each
i.e.(10x22x0.75)=23.57 meters
________________
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
7 say 23.60 meters
MATERIAL :
LABOUR :
Carpenter 1st Class each 2.50000 211.16 527.90
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 824.58
Labour as per item no. 1204002030 493.05 (-a-)
TOTAL : 1317.62
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-): 82.45
ADD FOR OVER HEAD CHARGES @5% Except on (-a-): 41.22
LABOUR FOR 23.600 Metre 1441.29
LABOUR PER Metre 61.05
1204303010 12 mm thick
Details of cost for 10 holes of
0.75m diametre each
i.e.(10x22x0.75)=23.57 meters
________________
7 say 23.60 meters
MATERIAL :
LABOUR :
Carpenter 1st Class each 2.50000 211.16 527.90
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 824.58
Labour as per item no. 1204003010 493.05 (-a-)
TOTAL : 1317.62
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-): 82.45
ADD FOR OVER HEAD CHARGES @5% Except on (-a-): 41.22
LABOUR FOR 23.600 Metre 1441.29
LABOUR PER Metre 61.05
1204303020 20 mm thick
Details of cost for 10 holes of
0.75m diametre each
i.e.(10x22x0.75)=23.57 meters
________________
7 say 23.60 meters
MATERIAL :
LABOUR :
Carpenter 1st Class each 2.50000 211.16 527.90
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 824.58
Labour as per item no. 1204003020 493.05 (-a-)
TOTAL : 1317.62
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-): 82.45
ADD FOR OVER HEAD CHARGES @5% Except on (-a-): 41.22
LABOUR FOR 23.600 Metre 1441.29
LABOUR PER Metre 61.05
1204303030 25 mm thick
Details of cost for 10 holes of
0.75m diametre each
i.e.(10x22x0.75)=23.57 meters
________________
7 say 23.60 meters
MATERIAL :
LABOUR :
Carpenter 1st Class each 2.50000 211.16 527.90
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 824.58
Labour as per item no. 1204001010 493.05 (-a-)
TOTAL : 1317.62
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-): 82.45
ADD FOR OVER HEAD CHARGES @5% Except on (-a-): 41.22
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR FOR 23.600 Metre 1441.29
LABOUR PER Metre 61.05
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 CUM 0.02800 110.95 3.11
LABOUR :
Carpenter 1st Class each 0.74000 211.16 156.26
Carpenter 2nd Class each 0.99000 186.67 184.80
Beldar each 1.47000 116.67 171.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 537.57
TOTAL : 537.57
ADD FOR CONTRACTORS PROFIT @10%: 53.76
ADD FOR OVER HEAD CHARGES @5% : 26.88
LABOUR FOR 10 R/Metre 618.20
LABOUR PER R/Metre 61.80
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
1204402000 2nd class indian teak wood.
Details of cost for 10 Metres.
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 CUM 0.02800 110.95 3.11
LABOUR :
Carpenter 1st Class each 0.74000 211.16 156.26
Carpenter 2nd Class each 0.99000 186.67 184.80
Beldar each 1.47000 116.67 171.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 537.57
TOTAL : 537.57
ADD FOR CONTRACTORS PROFIT @10% : 53.76
ADD FOR OVER HEAD CHARGES @5% ; 26.88
LABOUR FOR 10 R/Metre 618.20
LABOUR PER R/Metre 61.80
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 CUM 0.02800 110.95 3.11
LABOUR :
Carpenter 1st Class each 0.49000 211.16 103.47
Carpenter 2nd Class each 0.66000 186.67 123.20
Beldar each 0.98000 116.67 114.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 361.01
TOTAL : 361.01
ADD FOR CONTRACTORS PROFIT @10% : 36.10
ADD FOR OVER HEAD CHARGES @5% : 18.05
LABOUR FOR 10 R/Metre 415.16
LABOUR PER R/Metre 41.50
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 CUM 0.02800 110.95 3.11
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR :
Carpenter 1st Class each 0.49000 211.16 103.47
Carpenter 2nd Class each 0.66000 186.67 123.20
Beldar each 0.98000 116.67 114.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 361.01
TOTAL : 361.01
ADD FOR CONTRACTORS PROFIT @10% : 36.10
ADD FOR OVER HEAD CHARGES @5% : 18.05
LABOUR FOR 10 R/Metre 415.16
LABOUR PER R/Metre 41.50
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 CUM 0.05500 110.95 6.10
LABOUR :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Carpenter 1st Class each 0.99000 211.16 209.05
Carpenter 2nd Class each 0.99000 186.67 184.80
Beldar each 1.47000 116.67 171.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 595.36
TOTAL : 595.36
ADD FOR CONTRACTORS PROFIT @10% : 59.54
ADD FOR OVER HEAD CHARGES @5% : 29.77
LABOUR FOR 10 R/Metre 684.66
LABOUR PER R/Metre 68.45
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 CUM 0.05500 110.95 6.10
LABOUR :
Carpenter 1st Class each 0.99000 211.16 209.05
Carpenter 2nd Class each 0.99000 186.67 184.80
Beldar each 1.47000 116.67 171.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 595.36
TOTAL : 595.36
ADD FOR CONTRACTORS PROFIT @10% : 59.54
ADD FOR OVER HEAD CHARGES @5% : 29.77
LABOUR FOR 10 R/Metre 684.66
LABOUR PER R/Metre 68.45
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 CUM 0.05500 110.95 6.10
LABOUR :
Carpenter 1st Class each 0.66000 211.16 139.37
Carpenter 2nd Class each 0.66000 186.67 123.20
Beldar each 0.98000 116.67 114.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 396.90
TOTAL : 396.90
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR CONTRACTORS PROFIT @10% : 39.69
ADD FOR OVER HEAD CHARGES @5% : 19.85
LABOUR FOR 10 R/Metre 456.44
LABOUR PER R/Metre 45.65
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 CUM 0.05500 110.95 6.10
LABOUR :
Carpenter 1st Class each 0.66000 211.16 139.37
Carpenter 2nd Class each 0.66000 186.67 123.20
Beldar each 0.98000 116.67 114.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 396.90
TOTAL : 396.90
ADD FOR CONTRACTORS PROFIT @10% : 39.69
ADD FOR OVER HEAD CHARGES @5% : 19.85
LABOUR FOR 10 R/Metre 456.44
LABOUR PER R/Metre 45.65
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 CUM 0.02800 110.95 3.11
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 360.11
TOTAL : 360.11
ADD FOR CONTRACTORS PROFIT @10% : 36.01
ADD FOR OVER HEAD CHARGES @5% : 18.01
LABOUR FOR 10 R/Metre 414.12
LABOUR PER R/Metre 41.40
MATERIAL :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 CUM 0.02800 110.95 3.11
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 360.11
TOTAL : 360.11
ADD FOR CONTRACTORS PROFIT @10% : 36.01
ADD FOR OVER HEAD CHARGES @5% : 18.01
LABOUR FOR 10 R/Metre 414.12
LABOUR PER R/Metre 41.40
MATERIAL :
CARRIAGE :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Timber.
1 KM BY MECH. TRANSPORT 1 CUM 0.02800 110.95 3.11
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 240.07
TOTAL : 240.07
ADD FOR CONTRACTORS PROFIT @10% : 24.01
ADD FOR OVER HEAD CHARGES @5% : 12.00
LABOUR FOR 10 R/Metre 276.08
LABOUR PER R/Metre 27.60
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 CUM 0.02800 110.95 3.11
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 240.07
TOTAL : 240.07
ADD FOR CONTRACTORS PROFIT @10% : 24.01
ADD FOR OVER HEAD CHARGES @5% : 12.00
LABOUR FOR 10 R/Metre 276.08
LABOUR PER R/Metre 27.60
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 CUM 0.05300 110.95 5.88
LABOUR :
Carpenter 1st Class each 2.50000 211.16 527.90
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Carpenter 2nd Class each 2.50000 186.67 466.68
Beldar each 5.00000 116.67 583.35
scaffolding L.S. 7.00
SUNDRIES : L.S. 5.00
TOTAL : 7220.85
ADD FOR CONTRACTORS PROFIT 10% : 722.09
ADD FOR OVER HEAD CHARGES @5% : 361.04
COST FOR 100.00 Metre 8303.98
COST PER Metre 83.00
LABOUR PER Metre 18.30
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1589.93
TOTAL : 1589.93
ADD FOR CONTRACTORS PROFIT @10% : 158.99
ADD FOR OVER HEAD CHARGES @5% : 79.50
LABOUR FOR 100 Metre 1828.41
LABOUR PER Metre 18.30
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 CUM 0.05300 110.95 5.88
LABOUR :
Carpenter 1st Class each 1.68000 211.16 354.75
Carpenter 2nd Class each 1.68000 186.67 313.61
Beldar each 3.33000 116.67 388.51
scaffolding L.S. 7.00
SUNDRIES : L.S. 5.00
TOTAL : 4335.73
ADD FOR CONTRACTORS PROFIT 10% : 433.57
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR OVER HEAD CHARGES @5% : 216.79
COST FOR 100.00 Metre 4986.09
COST PER Metre 49.85
LABOUR PER Metre 12.30
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1068.87
TOTAL : 1068.87
ADD FOR CONTRACTORS PROFIT @10% : 106.89
ADD FOR OVER HEAD CHARGES @5% : 53.44
LABOUR FOR 100 Metre 1229.20
LABOUR PER Metre 12.30
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 CUM 0.05300 110.95 5.88
LABOUR :
Carpenter 1st Class each 1.68000 211.16 354.75
Carpenter 2nd Class each 1.68000 186.67 313.61
Beldar each 3.33000 116.67 388.51
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1068.87
TOTAL : 1068.87
ADD FOR CONTRACTORS PROFIT @10% : 106.89
ADD FOR OVER HEAD CHARGES @5% : 53.44
LABOUR FOR 100 Metre 1229.20
LABOUR PER Metre 12.30
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 CUM 0.06600 110.95 7.32
LABOUR :
Carpenter 1st Class each 2.50000 211.16 527.90
Carpenter 2nd Class each 2.50000 186.67 466.68
Beldar each 5.00000 116.67 583.35
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1589.93
TOTAL : 1589.93
ADD FOR CONTRACTORS PROFIT @10% : 158.99
ADD FOR OVER HEAD CHARGES @5% : 79.50
LABOUR FOR 100 Metre 1828.41
LABOUR PER Metre 18.30
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 CUM 0.06600 110.95 7.32
LABOUR :
Carpenter 1st Class each 1.68000 211.16 354.75
Carpenter 2nd Class each 1.68000 186.67 313.61
Beldar each 3.33000 116.67 388.51
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 CUM 0.06600 110.95 7.32
LABOUR :
Carpenter 1st Class each 1.68000 211.16 354.75
Carpenter 2nd Class each 1.68000 186.67 313.61
Beldar each 3.33000 116.67 388.51
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1068.87
TOTAL : 1068.87
ADD FOR CONTRACTORS PROFIT @10% : 106.89
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR OVER HEAD CHARGES @5% : 53.44
LABOUR FOR 100 Metre 1229.20
LABOUR PER Metre 12.30
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 CUM 0.07900 110.95 8.77
LABOUR :
Carpenter 1st Class each 2.50000 211.16 527.90
Carpenter 2nd Class each 2.50000 186.67 466.68
Beldar each 5.00000 116.67 583.35
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1589.93
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 1589.93
ADD FOR CONTRACTORS PROFIT @10% : 158.99
ADD FOR OVER HEAD CHARGES @5% : 79.50
LABOUR FOR 100 Metre 1828.41
LABOUR PER Metre 18.30
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 CUM 0.07900 110.95 8.77
LABOUR :
Carpenter 1st Class each 1.68000 211.16 354.75
Carpenter 2nd Class each 1.68000 186.67 313.61
Beldar each 3.33000 116.67 388.51
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1068.87
TOTAL : 1068.87
ADD FOR CONTRACTORS PROFIT @10% : 106.89
ADD FOR OVER HEAD CHARGES @5% : 53.44
LABOUR FOR 100 Metre 1229.20
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR PER Metre 12.30
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 CUM 0.07900 110.95 8.77
LABOUR :
Carpenter 1st Class each 1.68000 211.16 354.75
Carpenter 2nd Class each 1.68000 186.67 313.61
Beldar each 3.33000 116.67 388.51
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1068.87
TOTAL : 1068.87
ADD FOR CONTRACTORS PROFIT @10% : 106.89
ADD FOR OVER HEAD CHARGES @5% : 53.44
LABOUR FOR 100 Metre 1229.20
LABOUR PER Metre 12.30
LABOUR :
TOTAL : 527.90
ADD FOR CONTRACTORS PROFIT 10% : 52.79
ADD FOR OVER HEAD CHARGES @5% : 26.40
COST FOR 100.00 Metre 607.09
COST PER Metre 6.10
LABOUR PER Metre 6.10
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 527.90
TOTAL : 527.90
ADD FOR CONTRACTORS PROFIT @10% : 52.79
ADD FOR OVER HEAD CHARGES @5% : 26.40
LABOUR FOR 100 Metre 607.09
LABOUR PER Metre 6.10
MATERIAL :
CARRIAGE :
carriage for A.C. Sheets 15.00
LABOUR :
Carpenter 1st Class each 2.50000 211.16 527.90
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Carpenter 2nd Class each 2.50000 186.67 466.68
Beldar each 5.00000 116.67 583.35
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1589.93
TOTAL : 1589.93
ADD FOR CONTRACTORS PROFIT @10% : 158.99
ADD FOR OVER HEAD CHARGES @5% : 79.50
LABOUR FOR 100 Metre 1828.41
LABOUR PER Metre 18.30
MATERIAL :
Wooden strips of 1st class kail
wood=72x4.00x0.025x0.006 =0.043 cum
Add. for wastage @ 10% =0.004 cum
Total =0.047 cum1 cum 0.04700 53195.00 2500.16
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 CUM 0.04700 110.95 5.21
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1488.88
TOTAL : 1488.88
ADD FOR CONTRACTORS PROFIT @10% : 148.89
ADD FOR OVER HEAD CHARGES @5% : 74.44
LABOUR FOR 10.00 sq,m 1712.21
LABOUR PER Sqm 171.20
MATERIAL :
Wooden strips of 1st class kail
wood=72x4.00x0.025x0.006 =0.043 cum
Add. for wastage @ 10% =0.004 cum
Total =0.047 cum1 cum 0.04700 53195.00 2500.16
CARRIAGE :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Timber.
1 KM BY MECH. TRANSPORT 1 CUM 0.04700 110.95 5.21
Cement
1 KM BY MECH. TRANSPORT 1 tonne 0.20700 73.95 15.31
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 2150.17
TOTAL : 2150.17
ADD FOR CONTRACTORS PROFIT @10% : 215.02
ADD FOR OVER HEAD CHARGES @5% : 107.51
LABOUR FOR 10.00 sq,m 2472.69
LABOUR PER Sqm 247.25
MATERIAL :
CARRIAGE :
Cement
1 KM BY MECH. TRANSPORT 1 tonne 0.10400 73.95 7.69
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 930.17
TOTAL : 930.17
ADD FOR CONTRACTORS PROFIT @10% : 93.02
ADD FOR OVER HEAD CHARGES @5% : 46.51
LABOUR FOR 10.00 sq,m 1069.69
LABOUR PER Sqm 106.95
LABOUR :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Mason 1st class Each 1.00000 211.16 211.16
Beldar Each 1.00000 116.67 116.67
Bhishti Each 0.25000 116.67 29.17
TOTAL : 364.00
ADD FOR CONTRACTORS PROFIT 10% : 36.40
ADD FOR OVER HEAD CHARGES @5% : 18.20
COST FOR 10.00 Sqm 418.60
COST PERsqm 41.85
LABOUR PER Sqm 41.85
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 364.00
TOTAL : 364.00
ADD FOR CONTRACTORS PROFIT @10% : 36.40
ADD FOR OVER HEAD CHARGES @5% : 18.20
LABOUR FOR 10.00 sq,m 418.60
LABOUR PER Sqm 41.85
MATERIAL :
Plaster of paris:
(4.00x2.5x0.012x1121 =134.52kgs.
Add for wastage @ 20% =26.90kg.
CARRIAGE :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Cement
1 KM BY MECH. TRANSPORT 1 tonne 0.16100 73.95 11.91
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1468.34
TOTAL : 1468.34
ADD FOR CONTRACTORS PROFIT @10% : 146.83
ADD FOR OVER HEAD CHARGES @5% : 73.42
LABOUR FOR 10.00 sq,m 1688.59
LABOUR PER Sqm 168.85
LABOUR :
TOTAL : 168.91
ADD FOR CONTRACTORS PROFIT 10% : 16.89
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR OVER HEAD CHARGES @5% : 8.45
COST FOR 10.00 Sqm 194.25
COST PERsqm 19.40
LABOUR PER Sqm 19.40
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 168.91
TOTAL : 168.91
ADD FOR CONTRACTORS PROFIT @10% : 16.89
ADD FOR OVER HEAD CHARGES @5% : 8.45
LABOUR FOR 10.00 sq,m 194.25
LABOUR PER Sqm 19.40
MATERIAL :
CARRIAGE :
Carriage of cloth L.S. 1.50
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 192.31
TOTAL : 192.31
ADD FOR CONTRACTORS PROFIT @10% : 19.23
ADD FOR OVER HEAD CHARGES @5% : 9.62
LABOUR FOR 10.00 sq,m 221.15
LABOUR PER Sqm 22.10
MATERIAL :
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 192.31
TOTAL : 192.31
ADD FOR CONTRACTORS PROFIT @10% : 19.23
ADD FOR OVER HEAD CHARGES @5% : 9.62
LABOUR FOR 10.00 sq,m 221.15
LABOUR PER Sqm 22.10
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
1205703000 Canvas cloth
Detail of cost for 10 sq.m.
MATERIAL :
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 192.31
TOTAL : 192.31
ADD FOR CONTRACTORS PROFIT @10% : 19.23
ADD FOR OVER HEAD CHARGES @5% : 9.62
LABOUR FOR 10.00 sq,m 221.15
LABOUR PER Sqm 22.10
MATERIAL :
Fittings:
M.S. Flat angle iron clamps 50x6mmx50cm long
including nuts and bolts 1 No. 10.00000 60.00 600.00
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.16200 110.95 17.97
LABOUR :
Carpenter 1st Class each 2.38000 211.16 502.56
Beldar each 0.90000 116.67 105.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 632.56
TOTAL : 632.56
ADD FOR CONTRACTORS PROFIT @10% : 63.26
ADD FOR OVER HEAD CHARGES @5% : 31.63
LABOUR FOR 4.140 sq.m 727.45
LABOUR PER sq.m 175.70
MATERIAL :
Fittings:
M.S. Flat angle iron clamps 50x6mmx50cm long
including nuts and bolts 1 No. 10.00000 60.00 600.00
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.16200 110.95 17.97
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
100 MTRS BY HEAD LOAD 1 cum 0.16200 36.25 5.87
LABOUR :
Carpenter 1st Class each 2.38000 211.16 502.56
Beldar each 0.90000 116.67 105.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 632.56
TOTAL : 632.56
ADD FOR CONTRACTORS PROFIT @10% : 63.26
ADD FOR OVER HEAD CHARGES @5% : 31.63
LABOUR FOR 4.140 sq.m 727.45
LABOUR PER sq.m 175.70
MATERIAL :
Fittings:
M.S. Flat angle iron clamps 50x6mmx50cm long
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
including nuts and bolts 1 No. 10.00000 60.00 600.00
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.16200 110.95 17.97
LABOUR :
Carpenter 1st Class each 2.38000 211.16 502.56
Beldar each 0.90000 116.67 105.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 632.56
TOTAL : 632.56
ADD FOR CONTRACTORS PROFIT @10% : 63.26
ADD FOR OVER HEAD CHARGES @5% : 31.63
LABOUR FOR 4.140 sq.m 727.45
LABOUR PER sq.m 175.70
MATERIAL :
Fittings:
M.S. Flat angle iron clamps 50x6mmx50cm long
including nuts and bolts 1 No. 10.00000 60.00 600.00
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.16200 110.95 17.97
LABOUR :
Carpenter 1st Class each 2.38000 211.16 502.56
Beldar each 0.90000 116.67 105.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 632.56
TOTAL : 632.56
ADD FOR CONTRACTORS PROFIT @10% : 63.26
ADD FOR OVER HEAD CHARGES @5% : 31.63
LABOUR FOR 4.140 sq.m 727.45
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR PER sq.m 175.70
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.01380 110.95 1.53
LABOUR :
Carpenter 2nd Class each 0.75000 186.67 140.00
Mason 2nd class. each 0.75000 158.67 119.00
Beldar each 0.75000 116.67 87.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 366.51
TOTAL : 366.51
ADD FOR CONTRACTORS PROFIT @10% : 36.65
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR OVER HEAD CHARGES @5% : 18.33
LABOUR FOR 100.00 Nos. 421.48
LABOUR PER no. 4.20
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.01380 110.95 1.53
LABOUR :
Carpenter 2nd Class each 0.75000 186.67 140.00
Mason 2nd class. each 0.75000 158.67 119.00
Beldar each 0.75000 116.67 87.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 366.51
TOTAL : 366.51
ADD FOR CONTRACTORS PROFIT @10% : 36.65
ADD FOR OVER HEAD CHARGES @5% : 18.33
LABOUR FOR 100.00 Nos. 421.48
LABOUR PER no. 4.20
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
Priming coat.
Rate as per item No. 16036020. 1 sq.m. 3.00000 20.75 62.25 (-I-)
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.10500 110.95 11.65
LABOUR :
Carpenter 1st Class each 3.40000 211.16 717.94
Mason 2nd class. each 1.82000 186.67 339.74
Beldar each 1.50000 116.67 175.01
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1262.68
Labour as per item no. 1205901000 151.20 (-a-)
Labour as per item no. 16036020 28.80 (-a-)
TOTAL : 1442.68
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-) : 126.28
ADD FOR OVER HEAD CHARGES @5% Except on (-a-) : 63.14
LABOUR FOR 3.00 Sqm 1632.10
LABOUR PER Sqm. 544.00
MATERIAL :
Priming coat.
Rate as per item No. 16036020. 1 sq.m. 3.00000 20.75 62.25 (-I-)
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.10500 110.95 11.65
LABOUR :
Carpenter 1st Class each 3.40000 211.16 717.94
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Mason 2nd class. each 1.82000 186.67 339.74
Beldar each 1.50000 116.67 175.01
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1262.68
Labour as per item no. 1205901000 151.20 (-a-)
Labour as per item no. 16036020 28.80 (-a-)
TOTAL : 1442.68
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-) : 126.28
ADD FOR OVER HEAD CHARGES @5% Except on (-a-) : 63.14
LABOUR FOR 3.00 Sqm 1632.07
LABOUR PER Sqm. 544.00
MATERIAL :
Priming coat.
Rate as per item No. 16036020. 1 sq.m. 3.00000 20.75 62.25 (-I-)
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.10500 110.95 11.65
LABOUR :
Carpenter 1st Class each 2.27000 211.16 479.33
Mason 2nd class. each 1.22000 186.67 227.74
Beldar each 1.00000 116.67 116.67
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 873.73
Labour as per item no. 1205901000 151.20 (-a-)
Labour as per item no. 16036020 28.80 (-a-)
TOTAL : 1053.73
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-) : 87.37
ADD FOR OVER HEAD CHARGES @5% Except on (-a-) : 43.68
LABOUR FOR 3.00 Sqm 1184.78
LABOUR PER Sqm. 394.90
MATERIAL :
Priming coat.
Rate as per item No. 16036020. 1 sq.m. 3.00000 20.75 62.25 (-I-)
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.10500 110.95 11.65
LABOUR :
Carpenter 1st Class each 2.27000 211.16 479.33
Mason 2nd class. each 1.22000 186.67 227.74
Beldar each 1.00000 116.67 116.67
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 873.73
Labour as per item no. 1205901000 151.20 (-a-)
Labour as per item no. 16036020 28.80 (-a-)
TOTAL : 1053.73
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-) : 87.37
ADD FOR OVER HEAD CHARGES @5% Except on (-a-) : 43.68
LABOUR FOR 3.00 Sqm 1184.78
LABOUR PER Sqm. 394.90
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00660 110.95 0.73
LABOUR :
Carpenter 1st Class each 1.00000 211.16 211.16
Beldar each 0.25000 116.67 29.17
Beldar each 0.25000 116.67 29.17
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 284.48
Labour as per item no. 16036020 36.00 (-a-)
TOTAL : 320.48
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-) : 28.44
ADD FOR OVER HEAD CHARGES @5% Except on (-a-) : 14.22
LABOUR FOR 0.0063 cum 363.14
LABOUR PER cum 57641.25
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00660 110.95 0.73
LABOUR :
Carpenter 1st Class each 0.67000 211.16 141.48
Beldar each 0.17000 116.67 19.83
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 176.30
Labour as per item no. 16036020 36.00 (-a-)
TOTAL : 212.30
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-) : 17.63
ADD FOR OVER HEAD CHARGES @5% Except on (-a-) : 8.81
LABOUR FOR 0.0063 cum 238.74
LABOUR PER cum 37895.25
MATERIAL :
Priming coat
Rate as per item No. 16036020 1 sq.m 1.40000 20.75 29.05 (-I-)
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.06160 110.95 6.83
LABOUR :
Carpenter 1st Class each 2.60000 211.16 549.02
Carpenter 2nd Class each 0.12000 186.67 22.40
Beldar each 1.30000 116.67 151.67
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 763.07
Labour as per item no. 1205901000 109.20 (-a-)
Labour as per item no. 16036020 13.44 (-a-)
TOTAL : 885.71
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-) : 76.30
ADD FOR OVER HEAD CHARGES @5% Except on (-a-) : 38.15
LABOUR FOR 1.40 sqm 1000.16
LABOUR PER Sqm 714.40
MATERIAL :
Priming coat
Rate as per item No. 16036020 1 sq.m 1.40000 20.75 29.05 (-I-)
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.06160 110.95 6.83
LABOUR :
Carpenter 1st Class each 1.74000 211.16 367.42
Carpenter 2nd Class each 0.87000 186.67 162.40
Beldar each 0.08000 116.67 9.33
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 579.15
Labour as per item no. 1205901000 109.20 (-a-)
Labour as per item no. 16036020 13.44 (-a-)
TOTAL : 701.79
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-) : 57.91
ADD FOR OVER HEAD CHARGES @5% Except on (-a-) : 28.95
LABOUR FOR 1.40 sqm 788.65
LABOUR PER Sqm 563.30
MATERIAL :
Priming coat
Rate as per item No. 16036020 1 sq.m 1.40000 20.75 29.05 (-I-)
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.03850 110.95 4.27
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR :
Carpenter 1st Class each 2.60000 211.16 549.02
Carpenter 2nd Class each 0.12000 186.67 22.40
Beldar each 1.30000 116.67 151.67
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 763.08
Labour as per item no. 1205901000 109.20 (-a-)
Labour as per item no. 16036020 13.44 (-a-)
TOTAL : 885.72
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-) : 76.30
ADD FOR OVER HEAD CHARGES @5% Except on (-a-) : 38.15
LABOUR FOR 1.40 sqm 1000.17
LABOUR PER Sqm 714.40
MATERIAL :
Priming coat
Rate as per item No. 16036020 1 sq.m 1.40000 20.75 29.05 (-I-)
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.03850 110.95 4.27
LABOUR :
Carpenter 1st Class each 1.74000 211.16 367.42
Carpenter 2nd Class each 0.87000 186.67 162.40
Beldar each 0.08000 116.67 9.33
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 579.14
Labour as per item no. 1205901000 109.20 (-a-)
Labour as per item no. 16036020 13.44 (-a-)
TOTAL : 701.76
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-) : 57.91
ADD FOR OVER HEAD CHARGES @5% Except on (-a-) : 28.95
LABOUR FOR 1.40 sqm 788.64
LABOUR PER Sqm 563.30
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00700 110.95 0.78
LABOUR :
Carpenter 1st Class each 0.25000 211.16 52.79
Carpenter 2nd Class each 0.09000 186.67 16.80
Beldar each 0.25000 116.67 29.17
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 102.75
Labour as per item no. 1205901000 8.40 (-a-)
TOTAL : 111.15
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-) : 10.27
ADD FOR OVER HEAD CHARGES @5% Except on (-a-) : 5.13
LABOUR FOR 2.00 Metre 126.55
LABOUR PER Metre 63.25
MATERIAL :
Front.
1x170x10x1.2 cm = 0.0020 cum.
sides : 2x15x10x1.2cm =0.0004 cum
Top: 1x170x15x1.2 cm =0.0031 cum
Rod: 1x170x22/7x1/4x(2.5x2.5)cm =0.0008 cum
Breckets: 2x7.5x7.5x2.5 cm =0.0003 cum
Total = 0.0066 cum
Add for wastage @ 10% = 0.00066 cum
Total = 0.00726 cum
1 cum 0.00726 79390.00 576.37
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00700 110.95 0.78
LABOUR :
Carpenter 1st Class each 0.25000 211.16 52.79
Carpenter 2nd Class each 0.09000 186.67 16.80
Beldar each 0.25000 116.67 29.17
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 102.75
Labour as per item no. 1205901000 8.40 (-a-)
TOTAL : 111.15
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-) : 10.27
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR OVER HEAD CHARGES @5% Except on (-a-) : 5.13
LABOUR FOR 2.00 Metre 126.55
LABOUR PER Metre 63.25
MATERIAL :
Front.
1x170x10x1.2 cm = 0.0020 cum.
sides : 2x15x10x1.2cm =0.0004 cum
Top: 1x170x15x1.2 cm =0.0031 cum
Rod: 1x170x22/7x1/4x(2.5x2.5)cm =0.0008 cum
Breckets: 2x7.5x7.5x2.5 cm =0.0003 cum
Total = 0.0066 cum
Add for wastage @ 10% = 0.00066 cum
Total = 0.00726 cum
1 cum 0.00726 54020.00 392.19
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00700 110.95 0.78
LABOUR :
Carpenter 1st Class each 0.17000 211.16 35.90
Carpenter 2nd Class each 0.06000 186.67 11.20
Beldar each 0.17000 116.67 19.83
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 70.93
Labour as per item no. 1205901000 8.40 (-a-)
TOTAL : 79.33
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-) : 7.09
ADD FOR OVER HEAD CHARGES @5% Except on (-a-) : 3.55
LABOUR FOR 2.00 Metre 89.97
LABOUR PER Metre 45.00
MATERIAL :
Front.
1x170x10x1.2 cm = 0.0020 cum.
sides : 2x15x10x1.2cm =0.0004 cum
Top: 1x170x15x1.2 cm =0.0031 cum
Rod: 1x170x22/7x1/4x(2.5x2.5)cm =0.0003 cum
Breckets: 2x7.5x7.5x2.5 cm =0.0008 cum
Total = 0.0066 cum
Add for wastage @ 10% = 0.00066 cum
Total = 0.00726 cum
1 cum 0.00726 53195.00 386.20
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00700 110.95 0.78
LABOUR :
Carpenter 1st Class each 0.17000 211.16 35.90
Carpenter 2nd Class each 0.06000 186.67 11.20
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Beldar each 0.17000 116.67 19.83
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 70.93
Labour as per item no. 1205901000 8.40 (-a-)
TOTAL : 79.33
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-) : 7.09
ADD FOR OVER HEAD CHARGES @5% Except on (-a-) : 3.55
LABOUR FOR 2.00 Metre 89.97
LABOUR PER Metre 45.00
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00700 110.95 0.78
LABOUR :
Carpenter 1st Class each 0.30000 211.16 63.35
Carpenter 2nd Class each 0.30000 186.67 56.00
Beldar each 0.30000 116.67 35.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 158.35
Labour as per item no. 1205901000 8.40
TOTAL : 166.75
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-) : 15.83
ADD FOR OVER HEAD CHARGES @5% Except on (-a-) : 7.91
LABOUR FOR 2.00 Metre 190.49
LABOUR PER Metre 95.25
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00840 110.95 0.93
LABOUR :
Carpenter 1st Class each 0.30000 211.16 63.35
Carpenter 2nd Class each 0.11000 186.67 20.53
Beldar each 0.30000 116.67 35.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 122.88
Labour as per item no. 1205901000 8.40
TOTAL : 131.28
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-) : 12.28
ADD FOR OVER HEAD CHARGES @5% Except on (-a-) : 6.14
LABOUR FOR 2.00 Metre 149.70
LABOUR PER Metre 74.85
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00840 110.95 0.93
LABOUR :
Carpenter 1st Class each 0.20000 211.16 42.23
Carpenter 2nd Class each 0.12000 186.67 22.40
Beldar each 0.20000 116.67 23.33
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 89.46
Labour as per item no. 1205902000 8.40 (-a-)
TOTAL : 97.86
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-) : 8.94
ADD FOR OVER HEAD CHARGES @5% Except on (-a-) : 4.47
LABOUR FOR 2.00 Metre 111.27
LABOUR PER Metre 55.60
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
1206404000 1st class kail wood.
Details of cost for a pelmet
2 meter long.
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00840 110.95 0.93
LABOUR :
Carpenter 1st Class each 0.20000 211.16 42.23
Carpenter 2nd Class each 0.12000 186.67 22.40
Beldar each 0.20000 116.67 23.33
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 89.46
Labour as per item no. 1205902000 8.40 (-a-)
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 97.86
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-) : 8.94
ADD FOR OVER HEAD CHARGES @5% Except on (-a-) : 4.47
LABOUR FOR 2.00 Metre 111.27
LABOUR PER Metre 55.60
MATERIAL :
LABOUR :
For fixing of curtain rail L.S. 5.00
TOTAL : 137.75
ADD FOR CONTRACTORS PROFIT 10% 13.78
ADD FOR OVER HEAD CHARGES @5% 6.89
COST FOR 2 metre 148.40
COST PER Metre 74.20
LABOUR PER Metre 2.90
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 5.00
TOTAL : 5.00
ADD FOR CONTRACTORS PROFIT @10% : 0.50
ADD FOR OVER HEAD CHARGES @5% : 0.25
LABOUR FOR 2 Metre 5.75
LABOUR PER Metre 2.90
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
L.S. 2.00
M.S. Screws
CARRIAGE :
LABOUR :
TOTAL : 213.43
ADD FOR CONTRACTORS PROFIT 10% Except on (-I-) : 17.96
ADD FOR OVER HEAD CHARGES @5% Except on (-I-) : 8.98
COST FOR 2.00 Metre 240.37
COST PER Metre 120.20
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 36.40
Labour as per item no. 1205902000 8.40 (-a-)
TOTAL : 44.80
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-) : 3.64
ADD FOR OVER HEAD CHARGES @5% Except on (-a-) : 1.82
LABOUR FOR 2.00 Metre 50.26
LABOUR PER Metre 25.10
MATERIAL :
L.S. 2.00
M.S. Screws etc.
CARRIAGE :
LABOUR :
TOTAL : 185.92
ADD FOR CONTRACTORS PROFIT 10% Except on (-I-) : 15.21
ADD FOR OVER HEAD CHARGES @5% Except on (-I-) : 7.60
COST FOR 2.00 Metre 208.73
COST PER Metre 104.35
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 36.40
Labour as per item no. 1205902000 8.40 (-a-)
TOTAL : 44.80
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-) : 3.64
ADD FOR OVER HEAD CHARGES @5% Except on (-a-) : 1.82
LABOUR FOR 2.00 Metre 50.26
LABOUR PER Metre 25.10
MATERIAL :
L.S. 2.00
M.S. Screws etc.
CARRIAGE :
LABOUR :
TOTAL : 129.21
ADD FOR CONTRACTORS PROFIT 10% Except on (-I-) : 10.37
ADD FOR OVER HEAD CHARGES @5% Except on (-I-) : 5.18
COST FOR 2.00 Metre 114.76
COST PER Metre 72.35
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 24.26
Labour as per item no. 1205902000 8.40 (-a-)
TOTAL : 32.66
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-) : 2.42
ADD FOR OVER HEAD CHARGES @5% Except on (-a-) : 1.21
LABOUR FOR 2.00 Metre 36.29
LABOUR PER Metre 18.15
MATERIAL :
L.S. 2.00
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
M.S. Screws etc.
CARRIAGE :
LABOUR :
TOTAL : 129.21
ADD FOR CONTRACTORS PROFIT 10% Except on (-I-) : 10.25
ADD FOR OVER HEAD CHARGES @5% Except on (-I-) : 5.12
COST FOR 2.00 Metre 143.39
COST PER Metre 72.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 24.26
Labour as per item no. 1205902000 8.40 (-a-)
TOTAL : 32.66
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-) : 2.42
ADD FOR OVER HEAD CHARGES @5% Except on (-a-) : 1.21
LABOUR FOR 2.00 Metre 36.29
LABOUR PER Metre 18.15
MATERIAL :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
1st class indian teak wood.
Styles 1x4x200x9.5x4cm =0.0304 cum
Rails 1x4x150x9.5x4 cm. =0.0228 cum.
panels 3x2x59x41x2 cm. = 0.029 cum.
Beading 3x(2x0.54x12x37)x2x1.2 =0.0042 cum
Total = 0.0864 cum.
Add for wastage @ 10% = 0.0086 cum.
Total = 0.0950 cum.
1 cum. 0.09500 98625.00 9369.37
CARRIAGE :
LABOUR :
SUNDRIES : 75.00
TOTAL : 11174.05
ADD FOR CONTRACTORS PROFIT 10% 1117.40
ADD FOR OVER HEAD CHARGES @5% 558.70
COST FOR 3.00 Sqm. 12850.15
COST PER Sqm 4283.40
Labour per sqm. 618.40
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1613.20
TOTAL : 1613.20
ADD FOR CONTRACTORS PROFIT @10% 161.32
ADD FOR OVER HEAD CHARGES @5% 80.66
LABOUR FOR 3.00 Sqm. 1855.18
LABOUR PER Sqm 618.40
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.09500 110.95 10.54
LABOUR :
Carpenter 1st Class each 6.29000 211.16 1328.20
Beldar each 1.80000 116.67 210.01
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1613.20
TOTAL : 1613.20
ADD FOR CONTRACTORS PROFIT @10% : 161.32
ADD FOR OVER HEAD CHARGES @5% : 80.66
LABOUR FOR 3.00 Sqm. 1855.18
LABOUR PER Sqm 618.40
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.09500 110.95 10.54
LABOUR :
Carpenter 1st Class each 4.19000 211.16 884.76
Beldar each 1.20000 116.67 140.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1089.76
TOTAL : 1089.76
ADD FOR CONTRACTORS PROFIT @10% : 108.98
ADD FOR OVER HEAD CHARGES @5% : 54.49
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR FOR 3.00 Sqm. 1253.23
LABOUR PER Sqm 417.75
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.09500 110.95 10.54
LABOUR :
Carpenter 1st Class each 4.19000 211.16 884.76
Beldar each 1.20000 116.67 140.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1089.76
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 1089.76
ADD FOR CONTRACTORS PROFIT @10% : 108.98
ADD FOR OVER HEAD CHARGES @5% : 54.49
LABOUR FOR 3.00 Sqm. 1253.23
LABOUR PER Sqm 417.75
MATERIAL :
TOTAL : 35.50
ADD FOR CONTRACTORS PROFIT @10% : 3.55
ADD FOR OVER HEAD CHARGES @5% : 1.78
COST FOR 3.00 sq.m 40.83
COST PER sq.m 13.60
MATERIAL :
TOTAL : 106.50
ADD FOR CONTRACTORS PROFIT @10% : 10.65
ADD FOR OVER HEAD CHARGES @5% : 5.33
COST FOR 3.00 sq.m 122.48
COST PER sq.m 40.80
MATERIAL :
TOTAL : 35.50
ADD FOR CONTRACTORS PROFIT @10% : 3.55
ADD FOR OVER HEAD CHARGES @5% : 1.78
COST FOR 3.00 sq.m 40.83
COST PER sq.m 13.60
MATERIAL :
TOTAL : 63.90
ADD FOR CONTRACTORS PROFIT @10% : 6.39
ADD FOR OVER HEAD CHARGES @5% : 3.20
COST FOR 3.00 sq.m 73.49
COST PER sq.m 24.50
MATERIAL :
TOTAL : 230.75
ADD FOR CONTRACTORS PROFIT @10% : 23.08
ADD FOR OVER HEAD CHARGES @5% : 11.54
COST FOR 3.00 sq.m 242.28
COST PER sq.m 80.75
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.01700 110.95 1.89
LABOUR :
Carpenter 2nd Class each 0.18000 186.67 33.60
Mason 1st class each 0.25000 211.16 52.79
Black smith 2nd class each 0.25000 148.16 37.04
Beldar each 0.11000 116.67 12.83
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 141.26
Labour as per item No. : 0921010A 1.30 (-a-)
TOTAL : 142.56
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-) : 14.12
ADD FOR OVER HEAD CHARGES @5%Except on (-a-) : 7.06
LABOUR FOR0.600 Sqm. 163.74
LABOUR PER Sqm 272.90
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.01700 110.95 1.89
LABOUR :
Carpenter 2nd Class each 0.12000 186.67 22.40
Mason 1st class each 0.17000 211.16 35.90
Black smith 2nd class each 0.17000 148.16 25.19
Beldar each 0.07000 116.67 8.17
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 96.65
Labour as per item No. : 0921010A 1.30 (-a-)
TOTAL : 97.95
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-) : 9.66
ADD FOR OVER HEAD CHARGES @5%Except on (-a-) : 4.83
LABOUR FOR0.600 Sqm. 112.42
LABOUR PER Sqm 187.35
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.01700 110.95 1.88
LABOUR :
Carpenter 2nd Class each 0.12000 186.67 22.40
Mason 1st class each 0.17000 211.16 35.89
Black smith 2nd class each 0.17000 148.16 25.18
Beldar each 0.07000 116.67 8.16
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 96.63
Labour as per item No. : 0921010A 1.50 (-a-)
TOTAL : 97.93
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-) : 9.66
ADD FOR OVER HEAD CHARGES @5%Except on (-a-) : 4.83
LABOUR FOR0.600 Sqm. 112.42
LABOUR PER Sqm 187.35
MATERIAL :
CARRIAGE :
Timber.
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
1 KM BY MECH. TRANSPORT 1 cum 0.02640 110.95 2.93
LABOUR :
Carpenter 2nd Class each 0.18000 186.67 33.60
Mason 1st class each 0.25000 211.16 52.79
Black smith 2nd class each 0.25000 148.16 37.04
Beldar each 0.11000 116.67 12.83
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 141.26
Labour as per item No. : 0921010A 1.30 (-a-)
TOTAL : 142.56
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-) : 14.12
ADD FOR OVER HEAD CHARGES @5%Except on (-a-) : 7.06
LABOUR FOR0.600 Sqm. 163.74
LABOUR PER Sqm 272.90
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.02640 110.95 2.93
LABOUR :
Carpenter 2nd Class each 0.12000 186.67 22.40
Mason 1st class each 0.17000 211.16 35.90
Black smith 2nd class each 0.17000 148.16 25.19
Beldar each 0.07000 116.67 8.17
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 96.64
Labour as per item No. : 0921010A 1.30 (-a-)
TOTAL : 97.94
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-) : 9.66
ADD FOR OVER HEAD CHARGES @5%Except on (-a-) : 4.83
LABOUR FOR0.600 Sqm. 112.43
LABOUR PER Sqm 187.40
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.02640 110.95 2.93
LABOUR :
Carpenter 2nd Class each 0.12000 186.67 22.40
Mason 1st class each 0.17000 211.16 35.90
Black smith 2nd class each 0.17000 148.16 25.19
Beldar each 0.07000 116.67 8.17
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 96.64
Labour as per item No. : 0921010A 1.30 (-a-)
TOTAL : 97.94
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-) : 9.66
ADD FOR OVER HEAD CHARGES @5%Except on (-a-) : 4.83
LABOUR FOR0.600 Sqm. 112.43
LABOUR PER Sqm 187.40
MATERIAL :
CARRIAGE :
LABOUR :
TOTAL : 1515.10
ADD FOR CONTRACTORS PROFIT 10% 151.51
ADD FOR OVER HEAD CHARGES @5% 75.75
COST FOR 27.930 Kg. 1742.36
COST PER Kg. 62.40
LABOUR per kg. 8.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 206.30
TOTAL : 206.30
ADD FOR CONTRACTORS PROFIT @10% 20.63
ADD FOR OVER HEAD CHARGES @5% 10.31
LABOUR FOR0. 27.930 Kg. 237.24
LABOUR PER kg 8.50
MATERIAL :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
CARRIAGE :
LABOUR :
TOTAL : 1943.62
ADD FOR CONTRACTORS PROFIT 10% 194.36
ADD FOR OVER HEAD CHARGES @5% 97.18
COST FOR 33.670 Kg. 2235.16
COST PER Kg. 66.35
LABOUR per kg. 11.95
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 350.50
TOTAL : 350.50
ADD FOR CONTRACTORS PROFIT @10% 35.05
ADD FOR OVER HEAD CHARGES @5% 17.52
LABOUR FOR33.670 kg. 403.07
LABOUR PER kg 11.95
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
1207100000 Providing and fixing M.S. grills of require
pattern in wooden frames of windows
etc. with M.S. Flats, square or round bars
with round headed bolts and nuts or
by screws.
MATERIAL :
CARRIAGE :
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 333.86
TOTAL : 333.86
ADD FOR CONTRACTORS PROFIT @10% 33.38
ADD FOR OVER HEAD CHARGES @5% 16.69
LABOUR FOR 18.540 kg. 383.93
LABOUR PER kg 20.70
MATERIAL :
CARRIAGE :
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 215.96
TOTAL : 215.96
ADD FOR CONTRACTORS PROFIT @10% 21.60
ADD FOR OVER HEAD CHARGES @5% 10.80
LABOUR FOR 18.540 kg. 248.36
LABOUR PER kg 37.50
MATERIAL :
CARRIAGE :
Timber
1 KM BY MECH. TRANSPORT 1 cum 0.00650 110.95 0.72
LABOUR :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Carpenter 2nd Class each 0.33000 186.67 61.60
Beldar each 0.25000 116.67 29.17
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 105.76
TOTAL : 105.76
ADD FOR CONTRACTORS PROFIT @10% 10.57
ADD FOR OVER HEAD CHARGES @5% 5.28
LABOUR FOR 1.540 sqm 121.61
LABOUR PER sqm. 78.95
MATERIAL :
CARRIAGE :
Timber
1 KM BY MECH. TRANSPORT 1 cum 0.00650 110.95 0.72
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 100.76
TOTAL : 100.76
ADD FOR CONTRACTORS PROFIT @10% 10.07
ADD FOR OVER HEAD CHARGES @5% 5.03
LABOUR FOR 1.540 sqm 115.86
LABOUR PER sqm. 75.20
MATERIAL :
CARRIAGE :
Timber
1 KM BY MECH. TRANSPORT 1 cum 0.00660 110.95 0.73
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 95.76
TOTAL : 95.76
ADD FOR CONTRACTORS PROFIT @10% 9.58
ADD FOR OVER HEAD CHARGES @5% 4.79
LABOUR FOR 1.540 sqm 110.12
LABOUR PER sqm. 71.50
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00660 110.95 0.73
LABOUR :
Carpenter 2nd Class each 0.33000 186.67 61.60
Beldar each 0.25000 116.67 29.17
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 95.77
TOTAL : 95.77
ADD FOR CONTRACTORS PROFIT @10% : 9.58
ADD FOR OVER HEAD CHARGES @5% : 4.79
LABOUR FOR 1.540 sq.m 110.13
LABOUR PER sq.m 71.50
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00660 110.95 0.73
LABOUR :
Carpenter 2nd Class each 0.22000 186.67 41.07
Beldar each 0.18000 116.67 21.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 65.07
TOTAL : 65.07
ADD FOR CONTRACTORS PROFIT @10% : 6.51
ADD FOR OVER HEAD CHARGES @5% : 3.25
LABOUR FOR 1.540 sq.m 74.83
LABOUR PER sq.m 48.60
MATERIAL :
2nd class deodar wood.
Qty. same as per item 12075030000
Screws 40mm 1 cum 0.00660 53195.00 351.09
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00660 110.95 0.73
LABOUR :
Carpenter 2nd Class each 0.22000 186.67 41.07
Beldar each 0.18000 116.67 21.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 65.07
TOTAL : 65.07
ADD FOR CONTRACTORS PROFIT @10% : 6.51
ADD FOR OVER HEAD CHARGES @5% : 3.25
LABOUR FOR 1.540 sq.m 74.83
LABOUR PER sq.m 48.60
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00660 110.95 0.73
LABOUR :
Carpenter 2nd Class each 0.33000 186.67 61.60
Beldar each 0.25000 116.67 29.17
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 95.77
TOTAL : 95.77
ADD FOR CONTRACTORS PROFIT @10% : 9.58
ADD FOR OVER HEAD CHARGES @5% : 4.79
LABOUR FOR 1.540 sq.m 110.13
LABOUR PER sq.m 71.50
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00660 110.95 0.73
LABOUR :
Carpenter 2nd Class each 0.33000 186.67 61.60
Beldar each 0.25000 116.67 29.17
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 95.77
TOTAL : 95.77
ADD FOR CONTRACTORS PROFIT @10% : 9.58
ADD FOR OVER HEAD CHARGES @5% : 4.79
LABOUR FOR 1.540 sq.m 110.13
LABOUR PER sq.m 71.50
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00660 110.95 0.73
LABOUR :
Carpenter 2nd Class each 0.22000 186.67 41.07
Beldar each 0.18000 116.67 21.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 65.07
TOTAL : 65.07
ADD FOR CONTRACTORS PROFIT @10% : 6.51
ADD FOR OVER HEAD CHARGES @5% : 3.25
LABOUR FOR 1.540 sq.m 74.83
LABOUR PER sq.m 48.60
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00660 110.95 0.73
LABOUR :
Carpenter 2nd Class each 0.22000 186.67 41.07
Beldar each 0.18000 116.67 21.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 65.07
TOTAL : 65.07
ADD FOR CONTRACTORS PROFIT @10% : 6.51
ADD FOR OVER HEAD CHARGES @5% : 3.25
LABOUR FOR 1.540 sq.m 74.83
LABOUR PER sq.m 48.60
MATERIAL :
TOTAL : 118.80
ADD FOR CONTRACTORS PROFIT 10% 11.88
ADD FOR OVER HEAD CHARGES @5% 5.94
COST FOR 2.160 sq.m 136.62
COST PER sq.m 63.25
MATERIAL :
LABOUR :
TOTAL : 50.00
ADD FOR CONTRACTORS PROFIT 10% Except on (-I-) : 5.00
ADD FOR OVER HEAD CHARGES @5% Except on (-I-) : 2.50
COST FOR 1.00 each 57.50
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
COST PER each 57.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 11.84
Labour as per item No. : 0921010A 2.16
TOTAL : 14.00
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-) : 1.40
ADD FOR OVER HEAD CHARGES @5%Except on (-a-) : 0.70
LABOUR FOR0.1.00 each 16.10
LABOUR PER each 16.10
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.21300 110.95 23.63
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 401.51
Labour as per item No. : 16038000 2.91 (-a-)
TOTAL : 404.40
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-) : 40.14
ADD FOR OVER HEAD CHARGES @5%Except on (-a-) : 20.07
LABOUR FOR0.0.203 cum 464.63
LABOUR PER CUM 2288.70
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.21300 110.95 23.63
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 401.51
Labour as per item No. : 16038000 2.91 (-a-)
TOTAL : 404.42
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-) : 40.14
ADD FOR OVER HEAD CHARGES @5%Except on (-a-) : 20.07
LABOUR FOR0.0.203 cum 464.60
LABOUR PER CUM 2288.70
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.21300 110.95 23.63
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 401.51
Labour as per item No. : 16038000 2.91 (-a-)
TOTAL : 404.40
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-) : 40.14
ADD FOR OVER HEAD CHARGES @5%Except on (-a-) : 20.07
LABOUR FOR0.0.203 cum 464.61
LABOUR PER CUM 2288.70
MATERIAL :
Sal wood
450x30x15 cm = 0.203 cum
Add for wastage @ 5% = 0.010 cum
Total = 0.213 cum
1 cum 0.21300 15090.00 3214.17
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.21300 110.95 23.63
LABOUR :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Carpenter 2nd class each 0.70000 186.67 130.67
Bandhani each 0.70000 116.67 81.67
Beldar each 1.45000 116.67 169.17
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 401.51
Labour as per item No. : 16038000 2.91 (-a-)
TOTAL : 404.42
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-) : 40.14
ADD FOR OVER HEAD CHARGES @5%Except on (-a-) : 20.07
LABOUR FOR0.0.203 cum 464.61
LABOUR PER CUM 2288.70
MATERIAL :
Sal ballies :
80 mm dia & 2.5 to 3.0m. Long = 30m.
Add. for wastage @ 10% =3.00 m.
Total = 33.00 metres. 1 metres 33.00000 150.00 4950.00
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.66400 110.95 73.67
LABOUR :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 181.66
TOTAL : 181.66
ADD FOR CONTRACTORS PROFIT @10% : 18.16
ADD FOR OVER HEAD CHARGES @5% : 9.08
LABOUR FOR 30.00 metre 208.90
LABOUR PER Metre 6.95
MATERIAL :
Sal ballies :
100 mm dia 3.60m. Long = 30m.
Add. for wastage @ 10% =3.00 m.
Total = 33.00 metres. 1 metres 33.00000 150.00 4950.00
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 1.03000 110.95 114.28
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 267.50
TOTAL : 267.50
ADD FOR CONTRACTORS PROFIT @10% : 26.75
ADD FOR OVER HEAD CHARGES @5% : 13.37
LABOUR FOR 30.00 metre 307.62
LABOUR PER Metre 10.25
MATERIAL :
Sal ballies :
125 mm dia 3.60m. Long = 30m.
Add. for wastage @ 10% =3.00 m.
Total = 33.00 metres. 1 metre 33.00000 150.00 4950.00
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 1.60000 110.95 177.52
LABOUR :
Carpenter 2nd Class each 1.00000 186.67 186.67
Beldar each 1.00000 116.67 116.67
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 343.34
TOTAL : 343.34
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR CONTRACTORS PROFIT @10% : 34.33
ADD FOR OVER HEAD CHARGES @5% : 17.17
LABOUR FOR 30.00 metre 394.84
LABOUR PER Metre 13.15
MATERIAL :
Sal ballies :
150 mm dia 3.60m. Long = 30m.
Add. for wastage @ 10% =3.00 m.
Total = 33.00 metres. 1 metre 33.00000 150.00 4950.00
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 2.30000 110.95 255.19
LABOUR :
Carpenter 2nd Class each 1.25000 186.67 233.34
Beldar each 1.25000 116.67 145.84
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 419.18
TOTAL : 419.18
ADD FOR CONTRACTORS PROFIT @10% : 41.92
ADD FOR OVER HEAD CHARGES @5% : 20.96
LABOUR FOR 30.00 metre 482.05
LABOUR PER Metre 16.05
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.66400 110.95 73.67
LABOUR :
Carpenter 2nd Class each 1.00000 186.67 186.67
Bandhani each 0.25000 116.67 29.17
Beldar each 1.00000 116.67 116.67
TOTAL : 3490.25
ADD FOR CONTRACTORS PROFIT 10% 349.02
ADD FOR OVER HEAD CHARGES @5% 174.51
COST FOR 18.18 metres 4013.79
COST PER METRES 220.80
LABOUR PER metres 21.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 332.51
TOTAL : 332.51
ADD FOR CONTRACTORS PROFIT @10% : 33.25
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR OVER HEAD CHARGES @5% : 16.63
LABOUR FOR 18.18 metre 382.38
LABOUR PER Metre 21.00
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 1.03000 110.95 114.28
LABOUR :
Carpenter 2nd Class each 1.00000 186.67 186.67
Bandhani each 0.25000 116.67 29.17
Beldar each 1.00000 116.67 116.67
TOTAL : 3554.12
ADD FOR CONTRACTORS PROFIT 10% 355.41
ADD FOR OVER HEAD CHARGES @5% 177.71
COST FOR 18.18 metres 4087.24
COST PER METRES 224.80
LABOUR PER metres 21.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 332.51
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 332.51
ADD FOR CONTRACTORS PROFIT @10% : 33.25
ADD FOR OVER HEAD CHARGES @5% : 16.63
LABOUR FOR 18.18 metre 382.38
LABOUR PER Metre 21.00
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 1.60000 110.95 177.52
LABOUR :
Carpenter 2nd Class each 1.00000 186.67 186.67
Bandhani each 0.25000 116.67 29.17
Beldar each 1.00000 116.67 116.67
TOTAL : 3638.03
ADD FOR CONTRACTORS PROFIT 10% 363.80
ADD FOR OVER HEAD CHARGES @5% 181.90
COST FOR 18.18 metres 4183.73
COST PER METRES 230.10
LABOUR PER metres 21.00
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 332.51
TOTAL : 332.51
ADD FOR CONTRACTORS PROFIT @10% : 33.25
ADD FOR OVER HEAD CHARGES @5% : 16.63
LABOUR FOR 18.18 metre 382.38
LABOUR PER Metre 21.00
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 2.30000 110.95 255.19
LABOUR :
Carpenter 2nd Class each 1.00000 186.67 186.67
Bandhani each 0.25000 116.67 29.17
Beldar each 1.00000 116.67 116.67
TOTAL : 3741.07
ADD FOR CONTRACTORS PROFIT 10% 374.11
ADD FOR OVER HEAD CHARGES @5% 187.05
COST FOR 18.18 metres 4302.23
COST PER METRES 236.65
LABOUR PER metres 21.00
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 332.51
TOTAL : 332.51
ADD FOR CONTRACTORS PROFIT @10% : 33.25
ADD FOR OVER HEAD CHARGES @5% : 16.63
LABOUR FOR 18.18 metre 382.38
LABOUR PER Metre 21.00
Area-circular base
22/7x18.8x20cm = 0.118 sqm.
Offeset of base of top-
2x22/7x1/4(18.2)2-(13.8)2cm =0.026 sqm.
Middle ventical portion
22/7x13.8x60cm = 0.260 sqm.
Top hemisphere :
2x22/7x(18.8/2x18.8/2 =0.056 sqm.
Total = 0.460 sqm.
MATERIAL :
CARRIAGE :
Timber.
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
1 KM BY MECH. TRANSPORT 1 cum 0.00900 110.95 1.00
LABOUR :
Carpenter 1st Class each 2.55000 211.16 538.46
Carpenter 2nd Class each 0.26000 186.67 48.53
Beldar each 2.10000 116.67 245.01
SUNDRIES : 50.00
TOTAL : 1770.95
ADD FOR CONTRACTORS PROFIT 10% 177.09
ADD FOR OVER HEAD CHARGES @5% 88.55
COST FOR 0.460 SQM. 2036.59
COST PERsqm 4427.35
LABOUR PER sqm 2205.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 882.00
TOTAL : 882.00
ADD FOR CONTRACTORS PROFIT @10% : 88.20
ADD FOR OVER HEAD CHARGES @5% : 44.10
LABOUR FOR 0.460 sqm. 1014.30
LABOUR PER sqm. 2205.00
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00900 110.95 1.00
LABOUR :
Carpenter 1st Class each 2.55000 211.16 538.46
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Carpenter 2nd Class each 0.26000 186.67 48.53
Beldar each 2.10000 116.67 245.01
SUNDRIES : 50.00
TOTAL : 1597.83
ADD FOR CONTRACTORS PROFIT 10% 159.78
ADD FOR OVER HEAD CHARGES @5% 79.89
COST FOR 0.460 SQM. 1837.51
COST PERsqm 3994.60
LABOUR PER sqm 2205.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 882.00
TOTAL : 882.00
ADD FOR CONTRACTORS PROFIT @10% : 88.20
ADD FOR OVER HEAD CHARGES @5% : 44.10
LABOUR FOR 0.460 sqm. 1014.30
LABOUR PER sqm. 2205.00
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00900 110.95 1.00
LABOUR :
Carpenter 1st Class each 1.70000 211.16 358.97
Carpenter 2nd Class each 0.17000 186.67 31.73
Beldar each 1.40000 116.67 163.34
SUNDRIES : 30.00
TOTAL : 1071.55
ADD FOR CONTRACTORS PROFIT 10% 107.15
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR OVER HEAD CHARGES @5% 53.58
COST FOR 0.460 SQM. 1232.28
COST PERsqm 2678.90
LABOUR PER sqm 1460.10
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 584.04
TOTAL : 584.04
ADD FOR CONTRACTORS PROFIT @10% : 58.40
ADD FOR OVER HEAD CHARGES @5% : 29.20
LABOUR FOR 0.460 sqm. 671.65
LABOUR PER sqm. 1460.10
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00900 110.95 1.00
LABOUR :
Carpenter 1st Class each 1.70000 211.16 358.97
Carpenter 2nd Class each 0.17000 186.67 31.73
Beldar each 1.40000 116.67 163.34
SUNDRIES : 30.00
TOTAL : 1064.12
ADD FOR CONTRACTORS PROFIT 10% 106.41
ADD FOR OVER HEAD CHARGES @5% 53.21
COST FOR 0.460 SQM. 1223.74
COST PERsqm 2660.30
LABOUR PER sqm 1460.10
LABOUR RATE :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ACTUAL LABOUR+SUNDRIES 584.04
TOTAL : 584.04
ADD FOR CONTRACTORS PROFIT @10% : 58.40
ADD FOR OVER HEAD CHARGES @5% : 29.20
LABOUR FOR 0.460 sqm. 671.65
LABOUR PER sqm. 1460.10
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00900 110.95 1.00
LABOUR :
Carpenter 1st Class each 1.70000 211.16 358.97
Carpenter 2nd Class each 0.17000 186.67 31.73
Beldar each 1.40000 116.67 163.34
SUNDRIES : 30.00
TOTAL : 1064.12
ADD FOR CONTRACTORS PROFIT 10% 106.41
ADD FOR OVER HEAD CHARGES @5% 53.21
COST FOR 0.460 SQM. 1223.74
COST PERsqm 2660.30
LABOUR PER sqm 1460.10
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 584.04
TOTAL : 584.04
ADD FOR CONTRACTORS PROFIT @10% : 58.40
ADD FOR OVER HEAD CHARGES @5% : 29.20
LABOUR FOR 0.460 sqm. 671.65
LABOUR PER sqm. 1460.10
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00900 110.95 1.00
LABOUR :
Carpenter 1st Class each 1.70000 211.16 358.97
Carpenter 2nd Class each 0.17000 186.67 31.73
Beldar each 1.40000 116.67 163.34
SUNDRIES : 30.00
TOTAL : 950.81
ADD FOR CONTRACTORS PROFIT 10% 95.08
ADD FOR OVER HEAD CHARGES @5% 47.54
COST FOR 0.460 SQM. 1093.44
COST PERsqm 2377.00
LABOUR PER sqm 1460.10
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 584.04
TOTAL : 584.04
ADD FOR CONTRACTORS PROFIT @10% : 58.40
ADD FOR OVER HEAD CHARGES @5% : 29.20
LABOUR FOR 0.460 sqm. 671.65
LABOUR PER sqm. 1460.10
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.02100 110.95 2.33
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 231.00
TOTAL : 231.00
ADD FOR CONTRACTORS PROFIT @10% : 23.10
ADD FOR OVER HEAD CHARGES @5% : 11.55
LABOUR FOR 0.460 sqm. 265.65
LABOUR PER sqm. 577.50
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.02100 110.95 2.33
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 231.00
TOTAL : 231.00
ADD FOR CONTRACTORS PROFIT @10% : 23.10
ADD FOR OVER HEAD CHARGES @5% : 11.55
LABOUR FOR 0.460 sqm. 265.65
LABOUR PER sqm. 577.50
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.02100 110.95 2.33
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 150.67
TOTAL : 150.67
ADD FOR CONTRACTORS PROFIT @10% : 15.07
ADD FOR OVER HEAD CHARGES @5% : 7.53
LABOUR FOR 0.460 sqm. 173.27
LABOUR PER sqm. 376.65
MATERIAL :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.02100 110.95 2.33
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 150.67
TOTAL : 150.67
ADD FOR CONTRACTORS PROFIT @10% : 15.07
ADD FOR OVER HEAD CHARGES @5% : 7.53
LABOUR FOR 0.460 sqm. 173.27
LABOUR PER sqm. 376.65
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.02100 110.95 2.33
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 150.67
TOTAL : 150.67
ADD FOR CONTRACTORS PROFIT @10% : 15.07
ADD FOR OVER HEAD CHARGES @5% : 7.53
LABOUR FOR 0.460 sqm. 173.27
LABOUR PER sqm. 376.65
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.02100 110.95 2.33
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 150.67
TOTAL : 150.67
ADD FOR CONTRACTORS PROFIT @10% : 15.07
ADD FOR OVER HEAD CHARGES @5% : 7.53
LABOUR FOR 0.460 sqm. 173.27
LABOUR PER sqm. 376.65
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.02600 110.95 2.88
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 284.95
TOTAL : 284.95
ADD FOR CONTRACTORS PROFIT @10% : 28.49
ADD FOR OVER HEAD CHARGES @5% : 14.25
LABOUR FOR 0.460 sqm. 327.69
LABOUR PER sqm. 712.40
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.02600 110.95 2.88
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 284.95
TOTAL : 284.95
ADD FOR CONTRACTORS PROFIT @10% : 28.49
ADD FOR OVER HEAD CHARGES @5% : 14.25
LABOUR FOR 0.460 sqm. 327.69
LABOUR PER sqm. 712.40
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.02600 110.95 2.88
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 187.59
TOTAL : 187.59
ADD FOR CONTRACTORS PROFIT @10% : 18.76
ADD FOR OVER HEAD CHARGES @5% : 9.38
LABOUR FOR 0.460 sqm. 215.73
LABOUR PER sqm. 469.00
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.02600 110.95 2.88
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 187.59
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 187.59
ADD FOR CONTRACTORS PROFIT @10% : 18.76
ADD FOR OVER HEAD CHARGES @5% : 9.38
LABOUR FOR 0.460 sqm. 215.73
LABOUR PER sqm. 469.00
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.02600 110.95 2.88
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 187.59
TOTAL : 187.59
ADD FOR CONTRACTORS PROFIT @10% : 18.76
ADD FOR OVER HEAD CHARGES @5% : 9.38
LABOUR FOR 0.460 sqm. 215.73
LABOUR PER sqm. 469.00
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.02600 110.95 2.88
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 187.59
TOTAL : 187.59
ADD FOR CONTRACTORS PROFIT @10% : 18.76
ADD FOR OVER HEAD CHARGES @5% : 9.38
LABOUR FOR 0.460 sqm. 215.73
LABOUR PER sqm. 469.00
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00100 110.95 0.11
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 37.90
TOTAL : 37.90
ADD FOR CONTRACTORS PROFIT @10% : 3.79
ADD FOR OVER HEAD CHARGES @5% : 1.89
LABOUR FOR 0.305 metre 43.58
LABOUR PER metre 142.90
MATERIAL :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
2nd class indian teak wood. = 0.0009 cum
Add for wastage @ 5 % = 0.000045 cum
Total = 0.000945 cum
say Rs. 0.001 cum
1 cum 0.00100 79390.00 79.39
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00100 110.95 0.11
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 37.90
TOTAL : 37.90
ADD FOR CONTRACTORS PROFIT @10% : 3.79
ADD FOR OVER HEAD CHARGES @5% : 1.89
LABOUR FOR 0.305 metre 43.58
LABOUR PER metre 142.90
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00100 110.95 0.11
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 24.73
TOTAL : 24.73
ADD FOR CONTRACTORS PROFIT @10% : 2.47
ADD FOR OVER HEAD CHARGES @5% : 1.24
LABOUR FOR 0.305 metre 28.44
LABOUR PER metre 93.20
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00100 110.95 0.11
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 24.73
TOTAL : 24.73
ADD FOR CONTRACTORS PROFIT @10% : 2.47
ADD FOR OVER HEAD CHARGES @5% : 1.24
LABOUR FOR 0.305 metre 28.44
LABOUR PER metre 93.20
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00100 110.95 0.11
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 24.73
TOTAL : 24.73
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR CONTRACTORS PROFIT @10% : 2.47
ADD FOR OVER HEAD CHARGES @5% : 1.24
LABOUR FOR 0.305 metre 28.44
LABOUR PER metre 93.20
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00100 110.95 0.11
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 24.73
TOTAL : 24.73
ADD FOR CONTRACTORS PROFIT @10% : 2.47
ADD FOR OVER HEAD CHARGES @5% : 1.24
LABOUR FOR 0.305 metre 28.44
LABOUR PER metre 93.20
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00840 110.95 0.93
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 153.70
TOTAL : 153.70
ADD FOR CONTRACTORS PROFIT @10% : 15.37
ADD FOR OVER HEAD CHARGES @5% : 7.68
LABOUR FOR 1.00 metre 176.70
LABOUR PER metre 176.70
MATERIAL :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
2nd class Indian teak wood.
Quantity same as per item No. 1208701000
1 cum 0.00840 77190.00 648.40
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00840 110.95 0.93
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 153.70
TOTAL : 153.70
ADD FOR CONTRACTORS PROFIT @10% : 15.37
ADD FOR OVER HEAD CHARGES @5% : 7.68
LABOUR FOR 1.00 metre 176.75
LABOUR PER metre 176.75
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00840 110.95 0.93
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 100.41
TOTAL : 100.41
ADD FOR CONTRACTORS PROFIT @10% : 10.04
ADD FOR OVER HEAD CHARGES @5% : 5.02
LABOUR FOR 1.00 metre 115.47
LABOUR PER metre 115.45
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00840 110.95 0.93
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 100.41
TOTAL : 100.41
ADD FOR CONTRACTORS PROFIT @10% : 10.04
ADD FOR OVER HEAD CHARGES @5% : 5.02
LABOUR FOR 1.00 metre 115.47
LABOUR PER metre 115.45
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00840 110.95 0.93
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 100.41
TOTAL : 100.41
ADD FOR CONTRACTORS PROFIT @10% : 10.04
ADD FOR OVER HEAD CHARGES @5% : 5.02
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR FOR 1.00 metre 115.47
LABOUR PER metre 115.45
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00840 110.95 0.93
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 100.41
TOTAL : 100.41
ADD FOR CONTRACTORS PROFIT @10% : 10.04
ADD FOR OVER HEAD CHARGES @5% : 5.02
LABOUR FOR 1.00 metre 115.45
LABOUR PER metre 115.45
LABOUR :
TOTAL : 10.55
ADD FOR CONTRACTORS PROFIT 10% 1.05
ADD FOR OVER HEAD CHARGES @5% 0.52
COST FOR 1.00 metre 12.12
COST PER metre 12.10
LABOUR PER metre (Extra Rate) 12.10
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.01510 110.95 1.68
LABOUR :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 287.45
TOTAL : 287.45
ADD FOR CONTRACTORS PROFIT @10% : 28.74
ADD FOR OVER HEAD CHARGES @5% : 14.37
LABOUR FOR 3.050 metre 330.56
LABOUR PER metre 108.40
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.01510 110.95 1.68
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 287.45
TOTAL : 287.45
ADD FOR CONTRACTORS PROFIT @10% : 28.74
ADD FOR OVER HEAD CHARGES @5% : 14.37
LABOUR FOR 3.050 metre 330.56
LABOUR PER metre 108.40
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.01510 110.95 1.68
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 190.54
TOTAL : 190.54
ADD FOR CONTRACTORS PROFIT @10% : 19.05
ADD FOR OVER HEAD CHARGES @5% : 9.53
LABOUR FOR 3.050 metre 219.12
LABOUR PER metre 71.80
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
1209004000 2nd class deodar wood.
Details of cost for 3.05 metre run.
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.01510 110.95 1.68
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 190.54
TOTAL : 190.54
ADD FOR CONTRACTORS PROFIT @10% : 19.05
ADD FOR OVER HEAD CHARGES @5% : 9.53
LABOUR FOR 3.050 metre 219.12
LABOUR PER metre 71.80
MATERIAL :
CARRIAGE :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.01510 110.95 1.68
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 190.54
TOTAL : 190.54
ADD FOR CONTRACTORS PROFIT @10% : 19.05
ADD FOR OVER HEAD CHARGES @5% : 9.53
LABOUR FOR 3.050 metre 219.12
LABOUR PER metre 71.80
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.01510 110.95 1.68
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 190.54
TOTAL : 190.54
ADD FOR CONTRACTORS PROFIT @10% : 19.05
ADD FOR OVER HEAD CHARGES @5% : 9.53
LABOUR FOR 3.050 metre 219.12
LABOUR PER metre 71.80
LABOUR :
TOTAL : 80.24
ADD FOR CONTRACTORS PROFIT 10% 8.02
ADD FOR OVER HEAD CHARGES @5% 4.01
COST FOR 3.050 metre 92.28
COST PER metre 30.25
LABOUR PER metre 30.25
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 80.24
TOTAL : 80.24
ADD FOR CONTRACTORS PROFIT @10% : 8.02
ADD FOR OVER HEAD CHARGES @5% : 4.01
LABOUR FOR 3.050 metre 92.28
LABOUR PER metre 30.25
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00140 110.95 0.16
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 187.37
TOTAL : 187.37
ADD FOR CONTRACTORS PROFIT @10% : 18.74
ADD FOR OVER HEAD CHARGES @5% : 9.37
LABOUR FOR 1.00 cap 215.48
LABOUR PER cap 215.50
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
1209302000 2nd class indian teak wood.
Details of cost for one piece cap
15x15x6 cm.
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00142 110.95 0.16
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 187.37
TOTAL : 187.37
ADD FOR CONTRACTORS PROFIT @10% : 18.74
ADD FOR OVER HEAD CHARGES @5% : 9.37
LABOUR FOR 1.00 cap 215.48
LABOUR PER cap 215.50
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00140 110.95 0.16
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 126.25
TOTAL : 126.25
ADD FOR CONTRACTORS PROFIT @10% : 12.62
ADD FOR OVER HEAD CHARGES @5% : 6.31
LABOUR FOR 1.00 cap 145.19
LABOUR PER cap 145.20
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00140 110.95 0.16
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 126.25
TOTAL : 126.25
ADD FOR CONTRACTORS PROFIT @10% : 12.62
ADD FOR OVER HEAD CHARGES @5% : 6.31
LABOUR FOR 1.00 cap 145.19
LABOUR PER cap 145.20
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00140 110.95 0.16
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 126.25
TOTAL : 126.25
ADD FOR CONTRACTORS PROFIT @10% : 12.62
ADD FOR OVER HEAD CHARGES @5% : 6.31
LABOUR FOR 1.00 cap 145.19
LABOUR PER cap 145.20
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00140 110.95 0.16
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 126.25
TOTAL : 126.25
ADD FOR CONTRACTORS PROFIT @10% : 12.62
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR OVER HEAD CHARGES @5% : 6.31
LABOUR FOR 1.00 cap 145.19
LABOUR PER cap 145.20
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.03600 110.95 3.99
LABOUR :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Carpenter 1st Class each 0.57000 211.16 120.36
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 128.36
TOTAL : 128.36
ADD FOR CONTRACTORS PROFIT @10% : 12.84
ADD FOR OVER HEAD CHARGES @5% : 6.42
LABOUR FOR 0.034 cum 147.62
LABOUR PER cum 4341.60
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.03600 110.95 3.99
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 128.36
TOTAL : 128.36
ADD FOR CONTRACTORS PROFIT @10% : 12.84
ADD FOR OVER HEAD CHARGES @5% : 6.42
LABOUR FOR 0.034 cum 147.62
LABOUR PER cum 4341.00
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.03600 110.95 3.99
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 85.24
TOTAL : 85.24
ADD FOR CONTRACTORS PROFIT @10% : 8.52
ADD FOR OVER HEAD CHARGES @5% : 4.26
LABOUR FOR 0.034 cum 98.03
LABOUR PER cum 2883.10
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.03600 110.95 3.99
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 85.24
TOTAL : 85.24
ADD FOR CONTRACTORS PROFIT @10% : 8.52
ADD FOR OVER HEAD CHARGES @5% : 4.26
LABOUR FOR 0.034 cum 98.03
LABOUR PER cum 2883.10
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.03600 110.95 3.99
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 85.24
TOTAL : 85.24
ADD FOR CONTRACTORS PROFIT @10% : 8.52
ADD FOR OVER HEAD CHARGES @5% : 4.26
LABOUR FOR 0.034 cum 98.03
LABOUR PER cum 2883.10
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.03600 110.95 3.99
LABOUR :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Carpenter 1st Class each 0.38000 211.16 80.24
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 85.24
TOTAL : 85.24
ADD FOR CONTRACTORS PROFIT @10% : 8.52
ADD FOR OVER HEAD CHARGES @5% : 4.26
LABOUR FOR 0.034 cum 98.03
LABOUR PER cum 2883.10
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00840 110.95 0.93
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 65.24
TOTAL : 65.24
ADD FOR CONTRACTORS PROFIT @10% : 6.52
ADD FOR OVER HEAD CHARGES @5% : 3.26
LABOUR FOR 0.008 cum 75.02
LABOUR PER cum 9376.25
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00840 110.95 0.93
LABOUR :
LABOUR RATE :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ACTUAL LABOUR+SUNDRIES 65.24
TOTAL : 65.24
ADD FOR CONTRACTORS PROFIT @10% : 6.52
ADD FOR OVER HEAD CHARGES @5% : 3.26
LABOUR FOR 0.008 cum 75.02
LABOUR PER cum 9376.25
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00840 110.95 0.93
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 42.12
TOTAL : 42.12
ADD FOR CONTRACTORS PROFIT @10% : 4.21
ADD FOR OVER HEAD CHARGES @5% : 2.11
LABOUR FOR 0.008 cum 48.44
LABOUR PER cum 6054.80
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00840 110.95 0.93
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 42.12
TOTAL : 42.12
ADD FOR CONTRACTORS PROFIT @10% : 4.21
ADD FOR OVER HEAD CHARGES @5% : 2.11
LABOUR FOR 0.008 cum 48.44
LABOUR PER cum 6054.80
MATERIAL :
CARRIAGE :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00840 110.95 0.93
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 42.12
TOTAL : 42.12
ADD FOR CONTRACTORS PROFIT @10% : 4.21
ADD FOR OVER HEAD CHARGES @5% : 2.11
LABOUR FOR 0.008 cum 48.44
LABOUR PER cum 6054.80
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00840 110.95 0.93
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 42.12
TOTAL : 42.12
ADD FOR CONTRACTORS PROFIT @10% : 4.21
ADD FOR OVER HEAD CHARGES @5% : 2.11
LABOUR FOR 0.008 cum 48.44
LABOUR PER cum 6054.80
LABOUR :
TOTAL : 80.24
ADD FOR CONTRACTORS PROFIT 10% 8.02
ADD FOR OVER HEAD CHARGES @5% 4.01
COST FOR 1.00 each 92.28
COST PER Each 92.30
LABOUR PER Each 92.30
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 80.24
TOTAL : 80.24
ADD FOR CONTRACTORS PROFIT @10% : 8.02
ADD FOR OVER HEAD CHARGES @5% : 4.01
LABOUR FOR 1.00 each 92.28
LABOUR PER each 92.30
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00350 110.95 0.39
LABOUR :
TOTAL : 513.66
ADD FOR CONTRACTORS PROFIT 10% 51.37
ADD FOR OVER HEAD CHARGES @5% 25.68
COST FOR 1.00 cap 590.71
COST PER cap 590.70
LABOUR PER cap 204.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 177.37
TOTAL : 177.37
ADD FOR CONTRACTORS PROFIT @10% : 17.74
ADD FOR OVER HEAD CHARGES @5% : 8.87
LABOUR FOR 1.00 cap 203.98
LABOUR PER cap 204.00
MATERIAL :
CARRIAGE :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00350 110.95 0.39
LABOUR :
TOTAL : 448.05
ADD FOR CONTRACTORS PROFIT 10% 44.81
ADD FOR OVER HEAD CHARGES @5% 22.40
COST FOR 1.00 cap 515.26
COST PER cap 515.25
LABOUR PER cap 204.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 177.37
TOTAL : 177.37
ADD FOR CONTRACTORS PROFIT @10% : 17.74
ADD FOR OVER HEAD CHARGES @5% : 8.87
LABOUR FOR 1.00 cap 203.98
LABOUR PER cap 204.00
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00350 110.95 0.39
LABOUR :
TOTAL : 302.39
ADD FOR CONTRACTORS PROFIT 10% 30.24
ADD FOR OVER HEAD CHARGES @5% 15.12
COST FOR 1.00 cap 347.75
COST PER cap 347.75
LABOUR PER cap 136.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 118.25
TOTAL : 118.25
ADD FOR CONTRACTORS PROFIT @10% : 11.82
ADD FOR OVER HEAD CHARGES @5% : 5.91
LABOUR FOR 1.00 cap 135.99
LABOUR PER cap 136.00
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00350 110.95 0.39
LABOUR :
TOTAL : 299.57
ADD FOR CONTRACTORS PROFIT 10% 29.96
ADD FOR OVER HEAD CHARGES @5% 14.98
COST FOR 1.00 cap 344.51
COST PER cap 344.50
LABOUR PER cap 136.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 118.25
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 118.25
ADD FOR CONTRACTORS PROFIT @10% : 11.82
ADD FOR OVER HEAD CHARGES @5% : 5.91
LABOUR FOR 1.00 cap 135.99
LABOUR PER cap 136.00
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00350 110.95 0.39
LABOUR :
TOTAL : 299.57
ADD FOR CONTRACTORS PROFIT 10% 29.96
ADD FOR OVER HEAD CHARGES @5% 14.98
COST FOR 1.00 cap 344.51
COST PER cap 344.50
LABOUR PER cap 136.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 118.25
TOTAL : 118.25
ADD FOR CONTRACTORS PROFIT @10% : 11.82
ADD FOR OVER HEAD CHARGES @5% : 5.91
LABOUR FOR 1.00 cap 135.99
LABOUR PER cap 136.00
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00350 110.95 0.39
LABOUR :
TOTAL : 256.63
ADD FOR CONTRACTORS PROFIT 10% 25.66
ADD FOR OVER HEAD CHARGES @5% 12.83
COST FOR 1.00 cap 295.12
COST PER cap 295.10
LABOUR PER cap 136.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 118.25
TOTAL : 118.25
ADD FOR CONTRACTORS PROFIT @10% : 11.82
ADD FOR OVER HEAD CHARGES @5% : 5.91
LABOUR FOR 1.00 cap 135.99
LABOUR PER cap 136.00
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00240 110.95 0.27
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 253.61
TOTAL : 253.61
ADD FOR CONTRACTORS PROFIT @10% : 25.36
ADD FOR OVER HEAD CHARGES @5% : 12.68
LABOUR FOR 1.00 cap 291.65
LABOUR PER cap 291.65
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00240 110.95 0.27
LABOUR :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Carpenter 1st Class each 1.13000 211.16 238.61
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 253.61
TOTAL : 253.61
ADD FOR CONTRACTORS PROFIT @10% : 25.36
ADD FOR OVER HEAD CHARGES @5% : 12.68
LABOUR FOR 1.00 cap 291.65
LABOUR PER cap 291.65
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00240 110.95 0.27
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 168.37
TOTAL : 168.37
ADD FOR CONTRACTORS PROFIT @10% : 16.84
ADD FOR OVER HEAD CHARGES @5% : 8.42
LABOUR FOR 1.00 cap 193.63
LABOUR PER cap 193.60
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00240 110.95 0.27
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 168.37
TOTAL : 168.37
ADD FOR CONTRACTORS PROFIT @10% : 16.84
ADD FOR OVER HEAD CHARGES @5% : 8.42
LABOUR FOR 1.00 cap 193.63
LABOUR PER cap 193.60
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00240 110.95 0.27
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 168.37
TOTAL : 168.37
ADD FOR CONTRACTORS PROFIT @10% : 16.84
ADD FOR OVER HEAD CHARGES @5% : 8.42
LABOUR FOR 1.00 cap 193.63
LABOUR PER cap 193.60
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00240 110.95 0.27
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 168.37
TOTAL : 168.37
ADD FOR CONTRACTORS PROFIT @10% : 16.84
ADD FOR OVER HEAD CHARGES @5% : 8.42
LABOUR FOR 1.00 cap 193.63
LABOUR PER cap 193.60
MATERIAL :
1st class indian teak wood.
12.7x12.7x22.9 cm = 0.0037 cum
Add for wastage 5% = 0.0002 cum.
---------------------------
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Total = 0.0039 cum
1 cum 0.00390 95935.00 374.15
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00390 110.95 0.43
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 510.11
TOTAL : 510.11
ADD FOR CONTRACTORS PROFIT @10% : 51.01
ADD FOR OVER HEAD CHARGES @5% : 25.51
LABOUR FOR 1.00 cap 586.63
LABOUR PER cap 586.60
MATERIAL :
2nd class indian teak wood.
Quantity same as per item no. 1210001000
1 cum 0.00390 77190.00 301.04
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00390 110.95 0.43
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 505.11
TOTAL : 505.11
ADD FOR CONTRACTORS PROFIT @10% : 50.51
ADD FOR OVER HEAD CHARGES @5% : 25.26
LABOUR FOR 1.00 cap 580.88
LABOUR PER cap 580.90
MATERIAL :
1st class deodar wood.
Quantity same as per item no. 1210001000
1 cum 0.00390 52465.00 204.61
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00390 110.95 0.43
LABOUR :
LABOUR RATE :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ACTUAL LABOUR+SUNDRIES 336.74
TOTAL : 336.74
ADD FOR CONTRACTORS PROFIT @10% : 33.67
ADD FOR OVER HEAD CHARGES @5% : 16.84
LABOUR FOR 1.00 cap 387.25
LABOUR PER cap 387.25
MATERIAL :
2nd class deodar wood.
Quantity same as per item no. 1210001000
1 cum 0.00390 51660.00 201.47
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00390 110.95 0.43
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 336.74
TOTAL : 336.74
ADD FOR CONTRACTORS PROFIT @10% : 33.67
ADD FOR OVER HEAD CHARGES @5% : 16.84
LABOUR FOR 1.00 cap 387.25
LABOUR PER cap 387.25
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00390 110.95 0.43
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 336.74
TOTAL : 336.74
ADD FOR CONTRACTORS PROFIT @10% : 33.67
ADD FOR OVER HEAD CHARGES @5% : 16.84
LABOUR FOR 1.00 cap 387.25
LABOUR PER cap 387.25
MATERIAL :
2nd class kail wood
Quantity same as per item no. 1210001000
1 cum 0.00390 39390.00 153.62
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00390 110.95 0.43
LABOUR :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 336.74
TOTAL : 336.74
ADD FOR CONTRACTORS PROFIT @10% : 33.67
ADD FOR OVER HEAD CHARGES @5% : 16.84
LABOUR FOR 1.00 cap 387.25
LABOUR PER cap 387.25
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00600 110.95 0.67
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 945.12
TOTAL : 945.12
ADD FOR CONTRACTORS PROFIT @10% : 94.51
ADD FOR OVER HEAD CHARGES @5% : 47.26
LABOUR FOR 9.140 metre 1086.89
LABOUR PER metre 118.90
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00600 110.95 0.67
LABOUR :
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00600 110.95 0.67
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 631.75
TOTAL : 631.75
ADD FOR CONTRACTORS PROFIT @10% : 63.17
ADD FOR OVER HEAD CHARGES @5% : 31.59
LABOUR FOR 9.140 metre 726.51
LABOUR PER metre 79.50
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00600 110.95 0.67
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 631.75
TOTAL : 631.75
ADD FOR CONTRACTORS PROFIT @10% : 63.17
ADD FOR OVER HEAD CHARGES @5% : 31.59
LABOUR FOR 9.140 metre 726.51
LABOUR PER metre 79.50
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00600 110.95 0.67
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 631.75
TOTAL : 631.75
ADD FOR CONTRACTORS PROFIT @10% : 63.17
ADD FOR OVER HEAD CHARGES @5% : 31.59
LABOUR FOR 9.140 metre 726.51
LABOUR PER metre 79.50
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.00600 110.95 0.67
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 631.75
TOTAL : 631.75
ADD FOR CONTRACTORS PROFIT @10% : 63.17
ADD FOR OVER HEAD CHARGES @5% : 31.59
LABOUR FOR 9.140 metre 726.51
LABOUR PER metre 79.50
MATERIAL :
SAWING CHARGES :
Sleeper to scantling 1 cum 1.15000 420.00 483.00
cost per cum. 95933.00
Say Rs. 95935/-
MATERIAL :
SAWING CHARGES :
Sleeper to scantling 1 cum 1.15000 420.00 483.00
cost per cum. 77188.00
Say Rs. 77190/-
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
SAWING CHARGES :
Sleeper to scantling 1 cum 1.15000 420.00 483.00
cost per cum. 52463.00
Say Rs. 52465/-
MATERIAL :
SAWING CHARGES :
Sleeper to scantling 1 cum 1.15000 420.00 483.00
cost per cum. 51658.00
Say Rs. 51660/-
MATERIAL :
SAWING CHARGES :
Sleeper to scantling 1 cum 1.15000 420.00 483.00
cost per cum. 51658.00
Say Rs. 51660/-
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
SAWING CHARGES :
Sleeper to scantling 1 cum 1.15000 420.00 483.00
cost per cum. 39388.00
Say Rs. 39390/-
MATERIAL :
SAWING CHARGES :
Sleeper to scantling 1 cum 1.15000 420.00 483.00
cost per cum. 21298.00
Say Rs. 21300/-
MATERIAL :
SAWING CHARGES :
Sleeper to scantling 1 cum 1.15000 420.00 483.00
cost per cum. 18653.00
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Say Rs. 18650/-
MATERIAL :
SAWING CHARGES :
Sleeper to scantling 1 cum 1.15000 420.00 483.00
cost per cum. 15088.00
Say Rs. 15090/-
MATERIAL :
SAWING CHARGES :
Sleeper to planks 1 cum 1.18000 580.00 685.00
cost per cum. 98625.00
MATERIAL :
SAWING CHARGES :
Sleeper to planks 1 cum 1.18000 580.00 685.00
cost per cum. 79391.00
Say Rs. 79390/-
MATERIAL :
SAWING CHARGES :
Sleeper to Planks 1 cum 1.18000 580.00 685.00
cost per cum. 54021.00
Say Rs. 54020/-
MATERIAL :
SAWING CHARGES :
Sleeper to planks 1 cum 1.18000 580.00 685.00
cost per cum. 53195.00
MATERIAL :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
1st class kail wood
wood in sleepers =1.00 cum
Add for wastage @ 18% = 0.18 cum
Total = 1.18 cum
1 cum 1.18000 44500.00 52510.00
SAWING CHARGES :
Sleeper to planks 1 cum 1.18000 580.00 685.00
cost per cum. 53195.00
MATERIAL :
SAWING CHARGES :
Sleeper to planks 1 cum 1.18000 580.00 685.00
cost per cum. 40605.00
MATERIAL :
SAWING CHARGES :
Sleeper to planks 1 cum 1.18000 580.00 685.00
cost per cum. 22043.00
Say Rs. 22045.00
SAWING CHARGES :
Sleeper to planks 1 cum 1.18000 580.00 685.00
cost per cum. 19329.00
say Rs. 19330/-
MATERIAL :
sal wood.
wood in sleepers =1.00 cum
Add for wastage @ 18% = 0.18 cum
Total = 1.18 cum
1 cum 1.18000 12700.00 14986.00
SAWING CHARGES :
Sleeper to planks 1 cum 1.18000 580.00 685.00
cost per cum. 15671.00
say Rs. 15670/-
1210401000 300x16mm
Details of cost for 10 Nos.
MATERIAL :
CARRIAGE :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Carriage of material L.S. 3.00
LABOUR :
Carpenter 1st class each 0.50000 211.16 105.58
TOTAL : 1312.58
ADD FOR CONTRACTORS PROFIT 10% 131.26
ADD FOR OVER HEAD CHARGES @5% 65.63
COST FOR 10.00 no. 1509.47
COST PER No. 150.95
LABOUR PER no. 12.15
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 105.58
TOTAL : 105.58
ADD FOR CONTRACTORS PROFIT @10% : 10.56
ADD FOR OVER HEAD CHARGES @5% : 5.28
LABOUR FOR 10.00 no. 121.42
LABOUR PER no. 12.15
1210402000 250x16mm
Details of cost for 10 Nos.
MATERIAL :
CARRIAGE :
Carriage of material L.S. 3.00
LABOUR :
Carpenter 1st class each 0.50000 211.16 105.58
TOTAL : 1212.58
ADD FOR CONTRACTORS PROFIT 10% 121.26
ADD FOR OVER HEAD CHARGES @5% 60.63
COST FOR 10.00 nos 1394.47
COST PER no 139.45
LABOUR PER no. 12.15
LABOUR RATE :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ACTUAL LABOUR+SUNDRIES 105.58
TOTAL : 105.58
ADD FOR CONTRACTORS PROFIT @10% : 10.56
ADD FOR OVER HEAD CHARGES @5% : 5.28
LABOUR FOR 10.00 no. 121.42
LABOUR PER no. 12.15
1210501000 300x10mm
Details of cost for 10 Nos.
MATERIAL :
CARRIAGE :
Carriage of material L.S. 2.00
LABOUR :
Carpenter 1st class each 0.10000 211.16 21.11
TOTAL : 643.11
ADD FOR CONTRACTORS PROFIT 10% 64.31
ADD FOR OVER HEAD CHARGES @5% 32.16
COST FOR 10.00 nos 739.58
COST PER no. 73.95
LABOUR PER no. 2.40
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 21.11
TOTAL : 21.11
ADD FOR CONTRACTORS PROFIT @10% : 2.11
ADD FOR OVER HEAD CHARGES @5% : 1.06
LABOUR FOR 10.00 no. 24.28
LABOUR PER no. 2.40
1210502000 250x10mm
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Details of cost for 10 Nos.
MATERIAL :
CARRIAGE :
Carriage of material L.S. 2.00
LABOUR :
Carpenter 1st class each 0.10000 211.16 21.11
TOTAL : 543.11
ADD FOR CONTRACTORS PROFIT 10% 54.31
ADD FOR OVER HEAD CHARGES @5% 27.16
COST FOR 10.00 nos 624.58
COST PER no. 62.45
LABOUR PER no. 2.40
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 21.11
TOTAL : 21.11
ADD FOR CONTRACTORS PROFIT @10% : 2.11
ADD FOR OVER HEAD CHARGES @5% : 1.06
LABOUR FOR 10.00 nos. 24.28
LABOUR PER no. 2.40
1210503000 200x10mm
Details of cost for 10 Nos.
MATERIAL :
CARRIAGE :
Carriage of material L.S. 2.00
LABOUR :
Carpenter 1st class each 0.10000 211.16 21.11
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 443.11
ADD FOR CONTRACTORS PROFIT 10% 44.31
ADD FOR OVER HEAD CHARGES @5% 22.16
COST FOR 10.00 nos 509.58
COST PER no. 50.95
LABOUR PER no. 2.40
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 21.11
TOTAL : 21.11
ADD FOR CONTRACTORS PROFIT @10% : 2.11
ADD FOR OVER HEAD CHARGES @5% : 1.06
LABOUR FOR 10.00 no. 24.28
LABOUR PER no. 2.40
1210504000 150x10mm
Details of cost for 10 Nos.
MATERIAL :
CARRIAGE :
Carriage of material L.S. 2.00
LABOUR :
Carpenter 1st class each 0.10000 211.16 21.11
TOTAL : 393.11
ADD FOR CONTRACTORS PROFIT 10% 39.31
ADD FOR OVER HEAD CHARGES @5% 19.66
COST FOR 10.00 nos 452.08
COST PER no. 45.20
LABOUR PER no. 2.40
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 21.11
TOTAL : 21.11
ADD FOR CONTRACTORS PROFIT @10% : 2.11
ADD FOR OVER HEAD CHARGES @5% : 1.06
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR FOR 10.00 no. 24.28
LABOUR PER no. 2.40
1210505000 100x10mm
Details of cost for 10 Nos.
MATERIAL :
CARRIAGE :
Carriage of material L.S. 1.00
LABOUR :
Carpenter 1st class each 0.10000 211.16 21.11
TOTAL : 292.11
ADD FOR CONTRACTORS PROFIT 10% 29.21
ADD FOR OVER HEAD CHARGES @5% 14.61
COST FOR 10.00 nos 335.93
COST PER no. 33.60
LABOUR PER no. 2.40
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 21.11
TOTAL : 21.11
ADD FOR CONTRACTORS PROFIT @10% : 2.11
ADD FOR OVER HEAD CHARGES @5% : 1.06
LABOUR FOR 10.00 no. 24.28
LABOUR PER no. 2.40
1210601000 125 mm
Details of cost for 10 nos.
MATERIAL :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
CARRIAGE :
Carriage of material L.S. 1.00
LABOUR :
Carpenter 1st class each 0.06000 211.16 12.66
TOTAL : 273.66
ADD FOR CONTRACTORS PROFIT 10% 27.37
ADD FOR OVER HEAD CHARGES @5% 13.68
COST FOR 10.00 nos 314.71
COST PER no. 30.50
LABOUR PER no. 1.45
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 12.66
TOTAL : 12.66
ADD FOR CONTRACTORS PROFIT @10% : 1.27
ADD FOR OVER HEAD CHARGES @5% : 0.63
LABOUR FOR 10.00 no. 14.56
LABOUR PER no. 1.45
1210602000 100 mm
Details of cost for 10 nos.
MATERIAL :
CARRIAGE :
Carriage of material L.S. 1.00
LABOUR :
Carpenter 1st class each 0.06000 211.16 12.66
TOTAL : 223.66
ADD FOR CONTRACTORS PROFIT 10% 22.37
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR OVER HEAD CHARGES @5% 11.18
COST FOR 10.00 nos 257.21
COST PER No. 25.70
LABOUR PER no. 1.45
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 12.66
TOTAL : 12.66
ADD FOR CONTRACTORS PROFIT @10% : 1.27
ADD FOR OVER HEAD CHARGES @5% : 0.63
LABOUR FOR 10.00 no. 14.56
LABOUR PER no. 1.45
1210603000 75 mm
Details of cost for 10 nos.
MATERIAL :
CARRIAGE :
Carriage of material L.S. 1.00
LABOUR :
Carpenter 1st class each 0.06000 211.16 12.66
TOTAL : 203.66
ADD FOR CONTRACTORS PROFIT 10% 20.37
ADD FOR OVER HEAD CHARGES @5% 10.18
COST FOR 10.00 nos 234.21
COST PER no. 23.40
LABOUR PER no. 1.45
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 12.66
TOTAL : 12.66
ADD FOR CONTRACTORS PROFIT @10% : 1.27
ADD FOR OVER HEAD CHARGES @5% : 0.63
LABOUR FOR 10.00 no. 14.56
LABOUR PER no. 1.45
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
1210700000 Providing and fixing anodized aluminium for
light pivot with necessary screws.
Details of cost for 10 nos.
MATERIAL :
CARRIAGE :
Carriage of material L.S. 1.00
LABOUR :
Carpenter 1st class each 0.07000 211.16 14.78
TOTAL : 181.78
ADD FOR CONTRACTORS PROFIT 10% 18.18
ADD FOR OVER HEAD CHARGES @5% 9.09
COST FOR 10.00 nos 209.05
COST PER no. 20.90
LABOUR PER no. 1.70
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 14.78
TOTAL : 14.78
ADD FOR CONTRACTORS PROFIT @10% : 1.48
ADD FOR OVER HEAD CHARGES @5% : 0.74
LABOUR FOR 10.00 no. 17.00
LABOUR PER no. 1.70
MATERIAL :
CARRIAGE :
Carriage of material L.S. 1.00
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR :
Carpenter 1st class each 0.07000 211.16 14.78
TOTAL : 275.78
ADD FOR CONTRACTORS PROFIT 10% 27.58
ADD FOR OVER HEAD CHARGES @5% 13.79
COST FOR 10.00 nos 317.15
COST PER no. 31.70
LABOUR PER no. 1.70
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 14.78
TOTAL : 14.78
ADD FOR CONTRACTORS PROFIT @10% : 1.48
ADD FOR OVER HEAD CHARGES @5% : 0.74
LABOUR FOR 10.00 no. 17.00
LABOUR PER no. 1.70
MATERIAL :
CARRIAGE :
Carriage of material L.S. 1.00
LABOUR :
Carpenter 1st class each 0.10000 211.16 21.11
TOTAL : 282.11
ADD FOR CONTRACTORS PROFIT 10% 28.21
ADD FOR OVER HEAD CHARGES @5% 14.11
COST FOR 10.00 nos 324.43
COST PER no. 32.40
LABOUR PER no. 2.40
LABOUR RATE :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ACTUAL LABOUR+SUNDRIES 21.11
TOTAL : 21.11
ADD FOR CONTRACTORS PROFIT @10% : 2.11
ADD FOR OVER HEAD CHARGES @5% : 1.06
LABOUR FOR 10.00 no. 24.28
LABOUR PER no. 2.40
1211001000 300x16 mm
Details of cost for 10 Nos.
MATERIAL :
CARRIAGE :
Carriage of material L.S. 2.00
LABOUR :
Carpenter 1st class each 0.40000 211.16 84.46
SUNDRIES : 2.00
TOTAL : 5088.46
ADD FOR CONTRACTORS PROFIT 10% 508.85
ADD FOR OVER HEAD CHARGES @5% 254.42
COST FOR 10.00 nos 5851.73
COST PER no. 585.15
LABOUR PER no. 9.95
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 86.46
TOTAL : 86.46
ADD FOR CONTRACTORS PROFIT @10% : 8.65
ADD FOR OVER HEAD CHARGES @5% : 4.32
LABOUR FOR 10.00 no. 99.43
LABOUR PER no. 9.95
1211002000 200X16mm
Details of cost for 10 Nos.
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
CARRIAGE :
Carriage of material L.S. 2.00
LABOUR :
Carpenter 1st class each 0.40000 211.16 84.46
SUNDRIES : 2.00
TOTAL : 4088.46
ADD FOR CONTRACTORS PROFIT 10% 408.85
ADD FOR OVER HEAD CHARGES @5% 204.42
COST FOR 10.00 nos 4701.73
COST PER no. 470.15
LABOUR PER no. 9.95
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 86.46
TOTAL : 86.46
ADD FOR CONTRACTORS PROFIT @10% : 8.65
ADD FOR OVER HEAD CHARGES @5% : 4.32
LABOUR FOR 10.00 no. 99.43
LABOUR PER no. 9.95
1211101000 250x10 mm
Details of cost for 10 Nos.
MATERIAL :
CARRIAGE :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
carriage of material L.S. 2.50
LABOUR :
TOTAL : 2113.62
ADD FOR CONTRACTORS PROFIT 10% 211.36
ADD FOR OVER HEAD CHARGES @5% 105.68
COST FOR 10.00 Nos. 2430.66
COST PER No. 243.10
LABOUR PER No 2.40
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 21.12
TOTAL : 21.12
ADD FOR CONTRACTORS PROFIT @10% : 2.11
ADD FOR OVER HEAD CHARGES @5% : 1.06
LABOUR FOR 10 nos. 24.28
LABOUR PER no. 2.40
1211102000 200x10 mm
Details of cost for 10 Nos.
MATERIAL :
CARRIAGE :
LABOUR :
TOTAL : 1995.62
ADD FOR CONTRACTORS PROFIT 10% 199.56
ADD FOR OVER HEAD CHARGES @5% 99.78
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
COST FOR 10.00 Nos. 2294.96
COST PER No. 229.50
LABOUR PER No. 2.40
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 21.12
TOTAL : 21.12
ADD FOR CONTRACTORS PROFIT @10% : 2.11
ADD FOR OVER HEAD CHARGES @5% : 1.06
LABOUR FOR 10 nos. 24.28
LABOUR PER no. 2.40
1211103000 150x10 mm
Details of cost for 10 Nos.
MATERIAL :
CARRIAGE :
LABOUR :
TOTAL : 1472.39
ADD FOR CONTRACTORS PROFIT 10% 147.24
ADD FOR OVER HEAD CHARGES @5% 73.62
COST FOR 10.00 Nos. 1693.25
COST PER No. 169.30
LABOUR PER No 1.95
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 16.89
TOTAL : 16.89
ADD FOR CONTRACTORS PROFIT @10% : 1.69
ADD FOR OVER HEAD CHARGES @5% : 0.84
LABOUR FOR 10 nos. 19.43
LABOUR PER no. 1.95
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
1211104000 100x10 mm
Details of cost for 10 Nos.
MATERIAL :
CARRIAGE :
LABOUR :
TOTAL : 1022.39
ADD FOR CONTRACTORS PROFIT 10% 102.24
ADD FOR OVER HEAD CHARGES @5% 51.12
COST FOR 10.00 Nos. 1175.75
COST PER No. 117.60
LABOUR PER No 1.95
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 16.89
TOTAL : 16.89
ADD FOR CONTRACTORS PROFIT @10% : 1.69
ADD FOR OVER HEAD CHARGES @5% : 0.84
LABOUR FOR 10 nos. 19.43
LABOUR PER no. 1.95
1211201000 250mm
Details of cost for 10 Nos.
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
CARRIAGE :
LABOUR :
TOTAL : 1848.23
ADD FOR CONTRACTORS PROFIT 10% 184.82
ADD FOR OVER HEAD CHARGES @5% 92.41
COST FOR 10.00 Nos. 2125.47
COST PER No. 212.55
LABOUR PER No 4.85
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 42.23
TOTAL : 42.23
ADD FOR CONTRACTORS PROFIT @10% : 4.22
ADD FOR OVER HEAD CHARGES @5% : 2.11
LABOUR FOR 10 nos. 48.57
LABOUR PER no. 4.85
1211202000 150mm
Details of cost for 10 Nos.
MATERIAL :
LABOUR :
TOTAL : 1191.40
ADD FOR CONTRACTORS PROFIT 10% 119.14
ADD FOR OVER HEAD CHARGES @5% 59.57
COST FOR 10.00 Nos. 1370.11
COST PER No. 137.00
LABOUR PER No 4.10
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 35.90
TOTAL : 35.90
ADD FOR CONTRACTORS PROFIT @10% : 3.59
ADD FOR OVER HEAD CHARGES @5% : 1.79
LABOUR FOR 10 nos. 41.28
LABOUR PER no. 4.10
1211203000 100 mm
Details of cost for 10 Nos.
MATERIAL :
CARRIAGE :
LABOUR :
TOTAL : 991.40
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR CONTRACTORS PROFIT 10% 99.14
ADD FOR OVER HEAD CHARGES @5% 49.57
COST FOR 10.00 Nos. 1140.11
COST PER No. 114.00
LABOUR PER No 4.10
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 35.90
TOTAL : 35.90
ADD FOR CONTRACTORS PROFIT @10% : 3.59
ADD FOR OVER HEAD CHARGES @5% : 1.79
LABOUR FOR 10 nos. 41.28
LABOUR PER no. 4.10
1211301000 125mm
Details of cost for 10 Nos.
MATERIAL :
CARRIAGE :
LABOUR :
TOTAL : 1350.17
ADD FOR CONTRACTORS PROFIT 10% 135.02
ADD FOR OVER HEAD CHARGES @5% 67.51
COST FOR 10.00 Nos. 1552.70
COST PER No. 155.25
LABOUR PER No 1.45
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 12.67
TOTAL : 12.67
ADD FOR CONTRACTORS PROFIT @10% : 1.27
ADD FOR OVER HEAD CHARGES @5% : 0.63
LABOUR FOR 10 nos. 14.57
LABOUR PER no. 1.45
MATERIAL :
CARRIAGE :
LABOUR :
TOTAL : 1049.67
ADD FOR CONTRACTORS PROFIT 10% 104.97
ADD FOR OVER HEAD CHARGES @5% 52.48
COST FOR 10.00 Nos. 1207.12
COST PER No. 120.70
LABOUR PER No 1.45
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 12.67
TOTAL : 12.67
ADD FOR CONTRACTORS PROFIT @10% : 1.27
ADD FOR OVER HEAD CHARGES @5% : 0.63
LABOUR FOR 10 nos. 14.57
LABOUR PER no. 1.45
1211303000 75 mm
Details of cost for 10 Nos.
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
CARRIAGE :
LABOUR :
TOTAL : 799.67
ADD FOR CONTRACTORS PROFIT 10% 79.97
ADD FOR OVER HEAD CHARGES @5% 39.98
COST FOR 10.00 Nos. 919.62
COST PER No. 91.95
LABOUR PER No 1.45
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 12.67
TOTAL : 12.67
ADD FOR CONTRACTORS PROFIT @10% : 1.27
ADD FOR OVER HEAD CHARGES @5% : 0.63
LABOUR FOR 10 nos. 14.57
LABOUR PER no. 1.45
MATERIAL :
CARRIAGE :
LABOUR :
TOTAL : 349.67
ADD FOR CONTRACTORS PROFIT 10% 34.97
ADD FOR OVER HEAD CHARGES @5% 17.48
COST FOR 10.00 Nos. 402.12
COST PER No. 40.20
LABOUR PER No 1.45
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 12.67
TOTAL : 12.67
ADD FOR CONTRACTORS PROFIT @10% : 1.27
ADD FOR OVER HEAD CHARGES @5% : 0.63
LABOUR FOR 10 nos. 14.57
LABOUR PER no. 1.45
1211501000 300x16x5mm.
Details of cost for 10 Nos.
MATERIAL :
CARRIAGE :
LABOUR :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 1258.34
ADD FOR CONTRACTORS PROFIT 10% 125.83
ADD FOR OVER HEAD CHARGES @5% 62.92
COST FOR 10.00 Nos. 1447.09
COST PER No. 144.70
LABOUR PER No 2.90
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 25.34
TOTAL : 25.34
ADD FOR CONTRACTORS PROFIT @10% : 2.53
ADD FOR OVER HEAD CHARGES @5% : 1.27
LABOUR FOR 10 nos. 29.14
LABOUR PER no. 2.90
1211502000 250x16x5mm.
Details of cost for 10 Nos.
MATERIAL :
CARRIAGE :
LABOUR :
TOTAL : 1208.34
ADD FOR CONTRACTORS PROFIT 10% 120.83
ADD FOR OVER HEAD CHARGES @5% 60.42
COST FOR 10.00 Nos. 1389.59
COST PER No. 138.95
LABOUR PER No 2.90
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 25.34
TOTAL : 25.34
ADD FOR CONTRACTORS PROFIT @10% : 2.53
ADD FOR OVER HEAD CHARGES @5% : 1.27
LABOUR FOR 10 nos. 29.14
LABOUR PER no. 2.90
MATERIAL :
CARRIAGE :
LABOUR :
TOTAL : 577.90
ADD FOR CONTRACTORS PROFIT 10% 57.79
ADD FOR OVER HEAD CHARGES @5% 28.89
COST FOR 1.00 nos 664.58
COST PER No. 664.60
LABOUR PER No 41.30
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 35.90
TOTAL : 35.90
ADD FOR CONTRACTORS PROFIT @10% : 3.59
ADD FOR OVER HEAD CHARGES @5% : 1.79
LABOUR FOR 1.000 nos. 41.28
LABOUR PER no. 41.30
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
CARRIAGE :
LABOUR :
TOTAL : 537.90
ADD FOR CONTRACTORS PROFIT 10% 53.79
ADD FOR OVER HEAD CHARGES @5% 26.89
COST FOR 1.00 nos 618.58
COST PER No. 618.60
LABOUR PER No 41.30
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 35.90
TOTAL : 35.90
ADD FOR CONTRACTORS PROFIT @10% : 3.59
ADD FOR OVER HEAD CHARGES @5% : 1.79
LABOUR FOR 1.000 nos. 41.28
LABOUR PER no. 41.30
MATERIAL :
CARRIAGE :
LABOUR :
TOTAL : 557.90
ADD FOR CONTRACTORS PROFIT 10% 55.79
ADD FOR OVER HEAD CHARGES @5% 27.89
COST FOR 1.00 nos 641.58
COST PER No. 641.60
LABOUR PER No 41.30
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 35.90
TOTAL : 35.90
ADD FOR CONTRACTORS PROFIT @10% : 3.59
ADD FOR OVER HEAD CHARGES @5% : 1.79
LABOUR FOR 1.000 nos. 41.28
LABOUR PER no. 41.30
MATERIAL :
CARRIAGE :
TOTAL : 387.90
ADD FOR CONTRACTORS PROFIT 10% 38.79
ADD FOR OVER HEAD CHARGES @5% 19.39
COST FOR 1.00 nos 446.08
COST PER No. 446.10
LABOUR PER No 41.30
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 35.90
TOTAL : 35.90
ADD FOR CONTRACTORS PROFIT @10% : 3.59
ADD FOR OVER HEAD CHARGES @5% : 1.79
LABOUR FOR 1.000 nos. 41.28
LABOUR PER no. 41.30
MATERIAL :
CARRIAGE :
LABOUR :
TOTAL : 330.56
ADD FOR CONTRACTORS PROFIT 10% 33.06
ADD FOR OVER HEAD CHARGES @5% 16.53
COST FOR 10.00 nos 380.15
COST PER No. 38.00
LABOUR PER No 3.40
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 29.56
TOTAL : 29.56
ADD FOR CONTRACTORS PROFIT @10% : 2.96
ADD FOR OVER HEAD CHARGES @5% : 1.48
LABOUR FOR 10.000 nos. 34.00
LABOUR PER no. 3.40
MATERIAL :
LABOUR :
SUNDRIES : 3.50
TOTAL : 1583.28
ADD FOR CONTRACTORS PROFIT 10% 158.33
ADD FOR OVER HEAD CHARGES @5% 79.16
COST FOR 10.00 nos 1820.77
COST PER No. 182.10
LABOUR PER No 2.10
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 18.28
TOTAL : 18.28
ADD FOR CONTRACTORS PROFIT @10% : 1.83
ADD FOR OVER HEAD CHARGES @5% : 0.91
LABOUR FOR 10.000 nos. 21.02
LABOUR PER no. 2.10
1212201000 300 mm
Details of cost for 10 nos.
MATERIAL :
CARRIAGE :
LABOUR :
TOTAL : 434.67
ADD FOR CONTRACTORS PROFIT 10% 43.47
ADD FOR OVER HEAD CHARGES @5% 21.73
COST FOR 10.00 nos 499.87
COST PER No. 50.00
LABOUR PER No 1.45
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 12.67
TOTAL : 12.67
ADD FOR CONTRACTORS PROFIT @10% : 1.27
ADD FOR OVER HEAD CHARGES @5% : 0.63
LABOUR FOR 10.000 nos. 14.57
LABOUR PER no. 1.45
1212202000 250 mm
Details of cost for 10 nos.
MATERIAL :
CARRIAGE :
LABOUR :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Carpenter 1st Class each 0.06000 211.16 12.67
TOTAL : 413.67
ADD FOR CONTRACTORS PROFIT 10% 41.37
ADD FOR OVER HEAD CHARGES @5% 20.68
COST FOR 10.00 nos 475.72
COST PER No. 47.60
LABOUR PER No 1.45
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 12.67
TOTAL : 12.67
ADD FOR CONTRACTORS PROFIT @10% : 1.27
ADD FOR OVER HEAD CHARGES @5% : 0.63
LABOUR FOR 10.000 nos. 14.57
LABOUR PER no. 1.45
1212203000 200 mm
Details of cost for 10 nos.
MATERIAL :
CARRIAGE :
LABOUR :
TOTAL : 393.67
ADD FOR CONTRACTORS PROFIT 10% 39.37
ADD FOR OVER HEAD CHARGES @5% 19.68
COST FOR 10.00 nos 452.72
COST PER No. 45.30
LABOUR PER No. 1.45
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 12.67
TOTAL : 12.67
ADD FOR CONTRACTORS PROFIT @10% : 1.27
ADD FOR OVER HEAD CHARGES @5% : 0.63
LABOUR FOR 10.000 nos. 14.57
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR PER no. 1.45
1212204000 150 mm
Details of cost for 10 nos.
MATERIAL :
CARRIAGE :
LABOUR :
TOTAL : 363.67
ADD FOR CONTRACTORS PROFIT 10% 36.37
ADD FOR OVER HEAD CHARGES @5% 18.18
COST FOR 10.00 nos 418.22
COST PER No. 41.80
LABOUR PER No 1.45
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 12.67
TOTAL : 12.67
ADD FOR CONTRACTORS PROFIT @10% : 1.27
ADD FOR OVER HEAD CHARGES @5% : 0.63
LABOUR FOR 10.000 nos. 14.57
LABOUR PER no. 1.45
1212205000 100 mm
Details of cost for 10 nos.
MATERIAL :
CARRIAGE :
LABOUR :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 313.67
ADD FOR CONTRACTORS PROFIT 10% 31.37
ADD FOR OVER HEAD CHARGES @5% 15.68
COST FOR 10.00 nos 360.72
COST PER No. 36.10
LABOUR PER No 1.45
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 12.67
TOTAL : 12.67
ADD FOR CONTRACTORS PROFIT @10% : 1.27
ADD FOR OVER HEAD CHARGES @5% : 0.63
LABOUR FOR 10.000 nos. 14.57
LABOUR PER no. 1.45
MATERIAL :
LABOUR :
TOTAL : 458.12
ADD FOR CONTRACTORS PROFIT 10% 45.81
ADD FOR OVER HEAD CHARGES @5% 22.91
COST FOR 10.00 nos 526.83
COST PER No. 52.70
LABOUR PER No 2.40
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 21.12
TOTAL : 21.12
ADD FOR CONTRACTORS PROFIT @10% : 2.11
ADD FOR OVER HEAD CHARGES @5% : 1.06
LABOUR FOR 10.000 nos. 24.28
LABOUR PER no. 2.40
MATERIAL :
LABOUR :
TOTAL : 1053.89
ADD FOR CONTRACTORS PROFIT 10% 105.39
ADD FOR OVER HEAD CHARGES @5% 52.69
COST FOR 10.00 nos 1211.98
COST PER No. 121.20
LABOUR PER No 1.95
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 16.89
TOTAL : 16.89
ADD FOR CONTRACTORS PROFIT @10% : 1.69
ADD FOR OVER HEAD CHARGES @5% : 0.84
LABOUR FOR 10.000 nos. 19.43
LABOUR PER no. 1.95
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
1212402000 250 mm weighing not less than 0.28 kg.
Details of cost for 10 nos.
MATERIAL :
LABOUR :
TOTAL : 853.89
ADD FOR CONTRACTORS PROFIT 10% 85.39
ADD FOR OVER HEAD CHARGES @5% 42.69
COST FOR 10.00 nos 981.98
COST PER No. 98.20
LABOUR PER No 1.95
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 16.89
TOTAL : 16.89
ADD FOR CONTRACTORS PROFIT @10% : 1.69
ADD FOR OVER HEAD CHARGES @5% : 0.84
LABOUR FOR 10.000 nos. 19.43
LABOUR PER no. 1.95
MATERIAL :
TOTAL : 753.89
ADD FOR CONTRACTORS PROFIT 10% 75.39
ADD FOR OVER HEAD CHARGES @5% 37.69
COST FOR 10.00 nos 866.98
COST PER No. 86.70
LABOUR PER No 1.95
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 16.89
TOTAL : 16.89
ADD FOR CONTRACTORS PROFIT @10% : 1.69
ADD FOR OVER HEAD CHARGES @5% : 0.84
LABOUR FOR 10.000 nos. 19.43
LABOUR PER no. 1.95
MATERIAL :
LABOUR :
TOTAL : 858.12
ADD FOR CONTRACTORS PROFIT 10% 85.81
ADD FOR OVER HEAD CHARGES @5% 42.91
COST FOR 10.00 nos 986.83
COST PER No. 98.70
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR PER No 2.40
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 21.12
TOTAL : 21.12
ADD FOR CONTRACTORS PROFIT @10% : 2.11
ADD FOR OVER HEAD CHARGES @5% : 1.06
LABOUR FOR 10.000 nos. 24.28
LABOUR PER no. 2.40
MATERIAL :
LABOUR :
TOTAL : 281.89
ADD FOR CONTRACTORS PROFIT 10% 28.19
ADD FOR OVER HEAD CHARGES @5% 14.09
COST FOR 10.00 nos 324.18
COST PER No. 32.40
LABOUR PER No 1.95
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 16.89
TOTAL : 16.89
ADD FOR CONTRACTORS PROFIT @10% : 1.69
ADD FOR OVER HEAD CHARGES @5% : 0.84
LABOUR FOR 10.000 nos. 19.43
LABOUR PER no. 1.95
MATERIAL :
LABOUR :
TOTAL : 223.28
ADD FOR CONTRACTORS PROFIT 10% 22.33
ADD FOR OVER HEAD CHARGES @5% 11.16
COST FOR 10.00 nos 256.77
COST PER No. 25.70
LABOUR PER No 1.70
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 14.78
TOTAL : 14.78
ADD FOR CONTRACTORS PROFIT @10% : 1.48
ADD FOR OVER HEAD CHARGES @5% : 0.74
LABOUR FOR 10.000 nos. 17.00
LABOUR PER no. 1.70
MATERIAL :
LABOUR :
TOTAL : 182.56
ADD FOR CONTRACTORS PROFIT 10% 18.26
ADD FOR OVER HEAD CHARGES @5% 9.13
COST FOR 10.00 nos 209.95
COST PER No. 21.00
LABOUR PER No 3.40
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 29.56
TOTAL : 29.56
ADD FOR CONTRACTORS PROFIT @10% : 2.96
ADD FOR OVER HEAD CHARGES @5% : 1.48
LABOUR FOR 10.000 nos. 34.00
LABOUR PER no. 3.40
MATERIAL :
LABOUR :
TOTAL : 308.12
ADD FOR CONTRACTORS PROFIT 10% 30.81
ADD FOR OVER HEAD CHARGES @5% 15.41
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
COST FOR 10.00 nos 354.33
COST PER No. 35.40
LABOUR PER No 2.40
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 21.12
TOTAL : 21.12
ADD FOR CONTRACTORS PROFIT @10% : 2.11
ADD FOR OVER HEAD CHARGES @5% : 1.06
LABOUR FOR 10.000 nos. 24.28
LABOUR PER no. 2.40
1213001000 150 mm
Details of cost for 10 Nos.
MATERIAL :
LABOUR :
TOTAL : 839.89
ADD FOR CONTRACTORS PROFIT 10% 83.99
ADD FOR OVER HEAD CHARGES @5% 41.99
COST FOR 10.00 nos 965.88
COST PER No. 96.60
LABOUR PER No 1.95
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 16.89
TOTAL : 16.89
ADD FOR CONTRACTORS PROFIT @10% : 1.69
ADD FOR OVER HEAD CHARGES @5% : 0.84
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR FOR 10.000 nos. 19.43
LABOUR PER no. 1.95
1213002000 115 mm
Details of cost for 10 Nos.
MATERIAL :
LABOUR :
TOTAL : 520.39
ADD FOR CONTRACTORS PROFIT 10% 52.04
ADD FOR OVER HEAD CHARGES @5% 26.02
COST FOR 10.00 nos 598.45
COST PER No. 59.85
LABOUR PER No 1.95
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 16.89
TOTAL : 16.89
ADD FOR CONTRACTORS PROFIT @10% : 1.69
ADD FOR OVER HEAD CHARGES @5% : 0.84
LABOUR FOR 10.000 nos. 19.43
LABOUR PER no. 1.95
1213003000 90 mm
Details of cost for 10 Nos.
MATERIAL :
LABOUR :
TOTAL : 470.39
ADD FOR CONTRACTORS PROFIT 10% 47.04
ADD FOR OVER HEAD CHARGES @5% 23.52
COST FOR 10.00 nos 540.95
COST PER No. 54.10
LABOUR PER No 1.95
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 16.89
TOTAL : 16.89
ADD FOR CONTRACTORS PROFIT @10% : 1.69
ADD FOR OVER HEAD CHARGES @5% : 0.84
LABOUR FOR 10.000 nos. 19.43
LABOUR PER no. 1.95
MATERIAL :
CARRIAGE :
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 36.90
TOTAL : 36.90
ADD FOR CONTRACTORS PROFIT @10% : 3.69
ADD FOR OVER HEAD CHARGES @5% : 1.84
LABOUR FOR 1 cup board 42.43
LABOUR PER cub board 42.40
MATERIAL :
LABOUR :
TOTAL : 974.51
ADD FOR CONTRACTORS PROFIT 10% 97.45
ADD FOR OVER HEAD CHARGES @5% 48.73
COST FOR 10.00 nos 1120.69
COST PER No. 112.05
LABOUR PER No 2.35
LABOUR RATE :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ACTUAL LABOUR+SUNDRIES 20.61
TOTAL : 20.61
ADD FOR CONTRACTORS PROFIT @10% : 2.06
ADD FOR OVER HEAD CHARGES @5% : 1.03
LABOUR FOR 10.000 nos. 23.71
LABOUR PER no. 2.35
MATERIAL :
LABOUR :
TOTAL : 3074.61
ADD FOR CONTRACTORS PROFIT 10% 307.46
ADD FOR OVER HEAD CHARGES @5% 153.73
COST FOR 10.00 nos 3535.81
COST PER No. 353.60
LABOUR PER No 2.35
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 20.61
TOTAL : 20.61
ADD FOR CONTRACTORS PROFIT @10% : 2.06
ADD FOR OVER HEAD CHARGES @5% : 1.03
LABOUR FOR 10.000 nos. 23.71
LABOUR PER no. 2.35
1213401000 300x16mm.
Details of cost for 10 Nos.
MATERIAL :
CARRIAGE :
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 86.46
TOTAL : 86.46
ADD FOR CONTRACTORS PROFIT @10% : 8.65
ADD FOR OVER HEAD CHARGES @5% : 4.32
LABOUR FOR 10.000 nos. 99.43
LABOUR PER no. 9.95
1213402000 250x16mm.
Details of cost for 10 Nos.
MATERIAL :
CARRIAGE :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
carriage of material L.S. 2.00
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 86.46
TOTAL : 86.46
ADD FOR CONTRACTORS PROFIT @10% : 8.65
ADD FOR OVER HEAD CHARGES @5% : 4.32
LABOUR FOR 10.000 nos. 99.43
LABOUR PER no. 9.95
MATERIAL :
CARRIAGE :
LABOUR :
TOTAL : 537.90
ADD FOR CONTRACTORS PROFIT 10% 53.79
ADD FOR OVER HEAD CHARGES @5% 26.89
COST FOR 1.00 nos 618.58
COST PER No. 618.60
LABOUR PER No 41.30
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 35.90
TOTAL : 35.90
ADD FOR CONTRACTORS PROFIT @10% : 3.59
ADD FOR OVER HEAD CHARGES @5% : 1.79
LABOUR FOR 1.000 nos. 41.28
LABOUR PER no. 41.30
MATERIAL :
CARRIAGE :
LABOUR :
TOTAL : 487.90
ADD FOR CONTRACTORS PROFIT 10% 48.79
ADD FOR OVER HEAD CHARGES @5% 24.39
COST FOR 1.00 nos 561.08
COST PER No. 561.10
LABOUR PER No 41.30
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 35.90
TOTAL : 35.90
ADD FOR CONTRACTORS PROFIT @10% : 3.59
ADD FOR OVER HEAD CHARGES @5% : 1.79
LABOUR FOR 1.000 nos. 41.28
LABOUR PER no. 41.30
MATERIAL :
CARRIAGE :
LABOUR :
TOTAL : 437.90
ADD FOR CONTRACTORS PROFIT 10% 43.79
ADD FOR OVER HEAD CHARGES @5% 21.89
COST FOR 1.00 nos 503.58
COST PER No. 503.60
LABOUR PER No 41.30
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 35.90
TOTAL : 35.90
ADD FOR CONTRACTORS PROFIT @10% : 3.59
ADD FOR OVER HEAD CHARGES @5% : 1.79
LABOUR FOR 1.000 nos. 41.28
LABOUR PER no. 41.30
MATERIAL :
CARRIAGE :
TOTAL : 330.56
ADD FOR CONTRACTORS PROFIT 10% 33.06
ADD FOR OVER HEAD CHARGES @5% 16.53
COST FOR 10.00 nos 380.15
COST PER No. 38.00
LABOUR PER No 3.40
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 29.56
TOTAL : 29.56
ADD FOR CONTRACTORS PROFIT @10% : 2.96
ADD FOR OVER HEAD CHARGES @5% : 1.48
LABOUR FOR 10.000 nos. 34.00
LABOUR PER no. 3.40
MATERIAL :
CARRIAGE :
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 30.56
TOTAL : 30.56
ADD FOR CONTRACTORS PROFIT @10% : 3.06
ADD FOR OVER HEAD CHARGES @5% : 1.53
LABOUR FOR 1.000 nos. 35.14
LABOUR PER no. 35.15
1214001000 125x65x2.12mm
Details of cost for ten No.
MATERIAL :
LABOUR :
Carpenter 2nd Class each 0.14000 186.67 26.13
Beldar each 0.09000 116.67 10.50
TOTAL : 220.63
ADD FOR CONTRACTORS PROFIT 10% 22.06
ADD FOR OVER HEAD CHARGES @5% 11.03
COST FOR 10.00 nos 253.72
COST PER No. 25.40
LABOUR PER No 4.20
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 36.63
TOTAL : 36.63
ADD FOR CONTRACTORS PROFIT @10% : 3.66
ADD FOR OVER HEAD CHARGES @5% : 1.83
LABOUR FOR 10.000 nos. 42.12
LABOUR PER no. 4.21
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
1214002000 100x58x1.90mm
Details of cost for ten Nos.
MATERIAL :
LABOUR :
Carpenter 2nd Class each 0.14000 186.67 26.13
Beldar each 0.09000 116.67 10.50
TOTAL : 182.63
ADD FOR CONTRACTORS PROFIT 10% 18.26
ADD FOR OVER HEAD CHARGES @5% 9.13
COST FOR 10.00 nos 210.02
COST PER No. 21.00
LABOUR PER No 4.20
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 36.63
TOTAL : 36.63
ADD FOR CONTRACTORS PROFIT @10% : 3.66
ADD FOR OVER HEAD CHARGES @5% : 1.83
LABOUR FOR 10.000 nos. 42.12
LABOUR PER no. 4.20
1214003000 75x47x1.70mm
Details of cost for ten Nos.
MATERIAL :
LABOUR :
Carpenter 2nd Class each 0.14000 186.67 26.13
Beldar each 0.09000 116.67 10.50
TOTAL : 152.63
ADD FOR CONTRACTORS PROFIT 10% 15.26
ADD FOR OVER HEAD CHARGES @5% 7.63
COST FOR 10.00 nos 175.52
COST PER No. 17.55
LABOUR PER No 4.20
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 36.63
TOTAL : 36.63
ADD FOR CONTRACTORS PROFIT @10% : 3.66
ADD FOR OVER HEAD CHARGES @5% : 1.83
LABOUR FOR 10.000 nos. 42.12
LABOUR PER no. 4.20
1214004000 50x37x1.50mm
Details of cost for ten Nos.
MATERIAL :
LABOUR :
TOTAL : 73.93
ADD FOR CONTRACTORS PROFIT 10% 7.39
ADD FOR OVER HEAD CHARGES @5% 3.70
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
COST FOR 10.00 nos 85.02
COST PER No. 8.50
LABOUR PER No. 1.70
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 14.93
TOTAL : 14.93
ADD FOR CONTRACTORS PROFIT @10% : 1.49
ADD FOR OVER HEAD CHARGES @5% : 0.75
LABOUR FOR 10.000 nos. 17.17
LABOUR PER no. 1.70
1214101000 150x125x27x2.80mm
Details of cost for 10 Nos.
MATERIAL :
LABOUR :
TOTAL : 471.47
ADD FOR CONTRACTORS PROFIT 10% 47.15
ADD FOR OVER HEAD CHARGES @5% 23.57
COST FOR 10.00 nos 542.19
COST PER No. 54.20
LABOUR PER No 4.90
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 42.47
TOTAL : 42.47
ADD FOR CONTRACTORS PROFIT @10% : 4.25
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR OVER HEAD CHARGES @5% : 2.12
LABOUR FOR 10.000 nos. 48.84
LABOUR PER no. 4.90
1214102000 125x125x27x2.80mm
Details of cost for 10 Nos.
MATERIAL :
LABOUR :
TOTAL : 367.47
ADD FOR CONTRACTORS PROFIT 10% 36.75
ADD FOR OVER HEAD CHARGES @5% 18.37
COST FOR 10.00 nos 422.59
COST PER No. 42.25
LABOUR PER No 4.90
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 42.47
TOTAL : 42.47
ADD FOR CONTRACTORS PROFIT @10% : 4.25
ADD FOR OVER HEAD CHARGES @5% : 2.12
LABOUR FOR 10.000 nos. 48.84
LABOUR PER no. 4.90
1214103000 100x125x27x2.80mm
Details of cost for 10 Nos.
MATERIAL :
LABOUR :
TOTAL : 317.47
ADD FOR CONTRACTORS PROFIT 10% 31.75
ADD FOR OVER HEAD CHARGES @5% 15.87
COST FOR 10.00 nos 365.09
COST PER No. 36.50
LABOUR PER No 4.90
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 42.47
TOTAL : 42.47
ADD FOR CONTRACTORS PROFIT @10% : 4.25
ADD FOR OVER HEAD CHARGES @5% : 2.12
LABOUR FOR 10.000 nos. 48.84
LABOUR PER no. 4.90
1214104000 75x100x20x2.40mm
Details of cost for 10 Nos.
MATERIAL :
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 42.47
TOTAL : 42.47
ADD FOR CONTRACTORS PROFIT @10% : 4.25
ADD FOR OVER HEAD CHARGES @5% : 2.12
LABOUR FOR 10.000 nos. 48.84
LABOUR PER no. 4.90
1214201000 150mm
Details of cost for 10 Nos.
MATERIAL :
LABOUR :
TOTAL : 981.00
ADD FOR CONTRACTORS PROFIT 10% 98.10
ADD FOR OVER HEAD CHARGES @5% 49.05
COST FOR 10.00 nos 1128.15
COST PER No. 112.80
LABOUR PER No 11.25
LABOUR RATE :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ACTUAL LABOUR+SUNDRIES 98.00
TOTAL : 98.00
ADD FOR CONTRACTORS PROFIT @10% : 9.80
ADD FOR OVER HEAD CHARGES @5% : 4.90
LABOUR FOR 10.000 nos. 112.70
LABOUR PER no. 11.25
1214202000 125mm
Details of cost for 10 Nos.
MATERIAL :
LABOUR :
TOTAL : 931.00
ADD FOR CONTRACTORS PROFIT 10% 93.10
ADD FOR OVER HEAD CHARGES @5% 46.55
COST FOR 10.00 nos 1070.65
COST PER No. 107.05
LABOUR PER No 11.25
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 98.00
TOTAL : 98.00
ADD FOR CONTRACTORS PROFIT @10% : 9.80
ADD FOR OVER HEAD CHARGES @5% : 4.90
LABOUR FOR 10.000 nos. 112.70
LABOUR PER no. 11.25
1214203000 100mm
Details of cost for 10 Nos.
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
LABOUR :
TOTAL : 706.00
ADD FOR CONTRACTORS PROFIT 10% 70.60
ADD FOR OVER HEAD CHARGES @5% 35.30
COST FOR 10.00 nos 811.90
COST PER No. 81.20
LABOUR PER No. 11.25
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 98.00
TOTAL : 98.00
ADD FOR CONTRACTORS PROFIT @10% : 9.80
ADD FOR OVER HEAD CHARGES @5% : 4.90
LABOUR FOR 10.000 nos. 112.70
LABOUR PER no. 11.25
1214301000 150mm
Details of cost for 10 Nos.
MATERIAL :
LABOUR :
TOTAL : 1931.00
ADD FOR CONTRACTORS PROFIT 10% 193.10
ADD FOR OVER HEAD CHARGES @5% 96.55
COST FOR 10.00 nos 2220.65
COST PER No. 222.05
LABOUR PER No. 11.25
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 98.00
TOTAL : 98.00
ADD FOR CONTRACTORS PROFIT @10% : 9.80
ADD FOR OVER HEAD CHARGES @5% : 4.90
LABOUR FOR 10.000 nos. 112.70
LABOUR PER no. 11.25
1214301000 125mm
Details of cost for 10 Nos.
MATERIAL :
LABOUR :
TOTAL : 1631.00
ADD FOR CONTRACTORS PROFIT 10% 163.10
ADD FOR OVER HEAD CHARGES @5% 81.55
COST FOR 10.00 nos 1875.65
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
COST PER No. 187.55
LABOUR PER No. 11.25
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 98.00
TOTAL : 98.00
ADD FOR CONTRACTORS PROFIT @10% : 9.80
ADD FOR OVER HEAD CHARGES @5% : 4.90
LABOUR FOR 10.000 nos. 112.70
LABOUR PER no. 11.25
1214303000 100mm
Details of cost for 10 Nos.
MATERIAL :
LABOUR :
TOTAL : 1223.00
ADD FOR CONTRACTORS PROFIT 10% 122.30
ADD FOR OVER HEAD CHARGES @5% 61.15
COST FOR 10.00 nos 1406.45
COST PER No. 140.65
LABOUR PER No. 11.25
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 98.00
TOTAL : 98.00
ADD FOR CONTRACTORS PROFIT @10% : 9.80
ADD FOR OVER HEAD CHARGES @5% : 4.90
LABOUR FOR 10.000 nos. 112.70
LABOUR PER no. 11.25
1214401000 300x115x2.24mm
Details of cost for 10 Nos.
MATERIAL :
LABOUR :
TOTAL : 328.67
ADD FOR CONTRACTORS PROFIT 10% 32.87
ADD FOR OVER HEAD CHARGES @5% 16.43
COST FOR 10.00 nos 377.97
COST PER No. 37.80
LABOUR PER No. 6.15
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 53.67
TOTAL : 53.67
ADD FOR CONTRACTORS PROFIT @10% : 5.37
ADD FOR OVER HEAD CHARGES @5% : 2.68
LABOUR FOR 10.000 nos. 61.72
LABOUR PER no. 6.15
MATERIAL :
LABOUR :
TOTAL : 278.67
ADD FOR CONTRACTORS PROFIT 10% 27.87
ADD FOR OVER HEAD CHARGES @5% 13.93
COST FOR 10.00 nos 320.47
COST PER No. 32.05
LABOUR PER No. 6.15
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 53.67
TOTAL : 53.67
ADD FOR CONTRACTORS PROFIT @10% : 5.37
ADD FOR OVER HEAD CHARGES @5% : 2.68
LABOUR FOR 10.000 nos. 61.72
LABOUR PER no. 6.15
1214501000 300x16mm
MATERIAL :
LABOUR :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Carpenter 2nd class each 0.25000 186.67 46.67
TOTAL : 613.67
ADD FOR CONTRACTORS PROFIT 10% 61.37
ADD FOR OVER HEAD CHARGES @5% 30.68
COST FOR 10.00 nos 705.72
COST PER No. 70.60
LABOUR PER No. 5.35
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 46.67
TOTAL : 46.67
ADD FOR CONTRACTORS PROFIT @10% : 4.67
ADD FOR OVER HEAD CHARGES @5% : 2.33
LABOUR FOR 10.000 nos. 53.67
LABOUR PER no. 5.35
1214502000 250x16 mm
Details of cost for 10 Nos.
MATERIAL :
LABOUR :
TOTAL : 563.67
ADD FOR CONTRACTORS PROFIT 10% 56.37
ADD FOR OVER HEAD CHARGES @5% 28.18
COST FOR 10.00 nos 648.22
COST PER No. 64.80
LABOUR PER No. 5.35
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 46.67
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 46.67
ADD FOR CONTRACTORS PROFIT @10% : 4.67
ADD FOR OVER HEAD CHARGES @5% : 2.33
LABOUR FOR 10.000 nos. 53.67
LABOUR PER no. 5.35
1214601000 300x20x6mm
Details of cost for ten Nos.
MATERIAL :
LABOUR :
TOTAL : 396.90
ADD FOR CONTRACTORS PROFIT 10% 39.69
ADD FOR OVER HEAD CHARGES @5% 19.85
COST FOR 10.00 nos 456.44
COST PER No. 45.65
LABOUR PER No. 2.60
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 22.40
TOTAL : 22.40
ADD FOR CONTRACTORS PROFIT @10% : 2.24
ADD FOR OVER HEAD CHARGES @5% : 1.12
LABOUR FOR 10.000 nos. 25.76
LABOUR PER no. 2.60
1214602000 250x20x6 mm
Details of cost for ten Nos.
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
LABOUR :
TOTAL : 346.90
ADD FOR CONTRACTORS PROFIT 10% 34.69
ADD FOR OVER HEAD CHARGES @5% 17.35
COST FOR 10.00 nos 398.94
COST PER No. 39.90
LABOUR PER No. 2.60
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 22.40
TOTAL : 22.40
ADD FOR CONTRACTORS PROFIT @10% : 2.24
ADD FOR OVER HEAD CHARGES @5% : 1.12
LABOUR FOR 10.000 nos. 25.76
LABOUR PER no. 2.60
1214701000 250x10 mm
Details of cost for 10 Nos.
MATERIAL :
LABOUR :
TOTAL : 345.67
ADD FOR CONTRACTORS PROFIT 10% 34.57
ADD FOR OVER HEAD CHARGES @5% 17.28
COST FOR 10.00 nos 397.52
COST PER No. 39.75
LABOUR PER No. 2.15
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 18.67
TOTAL : 18.67
ADD FOR CONTRACTORS PROFIT @10% : 1.87
ADD FOR OVER HEAD CHARGES @5% : 0.93
LABOUR FOR 10.000 nos. 21.47
LABOUR PER no. 2.15
1214702000 200x10 mm
Details of cost for 10 Nos.
MATERIAL :
LABOUR :
TOTAL : 290.67
ADD FOR CONTRACTORS PROFIT 10% 29.07
ADD FOR OVER HEAD CHARGES @5% 14.53
COST FOR 10.00 nos 334.27
COST PER No. 33.40
LABOUR PER No. 2.15
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 18.67
TOTAL : 18.67
ADD FOR CONTRACTORS PROFIT @10% : 1.87
ADD FOR OVER HEAD CHARGES @5% : 0.93
LABOUR FOR 10.000 nos. 21.47
LABOUR PER no. 2.15
1214703000 150x10mm
Details of cost for 10 Nos.
MATERIAL :
LABOUR :
TOTAL : 235.67
ADD FOR CONTRACTORS PROFIT 10% 23.57
ADD FOR OVER HEAD CHARGES @5% 11.78
COST FOR 10.00 nos 271.02
COST PER No. 27.10
LABOUR PER No. 2.15
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 18.67
TOTAL : 18.67
ADD FOR CONTRACTORS PROFIT @10% : 1.87
ADD FOR OVER HEAD CHARGES @5% : 0.93
LABOUR FOR 10.000 nos. 21.47
LABOUR PER no. 2.15
1214704000 100x10mm
Details of cost for 10 Nos.
MATERIAL :
LABOUR :
TOTAL : 185.67
ADD FOR CONTRACTORS PROFIT 10% 18.57
ADD FOR OVER HEAD CHARGES @5% 9.28
COST FOR 10.00 nos 213.52
COST PER No. 21.35
LABOUR PER No. 2.15
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 18.67
TOTAL : 18.67
ADD FOR CONTRACTORS PROFIT @10% : 1.87
ADD FOR OVER HEAD CHARGES @5% : 0.93
LABOUR FOR 10.000 nos. 21.47
LABOUR PER no. 2.15
1214801000 125mm
Details of cost for 10 Nos.
MATERIAL :
LABOUR :
TOTAL : 122.20
ADD FOR CONTRACTORS PROFIT 10% 12.22
ADD FOR OVER HEAD CHARGES @5% 6.11
COST FOR 10.00 nos 140.53
COST PER No. 14.05
LABOUR PER No. 1.30
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 11.20
TOTAL : 11.20
ADD FOR CONTRACTORS PROFIT @10% : 1.12
ADD FOR OVER HEAD CHARGES @5% : 0.56
LABOUR FOR 10.000 nos. 12.88
LABOUR PER no. 1.30
1214802000 100mm.
Details of cost for 10 Nos.
MATERIAL :
LABOUR :
TOTAL : 122.20
ADD FOR CONTRACTORS PROFIT 10% 12.22
ADD FOR OVER HEAD CHARGES @5% 6.11
COST FOR 10.00 nos 140.53
COST PER No. 14.05
LABOUR PER No. 1.30
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 11.20
TOTAL : 11.20
ADD FOR CONTRACTORS PROFIT @10% : 1.12
ADD FOR OVER HEAD CHARGES @5% : 0.56
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR FOR 10.000 nos. 12.88
LABOUR PER no. 1.30
1214803000 75mm
Details of cost for 10 Nos.
MATERIAL :
LABOUR :
TOTAL : 102.20
ADD FOR CONTRACTORS PROFIT 10% 10.22
ADD FOR OVER HEAD CHARGES @5% 5.11
COST FOR 10.00 nos 117.53
COST PER No. 11.75
LABOUR PER No. 1.30
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 11.20
TOTAL : 11.20
ADD FOR CONTRACTORS PROFIT @10% : 1.12
ADD FOR OVER HEAD CHARGES @5% : 0.56
LABOUR FOR 10.000 nos. 12.88
LABOUR PER no. 1.30
MATERIAL :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
CARRIAGE :
LABOUR :
TOTAL : 161.70
ADD FOR CONTRACTORS PROFIT 10% 16.17
ADD FOR OVER HEAD CHARGES @5% 8.09
COST FOR 10.00 nos 185.96
COST PER No. 18.60
LABOUR PER No. 1.30
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 11.20
TOTAL : 11.20
ADD FOR CONTRACTORS PROFIT @10% : 1.12
ADD FOR OVER HEAD CHARGES @5% : 0.56
LABOUR FOR 10.000 nos. 12.88
LABOUR PER no. 1.30
1214902000 250mm
Details of cost for 10 Nos.
MATERIAL :
CARRIAGE :
LABOUR :
TOTAL : 131.70
ADD FOR CONTRACTORS PROFIT 10% 13.17
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR OVER HEAD CHARGES @5% 6.59
COST FOR 10.00 nos 151.46
COST PER No. 15.15
LABOUR PER No. 1.30
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 11.20
TOTAL : 11.20
ADD FOR CONTRACTORS PROFIT @10% : 1.12
ADD FOR OVER HEAD CHARGES @5% : 0.56
LABOUR FOR 10.000 nos. 12.88
LABOUR PER no. 1.30
1214903000 200mm
Details of cost for 10 Nos.
MATERIAL :
CARRIAGE :
LABOUR :
TOTAL : 111.70
ADD FOR CONTRACTORS PROFIT 10% 11.17
ADD FOR OVER HEAD CHARGES @5% 5.59
COST FOR 10.00 nos 128.46
COST PER No. 12.85
LABOUR PER No. 1.30
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 11.20
TOTAL : 11.20
ADD FOR CONTRACTORS PROFIT @10% : 1.12
ADD FOR OVER HEAD CHARGES @5% : 0.56
LABOUR FOR 10.000 nos. 12.88
LABOUR PER no. 1.30
1214904000 150 mm
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Details of cost for 10 Nos.
MATERIAL :
CARRIAGE :
LABOUR :
TOTAL : 91.70
ADD FOR CONTRACTORS PROFIT 10% 9.17
ADD FOR OVER HEAD CHARGES @5% 4.59
COST FOR 10.00 nos 105.46
COST PER No. 10.55
LABOUR PER No. 1.30
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 11.20
TOTAL : 11.20
ADD FOR CONTRACTORS PROFIT @10% : 1.12
ADD FOR OVER HEAD CHARGES @5% : 0.56
LABOUR FOR 10.000 nos. 12.88
LABOUR PER no. 1.30
1214905000 100mm
Details of cost for 10 Nos.
MATERIAL :
CARRIAGE :
LABOUR :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Carpenter 2nd class each 0.06000 186.67 11.20
TOTAL : 81.70
ADD FOR CONTRACTORS PROFIT 10% 8.17
ADD FOR OVER HEAD CHARGES @5% 4.09
COST FOR 10.00 nos 93.96
COST PER No. 9.40
LABOUR PER No. 1.30
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 11.20
TOTAL : 11.20
ADD FOR CONTRACTORS PROFIT @10% : 1.12
ADD FOR OVER HEAD CHARGES @5% : 0.56
LABOUR FOR 10.000 nos. 12.88
LABOUR PER no. 1.30
MATERIAL :
LABOUR :
TOTAL : 125.57
ADD FOR CONTRACTORS PROFIT 10% 12.56
ADD FOR OVER HEAD CHARGES @5% 6.28
COST FOR 10.00 nos 144.40
COST PER No. 14.45
LABOUR PER No. 1.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 13.07
TOTAL : 13.07
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR CONTRACTORS PROFIT @10% : 1.31
ADD FOR OVER HEAD CHARGES @5% : 0.65
LABOUR FOR 10.000 nos. 15.03
LABOUR PER no. 1.50
MATERIAL :
LABOUR :
TOTAL : 103.57
ADD FOR CONTRACTORS PROFIT 10% 10.36
ADD FOR OVER HEAD CHARGES @5% 5.18
COST FOR 10.00 nos 119.10
COST PER No. 11.90
LABOUR PER No. 1.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 13.07
TOTAL : 13.07
ADD FOR CONTRACTORS PROFIT @10% : 1.31
ADD FOR OVER HEAD CHARGES @5% : 0.65
LABOUR FOR 10.000 nos. 15.03
LABOUR PER no. 1.50
MATERIAL :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR :
TOTAL : 129.17
ADD FOR CONTRACTORS PROFIT 10% 12.92
ADD FOR OVER HEAD CHARGES @5% 6.46
COST FOR 10.00 nos 148.54
COST PER No. 14.85
LABOUR PER No. 2.15
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 18.67
TOTAL : 18.67
ADD FOR CONTRACTORS PROFIT @10% : 1.87
ADD FOR OVER HEAD CHARGES @5% : 0.93
LABOUR FOR 10.000 nos. 21.47
LABOUR PER no. 2.15
1215301000 150mm
Details of cost for 10 Nos.
MATERIAL :
LABOUR :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 135.93
ADD FOR CONTRACTORS PROFIT 10% 13.59
ADD FOR OVER HEAD CHARGES @5% 6.80
COST FOR 10.00 nos 156.32
COST PER No. 15.60
LABOUR PER No. 1.70
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 14.93
TOTAL : 14.93
ADD FOR CONTRACTORS PROFIT @10% : 1.49
ADD FOR OVER HEAD CHARGES @5% : 0.75
LABOUR FOR 10.000 nos. 17.17
LABOUR PER no. 1.70
1215302000 115 mm
Details of cost for 10 Nos.
MATERIAL :
LABOUR :
TOTAL : 133.43
ADD FOR CONTRACTORS PROFIT 10% 13.34
ADD FOR OVER HEAD CHARGES @5% 6.67
COST FOR 10.00 nos 153.45
COST PER No. 15.35
LABOUR PER No. 1.70
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 14.93
TOTAL : 14.93
ADD FOR CONTRACTORS PROFIT @10% : 1.49
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR OVER HEAD CHARGES @5% : 0.75
LABOUR FOR 10.000 nos. 17.17
LABOUR PER no. 1.70
1215303000 90 mm
Details of cost for 10 Nos.
MATERIAL :
LABOUR :
TOTAL : 113.43
ADD FOR CONTRACTORS PROFIT 10% 11.34
ADD FOR OVER HEAD CHARGES @5% 5.67
COST FOR 10.00 nos 130.45
COST PER No. 13.05
LABOUR PER No. 1.70
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 14.93
TOTAL : 14.93
ADD FOR CONTRACTORS PROFIT @10% : 1.49
ADD FOR OVER HEAD CHARGES @5% : 0.75
LABOUR FOR 10.000 nos. 17.17
LABOUR PER no. 1.70
1215401000 125x65x2.12 mm
Details of cost for 10 Nos.
MATERIAL :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR :
TOTAL : 190.13
ADD FOR CONTRACTORS PROFIT 10% 19.01
ADD FOR OVER HEAD CHARGES @5% 9.51
COST FOR 10.00 nos 218.65
COST PER No. 21.85
LABOUR PER No. 4.20
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 36.63
TOTAL : 36.63
ADD FOR CONTRACTORS PROFIT @10% : 3.66
ADD FOR OVER HEAD CHARGES @5% : 1.83
LABOUR FOR 10.000 nos. 42.13
LABOUR PER no. 4.20
1215402000 100x58x1.90 mm
Details of cost for 10 Nos.
MATERIAL :
LABOUR :
TOTAL : 147.13
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR CONTRACTORS PROFIT 10% 14.71
ADD FOR OVER HEAD CHARGES @5% 7.36
COST FOR 10.00 nos 169.20
COST PER No. 16.90
LABOUR PER No. 4.20
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 36.63
TOTAL : 36.63
ADD FOR CONTRACTORS PROFIT @10% : 3.66
ADD FOR OVER HEAD CHARGES @5% : 1.83
LABOUR FOR 10.000 nos. 42.13
LABOUR PER no. 4.20
1215403000 75x47x1.70 mm
Details of cost for 10 Nos.
MATERIAL :
LABOUR :
TOTAL : 122.63
ADD FOR CONTRACTORS PROFIT 10% 12.26
ADD FOR OVER HEAD CHARGES @5% 6.13
COST FOR 10.00 nos 141.03
COST PER No. 14.10
LABOUR PER No. 4.20
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 36.63
TOTAL : 36.63
ADD FOR CONTRACTORS PROFIT @10% : 3.66
ADD FOR OVER HEAD CHARGES @5% : 1.83
LABOUR FOR 10.000 nos. 42.13
LABOUR PER no. 4.20
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
1215404000 50x37x1.50mm
Details of cost for 10 Nos.
MATERIAL :
LABOUR :
TOTAL : 58.93
ADD FOR CONTRACTORS PROFIT 10% 5.89
ADD FOR OVER HEAD CHARGES @5% 2.95
COST FOR 10.00 nos 67.77
COST PER No. 6.75
LABOUR PER No. 1.70
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 14.93
TOTAL : 14.93
ADD FOR CONTRACTORS PROFIT @10% : 1.49
ADD FOR OVER HEAD CHARGES @5% : 0.75
LABOUR FOR 10.000 nos. 17.17
LABOUR PER no. 1.70
1215501000 150x125x27x2.80mm.
Details of cost for 10 Nos.
MATERIAL :
LABOUR :
Carpenter 2nd class each 0.14000 186.67 26.13
Beldar each 0.14 116.67 16.33
TOTAL : 496.97
ADD FOR CONTRACTORS PROFIT 10% 49.70
ADD FOR OVER HEAD CHARGES @5% 24.85
COST FOR 10.00 nos 571.51
COST PER No. 57.15
LABOUR PER No. 4.90
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 42.47
TOTAL : 42.47
ADD FOR CONTRACTORS PROFIT @10% : 4.25
ADD FOR OVER HEAD CHARGES @5% : 2.12
LABOUR FOR 10.000 nos. 48.84
LABOUR PER no. 4.90
1215502000 125x125x27x2.80
Details of cost for 10 Nos.
MATERIAL :
LABOUR :
Carpenter 2nd class each 0.14000 186.67 26.13
Beldar each 0.14 116.67 16.33
TOTAL : 467.97
ADD FOR CONTRACTORS PROFIT 10% 46.80
ADD FOR OVER HEAD CHARGES @5% 23.40
COST FOR 10.00 nos 538.16
COST PER No. 53.80
LABOUR PER No. 4.90
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 42.47
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 42.47
ADD FOR CONTRACTORS PROFIT @10% : 4.25
ADD FOR OVER HEAD CHARGES @5% : 2.12
LABOUR FOR 10.000 nos. 48.84
LABOUR PER no. 4.90
1215503000 100x125x27x2.80
Details of cost for 10 Nos.
MATERIAL :
LABOUR :
Carpenter 2nd class each 0.14000 186.67 26.13
Beldar each 0.14 116.67 16.33
TOTAL : 367.97
ADD FOR CONTRACTORS PROFIT 10% 36.80
ADD FOR OVER HEAD CHARGES @5% 18.40
COST FOR 10.00 nos 423.16
COST PER No. 42.30
LABOUR PER No. 4.90
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 42.47
TOTAL : 42.47
ADD FOR CONTRACTORS PROFIT @10% : 4.25
ADD FOR OVER HEAD CHARGES @5% : 2.12
LABOUR FOR 10.000 nos. 48.84
LABOUR PER no. 4.90
1215504000 75x100x20x2.40
Details of cost for 10 Nos.
MATERIAL :
LABOUR :
Carpenter 2nd class each 0.14000 186.67 26.13
Beldar each 0.14 116.67 16.33
TOTAL : 278.97
ADD FOR CONTRACTORS PROFIT 10% 27.90
ADD FOR OVER HEAD CHARGES @5% 13.95
COST FOR 10.00 nos 320.81
COST PER No. 32.10
LABOUR PER No. 4.90
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 42.47
TOTAL : 42.47
ADD FOR CONTRACTORS PROFIT @10% : 4.25
ADD FOR OVER HEAD CHARGES @5% : 2.12
LABOUR FOR 10.000 nos. 48.84
LABOUR PER no. 4.90
1215601000 150mm
Details of cost for 10 Nos.
MATERIAL :
LABOUR :
Carpenter 2nd class each 0.40000 186.67 74.66
Beldar each 0.21000 116.67 23.33
TOTAL : 981.49
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR CONTRACTORS PROFIT 10% 98.15
ADD FOR OVER HEAD CHARGES @5% 49.07
COST FOR 10.00 nos 1128.71
COST PER No. 112.85
LABOUR PER No. 11.25
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 97.99
TOTAL : 97.99
ADD FOR CONTRACTORS PROFIT @10% : 9.80
ADD FOR OVER HEAD CHARGES @5% : 4.90
LABOUR FOR 10.000 nos. 112.69
LABOUR PER no. 11.25
1215602000 125 mm
Details of cost for 10 Nos.
MATERIAL :
LABOUR :
Carpenter 2nd class each 0.40000 186.67 74.66
Beldar each 0.21000 116.67 23.33
TOTAL : 931.49
ADD FOR CONTRACTORS PROFIT 10% 93.15
ADD FOR OVER HEAD CHARGES @5% 46.57
COST FOR 10.00 nos 1071.21
COST PER No. 107.10
LABOUR PER No. 11.25
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 97.99
TOTAL : 97.99
ADD FOR CONTRACTORS PROFIT @10% : 9.80
ADD FOR OVER HEAD CHARGES @5% : 4.90
LABOUR FOR 10.000 nos. 112.69
LABOUR PER no. 1.25
1215603000 100 mm
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Details of cost for 10 Nos.
MATERIAL :
LABOUR :
Carpenter 2nd class each 0.40000 186.67 74.66
Beldar each 0.20000 116.67 23.33
TOTAL : 723.49
ADD FOR CONTRACTORS PROFIT 10% 72.35
ADD FOR OVER HEAD CHARGES @5% 36.17
COST FOR 10.00 nos 832.01
COST PER No. 83.20
LABOUR PER No. 11.25
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 97.99
TOTAL : 97.99
ADD FOR CONTRACTORS PROFIT @10% : 9.80
ADD FOR OVER HEAD CHARGES @5% : 4.90
LABOUR FOR 10.000 nos. 112.69
LABOUR PER no. 11.25
1215701000 150mm
Details of cost for 10 Nos.
MATERIAL :
LABOUR :
Carpenter 2nd class each 0.40000 186.67 74.66
Beldar each 0.20000 116.67 23.33
TOTAL : 1931.49
ADD FOR CONTRACTORS PROFIT 10% 193.15
ADD FOR OVER HEAD CHARGES @5% 96.57
COST FOR 10.00 nos 2221.21
COST PER No. 222.10
LABOUR PER No. 11.25
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 97.99
TOTAL : 97.99
ADD FOR CONTRACTORS PROFIT @10% : 9.80
ADD FOR OVER HEAD CHARGES @5% : 4.90
LABOUR FOR 10.000 nos. 112.69
LABOUR PER no. 11.25
1215702000 125 mm
Details of cost for 10 Nos.
MATERIAL :
LABOUR :
Carpenter 2nd class each 0.40000 186.67 74.66
Beldar each 0.20000 116.67 23.33
TOTAL : 1631.49
ADD FOR CONTRACTORS PROFIT 10% 163.15
ADD FOR OVER HEAD CHARGES @5% 81.57
COST FOR 10.00 nos 1876.21
COST PER No. 187.60
LABOUR PER No. 11.25
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 97.99
TOTAL : 97.99
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR CONTRACTORS PROFIT @10% : 9.80
ADD FOR OVER HEAD CHARGES @5% : 4.90
LABOUR FOR 10.000 nos. 112.69
LABOUR PER no. 11.25
1215703000 100 mm
Details of cost for 10 Nos.
MATERIAL :
LABOUR :
Carpenter 2nd class each 0.40000 186.67 74.66
Beldar each 0.20000 116.67 23.33
TOTAL : 1223.49
ADD FOR CONTRACTORS PROFIT 10% 122.35
ADD FOR OVER HEAD CHARGES @5% 61.17
COST FOR 10.00 nos 1407.01
COST PER No. 140.70
LABOUR PER No. 11.25
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 97.99
TOTAL : 97.99
ADD FOR CONTRACTORS PROFIT @10% : 9.80
ADD FOR OVER HEAD CHARGES @5% : 4.90
LABOUR FOR 10.000 nos. 112.69
LABOUR PER no. 11.25
MATERIAL :
LABOUR :
Carpenter 2nd class each 0.14000 186.67 26.13
Beldar each 0.09000 116.67 10.50
TOTAL : 93.63
ADD FOR CONTRACTORS PROFIT 10% 9.36
ADD FOR OVER HEAD CHARGES @5% 4.68
COST FOR 1.00 mtr. 107.67
COST PER mtr. 107.70
LABOUR PER mtr. 42.10
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 36.63
TOTAL : 36.63
ADD FOR CONTRACTORS PROFIT @10% : 3.66
ADD FOR OVER HEAD CHARGES @5% : 1.83
LABOUR FOR 1.000 mtr. 42.12
LABOUR PER mtr 42.10
MATERIAL :
LABOUR :
Carpenter 2nd class each 0.14000 186.67 26.13
Beldar each 0.09000 116.67 10.50
TOTAL : 93.63
ADD FOR CONTRACTORS PROFIT 10% 9.36
ADD FOR OVER HEAD CHARGES @5% 4.68
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
COST FOR 1.00 Mtr. 107.67
COST PER Mtr. 107.70
LABOUR PER Mtr. 42.10
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 36.63
TOTAL : 36.63
ADD FOR CONTRACTORS PROFIT @10% : 3.66
ADD FOR OVER HEAD CHARGES @5% : 1.83
LABOUR FOR 1.000 Mtr. 42.12
LABOUR PER Mtr. 42.10
1216001000 300x115x2.24mm
Details of cost for 10 Nos.
MATERIAL :
LABOUR :
Carpenter 2nd class each 0.20000 186.67 37.33
Beldar each 0.14000 116.67 16.33
TOTAL : 278.66
ADD FOR CONTRACTORS PROFIT 10% 27.87
ADD FOR OVER HEAD CHARGES @5% 13.93
COST FOR 10.00 nos 320.46
COST PER No. 32.05
LABOUR PER No. 6.15
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 53.66
TOTAL : 53.66
ADD FOR CONTRACTORS PROFIT @10% : 5.37
ADD FOR OVER HEAD CHARGES @5% : 2.68
LABOUR FOR 10.000 nos. 61.71
LABOUR PER no. 6.15
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
1216002000 250x100x2.24 mm
Details of cost for 10 Nos.
MATERIAL :
LABOUR :
Carpenter 2nd class each 0.20000 186.67 37.33
Beldar each 0.14000 116.67 16.33
TOTAL : 248.66
ADD FOR CONTRACTORS PROFIT 10% 24.87
ADD FOR OVER HEAD CHARGES @5% 12.43
COST FOR 10.00 nos 285.96
COST PER No. 28.60
LABOUR PER No. 6.15
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 53.66
TOTAL : 53.66
ADD FOR CONTRACTORS PROFIT @10% : 5.37
ADD FOR OVER HEAD CHARGES @5% : 2.68
LABOUR FOR 10.000 nos. 61.71
LABOUR PER no. 6.15
1216101000 300x16mm
Details of cost for 10 Nos.
MATERIAL :
LABOUR :
Carpenter 2nd class each 0.25000 186.67 46.66
TOTAL : 613.66
ADD FOR CONTRACTORS PROFIT 10% 61.37
ADD FOR OVER HEAD CHARGES @5% 30.68
COST FOR 10.00 nos 705.71
COST PER No. 70.60
LABOUR PER No. 5.35
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 46.66
TOTAL : 46.66
ADD FOR CONTRACTORS PROFIT @10% : 4.67
ADD FOR OVER HEAD CHARGES @5% : 2.33
LABOUR FOR 10.000 nos. 53.66
LABOUR PER no. 5.35
1216102000 250x16 mm
Details of cost for 10 Nos.
MATERIAL :
LABOUR :
Carpenter 2nd class each 0.25000 186.67 46.66
TOTAL : 563.66
ADD FOR CONTRACTORS PROFIT 10% 56.37
ADD FOR OVER HEAD CHARGES @5% 28.18
COST FOR 10.00 nos 648.21
COST PER No. 64.80
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR PER No. 5.35
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 46.66
TOTAL : 46.66
ADD FOR CONTRACTORS PROFIT @10% : 4.67
ADD FOR OVER HEAD CHARGES @5% : 2.33
LABOUR FOR 10.000 nos. 53.66
LABOUR PER no. 5.35
MATERIAL :
CARRIAGE :
LABOUR :
Carpenter 2nd class each 0.25000 186.67 46.66
TOTAL : 498.66
ADD FOR CONTRACTORS PROFIT 10% 49.87
ADD FOR OVER HEAD CHARGES @5% 24.93
COST FOR 10.00 nos 573.46
COST PER No. 57.35
LABOUR PER No. 5.35
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 46.66
TOTAL : 46.66
ADD FOR CONTRACTORS PROFIT @10% : 4.67
ADD FOR OVER HEAD CHARGES @5% : 2.33
LABOUR FOR 10.000 nos. 53.66
LABOUR PER no. 5.35
1216301000 300x20x6mm
Details of cost for 10 nos.
MATERIAL :
LABOUR :
Carpenter 2nd class each 0.12000 186.67 22.40
TOTAL : 395.90
ADD FOR CONTRACTORS PROFIT 10% 39.59
ADD FOR OVER HEAD CHARGES @5% 19.80
COST FOR 10.00 nos 455.29
COST PER No. 45.50
LABOUR PER No. 2.60
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 22.40
TOTAL : 22.40
ADD FOR CONTRACTORS PROFIT @10% : 2.24
ADD FOR OVER HEAD CHARGES @5% : 1.12
LABOUR FOR 10.000 nos. 25.76
LABOUR PER no. 2.60
1216302000 250x20x6mm
Details of cost for 10 nos.
MATERIAL :
TOTAL : 345.90
ADD FOR CONTRACTORS PROFIT 10% 34.59
ADD FOR OVER HEAD CHARGES @5% 17.30
COST FOR 10.00 nos 397.79
COST PER No. 39.80
LABOUR PER No. 2.60
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 22.40
TOTAL : 22.40
ADD FOR CONTRACTORS PROFIT @10% : 2.24
ADD FOR OVER HEAD CHARGES @5% : 1.12
LABOUR FOR 10.000 nos. 25.76
LABOUR PER no. 2.60
1216401000 250x10mm.
Details of cost for 10 Nos.
MATERIAL :
LABOUR :
Carpenter 2nd class each 0.10000 186.67 18.66
TOTAL : 325.66
ADD FOR CONTRACTORS PROFIT 10% 32.57
ADD FOR OVER HEAD CHARGES @5% 16.28
COST FOR 10.00 nos 374.51
COST PER No. 37.45
LABOUR PER No. 2.15
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 18.66
TOTAL : 18.66
ADD FOR CONTRACTORS PROFIT @10% : 1.87
ADD FOR OVER HEAD CHARGES @5% : 0.93
LABOUR FOR 10.000 nos. 21.46
LABOUR PER no. 2.15
1216402000 200x10mm
Details of cost for 10 Nos.
MATERIAL :
LABOUR :
Carpenter 2nd class each 0.10000 186.67 18.66
TOTAL : 295.66
ADD FOR CONTRACTORS PROFIT 10% 29.57
ADD FOR OVER HEAD CHARGES @5% 14.78
COST FOR 10.00 nos 340.01
COST PER No. 34.00
LABOUR PER No. 2.15
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 18.66
TOTAL : 18.66
ADD FOR CONTRACTORS PROFIT @10% : 1.87
ADD FOR OVER HEAD CHARGES @5% : 0.93
LABOUR FOR 10.000 nos. 21.46
LABOUR PER no. 2.15
1216403000 150x10mm
Details of cost for 10 Nos.
MATERIAL :
LABOUR :
Carpenter 2nd class each 0.08000 186.67 14.93
TOTAL : 230.93
ADD FOR CONTRACTORS PROFIT 10% 23.09
ADD FOR OVER HEAD CHARGES @5% 11.55
COST FOR 10.00 nos 265.57
COST PER No. 26.55
LABOUR PER No. 1.70
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 14.93
TOTAL : 14.93
ADD FOR CONTRACTORS PROFIT @10% : 1.49
ADD FOR OVER HEAD CHARGES @5% : 0.75
LABOUR FOR 10.000 nos. 17.17
LABOUR PER no. 1.70
1216404000 100x10mm
Details of cost for 10 Nos.
MATERIAL :
LABOUR :
Carpenter 2nd class each 0.08000 186.67 14.93
TOTAL : 170.93
ADD FOR CONTRACTORS PROFIT 10% 17.09
ADD FOR OVER HEAD CHARGES @5% 8.55
COST FOR 10.00 nos 196.57
COST PER No. 19.65
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR PER No. 1.70
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 14.93
TOTAL : 14.93
ADD FOR CONTRACTORS PROFIT @10% : 1.49
ADD FOR OVER HEAD CHARGES @5% : 0.75
LABOUR FOR 10.000 nos. 17.17
LABOUR PER no. 1.70
1216501000 125mm
Details of cost for 10 Nos.
MATERIAL :
LABOUR :
Carpenter 2nd class each 0.06000 186.67 11.20
TOTAL : 122.20
ADD FOR CONTRACTORS PROFIT 10% 12.22
ADD FOR OVER HEAD CHARGES @5% 6.11
COST FOR 10.00 nos 140.53
COST PER No. 14.05
LABOUR PER No. 1.30
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 11.20
TOTAL : 11.20
ADD FOR CONTRACTORS PROFIT @10% : 1.12
ADD FOR OVER HEAD CHARGES @5% : 0.56
LABOUR FOR 10.000 nos. 12.88
LABOUR PER no. 1.30
1216502000 100 mm
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Details of cost for 10 Nos.
MATERIAL :
LABOUR :
Carpenter 2nd class each 0.06000 186.67 11.20
TOTAL : 102.20
ADD FOR CONTRACTORS PROFIT 10% 10.22
ADD FOR OVER HEAD CHARGES @5% 5.11
COST FOR 10.00 nos 117.53
COST PER No. 11.75
LABOUR PER No. 1.30
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 11.20
TOTAL : 11.20
ADD FOR CONTRACTORS PROFIT @10% : 1.12
ADD FOR OVER HEAD CHARGES @5% : 0.56
LABOUR FOR 10.000 nos. 12.88
LABOUR PER no. 1.30
1216503000 75mm
Details of cost for 10 Nos.
MATERIAL :
LABOUR :
Carpenter 2nd class each 0.06000 186.67 11.20
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 92.20
ADD FOR CONTRACTORS PROFIT 10% 9.22
ADD FOR OVER HEAD CHARGES @5% 4.61
COST FOR 10.00 nos 106.03
COST PER No. 10.60
LABOUR PER No. 1.30
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 11.20
TOTAL : 11.20
ADD FOR CONTRACTORS PROFIT @10% : 1.12
ADD FOR OVER HEAD CHARGES @5% : 0.56
LABOUR FOR 10.000 nos. 12.88
LABOUR PER no. 1.30
MATERIAL :
CARRIAGE :
LABOUR :
Carpenter 2nd class each 0.06000 186.67 11.20
TOTAL : 162.20
ADD FOR CONTRACTORS PROFIT 10% 16.22
ADD FOR OVER HEAD CHARGES @5% 8.11
COST FOR 10.00 nos 186.53
COST PER No. 18.65
LABOUR PER No. 1.30
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 11.20
TOTAL : 11.20
ADD FOR CONTRACTORS PROFIT @10% : 1.12
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR OVER HEAD CHARGES @5% : 0.56
LABOUR FOR 10.000 nos. 12.88
LABOUR PER no. 1.30
1216602000 250mm
Details of cost for 10 Nos.
MATERIAL :
CARRIAGE :
LABOUR :
Carpenter 2nd class each 0.06000 186.67 11.20
TOTAL : 132.20
ADD FOR CONTRACTORS PROFIT 10% 13.22
ADD FOR OVER HEAD CHARGES @5% 6.61
COST FOR 10.00 nos 152.03
COST PER No. 15.20
LABOUR PER No. 1.30
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 11.20
TOTAL : 11.20
ADD FOR CONTRACTORS PROFIT @10% : 1.12
ADD FOR OVER HEAD CHARGES @5% : 0.56
LABOUR FOR 10.000 nos. 12.88
LABOUR PER no. 1.30
1216603000 200 mm
Details of cost for 10 Nos.
MATERIAL :
CARRIAGE :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR :
Carpenter 2nd class each 0.06000 186.67 11.20
TOTAL : 112.20
ADD FOR CONTRACTORS PROFIT 10% 11.22
ADD FOR OVER HEAD CHARGES @5% 5.61
COST FOR 10.00 nos 129.03
COST PER No. 12.90
LABOUR PER No. 1.30
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 11.20
TOTAL : 11.20
ADD FOR CONTRACTORS PROFIT @10% : 1.12
ADD FOR OVER HEAD CHARGES @5% : 0.56
LABOUR FOR 10.000 nos. 12.88
LABOUR PER no. 1.30
1216604000 150 mm
Details of cost for 10 Nos.
MATERIAL :
CARRIAGE :
LABOUR :
Carpenter 2nd class each 0.06000 186.67 11.20
TOTAL : 92.20
ADD FOR CONTRACTORS PROFIT 10% 9.22
ADD FOR OVER HEAD CHARGES @5% 4.61
COST FOR 10.00 nos 106.03
COST PER No. 10.60
LABOUR PER No. 1.30
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 11.20
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 11.20
ADD FOR CONTRACTORS PROFIT @10% : 1.12
ADD FOR OVER HEAD CHARGES @5% : 0.56
LABOUR FOR 10.000 nos. 12.88
LABOUR PER no. 1.30
1216605000 100 mm
Details of cost for 10 Nos.
MATERIAL :
CARRIAGE :
LABOUR :
Carpenter 2nd class each 0.06000 186.67 11.20
TOTAL : 82.20
ADD FOR CONTRACTORS PROFIT 10% 8.22
ADD FOR OVER HEAD CHARGES @5% 4.11
COST FOR 10.00 nos 94.53
COST PER No. 9.45
LABOUR PER No. 1.30
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 11.20
TOTAL : 11.20
ADD FOR CONTRACTORS PROFIT @10% : 1.12
ADD FOR OVER HEAD CHARGES @5% : 0.56
LABOUR FOR 10.000 nos. 12.88
LABOUR PER no. 1.30
MATERIAL :
CARRIAGE :
LABOUR :
Carpenter 2nd class each 0.07000 186.67 13.06
TOTAL : 121.06
ADD FOR CONTRACTORS PROFIT 10% 12.11
ADD FOR OVER HEAD CHARGES @5% 6.05
COST FOR 10.00 nos 139.22
COST PER No. 13.90
LABOUR PER No. 1.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 13.06
TOTAL : 13.06
ADD FOR CONTRACTORS PROFIT @10% : 1.31
ADD FOR OVER HEAD CHARGES @5% : 0.65
LABOUR FOR 10.000 nos. 15.02
LABOUR PER no. 1.50
MATERIAL :
CARRIAGE :
LABOUR :
Carpenter 2nd class each 0.07000 186.67 13.06
TOTAL : 104.06
ADD FOR CONTRACTORS PROFIT 10% 10.41
ADD FOR OVER HEAD CHARGES @5% 5.20
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
COST FOR 10.00 nos 119.67
COST PER No. 11.95
LABOUR PER No. 1.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 13.06
TOTAL : 13.06
ADD FOR CONTRACTORS PROFIT @10% : 1.31
ADD FOR OVER HEAD CHARGES @5% : 0.65
LABOUR FOR 10.000 nos. 15.02
LABOUR PER no. 1.50
MATERIAL :
300mm long M.S. chain with hooks Each 10.00000 10.00 100.00
CARRIAGE :
LABOUR :
Carpenter 2nd class each 0.10000 186.67 18.66
TOTAL : 129.66
ADD FOR CONTRACTORS PROFIT 10% 12.97
ADD FOR OVER HEAD CHARGES @5% 6.48
COST FOR 10.00 nos 149.11
COST PER No. 14.90
LABOUR PER No. 2.15
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 18.66
TOTAL : 18.66
ADD FOR CONTRACTORS PROFIT @10% : 1.87
ADD FOR OVER HEAD CHARGES @5% : 0.93
LABOUR FOR 10.000 nos. 21.46
LABOUR PER no. 2.15
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
1217000000 Providing and fixing M.S. safety hasps and
stapples with necessary screws etc.
complete.
MATERIAL :
M.S. safety hasps and staples 150 mmEach 10.00000 10.00 100.00
CARRIAGE :
LABOUR :
Carpenter 2nd class each 0.08000 186.67 14.93
TOTAL : 135.93
ADD FOR CONTRACTORS PROFIT 10% 13.59
ADD FOR OVER HEAD CHARGES @5% 6.80
COST FOR 10.00 nos 156.32
COST PER No. 15.60
LABOUR PER No. 1.70
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 14.93
TOTAL : 14.93
ADD FOR CONTRACTORS PROFIT @10% : 1.49
ADD FOR OVER HEAD CHARGES @5% : 0.75
LABOUR FOR 10.000 nos. 17.17
LABOUR PER no. 1.70
1217002000 115 mm
Details of cost for 10 Nos.
MATERIAL :
M.S. safety hasps and staples 115 mmEach 10.00000 8.00 80.00
CARRIAGE :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR :
Carpenter 2nd class each 0.08000 186.67 14.93
TOTAL : 113.43
ADD FOR CONTRACTORS PROFIT 10% 11.34
ADD FOR OVER HEAD CHARGES @5% 5.67
COST FOR 10.00 nos 130.44
COST PER No. 13.05
LABOUR PER No. 1.70
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 14.93
TOTAL : 14.93
ADD FOR CONTRACTORS PROFIT @10% : 1.49
ADD FOR OVER HEAD CHARGES @5% : 0.75
LABOUR FOR 10.000 nos. 17.17
LABOUR PER no. 1.70
1217003000 90 mm
Details of cost for 10 Nos.
MATERIAL :
CARRIAGE :
LABOUR :
Carpenter 2nd class each 0.08000 186.67 14.93
TOTAL : 93.43
ADD FOR CONTRACTORS PROFIT 10% 9.34
ADD FOR OVER HEAD CHARGES @5% 4.67
COST FOR 10.00 nos 107.44
COST PER No. 10.75
LABOUR PER No. 1.70
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 14.93
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 14.93
ADD FOR CONTRACTORS PROFIT @10% : 1.49
ADD FOR OVER HEAD CHARGES @5% : 0.75
LABOUR FOR 10.000 nos. 17.17
LABOUR PER no. 1.70
MATERIAL :
CARRIAGE :
LABOUR :
Carpenter 2nd class each 0.40000 186.67 74.67
Beldar each 0.20000 116.67 23.33
TOTAL : 620.00
ADD FOR CONTRACTORS PROFIT 10% 62.00
ADD FOR OVER HEAD CHARGES @5% 31.00
COST FOR 10.00 nos 713.00
COST PER No. 71.30
LABOUR PER No. 11.25
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 98.00
TOTAL : 98.00
ADD FOR CONTRACTORS PROFIT @10% : 9.80
ADD FOR OVER HEAD CHARGES @5% : 4.90
LABOUR FOR 10.000 nos. 112.70
LABOUR PER no. 11.25
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.07340 110.95 8.14
LABOUR :
Carpenter 1st Class each 2.72000 211.16 574.36
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 719.69
TOTAL : 719.69
ADD FOR CONTRACTORS PROFIT @10% : 71.97
ADD FOR OVER HEAD CHARGES @5% : 35.98
LABOUR FOR 2.160 Sqm 827.65
LABOUR PER sqm 383.15
MATERIAL :
CARRIAGE :
Timber.
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
1 KM BY MECH. TRANSPORT 1 cum 0.05300 110.95 5.88
LABOUR :
Carpenter 1st Class each 1.65000 211.16 348.41
Carpenter 2nd Class each 1.22000 186.67 227.74
Beldar each 1.29000 116.67 150.50
TOTAL : 4166.98
ADD FOR CONTRACTORS PROFIT 10% 416.70
ADD FOR OVER HEAD CHARGES @5% 208.35
COST FOR 2.160 sqm 4792.02
COST PER Sqm 2218.50
LABOUR PER Sqm 386.85
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 726.66
TOTAL : 726.66
ADD FOR CONTRACTORS PROFIT @10% : 72.67
ADD FOR OVER HEAD CHARGES @5% : 36.33
LABOUR FOR 2.160 Sqm 835.65
LABOUR PER sqm 386.85
1217401010 8 mm thick
Details of cost for 10 sqm.
MATERIAL :
CARRIAGE :
carriage of particle board L.S. 15.00
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR :
Carpenter 1st Class each 0.50000 211.16 105.58
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 175.92
TOTAL : 175.92
ADD FOR CONTRACTORS PROFIT @10% : 17.59
ADD FOR OVER HEAD CHARGES @5% : 8.80
LABOUR FOR 10.00 Sqm 202.30
LABOUR PER sqm 20.25
MATERIAL :
CARRIAGE :
carriage of particle board L.S. 15.00
LABOUR :
Carpenter 1st Class each 0.50000 211.16 105.58
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 175.92
TOTAL : 175.92
ADD FOR CONTRACTORS PROFIT @10% : 17.59
ADD FOR OVER HEAD CHARGES @5% : 8.80
LABOUR FOR 10.00 Sqm 202.30
LABOUR PER sqm 20.25
MATERIAL :
CARRIAGE :
carriage of particle board L.S. 15.00
LABOUR :
Carpenter 1st Class each 0.50000 211.16 105.58
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 175.92
TOTAL : 175.92
ADD FOR CONTRACTORS PROFIT @10% : 17.59
ADD FOR OVER HEAD CHARGES @5% : 8.80
LABOUR FOR 10.00 Sqm 202.30
LABOUR PER sqm 20.25
MATERIAL :
Gypsum board
12.5mm thick = 10.00 sqm.
Add 5% wastage =0.50 sqm.
Total =10.50 sqm. 1 sqm. 10.50000 300.00 3150.00
CARRIAGE :
carriage of gypsum board L.S. 15.00
LABOUR :
Carpenter 1st Class each 0.50000 211.16 105.58
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 175.92
TOTAL : 175.92
ADD FOR CONTRACTORS PROFIT @10% : 17.59
ADD FOR OVER HEAD CHARGES @5% : 8.80
LABOUR FOR 10.00 Sqm 202.30
LABOUR PER sqm 20.25
MATERIAL :
CARRIAGE :
carriage of particle board L.S. 15.00
LABOUR :
Carpenter 1st Class each 0.50000 211.16 105.58
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 175.92
TOTAL : 175.92
ADD FOR CONTRACTORS PROFIT @10% : 17.59
ADD FOR OVER HEAD CHARGES @5% : 8.80
LABOUR FOR 10.00 Sqm 202.30
LABOUR PER sqm 20.25
MATERIAL :
CARRIAGE :
carriage of particle board L.S. 15.00
LABOUR :
Carpenter 1st Class each 0.50000 211.16 105.58
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 175.92
TOTAL : 175.92
ADD FOR CONTRACTORS PROFIT @10% : 17.59
ADD FOR OVER HEAD CHARGES @5% : 8.80
LABOUR FOR 10.00 Sqm 202.30
LABOUR PER sqm 20.25
MATERIAL :
Particle board
8mm thick = 10.00 sqm.
Add 5% wastage =0.50 sqm.
Total =10.50 sqm. 1 sqm. 10.50000 250.00 2625.00
CARRIAGE :
carriage of particle board L.S. 15.00
LABOUR :
Carpenter 1st Class each 0.54000 211.16 114.03
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 171.19
TOTAL : 171.19
ADD FOR CONTRACTORS PROFIT @10% : 17.12
ADD FOR OVER HEAD CHARGES @5% : 8.56
LABOUR FOR 10.00 Sqm 196.87
LABOUR PER sqm 19.70
1217502010 6 mm thick.
Details of cost for 10 sqm.
MATERIAL :
CARRIAGE :
carriage of particle board L.S. 15.00
LABOUR :
Carpenter 1st Class each 0.54000 211.16 114.03
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 171.19
TOTAL : 171.19
ADD FOR CONTRACTORS PROFIT @10% : 17.12
ADD FOR OVER HEAD CHARGES @5% : 8.56
LABOUR FOR 10.00 Sqm 196.87
LABOUR PER sqm 19.70
1217502020 8 mm thick.
Details of cost for 10 sqm.
MATERIAL :
CARRIAGE :
carriage of particle board L.S. 15.00
LABOUR :
Carpenter 1st Class each 0.54000 211.16 114.03
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 171.19
TOTAL : 171.19
ADD FOR CONTRACTORS PROFIT @10% : 17.12
ADD FOR OVER HEAD CHARGES @5% : 8.56
LABOUR FOR 10.00 Sqm 196.87
LABOUR PER sqm 19.70
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
Gypsum board
9.5mm thick = 10.00 sqm.
Add 5% wastage =0.50 sqm.
Total =10.50 sqm. 1 sqm. 10.50000 230.00 2415.00
CARRIAGE :
carriage of particle board L.S. 15.00
LABOUR :
Carpenter 1st Class each 0.54000 211.16 114.03
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 171.19
TOTAL : 171.19
ADD FOR CONTRACTORS PROFIT @10% : 17.12
ADD FOR OVER HEAD CHARGES @5% : 8.56
LABOUR FOR 10.00 Sqm 196.87
LABOUR PER sqm 19.70
Gypsum board
12.5mm thick = 10.00 sqm.
Add 5% wastage =0.50 sqm.
Total =10.50 sqm. 1 sqm. 10.50000 300.00 3150.00
CARRIAGE :
carriage of particle board L.S. 15.00
LABOUR :
Carpenter 1st Class each 0.54000 211.16 114.03
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 171.19
TOTAL : 171.19
ADD FOR CONTRACTORS PROFIT @10% : 17.12
ADD FOR OVER HEAD CHARGES @5% : 8.56
LABOUR FOR 10.00 Sqm 196.87
LABOUR PER sqm 19.70
MATERIAL :
CARRIAGE :
carriage of particle board L.S. 15.00
LABOUR :
Carpenter 1st Class each 0.54000 211.16 114.03
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 171.19
TOTAL : 171.19
ADD FOR CONTRACTORS PROFIT @10% : 17.12
ADD FOR OVER HEAD CHARGES @5% : 8.56
LABOUR FOR 10.00 Sqm 196.87
LABOUR PER sqm 19.70
MATERIAL :
Anchor board
12mm thick = 10.00 sqm.
Add 5% wastage =0.50 sqm.
Total =10.50 sqm. 1 sqm. 10.50000 660.00 6930.00
CARRIAGE :
carriage of particle board L.S. 15.00
LABOUR :
Carpenter 1st Class each 0.54000 211.16 114.03
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 171.19
TOTAL : 171.19
ADD FOR CONTRACTORS PROFIT @10% : 17.12
ADD FOR OVER HEAD CHARGES @5% : 8.56
LABOUR FOR 10.00 Sqm 196.87
LABOUR PER sqm 19.70
Aluminium Section.
CARRIAGE
LABOUR :
for fabrication of frame
LABOUR RATE :
MATERIALS.
Aluminium snap
beading jindal section No. 4497 (both side)
2x2(0.75+1.26) = 8.04 mtr.
2x2(0.75+0.81) = 6.24 mtr.
Total = 14.28 mtr.
0.176 kg/mtr = 2.51 kg.
Aluminium hinge
100x75x4 mm 10 Nos. 4.00000 400.00 160.00
CARRIAGE
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR :
for fabrication Fitter
MATERIALS
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Glass panes 4.00 mm = 1.00 sqm.
Add for wastage & breaksge@10% = 0.10 sqm.
Total =1.10 sqm.
1 sqm. 1.10000 300.00 330.00
CARRIAGE
Glass panes
1 KM BY MECH TRANSPORT TONNE 0.01100 73.95 0.81
LABOUR :
Labour Rate:
MATERIALS
CARRIAGE
(Glass panes)
1 KM BY MECH TRANSPORT TONNE 0.01500 73.95 1.10
LABOUR :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 65.90
Add. For water charge @ 1.5% 9.41
TOTAL : 75.31
ADD FOR CONTRACTORS PROFIT @10% : 7.53
ADD FOR OVER HEAD CHARGES @5% : 3.77
TOTAL : 86.60
LABOUR PER sqm 86.60
MATERIAL :
CARRIAGE :
1 KM BY MECH TRANSPORT
AND 100MT. BY HEAD LOAD L.S. 10.00
SUNDRIES AND SCREWS ETC. L.S. 10.00
LABOUR :
For cutting hole and making it good & fixing
TOTAL : 1227.65
Add. For water charge @ 1.5% 18.31
Total 1245.94
ADD FOR CONTRACTORS PROFIT 10% 123.95
ADD FOR OVER HEAD CHARGES @5% 61.97
COST FOR 1.00 no. 1431.86
COST PER no 1431.85
LABOUR RATE :
MATERIAL :
E-Board 4mm thick =10.00 sqm
Add. Wastage @ 5%=0.50 sqm
Total =10.50 sqm Sqm 10.50000 560.00 5880.00
CARRIAGE :
LABOUR :
TOTAL : 6128.03
ADD FOR CONTRACTORS PROFIT 10% 612.80
ADD FOR OVER HEAD CHARGES @5% 306.40
COST FOR 10.00 sqm 7047.23
COST PER sqm 704.70
LABOUR RATE :
MATERIAL :
25mm thick commercial board
2.20x1.00m =2.20 sqm
Add. Wastage @ 5%=0.11 sqm
Total =2.31 sqm Sqm 2.31000 950.00 2194.50
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Nickel plated bright finished M.S.
piano hinges Mtr. 4.40000 50.00 220.00
Iron screws 25mm 100 Nos. 125.00000 25.00 31.25
CARRIAGE :
LABOUR :
TOTAL : 2657.74
ADD FOR CONTRACTORS PROFIT 10% 265.77
ADD FOR OVER HEAD CHARGES @5% 132.89
COST FOR 2.20 sqm 3056.40
COST PER sqm 1389.25
Labour per sqm 100.35
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 191.99
MATERIAL :
19mm thick commercial board
2.20x1.00m =2.20 sqm
Add. Wastage @ 5%=0.11 sqm
Total =2.31 sqm Sqm 2.31000 785.00 1813.35
LABOUR :
TOTAL : 2276.59
ADD FOR CONTRACTORS PROFIT 10% 227.66
ADD FOR OVER HEAD CHARGES @5% 113.83
COST FOR 2.20 sqm 2618.08
COST PER sqm 1190.00
Labour per sqm 100.35
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 191.99
MATERIAL :
19mm thick commercial board
=10.00 sqm
Add. Wastage @ 5%=0.50 sqm
Total =10.50 sqm Sqm 10.50000 785.00 8242.50
CARRIAGE :
LABOUR :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 8550.10
ADD FOR CONTRACTORS PROFIT 10% 855.01
ADD FOR OVER HEAD CHARGES @5% 427.50
COST FOR 10.00 sqm 9832.61
COST PER sqm 983.25
Labour per sqm 29.60
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 257.60
MATERIAL :
19mm thick commercial board
=10.00 sqm
Add. Wastage @ 5%=0.50 sqm
Total =10.50 sqm Sqm 10.50000 950.00 9975.00
CARRIAGE :
LABOUR :
TOTAL : 10282.60
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR CONTRACTORS PROFIT 10% 1028.26
ADD FOR OVER HEAD CHARGES @5% 514.13
COST FOR 10.00 sqm 11827.99
COST PER sqm 1182.50
Labour per sqm 29.60
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 257.60
MATERIAL :
1.00mm thick sunmica sheet
=10.00 sqm
Add. Wastage @ 5%=0.50 sqm
Total =10.50 sqm Sqm 10.50000 425.00 4462.50
CARRIAGE :
LABOUR :
TOTAL : 5542.50
ADD FOR CONTRACTORS PROFIT 10% 554.25
ADD FOR OVER HEAD CHARGES @5% 277.13
COST FOR 10.00 sqm 6373.88
COST PER sqm 637.40
Labour per sqm 53.45
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 465.00
MATERIAL :
1st class Indian teak wood
100x0.019x0.006 =0.0114 cum
Add. Wastage @ 5%=0.0011 cum
Total =0.0125 cum Cum 0.01250 98625.00 1232.80
CARRIAGE :
Carriage of Timber
1KM by Mechanical Trpt. cum 0.01250 110.95 1.38
100mtrs. By head load cum 0.01250 36.25 0.45
LABOUR :
Carpenter 1st class each 2.00000 211.16 422.32
Carpenter 2nd Class each 2.00000 186.67 373.34
Beldar each 4.00000 116.67 466.68
SCAFFOLDINGS L.S. 7.00
Sundries L.S. 5.00
TOTAL : 2640.97
ADD FOR CONTRACTORS PROFIT 10% 264.09
ADD FOR OVER HEAD CHARGES @5% 132.04
COST FOR 100 MTRS. 3037.10
COST PER Mtrs. 30.37
Say Rs. 30.35
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1274.34
MATERIAL :
1st class Indian teak wood
100x0.019x0.006 =0.0114 cum
Add. Wastage @ 5%=0.0011 cum
Total =0.0125 cum Cum 0.01250 54020.00 675.25
CARRIAGE :
Carriage of Timber
1KM by Mechanical Trpt. cum 0.01250 110.95 1.38
100mtrs. By head load cum 0.01250 36.25 0.45
LABOUR :
Carpenter 1st class each 1.50000 211.16 316.74
Carpenter 2nd Class each 1.50000 186.67 280.00
Beldar each 3.00000 116.67 350.01
SCAFFOLDINGS L.S. 7.00
Sundries L.S. 5.00
TOTAL : 1767.83
ADD FOR CONTRACTORS PROFIT 10% 176.78
ADD FOR OVER HEAD CHARGES @5% 88.39
COST FOR 100 MTRS. 2033.00
COST PER Mtrs. 20.33
Say Rs. 20.35
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 958.75
MATERIAL :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
4mm thick burl ply
=10.00 sqm
Add. Wastage @ 5%=0.50 sqm
Total =10.50 sqm sqm 10.50000 260.00 2730.00
CARRIAGE :
LABOUR :
Carpenter 1st class each 0.74000 211.16 156.25
Beldar each 0.74000 116.67 86.33
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 257.58
MATERIAL :
4mm thick water proof
=10.00 sqm
Add. Wastage @ 5%=0.50 sqm
Total =10.50 sqm sqm 10.50000 250.00 2625.00
CARRIAGE :
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR :
Carpenter 1st class each 0.74000 211.16 156.25
Beldar each 0.74000 116.67 86.33
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 257.58
MATERIAL :
9mm thick water proof kit ply
=10.00 sqm
Add. Wastage @ 5%=0.50 sqm
Total =10.50 sqm sqm 10.50000 520.00 5460.00
CARRIAGE :
LABOUR :
Carpenter 1st class each 0.74000 211.16 156.25
Beldar each 0.74000 116.67 86.33
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 257.58
MATERIAL :
12mm thick water proof
=10.00 sqm
Add. Wastage @ 5%=0.50 sqm
Total =10.50 sqm sqm 10.50000 625.00 6562.50
CARRIAGE :
LABOUR :
Carpenter 1st class each 0.74000 211.16 156.25
Beldar each 0.74000 116.67 86.33
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 257.58
MATERIAL :
Aluminium grill 8mm thick
=1.00 sqm
Add. Wastage @ 5%=0.05 sqm
Total =1.05 sqm sqm 1.05000 1350.00 1417.50
CARRIAGE :
LABOUR :
Carpenter 1st class each 0.25000 211.16 52.79
Beldar each 0.25000 116.67 29.17
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 96.96
MATERIAL :
Aluminium strips/beading
long side 3.50/0.60+1 =7x3.50 =24.50 metre
Short side 3.00+0.60+1 =6x3.00 =18.00 metre
Total =42.50 metre
Add. For wastage @ 5% =2.12 metre
L.S. 10.00
Total =44.62 metre
Carriage
1KM by Mechanical Trpt. cum 0.07000 73.95 5.18
100mtrs. By head load cum 0.07000 57.85 4.05
LABOUR :
Carpenter 1st class each 1.60000 211.16 337.85
Beldar each 1.60000 116.67 186.67
SCAFFOLDINGS L.S. 50.00
Sundries L.S. 15.00
TOTAL : 9217.45
ADD FOR CONTRACTORS PROFIT 10% 921.74
ADD FOR OVER HEAD CHARGES @5% 460.87
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
COST FOR 10.50 sqm 10600.06
COST PER SQm 1009.50
Labour per sqm. 64.55
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 589.52
MATERIAL :
LABOUR :
Carpenter 2nd class each 0.25000 186.67 46.66
Beldar each 0.25000 116.67 29.16
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 95.82
MATERIAL :
CARRIAGE
Carriage of PVC door frame &
screws etc. L.S. 25.00
LABOUR :
Labour for fixing of PVC door frame
to wall complete
Mason 1st class each 0.25000 211.16 52.80
Beldar each 0.25000 116.67 29.16
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 91.96
Add. Labour as per item NO. 120590200 33.60 (-a-)
Total 125.56
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-) : 9.19
ADD FOR OVER HEAD CHARGES @5% Except on (-a-) : 4.59
LABOUR FOR 4.86 Rmt. 139.34
LABOUR PER Rmt. 28.70
MATERIAL
LABOUR
labour for fixing PVC door frame to wall
complete
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 113.35
Add. Labour as per item NO. 120590200 33.60 (-a-)
Total 146.95
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-) : 11.33
ADD FOR OVER HEAD CHARGES @5% Except on (-a-) : 5.66
LABOUR FOR 4.86 Rmt. 163.94
LABOUR PER Rmt. 33.73
Say Rs. 33.75
MATERIAL
LABOUR
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 134.73
2700.39
Add. 5% for factory over head charges 135.00
Cost for 1.50 sqm 2835.40
Rate per sqm. 1890.25
Add 4.4% sale tax 83.17
Rate per sqm. 1973.40
Say Rs. 1973.00
WOOD WORK
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
12193000000 Providing and fixing to existing door
frames 30mm thick factory made wire
mesh solid PVC door shutters consisting
of frame made out of M.S. tube of 19
gauge thickness of size 19mmx19mm for
style and 15mmx15mm M.S. square tube
for top, bottom & Lock rail M.S. frame
shall have a coat of steel primer and
covered with 5mm thick PVC solid sheet
heat moulded "C" channel of size
75mmx30mmx60mm out of which 10mm
shall be bent at 90degree towards inner
side on front face of the door M.S. frame
at lock rail shall be covered with 100mm
wide PVC sheet out of which 10mm on
both the edges shall be bent at 90
degree on front face of the door and
85mm wide PVC sheet shall cover the
M.S. frame at top, bottom & lock rail lof
70mm on back side of door 5mm thick
20mm wide cross PVC sheet as gap
insert for top and bottom rail, PVC sheet
beading of 10mm thick, 15mm wide PVC
sheet beading in to be stick internally in
the back side of style and rails of door
with solvent cement adhesive i/c fixing of
G.I. wire mesh 85G
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 134.73
1 5mm thick plain PVC Solid Sheet Sqft 21.00 57.77 1213.21
VOLUME - IV
ANALYSIS FOR SCHEDULE OF RATES 2009
(VOLUME IV)
CONTENTS
Chapter No. Name of Sub-head Page No.
XIII Paving and flooring
XIV Roof Coverings
CHAPTER XIII
1 The through rates include the carriage of all materials up to a distance of 100 meters on
head-load and 1 kilometer by mechanical transport. The rate for items involving terrazzo
/ glazed tiles have been worked out on the basis of rates as at district headquarters of
Himachal Pradesh State. All other carriage shall be accounted for separately depending
up to locations of the site of work. The through rates include all wastage and the labor
rates include the charges on account of from work, tools and plants, scaffolding, sundries
and water charges etc.
2 The rates are applicable for laying of flooring up to floor level two. For every subsequent
storey-height an additional rate of 1% above through rates should be added.
3 The followings additional point should be accounted for while making payment for
terrazzo & terrazzo tile / glazed tile flooring -:
(i) The rates for terrazzo flooring are applicable or marble chips of size up to 15 mm
black or white or black and white shades. 10% extra in through rates shall be pad
if the chips of sizes above 15mm and up to 22 mm are used.
(ii) In case chocolate , gray, yellow or green marble chips instead of white, black and
white chips are used for terrazzo flooring, the following rates shall be added to the
through rates for one square meter of floor area -:
a For 600 top layer Rs 5.10
b For 8mm top layer Rs 7.15
c For 10mm top layer Rs. 9.20
d For 12mm top layer Rs 10.00
(iii) In case snow-white chips are required to be used. 10% extra on through rates shall
be paid for terrazzo-tile flooring as well as for terrazzo flooring. The rates for
assorted cock-tail colored terrazzo tile flooring shall be the same as for silver
Grey tile flooring and for terrazzo flooring with medium shade pigment.
(iv) In case 22mm thick checkered tile with chips of sizes up to 22mm are used
instead of terrazzo tiles, as additional rate of Rs 20.50 per square meter shall be
paid over the through rates. The labor ate shall remain un-changed. In case
checkered tiles without marble chips are used, the through rates of such checkered
tiles shall be 15% less than terrazzo-tiles.
4 The labor rates and through rates are applicable for glazed tiles of white shade and of all
sizes as required.
5 In case, the coloured glazed patterned tiles are used the labour rates shall be increased by
20% or through rates shall be increased by 10%. These rate are not applicable for
specially decorated tiles for which special rates shall be paid, if used.
6 The minimum thickness of top layer for various sizes of chips shall be as under -:
Grade No. Size of chips in mm Minimum thickness of top layers
00 1-2 6mm
0 2-4 6mm
1 4-7 9mm
2 7-10 12mms
Where chips of size larger than 100 mm are used, the minimum thickness should not be
less than 1/1/2 times the maximum size of chips, where large size chips such as 20mm or
25mm are used, they shall be only with a flat shape and bedded on the flat face so as to
keep the minimum thickness of wearing layer.
7 Black, blue, green, and similar other shades be considered as dark shade all shades other
than gray, silver gray and white shall be considered as medium shades for terrazzo tiles.
CHAPTER-XIII
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
CARRIAGE :
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Cement
1 KM BY MECH. TRANSPORT 1 Tonne 0.14950 73.95 11.06
Sand|
1 KM BY MECH. TRANSPORT 1 Cum 0.15100 110.95 16.75
Marble chips |
1 KM BY MECH. TRANSPORT 1 cum 0.05100 110.95 5.66
Marble powder|
1 KM BY MECH. TRANSPORT 1 Cum 0.00700 110.95 0.78
LABOUR :
Mason For Terrazo Work Each 2.16000 186.67 403.21
Beldar Each 3.78000 116.67 441.01
Bhishti Each 0.54000 116.67 63.00
Beldar
(Skilled)for rubbing and polishing Each 9.72000 116.67 1134.03
LABOUR RATE :
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ACTUAL LABOUR+SUNDRIES 2191.24
TOTAL : 2191.24
WATER CHARGES @ 1.5% : 54.20
TOTAL : 2245.44
ADD FOR CONTRACTORS PROFIT @10% : 224.54
ADD FOR OVER HEAD CHARGES@5% : 112.27
LABOUR FOR 10.000sq.m 2582.25
LABOUR PER sq.m 258.25
13010200 light shade pigment with white
cement (in top layer only)
Details of cost for 10 sqm
MATERIAL :
Cost same as per item
no.13010100
10 sqm 10.00000 4218.16 42181.60 (-I-)
Total: 4791.31
Add for water charges @1.5% Except on (-I-) : 8.60
Total: 4799.91
ADD FOR CONTRACTORS PROFIT @10% Except on (-I-) : 58.17
ADD FOR OVER HEAD CHARGES@5% Except on (-I-): 29.08
COST FOR 10.000 sqm. 4887.16
COST PER sqm. 488.70
LABOUR RATE :
Labour As per item no:1301010000.00 2582.25 (-a-)
TOTAL : 2582.25
Add for water charges except on ( -a- ) : 8.60
TOTAL : 2590.85
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON ( -a-): 0.86
ADD FOR OVER HEAD CHARGES@5% EXCEPT ON ( -a- ): 0.43
LABOUR FOR10.000 sqm. 2592.14
LABOUR PER sqm. 259.20
13010300 Medium shade pigment with
approximately 50% white cement
and 50% ordinary cement (in
top layer only)
Details of cost for 10 sqm
MATERIAL :
Total: 4515.11
Add for water charges @1.5% Except on (-I-) : 4.45
Total: 4519.56
ADD FOR CONTRACTORS PROFIT @10% Except on (-I-) : 30.14
ADD FOR OVER HEAD CHARGES@5% Except on (-I-): 15.07
COST FOR 10.000 sq.m 4564.77
COST PER sq.m 456.50
LABOUR RATE :
Labour As per item no:13010100 2582.25 (-a-)
TOTAL : 2582.25
Add for water charges except on ( -a- ) : 4.45
TOTAL : 2586.70
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON ( -a- ): 0.45
ADD FOR OVER HEAD CHARGES@5% EXCEPT ON ( -a- ): 0.22
LABOUR FOR10.000 sq.m 2587.37
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR PER sq.m 258.75
13010400 White cement without any
pigment (in top layer only)
Details of cost for 10 sqm
MATERIAL :
For 34mm. thick Under layer
10mm. stone aggregate.
1 Cum 0.30300 480.00 145.44
Sand.
1 Cum 0.15100 300.00 45.30
Cement.
1 Tonne 0.10900 4900.00 534.10
White cement.
1 Tonne 0.04050 18000.00 729.00
CARRIAGE :
Stone aggregate below 40mm.|
1 KM BY MECH. TRANSPORT 1 cum 0.30300 110.95 33.62
Sand|
1 KM BY MECH. TRANSPORT 1 cum 0.15100 110.95 16.75
Cement|
1 KM BY MECH. TRANSPORT 1 tonne 0.14950 73.95 11.06
Marble chips |
1 KM BY MECH. TRANSPORT 1 cum 0.05100 110.95 5.66
LABOUR :
Mason For Terrazo Work Each 2.16000 186.67 403.21
Beldar Each 3.78000 116.67 441.01
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Bhishti Each 0.54000 116.67 63.00
Beldar
(Skilled)for rubbing and polishing Each 9.72000 116.67 1134.03
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 2191.24
TOTAL : 2191.24
WATER CHARGES @ 1.5% : 58.77
TOTAL : 2250.01
ADD FOR CONTRACTORS PROFIT @10% : 225.00
ADD FOR OVER HEAD CHARGES@5% : 112.50
LABOUR FOR 10.000sq.m 2587.51
LABOUR PER sq.m 258.75
13010500 light shade pigment with
ordinary cement (in top layer
only)
Details of cost for 10 sqm
MATERIAL :
LABOUR RATE :
Labour As per item no:13010100 2582.25 (-a-)
TOTAL : 2582.25
Add for water charges except on ( -a- ) : 0.64
TOTAL : 2582.89
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a- ): 0.06
ADD FOR OVER HEAD CHARGES@5% EXCEPT ON ( -a- ): 0.03
LABOUR FOR10.000 sq.m 2582.98
LABOUR PER sq.m 258.30
13020000 40 mm thick marble chips
flooring rubbed and polished
to granolithic finish, under
layer 32 mm thick cement
concrete 1:2:4 (1 cement: 2
sand: 4 graded stone aggregate
10 mm and down gauge) and top
layer 8 mm thick marble chips
of required sizes laid in
cement marble powder mix 3:1
(3 cement : marble powder by
weight) in propontion of 4:7(4
cement marble powder mixed : 7
marble chips by volume).
MATERIAL :
CARRIAGE :
Sand|
1 KM BY MECH. TRANSPORT 1 cum 0.14400 110.95 15.98
Cement|
1 KM BY MECH. TRANSPORT 1 tonne 0.15500 73.95 11.46
Marble chips |
1 KM BY MECH. TRANSPORT 1 cum 0.07200 110.95 7.99
Marble powder|
1 KM BY MECH. TRANSPORT 1 cum 0.01200 110.95 1.33
LABOUR :
Mason For Terrazo Work Each 2.16000 186.67 403.21
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Beldar Each 3.78000 116.67 441.01
Bhishti Each 0.54000 116.67 63.00
Beldar
(Skilled)for rubbing and polishing Each 9.72000 116.67 1134.03
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 2191.24
TOTAL : 2191.24
WATER CHARGES @ 1.5% : 56.58
TOTAL : 2247.82
ADD FOR CONTRACTORS PROFIT @10% : 224.78
ADD FOR OVER HEAD CHARGES@5% : 112.39
LABOUR FOR 10.000sq.m 2584.99
LABOUR PER sq.m 258.50
13020200 light shade pigment with white
cement( in top layer only)
Detail of cost for 10 sqm
MATERIAL :
Total: 5138.92
Add for water charges @1.5% Except on (-I-) : 11.03
Total: 5149.95
ADD FOR CONTRACTORS PROFIT @10% Except on (-I-) : 74.68
ADD FOR OVER HEAD CHARGES@5% Except on (-I-): 37.34
COST FOR 10.000 sq.m 5261.97
COST PER sq.m 526.20
LABOUR RATE :
Labour As per item no:13020100 2584.99 (-a-)
TOTAL : 2584.99
Add for water charges except on (-a-) : 11.03
TOTAL : 2596.02
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a- ): 1.10
ADD FOR OVER HEAD CHARGES@5% EXCEPT ON ( -a- ): 0.55
LABOUR FOR10.000 sq.m 2597.67
LABOUR PER sq.m 259.75
13020300 Medium shade pigment with
approximate 50% white cement
and 50% ordinary cement (in
top layer only)
Details of cost for 10 sqm
MATERIAL :
Total: 4767.72
Add for water charges @1.5% Except on (-I-) : 5.48
Total: 4774.20
ADD FOR CONTRACTORS PROFIT @10% Except on (-I-) : 37.10
ADD FOR OVER HEAD CHARGES@5% Except on (-I-): 18.55
COST FOR 10.000 sq.m 4829.85
COST PER sq.m 483.00
LABOUR RATE :
Labour As per item no:13020100 2584.99 (-a-)
TOTAL : 2584.99
Add for water charges except on ( -a- ) : 5.48
TOTAL : 2590.47
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON ( -a- ): 0.55
ADD FOR OVER HEAD CHARGES@5% EXCEPT ON ( -a- ): 0.27
LABOUR FOR10.000 sq.m 2591.29
LABOUR PER sq.m 259.10
13020400 White cement without any
pigment (in top layer only)
Details of cost for 10 sqm
MATERIAL :
Sand
1 cum 0.14400 300.00 43.20
White cement
1 tonne 0.05200 18000.00 936.00
CARRIAGE :
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Sand|
1 KM BY MECH. TRANSPORT 1 cum 0.14400 110.95 15.98
Cement|
1 KM BY MECH. TRANSPORT 1 tonne 0.15530 73.95 11.48
Marble chips |
1 KM BY MECH. TRANSPORT 1 cum 0.07200 110.95 7.99
100 MTRS BY HEAD LOAD 1 cum 0.07200 54.35 3.91
LABOUR :
Mason For Terrazo Work Each 2.16000 186.67 403.21
Beldar Each 3.78000 116.67 441.01
Bhishti Each 0.54000 116.67 63.00
Beldar
(Skilled)for rubbing and polishing Each 9.72000 116.67 1134.03
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 2191.24
TOTAL : 2191.24
WATER CHARGES @ 1.5% : 62.40
TOTAL : 2253.64
ADD FOR CONTRACTORS PROFIT @10% : 225.36
ADD FOR OVER HEAD CHARGES@5% : 112.68
LABOUR FOR 10.000sq.m 2591.68
LABOUR PER sq.m 259.15
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
13020500 light shade pigment with
ordinary cement (in top layer
only)
Details of cost for 10 sqm
MATERIAL :
LABOUR RATE :
Labour As per item no:13020100 2584.99 (-a-)
TOTAL : 2584.99
Add for water charges except on ( -a-) : 0.82
TOTAL : 2585.81
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON ( -a-): 0.08
ADD FOR OVER HEAD CHARGES@5% EXCEPT ON (-a- ): 0.04
LABOUR FOR10.000 sq.m 2585.93
LABOUR PER sq.m 258.60
13030000 40 mm thick matble chips
flooring rupped and polished
to granolithic finesh, with
under layer 30 mm thick cement
concrete 1:2:4
(1 cement :2 sand: 4 graded
stone aggregate 10 mm and down
gauge) and top layer 10 mm
thick with marble chips of
required sazes laid in cement
marble powder mix 3:1 (3
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
cement : marble powder by
weight) in proportion of 4:7
(4 cement marble powder mix :
7 marble chips by volume).
MATERIAL :
Sand
1 cum 0.13600 300.00 40.80
Cement 1 tonne 0.09770 4900.00 478.73
Cement
1 tonne 0.06360 4900.00 311.64
Marble power.
1 cum 0.01400 1500.00 21.00
CARRIAGE :
Stone aggregate below 40mm.
1 KM BY MECH. TRANSPORT 1 cum 0.27200 110.95 30.18
Cement|
1 KM BY MECH. TRANSPORT 1 tonne 0.16130 73.95 11.93
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Marble chips |
1 KM BY MECH. TRANSPORT 1 cum 0.09200 110.95 10.21
Marble powder|
1 KM BY MECH. TRANSPORT 1 cum 0.01400 110.95 1.55
Sand|
1 KM BY MECH. TRANSPORT 1 cum 0.13600 110.95 15.09
LABOUR :
Mason For Terrazo Work each 2.16000 186.67 403.21
Beldar each 3.78000 116.67 441.01
Bhishti each 0.54000 116.67 63.00
Beldar
(Skilled)for rubbing and polishing each 9.72000 116.67 1134.03
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 2191.24
TOTAL : 2191.24
WATER CHARGES @ 1.5% : 58.88
TOTAL : 2250.12
ADD FOR CONTRACTORS PROFIT @10% : 225.01
ADD FOR OVER HEAD CHARGES@5% : 112.50
LABOUR FOR 10.000sq.m 2587.63
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR PER sq.m 258.75
13030200 light shade pigment with white
cement (in top layer only).
Details of cost for 10 sqm
MATERIAL :
Total: 5482.31
Add for water charges @1.5% Except on (-I-) : 13.50
Total: 5495.81
ADD FOR CONTRACTORS PROFIT @10% Except on (-I-) : 91.34
ADD FOR OVER HEAD CHARGES@5% Except on (-I-): 45.67
COST FOR 10.000 sqm. 5632.82
COST PER sqm. 563.30
LABOUR RATE :
Labour As per item no:13030100 2587.63 (-a-)
TOTAL : 2587.63
Add for water charges except on (-a-) : 13.50
TOTAL : 2601.13
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a- ): 1.35
ADD FOR OVER HEAD CHARGES@5% EXCEPT ON (-a- ): 0.67
LABOUR FOR10.000 sqm. 2603.15
LABOUR PER sqm. 260.30
13030300 Medium shade pigment with
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
approximate 50% white cement
and 50% ordinary cement (in
top layer only).
Details of cost for 10 sqm
MATERIAL :
LABOUR RATE :
Labour As per item no:13030100 2587.63 (-a-)
TOTAL : 2587.63
Add for water charges except on (-a-) : 6.92
TOTAL : 2594.55
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a- ): 0.69
ADD FOR OVER HEAD CHARGES@5% EXCEPT ON (-a- ): 0.35
LABOUR FOR10.000 sqm. 2595.59
LABOUR PER sqm. 259.55
13030400 White cement without any
pigment (in top layer only).
Details of cost for 10sqm
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
sand
1 cum 0.13600 300.00 40.80
cement
1 tonne 0.09770 4900.00 478.73
For 10mm thick top layer.
Marble chips. 1 quintal 1.60000 200.00 320.00
CARRIAGE :
Sand|
1 KM BY MECH. TRANSPORT 1 cum 0.13600 110.95 15.09
100 MTRS BY HEAD LOAD 1 cum 0.13600 54.35 7.39
Cement|
1 KM BY MECH. TRANSPORT 1 tonne 0.16130 73.95 11.93
Marble chips
1 KM BY MECH. TRANSPORT 1 cum 0.09500 110.95 10.54
LABOUR :
Mason For Terrazo Work each 2.16000 186.67 403.21
Beldar each 3.78000 116.67 441.01
Bhishti each 0.54000 116.67 63.00
Beldar
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
(Skilled)for rubbing and polishing each 9.72000 116.67 1134.03
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 2191.24
TOTAL : 2191.24
WATER CHARGES @ 1.5% : 66.09
TOTAL : 2257.33
ADD FOR CONTRACTORS PROFIT @10% : 225.73
ADD FOR OVER HEAD CHARGES@5% : 112.86
LABOUR FOR 10.000sq.m 2595.92
LABOUR PER sq.m 259.60
13030500 light shede pigment with
ordinary cement (in top layer
only). Details of cost for
10sqm
MATERIAL :
Cost same as per item No
13030100
10 sqm 10.00000 4582.40 4582.40 (-I-)
LABOUR RATE :
Labour As per item no:13030100 2587.63
TOTAL : 2587.63
Add for water charges except on (-a-) : 1.00
TOTAL : 2588.63
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a- ): 0.10
ADD FOR OVER HEAD CHARGES@5% EXCEPT ON (-a- ): 0.05
LABOUR FOR10.000 sqm. 2588.78
LABOUR PER sqm. 258.90
13040000 40mm. thick marble chips
flooring rubbed and polished
to granolithic finish with
under layer 28mm thick cement
concrete1:2:4(1cement:2sand
:4graded stone aggregate 10mm
and
down gauge) and top layer 12mm
thick with marble chips of
required sizes laid in cement
marble powder mix.3:1(3
cement:1 marble powder by
weight) in proportion of
4:7(4cement marble powder
mix:7 marble chips by volume).
Marble powder
1 cum 0.01700 1500.00 25.50
CARRIAGE :
Cement|
1 KM BY MECH. TRANSPORT 1 tonne 0.17070 73.95 12.62
Marble chips |
1 KM BY MECH. TRANSPORT 1 cum 0.10200 110.95 11.32
Marble powder|
1 KM BY MECH. TRANSPORT 1 cum 0.01700 110.95 1.89
100 MTRS BY HEAD LOAD 1 cum 0.01700 54.35 0.92
Sand|
1 KM BY MECH. TRANSPORT 1 cum 0.12500 110.95 13.86
LABOUR :
Mason For Terrazo Work Each 2.16000 186.67 403.21
Beldar Each 3.78000 116.67 441.01
Bhishti Each 0.54000 116.67 63.00
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Beldar
(Skilled)for rubbing and polishing Each 9.72000 116.67 1134.03
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 2191.24
TOTAL : 2191.24
WATER CHARGES @ 1.5% : 61.25
TOTAL : 2252.49
ADD FOR CONTRACTORS PROFIT @10% : 225.25
ADD FOR OVER HEAD CHARGES@5% : 112.62
LABOUR FOR 10.000sqm. 2590.36
LABOUR PER sqm. 259.00
13040200 light shade pigment with white
cement (in top layer only)
Details of cost for 10 sqm
MATERIAL :
Total: 5912.35
Add for water charges @1.5% Except on (-I-) : 17.19
Total: 5929.54
ADD FOR CONTRACTORS PROFIT @10% Except on (-I-) : 116.33
ADD FOR OVER HEAD CHARGES@5% Except on (-I-): 58.16
COST FOR 10.000 sqm. 6104.03
COST PER sqm. 610.40
LABOUR RATE :
Labour As per item no:13040100 2590.36 (-a-)
TOTAL : 2590.36
Add for water charges except on (-a-) : 17.19
TOTAL : 2607.55
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a- ): 1.72
ADD FOR OVER HEAD CHARGES@5% EXCEPT ON (-a- ): 0.86
LABOUR FOR10.000 sqm. 2610.13
LABOUR PER sqm. 261.00
13040300 Meduim shade pigment with
approximate 50% white cement
and
50% ordinary cement(in top
layer only)
Detail of cost for 10 sqm.
MATERIAL :
Total: 5353.45
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Add for water charges @1.5% Except on (-I-) : 8.80
Total: 5362.25
ADD FOR CONTRACTORS PROFIT @10% Except on (-I-) : 59.60
ADD FOR OVER HEAD CHARGES@5% Except on (-I-): 29.80
COST FOR 10.000 sqm. 5451.65
COST PER sqm. 545.15
LABOUR RATE :
Labour As per item no:13040100 2590.36 (-a-)
TOTAL : 2590.36
Add for water charges except on (-a-) : 8.80
TOTAL : 2599.16
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a- ): 0.88
ADD FOR OVER HEAD CHARGES@5% EXCEPT ON (-a- ): 0.44
LABOUR FOR10.000 sqm. 2600.48
LABOUR PER sqm. 260.00
13040400 White cement without any
pigment (in top layer only).
Details of cost for 10 sqm
MATERIAL :
Sand.
1 cum 0.12500 300.00 37.50
Cement.
1 tonne 0.08970 4900.00 439.53
CARRIAGE :
Cement|
1 KM BY MECH. TRANSPORT 1 tonne 0.17070 73.95 12.62
Sand|
1 KM BY MECH. TRANSPORT 1 cum 0.12500 110.95 13.87
Marble chips |
1 KM BY MECH. TRANSPORT 1 cum 0.11280 110.95 12.52
LABOUR :
Mason For Terrazo Work Each 2.16000 186.67 403.21
Beldar Each 3.78000 116.67 441.01
Bhishti Each 0.54000 116.67 63.00
Beldar
(Skilled)for rubbing and polishing Each 9.72000 116.67 1134.03
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 2191.24
TOTAL : 2191.24
WATER CHARGES @ 1.5% : 70.85
TOTAL : 2262.09
ADD FOR CONTRACTORS PROFIT @10% : 226.20
ADD FOR OVER HEAD CHARGES@5% : 113.10
LABOUR FOR 10.000sq.m. 2601.39
LABOUR PER sq.m. 260.15
13040500 Light shade pigment with
ordinary
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
cement (in top layer only)
Details of cost for 10 sqm
MATERIAL :
LABOUR RATE :
Labour As per item no:13040100 2590.36 (-a-)
TOTAL : 2590.36
Add for water charges except on (-a-) : 1.28
TOTAL : 2591.64
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a- ): 0.12
ADD FOR OVER HEAD CHARGES@5% EXCEPT ON (-a- ): 0.06
LABOUR FOR10.000 sqm. 2591.82
LABOUR PER sqm. 259.20
13050000 Marble chips skirting or dado
upto
30 cm. height (rubbed and
polished to granolithic finish
laid in cement marble powder mix
3:1 (3 cement : 1 Marble powder by weight)
in proportion of
4:7 (4cement marble powder
mix: 7 marble chips by volume)
in top layer:-
MATERIAL :
cement
1 cum 0.04050 4900.00 198.45
marble powder
1 cum 0.00700 1500.00 10.50
Marble chips
1 KM BY MECH. TRANSPORT 1 cum 0.05100 110.95 5.66
Cement
1 KM BY MECH. TRANSPORT 1 tonne 0.04050 73.95 2.99
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Marble powder|
1 KM BY MECH. TRANSPORT 1 cum 0.00700 110.95 0.78
.
100 MTRS BY HEAD LOAD 1 cum 0.00700 54.35 0.38
Trans. carr.of pigment L.S 0.20
Manual carr. of pigment 0.10
LABOUR :
Mason For Terrazo Work Each 2.70000 186.67 504.00
Beldar Each 4.05000 116.67 472.51
Bhishti Each 0.55000 116.67 64.17
Beldar
(Skilled)for rubbing and polishing Each 9.70000 116.67 1131.70
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 2322.37
Labour for cement mortar 1:3 24.77
TOTAL : 2347.14
WATER CHARGES @ 1.5% : 80.00
TOTAL : 2427.14
ADD FOR CONTRACTORS PROFIT @10% : 242.71
ADD FOR OVER HEAD CHARGES@5% : 121.35
LABOUR FOR 10.000sqm. 2791.20
LABOUR PER sqm. 279.10
13050102 light shade pigment with white
cement (in top layer only)
Details of cost for 10 sq.m
MATERIAL :
Total: 6797.44
Add for water charges @1.5% Except on (-I-) : 8.60
Total: 6806.04
ADD FOR CONTRACTORS PROFIT @10% Except on (-I-) : 58.17
ADD FOR OVER HEAD CHARGES@5% Except on (-I-): 29.08
COST FOR 10.000 sqm. 6893.29
COST PER sqm. 689.30
LABOUR RATE :
Labour As per item no: 2791.20 (-a-)
TOTAL : 2791.20
Add for water charges except on (-a-) : 8.60
TOTAL : 2799.80
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON ( -a-): 0.86
ADD FOR OVER HEAD CHARGES@5% EXCEPT ON (-a- ): 0.43
LABOUR FOR10.000 sqm. 2801.09
LABOUR PER sqm. 280.10
13050103 Medium shade pigment with
approximate 50 % white cement
and 50 % ordinary cement (in
top layer only)
Details of cost for 10 sq.m.
MATERIAL :
Total: 6517.31
Add for water charges @1.5% Except on (-I-) : 4.39
Total: 6521.70
ADD FOR CONTRACTORS PROFIT @10% Except on (-I-) : 29.74
ADD FOR OVER HEAD CHARGES@5% Except on (-I-): 14.87
COST FOR 10.000 sqm. 6566.31
COST PER sqm. 656.60
LABOUR RATE :
Labour As per item no:13050101 2791.20 (-a-)
TOTAL : 2791.20
Add for water charges except on (-a-) : 4.39
TOTAL : 2795.59
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a- ): 0.44
ADD FOR OVER HEAD CHARGES@5% EXCEPT ON (-a- ): 0.22
LABOUR FOR10.000 sqm. 2796.25
LABOUR PER sqm. 279.60
13050104 White cement without any
pigment (in top layer only)
Details of cost for 10 sq.m.
MATERIAL :
White cement
1 tonne 0.04050 18000.00 729.00
CARRIAGE :
Marble chips |
1 KM BY MECH. TRANSPORT 1 cum 0.05600 110.95 6.21
Cement|
1 KM BY MECH. TRANSPORT 1 tonne 0.04050 73.95 2.99
LABOUR :
Mason For Terrazo Work Each 2.70000 186.67 504.01
Beldar Each 4.05000 116.67 472.51
Beldar
(Skilled)for rubbing and polishing Each 9.70000 116.67 1131.70
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 2258.21
Labour for cement mortar 1:3 24.77
TOTAL : 2282.98
WATER CHARGES @ 1.5% : 34.24
TOTAL : 2317.22
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR CONTRACTORS PROFIT @10% : 231.72
ADD FOR OVER HEAD CHARGES@5% : 115.86
LABOUR FOR 10.000sqm. 2664.80
LABOUR PER sqm. 266.50
13050105 light shade pigment with
ordinary cement (in top layer
only)
Details of cost for 10 sq.m.
MATERIAL :
Total: 6266.89
Add for water charges @1.5% Except on (-I-) : 0.64
Total: 6267.53
ADD FOR CONTRACTORS PROFIT @10% Except on (-I-) : 4.32
ADD FOR OVER HEAD CHARGES@5% Except on (-I-): 2.16
COST FOR 10.000 sqm. 6274.01
COST PER sqm. 627.40
LABOUR RATE :
Labour As per item no:13050101 2791.20 (-a-)
TOTAL : 2791.20
Add for water charges except on (-a-) : 0.64
TOTAL : 2791.84
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a- ): 0.06
ADD FOR OVER HEAD CHARGES@5% EXCEPT ON (-a- ): 0.03
LABOUR FOR10.000 sqm. 2791.93
LABOUR PER sqm. 279.20
13050200 22 mm.thick with under layer
15mm.
thick cement plaster 1:3
(1cement
:3 sand) and top layer
7mm.thick.
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
cement
1 tonne 0.04630 4900.00 226.87
marble powder
1 cum 0.00900 1500.00 13.50
CARRIAGE :
Marble chips |
1 KM BY MECH. TRANSPORT 1 cum 0.06100 110.95 6.77
Cement|
1 KM BY MECH. TRANSPORT 1 tonne 0.04630 73.95 3.42
Marble powder|
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
1 KM BY MECH. TRANSPORT 1 cum 0.00900 110.95 1.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 2322.37
Labour for cement mortar 1:3 25.12
TOTAL : 2347.29
WATER CHARGES @ 1.5% : 35.20
TOTAL : 2382.49
ADD FOR CONTRACTORS PROFIT @10% : 238.25
ADD FOR OVER HEAD CHARGES@5% : 119.12
LABOUR FOR 10.000sqm. 2739.86
LABOUR PER sqm. 274.00
13050202 Light shade pigment with white
cement.(in top layer only)
Details of cost for 10 sq.m
MATERIAL :
Total: 4944.04
Add for water charges @1.5% Except on (-I-) : 9.82
Total: 4953.86
ADD FOR CONTRACTORS PROFIT @10% Except on (-I-) : 66.50
ADD FOR OVER HEAD CHARGES@5% Except on (-I-): 33.25
COST FOR 10.000 sq.m. 5053.61
COST PER sq.m. 505.35
LABOUR RATE :
Labour As per item no:13050201 2739.86 (-a-)
TOTAL : 2739.86
Add for water charges except on (-a-) : 9.82
TOTAL : 2749.68
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a- ): 0.98
ADD FOR OVER HEAD CHARGES@5% EXCEPT ON (-a- ): 0.49
LABOUR FOR10.000 sq.m. 2751.15
LABOUR PER sq.m. 275.10
13050203 Medium shade pigment with
approximate 50% white cement
and 50% ordinary cement (in
top layer only)
Details of cost for 10 sq.m
MATERIAL :
Total: 4623.92
Add for water charges @1.5% Except on (-I-) : 5.03
Total: 4628.95
ADD FOR CONTRACTORS PROFIT @10% Except on (-I-) : 34.00
ADD FOR OVER HEAD CHARGES@5% Except on (-I-): 19.00
COST FOR 10.000 sqm. 4679.95
COST PER sqm. 468.00
LABOUR RATE :
Labour As per item no:13050201 2739.86 (-a-)
TOTAL : 2739.86
Add for water charges except on (-a-) : 5.03
TOTAL : 2744.89
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a- ): 0.50
ADD FOR OVER HEAD CHARGES@5% EXCEPT ON (-a- ): 0.25
LABOUR FOR10.000 sqm. 2745.64
LABOUR PER sqm. 274.55
13050204 White cement without ant
pigment (in top layer only)
Detials of cost for 10 sq.m
MATERIAL :
White cement
1 cum 0.04630 18000.00 833.40
CARRIAGE :
Marble chips |
1 KM BY MECH. TRANSPORT 1 cum 0.06600 110.95 7.32
LABOUR :
Mason For Terrazo Work Each 2.70000 186.67 504.01
Beldar Each 4.05000 116.67 472.51
Bhishti Each 0.55000 116.67 64.17
Beldar
(Skilled)for rubbing and polishing Each 9.70000 116.67 1131.70
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 2212.37
Labour for cement mortar 1:3 25.92
TOTAL :1143.71 2238.29
WATER CHARGES @ 1.5% : 58.91
TOTAL : 2297.20
ADD FOR CONTRACTORS PROFIT @10% : 229.72
ADD FOR OVER HEAD CHARGES@5% : 114.86
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR FOR 10.000sqm. 2641.78
LABOUR PER sqm. 264.15
13050205 light shade pigment with
ordinary cement (in top layer
only)
Details of cost fot 10 sq.m
MATERIAL :
Total: 4337.51
Add for water charges @1.5% Except on (-I-) : 0.74
Total: 4338.25
ADD FOR CONTRACTORS PROFIT @10% Except on (-I-) : 4.93
ADD FOR OVER HEAD CHARGES@5% Except on (-I-): 2.46
COST FOR 10.000 sqm. 4345.64
COST PER sqm. 434.55
LABOUR RATE :
Labour As per item no:13050201 2739.86 (-a-)
TOTAL : 2739.86
Add for water charges except on (-a-) : 0.74
TOTAL : 2740.60
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a- ): 0.07
ADD FOR OVER HEAD CHARGES@5% EXCEPT ON (-a- ): 0.03
LABOUR FOR10.000 sqm. 2740.70
LABOUR PER sqm. 274.10
13060000 Extra for work in dado
exceeding 30 cm. in height:-
LABOUR :
Mason 2nd Class Each 0.20000 158.67 31.73
Beldar Each 0.40000 116.67 46.67
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 83.39
TOTAL : 83.39
WATER CHARGES @ 1.5% : 1.25
TOTAL : 84.64
ADD FOR CONTRACTORS PROFIT @10% : 8.46
ADD FOR OVER HEAD CHARGES@5% : 4.23
LABOUR FOR1.000sqm. 97.23
LABOUR PER sqm. 97.30
13060200 22 mm thick with under layer
15 mm thick cement plaster 1:3
(1 cement :3 sand)
Details of cost for per sq.m
LABOUR :
Mason 2nd Class. Each 0.20000 158.67 31.73
Beldar Each 0.40000 116.67 46.67
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 83.39
TOTAL : 83.39
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
WATER CHARGES @ 1.5% : 1.25
TOTAL : 84.64
ADD FOR CONTRACTORS PROFIT @10% : 8.46
ADD FOR OVER HEAD CHARGES@5% : 4.23
LABOUR FOR1.000Sq.m 97.33
LABOUR PER Sq.m 97.30
13070000 Extra for providing and fixing
aluminium strips 40 mm wide
and 1.5 mm thick painted with
a protective coat of bitumen
in joints of terrazzo floors.
Details of cost for 10sq.m.
MATERIAL :
ALUMINIUM SHEET
strips=10x0.04=0.40 sqm.
Add for wastage charges @ 5%
=0.02sqm.
-----------
=0.42sqm.
@ 4.12 kg.per sq.metre 1.73kg
1 kg 1.73000 200.00 346.00
CARRIAGE :
Aluminium Sheet|
1 KM BY MECH. TRANSPORT 1 tonne 0.00173 73.95 0.13
LABOUR :
Mason 2nd Class Each 0.25000 158.67 39.67
Beldar Each 0.25000 116.67 29.17
Total: 426.52
Add for water charges @1.5% Except on (-I-) : 6.28
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Total: 432.80
ADD FOR CONTRACTORS PROFIT @10% Except on (-I-) 42.53
ADD FOR OVER HEAD CHARGES@5% Except on (-I-) 21.26
COST FOR 10.000 sqm. 496.59
COST PER sqm. 49.65
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 72.82
Labour As per item no:160180000 3.84
TOTAL : 76.66
Add for water charges except on ( -a- ): 1.10
TOTAL : 77.76
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a- ): 7.39
ADD FOR OVER HEAD CHARGES@5% EXCEPT ON (-a- ): 3.69
LABOUR FOR10.000 sqm. 88.84
LABOUR PER sqm. 8.90
13080000 Extra for providing and fixing
glass strips in joints of
terrazzo floors.
LABOUR :
Mason 2nd Class Each 0.25000 158.67 39.67
Beldar Each 0.25000 116.67 29.17
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 72.82
TOTAL : 72.82
WATER CHARGES @ 1.5% : 4.42
TOTAL : 17.24
ADD FOR CONTRACTORS PROFIT @10% : 7.72
ADD FOR OVER HEAD CHARGES@5% : 3.86
LABOUR FOR 10.000Metre 88.82
LABOUR PER Metre 8.90
13080200 40 mm.wide and 6 mm.thick.
Details of cost for 10
Mtr.Length.
MATERIAL :
LABOUR :
Mason 2nd class Each 0.25000 158.67 39.67
Beldar Each 0.25000 116.67 29.16
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 72.82
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 72.82
WATER CHARGES @ 1.5% : 6.07
TOTAL : 78.89
ADD FOR CONTRACTORS PROFIT @10% : 7.88
ADD FOR OVER HEAD CHARGES@5% : 3.94
LABOUR FOR 10.000Metre 90.71
LABOUR PER Metre 9.05
13090000 Extra for providing and fixing
plastic strips in joints of
terrazzo floors.
Details of cost for 10
Mtr.length.
MATERIAL :
---------------
Total=11.00 metre
1 metre 11.00000 10.00 110.00
CARRIAGE :
Carriage ofplastic-strips L.S 1.00
LABOUR :
Mason 2nd Class Each 0.25000 158.67 39.67
Beldar Each 0.25000 116.67 29.17
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 72.82
TOTAL : 72.82
WATER CHARGES @ 1.5% : 2.75
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 75.57
ADD FOR CONTRACTORS PROFIT @10% : 7.55
ADD FOR OVER HEAD CHARGES@5% : 3.77
LABOUR FOR 10.000Metre 86.89
LABOUR PER Metre 8.70
13100000 Extra for terrazzo flooring
laid as floor borders, margins
and similar bands exceeding
7.5 cm. but not exceeding 30
cms in width.
LABOUR :
Mason For Terrazo Work Each 0.20000 186.67 37.33
Beldar Each 0.40000 116.67 46.67
TOTAL : 84.00
ADD FOR WATER CHARGES @ 1.5% : 1.25
TOTAL: 85.25
ADD FOR CONTRACTORS PROFIT @10% :. 8.52
ADD FOR OVER HEAD CHARGES@5% : 4.26
COST FOR 10.000 sqm. 98.03
COST PER sqm. 9.80
LABOUR PER sqm. 9.80
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 84.00
TOTAL : 84.00
WATER CHARGES @ 1.5% : 1.25
TOTAL : 85.25
ADD FOR CONTRACTORS PROFIT @10% : 8.52
ADD FOR OVER HEAD CHARGES@5% : 4.26
LABOUR FOR 10.000sqm. 98.03
LABOUR PER sqm. 9.80
13110000 Extra for laying terrazzo
flooring
on staircase treads not
exceeding
30 cm.in width including the
cost
of forming and nosing etc.
Details of cost for 10 Sq.m.
LABOUR :
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Mason For Terrazo Work Each 0.30000 186.67 56.00
Beldar Each 0.60000 116.67 70.00
TOTAL : 126.00
ADD FOR WATER CHARGES @ 1.5% : 1.90
TOTAL: 127.90
ADD FOR CONTRACTORS PROFIT @10% : 12.79
ADD FOR OVER HEAD CHARGES@5% : 6.40
COST FOR 10.000 sqm. 147.09
COST PER sqm. 14.70
LABOUR PER sqm. 14.70
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 126.00
TOTAL : 126.00
WATER CHARGES @ 1.5% : 1.90
TOTAL : 127.90
ADD FOR CONTRACTORS PROFIT @10% : 12.79
ADD FOR OVER HEAD CHARGES@5% : 6.40
LABOUR FOR 10.000sqm. 147.09
LABOUR PER sqm. 14.70
13120000 Extra for laying terrazzo
flooing in narrow bands not
exceeding 7.5 cms in width.
Details of cost for 5cm. band
200 Metres long.
LABOUR :
Mason For Terrazo Work Each 0.50000 186.67 93.34
Beldar Each 0.75000 116.67 87.50
TOTAL : 180.83
ADD FOR WATER CHARGES @ 1.5% : 2.71
TOTAL: 183.54
ADD FOR CONTRACTORS PROFIT @10% : 18.35
ADD FOR OVER HEAD CHARGES@5% : 9.17
COST FOR 10.000 sqm. 211.07
COST PER sqm. 21.10
LABOUR PER sqm. 21.10
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 180.83
TOTAL : 180.83
WATER CHARGES @ 1.5% : 2.71
TOTAL : 183.54
ADD FOR CONTRACTORS PROFIT @10% : 18.35
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR OVER HEAD CHARGES@5% : 9.17
LABOUR FOR 10.000sqm. 211.05
LABOUR PER sqm. 21.10
13130000 Extra for making moulded
nosing in terrazzo including
returned moulded ends and
angles to mouldings.
Details of cost for 10
Mtrs.length
LABOUR :
Mason For Terrazo Work Each 1.00000 186.67 186.67
Beldar Each 1.25000 116.67 145.84
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 352.50
TOTAL : 352.50
WATER CHARGES @ 1.5% : 5.28
TOTAL : 357.78
ADD FOR CONTRACTORS PROFIT @10% : 35.78
ADD FOR OVER HEAD CHARGES@5% : 17.89
LABOUR FOR 10.000Metre 409.45
LABOUR PER Metre 40.95
13140000 Special surface finishing to
treads, risers and the ends of
concrete steps and the like
including form work.
Details of cost for an area
of 10 sq.m.
MATERIAL :
CARRIAGE :
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Cement
1 KM BY MECH. TRANSPORT 1 tonne 0.02200 73.95 1.63
LABOUR :
Mason 1st class each 0.25000 211.16 52.79
Beldar each 0.25000 116.67 29.17
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 86.95
TOTAL : 86.95
WATER CHARGES @ 1.5% : 3.10
TOTAL : 90.05
ADD FOR CONTRACTORS PROFIT @10% : 9.00
ADD FOR OVER HEAD CHARGES@5% : 4.50
LABOUR FOR 10.000sqm. 103.55
LABOUR PER sqm. 10.35
13150000 Extra for treating the surface
with bees wax.
Details of cost for 10 sq.m
MATERIAL :
Max polish
1 kg 0.10000 250.00 25.00
Acetic acid, soap,cloth etc. L.S 1.00
CARRIAGE :
Carriage of wax polish L.S 0.50
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR :
Painter 1st Class Each 0.40000 148.16 59.26
Beldar Each 0.40000 116.67 46.67
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 110.92
TOTAL : 110.92
WATER CHARGES @ 1.5% : 2.06
TOTAL : 112.98
ADD FOR CONTRACTORS PROFIT @10% : 11.30
ADD FOR OVER HEAD CHARGES@5% : 5.65
LABOUR FOR 10.000sqm. 129.92
LABOUR PER sqm. 13.00
13160000 Precast terrazzo tiles hydraulic compressed 20 mm
thick with marble chips of
specified sizes laid in floors
treads of steps and landings
on a bed of 25 mm average
thickness of cement mortar 1:6
(1 cement :6 sand) jointed
with neat cement slurry mixed
with pigment to match the
shade of tiles(wherever
required) incliding rubbing
and polishing complete with
tiles of following shades:-
13160100 GREY.
Details of cost for 10 Sq.m.
MATERIAL :
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Terrazzo tiles including 10% 1sq.m 11.00000 270.00 2970.00
wastage.
CARRIAGE :
Terrazo tiles. |
1 KM BY MECH. TRANSPORT 1000 nos 171.0000 221.90 37944.90
Cement|
1 KM BY MECH. TRANSPORT 1 tonne 0.08800 73.95 6.51
LABOUR :
Mason For Terrazo Work Each 2.16000 186.67 403.21
Beldar Each 2.16000 116.67 252.01
Bhishti Each 0.30000 116.67 35.00
Floor Polisher Each 6.50000 148.16 963.04
MATERIAL :
CARRIAGE :
Terrazo tiles. |
1 KM BY MECH. TRANSPORT 1000 nos.171.0000 221.90 37.95
Cement|
1 KM BY MECH. TRANSPORT 1 tonne 0.08800 73.75 6.50
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1753.20
Labour for cement mortar 1:6 32.72
TOTAL : 1785.92
WATER CHARGES @ 1.5% : 94.73
TOTAL : 1880.65
ADD FOR CONTRACTORS PROFIT @10% : 188.06
ADD FOR OVER HEAD CHARGES@5% : 94.03
LABOUR FOR 10.000sqm. 2162.74
LABOUR PER sqm. 216.25
13160300 WHITE.
Details of cost for 10 sq.m
MATERIAL :
CARRIAGE :
Terrazo tiles. |
1 KM BY MECH. TRANSPORT 1000 nos.171.0000 221.90 37944.90
Cement|
1 KM BY MECH. TRANSPORT 1 tonne 0.08800 73.95 6.51
LABOUR :
Mason For Terrazo Work Each 2.16000 186.67 403.21
Beldar Each 2.16000 116.67 252.01
Floor Polisher Each 6.50000 148.16 963.04
Bhishti Each 0.30000 116.67 35.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1753.24
Labour for cement mortar 1:6 32.72
TOTAL : 1785.96
WATER CHARGES @ 1.5% : 110.61
TOTAL : 1896.57
ADD FOR CONTRACTORS PROFIT @10% : 189.65
ADD FOR OVER HEAD CHARGES@5% : 94.82
LABOUR FOR 10.000sqm. 2181.04
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR PER sqm. 218.10
13160400 MEDIUM.
Details of cost for 10 sq.m
Material :
CARRIAGE :
Terrazo tiles.
1 KM BY MECH. TRANSPORT 1000 nos.171.0000 221.90 37.95
Cement|
1 KM BY MECH. TRANSPORT 1 tonne 0.08800 73.95 6.51
LABOUR :
Mason For Terrazo Work Each 2.16000 186.67 403.21
Beldar Each 2.16000 116.67 252.01
Bhishti Each 0.30000 116.67 35.00
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Floor Polisher Each 6.50000 148.16 963.04
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1818.79
Labour for cement mortar 1:6 32.72
TOTAL : 1851.51
WATER CHARGES @ 1.5% : 98.68
TOTAL : 1980.19
ADD FOR CONTRACTORS PROFIT @10% : 195.01
ADD FOR OVER HEAD CHARGES@5% : 97.50
LABOUR FOR 10.000sqm. 2242.71
LABOUR PER sqm. 224.25
13160500 DARK.
Details of cost for 10 sq.m.
MATERIAL :
Grey Cement
For slurry 4.4 kg/sqm =44kg
For grouting=44kg
-----------
Total=88kg
1 tonne 0.08800 4900.00 431.20
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
CARRIAGE :
Terrazo tiles. |
1 KM BY MECH. TRANSPORT 1000 nos 171.0000 221.90 37.95
LABOUR :
Mason For Terrazo Work Each 2.16000 186.67 403.21
Beldar Each 2.16000 116.67 252.01
Bhishti Each 0.30000 116.67 35.00
Floor Polisher Each 6.50000 148.16 963.04
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1753.24
Labour for cement mortar 1:6 32.72
TOTAL : 1785.96
WATER CHARGES @ 1.5% : 100.00
TOTAL : 1885.96
ADD FOR CONTRACTORS PROFIT @10% : 188.80
ADD FOR OVER HEAD CHARGES@5% : 94.30
LABOUR FOR 10.000sqm. 2168.86
LABOUR PER sqm. 216.90
13170000 Extra, if terrazzo tiles are
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
laid in tread not exceeding 30
cm in width.
Details of cost for 10 sq.m
LABOUR :
Beldar Each 0.44000 116.67 51.33
Floor Polisher Each 0.65000 148.16 96.30
TOTAL : 147.63
ADD FOR WATER CHARGES @ 1.5% : 2.21
TOTAL: 149.84
ADD FOR CONTRACTORS PROFIT @10% : 14.98
ADD FOR OVER HEAD CHARGES@5% : 7.49
COST FOR 10.000 sqm. 172.31
COST PER sqm. 17.25
LABOUR PER sqm. 17.25
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 147.63
TOTAL : 147.63
WATER CHARGES @ 1.5% : 2.21
TOTAL : 149.84
ADD FOR CONTRACTORS PROFIT @10% : 14.98
ADD FOR OVER HEAD CHARGES@5% : 7.49
LABOUR FOR 10.000sqm. 172.31
LABOUR PER sqm. 17.25
13180000 Precast terrazzo tiles hydraulic compressed 20 mm
thick (with marble chips of
specified sizes) fixed on wall
on 10 mm thick cement plaster
1:3 (1 cement:3 sand) jointed
with neat cement slurry mixed
with pigment to match the
shade of tiles (wherever
required) including rubbing
and polishing complete with
tiles of following shades:-
13180100 GREY.
Details of cost for 10 Sq.m.
MATERIAL :
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
20mm thick terrazzo tiles
including 10% wastage etc.
1 sqm. 11.00000 270.00 2970.00
Terrazo tiles.
1 KM BY MECH. TRANSPORT 1000 nos 171.0000 221.90 37.95
Cement|
1 KM BY MECH. TRANSPORT 1 tonne 0.06600 73.95 4.88
LABOUR :
Mason For Terrazo Work Each 3.00000 186.67 560.01
Beldar Each 3.00000 116.67 350.01
Floor Polisher Each 7.30000 148.16 1081.57
MATERIAL :
CARRIAGE :
Terrazo tiles. |
1 KM BY MECH. TRANSPORT 1000 nos 171.000 221.90 37.95
Cement|
1 KM BY MECH. TRANSPORT 1 tonne 0.06600 73.95 4.88
LABOUR :
Mason For Terrazo Work Each 3.00000 186.67 560.01
Beldar Each 3.00000 116.67 350.01
Floor Polisher Each 7.30000 148.16 1081.57
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 2091.58
Labour for cement mortar 1:3 15.40
TOTAL : 2106.98
WATER CHARGES @ 1.5% : 98.86
TOTAL : 2205.84
ADD FOR CONTRACTORS PROFIT @10% : 220.58
ADD FOR OVER HEAD CHARGES@5% : 110.29
LABOUR FOR 10.000sqm. 2536.71
LABOUR PER sqm. 253.65
13180300 WHITE.
Details fo cost for 10 sq.m
MATERIAL :
CARRIAGE :
Terrazo tiles. |
1 KM BY MECH. TRANSPORT 1000 nos. 171.000 221.90 37.95
Cement|
1 KM BY MECH. TRANSPORT 1 tonne 0.06600 73.95 4.88
LABOUR :
Mason For Terrazo Work Each 3.00000 186.67 560.01
Beldar Each 3.00000 116.67 350.01
Floor Polisher Each 7.30000 148.16 1081.57
SUNDRIES : L.S. 100.00
TOTAL : 7360.96
ADD FOR WATER CHARGES @ 1.5% : 110.40
TOTAL: 7471.36
ADD FOR CONTRACTORS PROFIT 10% 747.13
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 2091.58
Labour for cement mortar 1:3 15.40
TOTAL : 2106.98
WATER CHARGES @ 1.5% : 110.40
TOTAL : 2227.38
ADD FOR CONTRACTORS PROFIT @10% : 222.73
ADD FOR OVER HEAD CHARGES@5% : 111.36
LABOUR FOR 10.000sqm. 2561.48
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR PER sqm. 256.15
13180400 MEDIUM.
Details of cost for 10 sq.m
MATERIAL :
CARRIAGE :
Terrazo tiles. |
1 KM BY MECH. TRANSPORT 1000 nos. 171.000 221.90 37.95
Cement|
1 KM BY MECH. TRANSPORT 1 tonne 0.06600 73.95 4.88
LABOUR :
Mason For Terrazo Work Each 3.00000 186.67 560.01
Beldar Each 3.00000 116.67 350.01
Floor Polisher Each 7.30000 148.16 1081.57
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 2091.58
Labour for cement mortar 1:3 15.40
TOTAL : 2106.98
WATER CHARGES @ 1.5% : 104.76
TOTAL : 2211.74
ADD FOR CONTRACTORS PROFIT @10% : 221.17
ADD FOR OVER HEAD CHARGES@5% : 110.58
LABOUR FOR 10.000sqm. 2543.49
LABOUR PER sqm. 254.35
13180500 DARK.
Details of cost for 10 sq.m
MATERIAL :
=22kg.
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
-----------
----------=4.62kg
1 kg 4.62000 75.00 346.50
CARRIAGE :
Terrazo tiles.
1 KM BY MECH. TRANSPORT 1000 nos. 171.000 221.90 37944.90
Cement
1 KM BY MECH. TRANSPORT 1 tonne 0.06600 73.95 4.88
LABOUR :
Mason For Terrazo Work Each 3.00000 186.67 560.01
Beldar Each 3.00000 116.67 350.01
Floor Polisher Each 7.30000 148.16 1081.57
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 2091.58
Labour for cement mortar 1:3 15.40
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 2106.98
WATER CHARGES @ 1.5% : 97.59
TOTAL : 2204.57
ADD FOR CONTRACTORS PROFIT @10% : 220.45
ADD FOR OVER HEAD CHARGES@5% : 110.22
LABOUR FOR 10.000sqm. 2535.25
LABOUR PER sqm. 253.50
13190000 Precast terrazzo tiles 20 mm
thick (with marble chips of
specified sizes) in skirting
and risers of steps not
exceeding 30 cm in height on
10 mm thick cement plaster 1:3
(1 cement: 3 sand)jointed with
neat cement slurry mixed with
pigment to match the shade of
tiles (wherever
required)including rubbing and
polishing complete with tiles
of following shades.:-
13190100 GREY
Details of cost for 10 Sq.m.
MATERIAL :
CARRIAGE :
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Terrazo tiles. |
1 KM BY MECH. TRANSPORT 1000 nos 171.000 221.90 37.95
Cement
1 KM BY MECH. TRANSPORT 1 tonne 0.06600 73.95 4.88
LABOUR :
Mason For Terrazo Work Each 3.25000 186.67 606.68
Beldar Each 3.25000 116.67 379.18
Floor Polisher Each 7.60000 148.16 1126.02
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 2211.85
Labour for cement mortar 1:3 15.40
TOTAL : 2227.25
WATER CHARGES @ 1.5% : 89.23
TOTAL : 2316.48
ADD FOR CONTRACTORS PROFIT @10% : 231.65
ADD FOR OVER HEAD CHARGES@5% : 115.82
LABOUR FOR 10.000sqm. 2663.95
LABOUR PER sqm. 266.40
13190200 SILVER GREY.
Details of cost for 10 sq.m
MATERIAL :
CARRIAGE :
Terrazo tiles. |
1 KM BY MECH. TRANSPORT 1000 nos 171.000 221.90 37.95
Cement
1 KM BY MECH. TRANSPORT 1 tonne 0.06600 73.95 4.88
LABOUR :
Mason For Terrazo Work Each 3.25000 186.67 606.68
Beldar Each 3.25000 116.67 379.18
Floor Polisher Each 7.60000 148.16 1126.02
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 2211.85
Labour for cement mortar 1:3 15.40
TOTAL : 2217.25
WATER CHARGES @ 1.5% : 100.67
TOTAL : 2327.92
ADD FOR CONTRACTORS PROFIT @10% : 232.79
ADD FOR OVER HEAD CHARGES@5% : 116.40
LABOUR FOR 10.000sqm. 2561.33
LABOUR PER sqm. 256.15
13190300 WHITE.
Details of cost for 10 sq.m
MATERIAL :
CARRIAGE :
Terrazo tiles. |
1 KM BY MECH. TRANSPORT 1000 nos 171.000 221.90 37.95
Cement|
1 KM BY MECH. TRANSPORT 1 tonne 0.06600 73.95 4.88
100 MTRS BY HEAD LOAD 1 tonne 0.06600 31.20 2.06
LABOUR :
Mason For Terrazo Work Each 3.25000 186.67 606.68
Beldar Each 3.24000 116.67 378.01
Floor Polisher Each 7.60000 148.16 1126.02
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 2211.85
Labour for cement mortar 1:3 15.40
TOTAL : 2226.25
WATER CHARGES @ 1.5% : 112.18
TOTAL : 2338.43
ADD FOR CONTRACTORS PROFIT @10% : 233.84
ADD FOR OVER HEAD CHARGES@5% : 116.92
LABOUR FOR 10.000sqm. 2689.19
LABOUR PER sqm. 268.90
13190400 MEDIUM.
Details of cost for 10 Sq.m.
MATERIAL :
CARRIAGE :
Terrazo tiles.
1 KM BY MECH. TRANSPORT 1000 nos 171.000 221.90 37.95
Cement|
1 KM BY MECH. TRANSPORT 1 tonne 0.06600 73.95 4.88
LABOUR :
Mason For Terrazo Work Each 3.25000 186.67 606.68
Beldar Each 3.25000 116.67 379.18
Floor Polisher Each 7.60000 148.16 1126.02
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 2211.86
Labour for cement mortar 1:3 15.40
TOTAL : 2227.26
WATER CHARGES @ 1.5% : 106.52
TOTAL : 2333.78
ADD FOR CONTRACTORS PROFIT @10% : 233.38
ADD FOR OVER HEAD CHARGES@5% : 116.69
LABOUR FOR 10.000sqm. 2683.85
LABOUR PER sqm. 268.40
13190500 DARK.
Details of cost for 10 sq.m
MATERIAL :
CARRIAGE :
Terrazo tiles. |
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
1 KM BY MECH. TRANSPORT 1000 nos 171.000 221.90 37.95
Cement|
1 KM BY MECH. TRANSPORT 1 tonne 0.06600 73.95 4.88
LABOUR :
Mason For Terrazo Work Each 3.25000 186.67 606.68
Beldar Each 3.25000 116.67 379.18
floor polisher Each 7.60000 148.16 1126.02
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 2211.86
Labour for cement mortar 1:3 15.40
TOTAL : 2227.26
WATER CHARGES @ 1.5% : 99.35
TOTAL : 2326.61
ADD FOR CONTRACTORS PROFIT @10% : 232.66
ADD FOR OVER HEAD CHARGES@5% : 116.33
LABOUR FOR 10.000sqm. 2675.60
LABOUR PER sqm. 267.55
13200000 Extra if cut tiles other than
half tiles had to be used in
risers of
steps, skirting and dado.
Details of cost for 10 sq.m
LABOUR RATE :
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Labour for cutting and rubbing :
Mason For Terrazo Work Each 1.75000 186.67 326.67
Beldar Each 1.75000 116.67 204.17
TOTAL : 530.84
ADD FOR WATER CHARGES @ 1.5% : 7.96
TOTAL: 538.80
ADD FOR CONTRACTORS PROFIT @10% : 53.88
ADD FOR OVER HEAD CHARGES@5% : 26.94
COST FOR 10.000 Sq.m 619.62
COST PER Sq.m 61.95
LABOUR PER Sq.m 61.95
LABOUR RATE :
MATERIAL :
CARRIAGE :
Carriage of tiles/Cement
L.S. 15.00
LABOUR :
Mason For Glazed tile work Each 0.70000 186.67 130.67
Beldar Each 0.70000 116.67 81.66
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 222.33
Labour for cement mortar 1:3 1.92
TOTAL : 224.25
WATER CHARGES @ 1.5% : 9.00
TOTAL : 233.25
ADD FOR CONTRACTORS PROFIT @10% : 23.32
ADD FOR OVER HEAD CHARGES@5% : 11.66
LABOUR FOR1.000sqm. 268.23
LABOUR PER sqm. 268.25
13220000 Extra for laying white glazed
tiles in treads of steps not
exceeding 30 cm. in width.
Details of cost for one square
mtr
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR :
Mason For Glazed tile work Each 0.15000 186.67 28.00
Beldar Each 0.15000 116.67 17.50
TOTAL : 45.50
ADD FOR WATER CHARGES @ 1.5% : 0.68
TOTAL: 46.18
ADD FOR CONTRACTORS PROFIT @10% : 4.61
ADD FOR OVER HEAD CHARGES@5% : 2.30
COST FOR1.000 sqm. 53.10
COST PER sqm. 53.10
LABOUR PER sqm. 53.10
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 45.50
TOTAL : 45.50
WATER CHARGES @ 1.5% : 0.68
TOTAL : 46.18
ADD FOR CONTRACTORS PROFIT @10% : 4.61
ADD FOR OVER HEAD CHARGES@5% : 2.30
LABOUR FOR1.000sqm. 53.10
LABOUR PER sqm. 53.10
13230000 White glazed tiles 6 mm thick
in skirting risers of steps
and dado 12 mm thick cement
mortar 1:3
(1 cement :3 sand) and jointed
with cement slurry.
Details of cost for one sq.m.
MATERIAL :
LABOUR :
Mason For Glazed tile work Each 0.77000 186.67 143.74
Beldar Each 0.77000 116.67 89.84
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 243.58
Labour for cement mortar 1:3 1.92
TOTAL : 245.50
WATER CHARGES @ 1.5% : 9.70
TOTAL : 255.20
ADD FOR CONTRACTORS PROFIT @10% : 25.52
ADD FOR OVER HEAD CHARGES@5% : 12.76
LABOUR FOR1.000sqm. 293.48
LABOUR PER sqm. 293.50
13240000 Extra for laying white glazed
tiles in skirting, risers of
steps and dado where they are
required to be cut.(only area
of portion of cut tiles to be
measured).
Details of cost for one sq.m
LABOUR :
Mason For Glazed tile work Each 1.75000 186.67 326.67
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Beldar Each 1.75000 116.67 204.17
TOTAL : 530.85
ADD FOR WATER CHARGES @ 1.5% : 7.96
TOTAL: 538.81
ADD FOR CONTRACTORS PROFIT @10% : 53.88
ADD FOR OVER HEAD CHARGES@5% : 26.94
COST FOR1.000 sqm. 619.63
COST PER sqm. 619.60
LABOUR PER sqm. 619.60
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 530.85
TOTAL : 530.85
WATER CHARGES @ 1.5% : 7.96
TOTAL : 538.81
ADD FOR CONTRACTORS PROFIT @10% : 53.88
ADD FOR OVER HEAD CHARGES@5% : 26.94
LABOUR FOR1.000sqm. 619.63
LABOUR PER sqm. 619.60
13250000 Providing and fixing 50 mm
internal or external angles
and fillet covers and borders or patterned angles
Details of cost for 10 Mtrs
length
MATERIAL :
Tiles.
1 KM BY MECH. TRANSPORT 1000 nos 69.00000 221.90 15.30
LABOUR :
Mason For Glazed tile work Each 0.25000 186.68 46.67
Beldar Each 0.25000 116.67 29.17
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 100.82
TOTAL : 100.82
WATER CHARGES @ 1.5% : 20.48
TOTAL : 121.30
ADD FOR CONTRACTORS PROFIT @10% : 12.13
ADD FOR OVER HEAD CHARGES@5% : 6.07
LABOUR FOR 10.000Metre 139.50
LABOUR PER Metre 13.95
13260100 15 mm thick cement concrete
topping 1:2 to 3 (1 cement: 2
to 3 stone aggregate of size
4.75 mm and below, by volume)
laid over and finished
monolithic with structural
slab.
Details of cost for 10 sq.m
MATERIAL :
Cement
1 tonne 0.10000 4900.00 490.00
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
CARRIAGE :
Stone Chips
1 KM BY MECH. TRANSPORT 1 cum 0.20000 110.95 22.19
Cement|
1 KM BY MECH. TRANSPORT 1 tonne 0.10000 7.95 7.40
LABOUR :
Mason 2nd Class each 0.90000 158.67 142.80
Beldar each 0.90000 116.67 105.00
Bhishti each 0.50000 116.67 58.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 306.13
TOTAL : 306.13
WATER CHARGES @ 1.5% : 14.44
TOTAL : 320.57
ADD FOR CONTRACTORS PROFIT @10% : 32.05
ADD FOR OVER HEAD CHARGES@5% : 16.02
LABOUR FOR 10.000sqm. 368.64
LABOUR PER sqm. 36.85
13260200 Reduced rate for difference of
cost usingwater borne agg.
instead of crushed stone agg.
Detail of cost for 10 sq.m
MATERIAL :
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Difference in cost of rate
using water borne agg. instead
of crushed stone agg. i.e.
Rate of Meterial code
020101100000(-)020102090000
(490-375) 1 cum 0.15000 115.00 17.25
TOTAL : 17.25
ADD FOR CONTRACTORS PROFIT @10% : 1.72
ADD FOR OVER HEAD CHARGES@5% : 0.86
COST FOR 10.000 Sq.m 19.83
COST PER Sq.m 2.00
MATERIAL :
Stone dust
1 cum 0.07000 700.00 49.00
Cement
1 tonne 0.13000 4900.00 637.00
CARRIAGE :
Cement|
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
1 KM BY MECH. TRANSPORT 1 tonne 0.13000 73.95 9.61
100 MTRS BY HEAD LOAD 1 tonne 0.13000 31.20 4.06
LABOUR :
Mason 2nd Class Each 1.00000 158.67 158.67
Beldar Each 1.20000 116.67 140.00
Bhishti Each 0.50000 116.67 58.34
MATERIAL :
TOTAL : 23.00
ADD FOR CONTRACTORS PROFIT @10% :. 2.30
ADD FOR OVER HEAD CHARGES@5% : 1.65
COST FOR 10.000 sqm. 26.95
COST PER sqm. 2.70
13280100 25 mm cement concrete flooring
1:2 :3(1 cement:2 send: 3
graded stone aggregate of size
12.5 mm and below by volume)
laid over set and hardened
face of structural slab or
baseconcrete and finished
with a floating coat of neat
cement (using cement slurry
for bond at the rate of 2.75
kg of cement per square metre
of floor).
Details of cost for 10 sq.m
MATERIAL :
Sand
1 cum 0.11900 300 35.70
CARRIAGE :
Sand
1 KM BY MECH. TRANSPORT 1 cum 0.11900 100.95 12.01
Cement|
1 KM BY MECH. TRANSPORT 1 tonne 0.10800 73.95 7.99
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 412.00
TOTAL : 412.00
WATER CHARGES @ 1.5% : 16.53
TOTAL : 428.53
ADD FOR CONTRACTORS PROFIT @10% : 42.85
ADD FOR OVER HEAD CHARGES@5% :1 21.42
LABOUR FOR 10.000sqm. 492.80
LABOUR PER sqm. 49.30
13280200 Reduced rate for difference of
cost using water borne
aggregate and crushed stone
aggregate.
Details of cost for 10 sq.m
MATERIAL :
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 16.69
ADD FOR CONTRACTORS PROFIT @10% : 1.66
ADD FOR OVER HEAD CHARGES@5% : 0.83
COST FOR 10.000 sqm. . 19.18
COST PER sqm. 1.90
MATERIAL :
Sand
1 cum 0.11100 300 33.30
Cement
1 tonne 0.10200 4900 499.80
CARRIAGE :
Sand
1 KM BY MECH. TRANSPORT 1 cum 0.11100 110.95 12.32
100 MTRS BY HEAD LOAD 1 cum 0.11100 54.35 6.03
Cement|
1 KM BY MECH. TRANSPORT 1 tonne 0.10200 73.95 7.54
LABOUR :
Mason 2nd Class Each 1.00000 158.67 158.67
Beldar Each 1.50000 116.67 175.01
Bhishti Each 0.50000 116.67 58.34
MATERIAL :
TOTAL : 24.98
ADD FOR CONTRACTORS PROFIT @10% : 2.50
ADD FOR OVER HEAD CHARGES@5% : 1.25
COST FOR 10.000 sqm. 28.73
COST PER sqm. 2.90
MATERIAL :
Sand
1 cum 0.11800 300.00 35.40
Cement
1 tonne 0.16100 4900.00 788.90
CARRIAGE :
Sand
1 KM BY MECH. TRANSPORT 1 cum 0.11800 110.95 13.09
Cement
1 KM BY MECH. TRANSPORT 1 tonne 0.16100 73.95 11.91
LABOUR :
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Mason 2nd Class Each 1.20000 158.67 190.40
Beldar Each 2.00000 116.67 233.34
Bhishti Each 0.50000 116.67 58.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 502.07
TOTAL : 502.07
WATER CHARGES @ 1.5% : 24.16
TOTAL : 526.23
ADD FOR CONTRACTORS PROFIT @10% : 52.62
ADD FOR OVER HEAD CHARGES@5% : 26.31
LABOUR FOR 10.000sqm. 605.16
LABOUR PER sqm. 60.50
13300200 Reduced rate for difference of
cost using water borne
aggregate and crushed stone
aggregate. Details of cost for 10 sqm
MATERIAL :
TOTAL : 43.69
ADD FOR CONTRACTORS PROFIT @10% : 4.36
ADD FOR OVER HEAD CHARGES@5% : 2.18
COST FOR 10.000 sqm. 50.23
COST PER sqm. 5.00
13310101 40 mm thick.
Details of cost for 10 Sq.m.
MATERIAL :
Cement
1 tonne 0.15000 4900.00 735.00
CARRIAGE :
Sand|
1 KM BY MECH. TRANSPORT 1 cum 0.17800 110.95 19.75
Cement|
1 KM BY MECH. TRANSPORT 1 tonne 0.15000 73.95 11.09
LABOUR :
Mason 2nd Class Each 1.20000 158.67 190.40
Beldar Each 2.00000 116.67 233.34
Bhishti Each 0.50000 116.67 58.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 507.07
TOTAL : 507.07
WATER CHARGES @ 1.5% : 23.48
Total 530.55
ADD FOR CONTRACTORS PROFIT @10% : 53.05
ADD FOR OVER HEAD CHARGES@5% : 26.52
LABOUR FOR 10.000sqm. 557.07
LABOUR PER sqm. 55.70
13310102 Reduced rate for difference of
cost using water borne
aggregate and crushed stone
aggregate.
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Detailes of cost for 10 sq.m
MATERIAL :
TOTAL : 40.05
ADD FOR CONTRACTORS PROFIT @10% : 4.00
ADD FOR OVER HEAD CHARGES@5% : 2.00
COST FOR 10.000 sqm. 46.05
COST PER sqm. 4.60
13310201 50mm thick.
Details of cost for 10 sq.m
MATERIAL :
Stone ballast 20mm nominal size 1 cum 0.33400 460.00 153.64
Cement
1 Tonne 0.18200 4900.00 891.80
CARRIAGE :
Sand|
1 KM BY MECH. TRANSPORT 1 cum 0.22200 110.95 24.63
Cement|
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
1 KM BY MECH. TRANSPORT 1 tonne 0.18200 73.95 13.46
LABOUR :
Mason 2nd Class Each 1.35000 158.67 214.20
Beldar Each 2.16000 116.67 252.01
Bhishti Each 0.57000 116.67 66.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 557.70
TOTAL : 557.70
WATER CHARGES @ 1.5% : 27.78
TOTAL : 585.48
ADD FOR CONTRACTORS PROFIT @10% : 58.54
ADD FOR OVER HEAD CHARGES@5% : 29.27
LABOUR FOR 10.000sqm. 673.29
LABOUR PER sqm. 67.30
13310202 Reduced rate for differrence
of cost using water borne
aggregete and crushed stone
aggregate.
Details of cost for 10 sq.m
MATERIAL :
TOTAL : 50.06
ADD FOR CONTRACTORS PROFIT @10% : 5.00
ADD FOR OVER HEAD CHARGES@5% : 2.50
COST FOR 10.000 Sqm 57.56
COST PER Sqm 5.75
MATERIAL :
Sand
1 cum 0.13400 300.00 40.20
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Cement
1 tonne 0.11800 4900.00 578.20
CARRIAGE :
Sand|
1 KM BY MECH. TRANSPORT 1 cum 0.24800 110.95 27.52
Cement|
1 KM BY MECH. TRANSPORT 1 tonne 0.11800 73.95 8.73
LABOUR :
Mason 2nd Class Each 1.20000 158.67 190.40
Beldar Each 2.00000 116.67 233.34
Bhishti Each 0.50000 116.67 58.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 507.07
TOTAL : 507.07
WATER CHARGES @ 1.5% : 34.26
TOTAL : 541.33
ADD FOR CONTRACTORS PROFIT @10% : 54.13
ADD FOR OVER HEAD CHARGES@5% : 27.06
LABOUR FOR 10.000sqm. 622.52
LABOUR PER sqm. 62.25
13320200 Reduced rate for diference of
cost using water borne
aggtegate and crushed stone
aggregate.
Details of cost for 10 sq.m
MATERIAL :
TOTAL : 30.04
ADD FOR CONTRACTORS PROFIT @10% : 3.00
ADD FOR OVER HEAD CHARGES@5% : 1.50
COST FOR 10.000 sqm. 34.54
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
COST PER sqm. 3.45
MATERIAL :
CARRIAGE :
Carriage of red oxide L.S. 1.00
LABOUR :
Labour & Sundries L.S 15.00
TOTAL : 157.10
ADD FOR WATER CHARGES @ 1.5% : 2.35
TOTAL: 159.45
ADD FOR CONTRACTORS PROFIT 10% 15.94
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 15.00
TOTAL : 15.00
WATER CHARGES @ 1.5% : 2.35
TOTAL : 17.35
ADD FOR CONTRACTORS PROFIT @10% : 1.73
ADD FOR OVER HEAD CHARGES@5% : 0.86
LABOUR FOR 10.000sqm. 19.95
LABOUR PER sqm. 2.00
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
13340100 Cement concrete pavement (25
mm to 50 mm thick) with 1:2:4
(1 cement :2 sand :4 stone
aggregate 20 mmnominal size)
including finishing with a
floating coat of neat cement
complete.
Details for cost for one cum
MATERIAL :
Sand
1 cum 0.44500 300.00 133.50
CARRIAGE :
Sand|
1 KM BY MECH. TRANSPORT 1 cum 0.44500 110.95 49.37
Cement|
1 KM BY MECH. TRANSPORT 1 tonne 0.37500 73.95 27.73
LABOUR :
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Mason 1st class Each 0.05000 211.16 10.56
Mason 2nd Class Each 0.40000 158.67 63.47
Beldar Each 1.68000 116.67 196.01
Bhishti Each 0.36000 116.67 42.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 342.01
TOTAL : 342.01
WATER CHARGES @ 1.5% : 44.80
TOTAL : 386.81
ADD FOR CONTRACTORS PROFIT @10% : 38.68
ADD FOR OVER HEAD CHARGES@5% : 19.34
LABOUR FOR 1 cum. 444.83
LABOUR PER cum. 444.80
13340200 Reduced rate for difference of
cost using water borne
aggregate and crushed stone
aggregate.
Details of cost for 1 cubic
metre
MATERIAL :
TOTAL : 100.10
ADD FOR CONTRACTORS PROFIT @10% : 10.00
ADD FOR OVER HEAD CHARGES@5% : 5.00
COST FOR1.000 Cum 115.10
COST PER Cum 115.10
LABOUR :
Mason 2nd Class Each 0.36000 158.67 57.12
Beldar Each 0.36000 116.67 42.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 109.12
TOTAL : 109.12
WATER CHARGES @ 1.5% : 1.64
TOTAL : 110.76
ADD FOR CONTRACTORS PROFIT @10% : 11.07
ADD FOR OVER HEAD CHARGES@5% : 5.53
LABOUR FOR 10.000sqm. 127.36
LABOUR PER sqm. 12.75
13360100 50 mm thick cement concrete
flooring with metallic
concrete hardner topping under
layer of 35 mm thick cement
concrete 1:2:4 (1 cement:2
sand:4 graded stone aggregate
20 mm nominal size) and top
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
layer of 15 mm thick metallic
concrete hardner consisting of
mix 1:2 (1 cementhardner mix
: 2 stone aggregate 6 mm
nominal size) by volume with
which metallic hardening
compound of approved quality
is mixed in the ratio 4:1 (4
parts of cement: 1 part of
metallic floor handening
compound of approved quality
by weight) including finishing
complete. Details of cost for 10 sq.m
MATERIAL :
Sand
1 cum 0.15600 300.00 46.80
Cement 0.112+0.076=0.188
1 tonne 0.18800 4900.00 921.20
CARRIAGE :
Sand|
1 KM BY MECH. TRANSPORT 1 cum 0.15600 110.95 17.31
Cement|
1 KM BY MECH. TRANSPORT 1 tonne 0.18800 73.95 13.90
LABOUR :
Mason 2nd Class Each 2.15000 158.67 341.14
Beldar Each 3.23000 116.67 376.84
Bhishti Each 0.27000 116.67 31.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 784.48
TOTAL : 784.48
WATER CHARGES @ 1.5% : 32.66
TOTAL : 817.14
ADD FOR CONTRACTORS PROFIT @10% : 81.71
ADD FOR OVER HEAD CHARGES@5% : 40.85
LABOUR FOR 10.000sqm. 939.70
LABOUR PER sqm. 94.00
13360200 Reduced rate for difference of
cost using water borne
aggregate and crushed stone
aggregate.
Details of cost for 10 sq.m
MATERIAL :
TOTAL : 35.1
ADD FOR CONTRACTORS PROFIT @10% : 3.51
ADD FOR OVER HEAD CHARGES@5% : 1.75
COST FOR 10.000 sqm. 40.36
COST PER sqm. 4.05
MATERIAL :
Sand
1 cum 0.20000 300.00 60.00
CARRIAGE :
Sand|
1 KM BY MECH. TRANSPORT 1 cum 0.20000 110.95 22.19
Cement
1 KM BY MECH. TRANSPORT 1 tonne 0.24900 73.95 18.41
LABOUR :
Mason 2nd Class Each 2.58000 158.67 409.37
Beldar Each 3.88000 116.67 452.68
Bhishti Each 0.32000 116.67 37.33
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 939.07
TOTAL : 939.37
WATER CHARGES @ 1.5% : 40.70
TOTAL : 980.07
ADD FOR CONTRACTORS PROFIT @10% : 98.00
ADD FOR OVER HEAD CHARGES@5% : 49.00
LABOUR FOR 10.000sqm. 1127.00
LABOUR PER sqm. 112.70
13370200 Reduced rate for difference of
cost using water borne
aggregate and crushed stone
aggregate.
Details of cost for 10 sq.m
MATERIAL :
TOTAL : 45.00
ADD FOR CONTRACTORS PROFIT @10% : 4.50
ADD FOR OVER HEAD CHARGES@5% : 2.25
COST FOR 10.000 sqm. 51.75
COST PER sqm. 5.15
MATERIAL :
CARRIAGE :
Cement|
1 KM BY MECH. TRANSPORT 1 tonne 0.01000 73.95 0.74
LABOUR :
Mason 2nd Class Each 1.00000 158.67 158.67
Beldar Each 1.00000 116.67 116.67
Bhishti Each 0.55000 116.67 64.17
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 354.50
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Labour for cement mortar 1:3 25.92
TOTAL : 380.42
WATER CHARGES @ 1.5% : 5.70
TOTAL : 386.12
ADD FOR CONTRACTORS PROFIT @10% : . 38.61
ADD FOR OVER HEAD CHARGES@5% : 19.30
LABOUR FOR 10.000sqm. 444.03
LABOUR PER sqm. 44.40
13380200 20 mm thick.
Details of cost for 10 sq.m
MATERIAL :
---------------
Total =0.255 cu.m.
. 1 cum 0.25500 3178.80 810.59
CARRIAGE :
Cement|
1 KM BY MECH. TRANSPORT 1 tonne 0.01000 73.95 0.74
LABOUR :
Mason 2nd Class Each 1.10000 158.67 174.54
Beldar each 1.10000 116.67 128.34
Bhishti each 0.55000 116.67 64.17
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 387.04
Labour for cement mortar 1:3 32.72
TOTAL : 419.76
WATER CHARGES @ 1.5% : 18.71
TOTAL : 438.47
ADD FOR CONTRACTORS PROFIT @10% : 43.84
ADD FOR OVER HEAD CHARGES@5% : 21.92
LABOUR FOR 10.000sqm. 504.23
LABOUR PER sqm. 50.40
13390000 Red oxide plaster skirting up
to 30 cm.height with top layer
of 5mmthick plaster of
cement mix using 3.50 kg. of
red oxide of iron per 50 kg. of cement with 10mm thick under layer of
of cement mortor 1:3 (1
cement: 3 sand) finishad with
floating coat of cement red
oxide mix of same proportion.
MATERIAL :
CARRIAGE :
Cement|
1 KM BY MECH. TRANSPORT 1 tonne 0.01000 73.95 0.74
LABOUR :
Mason 2nd Class Each 0.90000 158.67 142.80
Beldar Each 0.90000 116.67 105.00
Bhishti Each 0.50000 116.67 58.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 321.13
Labour for cement mortar 1:3 23.10
TOTAL : 344.23
WATER CHARGES @ 1.5% : 17.80
TOTAL : 362.03
ADD FOR CONTRACTORS PROFIT @10% : 36.20
ADD FOR OVER HEAD CHARGES@5% : 18.10
LABOUR FOR 10.000sqm. 416.33
LABOUR PER sqm. 41.60
13390200 20 mm thick with under layer
15 mm thick cement plaster
1:3(1 cement:3 sand).
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Details od cost for 10 sq.m
MATERIAL :
CARRIAGE :
Cement
1 KM BY MECH. TRANSPORT 1 tonne 0.01000 73.95 0.74
LABOUR :
Mason 2nd Class each 1.00000 158.67 158.67
Beldar each 1.20000 116.67 140.00
Bhishti each 0.50000 116.67 58.34
LABOUR RATE :
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ACTUAL LABOUR+SUNDRIES 372.00
Labour for cement mortar 1:3 29.78
TOTAL : 401.78
WATER CHARGES @ 1.5% : 21.05
TOTAL : 422.83
ADD FOR CONTRACTORS PROFIT @10% : 42.28
ADD FOR OVER HEAD CHARGES@5% : 21.14
LABOUR FOR 10.000sqm. 486.25
LABOUR PER sqm. 48.60
MATERIAL :
CARRIAGE :
Carriage of red oxide L.S 1.00
LABOUR :
Labour & sundries L.S 15.00
TOTAL : 85.70
ADD FOR WATER CHARGES @ 1.5% : 1.30
TOTAL: 87.00
ADD FOR CONTRACTORS PROFIT 10% 8.70
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.29810 110.95 33.07
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR :
Carpenter 1st Class Each 4.95000 211.16 1045.24
Beldar Each 3.30000 116.67 385.01
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1480.25
TOTAL : 1480.25
ADD FOR CONTRACTORS PROFIT @10% : 148.02
ADD FOR OVER HEAD CHARGES@5% : 74.01
LABOUR FOR 10.000sqm. 1702.28
LABOUR PER sqm. 170.20
13410200 Second class Indian teak wood
planks
Details of cost for 2.5m x4.0m
=10.00 Sq.m.
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.29810 110.95 33.07
LABOUR :
Carpenter 1st Class Each 4.95000 211.14 1045.14
Beldar Each 3.30000 116.67 385.01
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1480.25
TOTAL : 1480.25
ADD FOR CONTRACTORS PROFIT @10% : 148.02
ADD FOR OVER HEAD CHARGES@5% : 74.01
LABOUR FOR 10.000sqm. 1702.28
LABOUR PER sqm. 170.20
13410300 First class deodar wood planks
Details of cost
for2.5x4.00=10sqm.
MATERIAL :
CARRIAGE :
Timber.|
1 KM BY MECH. TRANSPORT 1 cum 0.29810 40.00 11.92
LABOUR :
Carpenter 1st Class Each 3.30000 211.16 696.83
Beldar Each 2.20000 116.67 256.67
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1003.49
TOTAL : 1003.49
ADD FOR CONTRACTORS PROFIT @10% : 100.35
ADD FOR OVER HEAD CHARGES@5% : 50.17
LABOUR FOR 10.000sqm. 1154.01
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR PER sqm. 115.40
13410400 First class kail wood planks
Details of cost for 2.5 m x
4.00= 10 sq.m
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.29810 110.95 33.07
LABOUR :
Carpenter 1st Class each 3.30000 211.16 696.83
Beldar each 2.20000 116.67 256.67
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1003.49
TOTAL : 1003.49
ADD FOR CONTRACTORS PROFIT @10% : 100.35
ADD FOR OVER HEAD CHARGES@5% : 50.17
LABOUR FOR 10.000sqm. 1154.01
LABOUR PER sqm. 115.40
13420000 38 mm thick parquet ( wood
block) flooring of 1st class
indian teak wood laid over 25
mm thick levelling layer of
cement concreate 1:2:4 (1
cement : 2 sand : stone
aggregate 10 mm nominal size)(
to be paid separately coated
with thin layer of hot
bitument )(blown-type) @ 2.45
kg. per sq m. including fixing
blocks in position after
dipping in hot bitumen ( blown
type) upto half depth, planed,
levelled smooth and finished
complete
Details of cost for one sq.m
MATERIAL :
CARRIAGE :
Tar Bitumen.
1 KM BY MECH. TRANSPORT 1 tonne 0.00445 123.25 0.55
Timber.|
1 KM BY MECH. TRANSPORT 1 cum 0.04180 110.95 4.64
LABOUR RATE :
For making and fixing blocks
spreading Bitumen etc.sand
papering & fixing flooring
Carpenter 1st Class Each 1.75000 211.16 369.53
Beldar Each 3.75000 116.67 437.51
Mason 1st class Each 0.55000 211.16 116.14
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 973.18
TOTAL : 973.18
ADD FOR CONTRACTORS PROFIT @10% : 97.31
ADD FOR OVER HEAD CHARGES@5% : 48.65
LABOUR FOR1.000sqm. 1119.15
LABOUR PER sqm. 1119.15
13430000 Extra for planing the lower
surface of wooden planking.
Details of cost for 10 sq.m
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR :
Carpenter 1st Class Each 1.50000 211.16 316.74
Beldar Each 0.57000 116.67 66.50
TOTAL : 383.24
ADD FOR CONTRACTORS PROFIT @10% : 38.32
ADD FOR OVER HEAD CHARGES@5% : 19.16
COST FOR 10.000 sqm. 440.72
COST PER sqm. 44.10
LABOUR PER sqm. 44.10
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 383.24
TOTAL : 383.24
ADD FOR CONTRACTORS PROFIT @10% : 38.32
ADD FOR OVER HEAD CHARGES@5% : 19.16
LABOUR FOR 10.000sqm. 440.72
LABOUR PER sqm. 44.10
13440000 Extra for providing and fixing
metal strips of 1:6 mm
thickness at junctions with
other floors:
MATERIAL :
LABOUR :
Carpenter 2nd Class Each 0.25000 186.67 46.67
Beldar Each 0.25000 116.67 29.17
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 90.82
TOTAL : 90.82
ADD FOR CONTRACTORS PROFIT @10% : 9.08
ADD FOR OVER HEAD CHARGES@5% : 4.54
LABOUR FOR 10.000sqm. 104.44
LABOUR PER sqm. 10.45
13440200 38 mmwide aluminium, strips
Details of cost for 10 sqm.
MATERIAL :
Aluminium sheet
10 x0.038=0.38 sqm
Wastage @ 5% =0.019
----------
Total =0.399 sqm.
CARRIAGE :
Carriage of Alumn.sheet. L.S 0.50
LABOUR :
Carpenter 2nd Class Each 0.25000 186.67 46.67
Beldar Each 0.25000 116.67 29.17
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 90.82
TOTAL : 90.82
ADD FOR CONTRACTORS PROFIT @10% : 9.08
ADD FOR OVER HEAD CHARGES@5% : 4.54
LABOUR FOR 10.000sqm. 104.44
LABOUR PER sqm. 10.45
13450000 Deduct for butt jointing in
place of tongued and grooved
type jointing in item
no.13410000.
Details of cost for 10 sq.m.
LABOUR :
Carpenter 1st Class Each 0.60000 211.16 126.70
Beldar Each 0.60000 116.67 70.00
TOTAL : 196.70
ADD FOR CONTRACTORS PROFIT @10% : 19.67
ADD FOR OVER HEAD CHARGES@5% : 9.83
COST FOR 10.000 sqm. 226.20
COST PER sqm. 22.60
LABOUR PER sqm. 22.60
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 196.70
TOTAL : 196.70
ADD FOR CONTRACTORS PROFIT @10% : 19.67
ADD FOR OVER HEAD CHARGES@5% : 9.83
LABOUR FOR 10.000sqm. 226.20
LABOUR PER sqm. 22.60
13460000 25 mm thick wooden flooring
laid over R.C.C/C.C. (slab to
be paid separately) thinly
coated with thin layer of hot
bitumen blown type @ 2.45 kg
per sq m including fixing of
wooden planks in position over
wooden plugs fixed in
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
c.c./R.c.c. floor including
planning and levelling
complete.
MATERIAL :
CARRIAGE :
Timber.
1 KM BY MECH. TRANSPORT 1 cum 0.27500 110.95 30.51
Tar Bitumen.
1 KM BY MECH. TRANSPORT 1 tonne 0.02450 123.25 3.02
LABOUR :
Carpenter 1st Class Each 1.50000 211.16 316.74
Beldar Each 1.00000 116.67 116.67
Total: 22484.60
Add for water charges @1.5% Except on (-I-) : 245.46
Total: 22730.06
ADD FOR CONTRACTORS PROFIT @10% Except on (-I-) & (-A-):
1661.00
ADD FOR OVER HEAD CHARGES@5% Except on (-I-) & (-A-): 830.50
COST FOR 10.000 sqm. 25221.55
COST PER sqm. 2522.15
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 458.41
Labour As per item no:1205902000 2016.00
TOTAL : 2474.41
Add for water charges except on (-a-): 245.46
TOTAL : 2719.87
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a-): 70.38
ADD FOR OVER HEAD CHARGES@5% EXCEPT ON (-a-): 35.79
LABOUR FOR10.000 sqm. 2825.44
LABOUR PER sqm. 282.55
13460200 Deodar wood second class.
Details of cost for 2.5 x 4.0m
=10.00 sq.m.
MATERIAL :
CARRIAGE :
Timber.|
1 KM BY MECH. TRANSPORT 1 cum 0.27500 110.95 30.51
Tar Bitumen. |
1 KM BY MECH. TRANSPORT 1 tonne 0.02450 123.25 3.02
LABOUR :
Carpenter 1st Class Each 1.50000 211.16 316.74
Beldar Each 1.00000 116.67 116.67
Total: 22257.72
Add for water charges @1.5% Except on (-I-) : 242.06
Total: 22499.78
ADD FOR CONTRACTORS PROFIT @10% Except on (-I-) 1637.98
ADD FOR OVER HEAD CHARGES@5% Except on (-I-) 818.99
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
COST FOR 10.000 sqm. 24956.75
COST PER sqm. 2495.70
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 458.41
Labour As per item no:1205902000 2016.00 (-a-)
TOTAL : 2474.41
Add for water charges except on (-a-): 242.06
TOTAL : 2716.47
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a-): 70.04
ADD FOR OVER HEAD CHARGES@5% EXCEPT ON (-a-): 35.02
LABOUR FOR10.000 sqm. 2821.53
LABOUR PER sqm. 282.15
13470000 First class brick flooring
laid dry and grouted with
MATERIAL :
CARRIAGE :
Bricks.|
1 KM BY MECH. TRANSPORT 1000 nos 500.000 277.35 138.67
LABOUR :
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Mason 2nd Class Each 1.08000 158.67 171.36
Beldar Each 1.62000 116.67 189.01
Bhishti Each 0.27000 116.67 31.50
TOTAL : 2814.42
ADD FOR WATER CHARGES @ 1.5% : 42.21
TOTAL: 2856.63
ADD FOR CONTRACTORS PROFIT 10% 285.66
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 391.86
Labour for cement mortar 1:4 37.22
TOTAL : 429.08
WATER CHARGES @ 1.5% : 42.21
TOTAL : 471.29
ADD FOR CONTRACTORS PROFIT @10% : 47.12
ADD FOR OVER HEAD CHARGES@5% : 23.56
LABOUR FOR 10.000sqm. 541.97
LABOUR PER sqm. 54.20
13470200 7 cm thick (using conventional
brick)
Details of cost for 10 sq.m.
MATERIAL :
CARRIAGE :
Bricks.|
1 KM BY MECH. TRANSPORT 1000 nos 377.000 277.35 104.56
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR :
Mason 2nd Class Each 0.81000 157.67 127.71
Beldar Each 1.08000 116.67 126.00
Bhishti Each 0.18000 116.67 21.00
TOTAL : 2156.08
ADD FOR WATER CHARGES @ 1.5% : 32.34
TOTAL: 2188.42
ADD FOR CONTRACTORS PROFIT 10% 218.84
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 275.52
Labour for cement mortar 1:4 30.80
TOTAL : 306.32
WATER CHARGES @ 1.5% : 32.34
TOTAL : 338.66
ADD FOR CONTRACTORS PROFIT @10% : 33.86
ADD FOR OVER HEAD CHARGES@5% : 16.93
LABOUR FOR 10.000sqm. 389.45
LABOUR PER sqm. 38.95
13470300 11.2 cm.thick (using
conventional brick)
Details of cost for 10 sq.m.
MATERIAL :
Bricks.|
1 KM BY MECH. TRANSPORT 1000 nos 565.00 277.35 156.70
LABOUR :
Mason 2nd Class Each 1.08000 158.67 171.36
Beldar Each 1.62000 116.67 189.01
Bhishti Each 0.27000 116.67 31.50
TOTAL : 3059.33
ADD FOR WATER CHARGES @ 1.5% : 45.88
TOTAL: 3105.21
ADD FOR CONTRACTORS PROFIT 10% 310.52
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 391.86
Labour for cement mortar 1:4 38.50
TOTAL : 430.36
WATER CHARGES @ 1.5% : 45.88
TOTAL : 476.24
ADD FOR CONTRACTORS PROFIT @10% : 47.62
ADD FOR OVER HEAD CHARGES@5% : 23.81
LABOUR FOR 10.000sqm. 547.67
LABOUR PER sqm. 54.75
MATERIAL :
CARRIAGE :
Bricks.|
1 KM BY MECH. TRANSPORT 1000 nos 500.00 277.35 138.67
LABOUR :
Mason 2nd Class Each 1.08000 158.67 171.36
Beldar Each 1.62000 116.67 189.01
Bhishti Each 0.27000 116.67 31.50
TOTAL : 2625.73
ADD FOR WATER CHARGES @ 1.5% : 39.38
TOTAL: 2665.11
ADD FOR CONTRACTORS PROFIT 10% 266.51
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 391.86
Labour for cement mortar 1:6 37.22
TOTAL : 429.08
WATER CHARGES @ 1.5% : 39.38
TOTAL : 468.46
ADD FOR CONTRACTORS PROFIT @10% : 46.84
ADD FOR OVER HEAD CHARGES@5% : 23.42
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR FOR 10.000sqm 538.72
LABOUR PER sqm. 53.90
13480200 7 cm.thick (using conventional
brick)
Details of cost for 10 sq.m.
MATERIAL :
CARRIAGE :
Bricks.
1 KM BY MECH. TRANSPORT 1000 nos 377.00 277.35 104560.95
LABOUR :
Mason 2nd Class Each 0.81000 158.67 128.52
Beldar Each 1.08000 116.67 126.00
Bhishti Each 0.18000 116.67 21.00
TOTAL : 1999.93
ADD FOR WATER CHARGES @ 1.5% : 30.00
TOTAL: 2029.93
ADD FOR CONTRACTORS PROFIT 10% 203.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 275.52
Labour for cement mortar 1:6 30.80
TOTAL : 306.32
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
WATER CHARGES @ 1.5% : 30.00
TOTAL : 336.32
ADD FOR CONTRACTORS PROFIT @10% : 33.63
ADD FOR OVER HEAD CHARGES@5% : 16.81
LABOUR FOR 10.000sqm. 386.76
LABOUR PER sqm. 37.70
13480300 11.2 cm. thick (using
conventional
bricks)
Details of cost for 10 sq.m.
MATERIAL :
CARRIAGE :
Bricks.
1 KM BY MECH. TRANSPORT 1000nos 565.00 277.35 156.70
LABOUR :
Mason 2nd Class Each 1.08000 158.67 171.36
Beldar Each 1.62000 116.67 189.01
Bhishti Each 0.27000 116.67 31.50
TOTAL : 2864.13
ADD FOR WATER CHARGES @ 1.5% : 42.96
TOTAL: 2907.09
ADD FOR CONTRACTORS PROFIT 10% 290.70
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 391.86
Labour for cement mortar 1:6 38.50
TOTAL : 430.36
WATER CHARGES @ 1.5% : 42.96
TOTAL : 473.32
ADD FOR CONTRACTORS PROFIT @10% : 47.33
ADD FOR OVER HEAD CHARGES@5% : 23.66
LABOUR FOR 10.000sqm. 544.31
LABOUR PER sqm. 54.45
13490000 Second class dry brick
flooring including filling
joints with fine sand.
MATERIAL :
Sand
1 cum 0.15000 300.00 45.00
Mud mortar
1 cum 0.15000 353.85 53.08
CARRIAGE :
Bricks.
1 KM BY MECH. TRANSPORT 1000 nos 540.00 277.35 149.76
Sand|
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
1 KM BY MECH. TRANSPORT 1 cum 0.15000 110.95 16.64
LABOUR :
Mason 2nd Class Each 0.90000 158.67 142.80
Beldar Each 1.98000 116.67 231.01
Bhishti Each 0.05000 116.67 5.83
TOTAL : 2219.03
ADD FOR WATER CHARGES @ 1.5% : 33.28
TOTAL: 2252.31
ADD FOR CONTRACTORS PROFIT 10% 225.23
ADD FOR OVER HEAD CHARGES@5% 112.61
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 379.63
Labour for mud mortar 18.36
TOTAL : 397.99
WATER CHARGES @ 1.5% : 5.97
TOTAL : 403.96
ADD FOR CONTRACTORS PROFIT @10% : 40.40
ADD FOR OVER HEAD CHARGES@5% : 20.20
LABOUR FOR 10.000sqm. 464.56
LABOUR PER sqm. 46.45
13490200 7 cm.thick (ushing modular
bricks).
Detail of cost for 10 Sq.m
MATERIAL :
Sand
1 cum 0.09000 300.00 27.00
Mud mortar
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
1 cum 0.15000 353.85 53.08
CARRIAGE :
Bricks.
1 KM BY MECH. TRANSPORT 1000 nos 410.00 277.35 113.71
Sand|
1 KM BY MECH. TRANSPORT 1 cum 0.09000 110.95 9.99
LABOUR :
Mason 2nd Class Each 0.40000 157.67 63.07
Beldar Each 1.35000 116.67 157.50
Bhishti Each 0.05000 116.67 5.83
TOTAL : 1625.02
ADD FOR WATER CHARGES @ 1.5% : 24.38
TOTAL: 1649.40
ADD FOR CONTRACTORS PROFIT 10% 164.94
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 226.79
Labour for mud mortar: 18.36
TOTAL : 245.15
WATER CHARGES @ 1.5% : 24.38
TOTAL : 269.53
ADD FOR CONTRACTORS PROFIT @10% : 26.95
ADD FOR OVER HEAD CHARGES@5% : 13.47
LABOUR FOR 10.000sqm. 309.45
LABOUR PER sqm. 31.00
13500000 linolium covering to floor,
plain or coloured laid with an
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
approved adhesive on sub floor
including cutting and fixing
complete to sub floor including
damp proofing treatment
(damp proofing treatment to be
measured separately for
payment.)
MATERIAL :
LABOUR :
Mason 2nd Class Each 0.50000 158.67 79.34
Beldar Each 0.50000 116.67 58.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 147.66
TOTAL : 147.66
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR CONTRACTORS PROFIT @10% : 14.76
ADD FOR OVER HEAD CHARGES@5% : 7.38
LABOUR FOR 10.000sqm. 169.80
LABOUR PER sqm. 17.00
13500200 3.2 mm to 4.5mm thick.
Details of cost for 10 sq.m.
MATERIAL :
LABOUR :
Mason 2nd Class Each 0.50000 158.67 79.34
Beldar Each 0.50000 116.67 58.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 147.66
TOTAL : 147.66
ADD FOR CONTRACTORS PROFIT @10% : 14.76
ADD FOR OVER HEAD CHARGES@5% : 7.38
LABOUR FOR 10.000sqm. 169.80
LABOUR PER sqm. 17.00
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
13510000 2 mm thick pvc/rubber tiles
flooring plain, coloured,
corbed or mosaic or mottled
finish, laid with approved
adhesive on sub floor (damp
proofing tretment(to be
measured separately for
payment.)
MATERIAL :
LABOUR :
Mason 2nd Class Each 1.50000 158.67 238.01
Beldar Each 1.50000 116.67 175.01
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 423.00
TOTAL : 423.00
ADD FOR CONTRACTORS PROFIT @10% : 42.30
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR OVER HEAD CHARGES@5% : 21.15
LABOUR FOR 10.000sq.m. 486.45
LABOUR PER sq.m. 48.65
13520000 3 mm thick pvc/rubber tile
flooring. plain, coloured,
corbed, or mosaic or mattled
finish. laid with approved
adhesive on sub floor
complete (sub- floor incuding
damp proofing treatment to be
measured separately for
payment) Details of cost for 10 sqm
MATERIAL :
CARRIAGE :
Carriage of material L.S 20.00
LABOUR :
Mason 2nd Class Each 1.50000 158.67 238.01
Beldar Each 1.50000 116.67 175.01
13530100 25 mm thick.
Details of cost for 10 sq.m.
MATERIAL :
or 0.064 tonne
1 tonne 0.06400 4900.00 313.60
=64x3.5
-----------=4.5 kg.
50
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
1 kg 4.50000 75.00 337.50
CARRIAGE :
Cement
1 KM BY MECH. TRANSPORT 1 tonne 0.06400 73.95 4.73
LABOUR :
Mason 2nd Class Each 5.40000 158.67 856.82
Beldar Each 8.21000 116.67 957.86
Beldar
(Skilled)for rubbing and polishing Each 10.80000 116.67 1260.04
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 3224.70
Labour for lime surkhi mortar 1:1:1 80.20
TOTAL : 3304.90
WATER CHARGES @ 1.5% : 120.85
TOTAL : 3425.75
ADD FOR CONTRACTORS PROFIT @10% : 342.58
ADD FOR OVER HEAD CHARGES@5% : 171.29
LABOUR FOR 10.000sqm. 3939.61
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR PER sqm. 393.95
13530200 30 mm thick.
Details of cost for 10 sq.m.
MATERIAL :
CARRIAGE :
Cement|
1 KM BY MECH. TRANSPORT 1 tonne 0.06800 73.95 5.03
LABOUR :
Mason 2nd Class Each 6.50000 158.67 1031.36
Beldar Each 10.80000 116.67 1260.04
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Beldar Each
(Skilled)for rubbing and polishing Each 10.80000 116.67 1260.04
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 3701.41
Labour for lime surkhi mortar 1:1:1 80.20
TOTAL : 3781.61
WATER CHARGES @ 1.5% : 133.10
TOTAL : 3914.71
ADD FOR CONTRACTORS PROFIT @10% : 391.47
ADD FOR OVER HEAD CHARGES@5% : 195.73
LABOUR FOR 10.000sqm. 4501.91
LABOUR PER sqm. 450.20
13530300 40 mm thick.
Detail of cost for 10 sq.m.
MATERIAL :
CARRIAGE :
Cement
1 KM BY MECH. TRANSPORT 1 tonne 0.07600 73.95 5.62
LABOUR :
Mason 2nd Class Each 7.00000 158.67 1110.69
Beldar Each 10.80000 116.67 1260.04
Beldar
(Skilled)for rubbing and polishing Each 10.80000 116.67 1260.04
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 3780.75
Labour for lime surkhi mortar 1:1:1 80.20
TOTAL : 3860.95
WATER CHARGES @ 1.5% : 147.15
TOTAL : 4008.10
ADD FOR CONTRACTORS PROFIT @10% : 400.81
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR OVER HEAD CHARGES@5% : 200.40
LABOUR FOR 10.000sqm. 4609.31
LABOUR PER sqm. 460.95
13540000 Kota stone slab flooring 20 mm
(average) thick base of cement
mortor 1:4 (1 cement :4 sand)
laid over and jointed with
grey cement slurry mixed with
pigment to match the shade of
the slab. including rubbing
and polishing complete.
13540100 25 mm thick.
Detail ofcost for 10 sq.m.
MATERIAL :
CARRIAGE :
LABOUR :
Mason 2nd Class Each 5.40000 158.67 856.82
Beldar Each 8.21000 116.67 957.86
Beldar Each
(Skilled)for rubbing and polishing Each 10.80000 116.67 1260.04
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 3224.71
Labour for cement mortar 1:4 28.74
TOTAL : 3253.45
WATER CHARGES @ 1.5% : 121.25
TOTAL : 3374.70
ADD FOR CONTRACTORS PROFIT @10% : 337.47
ADD FOR OVER HEAD CHARGES@5% : 168.73
LABOUR FOR 10.000sqm. 3880.90
LABOUR PER sqm. 388.10
13540200 30 mm thick.
Detail ofcost for 10 sq.m.
MATERIAL :
CARRIAGE :
Cement|
1 KM BY MECH. TRANSPORT 1 tonne 0.06800 73.95 5.03
100 MTRS BY HEAD LOAD 1 tonne 0.06800 31.20 2.12
LABOUR :
Mason 2nd Class Each 6.50000 158.67 1031.36
Beldar Each 10.80000 116.67 1260.04
Beldar Each
(Skilled)for rubbing and polishing Each 10.80000 116.67 1260.04
MATERIAL :
CARRIAGE :
Cement
1 KM BY MECH. TRANSPORT 1 tonne 0.07600 73.95 5.62
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
100 MTRS BY HEAD LOAD 1 tonne 0.07600 31.20 2.37
LABOUR :
Mason 2nd Class Each 7.00000 158.67 1110.69
Beldar each 10.80000 116.67 1260.04
Beldar Each
(Skilled)for rubbing and polishing Each 10.80000 116.67 1260.04
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 3780.75
Labour for cement mortar 1:4 28.74
TOTAL : 3809.49
WATER CHARGES @ 1.5% : 147.56
TOTAL : 3957.05
ADD FOR CONTRACTORS PROFIT @10% : 395.70
ADD FOR OVER HEAD CHARGES@5% : 197.85
LABOUR FOR 10.000sqm. 4550.60
LABOUR PER sqm. 455.05
13550000 Kota stone slab 25 mm thick in
risers of steps,skirting dado
and pillars laid on 12 mm
(average) thick cement mortor
MATERIAL :
CARRIAGE :
Cement
1 KM BY MECH. TRANSPORT 1 Tonne 0.06400 73.95 4.73
LABOUR :
Mason 2nd Class Each 6.50000 158.67 1031.36
Beldar Each 10.80000 116.67 1260.04
Beldar Each
(Skilled)for rubbing and polishing Each 10.80000 116.67 1260.04
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 3704.38
Labour for cement mortar 1:3 18.48
TOTAL : 3722.86
WATER CHARGES @ 1.5% : 126.78
TOTAL : 3849.64
ADD FOR CONTRACTORS PROFIT @10% : 384.96
ADD FOR OVER HEAD CHARGES@5% : 192.48
LABOUR FOR 10.000sqm. 4427.08
LABOUR PER sqm. 442.70
13560000 20 cm flagged stone flooring
laid in cement mortor 1:5 (1
cement :5 sand)
Detail of cost for 10 sq.m.
MATERIAL :
Stone
10 square metre x20 cum. =2.00 cum
Add for wastage @ 10% =0.2 cum
-------------
Total=2.20 cum
1 cum 2.20000 350.00 770.00
CARRIAGE :
LABOUR :
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Mason 2nd Class Each 1.04500 158.67 165.81
Beldar Each 1.60000 116.67 186.67
Bhishti Each 0.27000 116.67 31.50
TOTAL : 2984.68
ADD FOR WATER CHARGES @ 1.5% : 44.77
TOTAL: 3029.45
ADD FOR CONTRACTORS PROFIT 10% 302.94
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 383.98
Labour for cement mortar 1:5 84.71
TOTAL : 468.69
WATER CHARGES @ 1.5% : 44.77
TOTAL : 513.46
ADD FOR CONTRACTORS PROFIT @10% : 51.35
ADD FOR OVER HEAD CHARGES@5% : 25.67
LABOUR FOR 10.000sq.m. 590.48
LABOUR PER sq.m. 59.05
13570000 Providing and laying granite
stone in flooring
20mm(average)thickness base of
cement mortar 1:3(1cement:
3 sand) laid over and jointed
with
grey cement slurry mixed with
pigment to match the shade of
granite stone i/c rubbing and
polishing complete. 20mm.thick
MATERIAL :
20 mm thick granite
stone =10.00sqm
Add 15 % wastage=1.50 sqm
Total =11.50 sqm
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
1 sqm 11.50000 2500.00 28750.00
Cement mortar
1:3(1cement:3sand)
1 cum 0.22400 3178.80 712.05
Grey pigment.
1 Kg. 4.50000 75.00 337.50
CARRIAGE :
Cement|
1 KM BY MECH. TRANSPORT 1 tonne 0.06400 73.95 4.73
Granite Stone
1 KM BY MECH. TRANSPORT 1 tonne 0.64400 73.95 47.62
LABOUR :
Mason 2nd Class Each 5.40000 158.67 856.82
BeldarEach Each 8.21000 116.67 957.86
Beldar Each
(Skilled)for rubbing and polishing Each 10.80000 116.67 1260.04
MATERIAL :
cement mortar
1:4(1cement:4sand)
for bed.
1 cum 0.28000 2528.15 707.88
CARRIAGE :
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Talai Stone
1 KM BY MECH. TRANSPORT 1 tonne 1.77500 7395.00 131.26
LABOUR RATE :
For dressing of stone :
Mason 1st class Each 5.40000 211.16 1140.26
Beldar Each 1.30000 116.67 151.67
Black Smith 2nd Class Each 0.60000 148.16 88.90
Total: 5194.29
Add for water charges @1.5% Except on (-I-) : 70.46
Total: 5264.75
ADD FOR CONTRACTORS PROFIT @10% Except on (-I-) 476.82
ADD FOR OVER HEAD CHARGES@5% Except on (-I-) 238.41
COST FOR 10.000 sq.m. 5979.98
COST PER sq.m. 598.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1720.85
Labour for cement mortar 1:4 3592.00
Labour for cement mortar 1:3 17.32
Labour As per item no:17125010 433.00
TOTAL : 2207.09
Add for water charges except on (-a-): 70.46
TOTAL : 2277.55
ADD FOR CONTRACTORS PROFIT @10% EXCEPT ON (-a-): 184.45
ADD FOR OVER HEAD CHARGES@5% EXCEPT ON (-a-): 92.22
LABOUR FOR10.000 sq.m. 2554.22
LABOUR PER sq.m. 255.40
13590000 Providing and fixing Garsa (Kullu)
stone slab
12.5mm.cladding on R.C.C.surface
side as on faces of Arch
masonry
walls etc.on 12mm. thick
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
cement plaster
1:3(1cement:3sand) and jointed
with cement slurry i/c
scaffolding etc. complete.
Detail of cost for 10 Sq.m.
MATERIAL :
CARRIAGE :
Gadsa Stone
1 KM BY MECH. TRANSPORT 1 tonne 1.69500 73.95 125.35
Cement|
1 KM BY MECH. TRANSPORT 1 tonne 0.06400 73.95 4.73
LABOUR :
Mason 2nd Class Each 6.50000 158.67 1031.36
Beldar Each 10.00000 116.67 1166.70
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 2318.05
Labour for cement mortar 1:3 18.48
TOTAL : 2336.53
WATER CHARGES @ 1.5% 135.78
TOTAL : 2472.31
ADD FOR CONTRACTORS PROFIT @10% : 247.23
ADD FOR OVER HEAD CHARGES@5% : 123.61
LABOUR FOR 10.000sq.m. 2843.15
LABOUR PER sq.m. 284.30
13600000 Providing and laying spartic
ceremic tiles 5.5mm.thick in
flooring (300 x300mm.
size)treads
of steps laid on a bed of
12mm. thick cement mortar
1:3(1cement:
3 sand) finished with flush
pointing in white cement.
Detail of cost for one Sq.m.
MATERIAL :
Spartic
tiles300x300x5.5mm =11.11No
Add 2.5% for wastage =0.27no
Total = 11.38 Nos.
Say 11 Nos.
1 no 11.00000 50.00 550.00
CARRIAGE :
Bricks tiles.
1 KM BY MECH. TRANSPORT 1000 nos 11.00000 173.35 1.90
LABOUR :
Mason 1st class Each 0.70000 211.16 147.81
Beldar Each 0.70000 116.67 81.67
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 244.48
Labour for cement mortar 1:3 1.92
TOTAL : 246.40
WATER CHARGES @ 1.5% : 14.06
TOTAL : 260.46
ADD FOR CONTRACTORS PROFIT @10% : 26.05
ADD FOR OVER HEAD CHARGES@5% : 13.02
LABOUR FOR1.000sq.m. 299.53
LABOUR PER sq.m. 299.50
13610000 Providing and laying 20mm.
thick acid proof tiles of size
upto
300 x 300mm. of specified
shade in floors, treads of
steps and landing laid on a
bed of 12mm. thick acid proof mortor
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
1:3(1 cement:
3 sand) jointing with cement
slurry mixed with pigment to
match the shade of tiles.
Detail of cost for one Sq.m.
MATERIAL :
CARRIAGE :
Bricks /tiles.
1 KM BY MECH. TRANSPORT 1000 nos.46.00000 173.35 7.97
LABOUR :
Mason 1st class Each 0.70000 211.16 147.81
Beldar Each 0.70000 116.67 81.66
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 244.47
TOTAL : 244.47
WATER CHARGES @ 1.5% : 22.51
TOTAL : 266.98
ADD FOR CONTRACTORS PROFIT @10% : 26.70
ADD FOR OVER HEAD CHARGES@5% : 13.35
LABOUR FOR1.000sq.m. 307.03
LABOUR PER sq.m. 307.00
13620000 Providing and laying marble
work
(Table rubbed and polished) in
flooring on 20mm. thick base in
cement mortar
1:3(1cement:3sand)
including jointing with cement
mortar 1:2(1 white cement:2
marble
dust) with an admixure of
pigment
to match the shade of the
marble.
20 mm thick White makrana
marble.
MATERIAL :
Cement mortar
1:3(1cement:3sand)
1 cum 0.22400 3178.80 712.05
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Cement for slurry.
For bedding =44.00kg.
For joints =20.00kg.
Total =64.00kg.
or0.064tonne
1 tonne 0.06400 4900.00 313.60
( 64 x3.5)/50=4.5 kg.
0.0045tonne.
1 tonne 0.00450 18000.00 81.00
CARRIAGE :
Cement
1 KM BY MECH. TRANSPORT 1 tonne 0.06400 73.95 4.73
LABOUR RATE :
For dressing of stone :
Mason 1st class Each 13.50000 211.16 2850.66
Black Smith 1st Class Each 1.10000 186.67 205.34
Beldar Each 4.10000 116.67 478.35
Bandhani Each 4.50000 116.67 525.02
Beldar
(Skilled)for rubbing Each 4.50000 116.67 525.02
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 7284.05
Labour for cement mortar 1:3 28.75
TOTAL : 7312.80
WATER CHARGES @ 1.5% : 397.22
TOTAL : 7710.02
ADD FOR CONTRACTORS PROFIT @10% : 771.00
ADD FOR OVER HEAD CHARGES@5% : 385.50
LABOUR FOR 10.000sq.m. 8866.52
LABOUR PER sq.m. 886.65
13630000 Providing and laying marble
work
(table rubbed and polished) in
flooring 20mm. thick base in
cement mortar
1:3(1cement:3sand)
including jointing with cement
mortar 1:2(1 white cement:2
marble
dust)with an admixure of
pigmeent
to match the shade of the
marble.
20 mm.thick Pink makrana
marble.
MATERIAL :
Cement mortar
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
1:3(1cement:3sand).
1 cum 0.22400 3178.80 712.05
CARRIAGE :
Cement
1 KM BY MECH. TRANSPORT 1 tonne 0.06400 7395.00 4.73
LABOUR RATE :
For dressing of stone :
Mason 1st class Each 13.50000 211.16 2850.66
Black Smith 1st Class Each 1.10000 186.67 205.34
Beldar Each 4.10000 116.67 478.35
Bandhani Each 4.50000 116.67 525.02
Beldar
(Skilled)for rubbing Each 4.50000 116.67 525.02
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 7284.05
Labour for cement mortar 1:3 28.75
TOTAL : 7312.80
WATER CHARGES @ 1.5% : 307.25
TOTAL : 7620.05
ADD FOR CONTRACTORS PROFIT @10% : 762.00
ADD FOR OVER HEAD CHARGES@5% : 381.00
LABOUR FOR 10.000sq.m. 8763.05
LABOUR PER sq.m. 876.30
1364000000
Providing and fixing black
cuddapa stone slab 20mm thick
10 cm wide in flooring on 20mm
thick base of cement mortar 1:4
(1 cement : 4 sand) including
jointing with grey cement slurry
mixed with pigment to match the
shade of stone i/c rubbing and
polishing complete.
MATERIAL :
20mm thick black cuddapa stone
100x0.10m =10.00 sqm
Add. Wastage @ 15%=1.50 sqm
Total =11.50 sqm sqm 11.50000 265.00 3047.50
CARRIAGE :
Carriage of Cement/pigment
LABOUR :
Mason 2nd Class each 5.40000 158.67 856.81
Beldar each 8.21000 116.67 957.86
Beldar (Skilled) for rubbing & Polishing
Each 10.80000 116.67 1260.03
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 3224.70
Labour for cement mortar 28.75
Total 3253.45
Add. For water charges 111.95
Total 3365.40
ADD FOR CONTRACTORS PROFIT @10% : 336.54
ADD FOR OVER HEAD CHARGES @5% : 168.27
LABOUR FOR 100.00 Metre 10 cm wide 3870.21
LABOUR PER Metre 10 cm wide 38.70
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
1365000000 Providing and fixing 2mm thick
PVC antistatic venyl Flooring
plain or coloured, carbed or
mosaic/metalled finish laid with
approved adhesive on sub-floor
(damp proofing treatment to be
paid for separately)
Material
LABOUR :
Mason 2nd Class each 1.50000 158.67 238.00
Beldar each 1.50000 116.67 175.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 423.00
MATERIAL :
40mm thick red sand stone
100x0.10m =10.00 sqm
Add. Wastage @ 15%=1.50 sqm
Total =11.50 sqm sqm 11.50000 380.00 4370.00
CARRIAGE :
Carriage of Cement/pigment
LABOUR :
Mason 2nd Class each 7.00000 158.67 1110.70
Beldar each 10.80000 116.67 1260.03
Beldar (Skilled) for rubbing & Polishing
Each 10.80000 116.67 1260.03
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 3780.76
Labour for cement mortar 28.75
Total 3809.51
Add. For water charges 144.80
Total 3954.31
ADD FOR CONTRACTORS PROFIT @10% : 395.43
ADD FOR OVER HEAD CHARGES @5% : 197.71
LABOUR FOR 10.00 sqm 4546.45
LABOUR PER Sqm 454.65
MATERIAL :
40mm thick red sand stone
100x0.10m =10.00 sqm
Add. Wastage @ 15%=1.50 sqm
Total =11.50 sqm sqm 11.50000 380.00 4370.00
CARRIAGE :
Carriage of Cement/pigment
LABOUR :
Mason 2nd Class each 6.50000 158.67 1031.35
Beldar each 10.80000 116.67 1260.03
Beldar (Skilled) for rubbing & Polishing
Each 10.80000 116.67 1260.03
Mason 1st class (for making nosing Each 1.10000 211.16 232.28
Sundries L.S. 150.00
TOTAL : 9679.71
Add. For water charges @ 1.5% 145.20
TOTAL : 9824.90
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 3933.69
Labour for cement mortar 28.75
Total 3962.44
Add. For water charges 145.20
Total 4107.64
ADD FOR CONTRACTORS PROFIT @10% : 410.76
ADD FOR OVER HEAD CHARGES @5% : 205.38
LABOUR FOR 10.00 sqm 4723.78
LABOUR PER Sqm 472.40
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
1368000000 Providing and fixing 10mm thick
anti skid water proof stain and
impect resistent heavy duty
vetrified tiles Nitco or equivalant
600x600mmx10mm
manufactured of approved
shade and colour in flooring,
treads of steps and landings laid
over 12mm thick cement mortar
1:3 (1 cement : 3 sand) jointed
with cement slurry mixed with
pigment to match the shade of
tiles as required complete.
MATERIAL :
10mm thick vetrified tiles
=1.00 sqm
Add. Wastage @ 5%=0.05 sqm
Total =1.05 sqm sqm 1.05000 720.00 756.00
CARRIAGE :
Carriage of tile
Carriage of Cement/pigment
L.S 5.00
LABOUR :
Mason for terrazo work each 0.70000 186.67 130.66
Beldar each 0.70000 116.67 81.66
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Sundries L.S. 10.00
TOTAL : 1086.42
Add. For water charges @ 1.5% 16.30
TOTAL : 1102.72
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 222.32
Labour for cement mortar 1.92
Total 224.24
Add. For water charges 16.30
Total 240.54
ADD FOR CONTRACTORS PROFIT @10% : 24.05
ADD FOR OVER HEAD CHARGES @5% : 12.02
LABOUR FOR 1.00 sqm 276.61
LABOUR PER Sqm 276.60
MATERIAL :
Duro stone vetrified tiles
=1.00 sqm
Add. Wastage @ 5%=0.10 sqm
Total =1.10 sqm sqm 1.10000 720.00 792.00
CARRIAGE :
Carriage of tile
Carriage of Cement/pigment
L.S 5.00
LABOUR :
Mason for terrazo work each 0.70000 186.67 130.66
Beldar each 0.70000 116.67 81.66
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 222.32
Labour for cement mortar 1.92
Total 224.24
Add. For water charges 17.55
Total 241.79
ADD FOR CONTRACTORS PROFIT @10% : 24.17
ADD FOR OVER HEAD CHARGES @5% : 12.08
LABOUR FOR 1.00 sqm 278.04
LABOUR PER Sqm 278.00
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
1370000000 Providing and laying Duro stone
vetrified tiles
(300x300mmx8mm) in
grey/coloured of required shade
in skirting risers of steps and
dados on 12mm thick cement
mortar 1:3 (1 cement : 3 sand)
laid over and jointed with neat
cement slurry finished with flush
pointing in white cement mixed
with pigment of required shade
to match the shade of tiles
complete.
Detail o cost 1.00 sqm.
MATERIAL :
Duro stone vetrified tiles
=1.00 sqm
Add. Wastage @ 15%=0.10 sqm
Total =1.10 sqm
sqm 1.10000 550.00 605.00
CARRIAGE :
Carriage of tile
Carriage of Cement/pigment
L.S 5.00
LABOUR :
Mason for terrazo work each 0.77000 186.67 143.73
Beldar each 0.77000 116.67 89.83
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 243.56
Labour for cement mortar 1.92
Total 245.48
Add. For water charges 15.05
Total 260.53
ADD FOR CONTRACTORS PROFIT @10% : 26.05
ADD FOR OVER HEAD CHARGES @5% : 13.02
LABOUR FOR 1.00 sqm 299.60
LABOUR PER Sqm 299.60
MATERIAL :
Precast inter locking paver blocks (40mm thick
=10.00 sqm
Add. Wastage @ 15%=1.00 sqm
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Total =11.00 sqm
sqm 11.00000 390.00 4290.00
CARRIAGE :
Carriage of Cement/pigment
LABOUR :
Mason for terrazo work each 2.16000 186.67 403.20
Beldar each 2.16000 116.67 252.00
Bhisti Each 0.30000 116.67 35.00
Beldar (skilled) for rubbing,
polishing & curing 6.50000 116.67 758.35
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1523.55
Labour for cement mortar 32.72
Total 1556.27
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Add. For water charges @ 1.5% 108.98
Total 1665.25
ADD FOR CONTRACTORS PROFIT @10% : 166.52
ADD FOR OVER HEAD CHARGES @5% : 83.26
LABOUR FOR 10.00 sqm 1915.03
LABOUR PER Sqm 191.50
MATERIAL :
Precast inter locking paver blocks (60mm thick
=10.00 sqm
Add. Wastage @ 15%=1.00 sqm
Total =11.00 sqm
sqm 11.00000 475.00 5225.00
CARRIAGE :
Carriage of Cement/pigment
LABOUR :
Mason for terrazo work each 2.16000 186.67 403.20
Beldar each 2.16000 116.67 252.00
Bhisti Each 0.30000 116.67 35.00
Paving and Flooring
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Beldar (skilled) for rubbing,
polishing & curing 6.50000 116.67 758.35
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1523.55
Labour for cement mortar 32.72
Total 1556.27
Add. For water charges @ 1.5% 123.00
Total 1679.27
ADD FOR CONTRACTORS PROFIT @10% : 167.92
ADD FOR OVER HEAD CHARGES @5% : 83.99
LABOUR FOR 10.00 sqm 1931.18
LABOUR PER Sqm 193.10
MATERIAL :
Precast inter locking paver blocks (60mm thick
=10.00 sqm
Add. Wastage @ 10%=1.00 sqm
Total =11.00 sqm 11.00000 540.00 5940.00
CARRIAGE :
Carriage of Cement/pigment
LABOUR :
Mason for terrazo work each 2.16000 186.67 403.20
Beldar each 2.16000 116.67 252.00
Bhisti Each 0.30000 116.67 35.00
Beldar (skilled) for rubbing,
polishing & curing 6.50000 116.67 758.35
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1523.55
Labour for cement mortar 32.72
Total 1556.27
Add. For water charges @ 1.5% 133.72
Total 1689.99
ADD FOR CONTRACTORS PROFIT @10% : 168.99
ADD FOR OVER HEAD CHARGES @5% : 84.45
LABOUR FOR 10.00 sqm 1943.43
LABOUR PER Sqm 194.35
CHAPTER XIV
ROOF COVERINGS
Chapter XIV
ROOF COVERINGS
Notes :-
1 The labour and through rates include the carriage of materials for 100 meters on
head load and one kilometer by mechanical transport. These also include the cost
of water, tools and plants, scaffolding and cost of good earth for mud mortar
wherever required.
CHAPTER-XIV
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
14010000 Providing corrugated G.I sheet
roofing fixed with galvanised iron
J.or L. hooks bolts and nuts 8 mm
diameter with bitumen and G.I.
limpet washers filled with white
lead complete excluding the cost of
purlins refters and trusses.
MATERIAL :
MATERIALS:
C.G.I.sheet 0.80mm thick.
2 x 27 = 54Nos @ 15.82 kg each
=854.38 kg. (X)
2.5m x 0.90m is the size of plain
G.I.sheet which on being corrugated
will become 2.5 x 0.80m
(the size of plain sheet is taken
because the weight is available
only of plain sheets.)
2 x 27 = 54 Nos of size 2.80x0.90m
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
@ 17.72 kg each = 956.80 kg.(Y)
Total of (X) + (Y) =1811.16 kg.
Add for wastage @5%= 90.56 kg.
Total: =1901.72 kg.
or 19.0172 Qtls.
1 qtl. 19.01720 5500.00 104594.60
Limpet washers.
(Total of seam bolts and hooks
884 + 810 =1694 Nos. 100 nos 1694.00000 40.00 677.60
CARRIAGE :
C.G.I
1 KM BY MECH. TRANSPORT 1 tonne 1.90200 73.95 140.65
LABOUR :
Black Smith 2nd Class Each 1.30000 148.16 192.61
Carpenter 2nd Class Each 14.75000 186.67 2753.38
Beldar Each 14.75000 116.67 1720.88
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 4711.86
TOTAL : 4711.86
ADD FOR CONTRACTORS PROFIT @10% : 471.18
ADD FOR OVER HEAD CHARGES @5% : 235.59
LABOUR FOR 184.520 sq.m. 5418.63
LABOUR PER sq.m. 29.35
14010200 0.63 mm thick sheet.
Details of cost for area of roof
2x18.09x5.1=184.518 sq.m
MATERIAL :
MATERIALS:
C.G.I. sheets 0.63mm. thick.
CGI.sheets 2x27 =54 Nos.of size
2.80x0.90 metres @ 12.82 kg.
each sheet =692.28 kg.(L)
2x27 = 54 Nos of size
2.80x0.90 metres @ 14.38 kg.
each sheet =775.44 kg (M)
Total:(L+M) =1467.72 kg
Add wastage @ 5% = 73.39 kg
G. Total: =1541.41 kgs.
or 15.41 Qtls. 1 qtl. 15.41000 5500.00 84755.00
G.I. J or L. hooks.
Qty. same as per item No.14010100 10 nos 810.00000 60.00 4860.00
Limpet washers.
Qty. same as per item No.14010100 100 nos 1694.00000 40.00 677.60
Bitumen washers.
Qty same as per item No.14010100 100 nos 1694.00000 25.00 423.50
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
CARRIAGE :
C.G.I
1 KM BY MECH. TRANSPORT 1 tonne 1.54000 73.95 113.88
LABOUR :
Black Smith 2nd Class Each 1.30000 148.16 192.61
Carpenter 2nd Class Each 14.75000 186.67 2753.38
Beldar Each 14.75000 116.67 1720.88
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 4711.86
TOTAL : 4711.86
ADD FOR CONTRACTORS PROFIT @10% : 471.18
ADD FOR OVER HEAD CHARGES @5% : 235.59
LABOUR FOR 184.520 Sq.m 5418.63
LABOUR PER Sq.m 29.35
14020100 Extra for providing and fixing
curved coorrugated G .I sheet in
roofing
LABOUR :
Carpenter 2nd Class Each 2.65000 186.67 494.68
Beldar Each 2.50000 116.67 291.68
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 786.35
ADD FOR CONTRACTORS PROFIT @10% : 78.64
ADD FOR OVER HEAD CHARGES @5% : 39.32
COST FOR 184.520 sq.m. 904.30
COST PER sq.m. 4.90
LABOUR PER sq.m. 4.90
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 786.35
TOTAL : 786.35
ADD FOR CONTRACTORS PROFIT @10% : 78.64
ADD FOR OVER HEAD CHARGES @5% : 39.32
LABOUR FOR 184.520 sq.m. 904.30
LABOUR PER sq.m. 4.90
14020102 0.63 mm thick
Details of cost for 184.52 sqm.
LABOUR :
Carpenter 2nd Class Each 2.15000 186.67 401.34
Beldar Each 2.00000 116.67 233.34
TOTAL : 634.68
ADD FOR CONTRACTORS PROFIT @10% : 63.46
ADD FOR OVER HEAD CHARGES @5% : 31.73
COST FOR 184.520 sqm. 729.87
COST PER sqm. 3.95
LABOUR PER sqm. 3.95
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 634.68
TOTAL : 634.68
ADD FOR CONTRACTORS PROFIT @10% : 63.46
ADD FOR OVER HEAD CHARGES @5% : 31.73
LABOUR FOR 184.520 sqm. 729.87
LABOUR PER sqm. 3.95
14020200 Providing and fixing corrugated
G.I.sheets vertically or to a pitch
exceeding 60.
Details of cost for 184.52 sqm.
LABOUR :
Beldar Each 5.00000 116.67 583.35
TOTAL : 583.35
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR CONTRACTORS PROFIT @10% : 58.34
ADD FOR OVER HEAD CHARGES @5% : 29.17
COST FOR 184.520 sqm. 670.85
COST PER sqm. 3.65
LABOUR PER sqm. 3.65
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 583.35
TOTAL : 583.35
ADD FOR CONTRACTORS PROFIT @10% : 58.33
ADD FOR OVER HEAD CHARGES @5% : 29.17
LABOUR FOR 184.520 sqm. 670.85
LABOUR PER sqm. 3.65
14020300 Straight cutting and waste in
C.G.I. Sheet roofing for making
opening of area exceeding 40 sqdm
for chimney stacks, sky light etc.
MATERIAL :
LABOUR :
Black Smith 1st Class Each 0.12000 186.67 22.40
Beldar Each 0.12000 116.67 14.00
Total : 408.95
ADD FOR CONTRACTORS PROFIT @10% Except on (-I-) : 3.64
ADD FOR OVER HEAD CHARGES @5% Except on (-I-): 1.82
COST FOR 3.000 Metre 414.41
COST PER Metre 138.15
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 36.40
Labour As per item no :14010100 14.67
TOTAL : 51.07
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
MATERIAL :
LABOUR :
Black Smith 1st Class Each 2.50000 186.67 466.68
Beldar Each 5.00000 116.67 583.35
Total : 2510.43
ADD FOR CONTRACTORS PROFIT @10% Except on (-I-) : 251.05
ADD FOR OVER HEAD CHARGES @5% Except on (-I-): 125.52
COST FOR 15.710 Metre 2887.00
COST PER Metre 183.75
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1050.03
Labour As per item no :14010100 57.52
TOTAL : 1107.55
MATERIAL :
Perimetre of 10 holes
22/7x0.50x10 =15.71 Mtr.perimetre
The wastage will be:--
10xII/4x(0.50)2 = 1.96 sqm.
(Rate same as per item No.14010100 1 sqm 1.96000 621.15 1217.45
LABOUR :
Black Smith 1st Class Each 2.25000 186.67 420.00
Beldar Each 4.50000 116.67 525.02
Total : 2162.45
ADD FOR CONTRACTORS PROFIT @10% Except on (-I-) : 94.50
ADD FOR OVER HEAD CHARGES @5% Except on (-I-): 47.25
COST FOR 15.710 Metre 2304.20
COST PER Metre 146.65
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 945.00
Labour As per item no :14010200 57.52
TOTAL : 1002.52
LABOUR :
Black Smith 1st Class Each 1.00000 186.67 186.67
Beldar Each 0.25000 116.67 29.17
TOTAL : 215.83
ADD FOR CONTRACTORS PROFIT @10% : 21.58
ADD FOR OVER HEAD CHARGES @5% : 10.79
COST FOR 20.000 Recesses 248.20
COST PER Recesses 12.40
LABOUR PER Recesses 12.40
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 215.83
TOTAL : 215.83
ADD FOR CONTRACTORS PROFIT @10% : 21.58
ADD FOR OVER HEAD CHARGES @5% : 10.79
LABOUR FOR 20.000 Recesses 248.20
LABOUR PER Recesses 12.40
14020502 Area above 100 sq.cm. upto400 sq.cm.
Details of cost for 12 recesses.
LABOUR :
Black Smith 1st Class Each 1.00000 186.67 186.67
Beldar Each 1.00000 116.67 116.67
TOTAL : 303.34
ADD FOR CONTRACTORS PROFIT @10% : 30.33
ADD FOR OVER HEAD CHARGES @5% : 15.16
COST FOR 12.000 Recesses 348.83
COST PER Recesses 29.05
LABOUR PER Recesses 29.05
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 303.34
TOTAL : 303.34
ADD FOR CONTRACTORS PROFIT @10% : 30.33
ADD FOR OVER HEAD CHARGES @5% : 15.16
LABOUR FOR 12.000 Recesses 348.83
LABOUR PER Recesses 29.05
14020503 Above 400 sq.cm. in area.
Detail of cost for 8 recesses.
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR :
Black Smith 1st Class Each 1.00000 186.67 186.67
Beldar Each 1.00000 116.67 116.67
TOTAL : 303.34
ADD FOR CONTRACTORS PROFIT @10% : 30.33
ADD FOR OVER HEAD CHARGES @5% : 15.16
COST FOR 8.000 Recesses 348.83
COST PER Recesses 43.60
LABOUR PER Recesse 43.60
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES155.16 303.34
TOTAL : 306.34
ADD FOR CONTRACTORS PROFIT @10% : 30.33
ADD FOR OVER HEAD CHARGES @5% : 15.16
LABOUR FOR 8.000 Recesses 348.83
LABOUR PER Recesse 43.60
14030000 Providing ridges or hips 60 cm
over all in plain with galvanised
iron G.I.sheet J or L hooks.
bolts and nuts 8mm dia G.I. Limpet
and bitumen washers copmlete:-
MATERIAL :
CARRIAGE :
C.G.I Sheet
1 KM BY MECH. TRANSPORT 1 tonne 0.05800 73.95 4.29
LABOUR :
Carpenter 1st Class each 0.40000 211.16 84.46
Black Smith 1st Class each 1.04000 186.67 194.14
Black Smith 2nd Class each 1.04000 148.16 154.09
Beldar each 2.40000 116.67 280.01
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 722.68
TOTAL : 722.68
ADD FOR CONTRACTORS PROFIT @10% : 72.26
ADD FOR OVER HEAD CHARGES @5% : 36.13
LABOUR FOR 10.350 Metres 831.08
LABOUR PER Metres 80.30
14030200 0.63 mm thick G.I. sheet
Details of cost for 10.35 metre
long ridge
MATERIAL :
CARRIAGE :
C.G.I Sheet
1 KM BY MECH. TRANSPORT 1 tonne 0.04700 73.95 3.48
LABOUR :
Carpenter 1st Class Each 0.40000 211.16 84.46
Black Smith 1st Class Each 1.04000 186.67 194.14
Beldar Each 2.40000 116.67 280.01
Black Smith 2nd class Each 1.04000 148.16 154.09
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 722.68
TOTAL : 722.68
ADD FOR CONTRACTORS PROFIT 10% : 72.26
ADD FOR OVER HEAD CHARGES @5% : 36.13
LABOUR FOR 10.350 Metre 831.08
LABOUR PER Metre 80.30
14040000 Providing valleys 90 cm over all in
plain G.I. sheets fixed with
galvanised iron J or L hooks.
bolts and nuts 8mm dia G.I. limpet
and bitumen washers complete:-
MATERIAL :
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
CARRIAGE :
C.G.I Sheet |
1 KM BY MECH. TRANSPORT 1 tonne 0.12200 73.95 9.02
LABOUR :
Carpenter 1st Class Each 0.40000 211.16 84.46
Black Smith 1st Class Each 1.04000 186.67 194.14
Black Smith 2nd Class Each 1.04000 148.16 154.09
Beldar Each 2.40000 116.67 280.01
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 722.68
TOTAL : 722.68
ADD FOR CONTRACTORS PROFIT 10% : 72.26
ADD FOR OVER HEAD CHARGES @5% : 36.13
LABOUR FOR 9.325 Metre 831.08
LABOUR PER Metre 89.10
14040200 0.80 mm thick sheet.
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Details of cost for 9.325 metre.
MATERIAL :
CARRIAGE :
C.G.I Sheet
1 KM BY MECH. TRANSPORT 1 tonne 0.06500 73.95 4.81
LABOUR :
Carpenter 1st Class Each 0.40000 211.16 84.46
Black Smith 1st Class Each 1.04000 186.67 194.14
Black Smith 2nd Class Each 1.04000 148.16 154.09
Beldar Each 2.40000 116.67 280.01
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 722.68
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 722.68
ADD FOR CONTRACTORS PROFIT 10% : 72.26
ADD FOR OVER HEAD CHARGES @5% : 36.13
LABOUR FOR 9.325 metre 831.08
LABOUR PER metre 89.10
14040300 0.63 mm thick sheet
Details of cost for 9.325 metre.
MATERIAL :
CARRIAGE :
C.G.I Sheet
1 KM BY MECH. TRANSPORT 1 tonne 0.05200 73.95 3.85
LABOUR :
Carpenter 1st Class each 0.40000 211.16 84.46
Black Smith 1st Class each 1.04000 186.67 194.14
Black Smith 2nd Class each 1.04000 148.16 154.09
Beldar each 2.40000 116.67 280.01
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 722.68
TOTAL : 722.68
ADD FOR CONTRACTORS PROFIT 10% : 72.26
ADD FOR OVER HEAD CHARGES @5% : 36.13
LABOUR FOR 9.325 metre 831.08
LABOUR PER metre 89.10
14050000 Providing flushing 38cm.
overall in plain G.I. sheet fixed
with galvanised iron.
J or L hooks, bolts and nuts, G.I.
limpet and bitumen washers
complete bent to
shape and fixed in walls with
cement mortar 1:3 (1 cement.3 sand)
MATERIAL :
CARRIAGE :
C.G.I Sheet
1 KM BY MECH. TRANSPORT 1 tonne 0.05200 73.95 3.85
LABOUR :
Carpenter 1st Class Each 0.50000 211.16 105.58
Black Smith 1st Class Each 1.48000 186.67 276.27
Black Smith 2nd Class Each 1.00000 148.16 148.16
Beldar Each 3.00000 116.67 350.01
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 890.02
TOTAL : 890.02
ADD FOR CONTRACTORS PROFIT 10% : 89.00
ADD FOR OVER HEAD CHARGES @5% : 44.50
LABOUR FOR 12.125 Metre 1023.54
LABOUR PER Metre 84.40
14050200 1.00mm thick sheet
Details of cost for 12.125 metre
MATERIAL :
CARRIAGE :
C.G.I Sheet
1 KM BY MECH. TRANSPORT 1 tonne 0.04200 73.95 3.11
LABOUR :
Carpenter 1st Class Each 0.50000 211.16 105.58
Black Smith 1st Class Each 1.48000 186.67 276.27
Black Smith 2nd Class Each 1.00000 148.16 148.16
Beldar Each 3.00000 116.67 350.01
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 890.01
TOTAL : 890.01
ADD FOR CONTRACTORS PROFIT 10% : 89.00
ADD FOR OVER HEAD CHARGES @5% : 44.50
LABOUR FOR 12.125 metre 1023.51
LABOUR PER metre 84.40
14050300 0.80mm thick sheet.
Details of cost for 12.125 metre
MATERIAL :
CARRIAGE :
C.G.I Sheet
1 KM BY MECH. TRANSPORT 1 tonne 0.03400 73.95 2.51
LABOUR :
Carpenter 1st Class Each 0.50000 211.16 105.58
Black Smith 1st Class Each 1.48000 186.67 276.27
Black Smith 2nd Class Each 1.00000 148.16 148.16
Beldar Each 3.00000 116.67 350.01
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 890.01
TOTAL : 890.01
ADD FOR CONTRACTORS PROFIT 10% : 89.00
ADD FOR OVER HEAD CHARGES @5% : 44.50
LABOUR FOR 12.125 metre 1023.51
LABOUR PER metre 84.40
14050400 0.63mm thick sheet.
Details of cost for 12.125 metre.
MATERIAL :
CARRIAGE :
C.G.I Sheet
1 KM BY MECH. TRANSPORT 1 tonne 0.02800 73.95 2.07
LABOUR :
Carpenter 1st Class Each 0.50000 211.16 105.58
Black Smith 1st Class Each 1.48000 186.67 276.27
Black Smith 2nd Class Each 1.00000 146.16 146.16
Beldar Each 3.00000 116.67 350.01
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 890.01
TOTAL : 890.01
ADD FOR CONTRACTORS PROFIT 10% : 89.00
ADD FOR OVER HEAD CHARGES @5% : 44.50
LABOUR FOR 12.125 metre 1023.51
LABOUR PER metre 84.40
14060000 Providing and fixing 15 cm.
wide 45 cm. overall semicircular
plain G.I. sheetgutter with iron
brackets 40x3mm size bolts and
nuts and washers etc. including
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
making necessary conections with
rain water pipe complete as per
design.
MATERIAL :
CARRIAGE :
C.G.I Sheet
1 KM BY MECH. TRANSPORT 1 tonne 0.03200 73.95 2.37
LABOUR :
Carpenter 1st Class Each 0.35000 211.16 73.91
Black Smith 1st Class Each 0.90000 186.67 168.00
Black Smith 2nd Class Each 0.90000 148.16 133.34
Beldar Each 2.10000 116.67 245.01
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 630.24
TOTAL : 630.24
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR CONTRACTORS PROFIT 10% : 63.02
ADD FOR OVER HEAD CHARGES @5% : 31.51
LABOUR FOR 9.040 metre 724.77
LABOUR PER metre 80.20
14060200 0.63mm thick sheet.
Detail of cost for length of 9.04m
MATERIAL :
CARRIAGE :
C.G.I Sheet
1 KM BY MECH. TRANSPORT 1 tonne 0.02600 73.95 1.92
LABOUR :
Carpenter 1st Class Each 0.35000 211.16 73.91
Black Smith 1st Class Each 0.90000 186.67 168.00
Black Smith 2nd Class Each 0.90000 148.16 133.34
Beldar Each 2.10000 116.67 245.01
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 630.24
TOTAL : 630.24
ADD FOR CONTRACTORS PROFIT 10% : 31.51
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR OVER HEAD CHARGES @5% : 724.77
LABOUR FOR 9.040 metre 80.20
LABOUR PER metre
14070000 Extra for making opening or receses
in plain G.I. sheet of girth not
more than 1 metre.
LABOUR :
Black Smith 1st Class Each 1.00000 186.67 186.67
Beldar Each 0.25000 116.67 29.17
TOTAL : 215.83
ADD FOR WATER CHARGES @ 1.5% : 3.23
TOTAL : 219.06
ADD FOR CONTRACTORS PROFIT 10% : 21.90
ADD FOR OVER HEAD CHARGES @5% : 10.95
COST FOR 20.000 Recesses 251.91
COST PER Recesses 12.60
LABOUR PER Recesses 12.60
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 215.83
TOTAL : 215.83
WATER CHARGES @ 1.5% : 3.23
TOTAL : 219.06
ADD FOR CONTRACTORS PROFIT 10% : 21.90
ADD FOR OVER HEAD CHARGES @5% : 10.95
LABOUR FOR 20.000 Recesses 251.91
LABOUR PER Recesses 12.60
14070200 Above 100 sq. cm. up to
400 sq.cm. in area
Details of cost for 12 recesses.
LABOUR :
Black Smith 1st Class Each 1.00000 186.67 186.67
Beldar Each 1.00000 116.67 116.67
TOTAL : 303.34
ADD FOR WATER CHARGES @ 1.5% : 4.55
TOTAL : 307.89
ADD FOR CONTRACTORS PROFIT 10% : 30.78
ADD FOR OVER HEAD CHARGES @5% : 15.39
COST FOR 12.000 Recesses 354.07
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
COST PER Recesses 29.50
LABOUR PER Recesses 29.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 303.34
TOTAL : 303.34
WATER CHARGES @ 1.5% : 4.55
TOTAL : 307.89
ADD FOR CONTRACTORS PROFIT 10% : 30.78
ADD FOR OVER HEAD CHARGES @5% : 15.39
LABOUR FOR 12.000 Recesses 354.07
LABOUR PER Recesses 29.50
14070300 Above 400 sq. cm in area.
Detail of cost for 8 recesses.
LABOUR :
Black Smith 1st Class Each 1.00000 186.67 186.67
Beldar Each 1.00000 116.67 116.67
TOTAL : 303.34
ADD FOR WATER CHARGES @ 1.5% : 4.54
TOTAL : 307.89
ADD FOR CONTRACTORS PROFIT 10% : 30.78
ADD FOR OVER HEAD CHARGES @5% : 15.39
COST FOR 8.000 Recesses 354.07
COST PER Recesses 44.25
LABOUR PER Recesses 44.25
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 303.34
TOTAL : 303.34
WATER CHARGES @ 1.5% : 4.55
TOTAL : 307.89
ADD FOR CONTRACTORS PROFIT 10% : 30.78
ADD FOR OVER HEAD CHARGES @5% : 15.39
LABOUR FOR 8.000 Recesses 354.07
LABOUR PER Recesses 44.25
14080000 Extra for providing and fixing wind
ties of 40 x 6mm flat iron section
Details of cost for 30 metre
MATERIAL :
M.S.flat:
40mmx6mm =30 metre
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
wastage @ 5% =1.5 metre
--------------
=31.5 metre
@ 1.9 kg. per metre =59.85 kg.
or 0.5985 qtl. 1 qtl 0.59850 4500.00 2693.25
CARRIAGE :
M.S Flat
1 KM BY MECH. TRANSPORT 1 tonne 0.06000 73.95 4.44
LABOUR :
Black Smith 1st Class Each 0.50000 186.67 93.34
Beldar Each 0.50000 116.67 58.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 166.68
TOTAL : 166.68
ADD FOR CONTRACTORS PROFIT 10% : 16.66
ADD FOR OVER HEAD CHARGES @5% : 8.33
LABOUR FOR 30.000 metre 191.68
LABOUR PER metre 6.40
14090000 Conversion of plain G.I. sheet to rain
water pipe 0.63mm thick and fixing
the same
MATERIAL :
LABOUR :
Black Smith 2nd Class Each 1.74000 148.16 257.80
Beldar Each 0.74000 116.67 86.34
TOTAL : 1204.13
ADD FOR CONTRACTORS PROFIT 10% : 120.41
ADD FOR OVER HEAD CHARGES @5% : 60.20
COST FOR 10.000 metre 1384.74
COST PER metre 138.50
LABOUR PER metre 39.60
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 344.13
TOTAL : 344.13
ADD FOR CONTRACTORS PROFIT 10% : 34.41
ADD FOR OVER HEAD CHARGES @5% : 17.20
LABOUR FOR 10.000 metre 395.74
LABOUR PER metre 39.60
14090200 150mm dia
Details of cost for 10 metrelength
MATERIAL :
LABOUR :
Black Smith 2nd Class Each 1.74000 148.16 257.80
Beldar Each 0.74000 116.67 86.34
TOTAL : 1718.13
ADD FOR CONTRACTORS PROFIT 10% : 171.81
ADD FOR OVER HEAD CHARGES @5% : 85.90
COST FOR 10.000 metre 1975.84
COST PER metre 197.60
LABOUR PER metre 39.60
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 344.13
TOTAL : 344.13
ADD FOR CONTRACTORS PROFIT 10% : 34.41
ADD FOR OVER HEAD CHARGES @5% : 17.20
LABOUR FOR 10.000 metre 395.74
LABOUR PER metre 39.60
14100000 Providing and fixing of P.G.I.
sheet bend of required degree
(0.63mm thick sheet)for rain water
pipe
MATERIAL :
LABOUR :
Fixing charges L.S 5.00
TOTAL : 60.00
ADD FOR CONTRACTORS PROFIT 10% : 6.00
ADD FOR OVER HEAD CHARGES @5% : 3.00
COST FOR 1.000 Bend 69.00
COST PER Bend 69.00
LABOUR PER Bend 5.75
LABOUR RATE :
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ACTUAL LABOUR+SUNDRIES 5.00
TOTAL : 5.00
ADD FOR CONTRACTORS PROFIT 10% : 0.50
ADD FOR OVER HEAD CHARGES @5% : 0.25
LABOUR FOR 1.000 Bend 5.75
LABOUR PER Bend 5.75
14100200 150 mm dia
Details of cost for 1 bend
MATERIAL :
LABOUR :
Fixing charges L.S 5.00
TOTAL : 80.00
ADD FOR CONTRACTORS PROFIT 10% : 8.00
ADD FOR OVER HEAD CHARGES @5% : 4.00
COST FOR 1.000 Bend 92.00
COST PER Bend 92.00
LABOUR PER Bend 5.75
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 5.00
TOTAL : 5.00
ADD FOR CONTRACTORS PROFIT 10% 0.50
ADD FOR OVER HEAD CHARGES @5% : 0.25
LABOUR FOR 1.000 Bend 5.75
LABOUR PER Bend 5.75
14110000 Providing asbestos cement
corrugated /semi -corrugated sheets
roofing fixed with galvanised iron
J or L hooks bolts and nuts 8 mm
dia G.I.plain bitumun washers
complete excluding the cost of
purlins, rafters and trusses
6 mm thick
MATERIAL :
CARRIAGE :
Sheet
1 KM BY MECH. TRANSPORT 1 tonne 3.08000 73.95 227.77
LABOUR :
Black Smith 1st Class Each 2.34000 186.67 436.81
Carpenter 2nd Class Each 9.34000 186.67 1743.50
Beldar Each 9.34000 116.67 1089.70
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 3300.00
TOTAL : 3300.00
ADD FOR CONTRACTORS PROFIT 10% : 330.00
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR OVER HEAD CHARGES @5% : 165.00
LABOUR FOR 216.140 sq.m. 3795.00
LABOUR PER sq.m. 17.55
14120000 Extra for asbestos cement
corrugated /semi-corrugated
sheet.Roofing with vertical
sheeting or sheeting to a pitch
exceeding 60 Degree
Details of cost for 194.04 sq.m
LABOUR :
Beldar Each 6.00000 116.67 700.02
TOTAL : 700.02
ADD FOR CONTRACTORS PROFIT 10% : 70.00
ADD FOR OVER HEAD CHARGES @5% : 35.00
COST FOR 194.040 Sq.m 805.02
COST PER Sq.m 4.15
LABOUR PER Sq.m 4.15
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 700.02
TOTAL : 700.02
ADD FOR CONTRACTORS PROFIT 10% : 70.00
ADD FOR OVER HEAD CHARGES @5% : 35.00
LABOUR FOR 194.040 Sq.m 805.02
LABOUR PER Sq.m 4.15
14130000 Extra for straight cutting and
wasteinA.C.corrugated/semi/corrugat
ed sheet roofing for making
opening of area exceeding 40 sq.dm
for chimney stacks skylights etc.
MATERIAL :
LABOUR :
Carpenter 1st Class Each 0.12000 211.16 25.34
Beldar Each 0.12000 116.67 14.00
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Total : 258.30
ADD FOR CONTRACTORS PROFIT 10% Except on (-I-) : 3.93
ADD FOR OVER HEAD CHARGES @5% Except on (-I-): 1.96
COST FOR 3.000 Metre 264.19
COST PER Metre 88.05
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 39.33
Labour As per item no : 9.48
TOTAL : 48.81
MATERIAL :
LABOUR :
Carpenter 1st Class Each 1.00000 211.16 211.16
Beldar Each 1.00000 116.67 116.67
Total : 992.29
ADD FOR CONTRACTORS PROFIT 10% Except on (-I-) : 33.13
ADD FOR OVER HEAD CHARGES @5% Except on (-I-): 16.56
COST FOR 9.050 Metres. 1041.98
COST PER Metres. 115.15
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 331.33
Labour As per item no :14110000 28.60 (-a-)
TOTAL : 359.93
LABOUR :
Carpenter 1st Class Each 1.00000 211.16 211.16
Beldar Each 1.00000 116.67 116.67
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 332.83
TOTAL : 332.83
ADD FOR CONTRACTORS PROFIT 10% : 33.28
ADD FOR OVER HEAD CHARGES @5% : 16.64
LABOUR FOR 25.000 Holes 382.75
LABOUR PER Holes 15.30
14130302 Those exceeding 100 sq.cm. but not
exceeding 400 sq.cm in area
Details of cost for 13 holes of (23
cm. diametre)
LABOUR :
Carpenter 1st Class Each 1.00000 211.16 211.16
Beldar Each 1.00000 116.67 116.67
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 332.83
TOTAL : 332.83
ADD FOR CONTRACTORS PROFIT 10% : 33.28
ADD FOR OVER HEAD CHARGES @5% : 16.64
LABOUR FOR 13.000 Holes 382.75
LABOUR PER Holes 29.45
14130303 Those exceeding 400 sq.cm. in area
Details of cost for 9 holes of
(30 cm.diametre)
LABOUR :
Carpenter 1st Class Each 1.00000 211.16 211.16
Beldar Each 1.00000 116.67 116.67
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 332.83
TOTAL : 332.83
ADD FOR CONTRACTORS PROFIT 10% : 33.28
ADD FOR OVER HEAD CHARGES @5% : 16.64
LABOUR FOR 9.000 Holes 382.75
LABOUR PER Holes 42.50
14140000 Providing and fixing ridges and
hips in Asbestos cement sheets
roofing with G.I.J or L hooks,
bolts and nuts 8 mm diametres
G.I.plain and bitumen washers
complete
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
LABOUR :
Black Smith 1st Class Each 0.14000 186.67 26.13
Carpenter 2nd Class Each 0.55000 186.67 102.67
Beldar Each 1.64000 116.67 191.34
SUNDRIES : 5.00
TOTAL : 3375.13
ADD FOR CONTRACTORS PROFIT 10% 337.51
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 325.13
TOTAL : 325.13
ADD FOR CONTRACTORS PROFIT 10% : 32.51
ADD FOR OVER HEAD CHARGES @5% : 16.25
LABOUR FOR 20.200 metre 373.89
LABOUR PER metre 18.50
14140200 Serrated or plain wing adjustable
ridges.
Detail of cost for Consider a shed
of 20x10 m (External dimension at
plinth)
Length of ridge 20.20 Metres.
MATERIAL :
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Total : 5971.39
ADD FOR CONTRACTORS PROFIT 10% Except on (-I-) : 209.00
ADD FOR OVER HEAD CHARGES @5% Except on (-I-): 104.50
COST FOR 20.200 metre 6284.89
COST PER metre 311.15
LABOUR RATE :
Labour As per item no :14140100 373.89
TOTAL : 373.89
LABOUR FOR 20.200 metre 373.89
LABOUR PER metre 18.50
14140300 Close fitting adjustable ridges
MATERIAL :
LABOUR :
Black Smith 1st Class Each 0.14000 186.67 26.13
Carpenter 2nd Class Each 0.55000 186.67 102.67
Beldar Each 1.64000 116.67 191.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 325.13
TOTAL : 325.13
ADD FOR CONTRACTORS PROFIT 10% : 32.51
ADD FOR OVER HEAD CHARGES @5% : 16.25
LABOUR FOR 20.200 metre 373.89
LABOUR PER metre 18.50
MATERIAL :
LABOUR :
Black Smith 1st Class Each 0.14000 186.67 26.13
Carpenter 2nd Class Each 0.55000 186.67 102.67
Beldar Each 1.64000 116.67 191.34
SUNDRIES : 5.00
TOTAL : 5470.13
ADD FOR CONTRACTORS PROFIT 10% 547.01
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 325.13
TOTAL : 325.13
ADD FOR CONTRACTORS PROFIT 10% : 32.51
ADD FOR OVER HEAD CHARGES @5% : 16.25
LABOUR FOR 20.200 metre 373.89
LABOUR PER metre 18.50
MATERIAL :
LABOUR :
Black Smith 1st Class Each 0.14000 186.67 26.13
Carpenter 2nd Class Each 0.55000 186.67 102.67
Beldar Each 1.64000 116.67 191.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 325.13
TOTAL : 325.13
ADD FOR CONTRACTORS PROFIT 10% : 32.51
ADD FOR OVER HEAD CHARGES @5% : 16.25
LABOUR FOR 20.200 metre 373.89
LABOUR PER metre 18.50
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
14150000 Filling cement concrete 1:2:4: (1
cement : 2 sand : 4 garded stone
aggregate 12.5 mm nominal size in
gaps of A.C.sheet corrugations and
wings of ridges
MATERIAL :
Total : 206.20
COST FOR 10.000 metre 206.20
COST PER metre 20.60
LABOUR RATE :
Labour As per item no :09200300 42.62
TOTAL : 42.62
LABOUR FOR 10.000 metre 42.62
LABOUR PER metre 4.25
14160000 Providing and fixing asbestos
cement roofing acessories with
galvanized iron j or l hooks, bolts
and nuts and/or G.I.seam bolts and
nuts.
G.I.plain and bitumen washers etc
complete.
MATERIAL :
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 163.98
TOTAL : 163.98
ADD FOR CONTRACTORS PROFIT 10% : 16.39
ADD FOR OVER HEAD CHARGES @5% : 8.20
LABOUR FOR 20.200 metre 188.57
LABOUR PER metre 9.35
14160200 Eaves filler pieces
MATERIAL :
LABOUR :
Black Smith 1st Class Each 0.07000 186.67 13.07
Carpenter 2nd Class Each 0.28000 186.67 52.27
Beldar Each 0.82000 116.67 95.67
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 163.98
TOTAL : 163.98
ADD FOR CONTRACTORS PROFIT 10% : 16.39
ADD FOR OVER HEAD CHARGES @5% : 8.20
LABOUR FOR 20.200 metres 188.57
LABOUR PER metres 9.35
14160300 North ligth and ventilator curves
MATERIAL :
LABOUR :
Black Smith 1st Class Each 1.10000 186.67 205.34
Carpenter 2nd Class Each 0.30000 186.67 56.00
Beldar Each 1.00000 116.67 116.67
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 383.01
TOTAL : 383.01
ADD FOR CONTRACTORS PROFIT 10% : 38.30
ADD FOR OVER HEAD CHARGES @5% : 19.15
LABOUR FOR 20.200 metre 440.46
LABOUR PER metre 21.80
14160400 Barge boards.
MATERIAL :
G.I. washers for seam bolts. 100 nos 10.00000 50.00 5.00
LABOUR :
Black Smith 1st Class Each 0.04000 186.67 7.47
Carpenter 2nd Class Each 0.06000 186.67 11.20
Beldar Each 0.40000 116.67 46.67
MATERIAL :
LABOUR :
Black Smith 1st Class Each 0.50000 186.67 9.33
Carpenter 2nd Class Each 0.15000 186.67 28.00
Beldar Each 0.50000 116.67 58.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 97.66
TOTAL : 97.66
ADD FOR CONTRACTORS PROFIT 10% : 9.76
ADD FOR OVER HEAD CHARGES @5% : 4.88
LABOUR FOR 8.840 metres 112.30
LABOUR PER metres 12.70
14160600 Ridge finala.
MATERIAL :
LABOUR :
Sundries,Carriage,fixing L.S. 10.00
TOTAL : 130.00
ADD FOR CONTRACTORS PROFIT 10% : 13.00
ADD FOR OVER HEAD CHARGES @5% : 6.50
COST FOR 1.000 Pair 149.50
COST PER Pair 149.50
LABOUR PER Pair 11.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 10.00
TOTAL : 10.00
ADD FOR CONTRACTORS PROFIT 10% : 1.00
ADD FOR OVER HEAD CHARGES @5% : 0.50
LABOUR FOR 1.000 Pair 11.50
LABOUR PER Pair 11.50
14160700 Cowl type ventilator.
MATERIAL :
LABOUR :
Sundries,carriage,fixing L.S. 10.00
TOTAL : 280.00
ADD FOR CONTRACTORS PROFIT 10% : 28.00
ADD FOR OVER HEAD CHARGES @5% : 14.00
COST FOR 1.000 No 322.00
COST PER No 322.00
LABOUR PER No 11.50
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 10.00
TOTAL : 10.00
ADD FOR CONTRACTORS PROFIT 10% : 1.00
ADD FOR OVER HEAD CHARGES @5% : 0.50
LABOUR FOR 1.000 No 11.50
LABOUR PER No 11.50
14160800 Curved barge boards for north light
curves
MATERIAL :
Curved barge board for north light Each 2.00000 200.00 400.00
CARRIAGE :
Carriageofseam,bolts,nuts L.S 5.00
LABOUR :
Black Smith 1st Class Each 0.05000 186.67 9.33
Carpenter 2nd Class Each 0.25000 186.67 46.67
Beldar Each 0.25000 116.67 29.17
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 87.15
TOTAL : 87.15
ADD FOR CONTRACTORS PROFIT 10% : 8.71
ADD FOR OVER HEAD CHARGES @5% : 4.35
LABOUR FOR 2.000 Nos 100.22
LABOUR PER Nos 50.10
14160900 Roof light
MATERIAL :
LABOUR :
Fixing, sundries charges L.S. 10.00
TOTAL : 1415.00
ADD FOR CONTRACTORS PROFIT 10% : 141.50
ADD FOR OVER HEAD CHARGES @5% : 70.75
COST FOR 1.000 Roof light 1627.25
COST PER Roof light 1627.25
LABOUR PER Roof light 11.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 10.00
TOTAL : 10.00
ADD FOR CONTRACTORS PROFIT 10% : 1.00
ADD FOR OVER HEAD CHARGES @5% : 0.50
LABOUR FOR 1.000 Roof 11.50
LABOUR PER Roof 11.50
14161000 Expansion joints for ridges
Details of cost for 2 expansion
joints (pair)
MATERIAL :
LABOUR :
Black Smith 1st Class Each 0.05000 186.67 9.33
Carpenter 2nd Class Each 0.12000 186.67 22.40
Beldar Each 0.12000 116.67 14.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 47.73
TOTAL : 47.73
ADD FOR CONTRACTORS PROFIT 10% : 4.77
ADD FOR OVER HEAD CHARGES @5% : 2.38
LABOUR FOR 2.000 Pair 54.88
LABOUR PER Pair 27.45
14161100 Expension joints for north light
curves
MATERIAL :
CARRIAGE :
Carriageofexpansion joint L.S. 27.00
LABOUR :
Black Smith 1st Class Each 0.05000 186.67 9.34
Carpenter 2nd Class Each 0.20000 186.67 37.33
Beldar Each 0.20000 116.67 23.33
TOTAL : 237.00
ADD FOR CONTRACTORS PROFIT 10% 23.70
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 70.00
TOTAL : 70.00
ADD FOR CONTRACTORS PROFIT 10% : 7.00
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR OVER HEAD CHARGES @5% : 3.50
LABOUR FOR 1.000 Joint 80.50
LABOUR PER Joint 80.50
14161200 S.Type louvers
MATERIAL :
G.I. plain washers 6x6 m =36 nos. 100 nos 36.00000 50.00 18.00
CARRIAGE :
Carriage of S typeLouvers L.S 5.00
Carriage of Bolts/Nuts L.S 2.00
LABOUR :
Carpenter 1st Class Each 1.00000 211.16 211.16
Black Smith 1st Class Each 0.12000 186.67 22.40
Beldar Each 1.00000 116.67 116.67
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 360.23
TOTAL : 360.23
ADD FOR CONTRACTORS PROFIT 10% : 36.02
ADD FOR OVER HEAD CHARGES @5% : 18.01
LABOUR FOR 8.740 metre 414.26
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR PER metre 47.40
14170000 Providing and fixing asbestos
cement socketed half round eaves
gutters with bolts nuts bitumen
washers etc and flat iron brackets
40x3 mm size including asbestos
rope and plastic compound in joints
complete.
MATERIAL :
G.I.plain washer 2x11 =22 nos. 100 nos 22.00000 50.00 11.00
Bitumen washer 2x11 =22 nos. 100 nos 22.00000 25.00 5.50
LABOUR :
Black Smith 1st Class Each 0.15000 186.67 28.00
Carpenter 1st Class Each 1.33000 211.16 280.84
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Beldar Each 2.00000 116.67 233.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 557.18
TOTAL : 557.18
ADD FOR CONTRACTORS PROFIT 10% : 55.72
ADD FOR OVER HEAD CHARGES @5% : 27.86
LABOUR FOR 20.000 metre 640.76
LABOUR PER metre 32.00
14170200 225 mm nominal size
Details of cost for 20.00 metres
MATERIAL :
G.I. plain washers 6x11 =66 nos. 100 nos 66.00000 50.00 33.00
Bitumen washer 6x11 =66 nos. 100 nos 66.00000 25.00 16.50
LABOUR :
Carpenter 1st Class Each 1.33000 211.16 280.84
Black Smith 1st Class Each 0.15000 186.67 28.00
Beldar Each 2.00000 116.67 233.34
LABOUR RATE:
ACTUAL LABOUR+SUNDRIES 557.18
TOTAL 557.18
ADD FOR CONTRACTORS PROFIT 10% : 55.72
ADD FOR OVER HEAD CHARGES @ 5% 27.86
LABOUR FOR 20.000 metres 640.76
LABOUR PER metres 32.00
MATERIAL :
G.I.plain washers 6x11 =66 nos. 100 nos 66.00000 50.00 33.00
Bitumen washer 6x11 =66 nos. 100 nos 66.00000 25.00 16.50
LABOUR :
Carpenter 1st Class Each 1.33000 211.16 280.84
Black Smith 1st Class Each 0.15000 186.67 28.00
Beldar Each 2.00000 116.67 233.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 557.18
TOTAL : 557.18
ADD FOR CONTRACTORS PROFIT 10% : 55.72
ADD FOR OVER HEAD CHARGES @5% : 27.86
LABOUR FOR 20.000 metre 640.76
LABOUR PER metre 32.00
14180000 Providing and fixing asbestos
cement plain ended eaves or boundry
wall gutter with bolts nuts bitumen
washers etc and flat iron brackets
40x3 mm size including asbestos
rope and plastic roofing compound
in joints complete.
MATERIAL :
G.I.plain washers 11x16 =176 nos. 100 nos 176.00000 50.00 88.00
LABOUR :
Black Smith 1st Class Each 0.15000 186.67 28.00
Carpenter 1st Class Each 2.33000 211.16 492.00
Beldar Each 1.85000 116.67 215.84
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 775.84
TOTAL : 775.84
ADD FOR CONTRACTORS PROFIT 10% : 77.58
ADD FOR OVER HEAD CHARGES @5% : 38.79
LABOUR FOR 20.000 metre 892.21
LABOUR PER metre 44.60
14180200 300x150x225 mm nominal size
G.I. plain washers 11x2x8 =176Nos. 100 nos 176.00000 50.00 88.00
Bitumen washers 11x2x8 =176 nos. 100 nos 176.00000 25.00 44.00
LABOUR :
Black Smith 1st Class Each 0.15000 186.67 28.00
Carpenter 1st Class Each 2.33000 211.16 492.00
Beldar Each 1.85000 116.67 215.84
SUNDRIES : 10.00
TOTAL : 10429.16
ADD FOR CONTRACTORS PROFIT 10% 1042.92
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 775.84
TOTAL : 775.84
ADD FOR CONTRACTORS PROFIT 10% : 77.58
ADD FOR OVER HEAD CHARGES @5% : 38.79
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR FOR 20.000 metre 892.21
LABOUR PER metre 44.60
14180300 450x150x300 mm nominal size
MATERIAL :
Bitumen washers.
11x2x8 = 176 Nos. 100 nos 176.00000 25.00 44.00
LABOUR :
Black Smith 1st Class Each 0.15000 186.67 28.00
Carpenter 1st Class Each 2.33000 211.16 492.00
Beldar Each 1.85000 116.67 215.84
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 775.84
TOTAL : 775.84
ADD FOR CONTRACTORS PROFIT 10% : 77.58
ADD FOR OVER HEAD CHARGES @5% : 38.79
LABOUR FOR 20.000 metre 892.21
LABOUR PER metre 44.60
14180400 300x150x250 mm nominal size
MATERIAL :
G.I.plain washers 11x20 =220 nos. 100 nos 220.00000 50.00 110.00
Bitumen washer 11x20 =220 nos 100 nos 220.00000 25.00 55.00
LABOUR :
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Black Smith 1st Class Each 0.15000 186.67 28.00
Carpenter 1st Class Each 2.33000 211.16 492.00
Beldar Each 1.85000 116.67 215.84
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 775.84
TOTAL : 775.84
ADD FOR CONTRACTORS PROFIT 10% : 77.58
ADD FOR OVER HEAD CHARGES @5% : 38.79
LABOUR FOR 20.000 metre 892.18
LABOUR PER metre 44.60
14190000 Providing and fixing asbestos
cement plain ended valley gutters
with bolts nuts bitumen washers etc
and flat iron brackets 40x3 mm size
including asbestos rope amnd
plastic roofing compound in joints
complete
MATERIAL :
LABOUR :
Black Smith 1st Class Each 0.15000 186.67 28.00
Carpenter 1st Class Each 2.33000 211.16 492.00
Beldar Each 1.85000 116.67 215.84
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 775.84
TOTAL : 775.84
ADD FOR CONTRACTORS PROFIT 10% : 77.58
ADD FOR OVER HEAD CHARGES @5% : 38.79
LABOUR FOR 20.000 metre 892.18
LABOUR PER metre 44.60
MATERIAL :
Bitumen washers.
11x2x8 =176 Nos. 100 nos 176.00000 25.00 44.00
LABOUR :
Black Smith 1st Class Each 0.1500 186.67 28.00
Carpenter 1st Class Each 2.3300 211.16 492.00
Beldar Each 1.8500 116.67 215.84
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 775.84
TOTAL : 775.84
ADD FOR CONTRACTORS PROFIT 10% : 77.58
ADD FOR OVER HEAD CHARGES @5% : 38.79
LABOUR FOR 20.000 metre 892.18
LABOUR PER metre 44.60
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
14190300 600x150x225 mm nominal size
Details of cost for 20 metres
MATERIAL :
Bitumen washers.
11x2x8 = 176 Nos. 100 nos 176.0000 25.00 44.00
LABOUR :
Black Smith 1st Class Each 0.1500 186.67 28.00
Carpenter 1st Class Each 2.3300 211.16 492.00
Beldar Each 1.8500 116.67 215.84
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 775.84
TOTAL : 775.84
ADD FOR CONTRACTORS PROFIT 10% : 77.58
ADD FOR OVER HEAD CHARGES @5% : 38.79
LABOUR FOR 20.000 metres 892.18
LABOUR PER metres 44.60
14190400 900x200x225 mm nominal size
Details of cost for 20 metres
MATERIAL :
Bitumen washers.
11 x 24 = 264 Nos. 100 nos 264.0000 25.00 66.00
LABOUR :
Black Smith 1st Class Each 0.1500 186.67 28.00
Carpenter 1st Class Each 3.0000 211.16 633.48
Beldar Each 3.0000 1116.67 350.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1051.48
TOTAL : 1051.48
ADD FOR CONTRACTORS PROFIT 10% : 105.14
ADD FOR OVER HEAD CHARGES @5% : 52.57
LABOUR FOR 20.000 metres 1209.20
LABOUR PER metres 60.45
14200000 Extra for providing flat iron
brackets 50x6 mm size instead of
40x3 mm size with necessary bolts
nuts and washers etc for fixing
asbestos cement gutters with
purlins
Details of cost for 20 metres
MATERIAL :
TOTAL : 190.00
ADD FOR CONTRACTORS PROFIT 10% : 19.00
ADD FOR OVER HEAD CHARGES @5% : 19.00
COST FOR 20.000 metre 9.50
COST PER metre 218.50
LABOUR PER metre 10.90
LABOUR :
Labour for fixing L.S. 5.00
TOTAL : 96.50
ADD FOR CONTRACTORS PROFIT 10% 9.65
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 5.00
TOTAL : 3.25 5.00
ADD FOR CONTRACTORS PROFIT 10% : 0.50
ADD FOR OVER HEAD CHARGES @5% : 0.25
LABOUR FOR 1.000 No 5.75
LABOUR PER No 5.75
14210200 250 mm nominal size with 75 mm dia
or 100 mm or 150 mm dia drain
outlet
Details of cost for one drop end
MATERIAL :
LABOUR :
Labour for fixing L.S. 5.00
TOTAL : 131.50
ADD FOR CONTRACTORS PROFIT 10% 13.15
ADD FOR OVER HEAD CHARGES @5% 6.57
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 5.00
TOTAL : 5.00
ADD FOR CONTRACTORS PROFIT 10% : 0.50
ADD FOR OVER HEAD CHARGES @5% : 0.25
LABOUR FOR 1.000 No 5.75
LABOUR PER No 5.75
14210300 300 mm nominal size with 75 or 100
or 150 mm dia drain outlet
Details of cost for 1 A.C.drop end
MATERIAL :
LABOUR :
labour for fixing L.S. 5.00
TOTAL : 146.50
ADD FOR CONTRACTORS PROFIT 10% 14.65
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 5.00
TOTAL : 5.00
ADD FOR CONTRACTORS PROFIT 10% : 0.50
ADD FOR OVER HEAD CHARGES @5% : 0.25
LABOUR FOR 1.000 No 5.75
LABOUR PER No 5.75
14220000 Extra for providing and fixing
asbestos cement drop end for plain
ended eaves or boundary wall
gutters
MATERIAL :
LABOUR :
Labour for fixing L.S. 5.00
TOTAL : 166.50
ADD FOR CONTRACTORS PROFIT 10% 16.65
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 5.00
TOTAL : 5.00
ADD FOR CONTRACTORS PROFIT 10% : 0.50
ADD FOR OVER HEAD CHARGES @5% : 0.25
LABOUR FOR 1.000 No 5.75
LABOUR PER No 5.75
14220200 300x150x225 mm nominal size with 75
or 100 or 150mm dia outlet
Details of cost for one drop end
MATERIAL :
LABOUR :
Labour for fixing L.S. 5.00
TOTAL : 306.50
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR CONTRACTORS PROFIT 10% 30.65
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 5.00
TOTAL : 5.00
ADD FOR CONTRACTORS PROFIT 10% : 0.50
ADD FOR OVER HEAD CHARGES @5% : 0.25
LABOUR FOR 1.000 No 5.75
LABOUR PER No 5.75
14220300 450x150x300 mm nominal size with 75/100/150mm dia outlet
Details of cost for one drop end
MATERIAL :
TOTAL : 326.50
ADD FOR CONTRACTORS PROFIT 10% 32.65
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 5.00
TOTAL : 5.00
ADD FOR CONTRACTORS PROFIT 10% : 0.50
ADD FOR OVER HEAD CHARGES @5% : 0.25
LABOUR FOR 1.000 No 5.75
LABOUR PER No 5.75
14220400 500x150x250 mm nominal size with 75
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
or 100 or 150mm dia ourlet
Details of cost for one drop end
MATERIAL :
LABOUR :
Labour for fixing L.S. 5.00
TOTAL : 346.50
ADD FOR CONTRACTORS PROFIT 10% 34.65
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 5.00
TOTAL : 5.00
ADD FOR CONTRACTORS PROFIT 10% : 0.50
ADD FOR OVER HEAD CHARGES @5% : 0.25
LABOUR FOR 1.000 No 5.75
LABOUR PER No 5.75
14230000 Extra for providing and fixing
asbestos cement drop ends for plain
ended valley gutters
MATERIAL :
LABOUR :
Labour for fixing L.S 5.00
TOTAL : 231.50
ADD FOR CONTRACTORS PROFIT 10% 23.15
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 5.00
TOTAL : 5.00
ADD FOR CONTRACTORS PROFIT 10% : 0.50
ADD FOR OVER HEAD CHARGES @5% : 0.25
LABOUR FOR 1.000 No 5.75
LABOUR PER No 5.75
14230200 450x125x150 mm nominal size with 75
or 100 or150 mm dia outlet
Details of cost for one A.C. drop
end
MATERIAL :
LABOUR :
Labour for fixing L.S. 5.00
TOTAL : 281.50
ADD FOR CONTRACTORS PROFIT 10% 28.15
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 5.00
TOTAL : 5.00
ADD FOR CONTRACTORS PROFIT 10% : 0.50
ADD FOR OVER HEAD CHARGES @5% : 0.25
LABOUR FOR 1.000 No 5.75
LABOUR PER No 5.75
14230300 600x150x225x mm nominal size with
75 opr 100 or 150 mm dia outlet
Details of cost for one drop end
MATERIAL :
LABOUR :
Labour for fixing L.S 5.00
TOTAL : 366.50
ADD FOR CONTRACTORS PROFIT 10% 36.65
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 5.00
TOTAL : 5.00
ADD FOR CONTRACTORS PROFIT 10% : 0.50
ADD FOR OVER HEAD CHARGES @5% : 0.25
LABOUR FOR 1.000 No 5.75
LABOUR PER No 5.75
14230400 900x200x225 mm nominal size with 75
or 100 or 150 mm dia outlet Details
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
of cost for one drop end
MATERIAL :
A.c. drop end for plain ended Each 1.0000 370.00 370.00
valley gutters
CARRIAGE :
Carriage of material L.S. 1.50
LABOUR :
Labour for fixing L.S. 5.00
TOTAL : 376.50
ADD FOR CONTRACTORS PROFIT 10% 37.65
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 5.00
TOTAL : 5.00
ADD FOR CONTRACTORS PROFIT 10% : 0.50
ADD FOR OVER HEAD CHARGES @5% : 0.25
LABOUR FOR 1.000 No 5.75
LABOUR PER No
14240000 Extra for providing and fixing
asbestos cement stop end for
gutters
MATERIAL :
LABOUR :
Labour for fixing L.S. 2.00
TOTAL : 38.50
ADD FOR CONTRACTORS PROFIT 10% 3.85
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 2.00
TOTAL : 2.00
ADD FOR CONTRACTORS PROFIT 10% : 0.20
ADD FOR OVER HEAD CHARGES @5% : 0.10
LABOUR FOR 1.000 No 2.30
LABOUR PER No 2.30
14240102 For socketed half round eaves
gutters 250 mm nominal size
Details of cost for one stop end
MATERIAL :
LABOUR :
Labour for fixing L.S 2.00
TOTAL : 43.50
ADD FOR CONTRACTORS PROFIT 10% 4.35
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 2.00
TOTAL : 2.00
ADD FOR CONTRACTORS PROFIT 10% : 0.20
ADD FOR OVER HEAD CHARGES @5% : 0.10
LABOUR FOR 1.000 No 2.30
LABOUR PER No 2.30
MATERIAL :
LABOUR :
labour for fixing L.S 2.00
TOTAL : 73.50
ADD FOR CONTRACTORS PROFIT 10% 7.35
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 2.00
TOTAL : 1 2.00
ADD FOR CONTRACTORS PROFIT 10% : 0.30
ADD FOR OVER HEAD CHARGES @5% : 0.15
LABOUR FOR 1.000 No 2.30
LABOUR PER No 2.30
14240200 Extra for providing and fixing
asbestos cement stop ends for
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
gutters
MATERIAL :
LABOUR :
Labour for fixing L.S. 2.50
TOTAL : 94.25
ADD FOR CONTRACTORS PROFIT 10% 9.42
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 2.50
TOTAL : 2.50
ADD FOR CONTRACTORS PROFIT 10% : 0.25
ADD FOR OVER HEAD CHARGES @5% : 0.12
LABOUR FOR 1.000 No 2.87
LABOUR PER No 2.90
14240202 300x150x225 mm nominal size
Details of cost for one stop end
MATERIAL :
LABOUR :
labour for fixing L.S 2.50
TOTAL : 124.00
ADD FOR CONTRACTORS PROFIT 10% 12.40
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 2.50
TOTAL : 2.50
ADD FOR CONTRACTORS PROFIT 10% : 0.25
ADD FOR OVER HEAD CHARGES @5% : 0.12
LABOUR FOR 1.000 No 2.87
LABOUR PER No 2.90
14240203 450x150x300 mm nominal size
Details of cost for one stop end
MATERIAL :
LABOUR :
labour for fixing L.S 2.00
TOTAL : 144.00
ADD FOR CONTRACTORS PROFIT 10% 14.40
MATERIAL :
LABOUR :
labour for fixing L.S. 2.50
TOTAL : 154.00
ADD FOR CONTRACTORS PROFIT 10% 15.40
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 2.50
TOTAL : 2.50
ADD FOR CONTRACTORS PROFIT 10% : 0.25
ADD FOR OVER HEAD CHARGES @5% : 0.12
LABOUR FOR 1.000 No 2.87
LABOUR PER No 2.90
14240300 Extra for providing and fixing
asbestos cement
Stop ends for gutters for plain
ended valley gutters
MATERIAL :
LABOUR :
Labour for fixing L.S. 2.50
TOTAL : 254.00
ADD FOR CONTRACTORS PROFIT 10% 25.40
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 2.50
TOTAL : 2.50
ADD FOR CONTRACTORS PROFIT 10% : 0.25
ADD FOR OVER HEAD CHARGES @5% : 0.12
LABOUR FOR 1.000 No 2.87
LABOUR PER No 2.90
14240302 450x125x150 mm nominal size
details of cost for one stop end
MATERIAL :
LABOUR :
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
labour for fixing L.S 2.50
TOTAL : 124.00
ADD FOR CONTRACTORS PROFIT 10% 12.40
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 2.50
TOTAL : 2.50
ADD FOR CONTRACTORS PROFIT 10% : 0.25
ADD FOR OVER HEAD CHARGES @5% : 0.37
LABOUR FOR 1.000 No 2.87
LABOUR PER No 2.90
MATERIAL :
LABOUR :
Labour for fixing L.S. 2.50
TOTAL : 144.00
ADD FOR CONTRACTORS PROFIT 10% 14.40
MATERIAL :
LABOUR :
Labour for fixing L.S 2.50
TOTAL : 219.00
ADD FOR CONTRACTORS PROFIT 10% 21.90
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 2.50
TOTAL : 2.50
ADD FOR CONTRACTORS PROFIT 10% : 0.25
ADD FOR OVER HEAD CHARGES @5% : 0.12
LABOUR FOR 1.000 No 2.87
LABOUR PER No 2.90
14250000 Extra for providing and fixing
asbestos cement nozzles for gutters
MATERIAL :
LABOUR :
Labour for fixing L.S. 6.00
TOTAL : 107.50
ADD FOR CONTRACTORS PROFIT 10% 10.75
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.30
LABOUR FOR 1.000 No 6.90
LABOUR PER No 6.90
14250102 250 mm nominal size
Details of cost for one nozzle
MATERIAL :
LABOUR :
Labour for fixing L.S. 6.00
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 147.50
ADD FOR CONTRACTORS PROFIT 10% 14.75
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.30
LABOUR FOR 1.000 No 6.90
LABOUR PER No 6.90
14250103 300 mm nominal size
Details of cost for one nozzle
MATERIAL :
LABOUR :
Labour for fixing L.S. 6.00
TOTAL : 197.50
ADD FOR CONTRACTORS PROFIT 10% 19.75
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.30
LABOUR FOR 1.000 No 6.90
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR PER No 6.90
14250200 Nozzle for Plain ended eaves or boundary wall
gutters
MATERIAL :
LABOUR :
labour for fixing L.S. 6.00
TOTAL : 137.50
ADD FOR CONTRACTORS PROFIT 10% 13.75
ADD FOR OVER HEAD CHARGES @5% 6.87
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.30
LABOUR FOR 1.000 No 6.90
LABOUR PER No 6.90
14250202 300x150x225 mm nominal size
Details of cost forone nozzle
MATERIAL :
LABOUR :
Labour for fixing L.S 6.00
TOTAL : 247.50
ADD FOR CONTRACTORS PROFIT 10% 24.75
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.30
LABOUR FOR 1.000 No 6.90
LABOUR PER No 6.90
14250203 450x150x200 mm nominal size
Details of cost for one nozzle
MATERIAL :
LABOUR :
Labour for fixing L.S 6.00
TOTAL : 257.50
ADD FOR CONTRACTORS PROFIT 10% 25.75
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.30
LABOUR FOR 1.000 No 6.90
LABOUR PER No 6.90
14250204 500x150x250 mm nominal size
Details of cost for one nozzle
MATERIAL :
Labour :
Labour for fixing L.S 6.00
TOTAL : 287.50
ADD FOR CONTRACTORS PROFIT 10% 28.75
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.30
LABOUR FOR 1.000 No 6.90
LABOUR PER No 6.90
14250300 Nozzle for Plain ended valley gutters
MATERIAL :
LABOUR :
Labour for fixing L.S 6.00
TOTAL : 227.50
ADD FOR CONTRACTORS PROFIT 10% 22.75
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.30
LABOUR FOR 1.000 No 6.90
LABOUR PER No 6.90
MATERIAL :
LABOUR :
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
labour for fixing L.S 1.50
TOTAL : 277.50
ADD FOR CONTRACTORS PROFIT 10% 27.75
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.30
LABOUR FOR 1.000 No 6.90
LABOUR PER No 6.90
14250303 900x200x225 mmnominal size
Details of cost for one nozzle
MATERIAL :
LABOUR :
Labour for fixing L.S 6.00
TOTAL : 347.50
ADD FOR CONTRACTORS PROFIT 10% 34.75
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR OVER HEAD CHARGES @5% : 0.30
LABOUR FOR 1.000 No 6.90
LABOUR PER No 6.90
14260000 Extra providing and fixing asbestos
cement angles for
MATERIAL :
LABOUR :
Labour for fixing L.S 6.00
TOTAL : 127.50
ADD FOR CONTRACTORS PROFIT 10% 12.75
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.60
LABOUR FOR 1.000 No 6.90
LABOUR PER No 6.90
14260102 250 mm nominal size
Details of cost for one angle
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
LABOUR :
Labour for fixing L.S 6.00
TOTAL : 177.50
ADD FOR CONTRACTORS PROFIT 10% 17.75
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.30
LABOUR FOR 1.000 No 6.90
LABOUR PER No 6.90
14260103 300 mm nominal size
Details of cost for one angle
MATERIAL :
CARRIAGE :
Carriage of Material L.S. 1.50
LABOUR :
Labour for fixing L.S 6.00
TOTAL : 307.50
ADD FOR CONTRACTORS PROFIT 10% 30.75
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR OVER HEAD CHARGES @5% 15.37
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.30
LABOUR FOR 1.000 No 6.90
LABOUR PER No 6.90
14260200 Plain ended eaves for boundary wall
gutters
MATERIAL :
LABOUR :
Labour for fixing L.S 6.00
TOTAL : 187.50
ADD FOR CONTRACTORS PROFIT 10% 18.75
ADD FOR OVER HEAD CHARGES @5% 9.37
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR OVER HEAD CHARGES @5% : 0.30
LABOUR FOR 1.000 No 6.90
LABOUR PER No 6.90
14260202 300x150x225 mm nominal size
Details of cost for one angle
MATERIAL :
LABOUR :
Labour for fixing L.S 6.00
TOTAL : 307.50
ADD FOR CONTRACTORS PROFIT 10% 30.75
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.30
LABOUR FOR 1.000 No 6.90
LABOUR PER No 6.90
14260203 450x150x300 mm nominal size
Details of cost for one angle
MATERIAL :
LABOUR :
Labour for fixing L.S 6.00
TOTAL : 507.50
ADD FOR CONTRACTORS PROFIT 10% 50.75
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.30
LABOUR FOR 1.000 No 6.90
LABOUR PER No 6.90
14260204 500x150x250 mm nominal size
Details of cost for one angle
MATERIAL :
LABOUR :
Labour for fixing L.S 6.00
TOTAL : 557.50
ADD FOR CONTRACTORS PROFIT 10% 55.75
LABOUR RATE :
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.30
LABOUR FOR 1.000 No 6.90
LABOUR PER No 6.90
14270000 Slate roofing with 7.5 cm.
Single lap single layer fixed on
wooden batten(wood work to be paid
for separately)
MATERIAL :
CARRIAGE :
Slates.
1 KM BY MECH. TRANSPORT 1000 nos 259.0000 38.70 9.45
LABOUR :
Mason 2nd Class Each 1.6100 158.67 255.46
Beldar Each 5.3800 116.67 627.68
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 923.13
Labour for lime mortar1:3 10.74
TOTAL : 933.87
WATER CHARGES @ 1.5% : 45.08
TOTAL : 978.95
ADD FOR CONTRACTORS PROFIT 10% : 97.90
ADD FOR OVER HEAD CHARGES @5% : 48.95
LABOUR FOR 10.000 Sq.m 1125.80
LABOUR PER Sq.m 112.60
14270200 With slate 50x25 cm size
Details of cost for 10 sq.m.
MATERIAL :
CARRIAGE :
Slates.
1 KM BY MECH. TRANSPORT 1000 nos 141.0000 38.40 5.41
LABOUR :
Mason 2nd Class Each 1.6100 158.67 255.46
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Beldar Each 5.3800 116.67 627.68
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 923.13
Labour for lime mortar1:3 10.74
TOTAL : 933.87
WATER CHARGES @ 1.5% : 36.04
TOTAL : 969.91
ADD FOR CONTRACTORS PROFIT 10% : 96.99
ADD FOR OVER HEAD CHARGES @5% : 48.50
LABOUR FOR 10.000 sqm. 1115.40
LABOUR PER sqm. 111.55
14270300 With slates 60x30 cm size
Details of cost for 10 sqm.
MATERIAL :
CARRIAGE :
Slates.
1 KM BY MECH. TRANSPORT 1000 nos 89.0000 38.40 3.42
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR :
Mason 2nd Class Each 1.6100 158.67 255.46
Beldar Each 5.3800 116.67 628.68
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 923.13
Labour for lime mortar1:3 10.74
TOTAL : 933.87
WATER CHARGES @ 1.5% : 29.29
TOTAL : 963.16
ADD FOR CONTRACTORS PROFIT 10% : 96.31
ADD FOR OVER HEAD CHARGES @5% : 48.15
LABOUR FOR 10.000 sqm. 1107.62
LABOUR PER sqm. 110.75
14280000 Slate roofing with 7.5 cm lap
double layer fixed on wooden
battens (wood work to be paid for
separately)
14280100 40 x 20 cm
Detail of cost for 1 sqm.
Labour Rate :
Rate Double of itemno 14270100 225.20
14280200 50 cmx25 cm
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Detail of cost for 1 sqm.
Labour Rate :
Rate Double of itemno 14270200 225.20
14280300 60 cm x30 cm
Detail of cost for 1 sqm.
Labour Rate :
Rate Double of itemno 14270300 221.50
MATERIAL :
LABOUR RATE :
Labour for Heating lime concrete
and treatment with gur & bilgiri:
Mason 1st class Each 1.0000 211.16 211.16
Beldar Each 6.0000 116.67 700.02
Bhishti Each 0.2000 116.67 23.33
Total : 3419.81
Add for water charges @1.5% Except on (-I-) : 15.14
Total : 3434.95
ADD FOR CONTRACTORS PROFIT 10% Except on (-I-) : 102.46
ADD FOR OVER HEAD CHARGES @5% Except on (-I-): 51.23
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1009.51
Labour As per item no :0906000A 618.15
TOTAL : 1627.66
Add for water charges : 15.14
TOTAL : 1642.80
ADD FOR CONTRACTORS PROFIT 10% EXCEPT ON (-a-): 102.46
ADD FOR OVER HEAD CHARGES @5% EXCEPT ON (-a-): 51.23
LABOUR FOR 10.000 sqm. 1796.49
LABOUR PER sqm. 179.65
14300000 Lime concrete terracing on roofs
average thickness 10 cm laid to
fall with 25 mm nominal size
stone/brick aggregate and 50& lime
concrete 1:2 (1 lime purry :2
surkhi) rammed and finished with
gur and beligiri treeatment
complete and coverred with flat
brick -tiles grouted with cement
mortar 1:3 (1 cement: 3 sand) over
12 mm layer of cement mortar 1:3
(1cement : 3 sand) and finished
neat
Details of cost for 10 sqm.
MATERIAL :
CARRIAGE :
Bricks tiles.
1 KM BY MECH. TRANSPORT 1000 nos 500.0000 173.35 86.67
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
Extra labour for Laying Tiles :
Mason 1st class Each 0.8100 211.16 171.04
Beldar Each 1.0800 116.67 126.00
Bhishti Each 0.2700 116.67 31.50
Total : 5948.65
Add for water charges @1.5% Except on (-I-) : 35.40
Total : 5987.05
ADD FOR CONTRACTORS PROFIT 10% Except on (-I-) 239.55
ADD FOR OVER HEAD CHARGES @5% Except on (-I-) 119.75
COST FOR 10.000 sqm. 6343.37
COST PER sqm. 634.35
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 328.54
Labour As per item no :14290000 1796.50
Labour for cement mortar 1:3 16.68
TOTAL : 2141.72
Add for water charges : 35.40
TOTAL : 2177.12
ADD FOR CONTRACTORS PROFIT 10% EXCEPT ON (-a-): 38.06
ADD FOR OVER HEAD CHARGES @5% EXCEPT ON (-a-): 19.03
LABOUR FOR 10.000 sqm. 2234.21
LABOUR PER sqm. 223.40
14310000 Extra for every additional 0.5 cm
thickness of lime concrete
terracing
Details of cost for 10 sqm.
MATERIAL :
CARRIAGE :
LABOUR :
Beldar Each 0.0400 116.67 4.66
TOTAL : 92.90
ADD FOR WATER CHARGES @ 1.5% : 1.37
TOTAL : 92.90
ADD FOR CONTRACTORS PROFIT 10% 9.29
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 4.66
Labour for lime surkhi mortar 1:2 8.96
TOTAL : 13.62
WATER CHARGES @ 1.5% : 1.37
TOTAL : 14.99
ADD FOR CONTRACTORS PROFIT 10% : 1.49
ADD FOR OVER HEAD CHARGES @5% : 0.75
LABOUR FOR 10.000 sqm. 17.23
LABOUR PER sqm. 1.70
14320000 Providing and laying brick tiles
over mumty roots grouted with
cement mortar 1:3 (1 cement :3
sand) over a 12 mm layer of cement
mortar 1:3 (1 cement :3 sand ) and
finished neat.
Details of cost for 10 sqm.
MATERIAL :
CARRIAGE :
Bricks tiles.
1 KM BY MECH. TRANSPORT 1000 nos 500.0000 173.35 86.67
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
100 MTRS BY HEAD LOAD 1000 nos 500.0000 63.41 31.70
LABOUR :
Mason 1st class Each 0.8100 211.16 171.04
Beldar Each 1.0800 116.67 126.00
Bhishti Each 0.2700 116.67 31.50
TOTAL : 2544.52
ADD FOR WATER CHARGES @ 1.5% : 38.16
TOTAL : 2582.68
ADD FOR CONTRACTORS PROFIT 10% 258.26
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 328.54
Labour for cement mortar 1:3 24.12
TOTAL : 352.66
WATER CHARGES @ 1.5% : 38.16
TOTAL : 390.82
ADD FOR CONTRACTORS PROFIT 10% : 39.08
ADD FOR OVER HEAD CHARGES @5% : 19.54
LABOUR FOR 10.000 Sq.m 449.44
LABOUR PER Sq.m 44.95
14330000 Providing gola in lime concrete
with 25 mm nominal size stone/
brick aggregate and 50%of lime
mortar 1:2 (1 lime putty :2 surkhi
) underthe drip course and finished
with lime plaster 1:2 (1 lime
putty:2 surkhi ) complete.
Detail of cost for 30.48m. of gola
lime concrete 1:2(1 lime
putty:2surkhi)
Lime
concrete:30.48x.25x75/1000x75/1000
=0.471 Cum.
MATERIAL :
CARRIAGE :
LABOUR :
For preparing/measuring L.S. 25.00
Total : 630.25
Add for water charges @1.5% Except on (-I-) : 6.80
Total : 637.05
ADD FOR CONTRACTORS PROFIT 10% Except on (-I-): 46.06
ADD FOR OVER HEAD CHARGES @5% Except on (-I-): 23.03
COST FOR 30.480 metre 706.14
COST PER metre 23.15
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 40.00
Labour for lime surkhi mortar 1:2 25.07
Labour As per item no :17044020 104.83 (-a-)
TOTAL : 169.90
Add for water charges : 6.80
TOTAL : 176.70
ADD FOR CONTRACTORS PROFIT 10% EXCEPT ON (-a-): 7.18
ADD FOR OVER HEAD CHARGES @5% EXCEPT ON (-a-): 3.59
LABOUR FOR 30.480 metre 187.47
LABOUR PER metre 6.15
14340000 Providing angular fillet 7.5x7.5 cm
cement concrete 1:2:4 (1cement :2
sand :4 graded stone aggregate 20
mm nominal size
Details of cost for 30 metres
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
LABOUR :
Mason 1st class Each 0.1200 211.16 25.34
Total : 343.00
Add for water charges @1.5% Except on (-I-) : 0.75
Total : 343.75
ADD FOR CONTRACTORS PROFIT 10% Except on (-I-) : 5.10
ADD FOR OVER HEAD CHARGES @5% Except on (-I-): 2.55
COST FOR 30.000 metre 351.40
COST PER metre 11.70
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 50.34
Labour As per item no :09200300 59.98
TOTAL : 110.32
Add for water charges : 0.75
TOTAL : 111.07
ADD FOR CONTRACTORS PROFIT 10% EXCEPT ON (-a-): 5.10
ADD FOR OVER HEAD CHARGES @5% EXCEPT ON (-a-): 2.55
LABOUR FOR 30.000 metre 118.72
LABOUR PER metre 3.95
14350000 Providing angular fillet 7.5x7.5cm
lime concrete with 25 mm nominal
size stone/brick aggregate and 50 %
lime mortor (1 lime putty :2
surkhi)
Details of cost for 30 metres.
MATERIAL :
Total : 263.33
COST FOR 30.000 metre 263.33
COST PER metre 8.80
LABOUR RATE :
Labour As per item no :14340000 3.95 (-a-)
Ded. Labour As per item no 09200300-09060000 A (-) 1.75 (-a-)
TOTAL : 2.20
LABOUR PER metre 2.20
MATERIAL :
LABOUR :
Mason 1st class Each 0.2900 211.16 61.24
Beldar Each 0.2900 116.67 33.83
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 100.07
Labour for cement mortar 1:4 2.18
TOTAL : 102.25
WATER CHARGES @ 1.5% : 2.15
TOTAL : 104.40
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
14360100 ADD FOR CONTRACTORS PROFIT 10% : 10.44
ADD FOR OVER HEAD CHARGES @5% : 5.22
LABOUR FOR 3.000 metre 120.06
LABOUR PER metre 40.00
Painting top of roofs with bitumen
of approved Quality at 17 kg for 10
sqm. impregnated with a cost of
sand at 60m per 10 sqm. including
cleaning the slab surface with
brushes and finally with a piece of
cloth lightly soaked in kerosene
oil Complete.
MATERIAL :
CARRIAGE :
Tar Bitumen.
1 KM BY MECH. TRANSPORT 1 tonne 0.0170 123.25 2.10
Sand
1 KM BY MECH. TRANSPORT 1 cum 0.0600 110.95 6.66
LABOUR :
Beldar
For Cleaning the surface : Each 0.1100 116.67 12.83
Beldar
For Applying Kerosine oil : Each 0.1100 116.67 12.83
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Beldar
For Heating Material : Each 0.0800 116.67 9.33
Beldar
For Carriage of Hot Tar : Each 0.0800 116.67 9.33
Painter 2nd Class
For Spreading Hot Tar : Each 0.1500 128.33 19.25
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 73.57
TOTAL : 73.57
WATER CHARGES @ 1.5% : 13.40
TOTAL : 86.97
ADD FOR CONTRACTORS PROFIT 10% : 8.69
ADD FOR OVER HEAD CHARGES @5% : 4.35
LABOUR FOR 10.000 sqm. 100.01
LABOUR PER sqm. 10.00
14370200 With hot polymers modified bitumen
Details of cost for 10 sqm.
MATERIAL :
Total : 1094.80
Add for water charges @1.5% Except on (-I-) : 0.76
Total : 1095.56
ADD FOR CONTRACTORS PROFIT 10% Except on (-I-) : 5.28
ADD FOR OVER HEAD CHARGES @5% Except on (-I-): 2.64
COST FOR 10.000 sqm. 1103.48
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
COST PER sqm. 110.35
LABOUR RATE :
Labour As per item no :14370100 47.47
TOTAL : 100.00
Add for water charges except on (-a-) : 0.76
TOTAL : 100.76
LABOUR FOR 10.000 sqm. 101.00
LABOUR PER sqm. 10.10
14380000 Making khurras 45x45cm with average
minimum thickness of 5 cm. cement
concrete 1:2:4 (1 cement :2 sand: 4
stone aggregate of 20 mm nominal
size) finished with 12 mm cement
plaster 1:3 (1 cement : 3 sand )
and coat of neat cement rounding
the outlet complete
Details of cost for 1 khurras
MATERIAL :
Total : 78.80
Add for water charges @1.5% Except on (-I-) : 0.22
Total : 79.02
ADD FOR CONTRACTORS PROFIT 10% Except on (-I-) : 1.52
ADD FOR OVER HEAD CHARGES @5% Except on (-I-): 0.76
COST FOR 1.000 No. 81.30
COST PER No. 81.30
LABOUR RATE :
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Labour As per item no :09200300 7.14
Labour As per item no :17046010 10.10
Labour As per item no :17056000 3.88
TOTAL : 21.12
Add for water charges except on (-a-) : 0.22
TOTAL : 21.34
ADD FOR CONTRACTORS PROFIT 10% EXCEPT ON (-a-): 0.02
ADD FOR OVER HEAD CHARGES @5% EXCEPT ON (-a-): 0.01
LABOUR FOR 1.000 No. 21.37
LABOUR PER No. 21.40
14390000 Providing and fixing on wall face
C.I.rain water pipes including
fitting the joints with spun yarn
and cement mortar 1:2 (1 cement :2
sand)
MATERIAL :
75 mm dia pipe
length of one pipe =1.83 metre
Total nos of pipe reqd. = 5 nos. Each 5.0000 520.00 2600.00
LABOUR :
Fitter Each 0.2800 148.16 41.48
Beldar Each 0.5400 116.67 63.00
Bandhani Each 0.1300 116.67 15.17
TOTAL : 2764.64
ADD FOR CONTRACTORS PROFIT 10% 276.46
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 139.64
TOTAL : 139.64
ADD FOR CONTRACTORS PROFIT 10% : 13.96
ADD FOR OVER HEAD CHARGES @5% : 6.98
LABOUR FOR 8.700 metre 160.58
LABOUR PER metre 18.45
14390200 100 mm dia pipe
Details of cost for 8.7 metre.
MATERIAL :
LABOUR :
Fitter Each 0.3300 148.16 48.89
Beldar Each 0.6500 116.67 75.84
Bandhani Each 0.1600 116.67 18.67
TOTAL : 3313.39
ADD FOR CONTRACTORS PROFIT 10% 331.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 163.39
TOTAL : 163.39
ADD FOR CONTRACTORS PROFIT 10% : 16.34
ADD FOR OVER HEAD CHARGES @5% : 8.17
LABOUR FOR 8.700 Metre 187.90
LABOUR PER Metre 21.60
14390300 150 mm dia pipe
Details of cost for 8.7 metre.
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
LABOUR :
Fitter Each 0.5000 148.16 74.08
Beldar Each 0.9700 116.67 113.17
Bandhani Each 0.2100 116.67 24.50
TOTAL : 7756.74
ADD FOR CONTRACTORS PROFIT 10% 775.67
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 231.74
TOTAL : 231.74
ADD FOR CONTRACTORS PROFIT 10% : 23.17
ADD FOR OVER HEAD CHARGES @5% : 11.58
LABOUR FOR 8.700 Metre 266.49
LABOUR PER Metre 30.60
14400000 Providing and fixing m.s.holder bat
clamps of approved design to C.I.
or S.C.I pipes embeded in and
including cement concrete blocks 10
x10x10 cm of 1:2:4:mix (1 cement 2
sand 4 stone graded stone aggregate
20 mm nominal size) and cost of
cutting holes and making good the
wall etc.
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
C.C.Blocks of C.C.1:2:4.
5x0.10x0.10x0.10m =0.005 Cum.
Rate vide item No. 09200300. 1 cum 0.0050 3454.10 17.27
CARRIAGE :
carriage of material L.S 2.00
LABOUR :
Fitter Each 0.1250 148.16 18.52
Mason 2nd Class Each 0.7500 158.67 119.00
Beldar Each 0.5000 116.67 58.34
Total : 345.12
ADD FOR CONTRACTORS PROFIT 10% Except on (-I-) 32.78
ADD FOR OVER HEAD CHARGES @5% Except on (-I-) 16.39
COST FOR 5.000 Clamps 394.29
COST PER Clamps 78.85
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 200.85
Labour As per item no :09200300 3.57
TOTAL : 204.42
MATERIAL :
C.C.blocks of C.C.1:2:4.
5x0.1x0.1x0.1 =0.005 cu.m.
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
(Rate vide item no 09200300). 1 cum 0.0050 3454.10 17.27
CARRIAGE :
Carriage of material L.S 2.00
LABOUR :
Fitter Each 0.1250 148.16 18.52
Mason 2nd Class Each 0.7500 158.67 119.00
Beldar Each 0.5000 116.67 58.34
Total : 420.12
ADD FOR CONTRACTORS PROFIT 10% Except on (-I-) & (-A-): 40.28
ADD FOR OVER HEAD CHARGES @5% Except on (-I-) & (-A-): 20.14
COST FOR 5.000 Clamps 480.54
COST PER Clamps 96.10
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 200.85
Labour As per item no :09200300 3.57
TOTAL : 204.42
MATERIAL :
C.C.blocks of C.C.1:2:4.
5x0.1x0.1x0.1 =0.005 cum
(Rate vide item No.09200300). 1 cum 0.0050 345.10 17.27 (-I-)
CARRIAGE :
Carriage of material L.S 2.00
LABOUR :
Fitter Each 0.1250 148.16 18.52
Mason 2nd Class Each 0.7500 158.67 119.00
Beldar Each 0.5000 116.67 58.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 200.85
Labour As per item no :09200300 3.57 -a-
TOTAL : 204.42
14410101 75 mm diametre
Details of cost for one bend.
MATERIAL :
LABOUR :
Labour for fixing L.S. 5.00
TOTAL : 130.00
ADD FOR CONTRACTORS PROFIT 10% 13.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 5.00
TOTAL : 5.00
ADD FOR CONTRACTORS PROFIT 10% : 0.50
ADD FOR OVER HEAD CHARGES @5% : 0.25
LABOUR FOR 1.000 Bend 5.75
LABOUR PER Bend 5.75
14410102 100 mm diametre
Details of cost for one bend
MATERIAL :
LABOUR :
Labour for fixing L.S 5.00
TOTAL : 180.00
ADD FOR CONTRACTORS PROFIT 10% 18.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 5.00
TOTAL : 5.00
ADD FOR CONTRACTORS PROFIT 10% : 0.50
ADD FOR OVER HEAD CHARGES @5% : 0.25
LABOUR FOR 1.000 bend 5.75
LABOUR PER bend 5.75
14410103 150 mm dia metre
Details of cost for one bend.
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
LABOUR :
Labour for fixing L.S 5.50
TOTAL : 394.00
ADD FOR CONTRACTORS PROFIT 10% 39.40
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 5.50
TOTAL : 5.50
ADD FOR CONTRACTORS PROFIT 10% : 0.55
ADD FOR OVER HEAD CHARGES @5% : 0.27
LABOUR FOR 1.000 Bend 6.32
LABOUR PER Bend 6.30
14410200 C.I.head flat or corner type bend
MATERIAL :
LABOUR :
Labour for fixing L.S 5.00
TOTAL : 172.00
ADD FOR CONTRACTORS PROFIT 10% 17.20
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 5.00
TOTAL : 5.00
ADD FOR CONTRACTORS PROFIT 10% : 0.50
ADD FOR OVER HEAD CHARGES @5% : 0.25
LABOUR FOR 1.000 Bend 5.75
LABOUR PER Bend 5.75
14410202 100 mm diametre
MATERIAL :
LABOUR :
Labour for fixing L.S 5.50
TOTAL : 202.50
ADD FOR CONTRACTORS PROFIT 10% 20.25
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR OVER HEAD CHARGES @5% 10.12
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 5.50
TOTAL : 5.50
ADD FOR CONTRACTORS PROFIT 10% : 0.55
ADD FOR OVER HEAD CHARGES @5% : 0.27
LABOUR FOR 1.000 Bend 6.32
LABOUR PER Bend 6.30
14410203 150 mm diametre
Details of coat for one bend
MATERIAL :
LABOUR :
Labour for fixing L.S 6.00
TOTAL : 424.50
ADD FOR CONTRACTORS PROFIT 10% 42.45
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.30
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR FOR 1.000 Bend 6.90
LABOUR PER Bend 6.90
14410300 C.I.plain shoes plain
MATERIAL :
Cost for C.I.plain shoe 75mm dia. Each 1.0000 140.00 140.00
LABOUR :
Labour for fixing L.S 5.00
TOTAL : 151.00
ADD FOR CONTRACTORS PROFIT 10% 15.10
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 5.00
TOTAL : 5.00
ADD FOR CONTRACTORS PROFIT 10% : 0.50
ADD FOR OVER HEAD CHARGES @5% : 0.25
LABOUR FOR 1.000 Shoe 5.75
LABOUR PER Shoe 5.75
14410302 C.I. plain shoes 100 mm dia metre
Details of cost for one C.I. plain
shoe.
MATERIAL :
Cost for C.I plain shoe 100 mm dia Each 1.0000 180.00 180.00
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Cement Mortar Spun yarn etc. L.S 3.00
CARRIAGE :
Carriage of material L.S 4.00
LABOUR :
Labour for fixing L.S 6.00
TOTAL : 193.00
ADD FOR CONTRACTORS PROFIT 10% 19.30
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.30
LABOUR FOR 1.000 Shoe 6.90
LABOUR PER Shoe 6.90
14410303 150 mm diametre
Details of cost for one C.I. plain
shoe
MATERIAL :
Cost for C.I.plain shoe 150 mm dia Each 1.0000 320.00 320.00
LABOUR :
labour for fixing L.S 6.00
TOTAL : 336.00
ADD FOR CONTRACTORS PROFIT 10% 33.60
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.30
LABOUR FOR 1.000 Shoe 6.90
LABOUR PER Shoe 6.90
14410400 C.I. branch (plain)
MATERIAL :
LABOUR :
Labour for fixing L.S 6.00
TOTAL : 191.00
ADD FOR CONTRACTORS PROFIT 10% 19.10
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.30
LABOUR FOR 1.000 Branch 6.90
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR PER Branch 6.90
14410402 100 mm dia single branch
Details of cost for one branch.
MATERIAL :
LABOUR :
Labour for fixing L.S 7.00
TOTAL : 257.00
ADD FOR CONTRACTORS PROFIT 10% 25.70
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 7.00
TOTAL : 7.00
ADD FOR CONTRACTORS PROFIT 10% : 0.70
ADD FOR OVER HEAD CHARGES @5% : 0.35
LABOUR FOR 1.000 Branch 8.05
LABOUR PER Branch 8.05
14410403 150 mm dia metre single branch
Details of cost for one single
MATERIAL :
LABOUR :
labour for fixing L.S 10.00
TOTAL : 625.00
ADD FOR CONTRACTORS PROFIT 10% 62.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 10.00
TOTAL : 10.00
ADD FOR CONTRACTORS PROFIT 10% : 1.00
ADD FOR OVER HEAD CHARGES @5% : 0.50
LABOUR FOR 1.000 Branch 11.50
LABOUR PER Branch 11.50
14410404 C.I. double branches plain
75 mm dia double branch
Details of cost for one branch.
MATERIAL :
LABOUR :
Labour for fixing L.S 10.00
TOTAL : 325.00
ADD FOR CONTRACTORS PROFIT 10% 32.50
MATERIAL :
LABOUR :
Labour for fixing L.S 10.00
TOTAL : 375.00
ADD FOR CONTRACTORS PROFIT 10% 37.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 10.00
TOTAL : 10.00
ADD FOR CONTRACTORS PROFIT 10% : 1.00
ADD FOR OVER HEAD CHARGES @5% : 0.50
LABOUR FOR 1.000 Branch 11.50
LABOUR PER Branch 11.50
MATERIAL :
LABOUR :
Labour for fixing L.S 5.00
TOTAL : 141.50
ADD FOR CONTRACTORS PROFIT 10% 14.15
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 5.00
TOTAL : 5.00
ADD FOR CONTRACTORS PROFIT 10% : 0.50
ADD FOR OVER HEAD CHARGES @5% : 0.25
LABOUR FOR 1.000 Offset 5.75
LABOUR PER Offset 5.75
14410502 75 mm dia 75 mm projection.
Details of cost for one of offset
MATERIAL :
LABOUR :
Labour for fixing L.S 5.00
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 241.50
ADD FOR CONTRACTORS PROFIT 10% 24.15
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 5.00
TOTAL : 5.00
ADD FOR CONTRACTORS PROFIT 10% : 0.50
ADD FOR OVER HEAD CHARGES @5% : 0.25
LABOUR FOR 1.000 Offset 5.75
LABOUR PER Offset 5.75
14410503 75 mm dia 115 mm projection
Details of cost for one offset .
MATERIAL :
LABOUR :
Labour for fixing L.S 5.00
TOTAL : 262.00
ADD FOR CONTRACTORS PROFIT 10% 26.20
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 5.00
TOTAL : 5.00
ADD FOR CONTRACTORS PROFIT 10% : 0.50
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR OVER HEAD CHARGES @5% : 0.25
LABOUR FOR 1.000 Offset 5.75
LABOUR PER Offset 5.75
14410504 75mm dia 150 mm projection
Details of cost for one offset .
MATERIAL :
LABOUR :
labour for fixing L.S 5.50
TOTAL : 312.50
ADD FOR CONTRACTORS PROFIT 10% 31.25
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 5.50
TOTAL : 5.50
ADD FOR CONTRACTORS PROFIT 10% : 0.55
ADD FOR OVER HEAD CHARGES @5% : 0.27
LABOUR FOR 1.000 Offset 6.32
LABOUR PER Offset 6.30
14410505 100 mm dia 50 mm projection
Details of cost for one offset.
MATERIAL :
LABOUR :
Labour for fixing L.S 5.00
TOTAL : 211.00
ADD FOR CONTRACTORS PROFIT 10% 21.10
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 5.00
TOTAL : 5.00
ADD FOR CONTRACTORS PROFIT 10% : 0.50
ADD FOR OVER HEAD CHARGES @5% : 0.25
LABOUR FOR 1.000 Offset 5.75
LABOUR PER Offset 5.75
14410506 100 mm dia 75 mm projection
Details of cost for one offset .
MATERIAL :
LABOUR :
Labour for fixing L.S 5.50
TOTAL : 211.00
ADD FOR CONTRACTORS PROFIT 10% 21.10
MATERIAL :
75 mm dia pipe.
Length of one pipe =1.83 mt
Total no of pipe reqd. =5 nos Each 5.0000 520.00 2600.00
LABOUR :
Fitter Each 0.2800 148.16 41.48
Mason 2nd Class Each 0.3000 158.67 47.60
Beldar Each 0.5400 116.67 63.00
Bandhani Each 0.1300 116.67 15.17
TOTAL : 2812.24
ADD FOR CONTRACTORS PROFIT 10% 281.22
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 167.24
TOTAL : 167.24
ADD FOR CONTRACTORS PROFIT 10% : 16.32
ADD FOR OVER HEAD CHARGES @5% : 8.36
LABOUR FOR 8.700 metres 122.32
LABOUR PER metres 22.10
14420200 100 mm dia pipe
Details of cost for 8.7 metre
MATERIAL :
LABOUR :
Fitter Each 0.3300 148.16 48.89
Mason 2nd Class Each 0.3000 158.67 47.60
Beldar Each 0.6500 116.67 75.84
Bandhani Each 0.1600 116.67 18.67
TOTAL : 3360.98
ADD FOR CONTRACTORS PROFIT 10% 336.09
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 210.98
TOTAL : 210.98
ADD FOR CONTRACTORS PROFIT 10% : 21.09
ADD FOR OVER HEAD CHARGES @5% : 10.54
LABOUR FOR 8.700 metres 242.62
LABOUR PER metres 27.90
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
14420300 150 mm dia pipes
Details of cost for 8.7 metre
MATERIAL :
LABOUR :
Fitter Each 0.5000 148.16 74.08
Mason 2nd Class Each 0.4000 158.67 63.47
Beldar Each 0.9700 116.67 113.17
Bandhani Each 0.2100 116.67 24.50
TOTAL : 7820.20
ADD FOR CONTRACTORS PROFIT 10% 782.02
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 295.20
TOTAL : 295.20
ADD FOR CONTRACTORS PROFIT 10% : 29.52
ADD FOR OVER HEAD CHARGES @5% : 14.76
LABOUR FOR 8.700 metre 339.48
LABOUR PER metre 39.00
14430000 Providing lead caulked joints to
sand cost iron rain water pipe and
fittings
MATERIAL :
LABOUR :
Fitter Each 0.0500 148.16 7.41
Asstt. Fitter Each 0.0600 128.33 7.70
Beldar Each 0.0800 116.67 9.33
TOTAL : 134.88
ADD FOR CONTRACTORS PROFIT 10% 13.48
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 24.43
TOTAL : 1 24.43
ADD FOR CONTRACTORS PROFIT 10% : 2.44
ADD FOR OVER HEAD CHARGES @5% : 1.22
LABOUR FOR 1.000 Joint 28.09
LABOUR PER Joint 28.10
14430200 100 mm dia pipe
Details of cost for one joint.
MATERIAL :
TOTAL : 252.16
ADD FOR CONTRACTORS PROFIT 10% 25.21
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 39.61
TOTAL : 39.61
ADD FOR CONTRACTORS PROFIT 10% : 3.96
ADD FOR OVER HEAD CHARGES @5% : 1.98
LABOUR FOR 1.000 Joint 45.55
LABOUR PER Joint 45.55
14440000 Providing fixing and embedding sand
cast iron accessories for rain
water pipes in the masonry
surrounded with 12 mm thick cement
mortar of the same mix as that of
masonry (lead caulking will be paid
for separately)
14440101 75 mm dia
Details of cost for one bend .
MATERIAL :
LABOUR :
Labour for fixing L.S 5.00
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 128.00
ADD FOR CONTRACTORS PROFIT 10% 12.80
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 5.00
TOTAL : 5.00
ADD FOR CONTRACTORS PROFIT 10% : 0.50
ADD FOR OVER HEAD CHARGES @5% : 0.25
LABOUR FOR 1.000 Bend 5.75
LABOUR PER Bend 5.75
14440102 100 mm dia
Details of cost for one bend.
MATERIAL :
LABOUR :
Labour for fixing L.S 5.00
TOTAL : 178.00
ADD FOR CONTRACTORS PROFIT 10% 17.80
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 5.00
TOTAL : 5.00
ADD FOR CONTRACTORS PROFIT 10% : 0.50
ADD FOR OVER HEAD CHARGES @5% : 0.25
LABOUR FOR 1.000 bend 5.75
LABOUR PER bend 5.75
14440103 150 mm dia
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Details of cost for one bend.
MATERIAL :
CARRIAGE :
carriage of material L.S 5.00
LABOUR :
Labour for fixing L.S 7.50
TOTAL : 392.50
ADD FOR CONTRACTORS PROFIT 10% 39.25
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 7.50
TOTAL : 7.50
ADD FOR CONTRACTORS PROFIT 10% : 0.75
ADD FOR OVER HEAD CHARGES @5% : 0.37
LABOUR FOR 1.000 Bend 8.62
LABOUR PER Bend 8.60
14440200 sand cast iron plain shoe.
14440201 75 mm dia
Details of cost for one shoe.
MATERIAL :
LABOUR :
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Labour for fixing L.S 5.00
TOTAL : 149.00
ADD FOR CONTRACTORS PROFIT 10% 14.90
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 5.00
TOTAL : 5.00
ADD FOR CONTRACTORS PROFIT 10% : 0.50
ADD FOR OVER HEAD CHARGES @5% : 0.25
LABOUR FOR 1.000 Shoe 5.75
LABOUR PER Shoe 5.75
14440202 100 mm dia
Details of cost for one shoe .
MATERIAL :
LABOUR :
labour for fixing L.S 6.00
TOTAL : 191.00
ADD FOR CONTRACTORS PROFIT 10% 19.10
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.30
LABOUR FOR 1.000 Shoe 6.90
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR PER Shoe 6.90
14440203 150 mm dia
Details of cost for one shoe.
MATERIAL :
LABOUR :
Labour for fixing L.S 7.50
TOTAL : 332.50
ADD FOR CONTRACTORS PROFIT 10% 33.25
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 7.50
TOTAL : 7.50
ADD FOR CONTRACTORS PROFIT 10% : 0.75
ADD FOR OVER HEAD CHARGES @5% : 0.37
LABOUR FOR 1.000 Shoe 8.62
LABOUR PER Shoe 8.60
14450000 Providing and fixing on wall face
asbestos cement rain water pipe in
cluding jointing with spun yarn
soaked in bitumen and cement mortar
1:2 (1 cement :2 sand ) complete.
MATERIAL :
LABOUR :
Fitter Each 0.2000 148.16 29.63
Beldar Each 0.4000 116.67 46.67
Bandhani Each 0.1000 116.67 11.67
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 107.97
TOTAL : 107.97
ADD FOR CONTRACTORS PROFIT 10% : 10.80
ADD FOR OVER HEAD CHARGES @5% : 5.40
LABOUR FOR 10.000 metres 124.17
LABOUR PER metres 12.40
14450200 80 mm dia metre
Details of cost for 10 metre
MATERIAL :
LABOUR :
Fitter Each 0.2500 148.16 37.04
Beldar Each 0.5000 116.67 58.34
Bandhani Each 0.1200 116.67 14.00
TOTAL : 649.37
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR CONTRACTORS PROFIT 10% 67.93
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 129.37
TOTAL : 129.37
ADD FOR CONTRACTORS PROFIT 10% : 12.93
ADD FOR OVER HEAD CHARGES @5% : 6.46
LABOUR FOR 10.000 metre 148.77
LABOUR PER metre 14.90
14450300 100 mm diametre
Details of cost for 10 metres.
MATERIAL :
LABOUR :
Fitter Each 0.3000 148.16 44.45
Beldar Each 0.6000 116.67 70.00
Bandhani Each 0.1600 116.67 18.67
TOTAL : 798.11
ADD FOR CONTRACTORS PROFIT 10% 79.81
LABOUR RATE :
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ACTUAL LABOUR+SUNDRIES 153.11
TOTAL : 153.11
ADD FOR CONTRACTORS PROFIT 10% : 15.31
ADD FOR OVER HEAD CHARGES @5% : 7.65
LABOUR FOR 10.000 metres 176.07
LABOUR PER metres 17.60
14460000 Providing and fixing for A.C. pipe
wall plugs and atandard holder bat
clamps comprising of two semi
circular halves of flat iron and
cast iron base screwed on wooden
plugs.
14460100 50 mm dia
Details of cost for 5 nos.
MATERIAL :
wooden plugs.
(Rate vide item No.1205902000). Eacg 10.0000 12.75 127.50 -I-
CARRIAGE :
Carriage of material L.S 1.50
LABOUR :
Fitter Each 0.1700 148.16 25.19
Beldar Each 0.5000 116.67 58.34
Total : 315.51
ADD FOR CONTRACTORS PROFIT 10% Except on (-I-): 18.75
ADD FOR OVER HEAD CHARGES @5% Except on (-I-): 9.37
COST FOR 5.000 No 343.13
COST PER No 68.60
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 86.01
Labour As per item no :1205902000 42.00 (-a-)
TOTAL : 128.01
MATERIAL :
Wooden plugs.
(Rate same as per item
no.1205902000 of wood work). Each 10.0000 12.75 127.50 (-I-)
CARRIAGE :
Carriage of material L.S 1.50
LABOUR :
Fitter Each 0.1700 148.16 25.19
Beldar Each 0.5000 116.67 58.34
Total : 340.01
ADD FOR CONTRACTORS PROFIT 10% Except on (-I-) : 21.25
ADD FOR OVER HEAD CHARGES @5% Except on (-I-): 10.62
COST FOR 5.000 Nos 371.88
COST PER Nos 74.20
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 86.01
Labour As per item no :1205902000 42.00 (-a-)
TOTAL : 128.01
MATERIAL :
Wooden plugs
(Rate same as per item
no.1205902000 of wood work.) Each 10.0000 12.75 127.50 (-I-)
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
CARRIAGE :
Carriage of material L.S 1.50
LABOUR :
Fitter Each 0.1700 148.16 25.19
Beldar Each 0.5000 116.67 58.34
Total : 415.01
ADD FOR CONTRACTORS PROFIT 10% Except on (-I-): 28.75
ADD FOR OVER HEAD CHARGES @5% Except on (-I-) : 14.37
COST FOR 5.000 No 458.13
COST PER No 91.60
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 86.01
MATERIAL :
LABOUR :
Labour for fixing L.S 6.00
TOTAL : 56.00
ADD FOR CONTRACTORS PROFIT 10% 5.60
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.30
LABOUR FOR 1.000 Bend 6.90
LABOUR PER Bend 6.90
MATERIAL :
LABOUR :
Labour for fixing L.S 6.00
TOTAL : 61.00
ADD FOR CONTRACTORS PROFIT 10% 6.10
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.30
LABOUR FOR 1.000 Bend 6.90
LABOUR PER Bend 6.90
14470103 80 mm dia without door
Details of cost for one bend
without door.
MATERIAL :
LABOUR :
Labour for fixing L.S 6.00
TOTAL : 61.00
ADD FOR CONTRACTORS PROFIT 10% 6.10
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.30
LABOUR FOR 1.000 Bend 6.90
LABOUR PER Bend 6.90
14470104 80 mm dia with door
Details of cost for one bend with
door.
MATERIAL :
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR :
Labour for fixing L.S 6.00
TOTAL : 71.00
ADD FOR CONTRACTORS PROFIT 10% 7.10
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.30
LABOUR FOR 1.000 Bend 6.90
LABOUR PER Bend 6.90
MATERIAL :
LABOUR :
Labour for fixing L.S 6.00
TOTAL : 71.00
ADD FOR CONTRACTORS PROFIT 10% 7.10
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.30
LABOUR FOR 1.000 Bend 6.90
LABOUR PER Bend 6.90
14470106 100 mm dia with door
Details of cost for one bend with
door.
MATERIAL :
LABOUR :
Labour for fixing L.S 6.00
TOTAL : 76.00
ADD FOR CONTRACTORS PROFIT 10% 7.60
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.30
LABOUR FOR 1.000 Bend 6.90
LABOUR PER Bend 6.90
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
14470200 Offsets.
MATERIAL :
LABOUR :
Labour for fixing L.S 6.00
TOTAL : 61.00
ADD FOR CONTRACTORS PROFIT 10% 6.10
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
0.60
ADD FOR CONTRACTORS PROFIT 10% : 0.30
ADD FOR OVER HEAD CHARGES @5% : 6.90
LABOUR FOR 1.000 Offset 6.90
LABOUR PER Offset
14470202 Offset 50 mm projection 80 mm dia
Details of cost for one offset
MATERIAL :
LABOUR :
Labour for fixing L.S 6.00
TOTAL : 71.00
ADD FOR CONTRACTORS PROFIT 10% 7.10
MATERIAL :
LABOUR :
labour for fixing L.S 6.00
TOTAL : 81.00
ADD FOR CONTRACTORS PROFIT 10% 8.10
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.30
LABOUR FOR 1.000 Offset 6.90
LABOUR PER Offset 6.90
14470300 Offsets.
MATERIAL :
LABOUR :
Labour for fixing L.S 6.00
TOTAL : 81.00
ADD FOR CONTRACTORS PROFIT 10% 8.10
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.30
LABOUR FOR 1.000 Offset 6.90
LABOUR PER Offset 6.90
14470302 75 mm projection 80 mm dia.
Details of cost for one offset.
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
LABOUR :
Labour for fixing L.S 6.00
TOTAL : 131.00
ADD FOR CONTRACTORS PROFIT 10% 13.10
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.30
LABOUR FOR 1.000 Offset 6.90
LABOUR PER Offset 6.90
14470303 75 mm projection 100 mm dia.
Details of cost for one offset.
MATERIAL :
CARRIAGE :
Carriage of material L.S 5.00
LABOUR :
Labour for fixing L.S 6.00
TOTAL : 171.00
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR CONTRACTORS PROFIT 10% 17.10
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.30
LABOUR FOR 1.000 Offset 6.90
LABOUR PER Offset 6.90
14470400 Offset 100 mm projection.
14470401 50 mm dia
Details of cost for one offset.
MATERIAL :
LABOUR :
Labour for fixing L.S 6.00
TOTAL : 86.00
ADD FOR CONTRACTORS PROFIT 10% 8.60
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.30
LABOUR FOR 1.000 Offset 6.90
LABOUR PER Offset 6.90
14470402 80 mm dia .
Details of cost for one offset.
MATERIAL :
LABOUR :
Labour for fixing L.S 6.00
TOTAL : 101.00
ADD FOR CONTRACTORS PROFIT 10% 10.10
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.30
LABOUR FOR 1.000 Offset 6.90
LABOUR PER Offset 6.90
14470403 100 mm dia
Details of cost for one offset.
MATERIAL :
LABOUR :
Labour for fixing L.S 6.00
TOTAL : 121.00
ADD FOR CONTRACTORS PROFIT 10% 12.10
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.30
LABOUR FOR 1.000 Offset 6.90
LABOUR PER Offset 6.90
14470500 Offset 150 mm projection.
MATERIAL :
LABOUR :
Labour for fixing L.S 6.00
TOTAL : 96.00
ADD FOR CONTRACTORS PROFIT 10% 9.60
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.30
LABOUR FOR 1.000 Offset 6.90
LABOUR PER Offset 6.90
14470502 80 mm dia metre.
Details of cost for one offset
MATERIAL :
LABOUR :
Labour for fixing L.S 6.00
TOTAL : 161.00
ADD FOR CONTRACTORS PROFIT 10% 16.10
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.30
LABOUR FOR 1.000 Offset 6.90
LABOUR PER Offset 6.90
MATERIAL :
LABOUR :
Labour for fixing L.S 6.00
TOTAL : 181.00
ADD FOR CONTRACTORS PROFIT 10% 18.10
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.30
LABOUR FOR 1.000 Offset 6.90
LABOUR PER Offset 6.90
14470600 Offsets 200 mm projection
MATERIAL :
LABOUR :
Labour for fixing L.S 6.00
TOTAL : 121.00
ADD FOR CONTRACTORS PROFIT 10% 12.10
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.30
LABOUR FOR 1.000 Offset 6.90
LABOUR PER Offset 6.90
14470602 80 mm dia metre
Details of cost for one offset
MATERIAL :
LABOUR :
Labour for fixing L.S 6.00
TOTAL : 131.00
ADD FOR CONTRACTORS PROFIT 10% 13.10
LABOUR RATE :
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.30
LABOUR FOR 1.000 Offset 6.90
LABOUR PER Offset 6.90
14470603 100 mm dia metre
Detail of cost for one offset.
MATERIAL :
LABOUR :
Labour for fixing L.S 6.00
TOTAL : 141.00
ADD FOR CONTRACTORS PROFIT 10% 14.10
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.30
LABOUR FOR 1.000 Offset 6.90
LABOUR PER Offset 6.90
14470700 Offset 300 mm projection
MATERIAL :
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Cost of one offset. Each 1.0000 120.00 120.00
LABOUR :
Labour for fixing L.S 6.00
TOTAL : 141.00
ADD FOR CONTRACTORS PROFIT 10% 14.10
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.30
LABOUR FOR 1.000 Offset 6.90
LABOUR PER Offset 6.90
14470702 100 mm dia metre
Details of cost for one offset.
MATERIAL :
LABOUR :
Labour for fixing L.S 6.00
TOTAL : 151.00
ADD FOR CONTRACTORS PROFIT 10% 15.10
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.30
LABOUR FOR 1.000 Offset 6.90
LABOUR PER Offset 6.90
14470800 Offset 450 mm projection.
MATERIAL :
LABOUR :
Labour for fixing L.S 6.00
TOTAL : 156.00
ADD FOR CONTRACTORS PROFIT 10% 15.60
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.30
LABOUR FOR 1.000 Offset 6.90
LABOUR PER Offset 6.90
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
14470802 100 mm dia metre
Details of cost for one offset.
MATERIAL :
LABOUR :
Labour for fixing L.S 6.00
TOTAL : 161.00
ADD FOR CONTRACTORS PROFIT 10% 16.10
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.30
LABOUR FOR 1.000 Offset 6.90
LABOUR PER Offset 6.90
14470900 Offset 650 mm projection
100 mm dia metre
Details of cost for one offset.
MATERIAL :
LABOUR :
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Labour for fixing L.S 6.00
TOTAL : 221.00
ADD FOR CONTRACTORS PROFIT 10% 22.10
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.30
LABOUR FOR 1.000 Offset 6.90
LABOUR PER Offset 6.90
14471000 Junction equal single.
MATERIAL :
LABOUR :
Labour for fixing L.S 6.00
TOTAL : 91.00
ADD FOR CONTRACTORS PROFIT 10% 9.10
LABOUR RATE :
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.30
LABOUR FOR 1.000 Junction 6.90
LABOUR PER Junction 6.90
14471002 50 mm dia metre with door
MATERIAL :
LABOUR :
Labour for fixing L.S 6.00
TOTAL : 91.00
ADD FOR CONTRACTORS PROFIT 10% 9.10
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.30
LABOUR FOR 1.000 Junction 6.90
LABOUR PER Junction 3 6.90
14471003 80 mm dia metre without door
Details of cost for one junction
MATERIAL :
LABOUR :
Labour for fixing L.S 6.00
TOTAL : 81.00
ADD FOR CONTRACTORS PROFIT 10% 8.10
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.30
LABOUR FOR 1.000 Junction 6.90
LABOUR PER Junction 6.90
14471004 80 mm dia metre with door
Details of cost for one junction
MATERIAL :
LABOUR :
Labour for fixing L.S 6.00
TOTAL : 101.00
ADD FOR CONTRACTORS PROFIT 10% 10.10
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.30
LABOUR FOR 1.000 Junction 6.90
LABOUR PER Junction 6.90
MATERIAL :
LABOUR :
Labour for fixing L.S 6.00
TOTAL : 91.00
ADD FOR CONTRACTORS PROFIT 10% 9.10
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.30
LABOUR FOR 1.000 Junction 6.90
LABOUR PER Junction 6.90
14471006 100 mm dia metre with door
Details of cost for one junction
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
LABOUR :
Labour for fixing L.S 6.00
TOTAL : 121.00
ADD FOR CONTRACTORS PROFIT 10% 12.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.30
LABOUR FOR 1.000 Junction 6.90
LABOUR PER Junction 6.90
14471100 Junction equal double.
MATERIAL :
LABOUR :
Labour for fixing L.S 6.00
TOTAL : 91.00
ADD FOR CONTRACTORS PROFIT 10% 9.10
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.30
LABOUR FOR 1.000 Junction 6.90
LABOUR PER Junction 6.90
14471102 50 mm dia with door
Details of cost for one junction.
MATERIAL :
LABOUR :
Labour for fixing L.S 6.00
TOTAL : 106.00
ADD FOR CONTRACTORS PROFIT 10% 10.60
MATERIAL :
LABOUR :
Labour for fixing L.S 6.00
TOTAL : 126.00
ADD FOR CONTRACTORS PROFIT 10% 12.60
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.30
LABOUR FOR 1.000 Junction 6.90
LABOUR PER Junction 6.90
14471104 80 mm dia with door
Details of cost for one junction
MATERIAL :
LABOUR :
Labour for fixing L.S 6.00
TOTAL : 126.00
ADD FOR CONTRACTORS PROFIT 10% 12.60
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.30
LABOUR FOR 1.000 Junction 6.90
LABOUR PER Junction 6.90
14471105 100 mm dia without door
Details of cost for one junction .
MATERIAL :
LABOUR :
Labour for fixing L.S 6.00
TOTAL : 126.00
ADD FOR CONTRACTORS PROFIT 10% 12.60
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.30
LABOUR FOR 1.000 Junction 6.90
LABOUR PER Junction 6.90
14471106 100 mm dia with door
Details of cost for one junction .
MATERIAL :
LABOUR :
Labour for fixing L.S 6.00
TOTAL : 131.00
ADD FOR CONTRACTORS PROFIT 10% 13.10
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.30
LABOUR FOR 1.000 Junction 6.90
LABOUR PER Junction 6.90
14471200 Standard shoe
14471201 50 mm dia
Details of cost for one standard
shoe.
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
LABOUR :
Labour for fixing L.S 6.00
TOTAL : 61.00
ADD FOR CONTRACTORS PROFIT 10% 6.10
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.30
LABOUR FOR 1.000 Shoe 6.90
LABOUR PER Shoe 6.90
14471202 75 mm dia
Details of cost for one standard
shoe.
MATERIAL :
LABOUR :
Labour for fixing L.S 6.00
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 121.00
ADD FOR CONTRACTORS PROFIT 10% 12.10
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.30
LABOUR FOR 1.000 Shoe 6.90
LABOUR PER Shoe 6.90
14471203 100 mm dia
Details of cost for one standard
shoe.
MATERIAL :
LABOUR :
Labour for fixing L.S 6.00
TOTAL : 131.00
ADD FOR CONTRACTORS PROFIT 10% 13.10
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.30
LABOUR FOR 1.000 Shoe 6.90
LABOUR PER Shoe 6.90
14471300 Hexagonal rain water head
MATERIAL :
LABOUR :
Labour for fixing L.S 6.00
TOTAL : 121.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.30
LABOUR FOR 1.000 No 6.90
LABOUR PER No 6.90
14471302 300x250 mm,80 mm or 100 mm dia
Details of cost for one hexagonal
head.
MATERIAL :
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR :
Labour for fixing L.S 6.00
TOTAL : 141.00
ADD FOR CONTRACTORS PROFIT 10% 14.10
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.30
LABOUR FOR 1.000 No 6.90
LABOUR PER No 6.90
MATERIAL :
LABOUR :
Labour for fixing L.S 6.00
TOTAL : 171.00
ADD FOR CONTRACTORS PROFIT 10% 171.00
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.30
LABOUR FOR 1.000 Nos 6.90
LABOUR PER Nos 6.90
14471400 Pentagonal rain water head.
230x200 mm ,80 or 100 mm dia
Details of cost for one pentagonal
rain water head.
MATERIAL :
LABOUR :
Labour for fixing L.S 6.00
TOTAL : 111.00
ADD FOR CONTRACTORS PROFIT 10% 11.10
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6.00
TOTAL : 6.00
ADD FOR CONTRACTORS PROFIT 10% : 0.60
ADD FOR OVER HEAD CHARGES @5% : 0.30
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR FOR 1.000 No 6.90
LABOUR PER No 6.90
14480000 Providing and laying four courses
water proofing treatment with
bitumen felt over roofs consisting
of first and third courses of blow
or / and residual bitumen applied
hot at 1.45 kg per sq .m of area
for each course second course of
roofing felt type 3 grade 1
(hessian base self finished bitumen
felt) and fourth and final course
of stone grit 6 mm and down size or
pea sized gravel spread at 6 cu.dm
or 0.006 cu.m) per sq.m.welding
preperation of surface excluding
grading complete
Details of cost for 30 sq.m
MATERIAL :
Residual bitumen
30x2x1.45 =87kg
or 0.87 Qtl. or 0.087 tonne 1 tonne 0.087 43940.00 3822.78
------------
Total:-33 m2 1 sqm 33.000 80.00 2640.00
CARRIAGE :
Tar Bitumen.
1 KM BY MECH. TRANSPORT 1 tonne 0.162 123.35 19.98
Steam Coal.
1 KM BY MECH. TRANSPORT 1 tonne 0.017 100.85 1.71
LABOUR :
Painter 2nd Class Each 2.160 128.33 277.19
Beldar Each 3.240 116.67 378.01
Carpenter 2nd Class Each 0.180 186.67 33.60
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 818.80
TOTAL : 818.80
WATER CHARGES @ 1.5% : 112.74
TOTAL : 931.54
ADD FOR CONTRACTORS PROFIT 10% : 93.15
ADD FOR OVER HEAD CHARGES @5% : 46.57
LABOUR FOR 30.000 sqm. 1071.26
LABOUR PER sqm. 35.70
14490000 Providing and laying six courses
water proofing treatment with
bitumen felt over roofs consisting
of first third courses of blown or
resideual bitumen applied not 1.45
kg 1.20 and 1.45 kg persq.mof area
respectively second and fourth
course of roofing felt type 3 grade
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
i (hessain bese finished bitumen
felt ) sixth and final course of
stone girt 6 mm and down size or
pea sized gravel spread at 6 cu.dm
or (0.006 cu.m) per sq.m including
preparation of surface excluding
grading complete
Details of cost for 30 sq.m
MATERIAL :
CARRIAGE :
Tar Bitumen.
1 KM BY MECH. TRANSPORT 1 tonne 0.273 123.35 33.67
Steam Coal.
1 KM BY MECH. TRANSPORT 1 tonnne 0.025 100.85 2.52
LABOUR :
Painter 2nd Class Each 3.240 128.33 415.79
Beldar Each 4.860 116.67 567.02
Carpenter 2nd Class Each 0.270 186.67 50.40
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1183.19
TOTAL : 1183.19
WATER CHARGES @ 1.5% : 182.36
TOTAL : 1365.55
ADD FOR CONTRACTORS PROFIT 10% : 136.55
ADD FOR OVER HEAD CHARGES @5% : 68.24
LABOUR FOR 30.000 sqm. 1570.37
LABOUR PER sqm. 52.35
14500000 Supplying and applying bitumenous
solution primer on roof and or wall
surface at 0.24litre per sq m
Details of cost for 10 sq m
MATERIAL :
LABOUR :
Painter 2nd Class Each 0.170 128.33 21.82
Beldar Each 0.170 116.67 19.83
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 44.16
TOTAL : 44.16
WATER CHARGES @ 1.5% : 3.74
TOTAL : 47.90
ADD FOR CONTRACTORS PROFIT 10% : 4.79
ADD FOR OVER HEAD CHARGES @5% : 2.40
LABOUR FOR 10.000 sqm. 55.09
LABOUR PER sqm. 5.50
14510000 Deduct for omitting in water
proofing treatment final course of
spreading.
MATERIAL :
CARRIAGE :
LABOUR :
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
For screening/spreading L.S 15.00
SUNDRIES : L.S 2.00
TOTAL : 56.31
ADD FOR WATER CHARGES @ 1.5% : 0.84
TOTAL : 57.15
ADD FOR CONTRACTORS PROFIT 10% 5.71
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 17.00
TOTAL : 17.00
WATER CHARGES @ 1.5% : 0.84
TOTAL : 17.84
ADD FOR CONTRACTORS PROFIT 10% : 1.78
ADD FOR OVER HEAD CHARGES @5% : 0.89
LABOUR FOR 10.000 sqm. 20.51
LABOUR PER sqm. 2.05
14510200 Stone grit 6 mm and down size or
pea sized gravel 8 cu.dm,/sq.m .
Details of cost for 10 sq.m
MATERIAL :
CARRIAGE :
LABOUR :
For screening/spreading L.S 20.00
SUNDRIES : L.S 2.50
TOTAL : 74.92
ADD FOR WATER CHARGES @ 1.5% : 1.13
TOTAL : 76.05
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR CONTRACTORS PROFIT 10% 7.60
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 22.50
TOTAL : 22.50
WATER CHARGES @ 1.5% : 1.13
TOTAL : 23.63
ADD FOR CONTRACTORS PROFIT 10% : 2.36
ADD FOR OVER HEAD CHARGES @5% : 1.18
LABOUR FOR 10.000 sqm. 27.17
LABOUR PER sqm. 2.70
14520000 Grading roof for water treatment
with
MATERIAL :
LABOUR RATE :
Labour for Heating lime concrete
and treatment with gur & bilgiri:
Mason 1st class Each 1.00 211.16 211.16
Beldar Each 6.00 116.67 700.02
Bhishti Each 0.20 16.67 3.33
Total : 3344.81
Add for water charges @1.5% Except on (-I-) : 14.01
Total : 3358.82
ADD FOR CONTRACTORS PROFIT 10% Except on (-I-) : 94.85
ADD FOR OVER HEAD CHARGES @5% Except on (-I-): 47.42
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
COST FOR 10.000 sq.m. 3501.09
COST PER sq.m. 350.10
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 934.51
Labour As per item no :0906000A 618.15
TOTAL : 1552.66
Add for water charges : 14.01
TOTAL : 1566.67
ADD FOR CONTRACTORS PROFIT 10% EXCEPT ON (-a-): 94.85
ADD FOR OVER HEAD CHARGES @5% EXCEPT ON (-a-): 47.42
LABOUR FOR 10.000 sq.m. 1708.94
LABOUR PER sq.m. 170.90
14520200 Cemant concrete 1:2:4 (1 cement :2
sand 4 graded stone aggregate 20 mm
nominal size )
Details of cost for one cu.m .
MATERIAL :
Total : 3454.10
COST FOR 1.000 cum 3454.10
COST PER cum 3454.10
LABOUR RATE :
Labour As per item no :09200300 714.00
TOTAL : 714.00
LABOUR FOR 1.000 cum 714.00
LABOUR PER cum
14520300 Cement mortar 1:3 (1 cement:3 sand)
Details of cost for on cu.m.
MATERIAL :
LABOUR :
Mason 2nd Class Each 1.00 186.67 186.67
Beldar Each 7.00 116.67 816.69
Bhishti Each 0.50 116.67 58.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1106.70
Labour for cement mortar 1:3 128.35
TOTAL : 1235.05
WATER CHARGES @ 1.5% : 64.28
TOTAL : 1300.33
ADD FOR CONTRACTORS PROFIT 10% : 130.00
ADD FOR OVER HEAD CHARGES @5% : 65.00
LABOUR FOR 1.000 cum 1495.36
LABOUR PER cum 1495.35
14520400 Cemnent mortar 1:4 (1cement L4
sand)
Details of cost for one cu.m
MATERIAL :
LABOUR :
Mason 2nd Class Each 1.00 186.67 186.67
Beldar Each 7.00 116.67 816.69
Bhisti Each 0.50 116.67 58.34
SUNDRIES : L.S 45.00
TOTAL : 3634.85
ADD FOR WATER CHARGES @ 1.5% : 54.52
TOTAL : 3689.37
ADD FOR CONTRACTORS PROFIT 10% : 368.93
ADD FOR OVER HEAD CHARGES @5% : 184.46
COST FOR 1.000 cum. 4242.76
COST PER cum. 4242.75
LABOUR PER cum. 1483.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1106.70
Labour for cement mortar 1:4 128.35
TOTAL : 1235.05
WATER CHARGES @ 1.5% : 54.52
TOTAL : 1289.57
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR CONTRACTORS PROFIT 10% : 128.95
ADD FOR OVER HEAD CHARGES @5% : 64.47
LABOUR FOR 1.000 cum. 1482.99
LABOUR PER cum. 1483.00
14530000 Providing and laying plastic
roofing compound standrad black
(using 2.75 kg per sq m) over a
surface painted with cold plastic
roofing liquid compound at 0.24
litre per sq.m including spreading
and over the top of surface at 6 cu
dm. or (0.06 cu.dm) per sq.m etc
complete.
Details of cost for 10 sqm.
MATERIAL :
CARRIAGE :
Sand
1 KM BY MECH. TRANSPORT 1 Tonne 0.06 110.95 6.66
LABOUR :
Mason 2nd Class Each 0.25 186.67 46.67
Beldar Each 0.55 116.67 64.17
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 115.82
TOTAL : 115.82
WATER CHARGES @ 1.5% : 26.35
TOTAL : 142.17
ADD FOR CONTRACTORS PROFIT 10% : 14.21
ADD FOR OVER HEAD CHARGES @5% : 7.10
LABOUR FOR 10.000 sqm. 163.48
LABOUR PER sqm. 16.40
14540000 Providing perpex sheet roofing
fixed with G.I. or J. and L
hooks,bolts and nuts 8mm.dia metre
with bitumen and G.I. limpet
washers filled with white lead
complete excluding cost of purlins,
rafters and trusses.
2 mm thick sheet.
Details of cost for 184.518 sq.m.
MATERIAL :
Purpex Sheets
1 KM BY MECH. TRANSPORT 1 tonne 1.37 73.95 101.31
LABOUR :
Black Smith 2nd Class Each 1.30 148.16 192.61
Carpenter 2nd Class Each 14.75 186.67 2753.38
Beldar Each 14.75 116.67 1720.88
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 4711.86
TOTAL : 4711.86
ADD FOR CONTRACTORS PROFIT 10% : 471.18
ADD FOR OVER HEAD CHARGES @5% : 235.59
LABOUR FOR 184.520 sq.m. 5418.63
LABOUR PER sq.m. 29.35
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
1455000000 Providing and fixing 0.60mm thick
prepainted steel sheet in roofing with
hot dipped metallic zinc coated sheet
with top coat of regular modified
polyster (RNP) organic coating of 20
microns over 5 microns primer coating
to back coat of polyster of 5 microns
over 5 microns primer coating i/c fixing
with prepainted iron J or L hooks, bolts
and nuts 6mm dia metre with
prepainted limpet and rubber washers
complete with all accesoriees as
required as per the direction of
Engineer-in-charge.
Material
Prepainted sheet 0.60mm thick
54x2.50x0.80 =108.00 sqm
54x2.80x0.80 =120.96 sqm
Total =228.96
Add. Wastage 5% = 11.45
Total =240.41 sqm Sqm 240.41000 500.00 120205.00
CARRIAGE
Prepainted sheets
Prepainted sheets
LABOUR :
Black Smith 2nd class each 1.30000 148.16 192.60
Carpenter 2nd class each 14.75000 186.67 2753.38
Beldar Each 14.75000 116.67 1720.88
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 4691.86
Material
Prepainted sheet 60cm overall
ridges or hips =10.35 Rmt.
Add. Wastage 5% = 0.52 Rmt
Total =10.87 Rmt.
CARRIAGE
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Carriage of prepainted sheet ridges or hips
LABOUR :
Black Smith 1st class each 1.04000 186.67 194.13
Carpenter 2nd class each 0.40000 211.16 84.46
Beldar Each 2.40000 116.67 280.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 568.59
1457000000
Material
Prepainted sheet 90cm overall
=9.325 Rmt.
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Add. Wastage 5% = 0.465 Rmt
Total =9.790 Rmt.
CARRIAGE
LABOUR :
Carpenter 1st class each 0.40000 211.16 84.46
Black Smith 1st class each 1.04000 186.67 194.13
Black Smith 2nd class each 1.04000 148.16 154.08
Beldar Each 2.40000 116.67 280.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 722.67
Material
Prepainted sheet flushing =12.125 Rmt.
Add 5% for wastage & laps =0.60 Rmt.
Total =12.825 Rmt.
Rmt. 12.82500 200.00 2565.00
CARRIAGE
LABOUR :
Carpenter 1st class each 0.50000 211.16 105.58
Black Smith 1st class each 1.48000 186.67 276.27
Black Smith 2nd class each 1.00000 148.16 148.16
Beldar Each 3.00000 116.67 350.01
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 890.02
Material
LABOUR :
Fitter each 0.40000 148.16 59.26
Beldar each 0.40000 116.67 46.66
Bandhani each 0.10000 116.67 11.66
Material
LABOUR :
Fitter each 0.40000 148.16 59.26
Beldar each 0.40000 116.67 46.66
Bandhani each 0.10000 116.67 11.66
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 137.58
Material
LABOUR :
Fitter each 0.40000 148.16 59.26
Beldar each 0.40000 116.67 46.66
Bandhani each 0.10000 116.67 11.66
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 137.58
Material
PVC (D-Plast) accessories for Rain
water pipes
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
PVC Plain bend Each 1.00000 240.00 240.00
TOTAL : 252.00
ADD FOR CONTRACTORS PROFIT 10% 25.20
ADD FOR OVER HEAD CHARGES @5% 12.60
COST FOR 1 No 289.80
COST PERNo 289.80
Labour Per No 5.75
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 5.00
Material
PVC (D-Plast) accessories for Rain
water pipes
PVC corner type bend Each 1.00000 240.00 240.00
TOTAL : 252.00
ADD FOR CONTRACTORS PROFIT 10% 25.20
ADD FOR OVER HEAD CHARGES @5% 12.60
COST FOR 1 No 289.80
COST PERNo 289.80
Labour Per No 5.75
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 5.00
Material
PVC (D-Plast) accessories for Rain
water pipes
PVC shoe bend Each 1.00000 125.00 125.00
TOTAL : 137.00
ADD FOR CONTRACTORS PROFIT 10% 13.70
ADD FOR OVER HEAD CHARGES @5% 6.85
COST FOR 1 No 157.55
COST PERNo 157.55
Labour Per No 5.75
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 5.00
Materials
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
B.P. sheet 1.66 mm to 2mm thick
Front facia = 1x10x0.20 =2.00 sqm.
soffit =1x10x0.45 =4.50 sqm
Total =6.50 sqm
Welding charges
Priming coat
2x6.50 =13.00 sqm
sqm 13.00000 17.15 222.95 -I-
CARRIAGE
LABOUR :
Black Smith 1st class each 0.50000 186.67 93.34
Beldar each 0.50000 116.67 58.34
Bhandhani each 0.20000 116.67 23.33
TOTAL : 6967.06
ADD FOR CONTRACTORS PROFIT 10% 674.41
ADD FOR OVER HEAD CHARGES @5% 337.20
COST FOR 6.50 sqm 7978.67
COST PER Sqm 1227.50
Labour Rate sqm. 53.70
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 195.01
Labour for priming coat on steel work 124.80 -a-
Total 319.81
ADD FOR CONTRACTORS PROFIT @10% : 19.50
ADD FOR OVER HEAD CHARGES @5% : 9.75
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR FOR 6.50 sqm 349.06
LABOUR PER Sqm 53.70
Material
Polycarbonate transparent sheet
1.20mm thick sqm. 240.40000 890.00 213956.00
CARRIAGE
Polyearbonate sheet
1 KM by Mech. Trpt. Tonne 1.37000 73.95 101.30
100 Mtrs by head Load Tonne 1.37000 57.85 79.25
LABOUR :
Black Smith 2nd class each 1.30000 148.16 192.60
Carpenter 2nd class each 14.75000 186.67 2753.38
Beldar each 14.75000 116.67 1720.88
TOTAL : 228846.81
ADD FOR CONTRACTORS PROFIT 10% 22884.68
ADD FOR OVER HEAD CHARGES @5% 11442.34
COST FOR 184.518 sqm 263173.83
COST PER Sqm 1426.25
Labour Rate sqm. 29.35
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 4711.86
Material
Cement (Ordinary )
. @ 1 kg per 80kg of bitumen L.S. 5.00
Sand
. @ 0.25 cum per 80 kg of bitumen
12.38x0.25/80 =0.040 cum 0.04000 300.00 12.00
CARRIAGE
Carriage of bitumen
Roof Covering
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
1 KM by Mech. Trpt. Tonne 0.01250 123.35 1.55
100 Mtrs by head Load Tonne 0.01250 33.08 0.41
Carriage of sand
LABOUR :
Black Smith 2nd class each 0.40000 148.16 59.26
Carpenter 2nd class each 0.40000 186.67 74.66
Beldar each 1.00000 116.67 116.67
TOTAL : 2145.49
Add. For water charges @ 1.5% 32.18
Total 2177.67
ADD FOR CONTRACTORS PROFIT 10% 217.76
ADD FOR OVER HEAD CHARGES @5% 108.88
COST FOR 4.50 sqm 2504.32
COST PER Sqm 556.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 260.59
Add. For water charges @ 1.5% 32.18
Total 292.77
ADD FOR CONTRACTORS PROFIT @10% : 29.27
ADD FOR OVER HEAD CHARGES @5% : 14.63
LABOUR FOR 4.50 sqm 336.68
LABOUR PER Sqm 74.80
Confidential
For Office use
VOLUME - V
ANALYSIS FOR SCHEDULE OF RATES 2009
(VOLUME V)
CONTENTS
Chapter No. Name of Sub-head Page No.
XV Steel Work
XVI Painting and Polishing
CHAPTER XV
STEEL WORK
CHAPTER XV
STEEL WORK
Notes :
1. The through rates include the carriage of steel for a distance of 100 meters on head load
and one kilometer by mechanical transport, All other lead shall be paid separately
depending upon the location of the site of work. The labor rates include the cost on
account of water.
2. The through rates include the wastage of steel during fabrication.
3. The rated for hoisting take into account the element of labor cost only . The rates are
exclusive of the cost of temporary structures, arrangements for providing counter weight
or launching truss / nose and of hire charges of machinery etc. If actually required for
hoisting wherever such like items are required, additional rates shall be paid on the merits
of the individual case. For temporary structures, credit will be afforded for the salvaged
materials . The most economical procedure for hoisting as warranted according to site
condition shall be worked out by the Engineer-in Charge.
CHAPTER-XV
Steel Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
In R.S.Joists,channels
1501010000 angles,tees
MATERIAL :
R.S.Joist.
Detail of cost for R.S.Joist
300x140mm @ 44.2 kg/Metre
6.0m.x44.2kg = 265.20 kg.
Add 5% wastage= 13.00 kg
--
Total: 278.20 kg.
or 2.78 Qtls.
CARRIAGE :
Steel
1 KM BY MECH. TRANSPORT 1 tonne 0.27800 73.95 20.53
LABOUR RATE:
Black Smith 2nd Class each 0.60000 148.16 88.90
Bandhani each 1.20000 116.67 140.00
Beldar each 3.30000 116.67 385.01
Fitter each 0.60000 148.16 88.90
Total : 13389.49
Steel Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Add for water charges @1.5%
Except on (-I-) : 199.04
Total : 13588.53
ADD FOR CONTRACTORS
PROFIT @10% Except on (-I-) 1346.84
LABOUR :
ACTUAL LABOUR+SUNDRIES 722.81
MATERIAL :
CARRIAGE :
Steel
1 KM BY MECH. TRANSPORT 1 tonne 0.105000 73.95 7.76
Steel Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE:
Fitter each 0.60000 148.16 88.90
Black Smith 2nd Class each 0.60000 148.16 88.90
Beldar each 1.20000 116.67 140.00
Total : 5123.08
Add for water charges @1.5%
Except on (-I-) : 76.07
Total : 5199.15
ADD FOR CONTRACTORS
PROFIT @10% Except on (-I-) 514.77
LABOUR :
ACTUAL LABOUR+SUNDRIES 332.80
MATERIAL :
CARRIAGE :
Steel
1 KM BY MECH. TRANSPORT 1 tonne 0.99700 73.95 73.72
Steel Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE:
Fitter each 12.76000 148.16 1890.52
Black Smith 2nd Class each 6.38000 148.16 945.26
Beldar each 12.76000 116.67 1488.70
Total : 50063.33
Add for water charges @1.5%
Except on (-I-) : 745.45
Total : 50808.78
ADD FOR CONTRACTORS
PROFIT @10% Except on (-I-) 5044.21
LABOUR Rate :
ACTUAL LABOUR+SUNDRIES 4364.48
Splices.
300x200x20 mm @10 kg.
2x10kg =20.00kg.
150x150x10 mm@2 kg.
2x2kg =4.00 kg.
--
Total =24.00 kg.
Wastage @ 5% =1.20 kg.
---
Total =25.20 kg.
or 0.252 quintal
1 qtl 0.25200 4500.00 1134.00
=46.20 nos.
46.20Nos. @ 1.24 kg. per 10
rivets
=5.7 kg. or 0.057 quintal.
1 qtl 0.05700 5200.00 296.40
CARRIAGE :
Steel
1 KM BY MECH. TRANSPORT 1 tonne 0.32000 73.95 23.66
LABOUR RATE:
Black Smith 2nd Class each 4.10000 148.16 607.45
Steel Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Fitter each 4.10000 148.16 607.45
Beldar each 2.05000 116.67 239.17
Total : 16159.92
Add for water charges @1.5%
Except on (-I-) : 240.28
Total : 16500.20
ADD FOR CONTRACTORS
PROFIT @10% Except on (-I-) 1635.87
LABOUR :
ACTUAL LABOUR+SUNDRIES 1504.07
MATERIAL :
Angles stiffoners.
90x60x8 mm @ 8.9 kg.
6x3x8.275x8.9kg =44.00 kg.
Wastage 5% =2.20 kg.
Edge angle.
60x60x6 mm x6.84 kg.
2x2.385x6.84 kg =32.6 kgs.
Wastage 5% =1.63 kgs.
-
Total =34.23 kgs.
or 0.342 quintal.
1 qtl 0.34200 4500.00 1539.00
CARRIAGE :
Steel
1 KM BY MECH. TRANSPORT 1 tonne 0.81300 73.95 61.38
LABOUR RATE:
Black Smith 2nd Class each 15.61000 148.16 2312.78
Fitter each 15.61000 148.16 2312.78
Beldar each 15.61000 116.67 1821.21
LABOUR RATE:
ACTUAL LABOUR+SUNDRIES 6496.77
TOTAL : 6496.77
WATER CHARGES @ 1.5% : 649.64
TOTAL : 7145.81
ADD FOR CONTRACTORS
PROFIT @10% : 714.58
ADD FOR OVER HEAD
CHARGES @5% : 357.29
LABOUR FOR 7.750 Qtls 8217.68
LABOUR PER Qtls 1060.35
1502040000 In grating,Framed guards,
bars,ledders railings,brackets &
similar works.
Details of cost for 0.223 qtl.
MATERIAL :
12 mm dia bars
9x1 =9.0 m @ 0.89kg/Mtr.=8.01
kgs
Wastage @ 5% =0.40 kg.
CARRIAGE :
Steel
1 KM BY MECH. TRANSPORT 1 tonne 0.02300 73.95 1.70
LABOUR RATE:
Fitter each 0.67000 148.16 99.26
Black Smith 1st Class each 0.27000 186.67 50.40
Black Smith 2nd Class each 0.67000 148.16 99.26
Beldar Each 0.74000 116.67 86.33
Total : 1438.28
Add for water charges @1.5%
Except on (-I-) : 21.41
Total : 1459.69
ADD FOR CONTRACTORS
PROFIT @10% Except on (-I-) 144.93
Steel Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR :
ACTUAL LABOUR+SUNDRIES 385.25
MATERIAL :
Rivets 10 mm =8 nos.
=0.25 kg.or 0.0025qtl.
CARRIAGE :
Steel
1 KM BY MECH. TRANSPORT 1 tonne 0.08344 73.95 6.17
LABOUR RATE:
Black Smith 2nd Class each 0.98000 148.16 145.20
Fitter Each 0.20000 148.16 29.63
Beldar EACH 0.12000 116.67 14.00
Total : 4076.09
Add for water charges @1.5%
Except on (-I-) : 60.50
Total : 4136.59
ADD FOR CONTRACTORS
PROFIT @10% Except on (-I-) 409.37
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 138.83
MATERIAL :
Ties (flats).
50x12 mm @ 4.70 kg/m
2x2.7m =5.4 m @ 4.7
kg/m=25.38kgs
----------
Ties central (flats)
50x10 mm @ 3.90 kg/m.
1x2.28m =2.8m @ 3.90kg/m
=10.92kgs
Braces (Flats)
50x10 mm @ 3.90 kg/m
2x1.84m =3.68 m@ 3.90
kg/m=14.36kg
--
Total: 50.66 kgs.
Wastage @ 5% = 2.53 kgs.
-----
Total : 53.19 kgs.
or 0.53 qtl.
CARRIAGE :
Steel
1 KM BY MECH. TRANSPORT 1 TONNE 0.41500 73.95 30.68
LABOUR RATE:
Fitter EACH 13.28000 148.16 1967.56
Black Smith 1st Class EACH 15.31000 186.67 991.22
Black Smith 2nd Class EACH 13.28000 148.16 1967.56
Beldar EACH 14.65000 116.67 1709.21
Total : 26078.24
Add for water charges @1.5%
Except on (-I-) : 389.71
Total : 26467.95
ADD FOR CONTRACTORS
PROFIT @10% Except on (-I-) 2637.05
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 7160.39
MATERIAL :
Principal Rafters(T-Iron)
100x100x10 mm @ 15 Kg /Metre
2x4.75 m = 9.50 Mtr
@ 15 Kg /Mtr=142.50 Kg
Struts (Angles)
40 x 40 x 6 mm
@ 3.50 Kg /Mtr
2 x 1.35 m =2.70m
@ 3.50 Kg/m=9.45 Kg
------------
Total =151.95 Kg
Add wastage @ 5% = 7.60 Kg
------------
Total = 159.55 Kg
or=1.60 Qtl
1 qtl 1.60000 4500.00 7200.00
Ties (Flats)
50 x 12 mm @ 4.70 Kg/mtr
2x2.70 m=5.40 @4.70 Kg/M=
25.38 Kg
Central tie (Flat)
50x10mm @ 3.90 Kg/Mtr
1x2.28m @ 3.90 Kg/Mtr =10.92
Kg
Braces(Flat)
50x10mm @3.90 Kg/Mtr
2x1.84m = 3.68 @ 3.90Kg=14.36
Kg
Steel Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Total =50.66 Kg
Add wastage @ 5% =2.53 Kg
Total =53.19 Kg
=0.53 Qtl
=1.104 sqm.
1.104 sq.m @ 78.4
kg./sqm=86.55kgs
12 mm plates at the joint of
principal rafter and strut
2x0.3mx0.2m =0.12 sqm.
Tie beam.braces and strut
2x0.5mx0.3m =0.30 sq.m.
Sole plates.
2x0.46mx0.46m =0.42 sq.m.
Ancher plates
2x0.46mx0.10m =0.09 sq.m.
-
Total: =0.93 sq.m.
Say 1.00 sq.m.
1.00 sq.m. @ 94.4
kg./sqm=94.40kgs
-
Total: =180.05kgs
wastage @ 5% =9.05kgs
---------
Total: =190.00 kgs.
or 1.90 qtl.
1 QTL 1.90000 4500.00 8550.00
CARRIAGE :
Steel
1 KM BY MECH. TRANSPORT 1 TONNE 0.41500 73.95 30.68
LABOUR RATE:
Fitter EACH 13.28000 148.16 1967.56
Black Smith 1st Class EACH 5.31000 186.67 991.21
Black Smith 2nd Class EACH 13.28000 148.16 1967.56
Beldar EACH 14.65000 116.67 1709.21
Total : 26554.48
Add for water charges @1.5%
Except on (-I-) : 396.85
Total : 26951.33
ADD FOR CONTRACTORS
PROFIT @10% Except on (-I-) 2685.34
LABOUR :
ACTUAL LABOUR+SUNDRIES 7636.63
MATERIAL :
Principal Rafters(T-Iron)
100x100x10 mm @ 15 Kg /Metre
2x4.75 m = 9.50 Mtr
@ 15 Kg /Mtr=142.50 Kg
Struts (Angles)
40 x 40 x 6 mm
@ 3.50 Kg /Mtr
2 x 1.35 m =2.70m
@ 3.50 Kg/m=9.45 Kg
------------
Total =151.95 Kg
Ties (Flats)
50 x 12 mm @ 4.70 Kg/mtr
Steel Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
2x2.70 m=5.40 @4.70 Kg/M=
25.38 Kg
Central tie (Flat)
50x10mm @ 3.90 Kg/Mtr
1x2.28m @ 3.90 Kg/Mtr =10.92
Kg
Braces(Flat)
50x10mm @3.90 Kg/Mtr
2x1.84m = 3.68 @ 3.90Kg=14.36
Kg
Total =50.66 Kg
Add wastage @ 5% =2.53 Kg
Total =53.19 Kg
=0.53 Qtl
=1.104 sqm.
1.104 sq.m @ 78.4
kg./sqm=86.55kgs
12 mm plates at the joint of
principal rafter and strut
2x0.3mx0.2m =0.12 sqm.
Tie beam.braces and strut
2x0.5mx0.3m =0.30 sq.m.
Sole plates.
2x0.46mx0.46m =0.42 sq.m.
Ancher plates
2x0.46mx0.10m =0.09 sq.m.
-
Total: =0.93 sq.m.
Say 1.00 sq.m.
1.00 sq.m. @ 94.4
kg./sqm=94.40kgs
-
Total: =180.05kgs
wastage @ 5% =9.05kgs
---------
Total: =190.00 kgs.
or 1.90 qtl.
1 Qtl 1.90000 4500.00 8550.00
CARRIAGE :
Steel
1 KM BY MECH. TRANSPORT 1 Tonne 0.41500 73.95 30.68
LABOUR RATE:
Fitter Each 13.28000 148.16 1967.56
Black Smith 1st Class Each 5.31000 186.67 991.21
Black Smith 2nd Class Each 13.28000 148.16 1967.56
Beldar Each 14.65000 116.67 1709.21
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 8112.41
LABOUR RATE:
Labour as per item no. :
1502070200 Qtl 2493.25
LABOUR RATE:
Beldar Each 0.50400 116.67 58.80
TOTAL : 58.80
ADD FOR CONTRACTORS
PROFIT @10% : 5.88
ADD FOR OVER HEAD
CHARGES @5% : 2.94
COST COST FOR 1.000 Qtl 67.62
RATERATE PER Qtl. 67.60
LABOUR PER Qtl 67.60
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 58.80
TOTAL : 58.80
ADD FOR CONTRACTORS
PROFIT @10% : 5.88
ADD FOR OVER HEAD
CHARGES @5% : 2.94
LABOUR FOR 1.000 Qtl 67.62
LABOUR PER Qtl 67.60
150207030B B.)Hoisting trusses and trussed
purlins in building.
LABOUR RATE:
Beldar Each 1.03200 116.67 120.40
TOTAL : 120.40
ADD FOR CONTRACTORS
PROFIT @10% : 12.04
ADD FOR OVER HEAD
CHARGES @5% : 6.02
COSTCOST FOR 1.000 Qtl 138.46
RATERATE PER Qtl. 138.45
LABOUR PER Qtl 138.45
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 120.40
TOTAL : 120.40
ADD FOR CONTRACTORS
PROFIT @10% : 12.04
Steel Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR OVER HEAD
CHARGES @5% : 6.02
LABOUR FOR 1.000 Qtl 138.45
LABOUR PER Qtl 138.45
LABOUR RATE:
Beldar Each 2.06400 116.67 240.80
TOTAL : 240.80
ADD FOR CONTRACTORS
PROFIT @10% : 24.08
ADD FOR OVER HEAD
CHARGES @5% : 12.04
COSTCOST FOR 1.000 Qtl 276.92
RATERATE PER Qtl. 276.90
LABOUR PER Qtl 276.90
LABOUR :
ACTUAL LABOUR+SUNDRIES 240.80
TOTAL : 240.80
ADD FOR CONTRACTORS
PROFIT @10% : 24.08
ADD FOR OVER HEAD
CHARGES @5% : 12.04
LABOUR FOR 1.000 Qtl 276.92
LABOUR PER Qtl 276.90
D.)Hoisting trussed steeel
150207030D bridges beyond 15 mtr. but upto 30 mtr. span.
LABOUR RATE:
Beldar Each 3.09600 116.67 361.21
TOTAL : 361.21
ADD FOR CONTRACTORS
PROFIT @10% : 36.12
ADD FOR OVER HEAD
CHARGES @5% : 18.06
COST FOR 1.000 Qtl 415.39
RATE PER Qtl. 415.40
LABOUR PER Qtl 415.40
LABOUR :
ACTUAL LABOUR+SUNDRIES 361.21
TOTAL : 361.21
Steel Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR CONTRACTORS
PROFIT @10% : 36.12
ADD FOR OVER HEAD
CHARGES @5% : 18.06
LABOUR FOR 1.000 Qtl 415.39
LABOUR PER Qtl 415.40
MATERIAL :
R.S.joist
Plates
CARRIAGE :
Steel
1 KM BY MECH. TRANSPORT TONNE 1.00500 73.95 74.30
LABOUR RATE:
Fitter Each 12.76000 148.16 1890.52
Black Smith 2nd Class Each 6.38000 148.16 945.26
Beldar Each 22.76000 116.67 1488.70
Total : 50936.00
Add for water charges @1.5%
Except on (-I-) : 758.55
Total : 51694.55
ADD FOR CONTRACTORS
PROFIT @10% Except on (-I-) : 5132.92
LABOUR :
ACTUAL LABOUR+SUNDRIES 4369.48
MATERIAL :
R.S.joists
Cap plats
Base plate
same as pr item no.1502020000
=29.40 kg. or 0.294 qtl.
1 QTL 0.29400 4500.00 1323.00
Splices
same as per item no
1502020000=25.20 kg. or 0.25
qtl.
CARRIAGE :
Steel
1 KM BY MECH. TRANSPORT 1 TONNE 0.32100 73.95 23.73
LABOUR RATE:
Black Smith 2nd Class Each 4.10000 148.16 607.45
Fitter Each 4.10000 148.16 607.45
Beldar Each 2.05000 116.67 239.17
Total : 15741.12
Add for water charges @1.5%
Except on (-I-) : 234.00
Total : 15975.12
ADD FOR CONTRACTORS
PROFIT @10% Except on (-I-) 1583.36
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1504.07
Steel Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
Joists
Angle stiffeners
Edge angle
CARRIAGE :
Steel
1 KM BY MECH. TRANSPORT 1 TONNE 0.81400 73.95 60.20
LABOUR RATE:
Black Smith 2nd Class Each 15.61000 148.16 2312.77
Fitter Each 15.61000 148.16 2312.78
Beldar Each 15.61000 116.67 1821.21
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 6496.76
TOTAL : 6496.76
WATER CHARGES @ 1.5% : 500.42
TOTAL : 6997.18
Steel Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR CONTRACTORS
PROFIT @10% : 699.71
ADD FOR OVER HEAD
CHARGES @5% : 349.85
LABOUR FOR 7.750 QTL 8046.74
LABOUR PER Qtl 1038.30
1503040000 In gratings, Framed guards, bars
ladders railings brackets and
similar works.
MATERIAL :
M.S.Flats
same as in item no.1502040000
=14.50 kg.or 0.145 qtl.
1 QTL 0.14500 4500.00 652.50
12 mm dia bars
same as in item no.1502040000
=840
kg. or 0.084 qtl.
1 QTL. 0.08400 4300.00 361.20
CARRIAGE :
Steel
1 KM BY MECH. TRANSPORT 1 TONNE 0.02300 73.95 1.70
LABOUR RATE:
Fitter Each 0.67000 148.16 99.26
Black Smith 1st Class Each 0.27000 186.67 50.40
Black Smith 2nd Class Each 0.67000 148.16 99.26
Steel Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Beldar Each 0.74000 111.67 86.34
Total : 1447.21
Add for water charges @1.5%
Except on (-I-) : 21.55
Total : 1468.76
ADD FOR CONTRACTORS
PROFIT @10% Except on (-I-) 145.84
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 385.26
MATERIAL :
CARRIAGE :
Steel
1 KM BY MECH. TRANSPORT 1 tonne 0.08344 73.95 6.17
LABOUR RATE:
Black Smith 2nd Class Each 0.98000 148.16 145.20
Fitter Each 0.20000 148.16 29.63
Beldar Each 0.12000 116.67 14.00
Total : 4090.56
Add for water charges @1.5%
Except on (-I-) : 60.71
Total : 4151.27
ADD FOR CONTRACTORS
PROFIT @10% Except on (-I-) -A-
): 410.83
ADD FOR OVER HEAD
CHARGES @5% Except on (-I-)
A-): 205.41
COST FOR 0.796 QTL 4767.51
RATE PER Qtl. 5989.30
LABOUR RATE:
ACTUAL LABOUR+SUNDRIES 238.83
MATERIAL :
Ties (flats)
same as per in item
no.1502060000
=0.53 qtl.
1 QTL. 0.53000 4500.00 2385.00
Gusset plates
same as per item 1502060000
=1.90qtl.
1 QTL. 1.90000 4500.00 8550.00
CARRIAGE :
Steel
1 KM BY MECH. TRANSPORT 1 TONNE 0.42200 73.95 31.20
LABOUR RATE:
Fitter EACH 6.64000 148.16 983.78
Total : 24267.12
Add for water charges @1.5%
Except on (-I-) : 362.55
Total : 24629.67
ADD FOR CONTRACTORS
PROFIT @10% Except on (-I-) 2453.22
LABOUR RATE:
ACTUAL LABOUR+SUNDRIES 4997.34
Steel Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
Ties (flats)
same as per in item
no.1502060000
=0.53 qtl.
1 QTL. 0.53000 4500.00 2385.00
Gusset plates
same as per item 1502060000
=1.90qtl.
CARRIAGE :
Steel
1 KM BY MECH. TRANSPORT 1 TONNE 0.42200 73.95 31.20
LABOUR RATE:
Fitter EACH 6.64000 148.16 983.78
Black Smith 1st Class EACH 3.69000 186.67 688.81
Black Smith 2nd Class EACH 9.22000 148.16 1366.03
Beldar EACH 2.21000 116.67 1424.54
Total : 24805.96
Add for water charges @1.5%
Except on (-I-) : 370.62
Total : 25176.60
ADD FOR CONTRACTORS
PROFIT @10% Except on (-I-) 2507.91
MATERIAL :
Ties (flats)
same as per in item
no.1502060000
=0.53 qtl.
1 QTL. 0.53000 4500.00 2385.00
Gusset plates
same as per item 1502060000
=1.90qtl.
1 QTL. 1.90000 4500.00 8550.00
CARRIAGE :
Steel
1 KM BY MECH. TRANSPORT 1 TONNE 0.42200 73.95 31.20
LABOUR RATE:
Fitter EACH 6.64000 148.16 983.78
Black Smith 1st Class EACH 3.69000 186.67 688.81
Black Smith 2nd Class EACH 9.22000 148.16 1366.03
Beldar EACH 12.21000 116.67 1424.54
Total : 25290.16
Add for water charges @1.5%
Except on (-I-) : 377.89
Total : 25668.05
ADD FOR CONTRACTORS
PROFIT @10% Except on (-I-) 2557.06
LABOUR :
ACTUAL LABOUR+SUNDRIES 5965.70
Steel Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE:
Labour as per item no. :
1503070200 Qtl 1828.25
LABOUR RATE:
Beldar Each 0.50400 116.67 58.80
TOTAL : 58.80
Steel Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR CONTRACTORS
PROFIT @10% : 5.88
ADD FOR OVER HEAD
CHARGES @5% : 2.94
COST FOR 1.000 Qtl 67.62
RATE PER Qtl. 67.60
LABOUR PER Qtl 67.60
LABOUR RATE:
ACTUAL LABOUR+SUNDRIES 58.80
TOTAL : 58.80
ADD FOR CONTRACTORS
PROFIT @10% : 5.88
ADD FOR OVER HEAD
CHARGES @5% : 2.94
LABOUR FOR 1.000 qtl 67.62
LABOUR PER Qtl 67.60
150307030B B.)Hoisting trusses and trussed
purlins in building.
Detail of cost PER QTL.
LABOUR RATE:
Beldar Each 1.03200 116.67 120.40
TOTAL : 120.40
ADD FOR CONTRACTORS
PROFIT @10% : 12.04
ADD FOR OVER HEAD
CHARGES @5% : 12.04
COST FOR 1.000 Qtl 6.02
RATE PER Qtl. 138.46
LABOUR PER Qtl 138.45
138.45
LABOUR :
ACTUAL LABOUR+SUNDRIES 120.40
TOTAL : 120.40
ADD FOR CONTRACTORS
PROFIT @10% : 12.04
ADD FOR OVER HEAD
CHARGES @5% : 6.02
LABOUR FOR 1.000 Qtl 138.46
LABOUR PER Qtl 138.45
TOTAL : 240.80
ADD FOR CONTRACTORS
PROFIT @10% : 24.08
ADD FOR OVER HEAD
CHARGES @5% : 12.04
COST FOR 1.000 Qtl 276.92
RATE PER Qtl. 276.92
LABOUR PER Qtl 276.90
LABOUR :
ACTUAL LABOUR+SUNDRIES 240.80
TOTAL : 240.80
ADD FOR CONTRACTORS
PROFIT @10% : 24.08
ADD FOR OVER HEAD
CHARGES @5% : 12.04
LABOUR FOR 1.000 Qtl 276.92
LABOUR PER Qtl 276.90
D.)Hoisting trussed steeel
bridges.(beyond 15meters but
150307030D upto 30 meters span)
Detail of cost PER QTL.
LABOUR RATE:
Beldar Each 3.09600 116.67 361.21
TOTAL : 361.21
ADD FOR CONTRACTORS
PROFIT @10% : 36.12
ADD FOR OVER HEAD
CHARGES @5% : 18.06
COST FOR 1.000 Qtl 415.39
RATE PER Qtl. 415.40
LABOUR PER Qtl 415.40
LABOUR RATE:
ACTUAL LABOUR+SUNDRIES 361.21
TOTAL : 361.21
ADD FOR CONTRACTORS
PROFIT @10% : 36.12
ADD FOR OVER HEAD
CHARGES @5% : 18.06
LABOUR FOR 1.000 qtl 415.39
LABOUR PER Qtl 415.40
Steel Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Reduction in stiffening trusses(I
.e. C-A) : 209.30
1504000000 Steel work welded in built up
sections,trusses and framed
work,including cutting ,hoisting
,fixing in position and applying a
priming coat of red lead paint.
MATERIAL :
R.S.joists
Plates
same as per item no.150201
=593.5
kg. .or. 5.935 qtl
1 QTL. 5.93500 4500.00 26707.50
Priming coat
CARRIAGE :
Steel
1 KM BY MECH. TRANSPORT 1 TONNE 0.95000 73.95 70.25
LABOUR RATE:
Black Smith 1st Class EACH 3.00000 186.67 560.01
Bandhani EACH 3.00000 116.67 350.01
Beldar EACH 7.00000 116.67 816.69
Total : 55087.21
Add for water charges @1.5%
Except on (-I-) : 820.82
Total : 55908.03
ADD FOR CONTRACTORS
PROFIT @10% Except on (-I-) 5554.27
LABOUR :
ACTUAL LABOUR+SUNDRIES 1756.71
R.S.joists
Cap plate.
same as per item no.1502020000
=6.8
kg.or 0.068 qtl.
1 QTL. 0.06800 4500.00 306.00
Base plate.
400x400x20 mm
Splices
CARRIAGE :
Steel
1 KM BY MECH. TRANSPORT 1 TONNE 0.31400 73.95 23.22
LABOUR RATE:
Black Smith 2nd Class EACH 1.50000 148.16 222.24
Beldar EACH 2.00000 116.67 233.34
Bandhani EACH 1.00000 116.67 116.67
Total : 15700.92
Add for water charges @1.5%
Except on (-I-) : 233.40
Total : 15934.32
ADD FOR CONTRACTORS
PROFIT @10% Except on (-I-) 1579.28
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 622.25
MATERIAL :
Angles stiffeners.
CARRIAGE :
Steel
1 KM BY MECH. TRANSPORT 1 TONNE 0.81100 73.95 59.97
LABOUR RATE:
Black Smith 1st Class EACH 1.00000 186.67 186.67
Beldar EACH 2.00000 116.67 233.34
Bandhani EACH 0.50000 116.67 58.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 528.35
TOTAL : 528.35
WATER CHARGES @ 1.5% : 567.81
TOTAL : 1096.16
ADD FOR CONTRACTORS
PROFIT @10% : 109.61
ADD FOR OVER HEAD
CHARGES @5% : 54.80
LABOUR FOR 7.726 QTL. 1260.57
LABOUR PER Qtl. 163.15
1504040000 In gratings framed guard
bars,ladders,railling,brackets and
similar works.
Details of cost for 0.218 qtl.
Consider 1m X 1m framed guard
bars
gratings.
MATERIAL :
M.S.Flat.
12 mm dia bars
CARRIAGE :
Steel
1 KM BY MECH. TRANSPORT 1 TONNE 0.02290 73.95 1.70
LABOUR RATE:
Black smith 1st class EACH 0.70000 186.67 0.00
Beldar EACH 0.50000 116.67 0.00
Bandhani EACH 0.25000 116.67 14.80
Total : 1415.18
Add for water charges @1.5%
Except on (-I-) : 21.07
Total : 1436.25
ADD FOR CONTRACTORS
PROFIT @10% Except on (-I-) 142.59
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 168.16
MATERIAL :
CARRIAGE :
Steel
1 KM BY MECH. TRANSPORT 1 TONNE 0.08320 73.95 6.15
LABOUR RATE:
Black Smith 1st Class EACH 0.20000 186.67 37.33
Beldar EACH 0.20000 116.67 23.33
Bandhani EACH 0.06000 116.67 7.00
Total : 4121.89
Add for water charges @1.5%
Except on (-I-) : 61.18
Total : 4183.07
ADD FOR CONTRACTORS
PROFIT @10% Except on (-I-) 414.02
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 117.66
MATERIAL :
Gusset plates.
Priming coat
same as in item no 1502060000
1 SQ.M 5.68000 17.15 97.41 (-I-)
CARRIAGE :
Steel
1 KM BY MECH. TRANSPORT 1 TONNE 0.40800 73.95 30.17
LABOUR RATE:
Black Smith 1st Class EACH 1.50000 186.67 280.00
Beldar EACH 3.50000 116.67 408.34
Bandhani EACH 0.75000 116.67 87.50
Total : 22054.95
Add for water charges @1.5%
Except on (-I-) : 329.36
Total : 22384.31
ADD FOR CONTRACTORS
PROFIT @10% Except on (-I-) 2228.68
Steel Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE:
ACTUAL LABOUR+SUNDRIES 1293.69
MATERIAL :
Ties (flates)
Gusset plates.
Priming coat
same as in item no 1502060000
1 SQ.M 5.68000 17.15 97.41 (-I-)
CARRIAGE :
Steel
1 KM BY MECH. TRANSPORT 1 TONNE 0.40800 73.95 30.17
LABOUR RATE:
Black Smith 1st Class EACH 1.50000 186.67 280.00
Beldar EACH 5.50000 116.67 641.68
Bandhani EACH 0.75000 116.67 87.50
Total : 22759.63
Add for water charges @1.5%
Except on (-I-) : 339.93
Total : 23099.56
ADD FOR CONTRACTORS
PROFIT @10% Except on (-I-) 2300.21
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1998.37
MATERIAL :
Ties (flates)
Gusset plates.
Priming coat
same as in item no 1502060000
1 SQ.M 5.68000 17.15 97.41 (-I-)
CARRIAGE :
Steel
1 KM BY MECH. TRANSPORT 1 TONNE 0.40800 73.95 30.17
LABOUR RATE:
Black Smith 1st Class EACH 1.50000 186.67 280.00
Beldar EACH 5.50000 116.67 641.68
Bandhani EACH 0.75000 116.67 87.50
Total : 23225.49
Add for water charges @1.5%
Except on (-I-) : 346.92
Total : 23572.41
ADD FOR CONTRACTORS
PROFIT @10% Except on (-I-) 2347.49
LABOUR :
ACTUAL LABOUR+SUNDRIES 2464.23
LABOUR RATE:
Steel Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Labour as per item no. :
1504070200 Qtl 845.05
LABOUR RATE:
Beldar Each 0.50400 116.67 58.80
TOTAL : 58.50
ADD FOR CONTRACTORS
PROFIT @10% : 5.88
ADD FOR OVER HEAD
CHARGES @5% : 2.94
COST FOR 1.000 Qtl 67.62
RATE PER Qtl. 67.60
LABOUR PER Qtl 67.60
LABOUR :
ACTUAL LABOUR+SUNDRIES 58.80
TOTAL : 58.50
ADD FOR CONTRACTORS
PROFIT @10% : 5.88
ADD FOR OVER HEAD
CHARGES @5% : 2.94
LABOUR FOR 1.000 Qtl 67.62
LABOUR PER Qtl 67.60
150407030B B.)Hoisting trusses and trussed
purlins in building.
Detail of cost PER QTL.
LABOUR RATE:
Beldar Each 1.03200 116.67 120.40
TOTAL : 120.40
ADD FOR CONTRACTORS
PROFIT @10% : 12.04
Steel Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR OVER HEAD
CHARGES @5% : 6.02
COST FOR 1.000 Qtl 138.46
RATE PER Qtl. 138.45
LABOUR PER Qtl 138.45
LABOUR :
ACTUAL LABOUR+SUNDRIES 120.40
TOTAL : 120.40
ADD FOR CONTRACTORS
PROFIT @10% : 12.04
ADD FOR OVER HEAD
CHARGES @5% : 6.02
LABOUR FOR 1.000 Qtl 138.46
LABOUR PER Qtl 138.45
LABOUR RATE:
Beldar Each 2.064000 116.67 240.80
TOTAL : 240.80
ADD FOR CONTRACTORS
PROFIT @10% : 27.08
ADD FOR OVER HEAD
CHARGES @5% : 12.04
COST FOR 1.000 Qtl 276.92
RATE PER Qtl. 276.90
LABOUR PER Qtl 276.90
LABOUR :
ACTUAL LABOUR+SUNDRIES 240.80
TOTAL : 240.80
ADD FOR CONTRACTORS
PROFIT @10% : 24.08
ADD FOR OVER HEAD
CHARGES @5% : 12.04
LABOUR FOR 1.000 Qtl 276.92
LABOUR PER Qtl 276.90
D.)Hoisting trussed steeel
bridges.(Beyond span 15mtr. But
150407030D upto 30mtrs span)
Detail of Cost PER QTL.
LABOUR RATE:
Beldar Each 3.09600 116.67 361.20
Steel Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 361.20
ADD FOR CONTRACTORS
PROFIT @10% : 36.12
ADD FOR OVER HEAD
CHARGES @5% : 18.06
COST FOR 1.000 Qtl 415.38
RATE PER Qtl. 415.40
LABOUR PER Qtl 415.40
LABOUR :
ACTUAL LABOUR+SUNDRIES 361.20
TOTAL : 361.20
ADD FOR CONTRACTORS
PROFIT @10% : 36.12
ADD FOR OVER HEAD
CHARGES @5% : 18.06
LABOUR FOR 1.000 Qtl 415.38
LABOUR PER Qtl 415.40
Reduction in stiffening trusses(I
.e. C-A) : (276.90-67.60) 209.30
1505010000 Profile-A
Detail of cost for 5 metres.
MATERIAL :
LABOUR RATE:
Fitter Each 0.15000 148.16 22.22
Beldar Each 0.20000 116.67 23.33
12.00
SUNDRIES : L.S
TOTAL : 1010.45
ADD FOR CONTRACTORS
PROFIT 10% 101.04
LABOUR :
ACTUAL LABOUR+SUNDRIES 57.55
TOTAL : 57.55
ADD FOR CONTRACTORS
PROFIT @10% : 5.75
ADD FOR OVER HEAD
CHARGES @5% : 2.87
LABOUR FOR 5.000 Metre 66.17
LABOUR PER Metre 13.25
1505020000 PROFILE -B
Detail of cost for 5 metre.
MATERIAL :
LABOUR RATE:
Fitter Each 0.15000 148.16 22.22
Beldar Each 0.20000 116.67 23.33
LABOUR :
ACTUAL LABOUR+SUNDRIES 60.55
TOTAL : 60.55
ADD FOR CONTRACTORS
PROFIT @10% : 6.05
ADD FOR OVER HEAD
CHARGES @5% : 3.02
LABOUR FOR 5.000 Metre 69.62
LABOUR PER Metre 13.90
1505030000 PROFILE -C
Detail of cost for 5 metres.
MATERIAL :
LABOUR RATE:
Fitter Each 0.15000 148.16 22.22
Beldar Each 0.20000 116.67 23.33
Steel Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
SUNDRIES : L.S 15.00
TOTAL : 1180.10
ADD FOR CONTRACTORS
PROFIT 10% 118.01
LABOUR :
ACTUAL LABOUR+SUNDRIES 60.55
TOTAL : 60.55
ADD FOR CONTRACTORS
PROFIT @10% : 6.05
ADD FOR OVER HEAD
CHARGES @5% : 3.02
LABOUR FOR 5.000 Metre 69.62
LABOUR PER Metre 13.90
1506000000 Providing and fixing angle iron
door,window,clerestory window
frame
manufactured from steel iron
section of 40X40X6
mm,thickness
including hinges jamb,lock
jamb,beed and if required angle
thrashold ofmild steel angle
50X25
mm welded or rigidly fixed by
MATERIAL :
Steel Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Size of frame 2+2+1 =5 mtrs.
Weight of angle iron =5x3.50
=17.50kg
Wastage 5% =0.88
-----------------------------
Total =18.38 kg
LABOUR RATE:
Fitter EACH 0.150000 148.16 22.22
Beldar EACH 0.200000 116.67 23.33
LABOUR :
ACTUAL LABOUR+SUNDRIES 57.55
TOTAL : 57.55
ADD FOR CONTRACTORS
PROFIT @10% : 5.75
ADD FOR OVER HEAD
CHARGES @5% : 2.87
LABOUR FOR 5.000 Metre 66.17
Steel Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR PER Metre 13.25
1507000000 Providing and fixing in position
collapsible steel shutters with
vertical channels 20 mm X10
mmX2mm
MATERIAL :
=12.705 kg.
=0.13 qtl.
1 QTL. 0.13000 4500.00 585.00
Priming coat
Channels =36x0.07x2.4 =6.57
sq.m
Tee =0.16x3.3 =0.53 sq/m
Flats =0.05x68 =3.4 sq.m
=10.50 sq.m.
1 SQ.M. 10.50000 17.15 180.07 (-I-)
Pullyes 38 mm dia
Each 10.00000 50.00 500.00
CARRIAGE :
Steel
1 KM BY MECH. TRANSPORT 1 TONNE 0.12600 73.95 9.31
LABOUR RATE:
Fitter EACH 3.60000 148.16 533.37
Black Smith 1st Class EACH 7.20000 186.67 1344.02
Black Smith 2nd Class EACH 7.20000 148.16 1066.75
Mason 1st class EACH 0.60000 211.16 126.70
Mason 2nd Class Each 0.60000 158.67 95.20
Beldar Each 9.60000 116.67 1120.03
Total : 10982.75
Add for water charges @1.5%
Except on (-I-) : 162.04
Total : 11144.79
ADD FOR CONTRACTORS
PROFIT @10% Except on (-I-) 1096.47
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 4386.07
MATERIAL :
Total =0.0562sqm
8x0.0562 =0.4496 sq.m.
2x(22/7)x(0.3)2 =0.1414 sqm
---------
Total = 0.5910 sq.m.
@ 24.73 kg./sq.m. =14.62 kg
Wastage @ 10% =1.46 kg.
Total =16.08 kg. or 0.161 qtl.
1 QTL. 0.16100 4500.00 724.50
Pulley 25 mm dia
Steel Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Each 8.00000 50.00 400.00
CARRIAGE :
Steel
1 KM BY MECH. TRANSPORT 1 TONNE 0.21580 73.95 15.95
LABOUR RATE:
Fitter EACH 2.40000 148.16 355.58
Black Smith 1st Class EACH 3.60000 186.67 672.01
Black Smith 2nd Class EACH 4.80000 148.16 711.16
Beldar EACH 4.80000 116.67 560.01
Mason 1st class EACH 0.07000 211.16 14.78
Mason 2nd Class EACH 0.07000 158.67 11.10
Total : 13605.67
Add for water charges @1.5%
Except on (-I-) : 199.45
Total : 13705.12
ADD FOR CONTRACTORS
PROFIT @10% Except on (-I-) 1339.64
LABOUR :
ACTUAL LABOUR+SUNDRIES 2399.64
MATERIAL :
Hooks
Each 2.00000 10.00 20.00
Priming coat
Steel Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
M.S sheet =11.52 sq.m
Angle iron
0.16x24.3=3.89 sq.m
total =15.41 Sq.m
CARRIAGE :
Steel
1 KM BY MECH. TRANSPORT 1 tonne 0.15940 73.95 11.78
LABOUR RATE:
Fitter each 2.40000 148.16 355.58
Black Smith 1st Class each 3.60000 186.67 672.01
Black Smith 2nd Class each 4.80000 148.16 711.16
Mason 1st class each 0.07000 211.16 14.78
Mason 2nd Class each 0.07000 158.67 11.10
Beldar each 6.00000 116.67 700.02
Total : 11015.83
Add for water charges @1.5%
Except on (-I-) : 161.27
Total : 11177.10
ADD FOR CONTRACTORS
PROFIT @10% Except on (-I-) 1091.28
LABOUR :
ACTUAL LABOUR+SUNDRIES 2539.65
MATERIAL :
Hooks
Each 2.00000 10.00 20.00
Priming coat
M.S. Sheets =11.52 sq.m.
Angles iron = 14.40x0.16 =2.30
sqm
----------------------
Flats 0.072x12.2 =0.88 sq.m.
Total =14.70 sq.m.
1 sq.m. 14.70000 17.15 252.10 (-I-)
CARRIAGE :
Steel
1 KM BY MECH. TRANSPORT 1 tonne 0.14570 73.95 10.75
Steel Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
100 MTRS BY HEAD LOAD 1 tonne 0.14570 57.85 8.42
LABOUR RATE:
Fitter each 2.40000 148.16 355.58
Mason 1st class each 0.07000 211.16 14.78
Mason 2nd Class each 0.07000 158.67 11.10
Black Smith 1st Class each 3.60000 186.67 672.01
Black Smith 2nd Class each 4.80000 148.16 711.16
Beldar each 6.00000 116.67 700.02
Total : 10385.32
Add for water charges @1.5%
Except on (-I-) : 152.00
Total : 10537.32
ADD FOR CONTRACTORS
PROFIT @10% Except on (-I-) 1028.52
LABOUR :
ACTUAL LABOUR+SUNDRIES 2539.65
MATERIAL :
LABOUR RATE:
Fitter each 3.06000 148.16 453.36
Beldar each 2.70000 116.67 315.00
Mason 1st class each 0.14000 211.16 29.56
Mason 2nd Class each 0.14000 158.67 22.21
TOTAL : 6870.13
Add. Water charges @ 1.5% 103.05
ADD FOR CONTRACTORS
PROFIT 10% 697.31
ADD FOR OVER HEAD
CHARGES @5% 348.65
MATERIAL :
Total : 1019.20
LABOUR :
Labour As per item no
:1510010000
TOTAL : 141.55
LABOUR FOR 1.000 sq.m 141.55
LABOUR PER sq.m 141.55
1511000000 Providing and fixing 27.5
MATERIAL :
LABOUR RATE:
LABOUR :
ACTUAL LABOUR+SUNDRIES 5.00
TOTAL : 5.00
WATER CHARGES @ 1.5% : 9.25
TOTAL : 14.25
ADD FOR CONTRACTORS
PROFIT @10% : 1.42
ADD FOR OVER HEAD
CHARGES @5% : 0.71
LABOUR FOR 1.000 No 16.38
LABOUR PER No 16.40
1512000000 Providing and fixing top cover for
rolling shutters.
MATERIAL :
LABOUR RATE:
TOTAL : 423.25
ADD FOR CONTRACTORS
PROFIT 10% 42.32
LABOUR :
ACTUAL LABOUR+SUNDRIES 7.00
TOTAL : 7.00
WATER CHARGES @ 1.5% : 6.25
TOTAL : 13.25
ADD FOR CONTRACTORS
PROFIT @10% : 1.32
ADD FOR OVER HEAD
CHARGES @5% : 0.66
LABOUR FOR 1.000 metre 15.23
LABOUR PER metre 15.20
Shutters having width 3.5 metre
1512020000 and
above.
Detail of cost for one metre
length.
Steel Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
LABOUR RATE:
LABOUR :
ACTUAL LABOUR+SUNDRIES 7.00
TOTAL : 7.00
WATER CHARGES @ 1.5% : 8.86
TOTAL : 15.88
ADD FOR CONTRACTORS
PROFIT @10% : 1.58
ADD FOR OVER HEAD
CHARGES @5% : 0.79
LABOUR FOR 1.000 metre 18.25
LABOUR PER metre 18.25
1513000000 Providing and fixing ball bearing
for rolling shutters.
MATERIAL :
Ball bearing
Steel Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Each 1.00000 650.00 650.00
CARRIAGE :
Carriage of material L.S 10.00
LABOUR RATE:
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 7.00
TOTAL : 7.00
WATER CHARGES @ 1.5% : 10.00
TOTAL : 17.00
ADD FOR CONTRACTORS
PROFIT @10% : 1.70
ADD FOR OVER HEAD
CHARGES @5% : 0.85
LABOUR FOR 1.000 No 19.55
LABOUR PER No 19.55
Extra providing mechanical
1514000000 device
chain and crank operation for
operating rolling shutters.
Rolling shutters(Mechanical
device
for operation)
1 sq.m. 1.00000 625.00 625.00
LABOUR RATE:
TOTAL : 635.00
ADD FOR WATER CHARGES @
1.5% : 9.52
TOTAL : 644.52
ADD FOR CONTRACTORS
PROFIT @10% : 64.45
ADD FOR OVER HEAD
CHARGES @5% : 32.22
COST FOR 1.000 sq.m 741.19
COST PER sq.m 741.20
LABOUR PER sq.m 22.45
LABOUR RATE:
ACTUAL LABOUR+SUNDRIES 10.00
TOTAL : 10.00
WATER CHARGES @ 1.5% : 9.52
TOTAL : 19.52
ADD FOR CONTRACTORS
PROFIT @10% : 1.95
ADD FOR OVER HEAD
CHARGES @5% : 0.97
LABOUR FOR 1.000 sq.m 22.44
LABOUR PER sq.m 22.45
MATERIAL :
Rolling shutters(Mechanical
device
for operation)
Steel Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
1 sq.m. 1.00000 625.00 625.00
LABOUR RATE:
TOTAL : 635.00
ADD FOR WATER CHARGES @
1.5% : 9.52
TOTAL : 644.52
ADD FOR CONTRACTORS
PROFIT @10% : 64.45
ADD FOR OVER HEAD
CHARGES @5% : 32.22
COST FOR 1.000 sq.m. 741.19
COST PER sq.m. 741.20
LABOUR PER sq.m. 22.45
LABOUR RATE:
ACTUAL LABOUR+SUNDRIES 10.00
TOTAL : 10.00
WATER CHARGES @ 1.5% : 9.52
TOTAL : 19.52
ADD FOR CONTRACTORS
PROFIT @10% : 1.95
ADD FOR OVER HEAD
CHARGES @5% : 0.97
LABOUR FOR 1.000 sq.m. 22.44
LABOUR PER sq.m. 22.45
1515000000 Fixing standerd steel glazed
doos,windows and ventilator,s in
walls with 16X3.15mm lugs
10cm.long
embeded in cement concrete
blocks
15X10X10 cm.of 1:3:6(1 cement
3
sand:6 graded stone aggregate
20 mm
nominal size)or with wooden
plugs
and screws or rawl plugs and
screws
or with fixing clip,or with bolt
and nut as required,including
fixing of glass panes wih glazing
MATERIAL :
LABOUR RATE:
Black Smith 1st Class each 0.40000 186.67 74.66
Total : 262.43
Add for water charges @1.5%
Except on (-I-) : 3.58
Total : 266.01
ADD FOR CONTRACTORS
PROFIT @10% Except on (-I-) : 24.18
LABOUR RATE:
ACTUAL LABOUR+SUNDRIES 163.30
MATERIAL :
Steel Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Ready made steel door with
necessary hinges
Fixing charges.
Total : 1261.33
LABOUR RATE:
MATERIAL :
Fixing charges
Total : 1361.33
LABOUR RATE :
MATERIAL :
Fixing charges
Total : 1561.33
LABOUR RATE :
MATERIAL :
Fixing charges
Total : 1231.33
LABOUR RATE :
MATERIAL :
Fixing charges
Total : 1356.33
LABOUR :
Steel Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
Fixing charges
Total : 1556.33
Steel Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR CONTRACTORS
PROFIT @10% Except on (-I-) 133.60
LABOUR :
MATERIAL :
Fixing charges
Total : 1556.33
LABOUR :
MATERIAL :
LABOUR RATE:
TOTAL : 515.06
ADD FOR WATER CHARGES @
1.5% : 7.72
TOTAL : 522.78
ADD FOR CONTRACTORS
PROFIT @10% : 52.28
ADD FOR OVER HEAD
CHARGES @5% : 26.14
COST FOR 1.662 sq.m. 601.20
COST PER sq.m. 361.70
LABOUR PER sq.m.
LABOUR :
ACTUAL LABOUR+SUNDRIES 30.00
TOTAL : 30.00
WATER CHARGES @ 1.5% : 7.72
TOTAL : 37.72
ADD FOR CONTRACTORS
PROFIT @10% : 3.77
ADD FOR OVER HEAD
CHARGES @5% : 1.88
LABOUR FOR 1.662 sq.m. 43.37
LABOUR PER sq.m. 43.40
1517020000 Steel windows
Details of cost for one window
size
1.194x0.594 m =0.709 sqm.
MATERIAL :
TOTAL : 262.90
ADD FOR WATER CHARGES @
1.5% : 3.94
TOTAL : 266.84
ADD FOR CONTRACTORS
PROFIT @10% : 26.68
ADD FOR OVER HEAD
CHARGES @5% : 13.34
FOR 0.709 sq.m. 306.86
PER sq.m. 432.70
LABOUR PER sq.m. 22.60
LABOUR :
ACTUAL LABOUR+SUNDRIES 10.00
TOTAL : 10.00
WATER CHARGES @ 1.5% : 3.94
TOTAL : 13.94
ADD FOR CONTRACTORS
PROFIT @10% : 1.39
ADD FOR OVER HEAD
CHARGES @5% : 0.69
LABOUR FOR 0.709 sq.m. 16.02
LABOUR PER sq.m. 22.60
1517030000 Steel ventilators
Detail of cost for one
ventilator(1.80 x0.60 ) size 1.794
mx0.594 sqm. =1.065 Sqm.
MATERIAL :
LABOUR RATE:
TOTAL : 398.90
Add. Water charges @ 1.5% 5.98
ADD FOR CONTRACTORS
PROFIT @10% : 404.88
ADD FOR OVER HEAD
CHARGES @5% : 40.48
COST FOR 1.065 sq.m. 20.24
COST PER sq.m. 465.60
LABOUR PER sq.m. 437.20
28.05
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 20.00
TOTAL : 20.00
Add. Water charges @ 1.5% 5.98
TOTAL : 25.98
ADD FOR CONTRACTORS
PROFIT @10% : 2.59
ADD FOR OVER HEAD
CHARGES @5% : 1.30
LABOUR FOR 1.065 sq.m. 29.87
LABOUR PER sq.m. 28.05
1518000000 Providing and fixing 20 mm x
6mm
mild steel 15 cm long clamps for
securing chick tops.
Detail of cost for one clamp.
MATERIAL :
LABOUR RATE:
TOTAL : 28.00
ADD FOR WATER CHARGES @
1.5% : 0.42
TOTAL : 28.42
ADD FOR CONTRACTORS
PROFIT @10% : 2.84
Steel Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR OVER HEAD
CHARGES @5% : 1.42
COST FOR 1.000 No 32.68
RATE PER No 32.70
LABOUR PER No 6.20
LABOUR :
ACTUAL LABOUR+SUNDRIES 5.00
TOTAL : 5.00
WATER CHARGES @ 1.5% : 0.42
TOTAL : 5.42
ADD FOR CONTRACTORS
PROFIT @10% : 0.54
ADD FOR OVER HEAD
CHARGES @5% : 0.27
LABOUR FOR 1.000 No 6.23
LABOUR PER No 6.20
1519000000 Provinding and fixing mild steel
rings of 6mm round bar and 40
mm
internal dia for fastening ropes of
chicks .
Detail of cost for 1 ring.
MATERIAL :
LABOUR :
TOTAL : 28.00
ADD FOR WATER CHARGES @
1.5% : 0.42
TOTAL : 28.42
ADD FOR CONTRACTORS
PROFIT @10% : 2.84
ADD FOR OVER HEAD
CHARGES @5% : 1.42
COST FOR 1.000 No 32.68
RATE PER No 32.70
LABOUR PER No 6.20
LABOUR RATE :
Steel Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ACTUAL LABOUR+SUNDRIES 5.00
TOTAL : 5.00
WATER CHARGES @ 1.5% : 0.42
TOTAL : 5.42
ADD FOR CONTRACTORS
PROFIT @10% : 0.54
ADD FOR OVER HEAD
CHARGES @5% : 0.27
LABOUR FOR 1.000 No 6.23
LABOUR PER No 6.20
Providing and fixing M.S.fan
1520000000 clamp
type -1 of 16 mm dia M.S. bar
bent
to shape with hooked ends in
R.C.C
slab during laying including
painting the exposed portion of
loop,all as per standard design
complete.
Details of cost for one clamp.
MATERIAL :
LABOUR RATE:
Black Smith 2nd Class each 0.05000 148.16 7.40
Beldar EACH 0.05000 116.67 5.83
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 14.23
TOTAL : 14.23
WATER CHARGES @ 1.5% : 1.32
TOTAL : 15.55
ADD FOR CONTRACTORS
PROFIT @10% : 1.55
ADD FOR OVER HEAD
CHARGES @5% : 0.77
LABOUR FOR 1.000 No 17.87
LABOUR PER No 17.90
1521000000 Extra over item 1520000000 for
providing
and fixing M.S fan clamp type-II
as
per standard design laying
towards
MATERIAL :
LABOUR RATE:
TOTAL : 70.80
Steel Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR WATER CHARGES @
1.5% : 1.06
TOTAL : 71.86
ADD FOR CONTRACTORS
PROFIT 10% 7.18
LABOUR :
ACTUAL LABOUR+SUNDRIES 1.00
TOTAL : 1.00
WATER CHARGES @ 1.5% : 1.06
TOTAL : 2.06
ADD FOR CONTRACTORS
PROFIT @10% : 0.20
ADD FOR OVER HEAD
CHARGES @5% : 0.10
LABOUR FOR 50.000 Cm 2.36
LABOUR PER Cm 0.05
1522000000 Providing and fixing in R.C.C
MATERIAL :
LABOUR RATE:
Black Smith 2nd Class EACH 0.04000 148.16 5.92
Beldar EACH 0.04000 116.67 4.66
LABOUR :
ACTUAL LABOUR+SUNDRIES 11.08
TOTAL : 11.08
WATER CHARGES @ 1.5% : 1.14
TOTAL : 12.22
ADD FOR CONTRACTORS
PROFIT @10% : 1.22
ADD FOR OVER HEAD
CHARGES @5% : 0.61
LABOUR FOR 1.000 No 14.05
LABOUR PER No 14.05
Steel Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
1523000000 Providing and fixing M.S.round
MATERIAL :
LABOUR RATE:
Black Smith 2nd Class EACH 0.03000 148.16 4.45
TOTAL : 113.60
ADD FOR WATER CHARGES @
1.5% : 1.70
TOTAL : 115.30
LABOUR :
ACTUAL LABOUR+SUNDRIES 7.95
TOTAL : 7.95
WATER CHARGES @ 1.5% : 1.70
TOTAL : 9.65
Steel Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR CONTRACTORS
PROFIT @10% : 0.96
ADD FOR OVER HEAD
CHARGES @5% : 0.48
LABOUR FOR 0.024 Qtl 11.09
LABOUR PER Qtl 462.10
1524000000 Providing and fixing M.S.bolts of
sizes with nuts and washers
complete.
Detail of cost for 0.10 quintal of
nuts and washers.
MATERIAL :
CARRIAGE :
Steel
1 KM BY MECH. TRANSPORT 1 TONNE 0.01000 73.95 0.74
LABOUR RATE:
Black Smith 2nd Class EACH 0.46000 148.16 68.15
Beldar EACH 0.46000 116.67 53.66
LABOUR RATE :
Steel Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ACTUAL LABOUR+SUNDRIES 128.81
TOTAL : 128.81
WATER CHARGES @ 1.5% : 11.28
TOTAL : 140.09
ADD FOR CONTRACTORS
PROFIT @10% : 14.00
ADD FOR OVER HEAD
CHARGES @5% : 7.00
LABOUR FOR 0.100 QTL. 161.09
LABOUR PER Qtl. 1610.00
MATERIAL :
Rivets
1 Qtl 0.10000 5200.00 520.00
CARRIAGE :
Steel
1 KM BY MECH. TRANSPORT 1 TONNE 0.01000 73.95 0.74
LABOUR RATE:
Fitter EACH 1.00000 148.16 148.16
Beldar EACH 0.50000 116.67 58.33
Stone Breaker EACH 0.50000 116.67 58.33
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 284.82
TOTAL : 284.82
WATER CHARGES @ 1.5% : 12.09
TOTAL : 296.91
ADD FOR CONTRACTORS
PROFIT @10% : 29.69
ADD FOR OVER HEAD
CHARGES @5% : 14.84
LABOUR FOR 0.100 Qtl. 341.44
LABOUR PER Qtl. 3414.40
1526000000 Welding by Gas plant.
Detail of cost for per cm.length
Welding Charges by Gas Plant 1 cm 1.00000 3.00 3.00
TOTAL : 3.00
ADD FOR CONTRACTORS
PROFIT @10% : 0.30
ADD FOR OVER HEAD
CHARGES @5% : 0.15
COST FOR 1.000 cm 3.45
RATE PER cm 3.45
TOTAL : 2.00
ADD FOR CONTRACTORS
PROFIT @10% : 0.20
ADD FOR OVER HEAD
CHARGES @5% : 0.10
COST FOR 1.000 cm 2.30
RATE PER cm 2.30
MATERIAL :
Wire ropes
1 qtl 1.00000 8750.00 8750.00
CARRIAGE :
1 km. By mech. Trpt. Tonne 0.10000 73.95 7.39
100mtrs. By head load. Tonne 0.10000 57.85 5.78
LABOUR RATE:
TOTAL : 9743.17
ADD FOR CONTRACTORS
PROFIT 10% 974.31
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 980.00
TOTAL : 980.00
ADD FOR CONTRACTORS
PROFIT @10% : 98.00
ADD FOR OVER HEAD
CHARGES @5% : 49.00
LABOUR FOR 1.000 qtl 1127.00
LABOUR PER Qtl 1127.00
1529000000 Providing and fixing in position
steel accessories like clamps
,suspenders,rope grips,U-Bolts
ancherage bolts with pulleys
etc.alongwith fixrures for a
suspension bridges.
Details of cost for 1 Quintal
MATERIAL :
Steel Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Mild steel accessories
1 Qtl 1.00000 7250.00 7250.00
CARRIAGE :
1 km. By mech. Trpt. Tonne 0.10000 73.95 7.39
100mtrs. By head load. Tonne 0.10000 57.85 5.78
LABOUR RATE:
TOTAL : 8713.18
ADD FOR CONTRACTORS
PROFIT 10% 871.31
LABOUR :
ACTUAL LABOUR+SUNDRIES 1450.00
TOTAL : 1450.00
MATERIAL :
LABOUR RATE:
TOTAL : 10513.18
ADD FOR CONTRACTORS
PROFIT10% 1051.31
LABOUR :
ACTUAL LABOUR+SUNDRIES 500.00
TOTAL : 500.00
ADD FOR CONTRACTORS
PROFIT @10% : 50.00
ADD FOR OVER HEAD
CHARGES @5% : 25.00
LABOUR FOR 1.000 Qtl 575.00
LABOUR PER Qtl 575.00
1531000000 Providing and fixing in position
cast iron fixtures like saddles
,rocks and roller bearings
alongwith rollers,grease box and
other fixtures.
Details of cost for one Quintal
MATERIAL :
LABOUR RATE:
TOTAL : 2613.18
Steel Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR CONTRACTORS
PROFIT 10%
MATERIAL :
Steel Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
M.S.Angle 50mmx50mmx6mm.
Size of frame 2m+2m+1m =5.0
Mtrs.
LABOUR RATE:
Fitter Each 0.15000 148.16 22.22
Beldar Each 0.20000 116.67 23.33
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 55.55
TOTAL : 55.55
ADD FOR CONTRACTORS
PROFIT @10% : 5.55
Steel Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR OVER HEAD
CHARGES @5% : 2.77
LABOUR FOR 5.000 Metre 63.88
LABOUR PER Metre 12.80
1533000000 Providing and fixing angle iron
cupboard frames manufactured
from
M.S.Angle iron section
25X25X5mm
thickness including hinges
jamb,lock jamb,beed and if
required
angle thrashold of mild steel
angle
25X25 mm welded or rigidly fixed
by
MATERIAL :
M.S.Angle 25mmx25mmx5mm.
Size of frame=2m+2m+1m=5.0
Metres.
LABOUR RATE:
Fitter Each 0.15000 148.16 22.22
Beldar Each 0.20000 116.67 23.33
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 55.55
TOTAL : 55.55
ADD FOR CONTRACTORS
PROFIT @10% : 5.55
ADD FOR OVER HEAD
CHARGES @5% : 2.77
LABOUR FOR 5.000 Metre 63.88
LABOUR PER Metre 12.80
Material
CARRIAGE
LABOUR :
Black Smith 1st class each 0.30000 186.67 56.00
Beldar each 0.30000 116.67 35.00
TOTAL : 609.98
ADD FOR CONTRACTORS
PROFIT 10% Except on (-I-) : 59.30
ADD FOR OVER HEAD
CHARGES @5% Except on (-I-)
: 29.65
COST FOR 6.00 Rmt. 698.93
COST PER RMT 116.50
Labour Per Rmt. 23.80
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 116.00
Steel Work
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Notes :
1. The through rates include the carriage of all materials for 100 meters on head load and
one kilometer by mechanical transport. All other additional carriage shall be accounted
for separately.
2. The through rates include the cost of materials, wastage, sand papers and brushes
required for completion of any item. The labour rates include the cost of brushes, sand
papers scaffolding etc. and other appurtenant sundries.
3. The specification- paints, and other goods shall be of Grade I notified by the Engineer-
In-Chief, Himachal Pradesh PWD , from time to time.
CHAPTER-XVI
Painting and Polishing
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE:
ACTUAL LABOUR+SUNDRIES 205.45
TOTAL : 205.45
ADD FOR CONTRACTORS PROFIT @10% : 20.55
ADD FOR OVER HEAD CHARGES @5%: 10.27
LABOUR FOR 10.00 sqm 236.37
LABOUR PER Sqm 23.60
Material :
L.S 0.50
LABOUR:
Painter 2nd class Each 0.81000 128.33 103.95
Beldar Each 0.81000 116.67 94.50
Painting and Polishing
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR :
ACTUAL LABOUR+SUNDRIES 203.45
TOTAL : 203.45
ADD FOR CONTRACTORS PROFIT @10% : 20.35
ADD FOR OVER HEAD CHARGES @5%: 10.17
LABOUR FOR 10.00 sqm 233.96
LABOUR PER Sqm 23.40
MATERIAL:
CARRIAGE:
carriage of material L.S 0.50
LABOUR:
Painter 2nd class Each 0.54000 128.33 69.30
Beldar Each 0.54000 116.67 63.00
LABOUR :
ACTUAL LABOUR+SUNDRIES 136.30
TOTAL : 136.30
ADD FOR CONTRACTORS PROFIT @10% : 13.63
ADD FOR OVER HEAD CHARGES @5%: 6.81
LABOUR FOR 10.00 sqm 156.74
LABOUR PER Sqm 15.70
Painting and Polishing
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
16002000 Applying priming coat over new
steel & other metal surfaces after
& including preparing the surface
by thoroughly cleaning oil grease
dirt and other foreign matter and
scoured with wire brushes fine
steel wool scrapers and sand paper
complete.
MATERIAL:
CARRIAGE:
carriage of material L.S 1.00
LABOUR:
Painter 2nd class Each 0.30000 128.33 38.50
Beldar Each 0.30000 116.67 35.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 83.50
TOTAL : 83.50
ADD FOR CONTRACTORS PROFIT @10% : 8.35
ADD FOR OVER HEAD CHARGES @5%: 4.17
LABOUR FOR 10.00 sqm 96.02
LABOUR PER Sqm 9.60
MATERIAL:
CARRIAGE:
carriage of material L.S 0.50
LABOUR RATE:
Painter 2nd class Each 0.30000 148.16 44.45
Beldar Each 0.30000 116.67 35.00
LABOUR RATE:
ACTUAL LABOUR+SUNDRIES 89.45
TOTAL : 89.45
ADD FOR CONTRACTORS PROFIT @10% : 8.94
ADD FOR OVER HEAD CHARGES @5%: 4.47
LABOUR FOR 10.00 sqm 102.86
LABOUR PER Sqm 10.30
16004010 50 mm dia
Details of cost for 10 metre,
---------------------------------------------
MATERIAL:
Painting and Polishing
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Priming coat. 1 sqm. 1.78000 17.15 30.52 (-I-)
Area (22/7) x56.4 mm x 10m = 1.78 sqm.
(Rate same as per item No. 16002010).
LABOUR:
Extra for labour & wastage L.S, 9.50
Total 45.02
ADD FOR CONTRACTORS PROFIT@ 10%: EXCEPT ON (-I-) : 1.45
ADD FOR OVER HEAD CHARGES @5%: EXCEPT ON (-I-) : 0.72
Cost for 10 Metress 47.19
Cost Per Metress 4.70
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 9.50
Labour as per item no : 16002010 (1.78X9.60) 17.08 (-a-)
TOTAL : 26.58
ADD FOR CONTRACTORS PROFIT @10% except on (-a-) above: 0.95
ADD FOR OVER HEAD CHARGES @5%: except on (-a-) above: 0.47
LABOUR FOR 10.00 Metres 28.00
LABOUR PER Metres 2.80
16004020 75 mm dia
Details of cost for 10 metre,
---------------------------------------------
MATERIAL:
Priming coat.
Area (22/7) x81.4 mm x 10m = 2.56 sqm.
(Rate same as per item No. 16002010).
1 sqm 2.56000 17.15 43.90 (-I-)
wire brushes for cleaing. L.S 5.00
LABOUR:
Extra for labour & wastage L.S 9.50
Total 58.40
ADD FOR CONTRACTORS PROFIT@ 10%: EXCEPT ON (-I-) : 1.45
ADD FOR OVER HEAD CHARGES @5%: EXCEPT ON (-I-) : 0.72
Cost for 10 Metress 60.57
Cost Per Metress 6.05
Painting and Polishing
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 9.50
Labour as per item no : 16002010 24.58
TOTAL : 34.08
ADD FOR CONTRACTORS PROFIT @10% except on (-a-) : 0.95
ADD FOR OVER HEAD CHARGES @5%: except on (-a-): 0.47
LABOUR FOR 10.00 Metres 35.50
LABOUR PER Metres 3.55
MATERIAL:
Priming coat.
Area (22/7) x106.4 mm x 10m = 3.44 sqm.
(Rate same as per item No. 16002010).
1 sqm 3.44000 17.15 57.35 (-I-)
LABOUR:
Extra for labour & wastage L.S 9.50
Total 71.85
ADD FOR CONTRACTORS PROFIT@ 10%: Exce[t on (-I-) : 1.45
ADD FOR OVER HEAD CHARGES @5%:Except on (-I-) : 0.72
Cost for 10 Metress 74.02
Cost Per Metress 7.40
LABOUR RATE:
ACTUAL LABOUR+SUNDRIES 9.50
Labour as per item no : 16002010 32.10 (-a-)
TOTAL : 41.60
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-): 0.95
ADD FOR OVER HEAD CHARGES @5%: Except on (-a-): 0.47
LABOUR FOR 10.00 Metres 43.02
LABOUR PER Metres 4.30
MATERIAL:
Painting and Polishing
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Priming coat.
Area (22/7) x157.2 mm x 10m = 4.94 sqm.
(Rate same as per item No. 16002010).
1 sqm 4.94000 17.15 84.72 (-I-)
LABOUR RATE :
Extra for labour & wastage L.S 9.50
Total 99.22
ADD FOR CONTRACTORS PROFIT@ 10%: EXCEPT ON (-I-) : 1.45
ADD FOR OVER HEAD CHARGES @5%: EXCEPT ON (-I-) : 0.72
Cost for 10 Metress 101.39
Cost Per Metress 10.15
LABOUR RATE:
ACTUAL LABOUR+SUNDRIES 9.50
Labour as per item no : 16002010 47.42 (-a-)
TOTAL : 56.92
ADD FOR CONTRACTORS PROFIT @10% EXCEPT on (-a-): 0.95
ADD FOR OVER HEAD CHARGES @5%: EXCEPT on (-a-): 0.47
LABOUR FOR 10.00 Metres 58.34
LABOUR PER Metres 5.85
Priming coat.
Area 10 x 90= 9.00 sqm.
(Rate same as per item No. 16002010).
1 sqm 9.00000 17.15 154.35
LABOUR:
Extra for labour & wastage L.S 9.50
Total 168.85
ADD FOR CONTRACTORS PROFIT@ 10%: Exce[t on (-I-) : 1.45
ADD FOR OVER HEAD CHARGES @5%:Except on (-I-) : 0.72
Cost for 10 Metres 171.02
Cost Per Metres 17.10
Painting and Polishing
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 9.50
Labour as per item no : 16002010 86.40
TOTAL : 95.90
ADD FOR CONTRACTORS PROFIT @10% Except on (-a-): 0.95
ADD FOR OVER HEAD CHARGES @5%: Except on (-a-): 0.47
LABOUR FOR 10.00 Metres 97.32
LABOUR PER Metre 9.70
MATERIAL:
CARRIAGE:
carriage of material L.S 1.50
LABOUR:
Painter 2nd class Each 0.54000 128.33 39.30
Beldar Each 0.54000 116.67 63.00
LABOUR RATE:
ACTUAL LABOUR+SUNDRIES 142.30
TOTAL : 142.30
ADD FOR CONTRACTORS PROFIT @10% : 14.23
ADD FOR OVER HEAD CHARGES @5%: 7.12
LABOUR FOR 10.00 sqm 163.65
LABOUR PER Sqm 16.35
Painting and Polishing
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL:
CARRIAGE:
carriage of material L.S 1.50
LABOUR:
Painter 2nd class Each 0.54000 128.33 69.30
Beldar Each 0.54000 116.67 63.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 142.30
TOTAL : 142.30
ADD FOR CONTRACTORS PROFIT @10% : 14.23
ADD FOR OVER HEAD CHARGES @5% : 7.12
LABOUR FOR 10.00 sqm 163.65
LABOUR PER Sqm 16.35
MATERIAL:
LABOUR:
Painter 1st class Each 0.54000 148.16 80.00
Beldar Each 0.54000 116.67 63.00
LABOUR RATE:
ACTUAL LABOUR+SUNDRIES 153.00
TOTAL : 153.00
ADD FOR CONTRACTORS PROFIT @10% : 15.30
ADD FOR OVER HEAD CHARGES @5%: 7.65
LABOUR FOR 10.00 sqm 175.95
LABOUR PER Sqm 17.60
MATERIAL:
LABOUR:
Painter 1st class Each 0.54000 148.16 80.00
Beldar Each 0.54000 116.67 63.00
MATERIAL:
CARRIAGE:
carriage of material L.S 1.50
LABOUR:
Painter 2nd class Each 0.36000 128.33 46.20
Beldar Each 0.36000 116.67 42.00
LABOUR RATE:
ACTUAL LABOUR+SUNDRIES 98.20
TOTAL : 98.20
ADD FOR CONTRACTORS PROFIT @10% : 9.82
ADD FOR OVER HEAD CHARGES @5%: 4.91
LABOUR FOR 10.00 sqm 102.93
LABOUR PER Sqm 10.30
Painting and Polishing
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
16007020 With Enamel paint other than white
Details of cost for 10 sq, metre,
---------------------------------------------
MATERIAL:
CARRIAGE:
carriage of material L.S 1.50
LABOUR:
Painter 2nd class Each 0.36000 128.33 46.20
Beldar Each 0.36000 116.67 42.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 98.20
TOTAL : 98.20
ADD FOR CONTRACTORS PROFIT @10% : 9.82
ADD FOR OVER HEAD CHARGES @5%: 4.91
LABOUR FOR 10.00 sqm 102.93
LABOUR PER Sqm 10.30
MATERIAL:
LABOUR:
Painter 1st class Each 0.36000 148.16 53.34
Beldar Each 0.36000 116.67 42.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 105.34
TOTAL : 105.34
ADD FOR CONTRACTORS PROFIT @10% : 10.54
ADD FOR OVER HEAD CHARGES @5%: 5.27
LABOUR FOR 10.00 sqm 121.15
LABOUR PER Sqm 12.10
MATERIAL:
LABOUR:
Painter 1st class Each 0.36000 148.16 53.34
Beldar Each 0.36000 116.67 42.00
LABOUR RATE:
ACTUAL LABOUR+SUNDRIES 105.34
TOTAL : 105.34
ADD FOR CONTRACTORS PROFIT @10% : 10.54
ADD FOR OVER HEAD CHARGES @5%: 5.27
LABOUR FOR 10.00 sqm 121.15
LABOUR PER Sqm 12.10
MATERIAL:
CARRIAGE:
carriage of material L.S 1.50
LABOUR:
Painter 2nd class Each 0.30000 128.33 38.50
Beldar Each 0.30000 116.67 35.00
LABOUR RATE:
ACTUAL LABOUR+SUNDRIES 83.50
TOTAL : 83.50
ADD FOR CONTRACTORS PROFIT @10% : 8.35
ADD FOR OVER HEAD CHARGES @5%: 4.17
LABOUR FOR 10.00 sqm 96.02
LABOUR PER Sqm 9.60
CARRIAGE:
carriage of material L.S 1.50
LABOUR:
Painter 2nd class Each 0.30000 128.33 38.50
Beldar Each 0.30000 116.67 35.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 83.50
TOTAL : 83.50
ADD FOR CONTRACTORS PROFIT @10% : 8.35
ADD FOR OVER HEAD CHARGES @5%: 4.17
LABOUR FOR 10.00 sqm 96.02
LABOUR PER Sqm 9.60
MATERIAL:
LABOUR:
Painter 1st class Each 0.30000 148.16 44.45
Beldar Each 0.30000 116.67 35.00
Painting and Polishing
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Sundries (Brushes and sand paper etc.) L.S 10.00
Total 198.55
ADD FOR CONTRACTORS PROFIT@ 10%: 19.86
ADD FOR OVER HEAD CHARGES @5%: 9.93
Cost for 10 sqm 228.34
Cost Per sqm. 22.85
Labour Per sqm. 10.25
LABOUR RATE:
ACTUAL LABOUR+SUNDRIES 89.45
TOTAL : 89.45
ADD FOR CONTRACTORS PROFIT @10% : 8.95
ADD FOR OVER HEAD CHARGES @5%: 4.27
LABOUR FOR 10.00 sqm 102.67
LABOUR PER Sqm 10.25
MATERIAL:
LABOUR:
Painter 1st class Each 0.30000 148.16 44.45
Beldar Each 0.30000 116.67 35.00
LABOUR RATE:
ACTUAL LABOUR+SUNDRIES 89.45
TOTAL : 89.45
ADD FOR CONTRACTORS PROFIT @10% : 8.94
ADD FOR OVER HEAD CHARGES @5%: 4.47
LABOUR FOR 10.00 sqm 102.86
LABOUR PER Sqm 10.25
Painting and Polishing
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
CARRIAGE:
carriage of material L.S 1.50
LABOUR:
Painter 2nd class Each 0.54000 128.33 69.30
Beldar Each 0.54000 116.67 63.00
LABOUR RATE:
ACTUAL LABOUR+SUNDRIES 142.30
TOTAL : 142.30
ADD FOR CONTRACTORS PROFIT @10% : 14.23
ADD FOR OVER HEAD CHARGES @5%: 7.11
LABOUR FOR 10.00 sqm 163.14
LABOUR PER Sqm 16.35
MATERIAL :
CARRIAGE:
carriage of material L.S 1.50
LABOUR:
Painter 2nd class Each 0.54000 128.33 69.30
Beldar Each 0.54000 116.67 63.00
LABOUR RATE:
ACTUAL LABOUR+SUNDRIES 142.30
TOTAL : 142.30
ADD FOR CONTRACTORS PROFIT @10% : 14.23
ADD FOR OVER HEAD CHARGES @5%: 7.11
LABOUR FOR 10.00 sqm 163.14
LABOUR PER Sqm 16.35
MATERIAL :
CARRIAGE:
carriage of material L.S 1.50
LABOUR:
Painter 2nd class Each 0.36000 128.33 46.20
Beldar Each 0.36000 116.67 42.00
LABOUR RATE:
ACTUAL LABOUR+SUNDRIES 98.20
TOTAL : 98.20
ADD FOR CONTRACTORS PROFIT @10% : 9.82
ADD FOR OVER HEAD CHARGES @5%: 4.91
LABOUR FOR 10.00 sqm 102.93
LABOUR PER Sqm 10.30
MATERIAL :
CARRIAGE:
carriage of material L.S 1.50
LABOUR:
Painter 2nd class Each 0.36000 128.33 46.20
Beldar Each 0.36000 116.67 42.00
Painting and Polishing
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Sundries (Brushes and sand paper etc.) L.S 10.00
Total 219.70
ADD FOR CONTRACTORS PROFIT@ 10%: 21.97
ADD FOR OVER HEAD CHARGES @5%: 10.98
Cost for 10 sqm 252.65
Cost Per sqm. 25.25
Labour Per sqm. 10.30
LABOUR RATE:
ACTUAL LABOUR+SUNDRIES 98.20
TOTAL : 98.20
ADD FOR CONTRACTORS PROFIT @10% : 9.82
ADD FOR OVER HEAD CHARGES @5%: 4.91
LABOUR FOR 10.00 sqm 102.93
LABOUR PER Sqm 10.30
MATERIAL :
CARRIAGE:
carriage of material L.S 1.50
LABOUR:
Painter 2nd class Each 0.30000 128.33 38.50
Beldar Each 0.30000 116.67 35.00
LABOUR RATE:
ACTUAL LABOUR+SUNDRIES 83.50
TOTAL : 83.50
Painting and Polishing
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR CONTRACTORS PROFIT @10% : 8.35
ADD FOR OVER HEAD CHARGES @5%: 4.17
LABOUR FOR 10.00 sqm 96.02
LABOUR PER Sqm 9.60
MATERIAL :
CARRIAGE:
carriage of material L.S 1.50
LABOUR:
Painter 2nd class Each 0.30000 128.33 38.50
Beldar Each 0.30000 116.67 35.00
LABOUR RATE:
ACTUAL LABOUR+SUNDRIES 83.50
TOTAL : 83.50
ADD FOR CONTRACTORS PROFIT @10% : 8.35
ADD FOR OVER HEAD CHARGES @5%: 4.17
LABOUR FOR 10.00 sqm 96.02
LABOUR PER Sqm 9.60
MATERIAL :
Aluminium paint
CARRIAGE:
carriage of material L.S 1.50
LABOUR:
Painter 2nd class Each 0.54000 128.33 69.30
Beldar Each 0.54000 116.67 63.00
LABOUR RATE:
ACTUAL LABOUR+SUNDRIES 142.30
TOTAL : 142.30
ADD FOR CONTRACTORS PROFIT @10% : 14.23
ADD FOR OVER HEAD CHARGES @5%: 7.11
LABOUR FOR 10.00 sqm 163.64
LABOUR PER Sqm 16.35
MATERIAL :
Aluminium paint
CARRIAGE:
carriage of material L.S 1.50
Painting and Polishing
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR:
Painter 2nd class Each 0.36000 128.33 46.20
Beldar Each 0.36000 116.67 42.00
LABOUR RATE:
ACTUAL LABOUR+SUNDRIES 98.20
TOTAL : 98.20
ADD FOR CONTRACTORS PROFIT @10% : 9.82
ADD FOR OVER HEAD CHARGES @5%: 4.91
LABOUR FOR 10.00 sqm 112.93
LABOUR PER Sqm 11.30
MATERIAL :
Bitumen paint
CARRIAGE:
carriage of material L.S 1.50
LABOUR:
Painter 2nd class Each 0.84000 128.33 107.80
Beldar Each 0.84000 116.67 98.00
LABOUR RATE:
ACTUAL LABOUR+SUNDRIES 215.80
TOTAL : 215.80
ADD FOR CONTRACTORS PROFIT @10% : 21.58
ADD FOR OVER HEAD CHARGES @5%: 10.79
LABOUR FOR 10.00 sqm 248.17
LABOUR PER Sqm 24.80
Bituminous paint
1 litre 0.95000 1.00 104.50
CARRIAGE :
Carriage of material L.S. 1.50
LABOUR :
Painter 2nd class Each 0.54000 128.33 69.30
Beldar Each 0.54000 116.67 63.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 142.30
TOTAL : 142.30
ADD FOR CONTRACTORS PROFIT@ 10%: 14.23
ADD FOR OVER HEAD CHARGES @5%: 7.11
LABOUR FOR 10.00 Sq.m 163.64
LABOUR PER Sq.m 16.35
Painting and Polishing
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Bituminous paint
1 litre 0.57000 110.00 62.70
CARRIAGE :
Carriage of material L.S. 1.50
LABOUR :
Painter 2nd class Each 0.36000 128.33 46.20
Beldar Each 0.36000 116.67 42.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 98.20
TOTAL : 98.20
ADD FOR CONTRACTORS PROFIT@ 10%: 9.82
ADD FOR OVER HEAD CHARGES @5%: 4.91
LABOUR FOR 10.00 Sq.m 102.93
LABOUR PER Sq.m 10.30
CARRIAGE :
Carriage of material L.S. 1.50
LABOUR :
Painter 2nd class Each 0.54000 128.33 69.30
Beldar Each 0.54000 116.67 63.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 142.30
TOTAL : 142.30
ADD FOR CONTRACTORS PROFIT@ 10%: 14.23
ADD FOR OVER HEAD CHARGES @5%: 7.11
LABOUR FOR 10.00 Sq.m 163.64
LABOUR PER Sq.m 16.35
CARRIAGE :
Carriage of material L.S. 1.50
LABOUR :
Painter 2nd class Each 0.36000 128.33 46.20
Painting and Polishing
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Beldar Each 0.36000 116.67 42.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 98.20
TOTAL : 98.20
ADD FOR CONTRACTORS PROFIT@ 10%: 9.82
ADD FOR OVER HEAD CHARGES @5%: 4.91
LABOUR FOR 10.00 Sq.m 102.93
LABOUR PER Sq.m 10.30
CARRIAGE :
Carriage of material L.S. 1.50
LABOUR :
Painter 2nd class Each 0.30000 128.33 38.50
Beldar Each 0.30000 116.67 35.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 83.50
TOTAL : 83.50
ADD FOR CONTRACTORS PROFIT@ 10%: 8.35
Painting and Polishing
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR OVER HEAD CHARGES @5%: 4.17
LABOUR FOR 10.00 Sq.m 96.02
LABOUR PER Sq.m 9.60
Coaltar Paint
1 litre 0.95000 85.00 80.75
CARRIAGE :
Carriage of material L.S. 1.50
LABOUR :
Painter 2nd class Each 0.54000 128.33 69.30
Beldar Each 0.54000 116.67 63.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 142.30
TOTAL : 142.30
ADD FOR CONTRACTORS PROFIT@ 10%: 14.23
ADD FOR OVER HEAD CHARGES @5%: 7.11
LABOUR FOR 10.00 Sq.m 163.64
LABOUR PER Sq.m 16.35
Coaltar Paint
1 litre 0.57000 85.00 48.45
CARRIAGE :
Carriage of material L.S. 1.50
LABOUR :
Painter 2nd class Each 0.36000 128.33 46.20
Beldar Each 0.36000 116.67 42.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 98.20
TOTAL : 98.20
ADD FOR CONTRACTORS PROFIT@ 10%: 9.82
ADD FOR OVER HEAD CHARGES @5%: 4.91
LABOUR FOR 10.00 Sq.m 102.93
LABOUR PER Sq.m 10.30
Coaltar Paint
1 litre 0.57000 85.00 48.45
CARRIAGE :
Carriage of material L.S. 1.50
LABOUR :
Painter 2nd class Each 0.30000 128.33 38.50
Beldar Each 0.30000 116.67 35.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 83.50
TOTAL : 83.50
ADD FOR CONTRACTORS PROFIT@ 10%: 8.35
ADD FOR OVER HEAD CHARGES @5%: 4.17
LABOUR FOR 10.00 Sq.m 96.02
LABOUR PER Sq.m 9.60
16027010 50 mm dia.
Details of cost for 10 Metre
------------------------------------------
MATERIAL:
LABOUR :
Extra labour & wastage
L.S. 25.00
TOTAL : 106.18
ADD FOR CONTRACTORS PROFIT@ 10%: Except on (-I-): 2.75
ADD FOR OVER HEAD CHARGES @5%: Except on (-I-): 1.37
COST FOR 10.00 Metre 110.30
Painting and Polishing
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
COST PER Metre 11.05
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 25.00
Labour as per iten no : 16016000 44.14 (-a-)
Total 69.14
16027020 75 mm dia
Details of cost for 10 Metre
------------------------------------------
MATERIAL:
LABOUR :
Extra labour & wastage
L.S. 25.00
TOTAL : 140.65
ADD FOR CONTRACTORS PROFIT@ 10%: Except on (-I-): 2.75
ADD FOR OVER HEAD CHARGES @5%: Except on (-I-): 1.37
COST FOR 10.00 Metre 144.77
COST PER Metre 14.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 25.00
Labour as per iten no : 16016000 63.48 (-a-)
Total 88.48
MATERIAL:
LABOUR :
Extra labour & wastage
L.S. 25.00
TOTAL : 175.30
ADD FOR CONTRACTORS PROFIT@ 10%: Except on (-I-): 2.75
ADD FOR OVER HEAD CHARGES @5%: Except on (-I-): 1.37
COST FOR 10.00 Metre 179.42
COST PER Metre 17.95
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 25.00
Labour as per iten no : 16016000 82.93 (-a-)
Total 107.93
MATERIAL:
LABOUR :
Extra labour & wastage
L.S. 25.00
TOTAL : 245.85
ADD FOR CONTRACTORS PROFIT@ 10%: Except on (-I-): 2.75
ADD FOR OVER HEAD CHARGES @5%: Except on (-I-): 1.34
COST FOR 10.00 Metre 249.94
COST PER Metre 25.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 25.00
Labour as per iten no : 16016000 122.51 (-a-)
Total 147.51
MATERIAL:
LABOUR :
Extra labour & wastage
L.S. 25.00
TOTAL : 425.30
ADD FOR CONTRACTORS PROFIT@ 10%: Except on (-I-): 2.75
ADD FOR OVER HEAD CHARGES @5%: Except on (-I-): 1.34
COST FOR 10.00 Metre 429.39
COST PER Metre 42.95
Painting and Polishing
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 25.00
Labour as per iten no : 16016000 223.20 (-a-)
Total 248.20
16028010 50 mm dia .
Details of cost for 10 Metre
------------------------------------------
MATERIAL:
LABOUR :
Extra labour & wastage
L.S. 10.00
TOTAL : 45.78
ADD FOR CONTRACTORS PROFIT@ 10%: Except on (-I-) : 1.25
ADD FOR OVER HEAD CHARGES @5%: Except on (-I-) : 0.62
COST FOR 10.00 Metre 47.65
COST PER Metre 4.75
Painting and Polishing
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 10.00
Labour as per iten no : 16018000 18.33 (-a-)
Total 28.33
16028020 75 mm dia.
Details of cost for 10 Metre
------------------------------------------
MATERIAL:
LABOUR :
Extra labour & wastage
L.S. 10.00
TOTAL : 60.37
ADD FOR CONTRACTORS PROFIT@ 10%: Except on (-I-) : 1.25
ADD FOR OVER HEAD CHARGES @5%: Except on (-I-) : 0.62
COST FOR 10.00 Metre 62.24
COST PER Metre 6.20
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 10.00
Labour as per iten no : 16018000 26.36 (-a-)
Total 36.36
MATERIAL:
LABOUR :
Extra labour & wastage
L.S. 10.00
TOTAL : 75.03
ADD FOR CONTRACTORS PROFIT@ 10%: Except on (-I-) : 1.25
ADD FOR OVER HEAD CHARGES @5%: Except on (-I-) : 0.62
COST FOR 10.00 Metre 76.90
COST PER Metre 7.70
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 10.00
Labour as per iten no : 16018000 34.34 (-a-)
Total 44.44
MATERIAL:
LABOUR :
Painting and Polishing
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Extra labour & wastage
L.S. 10.00
TOTAL : 104.88
ADD FOR CONTRACTORS PROFIT@ 10%: Except on (-I-) : 1.25
ADD FOR OVER HEAD CHARGES @5%: Except on (-I-) : 0.62
COST FOR 10.00 Metre 106.75
COST PER Metre 10.70
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 10.00
Labour as per iten no : 16018000 50.88
Total 60.88
MATERIAL:
LABOUR :
Extra labour & wastage
L.S. 10.00
TOTAL : 180.80
ADD FOR CONTRACTORS PROFIT@ 10%: Except on (-I-) : 1.25
ADD FOR OVER HEAD CHARGES @5%: Except on (-I-) : 0.62
COST FOR 10.00 Metre 182.67
COST PER Metre 18.25
LABOUR RATE :
Painting and Polishing
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ACTUAL LABOUR+SUNDRIES 10.00
Labour as per iten no : 16018000 92.70 (-a-)
Total 102.70
16029010 50 mm dia
Details of cost for 10 Metre
------------------------------------------
MATERIAL:
LABOUR :
Extra labour & wastage
L.S. 15.00
TOTAL : 79.71
ADD FOR CONTRACTORS PROFIT@ 10%: Except on (-I-) : 1.75
ADD FOR OVER HEAD CHARGES @5%: Except on (-I-) : 0.87
COST FOR 10.00 Metre 82.33
COST PER Metre 8.25
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 15.00
Labour as per iten no : 16014000 29.10 (-a-)
Total 44.10
16029020 75 mm dia
Details of cost for 10 Metre
------------------------------------------
MATERIAL:
LABOUR :
Extra labour & wastage
L.S. 15.00
TOTAL : 106.97
ADD FOR CONTRACTORS PROFIT@ 10%: Except on (-I-) : 1.75
ADD FOR OVER HEAD CHARGES @5%: Except on (-I-) : 0.87
COST FOR 10.00 Metre 109.59
COST PER Metre 10.95
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 15.00
Labour as per iten no : 16014000 41.85 (-a-)
Total 56.85
MATERIAL:
LABOUR :
Extra labour & wastage
L.S. 15.00
TOTAL : 134.37
ADD FOR CONTRACTORS PROFIT@ 10%: Except on (-I-) : 1.75
ADD FOR OVER HEAD CHARGES @5%: Except on (-I-) : 0.87
COST FOR 10.00 Metre 136.99
COST PER Metre 13.70
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 15.00
Labour as per iten no : 16014000 54.67 (-a-)
Total 69.67
MATERIAL:
LABOUR :
Extra labour & wastage
L.S. 15.00
TOTAL : 190.15
ADD FOR CONTRACTORS PROFIT@ 10%: Except on (-I-) : 1.75
ADD FOR OVER HEAD CHARGES @5%: Except on (-I-) : 0.87
Painting and Polishing
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
COST FOR 10.00 Metre 192.77
COST PER Metre 19.25
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 15.00
Labour as per iten no : 16014000 80.76 (-a-)
Total 95.76
MATERIAL:
LABOUR :
Extra labour & wastage
L.S. 15.00
TOTAL : 332.05
ADD FOR CONTRACTORS PROFIT@ 10%: Except on (-I-) : 1.75
ADD FOR OVER HEAD CHARGES @5%: Except on (-I-) : 0.87
COST FOR 10.00 Metre 334.67
COST PER Metre 33.45
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 15.00
Labour as per iten no : 16014000 147.15 (-a-)
Total 162.15
16030010 50 mm dia
Details of cost for 10 Metre
------------------------------------------
MATERIAL:
LABOUR :
Extra labour & wastage
L.S. 10.00
TOTAL : 51.75
ADD FOR CONTRACTORS PROFIT@ 10%: Except on (-I-) : 1.25
ADD FOR OVER HEAD CHARGES @5%: Except on (-I-) : 0.62
COST FOR 10.00 Metre 53.62
COST PER Metre 5.35
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 10.00
Labour as per iten no : 16015000 18.33
Total 28.33
MATERIAL:
LABOUR :
Extra labour & wastage
L.S. 10.00
TOTAL : 68.95
ADD FOR CONTRACTORS PROFIT@ 10%: Except on (-I-) : 1.25
ADD FOR OVER HEAD CHARGES @5%: Except on (-I-) : 0.62
COST FOR 10.00 Metre 70.82
COST PER Metre 7.10
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 10.00
Labour as per iten no : 16015000 26.36 (-a-)
Total 36.36
MATERIAL:
LABOUR :
Extra labour & wastage
L.S. 10.00
TOTAL : 86.24
ADD FOR CONTRACTORS PROFIT@ 10%: Except on (-I-) : 1.25
ADD FOR OVER HEAD CHARGES @5%: Except on (-I-) : 0.62
COST FOR 10.00 Metre 88.11
COST PER Metre 8.80
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 10.00
Labour as per iten no : 16015000 34.44 (-a-)
Total 44.44
MATERIAL:
LABOUR :
Extra labour & wastage
L.S. 10.00
TOTAL : 121.42
ADD FOR CONTRACTORS PROFIT@ 10%: Except on (-I-) : 1.25
ADD FOR OVER HEAD CHARGES @5%: Except on (-I-) : 0.62
COST FOR 10.00 Metre 123.29
COST PER Metre 12.30
Painting and Polishing
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 10.00
Labour as per iten no : 16015000 50.88 (-a-)
Total 60.88
MATERIAL:
LABOUR :
Extra labour & wastage
L.S. 10.00
TOTAL : 210.45
ADD FOR CONTRACTORS PROFIT@ 10%: Except on (-I-) : 1.25
ADD FOR OVER HEAD CHARGES @5%: Except on (-I-) : 0.62
COST FOR 10.00 Metre 212.82
COST PER Metre 21.30
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 10.00
Labour as per iten no : 16015000 92.70 (-a-)
Total 102.70
16031010 50 mm dia
Details of cost for 10 Sqm
------------------------------------------
MATERIAL:
Bituminous paint
1 litre 0.54000 110.00 59.40
CARRIAGE
Carriage of material
L.S. 1.50
LABOUR :
Painter 2nd class Each 0.30000 128.33 38.50
Beldar Each 0.30000 116.67 35.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 83.50
Total 83.50
MATERIAL:
Bituminous paint
1 litre 0.54000 110.00 59.40
CARRIAGE
Carriage of material
L.S. 1.50
LABOUR :
Painter 2nd class Each 0.30000 128.33 38.50
Beldar Each 0.30000 116.67 35.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 83.50
Total 83.50
MATERIAL:
Painting and Polishing
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Bituminous paint
1 litre 0.54000 110.00 59.40
CARRIAGE
Carriage of material
L.S. 1.50
LABOUR :
Painter 2nd class Each 0.30000 128.33 38.50
Beldar Each 0.30000 116.67 35.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 83.50
Total 83.50
MATERIAL:
Bituminous paint
1 litre 0.54000 110.00 59.40
Painting and Polishing
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
CARRIAGE
Carriage of material
L.S. 1.50
LABOUR :
Painter 2nd class Each 0.30000 128.33 38.50
Beldar Each 0.30000 116.67 35.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 83.50
Total 83.50
MATERIAL:
Bituminous paint
1 litre 0.54000 110.00 59.40
CARRIAGE
Carriage of material
L.S. 1.50
Painting and Polishing
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR :
Painter 2nd class Each 0.30000 128.33 38.50
Beldar Each 0.30000 116.67 35.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 83.50
Total 83.50
16032010 50 mm dia.
Details of cost for 10 Sqm
------------------------------------------
MATERIAL:
Aluminium paint
1 litre 0.46000 200.00 92.00
CARRIAGE
Carriage of material
Painting and Polishing
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
L.S. 1.50
LABOUR :
Painter 1st class Each 0.30000 148.16 44.45
Beldar Each 0.30000 116.67 35.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 89.45
Total 89.45
16032020 75 mm dia
Details of cost for 10 Sqm
------------------------------------------
MATERIAL:
Aluminium paint
1 litre 0.46000 200.00 92.00
CARRIAGE
Carriage of material
L.S. 1.50
LABOUR :
Painter 1st class Each 0.30000 148.16 44.45
Beldar Each 0.30000 116.67 35.00
Painting and Polishing
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 89.45
Total 89.45
MATERIAL:
Aluminium paint
1 litre 0.46000 200.00 92.00
CARRIAGE
Carriage of material
L.S. 1.50
LABOUR :
Painter 1st class Each 0.30000 148.16 44.45
Beldar Each 0.30000 116.67 35.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 89.45
Total 89.45
MATERIAL:
Aluminium paint
1 litre 0.46000 200.00 92.00
CARRIAGE
Carriage of material
L.S. 1.50
LABOUR :
Painter 1st class Each 0.30000 148.16 44.45
Beldar Each 0.30000 116.67 35.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 89.45
Total 89.45
MATERIAL:
Aluminium paint
1 litre 0.46000 200.00 92.00
CARRIAGE
Carriage of material
L.S. 1.50
LABOUR :
Painter 1st class Each 0.30000 148.16 44.45
Beldar Each 0.30000 116.67 35.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 89.45
Total 89.45
MATERIAL:
CARRIAGE
Carriage of material
L.S. 1.50
LABOUR :
Painter 2nd class Each 0.54000 128.33 69.30
Beldar Each 0.54000 116.67 63.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 144.80
Total 144.80
ADD FOR CONTRACTORS PROFIT@ 10%: 14.48
ADD FOR OVER HEAD CHARGES @5%: 7.24
LABOUR FOR 10.00 Sqm 166.52
LABOUR PER Sqm 16.65
MATERIAL:
Readymixed paint
(White /grey/green shade) 1 litre 0.80000 145.00 166.00
CARRIAGE
Carriage of material
L.S. 1.50
LABOUR :
Painter 2nd class Each 0.54000 128.33 69.30
Beldar Each 0.54000 116.67 63.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 144.80
Total 144.80
ADD FOR CONTRACTORS PROFIT@ 10%: 14.48
ADD FOR OVER HEAD CHARGES @5%: 7.24
LABOUR FOR 10.00 Sqm 166.52
LABOUR PER Sqm 16.65
MATERIAL:
CARRIAGE
Carriage of material
L.S. 1.50
LABOUR :
Painter 2nd class Each 0.36000 128.33 46.20
Beldar Each 0.36000 116.67 42.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 100.70
Total 100.70
ADD FOR CONTRACTORS PROFIT@ 10%: 10.07
ADD FOR OVER HEAD CHARGES @5%: 5.03
LABOUR FOR 10.00 Sqm 115.80
LABOUR PER Sqm 11.60
MATERIAL:
Readymixed paint
(White /grey/green shade) 1 litre 0.46000 145.00 66.70
CARRIAGE
Carriage of material
L.S. 1.50
Painting and Polishing
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR :
Painter 2nd class Each 0.36000 128.33 46.20
Beldar Each 0.36000 116.67 42.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 100.70
Total 100.70
ADD FOR CONTRACTORS PROFIT@ 10%: 10.07
ADD FOR OVER HEAD CHARGES @5%: 5.03
LABOUR FOR 10.00 Sqm 115.80
LABOUR PER Sqm 11.60
MATERIAL:
Paint remover
1 litre 0.70000 130.00 91.00
CARRIAGE:
carriage of material
L.S. 1.00
LABOUR :
Painting and Polishing
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Painter 2nd class Each 0.54000 128.33 69.30
Beldar Each 0.54000 116.67 63.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 147.30
Total 147.30
ADD FOR CONTRACTORS PROFIT@ 10%: 17.73
ADD FOR OVER HEAD CHARGES @5%: 7.36
LABOUR FOR 10.00 Sqm 169.39
LABOUR PER Sqm 16.95
MATERIAL:
Caustic soda
1 kg. 0.73000 30.00 21.00
CARRIAGE:
carriage of material
L.S. 1.00
LABOUR :
Painter 2nd class Each 0.27000 128.33 34.65
Beldar Each 0.54000 116.67 63.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 112.65
Total 112.65
ADD FOR CONTRACTORS PROFIT@ 10%: 11.26
ADD FOR OVER HEAD CHARGES @5%: 5.63
LABOUR FOR 10.00 Sqm 129.54
LABOUR PER Sqm 12.95
MATERIAL:
CARRIAGE:
carriage of material L.S. 1.50
LABOUR :
Painter 2nd class Each 0.81000 128.33 103.95
Beldar Each 0.81000 116.67 94.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 213.45
Total 213.45
Painting and Polishing
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR CONTRACTORS PROFIT@ 10%: 21.34
ADD FOR OVER HEAD CHARGES @5%: 10.67
LABOUR FOR 10.00 Sqm 245.46
LABOUR PER Sqm 24.55
MATERIAL:
CARRIAGE:
carriage of material L.S. 1.50
LABOUR :
Painter 2nd class Each 0.30000 128.33 38.50
Beldar Each 0.30000 116.67 35.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 83.50
Total 83.50
ADD FOR CONTRACTORS PROFIT@ 10%: 8.35
ADD FOR OVER HEAD CHARGES @5%: 4.17
Painting and Polishing
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR FOR 10.00 Sqm 96.02
LABOUR PER Sqm 9.60
MATERIAL:
CARRIAGE:
carriage of material L.S. 2.00
LABOUR :
Painter 2nd class Each 0.30000 128.33 38.50
Beldar Each 0.30000 116.67 35.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 83.50
Total 83.50
ADD FOR CONTRACTORS PROFIT@ 10%: 8.35
ADD FOR OVER HEAD CHARGES @5%: 4.17
LABOUR FOR 10.00 Sqm 96.02
LABOUR PER Sqm 9.60
MATERIAL:
CARRIAGE:
carriage of material L.S. 1.50
LABOUR :
Painter 2nd class Each 0.30000 128.33 38.50
Beldar Each 0.30000 116.67 35.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 83.50
Total 83.50
ADD FOR CONTRACTORS PROFIT@ 10%: 8.35
ADD FOR OVER HEAD CHARGES @5%: 4.17
LABOUR FOR 10.00 Sqm 96.02
LABOUR PER Sqm 9.60
MATERIAL:
LABOUR :
Painter 2nd class Each 0.30000 128.33 38.50
Beldar Each 0.30000 116.67 35.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 83.50
Total 83.50
ADD FOR CONTRACTORS PROFIT@ 10%: 8.35
ADD FOR OVER HEAD CHARGES @5%: 4.17
LABOUR FOR 10.00 Sqm 96.02
LABOUR PER Sqm 9.60
MATERIAL:
CARRIAGE:
carriage of material L.S. 1.50
LABOUR :
Painter 2nd class Each 0.30000 128.33 38.50
Beldar Each 0.30000 116.67 35.00
Painting and Polishing
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
SUNDRIES (Brushes and sand paper etc.) L.S. 10.00
TOTAL : 191.25
ADD FOR CONTRACTORS PROFIT@ 10%: 19.12
ADD FOR OVER HEAD CHARGES @5%: 9.56
COST FOR 10.00 Sqm. 219.93
COST PER Sqm 22.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 83.50
Total 83.50
ADD FOR CONTRACTORS PROFIT@ 10%: 8.35
ADD FOR OVER HEAD CHARGES @5%: 4.17
LABOUR FOR 10.00 Sqm 96.02
LABOUR PER Sqm 9.60
MATERIAL:
CARRIAGE:
carriage of material L.S. 1.50
LABOUR :
Painter 2nd class Each 0.24000 128.33 30.80
Beldar Each 0.24000 116.67 28.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 68.80
Total 68.80
ADD FOR CONTRACTORS PROFIT@ 10%: 6.88
ADD FOR OVER HEAD CHARGES @5%: 3.44
LABOUR FOR 10.00 Sqm 79.02
LABOUR PER Sqm 7.90
MATERIAL:
CARRIAGE:
carriage of material L.S. 1.50
LABOUR :
Painter 2nd class Each 0.24000 128.33 30.80
Beldar Each 0.24000 116.67 28.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 68.80
Total 68.80
ADD FOR CONTRACTORS PROFIT@ 10%: 6.88
ADD FOR OVER HEAD CHARGES @5%: 3.44
LABOUR FOR 10.00 Sqm 79.02
LABOUR PER Sqm 7.90
MATERIAL:
CARRIAGE:
carriage of material L.S. 1.50
LABOUR :
Painter 2nd class Each 0.24000 128.33 30.80
Beldar Each 0.24000 116.67 28.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 68.80
Total 68.80
ADD FOR CONTRACTORS PROFIT@ 10%: 6.88
ADD FOR OVER HEAD CHARGES @5%: 3.44
LABOUR FOR 10.00 Sqm 79.02
LABOUR PER Sqm 7.90
MATERIAL:
Enmel primer.
1 Litre 0.75000 160.00 120.00
CARRIAGE:
carriage of material L.S. 1.50
Painting and Polishing
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR :
Painter 2nd class Each 0.24000 128.33 30.80
Beldar Each 0.24000 116.67 28.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 68.80
Total 68.80
ADD FOR CONTRACTORS PROFIT@ 10%: 6.88
ADD FOR OVER HEAD CHARGES @5%: 3.44
LABOUR FOR 10.00 Sqm 79.02
LABOUR PER Sqm 7.90
MATERIAL:
CARRIAGE:
carriage of material L.S. 1.50
LABOUR :
Painter 2nd class Each 0.24000 128.33 30.80
Beldar Each 0.24000 116.67 28.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 68.80
Total 68.80
ADD FOR CONTRACTORS PROFIT@ 10%: 6.88
ADD FOR OVER HEAD CHARGES @5%: 3.44
LABOUR FOR 10.00 Sqm 79.02
LABOUR PER Sqm 7.90
MATERIAL:
CARRIAGE:
carriage of material L.S. 1.00
LABOUR :
Painter 2nd class Each 0.15000 128.33 19.25
Beldar Each 0.15000 116.67 17.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 46.75
Total 76.75
ADD FOR CONTRACTORS PROFIT@ 10%: 4.68
Painting and Polishing
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ADD FOR OVER HEAD CHARGES @5%: 2.34
LABOUR FOR 10.00 Sqm 53.76
LABOUR PER Sqm 5.40
MATERIAL:
CARRIAGE:
carriage of material L.S. 1.00
LABOUR :
Painter 2nd class Each 0.11000 128.33 14.11
Beldar Each 0.11000 116.67 12.83
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 36.93
Total 36.93
ADD FOR CONTRACTORS PROFIT@ 10%: 3.69
ADD FOR OVER HEAD CHARGES @5%: 1.85
LABOUR FOR 10.00 Sqm 42.47
LABOUR PER Sqm 4.25
MATERIAL:
LABOUR :
Painter 1st class Each 0.54000 148.16 80.00
Beldar Each 0.54000 116.67 63.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 153.00
Total 153.00
ADD FOR CONTRACTORS PROFIT@ 10%: 15.30
ADD FOR OVER HEAD CHARGES @5%: 7.65
LABOUR FOR 10.00 Sqm 175.95
LABOUR PER Sqm 17.60
MATERIAL:
LABOUR :
Painter 1st class Each 0.54000 148.16 80.00
Beldar Each 0.54000 116.67 63.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 153.00
Total 153.00
ADD FOR CONTRACTORS PROFIT@ 10%: 15.30
ADD FOR OVER HEAD CHARGES @5%: 7.65
LABOUR FOR 10.00 Sqm 175.95
LABOUR PER Sqm 17.60
MATERIAL:
LABOUR :
Painter 1st class Each 0.36000 148.16 53.34
Beldar Each 0.36000 116.67 42.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 105.33
Total 105.33
ADD FOR CONTRACTORS PROFIT@ 10%: 10.53
ADD FOR OVER HEAD CHARGES @5%: 5.26
LABOUR FOR 10.00 Sqm 121.12
LABOUR PER Sqm 12.10
MATERIAL:
LABOUR :
Painter 1st class Each 0.36000 148.16 53.34
Beldar Each 0.36000 116.67 42.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 105.33
Total 105.33
ADD FOR CONTRACTORS PROFIT@ 10%: 10.53
ADD FOR OVER HEAD CHARGES @5%: 5.26
LABOUR FOR 10.00 Sqm 121.12
LABOUR PER Sqm 12.10
MATERIAL:
CARRIAGE:
carriage of material L.S. 1.50
LABOUR :
Painter 1st class Each 0.30000 148.16 44.45
Beldar Each 0.30000 116.67 35.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 89.45
Total 89.45
ADD FOR CONTRACTORS PROFIT@ 10%: 8.94
ADD FOR OVER HEAD CHARGES @5%: 4.47
LABOUR FOR 10.00 Sqm 102.86
Painting and Polishing
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR PER Sqm 10.30
MATERIAL:
CARRIAGE:
carriage of material L.S. 1.50
LABOUR :
Painter 1st class Each 0.30000 148.16 44.45
Beldar Each 0.30000 116.67 35.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 89.45
Total 89.45
ADD FOR CONTRACTORS PROFIT@ 10%: 8.94
ADD FOR OVER HEAD CHARGES @5%: 4.47
LABOUR FOR 10.00 Sqm 102.86
LABOUR PER Sqm 10.30
MATERIAL:
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 153.00
Total 153.00
ADD FOR CONTRACTORS PROFIT@ 10%: 15.30
ADD FOR OVER HEAD CHARGES @5%: 7.65
LABOUR FOR 10.00 Sqm 175.95
LABOUR PER Sqm 17.60
MATERIAL:
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 153.00
Total 153.00
ADD FOR CONTRACTORS PROFIT@ 10%: Except on (-a-): 15.30
ADD FOR OVER HEAD CHARGES @5%: Except on (-a-): 7.65
LABOUR FOR 10.00 Sqm 175.95
LABOUR PER Sqm 17.60
MATERIAL:
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 105.33
Total 105.33
ADD FOR CONTRACTORS PROFIT@ 10%: 10.53
ADD FOR OVER HEAD CHARGES @5%: 5.26
LABOUR FOR 10.00 Sqm 121.12
LABOUR PER Sqm 12.10
MATERIAL:
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 105.33
Total 105.33
ADD FOR CONTRACTORS PROFIT@ 10%: 10.53
ADD FOR OVER HEAD CHARGES @5%: 5.26
LABOUR FOR 10.00 Sqm 121.12
LABOUR PER Sqm 12.10
Painting and Polishing
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL:
CARRIAGE:
carriage of material L.S. 1.50
LABOUR :
Painter 1st class Each 0.30000 148.16 44.45
Beldar Each 0.30000 116.67 35.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 89.45
Total 89.45
ADD FOR CONTRACTORS PROFIT@ 10%: 8.94
ADD FOR OVER HEAD CHARGES @5%: 4.47
LABOUR FOR 10.00 Sqm 102.86
LABOUR PER Sqm 10.30
MATERIAL:
LABOUR :
Painter 1st class Each 0.30000 148.16 44.45
Beldar Each 0.30000 116.67 35.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 89.45
Total 89.45
ADD FOR CONTRACTORS PROFIT@ 10%: 8.94
ADD FOR OVER HEAD CHARGES @5%: 4.47
LABOUR FOR 10.00 Sqm 102.86
LABOUR PER Sqm 10.30
MATERIAL :
LABOUR :
Painter 1st class Each 0.54000 148.16 80.00
Beldar Each 0.54000 116.67 63.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 153.00
Total 153.00
ADD FOR CONTRACTORS PROFIT@ 10%: 15.30
ADD FOR OVER HEAD CHARGES @5%: 7.65
LABOUR FOR 10.00 Sqm 175.95
LABOUR PER Sqm 17.60
MATERIAL :
LABOUR :
Painter 1st class Each 0.54000 148.16 80.00
Beldar Each 0.54000 116.67 63.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 153.00
Total 153.00
ADD FOR CONTRACTORS PROFIT@ 10%: 15.30
ADD FOR OVER HEAD CHARGES @5%: 7.65
LABOUR FOR 10.00 Sqm 175.95
LABOUR PER Sqm 17.60
MATERIAL :
LABOUR :
Painter 1st class Each 0.36000 148.16 53.34
Beldar Each 0.36000 116.67 42.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 105.33
Total 105.33
ADD FOR CONTRACTORS PROFIT@ 10%: 10.53
ADD FOR OVER HEAD CHARGES @5%: 5.26
LABOUR FOR 10.00 Sqm 121.12
LABOUR PER Sqm 12.10
MATERIAL :
Readymixed paint
1 Litre 0.65000 160.00 104.00
CARRIAGE :
Carriage of material L.S 1.50
LABOUR :
Painter 1st class Each 0.30000 148.16 44.45
Beldar Each 0.30000 116.67 35.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 89.45
Total 89.45
ADD FOR CONTRACTORS PROFIT@ 10%: 8.94
ADD FOR OVER HEAD CHARGES @5%: 4.47
LABOUR FOR 10.00 Sqm 102.86
LABOUR PER Sqm 10.30
Painting and Polishing
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
16049000 Applying spirit or oil stains (any
colour)on wood and wood based
surfaces to given an even surfaces
including cleaning the surfaces of
all dirt,dust and sand papering so as to
produce a smooth dry and matt
surface including stopping &
knotting.
Detail of cost for 10 sqm.
Material :
Spirit
1 litre 1.63000 75.00 122.25
CARRIAGE :
Carriage of Material L.S 1.50
LABOUR :
Painter 1st class Each 2.15000 148.16 318.54
Beldar Each 0.54000 116.67 63.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 386.54
Total 386.54
ADD FOR CONTRACTORS PROFIT@ 10%: 38.65
ADD FOR OVER HEAD CHARGES @5%: 19.32
LABOUR FOR 10.00 Sqm 444.52
LABOUR PER Sqm 44.45
Painting and Polishing
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Material :
CARRIAGE :
Carriage of Material L.S 1.50
LABOUR :
Painter 1st class Each 0.90000 148.16 133.34
Beldar Each 0.90000 116.67 105.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 248.34
Total 248.34
ADD FOR CONTRACTORS PROFIT@ 10%: Except on (-a-): 24.83
ADD FOR OVER HEAD CHARGES @5%: Except on (-a-): 12.41
LABOUR FOR 10.00 Sqm 285.59
LABOUR PER Sqm 28.55
Painting and Polishing
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Material :
varnish
1 litre 0.75000 115.00 86.25
Repair to surface
L.S 2.50
CARRIAGE :
Carriage of Material L.S 1.50
LABOUR :
Painter 1st class Each 0.36000 148.16 53.34
Beldar Each 0.36000 116.67 42.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 105.33
Total 105.33
ADD FOR CONTRACTORS PROFIT@ 10%: 10.53
ADD FOR OVER HEAD CHARGES @5%: 5.26
LABOUR FOR 10.00 Sqm 121.12
LABOUR PER Sqm 12.10
Material :
varnish
1 litre 0.75000 115.00 86.25
CARRIAGE :
Carriage of Material L.S 1.50
LABOUR :
Painter 1st class Each 0.30000 148.16 44.45
Beldar Each 0.30000 116.67 35.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 89.45
Total 89.45
ADD FOR CONTRACTORS PROFIT@ 10%: 8.94
ADD FOR OVER HEAD CHARGES @5%: 4.47
LABOUR FOR 10.00 Sqm 102.86
LABOUR PER Sqm 10.30
MATERIAL:
Spirit
1 litre 1.60000 75.00 120.00
Painting and Polishing
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Shallac
1 kg. 0.24500 100.00 24.50
CARRIAGE :
Carriagge of material L.S. 1.50
LABOUR :
Painter 2nd class Each 3.50000 128.33 449.15
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 454.15
Total 454.15
ADD FOR CONTRACTORS PROFIT@ 10%: 45.41
ADD FOR OVER HEAD CHARGES @5%: 22.70
LABOUR FOR 10.00 Sqm 522.27
LABOUR PER Sqm 52.20
MATERIAL:
Painting and Polishing
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Spirit
1 litre 0.95000 75.00 71.25
Shallac
1 kg. 0.13000 100.00 13.00
CARRIAGE :
Carriagge of material L.S. 1.50
LABOUR :
Painter 2nd class Each 1.75000 128.33 224.58
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 229.58
Total 229.58
ADD FOR CONTRACTORS PROFIT@ 10%: 22.95
ADD FOR OVER HEAD CHARGES @5%: 11.47
LABOUR FOR 10.00 Sqm 264.01
LABOUR PER Sqm 26.40
MATERIAL:
Spirit
1 litre 0.95000 75.00 71.25
Shallac
1 kg. 0.13000 100.00 13.00
Painting and Polishing
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
woollen cloth putty, sand paper L.S. 10.00
CARRIAGE :
Carriagge of material L.S. 1.50
LABOUR :
Painter 2nd class Each 1.40000 128.33 179.66
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 184.66
Total 184.66
ADD FOR CONTRACTORS PROFIT@ 10%: 18.46
ADD FOR OVER HEAD CHARGES @5%: 9.23
LABOUR FOR 10.00 Sqm 212.35
LABOUR PER Sqm 21.25
MATERIAL:
CARRIAGE :
Carriagge of material L.S. 1.50
LABOUR :
Painter 2nd class Each 0.23000 128.33 29.52
Painting and Polishing
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Beldar Each 0.23000 116.67 26.83
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 66.34
Total 66.34
ADD FOR CONTRACTORS PROFIT@ 10%: 6.63
ADD FOR OVER HEAD CHARGES @5%: 3.31
LABOUR FOR 10.00 Sqm 76.28
LABOUR PER Sqm 7.60
MATERIAL:
CARRIAGE :
Carriagge of material L.S. 1.50
LABOUR :
Painter 2nd class Each 0.20000 128.33 25.67
Beldar Each 0.18000 116.67 21.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 56.66
Total 56.66
ADD FOR CONTRACTORS PROFIT@ 10%: 5.66
ADD FOR OVER HEAD CHARGES @5%: 2.83
LABOUR FOR 10.00 Sqm 65.15
LABOUR PER Sqm 6.50
MATERIAL:
CARRIAGE :
Carriagge of material L.S. 1.50
LABOUR :
Painter 2nd class Each 0.70000 128.33 89.83
Beldar Each 0.70000 116.67 81.67
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 181.49
Total 181.49
ADD FOR CONTRACTORS PROFIT@ 10%: 18.15
ADD FOR OVER HEAD CHARGES @5%: 9.07
LABOUR FOR 10.00 Sqm 208.71
LABOUR PER Sqm 20.90
MATERIAL:
CARRIAGE :
Carriagge of material L.S. 1.50
LABOUR :
Painter 2nd class Each 0.35000 128.33 44.92
Beldar Each 0.35000 116.67 40.83
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 95.74
Total 95.74
ADD FOR CONTRACTORS PROFIT@ 10%: 9.57
ADD FOR OVER HEAD CHARGES @5%: 4.78
LABOUR FOR 10.00 Sqm 110.10
LABOUR PER Sqm 11.00
MATERIAL :
CARRIAGE :
Carriagge of material L.S. 1.50
LABOUR :
Painter 2nd class Each 0.54000 128.33 69.30
Beldar Each 0.54000 116.67 63.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 142.30
Total 142.30
ADD FOR CONTRACTORS PROFIT@ 10%: 14.23
ADD FOR OVER HEAD CHARGES @5%: 7.11
LABOUR FOR 10.00 Sqm 163.64
LABOUR PER Sqm 16.35
MATERIAL :
CARRIAGE :
Carriagge of material L.S. 1.50
LABOUR :
Painter 2nd class Each 0.36000 128.33 46.20
Beldar Each 0.36000 116.67 42.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 98.20
Total 98.20
ADD FOR CONTRACTORS PROFIT@ 10%: 9.82
ADD FOR OVER HEAD CHARGES @5%: 4.91
LABOUR FOR 10.00 Sqm 112.93
LABOUR PER Sqm 11.30
MATERIAL :
CARRIAGE :
Carriagge of material L.S. 1.50
Painting and Polishing
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR :
Painter 2nd class Each 0.30000 128.33 38.50
Beldar Each 0.30000 116.67 35.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 83.50
Total 83.50
ADD FOR CONTRACTORS PROFIT@ 10%: 8.35
ADD FOR OVER HEAD CHARGES @5%: 4.17
LABOUR FOR 10.00 Sqm 96.02
LABOUR PER Sqm 9.60
MATERIAL :
CARRIAGE :
Carriagge of material L.S. 1.50
LABOUR :
Painter 2nd class Each 0.36000 128.33 46.20
Beldar Each 0.36000 116.67 42.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 98.20
Total 98.20
ADD FOR CONTRACTORS PROFIT@ 10%: 9.82
ADD FOR OVER HEAD CHARGES @5%: 4.91
LABOUR FOR 10.00 Sqm 112.93
LABOUR PER Sqm 11.30
MATERIAL :
CARRIAGE :
Carriagge of material L.S. 1.50
LABOUR :
Painter 2nd class Each 0.30000 128.33 38.50
Beldar Each 0.30000 116.67 35.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 83.50
Total 83.50
ADD FOR CONTRACTORS PROFIT@ 10%: 8.35
ADD FOR OVER HEAD CHARGES @5%: 4.17
LABOUR FOR 10.00 Sqm 96.02
LABOUR PER Sqm 9.60
MATERIAL :
CARRIAGE :
Carriagge of material L.S. 1.50
LABOUR :
Beldar Each 0.43000 116.67 50.16
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 60.16
Total 60.16
ADD FOR CONTRACTORS PROFIT@ 10%: 6.01
ADD FOR OVER HEAD CHARGES @5%: 3.00
LABOUR FOR 10.00 Sqm 69.17
LABOUR PER Sqm 6.90
MATERIAL :
CARRIAGE :
Carriagge of material L.S. 1.00
LABOUR :
Beldar Each 0.36000 116.67 42.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 47.00
Total 47.00
ADD FOR CONTRACTORS PROFIT@ 10%: 4.70
ADD FOR OVER HEAD CHARGES @5%: 2.35
LABOUR FOR 10.00 Sqm 54.05
LABOUR PER Sqm 5.40
MATERIAL :
CARRIAGE :
Carriagge of material L.S. 1.00
LABOUR :
Beldar Each 0.30000 116.67 35.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 40.00
Total 40.00
ADD FOR CONTRACTORS PROFIT@ 10%: 4.00
ADD FOR OVER HEAD CHARGES @5%: 2.00
LABOUR FOR 10.00 Sqm 46.00
LABOUR PER Sqm 4.60
MATERIAL :
CARRIAGE :
Carriagge of material L.S. 2.50
LABOUR :
Beldar Each 0.25000 116.67 29.17
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 32.66
Total 32.66
ADD FOR CONTRACTORS PROFIT@ 10%: 3.26
ADD FOR OVER HEAD CHARGES @5%: 1.63
LABOUR FOR 10.00 Sqm 37.55
LABOUR PER Sqm 3.75
MATERIAL :
CARRIAGE :
Carriagge of material L.S. 1.50
LABOUR :
Beldar Each 0.25000 116.67 29.17
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 34.16
Total 34.16
ADD FOR CONTRACTORS PROFIT@ 10%: 3.41
ADD FOR OVER HEAD CHARGES @5%: 1.70
LABOUR FOR 10.00 Sqm 39.27
LABOUR PER Sqm 3.90
MATERIAL :
CARRIAGE :
Carriagge of material L.S. 1.00
LABOUR :
Painter 2nd class Each 0.25 128.33 32.08
Beldar Each 0.25000 116.67 29.17
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 71.24
Total 71.24
ADD FOR CONTRACTORS PROFIT@ 10%: 7.12
ADD FOR OVER HEAD CHARGES @5%: 3.56
LABOUR FOR 10.00 Sqm 81.92
LABOUR PER Sqm 8.20
MATERIAL :
LABOUR :
Painter 2nd class Each 0.25000 128.33 32.08
Beldar Each 0.25000 116.67 29.17
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 71.24
Total 71.24
ADD FOR CONTRACTORS PROFIT@ 10%: 7.12
ADD FOR OVER HEAD CHARGES @5%: 3.56
LABOUR FOR 10.00 Sqm 81.92
LABOUR PER Sqm 8.20
MATERIAL :
Flat oil wall paint (interior use) 1 litre 1.10000 180.00 198.00
CARRIAGE :
Carriagge of material L.S. 1.00
Painting and Polishing
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR :
Painter 1st class Each 0.54000 148.16 80.01
Beldar Each 0.54000 116.67 63.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 148.00
Total 148.00
ADD FOR CONTRACTORS PROFIT@ 10%: 14.80
ADD FOR OVER HEAD CHARGES @5%: 7.40
LABOUR FOR 10.00 Sqm 170.20
LABOUR PER Sqm 17.00
MATERIAL :
Flat oil wall paint (interior use) 1 litre 0.65000 180.00 117.00
CARRIAGE :
Carriagge of material L.S. 1.00
LABOUR :
Painter 1st class Each 0.36000 148.16 53.34
Beldar Each 0.36000 116.67 42.00
Painting and Polishing
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 98.33
Total 98.33
ADD FOR CONTRACTORS PROFIT@ 10%: 9.83
ADD FOR OVER HEAD CHARGES @5%: 4.91
LABOUR FOR 10.00 Sqm 113.07
LABOUR PER Sqm 11.30
MATERIAL :
Flat oil wall paint (interior use) 1 litre 0.65000 180.00 117.00
CARRIAGE :
Carriagge of material L.S. 1.00
LABOUR :
Painter 1st class Each 0.30000 148.16 44.45
Beldar Each 0.30000 116.67 35.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 82.45
Total 82.45
ADD FOR CONTRACTORS PROFIT@ 10%: 8.24
ADD FOR OVER HEAD CHARGES @5%: 4.12
LABOUR FOR 10.00 Sqm 94.81
LABOUR PER Sqm 9.50
MATERIAL :
CARRIAGE :
Carriagge of material L.S. 1.00
LABOUR :
Painter 1st class Each 0.54000 148.16 80.01
Beldar Each 0.54000 116.67 63.00
LABOUR RATE :
Painting and Polishing
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
ACTUAL LABOUR+SUNDRIES 153.00
Total 153.00
ADD FOR CONTRACTORS PROFIT@ 10%: 15.30
ADD FOR OVER HEAD CHARGES @5%: 7.65
LABOUR FOR 10.00 Sqm 175.95
LABOUR PER Sqm 17.60
MATERIAL :
CARRIAGE :
Carriagge of material L.S. 1.00
LABOUR :
Painter 1st class Each 0.54000 148.16 80.01
Beldar Each 0.54000 116.67 63.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 153.00
Total 153.00
ADD FOR CONTRACTORS PROFIT@ 10%: 15.30
ADD FOR OVER HEAD CHARGES @5%: 7.65
LABOUR FOR 10.00 Sqm 175.95
LABOUR PER Sqm 17.60
MATERIAL :
CARRIAGE :
Carriagge of material L.S. 1.00
LABOUR :
Painter 1st class Each 0.36000 148.16 53.34
Beldar Each 0.36000 116.67 42.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 105.33
Total 105.33
ADD FOR CONTRACTORS PROFIT@ 10%: 10.53
ADD FOR OVER HEAD CHARGES @5%: 5.26
LABOUR FOR 10.00 Sqm 121.12
LABOUR PER Sqm 12.10
MATERIAL :
CARRIAGE :
Carriagge of material L.S. 1.00
LABOUR :
Painter 1st class Each 0.36000 148.16 53.34
Beldar Each 0.36000 116.67 42.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 105.33
Total 105.33
ADD FOR CONTRACTORS PROFIT@ 10%: 10.53
ADD FOR OVER HEAD CHARGES @5%: 5.26
LABOUR FOR 10.00 Sqm 121.12
LABOUR PER Sqm 12.10
MATERIAL :
CARRIAGE :
Carriagge of material L.S. 1.00
LABOUR :
Painter 1st class Each 0.30000 148.16 44.45
Beldar Each 0.30000 116.67 35.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 89.45
Total 89.45
ADD FOR CONTRACTORS PROFIT@ 10%: 8.94
ADD FOR OVER HEAD CHARGES @5%: 4.47
LABOUR FOR 10.00 Sqm 102.86
LABOUR PER Sqm 10.30
MATERIAL :
CARRIAGE :
Carriagge of material L.S. 1.00
LABOUR :
Painter 1st class Each 0.30000 148.16 44.45
Beldar Each 0.30000 116.67 35.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 89.45
Total 89.45
ADD FOR CONTRACTORS PROFIT@ 10%: 8.94
ADD FOR OVER HEAD CHARGES @5%: 4.47
LABOUR FOR 10.00 Sqm 102.86
LABOUR PER Sqm 10.30
Painting and Polishing
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
CARRIAGE :
Carriagge of material L.S. 1.00
LABOUR :
Painter 1st class Each 0.54000 148.16 80.01
Beldar Each 0.54000 116.67 63.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 153.00
Total 153.00
ADD FOR CONTRACTORS PROFIT@ 10%: 15.30
ADD FOR OVER HEAD CHARGES @5%: 7.65
LABOUR FOR 10.00 Sqm 175.95
LABOUR PER Sqm 17.60
MATERIAL :
CARRIAGE :
Carriagge of material L.S. 1.00
LABOUR :
Painter 1st class Each 0.36000 148.16 53.34
Beldar Each 0.36000 116.67 42.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 105.33
Total 105.33
ADD FOR CONTRACTORS PROFIT@ 10%: 10.53
ADD FOR OVER HEAD CHARGES @5%: 5.26
LABOUR FOR 10.00 Sqm 121.12
LABOUR PER Sqm 12.10
MATERIAL :
CARRIAGE :
Carriagge of material L.S. 1.00
LABOUR :
Painting and Polishing
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Painter 1st class Each 0.30000 148.16 44.45
Beldar Each 0.30000 116.67 35.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 89.45
Total 89.45
ADD FOR CONTRACTORS PROFIT@ 10%: 8.94
ADD FOR OVER HEAD CHARGES @5%: 4.47
LABOUR FOR 10.00 Sqm 102.86
LABOUR PER Sqm 10.30
MATERIAL :
CARRIAGE :
Carriagge of material L.S. 9.50
LABOUR :
Painter 1st class Each 0.40000 148.16 59.26
Beldar Each 0.40000 116.67 46.67
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 115.92
Total 115.92
ADD FOR CONTRACTORS PROFIT@ 10%: 11.59
ADD FOR OVER HEAD CHARGES @5%: 5.75
LABOUR FOR 10.00 Sqm 133.30
LABOUR PER Sqm 13.35
MATERIAL :
CARRIAGE :
Carriagge of material L.S. 9.50
LABOUR :
Painter 1st class Each 0.40000 148.16 59.26
Beldar Each 0.40000 116.67 46.67
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 115.92
Total 115.92
ADD FOR CONTRACTORS PROFIT@ 10%: 11.59
ADD FOR OVER HEAD CHARGES @5%: 5.75
LABOUR FOR 10.00 Sqm 133.30
LABOUR PER Sqm 13.35
Painting and Polishing
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
16082000 Coal tarring one coat on previously
painted concrete/masonry/asbestos
cement/plastered surfaces using
0.12 litres of coal tar per sqm to
give an even shade including
cleaning of all dirt,dust and other
foreign matter.
Surfaces over 10 cum in with girth
Detail of cost for 10 sqm.
MATERIAL :
CARRIAGE :
Carriagge of material L.S. 1.00
LABOUR :
Beldar Each 0.36000 116.67 42.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 47.00
Total 47.00
ADD FOR CONTRACTORS PROFIT@ 10%: 4.70
ADD FOR OVER HEAD CHARGES @5%: 2.35
LABOUR FOR 10.00 Sqm 54.05
LABOUR PER Sqm 5.40
MATERIAL :
CARRIAGE :
Carriagge of material L.S. 1.00
LABOUR :
Painter 1st class Each 6.00000 148.16 888.96
Beldar Each 2.00000 116.67 233.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1146.30
Total 1146.30
ADD FOR CONTRACTORS PROFIT@ 10%: 114.63
ADD FOR OVER HEAD CHARGES @5%: 57.31
Cost for 100 letters/figures of 15 cm height. 1318.24
Cost per letter/figure per cm. height 0.90
16083020 Roman(letters/figures)
MATERIAL :
CARRIAGE :
Carriagge of material L.S. 1.00
LABOUR :
Painter 1st class Each 6.00000 148.16 888.96
Beldar Each 2.00000 116.67 233.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1146.30
Total 1146.30
ADD FOR CONTRACTORS PROFIT@ 10%: 114.63
ADD FOR OVER HEAD CHARGES @5%: 57.31
Cost for 100 letters/figures of 15 cm height. 1318.24
Cost per letter/figure per cm. height 0.90
16083030 Italic(letters/figures)
MATERIAL :
CARRIAGE :
Carriagge of material L.S. 1.00
LABOUR :
Painter 1st class Each 6.00000 148.16 888.96
Beldar Each 2.00000 116.67 233.34
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1146.30
Total 1146.30
ADD FOR CONTRACTORS PROFIT@ 10%: 114.63
ADD FOR OVER HEAD CHARGES @5%: 57.31
Cost for 100 letters/figures of 15 cm height. 1318.24
Cost per letter/figure per cm. height 0.90
16083040 Indian(letters/figures)
MATERIAL :
CARRIAGE :
Carriagge of material L.S. 1.00
LABOUR :
Painter 1st class Each 6.60000 148.16 977.85
Beldar Each 2.20000 116.67 256.67
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1258.52
Total 1258.52
ADD FOR CONTRACTORS PROFIT@ 10%: 125.85
ADD FOR OVER HEAD CHARGES @5%: 62.92
Cost for 100 letters/figures of 15 cm height. 1447.29
Cost per letter/figure per cm. height 0.95
MATERIAL :
CARRIAGE :
Carriagge of material L.S. 1.00
LABOUR :
Painter 1st class Each 18.00000 148.16 2666.88
Beldar Each 6.00000 116.67 700.02
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 3390.90
Total 3390.90
ADD FOR CONTRACTORS PROFIT@ 10%: 339.09
ADD FOR OVER HEAD CHARGES @5%: 169.54
Cost for 100 letters/figures of 15 cm height. 3899.53
Cost per letter/figure per cm. height 39.00
MATERIAL :
Total : 16.80
ADD FOR CONTRACTORS PROFIT@ 10%: 1.68
ADD FOR OVER HEAD CHARGES @5%: 0.84
Cost for 100 letters/figures of 15 cm height. 19.32
Cost per letter/figure per cm. height 0.02
MATERIAL :
Total : 16.80
ADD FOR CONTRACTORS PROFIT@ 10%: 1.68
ADD FOR OVER HEAD CHARGES @5%: 0.84
Cost for 100 letters/figures of 15 cm height. 19.32
Cost per letter/figure per cm. height 0.02
MATERIAL :
Total : 22.40
ADD FOR CONTRACTORS PROFIT@ 10%: 2.24
ADD FOR OVER HEAD CHARGES @5%: 1.12
Cost for 100 letters/figures of 15 cm height. 25.76
Cost per letter/figure per cm. height 0.02
Total : 22.40
ADD FOR CONTRACTORS PROFIT@ 10%: 2.24
ADD FOR OVER HEAD CHARGES @5%: 1.12
Cost for 100 letters/figures of 15 cm height. 25.76
Cost per letter/figure per cm. height 0.02
MATERIAL :
Total : 50.40
ADD FOR CONTRACTORS PROFIT@ 10%: 5.04
ADD FOR OVER HEAD CHARGES @5%: 2.52
Cost for 100 .00 Figures 57.96
Cost per figure 0.60
MATERIAL :
Total : 50.40
ADD FOR CONTRACTORS PROFIT@ 10%: 5.04
ADD FOR OVER HEAD CHARGES @5%: 2.52
Cost for 100 .00 Figures 57.96
Cost per figure 0.60
MATERIAL :
Total : 67.20
ADD FOR CONTRACTORS PROFIT@ 10%: 6.72
ADD FOR OVER HEAD CHARGES @5%: 3.36
Cost for 100 .00 Figures 77.28
Cost per figure 0.75
MATERIAL :
Total : 67.20
ADD FOR CONTRACTORS PROFIT@ 10%: 6.72
ADD FOR OVER HEAD CHARGES @5%: 3.36
Cost for 100 .00 Figures 77.28
Cost per figure 0.75
MATERIAL :
CARRIAGE :
Carriagge of material L.S. 0.50
LABOUR :
Painter 2nd class Each 4.00000 128.33 513.32
Beldar Each 1.00000 116.67 116.67
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 639.99
Total 639.99
ADD FOR CONTRACTORS PROFIT@ 10%: 63.99
ADD FOR OVER HEAD CHARGES @5%: 32.00
Cost for 100 letters/figures of 15 cm height. 735.98
Cost per letter/figure per cm. height 0.50
MATERIAL :
CARRIAGE :
Carriagge of material L.S. 0.50
LABOUR :
Painter 2nd class Each 4.00000 128.33 513.32
Beldar Each 1.00000 116.67 116.67
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 639.99
Total 639.99
ADD FOR CONTRACTORS PROFIT@ 10%: 63.99
ADD FOR OVER HEAD CHARGES @5%: 32.00
Cost for 100 letters/figures of 15 cm height. 735.98
Cost per letter/figure per cm. height 0.50
MATERIAL :
CARRIAGE :
Carriagge of material L.S. 0.50
LABOUR :
Painter 2nd class Each 4.00000 128.33 513.32
Beldar Each 1.00000 116.67 116.67
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 639.99
Total 639.99
ADD FOR CONTRACTORS PROFIT@ 10%: 63.99
ADD FOR OVER HEAD CHARGES @5%: 32.00
Cost for 100 letters/figures of 15 cm height. 735.98
Cost per letter/figure per cm. height 0.50
MATERIAL :
CARRIAGE :
Carriagge of material L.S. 0.50
LABOUR :
Painter 2nd class Each 4.00000 128.33 513.32
Beldar Each 1.00000 116.67 116.67
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 639.99
Total 639.99
ADD FOR CONTRACTORS PROFIT@ 10%: 63.99
ADD FOR OVER HEAD CHARGES @5%: 32.00
Cost for 100 letters/figures of 15 cm height. 735.98
Cost per letter/figure per cm. height 0.50
MATERIAL :
Synthetic enamel paint (other than White) 1 litre 0.37000 170.00 62.90
CARRIAGE :
Carriagge of material L.S. 0.50
LABOUR :
Painter 2nd class Each 4.00000 128.33 513.32
Beldar Each 1.00000 116.67 116.67
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 639.99
Total 639.99
ADD FOR CONTRACTORS PROFIT@ 10%: 63.99
ADD FOR OVER HEAD CHARGES @5%: 32.00
Cost for 100 letters/figures of 15 cm height. 735.98
Cost per letter/figure per cm. height 0.50
MATERIAL :
CARRIAGE :
Carriagge of material L.S. 2.00
LABOUR :
Painter 1st class Each 0.36000 148.16 53.33
Beldar Each 0.36000 116.67 42.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 103.33
Total 103.33
ADD FOR CONTRACTORS PROFIT@ 10%: 10.33
ADD FOR OVER HEAD CHARGES @5%: 5.16
COST FOR 10.00 sqm. 118.82
COST PER sqm. 11.90
Painting and Polishing
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
16089000 Sealing surfaces previously treated
with tar, wood preservative
etc.with one coat of knotting to
prevent bleeding through paint
Details of cost for 10 sqm
MATERIAL :
CARRIAGE :
Carriagge of material L.S. 2.50
LABOUR :
Painter 1st class Each 0.23000 148.16 34.07
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 41.07
Total 41.07
ADD FOR CONTRACTORS PROFIT@ 10%: 4.10
ADD FOR OVER HEAD CHARGES @5%: 2.05
COST FOR 10.00 sqm. 47.22
COST PER sqm. 4.70
MATERIAL :
Knotting materials
Tranparent wood filter. 1 litre 0.71000 135.00 98.85
CARRIAGE :
Carriagge of material L.S. 2.50
Painting and Polishing
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR :
Painter 1st class Each 0.40000 148.16 59.26
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 66.26
Total 66.26
ADD FOR CONTRACTORS PROFIT@ 10%: 6.62
ADD FOR OVER HEAD CHARGES @5%: 3.31
COST FOR 10.00 sqm. 76.19
COST PER sqm. 7.60
MATERIAL :
CARRIAGE :
Carriagge of material L.S. 1.00
LABOUR :
Painter 1st class Each 0.54000 148.16 80.00
Beldar Each 0.54000 116.67 63.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 163.00
Total 163.00
ADD FOR CONTRACTORS PROFIT@ 10%: 16.30
ADD FOR OVER HEAD CHARGES @5%: 8.15
COST FOR 10.00 sqm. 187.45
COST PER sqm. 18.75
MATERIAL :
CARRIAGE :
Carriagge of material L.S. 1.00
LABOUR :
Painter 1st class Each 0.36000 148.16 53.33
Beldar Each 0.36000 116.67 42.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 105.33
Total 105.33
ADD FOR CONTRACTORS PROFIT@ 10%: 10.53
ADD FOR OVER HEAD CHARGES @5%: 5.26
COST FOR 10.00 sqm. 121.12
COST PER sqm. 12.10
MATERIAL :
Aluminium paint
1 litre 0.80000 200.00 160.00
CARRIAGE :
Carriagge of material L.S. 1.50
LABOUR :
Painter 2nd class Each 0.54000 128.33 69.30
Beldar Each 0.54000 116.67 63.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 140.80
Total 140.80
ADD FOR CONTRACTORS PROFIT@ 10%: 14.08
ADD FOR OVER HEAD CHARGES @5%: 7.04
COST FOR 10.00 sqm. 161.92
COST PER sqm. 16.20
MATERIAL :
Aluminium paint
1 litre 0.46000 200.00 92.00
CARRIAGE :
Painting and Polishing
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Carriagge of material L.S. 1.50
LABOUR :
Painter 2nd class Each 0.36000 128.33 46.20
Beldar Each 0.36000 116.67 42.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 96.70
Total 96.70
ADD FOR CONTRACTORS PROFIT@ 10%: 9.67
ADD FOR OVER HEAD CHARGES @5%: 4.83
COST FOR 10.00 sqm. 111.20
COST PER sqm. 11.20
MATERIAL :
Bitumastic paint.
1 litre 1.52000 110.00 167.20
CARRIAGE :
Carriagge of material L.S. 1.50
LABOUR :
Painter 2nd class Each 0.84000 128.33 107.80
Beldar Each 0.84000 116.67 98.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 215.80
Total 215.80
ADD FOR CONTRACTORS PROFIT@ 10%: 21.58
ADD FOR OVER HEAD CHARGES @5%: 10.79
COST FOR 10.00 sqm. 248.17
COST PER sqm. 24.80
MATERIAL :
Bitumastic paint.
1 litre 0.57000 110.00 62.70
CARRIAGE :
Carriagge of material L.S. 1.50
LABOUR :
Painter 2nd class Each 0.36000 128.33 46.20
Beldar Each 0.36000 116.67 42.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 98.20
Total 98.20
ADD FOR CONTRACTORS PROFIT@ 10%: 9.82
ADD FOR OVER HEAD CHARGES @5%: 4.91
COST FOR 10.00 sqm. 112.93
COST PER sqm. 11.30
MATERIAL :
Bitumastic paint.
1 litre 0.95000 110.00 104.50
CARRIAGE :
Carriagge of material L.S. 1.50
LABOUR :
Painter 2nd class Each 0.54000 128.33 69.30
Beldar Each 0.54000 116.67 63.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 142.30
Total 142.30
ADD FOR CONTRACTORS PROFIT@ 10%: 14.23
ADD FOR OVER HEAD CHARGES @5%: 7.11
COST FOR 10.00 sqm. 163.64
COST PER sqm. 16.35
MATERIAL :
LABOUR :
Painter 2nd class Each 0.49000 128.33 62.88
Beldar Each 0.49000 116.67 57.16
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 129.04
Total 129.04
ADD FOR CONTRACTORS PROFIT@ 10%: 12.90
ADD FOR OVER HEAD CHARGES @5%: 6.45
COST FOR 100.00 mtr. 148.39
COST PER meter 1.50
MATERIAL :
CARRIAGE :
Carriagge of material L.S. 0.50
LABOUR :
Painter 2nd class Each 0.49000 128.33 62.88
Beldar Each 0.49000 116.67 57.16
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 129.04
Total 129.04
ADD FOR CONTRACTORS PROFIT@ 10%: 12.90
ADD FOR OVER HEAD CHARGES @5%: 6.45
COST FOR 100.00 mtr. 148.39
COST PER mtr. 1.50
MATERIAL :
CARRIAGE :
Carriagge of material L.S. 0.50
LABOUR :
Painter 2nd class Each 0.17000 128.33 21.82
Beldar Each 0.17000 116.67 19.83
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 49.65
Total 49.65
ADD FOR CONTRACTORS PROFIT@ 10%: 4.96
ADD FOR OVER HEAD CHARGES @5%: 2.48
COST FOR 1.00 Fire place 57.09
COST PER fire place 57.10
Painting and Polishing
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
MATERIAL :
CARRIAGE :
Carriagge of material L.S. 9.50
LABOUR :
Painter 2nd class Each 0.17000 128.33 21.82
Beldar Each 0.17000 116.67 19.83
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 49.65
Total 49.65
ADD FOR CONTRACTORS PROFIT@ 10%: 4.96
ADD FOR OVER HEAD CHARGES @5%: 2.48
COST FOR 1.00 Fire place 57.09
COST PER fire place 57.10
MATERIAL :
CARRIAGE :
Carriagge of material L.S. 0.50
Painting and Polishing
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
LABOUR :
Painter 2nd class Each 0.27000 128.33 34.65
Beldar Each 0.27000 116.67 31.50
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 76.15
Total 76.15
ADD FOR CONTRACTORS PROFIT@ 10%: 7.61
ADD FOR OVER HEAD CHARGES @5%: 3.80
LABOUR FOR 100.00 Metre 87.56
LABOUR PER Metre 0.90
Materials
CARRIAGE
LABOUR :
Painter 2nd class each 0.25000 128.33 32.08
Beldar each 0.25000 116.67 29.17
Painting and Polishing
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
TOTAL : 204.65
ADD FOR CONTRACTORS PROFIT 10% : 20.46
ADD FOR OVER HEAD CHARGES @5% : 10.23
COST FOR 10.00 Sqm 235.34
COST PER sqm 23.50
Labour Per sq,m 8.75
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 76.25
Materials
CARRIAGE
LABOUR :
Painter 1st Class each 0.54000 148.16 80.00
Beldar each 0.54000 116.67 63.00
TOTAL : 651.40
ADD FOR CONTRACTORS PROFIT 10% : 65.14
ADD FOR OVER HEAD CHARGES @5% : 32.57
Painting and Polishing
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
COST FOR 10.00 Sqm 749.10
COST PER sqm 74.90
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 158.00
Materials
CARRIAGE
LABOUR :
Painter 1st Class each 0.40000 148.16 59.26
Beldar each 0.40000 116.67 46.66
Bhisti each 0.40000 116.67 46.66
TOTAL : 272.58
Add. For water charges @ 1.5% 4.08
Total 276.66
ADD FOR CONTRACTORS PROFIT 10% : 27.66
ADD FOR OVER HEAD CHARGES @5% : 13.83
COST FOR 10.00 Sqm 318.15
COST PER sqm 31.80
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 162.58
Add. For water charges 4.08
Painting and Polishing
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Total 166.66
ADD FOR CONTRACTORS PROFIT @10% 16.66
ADD FOR OVER HEAD CHARGES @5% 8.33
LABOUR FOR 10.00 sqm 191.65
LABOUR PER Sqm 19.15
Materials
CARRIAGE
LABOUR :
Painter 1st Class each 0.54000 148.16 80.00
Beldar each 0.54000 116.67 63.00
TOTAL : 469.60
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 150.00
Materials
CARRIAGE
LABOUR :
Painter 1st Class each 0.54000 148.16 80.00
Beldar each 0.54000 116.67 63.00
TOTAL : 385.40
Add. For water charges @ 1.5% 5.78
Total 391.18
ADD FOR CONTRACTORS PROFIT 10% : 39.11
ADD FOR OVER HEAD CHARGES @5% : 19.55
COST FOR 10.00 Sqm 449.85
COST PER sqm 44.98
Labour per sqm 18.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 150.00
Add. For water charges @ 1.5% 5.90
Total 156.40
ADD FOR CONTRACTORS PROFIT @10% 15.64
ADD FOR OVER HEAD CHARGES @5% 7.82
LABOUR FOR 10.00 sqm 179.86
LABOUR PER Sqm 18.00
Painting and Polishing
ITEM CODE DESCRIPTION UNIT QTY. RATE COST REMARKS
Materials
CARRIAGE
LABOUR :
Painter 2nd class each 3.50000 128.33 449.15
TOTAL : 998.15
ADD FOR CONTRACTORS PROFIT 10% : 99.82
ADD FOR OVER HEAD CHARGES @5% : 49.91
COST FOR 10.00 Sqm 1147.88
COST PER sqm 114.80
Labour per sqm 52.20
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 454.15
ADD FOR CONTRACTORS PROFIT @10% 45.42
ADD FOR OVER HEAD CHARGES @5% 22.71
LABOUR FOR 10.00 sqm 522.28
LABOUR PER Sqm 52.20
Confidential
For Office use
VOLUME - VI
ANALYSIS FOR SCHEDULE OF RATES 2009
(VOLUME VI)
CONTENTS
Chapter No. Name of Sub-head Page No.
XVII Plastering, pointing, white washing , Colour
Washing, Distempering and other finishes
XVIII Repairs to Buildings
XIX Miscellaneous Work
CHAPTER XVII
PLASTERING, POINTING, WHITE
WASHING, COLOUR WASHING,
DISTEMPERING AND OTHER FINISHES
CHAPTER XVII
PLASTERING, POINTING, WHITE WASHING , COLOUR
WASHING, DISTEMPERING AND OTHER FINISHES
Notes :
1 The through rates include the carriage of all materials for 100 meters on head load
and one kilometer by mechanical transport.
2 The labour rates include the sundry items like sand papers, scrappers, soap and
soda etc. as also the water charges.
3 The labour rates also include the labor required for thoroughly mixing the mortar
and all sorts of scaffolding and ladders, etc.
4 The paints used shall be specified in HPPWD Specification 1993 of Grade I or
as declared by the Engineer. In-Chief, HPPWD.
CHAPTER -XVII
PLASTERING, POINTING, WHITE WASHING, COLOUR WASHING, DISTEMPERING & OTHER
FINISHES
MATERIAL :
Lime surkhi mortar 1:1:1
(1 lime:1surkhi:1sand).
Rate as per item no. : 0407. cum. 0.1650 2405.75 396.95
LABOUR :
Mason 2nd Class Each 0.8000 158.67 126.94
Beldar Each 0.8000 116.67 93.34
Bhishti Each 0.9800 116.67 114.34
MATERIAL :
MATERIAL :
lime surkhi mortar 1:1:1
(1 lime putty:1 sand :1 surkhi)
cum. 0.1140 2405.75 274.26
LABOUR :
Mason 2nd Class Each 1.5000 158.67 238.01
Beldar Each 1.5000 116.67 175.01
Bhishti Each 1.4200 116.67 165.67
MATERIAL :
lime surkhi mortar 1:1:1
(1 lime putty:1 sand :1 surkhi)
cum. 0.1720 2405.75 413.79
MATERIAL :
lime surkhi mortar 1:1:1
(1 lime putty:1 sand :1 surkhi)
cum. 0.1650 2405.75 396.95
MATERIAL :
lime surkhi mortar 1:1:1
(1 lime putty:1 sand :1 surkhi)
cum. 0.2270 2405.75 546.11
MATERIAL :
lime surkhi mortar 1:1:1
(1 lime putty:1 sand :1 surkhi)
cum. 0.2820 2405.75 678.42
MATERIAL :
lime surkhi mortar 1:1:2
(1 lime putty:1 surkhi:2 sand)
cum. 0.1650 2058.25 339.61
LABOUR :
Mason 2nd Class Each 0.8000 158.67 126.94
Beldar Each 0.8000 116.67 93.34
Bhishti Each 0.9800 116.67 114.34
TOTAL : 403.90
WATER CHARGES @ 1.5% : 10.30
TOTAL : 414.20
ADD FOR CONTRACTORS PROFIT @10% : 41.42
ADD FOR OVER HEAD CHARGES @5% : 20.71
LABOUR FOR 10.000 sqm. 476.33
LABOUR RATE PER sqm. 47.65
PLASTERING, POINTING, WHITE WASHING, COLOUR WASHING, DISTEMPERING & OTHER
FINISHES
MATERIAL :
lime surkhi mortar 1:1:2
(1 lime putty:1 surkhi:2 sand)
cum. 0.1720 2058.25 354.02
LABOUR :
Mason 2nd Class Each 0.8300 158.67 131.70
Beldar Each 0.8300 116.67 96.84
Bhishti Each 0.9800 116.67 114.34
TOTAL : 414.57
WATER CHARGES @ 1.5% : 10.64
TOTAL : 425.21
ADD FOR CONTRACTORS PROFIT @10% : 42.52
ADD FOR OVER HEAD CHARGES @5% : 21.26
LABOUR FOR 10.000 sqm. 488.99
LABOUR RATE PER sqm. 48.90
MATERIAL :
lime surkhi mortar 1:1:2
(1 lime putty:1 surkhi:2 sand)
cum. 0.1140 2058.25 234.64
MATERIAL :
MATERIAL :
lime surkhi mortar 1:1:2
(1 lime putty:1 surkhi:2 sand)
cum. 0.1650 2058.25 339.61
MATERIAL :
lime surkhi mortar 1:1:2
(1 lime putty:1 surkhi:2 sand)
cum. 0.2270 2058.25 467.22
MATERIAL :
lime surkhi mortar 1:1:2
(1 lime putty:1 surkhi:2 sand)
cum. 0.2820 2058.25 580.43
MATERIAL :
lime mortar 1:2
(1 lime putty:2sand)
cum. 0.1650 2358.20 389.10
LABOUR :
Mason 2nd Class Each 0.8000 158.67 126.94
Beldar Each 0.8000 116.67 93.34
Bhishti Each 0.9800 116.67 114.34
SUNDRIES(Scaffolding & solution of lime putty): L.S. 12.50
TOTAL : 736.21
ADD FOR WATER CHARGES @ 1.5% : 11.04
TOTAL : 747.25
ADD FOR CONTRACTORS PROFIT @10% : 74.73
ADD FOR OVER HEAD CHARGES @5% : 37.36
COST FOR 10.000 Sqm. 859.34
COST PER Sqm. 85.95
LABOUR RATE PER Sqm. 47.70
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 347.11
MATERIAL :
lime surkhi mortar 1:2
(1 lime putty: 2 surkhi)
MATERIAL :
lime surkhi mortar 1:2
(1 lime putty: 2 surkhi)
MATERIAL :
lime surkhi mortar 1:2
(1 lime putty: 2 surkhi)
cum. 0.1720 2444.30 420.42
MATERIAL :
lime surkhi mortar 1:2
(1 lime putty: 2 surkhi)
MATERIAL :
lime surkhi mortar 1:2
(1 lime putty: 2 surkhi)
MATERIAL :
lime surkhi mortar 1:2
(1 lime putty: 2 surkhi)
MATERIAL :
lime surkhi mortar 1:3
(1 lime :3 surkhi)
cum. 0.1650 2122.42 350.20
LABOUR :
Mason 2nd Class Each 0.8000 158.67 126.94
Beldar Each 0.8000 116.67 93.34
Bhishti Each 0.9800 116.67 114.34
SUNDRIES(Scaffolding & solution of lime putty): L.S. 12.50
TOTAL : 697.31
ADD FOR WATER CHARGES @ 1.5% : 10.46
TOTAL : 707.77
ADD FOR CONTRACTORS PROFIT @10% : 70.78
ADD FOR OVER HEAD CHARGES @5% : 35.39
COST FOR 10.000 Sqm. 813.93
COST PER Sqm. 81.40
LABOUR RATE PER Sqm. 47.65
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 347.11
MATERIAL :
lime surkhi mortar 1:3
(1 lime :3 surkhi)
cum. 0.1720 2122.42 365.06
LABOUR :
Mason 2nd Class Each 0.8300 158.67 131.70
Beldar Each 0.8300 116.67 96.84
Bhishti Each 0.9800 116.67 114.34
SUNDRIES(Scaffolding & solution of lime putty): L.S. 12.50
TOTAL : 720.43
ADD FOR WATER CHARGES @ 1.5% : 10.81
TOTAL : 731.23
ADD FOR CONTRACTORS PROFIT @10% : 73.12
ADD FOR OVER HEAD CHARGES @5% : 36.56
COST FOR 10.000 Sqm. 840.92
COST PER Sqm. 84.10
LABOUR RATE PER Sqm. 48.90
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 355.37
MATERIAL :
lime surkhi mortar 1:3
(1 lime :3 surkhi)
cum. 0.1140 2122.42 241.96
MATERIAL :
lime surkhi mortar 1:3
(1 lime :3 surkhi)
cum. 0.1720 2122.42 365.06
MATERIAL :
lime surkhi mortar 1:3
(1 lime :3 surkhi)
cum. 0.1650 2122.42 350.20
MATERIAL :
lime surkhi mortar 1:3
(1 lime :3 surkhi)
cum. 0.2270 2122.42 481.79
MATERIAL :
lime surkhi mortar 1:3
(1 lime :3 surkhi)
cum. 0.2820 2122.42 598.52
MATERIAL :
lime mortar 1:2
(1 lime putty:2sand)
cum. 0.1650 2358.20 389.10
LABOUR :
Mason 2nd Class Each 0.8000 158.67 126.94
Beldar Each 0.8000 116.67 93.34
Bhishti Each 0.9800 116.67 114.34
SUNDRIES(Scaffolding & solution of lime putty): L.S. 12.50
TOTAL : 736.21
ADD FOR WATER CHARGES @ 1.5% : 11.04
TOTAL : 747.25
ADD FOR CONTRACTORS PROFIT @10% : 74.73
ADD FOR OVER HEAD CHARGES @5% : 37.36
COST FOR 10.000 Sqm. 859.34
COST PER Sqm. 85.95
LABOUR RATE PER Sqm. 47.70
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 347.11
MATERIAL :
lime mortar 1:2
(1 lime putty:2sand)
cum. 0.1720 2358.20 405.61
LABOUR :
Mason 2nd Class Each 0.8300 158.67 131.70
Beldar Each 0.8300 116.67 96.84
Bhishti Each 0.9800 116.67 114.34
SUNDRIES(Scaffolding & solution of lime putty): L.S. 12.50
TOTAL : 760.98
ADD FOR WATER CHARGES @ 1.5% : 11.41
TOTAL : 772.39
ADD FOR CONTRACTORS PROFIT @10% : 77.24
ADD FOR OVER HEAD CHARGES @5% : 38.62
COST FOR 10.000 Sqm. 888.25
COST PER Sqm. 88.85
LABOUR RATE PER Sqm. 49.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 355.37
MATERIAL :
lime mortar 1:2
(1 lime putty:2sand)
cum. 0.2240 2358.20 528.24
LABOUR :
Mason 2nd Class Each 1.5000 158.67 238.01
Beldar Each 1.5000 116.67 175.01
Bhishti Each 1.4200 116.67 165.67
SUNDRIES(Scaffolding & solution of lime putty): L.S. 12.50
TOTAL : 1119.42
ADD FOR WATER CHARGES @ 1.5% : 16.79
TOTAL : 1136.21
ADD FOR CONTRACTORS PROFIT @10% : 113.62
ADD FOR OVER HEAD CHARGES @5% : 56.81
COST FOR 10.000 Sqm. 1306.64
COST PER Sqm. 130.65
LABOUR RATE PER Sqm. 78.80
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 591.18
MATERIAL :
lime mortar 1:2
(1 lime putty:2sand)
cum. 0.2820 2358.20 665.01
LABOUR :
Mason 2nd Class Each 1.8000 158.67 285.61
Beldar Each 1.8000 116.67 210.01
Bhishti Each 1.8100 116.67 211.17
SUNDRIES(Scaffolding & solution of lime putty): L.S. 12.50
TOTAL : 1384.30
ADD FOR WATER CHARGES @ 1.5% : 20.76
TOTAL : 1405.06
ADD FOR CONTRACTORS PROFIT @10% : 140.51
ADD FOR OVER HEAD CHARGES @5% : 70.25
COST FOR 10.000 Sqm. 1615.82
COST PER Sqm. 161.60
LABOUR RATE PER Sqm. 96.25
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 719.28
MATERIAL :
lime mortar 1:2
(1 lime putty:2sand)
cum. 0.2750 2358.20 648.51
LABOUR :
Mason 2nd Class Each 1.7700 158.67 280.85
Beldar Each 1.7700 116.67 206.51
Bhishti Each 1.8100 116.67 211.17
SUNDRIES(Scaffolding & solution of lime putty): L.S. 12.50
TOTAL : 1359.53
ADD FOR WATER CHARGES @ 1.5% : 20.39
TOTAL : 1379.92
ADD FOR CONTRACTORS PROFIT @10% : 137.99
ADD FOR OVER HEAD CHARGES @5% : 69.00
COST FOR 10.000 Sqm. 1586.91
COST PER Sqm. 158.70
LABOUR RATE PER Sqm. 95.00
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 711.02
MATERIAL :
PLASTERING, POINTING, WHITE WASHING, COLOUR WASHING, DISTEMPERING & OTHER
FINISHES
MATERIAL :
lime mortar 1:2
(1 lime putty:2sand)
cum. 0.3920 2358.20 924.41
LABOUR :
PLASTERING, POINTING, WHITE WASHING, COLOUR WASHING, DISTEMPERING & OTHER
FINISHES
MATERIAL :
lime mortar1:3
(1 lime putty:3sand)
cum. 0.1650 2025.45 334.20
LABOUR :
Mason 2nd Class Each 0.8000 158.67 126.94
Beldar Each 0.8000 116.67 93.34
Bhishti Each 0.9800 116.67 114.34
SUNDRIES(Scaffolding & solution of lime putty): L.S. 12.50
TOTAL : 681.31
PLASTERING, POINTING, WHITE WASHING, COLOUR WASHING, DISTEMPERING & OTHER
FINISHES
MATERIAL :
lime mortar1:3
(1 lime putty:3sand)
cum. 0.1720 2025.45 348.38
LABOUR :
Mason 2nd Class Each 0.8300 158.67 131.70
Beldar Each 0.8300 116.67 96.84
Bhishti Each 0.9800 116.67 114.34
SUNDRIES(Scaffolding & solution of lime putty): L.S. 12.50
TOTAL : 703.75
ADD FOR WATER CHARGES @ 1.5% : 10.56
TOTAL : 714.30
ADD FOR CONTRACTORS PROFIT @10% : 71.43
ADD FOR OVER HEAD CHARGES @5% : 35.72
COST FOR 10.000 Sqm. 821.45
PLASTERING, POINTING, WHITE WASHING, COLOUR WASHING, DISTEMPERING & OTHER
FINISHES
MATERIAL :
lime mortar1:3
(1 lime putty:3sand)
cum. 0.2240 2025.45 453.70
LABOUR :
Mason 2nd Class Each 1.5000 158.67 238.01
Beldar Each 1.5000 116.67 175.01
Bhishti Each 1.4200 116.67 165.67
SUNDRIES(Scaffolding & solution of lime putty): L.S. 12.50
TOTAL : 1044.88
ADD FOR WATER CHARGES @ 1.5% : 15.67
TOTAL : 1060.56
ADD FOR CONTRACTORS PROFIT @10% : 106.06
ADD FOR OVER HEAD CHARGES @5% : 53.03
COST FOR 10.000 Sqm. 1219.64
COST PER Sqm. 121.95
LABOUR RATE PER Sqm. 78.65
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 591.18
PLASTERING, POINTING, WHITE WASHING, COLOUR WASHING, DISTEMPERING & OTHER
FINISHES
MATERIAL :
lime mortar1:3
(1 lime putty:3sand)
cum. 0.2820 2025.45 571.18
LABOUR :
Mason 2nd Class Each 1.8000 158.67 285.61
Beldar Each 1.8000 116.67 210.01
Bhishti Each 1.8100 116.67 211.17
SUNDRIES(Scaffolding & solution of lime putty): L.S. 12.50
TOTAL : 1290.46
ADD FOR WATER CHARGES @ 1.5% : 19.36
TOTAL : 1309.82
ADD FOR CONTRACTORS PROFIT @10% : 130.98
ADD FOR OVER HEAD CHARGES @5% : 65.49
COST FOR 10.000 Sqm. 1506.29
COST PER Sqm. 150.65
LABOUR RATE PER Sqm. 96.10
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 719.28
MATERIAL :
lime mortar1:3
(1 lime putty:3sand)
cum. 0.2750 2025.45 557.00
LABOUR :
Mason 2nd Class Each 1.7700 158.67 280.85
Beldar Each 1.7700 116.67 206.51
Bhishti Each 1.8100 116.67 211.17
SUNDRIES(Scaffolding & solution of lime putty): L.S. 12.50
TOTAL : 1268.02
ADD FOR WATER CHARGES @ 1.5% : 19.02
TOTAL : 1287.04
ADD FOR CONTRACTORS PROFIT @10% : 128.70
ADD FOR OVER HEAD CHARGES @5% : 64.35
COST FOR 10.000 Sqm. 1480.10
COST PER Sqm. 148.00
LABOUR RATE PER Sqm. 94.85
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 711.02
MATERIAL :
lime mortar1:3
(1 lime putty:3sand)
cum. 0.3370 2025.45 682.58
LABOUR :
Mason 2nd Class Each 2.0700 158.67 328.45
Beldar Each 2.0700 116.67 241.51
Bhishti Each 2.1400 116.67 249.67
SUNDRIES(Scaffolding & solution of lime putty): L.S. 12.50
TOTAL : 1514.70
ADD FOR WATER CHARGES @ 1.5% : 22.72
TOTAL : 1537.42
ADD FOR CONTRACTORS PROFIT @10% : 153.74
ADD FOR OVER HEAD CHARGES @5% : 76.87
COST FOR 10.000 Sqm. 1768.04
COST PER Sqm. 176.80
LABOUR RATE PER Sqm. 111.65
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 832.13
MATERIAL :
lime mortar1:3
(1 lime putty:3sand)
cum. 0.3920 2025.45 793.98
LABOUR :
Mason 2nd Class Each 2.7700 158.67 439.52
Beldar Each 2.7700 116.67 323.18
Bhishti Each 2.6400 116.67 308.01
SUNDRIES(Scaffolding & solution of lime putty): L.S. 12.50
TOTAL : 1877.18
ADD FOR WATER CHARGES @ 1.5% : 28.16
TOTAL : 1905.33
ADD FOR CONTRACTORS PROFIT @10% : 190.53
ADD FOR OVER HEAD CHARGES @5% : 95.27
COST FOR 10.000 Sqm. 2191.13
COST PER Sqm. 219.00
LABOUR RATE PER Sqm. 143.30
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 1083.20
MATERIAL :
lime mortar1:1
(1 lime putty :1 sand )
cu.m 0.0300 3023.45 90.70
LABOUR :
Mason 2nd Class Each 0.3600 158.67 57.12
Beldar Each 0.3600 116.67 42.00
MATERIAL :
cement mortar 1:3
(1 cement :3 sand)
cum. 0.0720 3178.80 228.87
LABOUR :
Mason 2nd Class Each 0.6500 158.67 103.14
Beldar Each 0.8100 116.67 94.50
Bhishti Each 0.2700 116.67 31.50
PLASTERING, POINTING, WHITE WASHING, COLOUR WASHING, DISTEMPERING & OTHER
FINISHES
MATERIAL :
cement mortar 1:4
(1 cement :4 sand):
cum. 0.0720 2528.15 182.03
LABOUR :
Mason 2nd Class Each 0.6500 158.67 103.14
Beldar Each 0.8100 116.67 94.50
Bhishti Each 0.2700 116.67 31.50
Total :- 83.50
Cost per Sq.m : 83.50
LABOUR RATE :
Labour Rate as per item no. : 17044010 29.25
Labour Rate as per item no. : 17056000 13.40
Labour Rate as per item no. : 17152000 1.60
Total :- 44.25
Labour Rate per Sq.m : 44.25
MATERIAL :
cement mortar 1:3
(1 cement :3 sand)
cum. 0.1140 3178.80 362.38
LABOUR :
Mason 2nd Class Each 0.6000 158.67 95.20
Beldar Each 0.6000 116.67 70.00
Bhishti Each 0.9000 116.67 105.00
MATERIAL :
cement mortar 1:4
PLASTERING, POINTING, WHITE WASHING, COLOUR WASHING, DISTEMPERING & OTHER
FINISHES
MATERIAL :
cement mortar 1:5
(1 cement:5 sand)
cum. 0.1140 2177.80 248.27
LABOUR :
Mason 2nd Class Each 0.6000 158.67 95.20
Beldar Each 0.6000 116.67 70.00
Bhishti Each 0.9000 116.67 105.00
MATERIAL :
cement mortar 1:6
(1 cement :6 sand):
cum. 0.1140 1877.50 214.04
LABOUR :
Mason 2nd Class Each 0.6000 158.67 95.20
Beldar Each 0.6000 116.67 70.00
Bhishti Each 0.9000 116.67 105.00
MATERIAL :
cement mortar 1:7
(1 cement :7 sand)
cum. 0.1140 1727.35 196.92
LABOUR :
Mason 2nd Class Each 0.6000 158.67 95.20
Beldar Each 0.6000 116.67 70.00
Bhishti Each 0.9000 116.67 105.00
MATERIAL :
cement mortar 1:8
(1 cement :8 sand):
cum. 0.1140 1577.20 179.80
LABOUR :
Mason 2nd Class Each 0.6000 158.67 95.20
PLASTERING, POINTING, WHITE WASHING, COLOUR WASHING, DISTEMPERING & OTHER
FINISHES
MATERIAL :
cement mortar 1:3
(1 cement :3 sand)
cum. 0.1720 3178.80 546.75
LABOUR :
Mason 2nd Class Each 0.8300 158.67 131.70
Beldar Each 0.8300 116.67 96.84
Bhishti Each 0.9800 116.67 114.34
PLASTERING, POINTING, WHITE WASHING, COLOUR WASHING, DISTEMPERING & OTHER
FINISHES
MATERIAL :
cement mortar 1:4
(1 cement :4 sand):
cum. 0.1720 2528.15 434.84
LABOUR :
Mason 2nd Class each 0.8300 158.67 131.70
Beldar each 0.8300 116.67 96.84
Bhishti each 0.9800 116.67 114.34
MATERIAL :
cement mortar 1:5
(1 cement:5 sand)
cum. 0.1720 2177.80 374.58
LABOUR :
Mason 2nd Class each 0.8300 158.67 131.70
Beldar each 0.8300 116.67 96.84
Bhishti each 0.9800 116.67 114.34
MATERIAL :
cement mortar 1:6
(1 cement :6 sand):
cum. 0.1720 1877.50 322.93
LABOUR :
Mason 2nd Class each 0.8300 158.67 131.70
Beldar each 0.8300 116.67 96.84
Bhishti Each 0.9800 116.67 114.34
MATERIAL :
cement mortar 1:7
(1 cement :7 sand)
cum. 0.1720 1727.35 297.10
LABOUR :
Mason 2nd Class each 0.8300 158.67 131.70
Beldar each 0.8300 116.67 96.84
Bhishti each 0.9800 116.67 114.34
MATERIAL :
cement mortar 1:8
(1 cement :8 sand):
cum. 0.1720 1577.20 271.28
LABOUR :
Mason 2nd Class each 0.8300 158.67 131.70
Beldar each 0.8300 116.67 96.84
Bhishti each 0.9800 116.67 114.34
MATERIAL :
cement mortar 1:3
(1 cement :3 sand)
cum. 0.1650 3178.80 524.50
LABOUR :
Mason 2nd Class each 0.8000 158.67 126.94
Beldar each 0.8000 116.67 93.34
Bhishti each 0.9800 116.67 114.34
MATERIAL :
cement mortar 1:4
(1 cement :4 sand):
cum. 0.1650 2528.15 417.14
LABOUR :
Mason 2nd Class each 0.8000 158.67 126.94
Beldar each 0.8000 116.67 93.34
Bhishti each 0.9800 116.67 114.34
MATERIAL :
cement mortar 1:5
(1 cement:5 sand)
cum. 0.1650 2177.80 359.34
LABOUR :
PLASTERING, POINTING, WHITE WASHING, COLOUR WASHING, DISTEMPERING & OTHER
FINISHES
MATERIAL :
cement mortar 1:6
(1 cement :6 sand):
cum. 0.1650 1877.50 309.79
LABOUR :
Mason 2nd Class each 0.8000 158.67 126.94
Beldar each 0.8000 116.67 93.34
Bhishti each 0.9800 116.67 114.34
MATERIAL :
cement mortar 1:7
(1 cement :7 sand)
cum. 0.1650 1727.35 285.01
LABOUR :
Mason 2nd Class each 0.8000 158.67 126.94
Beldar each 0.8000 116.67 93.34
Bhishti each 0.9800 116.67 114.34
MATERIAL :
cement mortar 1:8
(1 cement :8 sand):
PLASTERING, POINTING, WHITE WASHING, COLOUR WASHING, DISTEMPERING & OTHER
FINISHES
MATERIAL :
cement mortar 1:3
(1 cement :3 sand)
cum. 0.2240 3178.80 712.05
LABOUR :
Mason 2nd Class each 1.0000 158.67 158.67
Beldar each 1.0000 116.67 116.67
PLASTERING, POINTING, WHITE WASHING, COLOUR WASHING, DISTEMPERING & OTHER
FINISHES
MATERIAL :
cement mortar 1:4
(1 cement :4 sand):
cum. 0.2240 2528.15 566.31
LABOUR :
Mason 2nd Class each 1.0000 158.67 158.67
Beldar each 1.0000 116.67 116.67
Bhishti each 1.0600 116.67 123.67
MATERIAL :
cement mortar 1:5
(1 cement:5 sand)
cum. 0.2240 2177.80 487.83
LABOUR :
Mason 2nd Class each 1.0000 158.67 158.67
Beldar each 1.0000 116.67 116.67
Bhishti each 1.0600 116.67 123.67
MATERIAL :
cement mortar 1:7
(1 cement :7 sand)
cum. 0.2240 1727.35 386.93
LABOUR :
Mason 2nd Class each 1.0000 158.67 158.67
Beldar each 1.0000 116.67 116.67
Bhishti each 1.0600 116.67 123.67
MATERIAL :
cement mortar 1:8
(1 cement :8 sand):
cum. 0.2240 1577.20 353.29
LABOUR :
Mason 2nd Class each 1.0000 158.67 158.67
Beldar each 1.0000 116.67 116.67
Bhishti each 1.0600 116.67 123.67
MATERIAL :
cement mortar 1:3
(1 cement :3 sand)
cum. 0.1650 3178.80 524.50
LABOUR :
Mason 2nd Class each 1.3000 158.67 206.27
Beldar each 1.3000 116.67 151.67
Bhishti each 1.4800 116.67 172.67
MATERIAL :
cement mortar 1:4
(1 cement :4 sand):
cum. 0.1650 2528.15 417.14
LABOUR :
Mason 2nd Class each 1.3000 158.67 206.27
Beldar each 1.3000 116.67 151.67
Bhishti each 1.4800 116.67 172.67
MATERIAL :
cement mortar 1:5
(1 cement:5 sand)
PLASTERING, POINTING, WHITE WASHING, COLOUR WASHING, DISTEMPERING & OTHER
FINISHES
MATERIAL :
cement mortar 1:6
(1 cement :6 sand):
cum. 0.1650 1877.50 309.79
LABOUR :
Mason 2nd Class each 1.3000 158.67 206.27
Beldar each 1.3000 116.67 151.67
Bhishti each 1.4800 116.67 172.67
MATERIAL :
cement mortar 1:7
(1 cement :7 sand)
cum. 0.1650 1727.35 285.01
LABOUR :
Mason 2nd Class each 1.3000 158.67 206.27
Beldar Each 1.3000 116.67 151.67
Bhishti each 1.4800 116.67 172.67
MATERIAL :
cement mortar 1:8
(1 cement :8 sand):
cum. 0.1650 1577.20 260.24
LABOUR :
Mason 2nd Class each 1.3000 158.67 206.27
Beldar each 1.3000 116.67 151.67
Bhishti each 1.4800 116.67 172.67
MATERIAL :
cement mortar 1:3
(1 cement :3 sand)
cum. 0.2310 3178.80 734.30
LABOUR :
Mason 2nd Class each 1.5300 158.67 242.77
Beldar each 1.5300 116.67 178.51
Bhishti each 1.4800 116.67 172.67
MATERIAL :
cement mortar 1:4
(1 cement :4 sand):
cum. 0.2310 2528.15 584.00
LABOUR :
Mason 2nd Class each 1.5300 158.67 242.77
PLASTERING, POINTING, WHITE WASHING, COLOUR WASHING, DISTEMPERING & OTHER
FINISHES
MATERIAL :
cement mortar 1:5
(1 cement:5 sand)
cum. 0.2310 2177.80 503.07
LABOUR :
Mason 2nd Class each 1.5300 158.67 242.77
Beldar each 1.5300 116.67 178.51
Bhishti each 1.4800 116.67 172.67
MATERIAL :
cement mortar 1:6
(1 cement :6 sand):
cum. 0.2310 1877.50 433.70
LABOUR :
Mason 2nd Class each 1.5300 158.67 242.77
Beldar each 1.5300 116.67 178.51
Bhishti each 1.4800 116.67 172.67
MATERIAL :
cement mortar 1:7
(1 cement :7 sand)
cum. 0.2310 1727.35 399.02
LABOUR :
Mason 2nd Class each 1.5300 158.67 242.77
Beldar each 1.5300 116.67 178.51
Bhishti each 1.4800 116.67 172.67
MATERIAL :
cement mortar 1:8
(1 cement :8 sand):
cum. 0.2310 1577.20 364.33
LABOUR :
Mason 2nd Class each 1.5300 158.67 242.77
Beldar each 1.5300 116.67 178.51
Bhishti each 1.4800 116.67 172.67
MATERIAL :
cement mortar 1:3
(1 cement :3 sand)
cum. 0.2240 3178.80 712.05
LABOUR :
Mason 2nd Class each 1.5000 158.67 238.01
Beldar each 1.5000 116.67 175.01
Bhishti each 1.4200 116.67 165.67
MATERIAL :
MATERIAL :
cement mortar 1:5
(1 cement:5 sand)
cum. 0.2240 2177.80 487.83
LABOUR :
Mason 2nd Class each 1.5000 158.67 238.01
Beldar each 1.5000 116.67 175.01
Bhishti each 1.4200 116.67 165.67
MATERIAL :
cement mortar 1:6
PLASTERING, POINTING, WHITE WASHING, COLOUR WASHING, DISTEMPERING & OTHER
FINISHES
MATERIAL :
cement mortar 1:7
(1 cement :7 sand)
cum. 0.2240 1727.35 386.93
LABOUR :
Mason 2nd Class each 1.5000 158.67 238.01
Beldar each 1.5000 116.67 175.01
Bhishti each 1.4200 116.67 165.67
MATERIAL :
cement mortar 1:8
(1 cement :8 sand):
cum. 0.2240 1577.20 353.29
LABOUR :
Mason 2nd Class each 1.5000 158.67 238.01
Beldar each 1.5000 116.67 175.01
Bhishti each 1.4200 116.67 165.67
MATERIAL :
cement mortar 1:5
(1 cement:5 sand)
cum. 0.2310 2177.80 503.07
lime mortar1:1
(1 lime putty :1 sand )
cu.m 0.0550 3023.45 166.29
LABOUR :
Mason 2nd Class each 2.2300 158.67 353.83
Beldar each 2.2300 116.67 260.17
Bhishti each 1.9800 116.67 231.01
MATERIAL :
cement mortar 1:6
(1 cement :6 sand):
cum. 0.2310 1877.50 433.70
lime mortar1:1
(1 lime putty :1 sand )
cu.m 0.0550 3023.45 166.29
LABOUR :
Mason 2nd Class each 2.2300 158.67 353.83
Beldar each 2.2300 116.67 260.17
Bhishti each 1.9800 116.67 231.01
MATERIAL :
cement mortar 1:4
(1 cement :4 sand):
cum. 0.2310 2528.15 584.00
MATERIAL :
cement mortar 1:3
(1 cement :3 sand)
cum. 0.2310 3178.80 734.30
MATERIAL :
Cement : tonne 0.0220 4900.00 107.80
CARRIAGE :
Carriage of Cement L.S 1.80
LABOUR :
Mason 2nd Class each 0.3600 158.67 57.12
Beldar each 0.3600 116.67 42.00
Bhishti each 0.1200 116.67 14.00
TOTAL : 222.72
ADD FOR WATER CHARGES @ 1.5% : L.S. 3.34
TOTAL : 226.06
ADD FOR CONTRACTORS PROFIT 10% 22.61
ADD FOR OVER HEAD CHARGES @5% : 11.30
COST FOR 10.000 sq.m 259.97
COST PER sq.m 26.00
LABOUR RATE PER sq.m 13.40
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 113.12
TOTAL : 113.12
WATER CHARGES @ 1.5% : 3.34
TOTAL : 116.46
ADD FOR CONTRACTORS PROFIT @10% : 11.65
ADD FOR OVER HEAD CHARGES @5% : 5.82
LABOUR FOR 10.000 sq.m 133.93
LABOUR RATE PER sq.m 13.40
MATERIAL :
Damp proofing compound kg. 1.0000 35.00 35.00
CARRIAGE :
Carriage & Labour for MixL.S 5.00
TOTAL : 40.00
PLASTERING, POINTING, WHITE WASHING, COLOUR WASHING, DISTEMPERING & OTHER
FINISHES
MATERIAL :
cement lime mortar 1:1:6
(1 cement:1 lime putty 6 sand)
cum. 0.1140 2692.70 306.97
LABOUR :
Mason 2nd Class each 0.6000 158.67 95.20
Beldar each 0.6000 116.67 70.00
Bhishti each 0.9000 116.67 105.00
MATERIAL :
cement lime mortar 1:2:9:
(1 cement:2 lime putty:9 sand:)
cum. 0.1720 2489.10 428.13
LABOUR :
Mason 2nd Class each 0.8300 158.67 131.70
Beldar each 0.8300 116.67 96.84
Bhishti each 0.9800 116.67 114.34
MATERIAL :
MATERIAL :
cement lime mortar 1:2:9:
(1 cement:2 lime putty:9 sand:)
cum. 0.1650 2489.10 410.70
LABOUR :
Mason 2nd Class each 0.8000 158.67 126.94
Beldar each 0.8000 116.67 93.34
Bhishti each 0.9800 116.67 114.34
MATERIAL :
cement lime mortar 1:1:6
(1 cement:1 lime putty 6 sand)
cum. 0.2240 2692.70 603.16
LABOUR :
Mason 2nd Class each 1.0000 158.67 158.67
Beldar each 1.0000 116.67 116.67
Bhishti each 1.0600 116.67 123.67
MATERIAL :
cement lime mortar 1:2:9:
(1 cement:2 lime putty:9 sand:)
cum. 0.2240 2489.10 557.56
LABOUR :
Mason 2nd Class each 1.0000 158.67 158.67
Beldar each 1.0000 116.67 116.67
Bhishti each 1.0600 116.67 123.67
MATERIAL :
cement lime mortar 1:1:6
(1 cement:1 lime putty 6 sand)
cum. 0.1650 2692.70 444.30
LABOUR :
Mason 2nd Class each 1.3000 158.67 206.27
Beldar each 1.3000 116.67 151.67
Bhishti each 1.4800 116.67 172.67
MATERIAL :
cement lime mortar 1:1:6
(1 cement:1 lime putty 6 sand)
cum. 0.2310 2692.70 622.01
LABOUR :
Mason 2nd Class each 1.5300 158.67 242.77
Beldar each 1.5300 116.67 178.51
Bhishti each 1.4800 116.67 172.67
MATERIAL :
PLASTERING, POINTING, WHITE WASHING, COLOUR WASHING, DISTEMPERING & OTHER
FINISHES
MATERIAL :
cement lime mortar 1:1:6
PLASTERING, POINTING, WHITE WASHING, COLOUR WASHING, DISTEMPERING & OTHER
FINISHES
lime mortar1:1
(1 lime putty :1 sand )
cu.m 0.0550 3023.45 166.29
LABOUR :
Mason 2nd Class each 2.2300 158.67 353.83
Beldar each 2.2300 116.67 260.17
Bhishti each 1.9800 116.67 231.01
MATERIAL :
cement lime mortar 1:1:6
(1 cement:1 lime putty 6 sand)
cum. 0.1140 2692.70 306.97
MATERIAL :
cement lime mortar 1:1:6
(1 cement:1 lime putty 6 sand)
cum. 0.1720 2692.70 463.14
MATERIAL :
cement lime mortar 1:1:6
(1 cement:1 lime putty 6 sand)
cum. 0.1650 2692.70 444.30
MATERIAL :
cement lime mortar 1:1:6
(1 cement:1 lime putty 6 sand)
cum. 0.1140 2692.70 306.97
lime mortar1:1
(1 lime putty :1 sand )
cu.m 0.0550 3023.45 166.29
LABOUR :
Mason 2nd Class each 2.2300 158.67 353.83
Beldar each 2.2300 116.67 260.17
Bhishti each 1.9800 116.67 231.01
MATERIAL :
Good earth cu.m. 0.2810 75.00 21.08
MATERIAL :
Good earth cu.m. 0.2260 75.00 16.95
MATERIAL :
cement mortar 1:4
(1 cement :4 sand):
cum. 0.1720 2528.15 434.84
MATERIAL :
Rate as per item no. : 17077010 7.50
Total :- 7.50
Add 25% for two coat plaster 1.88
Cost per sq. m/no. of storeys 9.38 say 9.40
17077030 ii)Three coat plaster :-
Detail of cost for 1sq.m per storey
Rate for single coat plaster as per
item 17077010 7.50
MATERIAL :
Rate as per item no. : 17077010
Total :- 7.5
Add 50% for three coat plaster 3.75
PLASTERING, POINTING, WHITE WASHING, COLOUR WASHING, DISTEMPERING & OTHER
FINISHES
TOTAL : 4.20
ADD FOR WATER CHARGES @ 1.5% : 0.06
TOTAL : 4.26
ADD FOR CONTRACTORS PROFIT @10% : 0.43
ADD FOR OVER HEAD CHARGES @5% : 0.21
Cost per sqm 4.90
LABOUR RATE PER sq.m 4.90
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 4.20
TOTAL : 4.20
WATER CHARGES @ 1.5% : 0.06
TOTAL : 4.26
ADD FOR CONTRACTORS PROFIT @10% : 0.43
ADD FOR OVER HEAD CHARGES @5% : 0.21
LABOUR FOR 1.000 sq.m 4.90
LABOUR RATE PER sq.m 4.90
17077050 Floating coat of neat cement.
MATERIAL :
Rate as per item no. : 17077040 4.90
Total :- 4.90
17078000 Rough side exterior cement plaster
on wall upto a height of 10meters
above ground level with a mixture
of sand and gravel or crushed stone
graded from 6mm to 12mm nominal
size dashed over and including
fresh plaster in two coats,backing
coat 10mm cement plaster 1:3(1
cement:3 sand)and finishing coat
10mm cement plaster with cement
mortar 1:3(1 cement:3 sand)mixed
with 10% finely grounded hyderated
lime by volume of cement including
arriss,chamfers and/or rounded
angles not exceeding 80mm in girth.
MATERIAL :
cement mortar 1:3
(1 cement :3 sand)
cum. 0.2240 3178.80 712.05
MATERIAL :
MATERIAL :
cement mortar 1:3
(1 cement :3 sand)
cum. 0.2240 3178.80 712.05
MATERIAL :
cement mortar 1:3
(1 cement :3 sand)
cum. 0.2240 3178.80 712.05
PLASTERING, POINTING, WHITE WASHING, COLOUR WASHING, DISTEMPERING & OTHER
FINISHES
Total :- 0.90
Add 25% for Extra add.coat of plaster 0.23
Total :- 1.13
cost per sq.m. 1.15
Total :- 0.90
Add 50% for extra two coat plaster 0.45
Total :- 1.35
17082040 Lime punning
MATERIAL :
Rate as per item no. : 17082010 0.90
Total :- 0.90
17082050 Floating coat of Neat Cement :-
Rate same as per item 1708201
MATERIAL :
Rate as per item no. : 17082010 0.90
Total :- 0.90
17083000 Extra for exterior plastering over
walls beyond height of 10 metres
above ground level for every
additional height of 5 metres or
part thereof.
17083010 (i) Single coat plaster.
Detail of cost for 10 sq.m.
LABOUR :
Beldar each 0.0150 116.67 1.75
Bhishti each 0.0150 116.67 1.75
Total :- 1.30
17083050 Floating coat of neat cement.
MATERIAL :
Rate as per item no. : 17083030 1.30
Total :- 1.30
17084000 15mm thick plain cement mortar
bands in cement mortar 1:4(1
Cement:4 Sand)upto 300 mm in width.
17084010 (a) Flush band.
Detail of cost for 10 meter long 10cm wide band
MATERIAL :
cement mortar 1:4
(1 cement :4 sand):
cum. 0.0170 2528.15 42.98
LABOUR :
Mason 2nd Class each 0.2700 158.67 42.84
Beldar each 0.2700 116.67 31.50
Bhishti each 0.0500 116.67 5.83
MATERIAL :
cement mortar 1:4
(1 cement :4 sand):
cum. 0.0170 2528.15 42.98
LABOUR :
Mason 2nd Class each 0.3000 158.67 47.60
Beldar each 0.3000 116.67 35.00
Bhishti each 0.0500 116.67 5.83
MATERIAL :
cement mortar 1:4
(1 cement :4 sand):
cum. 0.0170 2528.15 42.98
LABOUR :
Mason 2nd Class each 0.3500 158.67 55.53
Beldar each 0.3500 116.67 40.83
Bhishti each 0.0500 116.67 5.83
MATERIAL :
PLASTERING, POINTING, WHITE WASHING, COLOUR WASHING, DISTEMPERING & OTHER
FINISHES
MATERIAL :
cement mortar 1:4
(1 cement :4 sand):
cum. 0.1700 2528.15 429.79
LABOUR :
Mason 2nd Class each 2.2000 158.67 349.07
Beldar each 2.2000 116.67 256.67
Bhishti each 0.5000 116.67 58.34
MATERIAL :
cement mortar 1:4
(1 cement :4 sand):
cum. 0.1700 2528.15 429.79
LABOUR :
Mason 2nd Class each 2.7000 158.67 428.41
Beldar each 2.7000 116.67 315.01
Bhishti each 0.5000 116.67 58.34
MATERIAL :
cement mortar 1:4
(1 cement :4 sand):
cum. 0.0230 2528.15 58.15
LABOUR :
Mason 2nd Class each 0.3000 158.67 47.60
Beldar each 0.3000 116.67 35.00
Bhishti each 0.0500 116.67 5.83
MATERIAL :
cement mortar 1:4
PLASTERING, POINTING, WHITE WASHING, COLOUR WASHING, DISTEMPERING & OTHER
FINISHES
MATERIAL :
cement mortar 1:4
(1 cement :4 sand):
cum. 0.0230 2528.15 58.15
LABOUR :
Mason 2nd Class each 0.3800 158.67 60.29
Beldar each 0.3800 116.67 44.33
Bhishti each 0.0500 116.67 5.83
MATERIAL :
cement mortar 1:4
(1 cement :4 sand):
cum. 0.2240 2528.15 566.31
LABOUR :
Mason 2nd Class each 2.2000 158.67 349.07
Beldar each 2.2000 116.67 256.67
Bhishti each 0.0500 116.67 5.83
MATERIAL :
cement mortar 1:4
(1 cement :4 sand):
cum. 0.2240 2528.15 566.31
LABOUR :
Mason 2nd Class each 2.5000 158.67 396.68
Beldar each 2.5000 116.67 291.68
Bhishti each 0.0500 116.67 5.83
MATERIAL :
cement mortar 1:4
(1 cement :4 sand):
PLASTERING, POINTING, WHITE WASHING, COLOUR WASHING, DISTEMPERING & OTHER
FINISHES
MATERIAL :
cement mortar 1:4
(1 cement :4 sand):
cum. 0.0170 2528.15 42.98
LABOUR :
Mason 2nd Class each 0.6500 158.67 103.14
Beldar each 0.6500 116.67 75.84
Bhishti each 0.0500 116.67 5.83
MATERIAL :
cement mortar 1:4
(1 cement :4 sand):
cum. 0.0230 2528.15 58.15
LABOUR :
Mason 2nd Class each 0.8700 158.67 138.04
Beldar each 0.8700 116.67 101.50
Bhishti each 0.0500 116.67 5.83
MATERIAL :
cement mortar 1:5
(1 cement:5 sand)
cum. 0.0170 2177.80 37.02
MATERIAL :
lime mortar 1:2
(1 lime putty:2sand)
cum. 0.0300 2358.20 70.75
LABOUR :
Mason 2nd Class each 0.7500 158.67 119.00
Beldar each 0.7500 116.67 87.50
Bhishti each 0.8000 116.67 93.34
MATERIAL :
lime mortar 1:2
PLASTERING, POINTING, WHITE WASHING, COLOUR WASHING, DISTEMPERING & OTHER
FINISHES
MATERIAL :
lime mortar 1:2
(1 lime putty:2sand)
cum. 0.0300 2358.20 70.75
LABOUR :
Mason 2nd Class each 0.8000 158.67 126.94
Beldar each 0.8000 116.67 93.34
Bhishti each 0.8000 116.67 93.34
MATERIAL :
lime mortar 1:2
(1 lime putty:2sand)
cum. 0.0460 2358.20 108.48
LABOUR :
Mason 2nd Class each 1.6200 158.67 257.05
Beldar each 1.6200 116.67 189.01
Bhishti each 0.8000 116.67 93.34
MATERIAL :
lime mortar1:3
(1 lime putty:3sand)
cum. 0.0300 2025.45 60.76
LABOUR :
Mason 2nd Class each 0.7500 158.67 119.00
Beldar each 0.7500 116.67 87.50
Bhishti each 0.8000 116.67 93.34
MATERIAL :
lime mortar1:3
(1 lime putty:3sand)
cum. 0.0300 2025.45 60.76
LABOUR :
PLASTERING, POINTING, WHITE WASHING, COLOUR WASHING, DISTEMPERING & OTHER
FINISHES
MATERIAL :
lime mortar1:3
(1 lime putty:3sand)
cum. 0.0300 2025.45 60.76
LABOUR :
Mason 2nd Class each 0.8000 158.67 126.94
Beldar each 0.8000 116.67 93.34
Bhishti each 0.8000 116.67 93.34
MATERIAL :
lime mortar1:3
(1 lime putty:3sand)
cum. 0.0460 2025.45 93.17
LABOUR :
Mason 2nd Class each 1.6200 158.67 257.05
Beldar each 1.6200 116.67 189.01
Bhishti each 0.8000 116.67 93.34
MATERIAL :
lime surkhi mortar 1:2
(1 lime putty: 2 surkhi)
MATERIAL :
lime surkhi mortar 1:2
(1 lime putty: 2 surkhi)
cum. 0.0300 2444.30 73.33
LABOUR :
Mason 2nd Class each 0.8000 158.67 126.94
Beldar each 0.8000 116.67 93.34
PLASTERING, POINTING, WHITE WASHING, COLOUR WASHING, DISTEMPERING & OTHER
FINISHES
MATERIAL :
lime surkhi mortar 1:2
(1 lime putty: 2 surkhi)
MATERIAL :
lime surkhi mortar 1:3
(1 lime :3 surkhi)
cum. 0.0300 2122.42 63.67
LABOUR :
Mason 2nd Class each 0.7500 158.67 119.00
Beldar each 0.7500 116.67 87.50
Bhishti each 0.8000 116.67 93.34
MATERIAL :
lime surkhi mortar 1:3
(1 lime :3 surkhi)
cum. 0.0300 2122.42 63.67
LABOUR :
Mason 2nd Class each 0.8000 158.67 126.94
Beldar each 0.8000 116.67 93.34
Bhishti each 0.8000 116.67 93.34
MATERIAL :
lime surkhi mortar 1:3
(1 lime :3 surkhi)
cum. 0.0300 2122.42 63.67
LABOUR :
Mason 2nd Class each 0.8000 158.67 126.94
Beldar each 0.8000 116.67 93.34
Bhishti each 0.8000 116.67 93.34
PLASTERING, POINTING, WHITE WASHING, COLOUR WASHING, DISTEMPERING & OTHER
FINISHES
MATERIAL :
cement mortar 1:3
(1 cement :3 sand)
cum. 0.0300 3178.80 95.36
LABOUR :
Mason 2nd Class each 0.7500 158.67 119.00
Beldar each 0.7500 116.67 87.50
Bhishti each 0.8000 116.67 93.34
MATERIAL :
cement mortar 1:3
(1 cement :3 sand)
cum. 0.0300 3178.80 95.36
LABOUR :
Mason 2nd Class each 0.8000 158.67 126.94
Beldar each 0.8000 116.67 93.34
Bhishti each 0.8000 116.67 93.34
MATERIAL :
cement mortar 1:3
(1 cement :3 sand)
cum. 0.0300 3178.80 95.36
LABOUR :
Mason 2nd Class each 0.8000 158.67 126.94
Beldar each 0.8000 116.67 93.34
Bhishti each 0.8000 116.67 93.34
MATERIAL :
cement mortar 1:3
(1 cement :3 sand)
cum. 0.0460 3178.80 146.22
LABOUR :
Mason 2nd Class each 1.6200 158.67 257.05
Beldar each 1.6200 116.67 189.01
Bhishti each 0.8000 116.67 93.34
MATERIAL :
cement mortar 1:4
(1 cement :4 sand):
cum. 0.0300 2528.15 75.84
LABOUR :
Mason 2nd Class each 0.7500 158.67 119.00
Beldar each 0.7500 116.67 87.50
Bhishti each 0.8000 116.67 93.34
MATERIAL :
cement mortar 1:4
(1 cement :4 sand):
cum. 0.0300 2528.15 75.84
LABOUR :
Mason 2nd Class each 0.8000 158.67 126.94
Beldar each 0.8000 116.67 93.34
Bhishti each 0.8000 116.67 93.34
MATERIAL :
cement mortar 1:4
PLASTERING, POINTING, WHITE WASHING, COLOUR WASHING, DISTEMPERING & OTHER
FINISHES
MATERIAL :
cement mortar 1:4
(1 cement :4 sand):
cum. 0.0460 2528.15 116.29
LABOUR :
Mason 2nd Class each 1.6200 158.67 257.05
Beldar each 1.6200 116.67 189.01
Bhishti each 0.8000 116.67 93.34
MATERIAL :
cement lime mortar 1:1:3
(1 cement:1 lime putty:3 sand)
cum. 0.0300 3746.70 112.40
LABOUR :
Mason 2nd Class each 0.7500 158.67 119.00
Beldar each 0.7500 116.67 87.50
Bhishti each 0.8000 116.67 93.34
MATERIAL :
cement lime mortar 1:1:3
(1 cement:1 lime putty:3 sand)
cum. 0.0300 3746.70 112.40
LABOUR :
Mason 2nd Class each 0.8000 158.67 126.94
Beldar each 0.8000 116.67 93.34
Bhishti each 0.8000 116.67 93.34
MATERIAL :
cement lime mortar 1:1:3
PLASTERING, POINTING, WHITE WASHING, COLOUR WASHING, DISTEMPERING & OTHER
FINISHES
MATERIAL :
cement mortar 1:2
(1 cement :2 sand)
cum. 0.0200 3973.85 79.48
LABOUR :
Mason 2nd Class each 0.5400 158.67 85.68
Beldar each 0.5400 116.67 63.00
Bhishti each 0.8000 116.67 93.34
MATERIAL :
cement mortar 1:2
(1 cement :2 sand)
cum. 0.0200 3973.85 79.48
LABOUR :
Mason 2nd Class each 0.6000 158.67 95.20
Beldar each 0.6000 116.67 70.00
Bhishti each 0.8000 116.67 93.34
MATERIAL :
cement mortar 1:3
(1 cement :3 sand)
cum. 0.0200 3178.80 63.58
LABOUR :
Mason 2nd Class each 0.5400 158.67 85.68
Beldar each 0.5400 116.67 63.00
Bhishti each 0.8000 116.67 93.34
MATERIAL :
cement mortar 1:3
PLASTERING, POINTING, WHITE WASHING, COLOUR WASHING, DISTEMPERING & OTHER
FINISHES
MATERIAL :
cement mortar 1:4
(1 cement :4 sand):
cum. 0.0200 2528.15 50.56
LABOUR :
Mason 2nd Class each 0.5400 158.67 85.68
Beldar each 0.5400 116.67 63.00
Bhishti each 0.8000 116.67 93.34
MATERIAL :
cement mortar 1:4
(1 cement :4 sand):
cum. 0.0200 2528.15 50.56
LABOUR :
Mason 2nd Class each 0.6000 158.67 95.20
Beldar each 0.6000 116.67 70.00
Bhishti each 0.8000 116.67 93.34
MATERIAL :
cement mortar 1:5
(1 cement:5 sand)
cum. 0.0200 2177.80 43.56
LABOUR :
Mason 2nd Class each 0.5400 158.67 85.68
Beldar each 0.5400 116.67 63.00
Bhishti each 0.8000 116.67 93.34
MATERIAL :
cement mortar 1:5
PLASTERING, POINTING, WHITE WASHING, COLOUR WASHING, DISTEMPERING & OTHER
FINISHES
MATERIAL :
cement mortar 1:6
(1 cement :6 sand):
cum. 0.0200 1877.50 37.55
LABOUR :
Mason 2nd Class each 0.5400 158.67 85.68
Beldar each 0.5400 116.67 63.00
Bhishti each 0.8000 116.67 93.34
MATERIAL :
cement mortar 1:6
(1 cement :6 sand):
cum. 0.0200 1877.50 37.55
LABOUR :
Mason 2nd Class each 0.6000 158.67 95.20
Beldar each 0.6000 116.67 70.00
Bhishti each 0.8000 116.67 93.34
MATERIAL :
cement mortar 1:2
(1 cement :2 sand)
cum. 0.0300 3973.85 119.22
LABOUR :
Mason 2nd Class each 0.7500 158.67 119.00
Beldar each 0.7500 116.67 87.50
Bhishti each 0.8000 116.67 93.34
MATERIAL :
PLASTERING, POINTING, WHITE WASHING, COLOUR WASHING, DISTEMPERING & OTHER
FINISHES
MATERIAL :
cement mortar 1:3
(1 cement :3 sand)
cum. 0.0300 3178.80 95.36
LABOUR :
Mason 2nd Class each 0.7500 158.67 119.00
Beldar each 0.7500 116.67 87.50
Bhishti each 0.8000 116.67 93.34
MATERIAL :
cement mortar 1:3
(1 cement :3 sand)
cum. 0.0300 3178.80 95.36
LABOUR :
Mason 2nd Class each 0.8000 158.67 126.94
Beldar each 0.8000 116.67 93.34
Bhishti each 0.8000 116.67 93.34
MATERIAL :
cement mortar 1:4
(1 cement :4 sand):
cum. 0.0300 2528.15 75.84
LABOUR :
Mason 2nd Class each 0.7500 158.67 119.00
Beldar each 0.7500 116.67 87.50
Bhishti each 0.8000 116.67 93.34
(1 cement :4 sand):
cum. 0.0300 2528.15 75.84
LABOUR :
Mason 2nd Class each 0.8000 158.67 126.94
Beldar each 0.8000 116.67 93.34
Bhishti each 0.8000 116.67 93.34
MATERIAL :
cement mortar 1:5
(1 cement:5 sand)
cum. 0.0300 2177.80 65.33
LABOUR :
Mason 2nd Class each 0.7500 158.67 119.00
Beldar each 0.7500 116.67 87.50
Bhishti each 0.8000 116.67 93.34
PLASTERING, POINTING, WHITE WASHING, COLOUR WASHING, DISTEMPERING & OTHER
FINISHES
MATERIAL :
cement mortar 1:5
(1 cement:5 sand)
cum. 0.0300 2177.80 65.33
LABOUR :
Mason 2nd Class each 0.8000 158.67 126.94
Beldar each 0.8000 116.67 93.34
Bhishti each 0.8000 116.67 93.34
MATERIAL :
cement mortar 1:6
(1 cement :6 sand):
cum. 0.0300 1877.50 56.33
LABOUR :
Mason 2nd Class each 0.7500 158.67 119.00
Beldar each 0.7500 116.67 87.50
Bhishti each 0.8000 116.67 93.34
MATERIAL :
cement mortar 1:6
(1 cement :6 sand):
cum. 0.0300 1877.50 56.33
LABOUR :
Mason 2nd Class each 0.8000 158.67 126.94
Beldar each 0.8000 116.67 93.34
Bhishti each 0.8000 116.67 93.34
MATERIAL :
lime mortar 1:2
(1 lime putty:2sand)
cum. 0.0460 2358.20 108.48
LABOUR :
Mason 2nd Class each 1.0000 158.67 158.67
Beldar each 1.0000 116.67 116.67
Bhishti each 0.8000 116.67 93.34
PLASTERING, POINTING, WHITE WASHING, COLOUR WASHING, DISTEMPERING & OTHER
FINISHES
MATERIAL :
lime mortar 1:2
(1 lime putty:2sand)
cum. 0.0460 2358.20 108.48
LABOUR :
Mason 2nd Class each 1.1000 158.67 174.54
Beldar each 1.1000 116.67 128.34
Bhishti each 0.8000 116.67 93.34
MATERIAL :
lime mortar 1:2
(1 lime putty:2sand)
cum. 0.0460 2358.20 108.48
LABOUR :
Mason 2nd Class each 1.4800 158.67 234.83
Beldar each 1.4800 116.67 172.67
Bhishti each 0.8000 116.67 93.34
MATERIAL :
lime mortar1:3
(1 lime putty:3sand)
cum. 0.0460 2025.45 93.17
LABOUR :
Mason 2nd Class each 1.0000 158.67 158.67
Beldar each 1.0000 116.67 116.67
Bhishti each 0.8000 116.67 93.34
MATERIAL :
lime mortar1:3
(1 lime putty:3sand)
cum. 0.0460 2025.45 93.17
LABOUR :
Mason 2nd Class each 1.1000 158.67 174.54
Beldar each 1.1000 116.67 128.34
Bhishti each 0.8000 116.67 93.34
MATERIAL :
lime mortar1:3
(1 lime putty:3sand)
cum. 0.0460 2025.45 93.17
LABOUR :
Mason 2nd Class each 1.4800 158.67 234.83
Beldar each 1.4800 116.67 172.67
Bhishti each 0.8000 116.67 93.34
MATERIAL :
lime surkhi mortar 1:2
(1 lime putty: 2 surkhi)
MATERIAL :
lime surkhi mortar 1:2
(1 lime putty: 2 surkhi)
MATERIAL :
lime surkhi mortar 1:2
(1 lime putty: 2 surkhi)
MATERIAL :
lime surkhi mortar 1:3
(1 lime :3 surkhi)
cum. 0.0460 2122.42 97.63
LABOUR :
Mason 2nd Class each 1.0000 158.67 158.67
Beldar each 1.0000 116.67 116.67
Bhishti each 0.8000 116.67 93.34
MATERIAL :
lime surkhi mortar 1:3
(1 lime :3 surkhi)
cum. 0.0460 2122.42 97.63
LABOUR :
Mason 2nd Class each 1.1000 158.67 174.54
Beldar each 1.1000 116.67 128.34
Bhishti each 0.8000 116.67 93.34
MATERIAL :
cement mortar 1:3
(1 cement :3 sand)
cum. 0.0460 3178.80 146.22
LABOUR :
Mason 2nd Class each 1.0000 158.67 158.67
Beldar each 1.0000 116.67 116.67
Bhishti each 0.8000 116.67 93.34
MATERIAL :
cement mortar 1:3
(1 cement :3 sand)
cum. 0.0460 3178.80 146.22
LABOUR :
Mason 2nd Class each 1.1000 158.67 174.54
Beldar each 1.1000 116.67 128.34
Bhishti each 0.8000 116.67 93.34
MATERIAL :
cement mortar 1:3
(1 cement :3 sand)
cum. 0.0460 3178.80 146.22
LABOUR :
Mason 2nd Class each 1.4800 158.67 234.83
Beldar each 1.4800 116.67 172.67
Bhishti each 0.8000 116.67 93.34
MATERIAL :
PLASTERING, POINTING, WHITE WASHING, COLOUR WASHING, DISTEMPERING & OTHER
FINISHES
MATERIAL :
cement mortar 1:4
(1 cement :4 sand):
cum. 0.0460 2528.15 116.29
LABOUR :
Mason 2nd Class each 1.1000 158.67 174.54
Beldar each 1.1000 116.67 128.34
Bhishti each 0.8000 116.67 93.34
MATERIAL :
cement mortar 1:4
(1 cement :4 sand):
cum. 0.0460 2528.15 116.29
LABOUR :
Mason 2nd Class each 1.4800 158.67 234.83
Beldar each 1.4800 116.67 172.67
Bhishti each 0.8000 116.67 93.34
MATERIAL :
cement lime mortar 1:1:3
(1 cement:1 lime putty:3 sand)
cum. 0.0460 3746.70 172.35
MATERIAL :
cement lime mortar 1:1:3
(1 cement:1 lime putty:3 sand)
cum. 0.0460 3746.70 172.35
MATERIAL :
lime surkhi mortar 1:2
(1 lime putty: 2 surkhi)
MATERIAL :
lime surkhi mortar 1:2
(1 lime putty: 2 surkhi)
MATERIAL :
lime surkhi mortar 1:2
(1 lime putty: 2 surkhi)
MATERIAL :
lime mortar1:3
(1 lime putty:3surkhi)
cum. 0.0230 2025.45 46.59
PLASTERING, POINTING, WHITE WASHING, COLOUR WASHING, DISTEMPERING & OTHER
FINISHES
MATERIAL :
lime mortar1:3
(1 lime putty:3surkhi)
cum. 0.0230 2025.45 46.59
LABOUR :
Mason 2nd Class each 0.7300 158.67 115.83
Beldar each 0.7300 116.67 85.17
Bhishti each 0.8000 116.67 93.34
MATERIAL :
lime mortar1:3
(1 lime putty:3surkhi)
cum. 0.0380 2025.45 76.97
LABOUR :
Mason 2nd Class each 1.4600 158.67 231.66
Beldar each 1.4600 116.67 170.34
Bhishti each 0.8000 116.67 93.34
MATERIAL :
cement mortar 1:3
(1 cement :3 sand)
cum. 0.0230 3178.80 73.11
LABOUR :
Mason 2nd Class each 0.6900 158.67 109.48
Beldar each 0.6900 116.67 80.50
Bhishti each 0.8000 116.67 93.34
MATERIAL :
cement mortar 1:3
(1 cement :3 sand)
cum. 0.0230 3178.80 73.11
LABOUR :
Mason 2nd Class each 0.7300 158.67 115.83
PLASTERING, POINTING, WHITE WASHING, COLOUR WASHING, DISTEMPERING & OTHER
FINISHES
MATERIAL :
cement mortar 1:3
(1 cement :3 sand)
cum. 0.0380 3178.80 120.79
LABOUR :
Mason 2nd Class each 1.4600 158.67 231.66
Beldar each 1.4600 116.67 170.34
Bhishti each 0.8000 116.67 93.34
MATERIAL :
cement mortar 1:4
(1 cement :4 sand):
cum. 0.0230 2528.15 58.15
LABOUR :
Mason 2nd Class each 0.6900 158.67 109.48
Beldar each 0.6900 116.67 80.50
Bhishti each 0.8000 116.67 93.34
MATERIAL :
cement mortar 1:4
(1 cement :4 sand):
cum. 0.0230 2528.15 58.15
LABOUR :
Mason 2nd Class each 0.7300 158.67 115.83
Beldar each 0.7300 116.67 85.17
Bhishti each 0.8000 116.67 93.34
MATERIAL :
MATERIAL :
lime surkhi mortar 1:2
(1 lime putty: 2 surkhi)
MATERIAL :
lime surkhi mortar 1:2
(1 lime putty: 2 surkhi)
MATERIAL :
lime mortar 1:2
(1 lime putty:2sand)
cum. 0.0380 2358.20 89.61
LABOUR :
Mason 2nd Class each 2.0000 158.67 317.34
Beldar each 2.0000 116.67 233.34
Bhishti each 0.8000 116.67 93.34
MATERIAL :
PLASTERING, POINTING, WHITE WASHING, COLOUR WASHING, DISTEMPERING & OTHER
FINISHES
MATERIAL :
lime mortar1:3
(1 lime putty:3sand)
cum. 0.0230 2025.45 46.59
LABOUR :
Mason 2nd Class each 1.0000 158.67 158.67
Beldar each 1.0000 116.67 116.67
Bhishti each 0.8000 116.67 93.34
MATERIAL :
lime mortar1:3
(1 lime putty:3sand)
cum. 0.0380 2025.45 76.97
LABOUR :
Mason 2nd Class each 2.0000 158.67 317.34
Beldar each 2.0000 116.67 233.34
Bhishti each 0.8000 116.67 93.34
MATERIAL :
cement mortar 1:3
(1 cement :3 sand)
cum. 0.0230 3178.80 73.11
LABOUR :
Mason 2nd Class each 0.9400 158.67 149.15
Beldar each 0.9400 116.67 109.67
Bhishti each 0.8000 116.67 93.34
MATERIAL :
cement mortar 1:3
(1 cement :3 sand)
cum. 0.0230 3178.80 73.11
PLASTERING, POINTING, WHITE WASHING, COLOUR WASHING, DISTEMPERING & OTHER
FINISHES
MATERIAL :
cement mortar 1:3
(1 cement :3 sand)
cum. 0.0380 3178.80 120.79
LABOUR :
Mason 2nd Class each 2.0000 158.67 317.34
Beldar each 2.0000 116.67 233.34
Bhishti each 0.8000 116.67 93.34
MATERIAL :
cement mortar 1:4
(1 cement :4 sand):
cum. 0.0230 2528.15 58.15
LABOUR :
Mason 2nd Class each 0.9400 158.67 149.15
Beldar each 0.9400 116.67 109.67
Bhishti each 0.8000 116.67 93.34
MATERIAL :
cement mortar 1:4
(1 cement :4 sand):
cum. 0.0230 2528.15 58.15
LABOUR :
Mason 2nd Class each 1.0000 158.67 158.67
Beldar each 1.0000 116.67 116.67
Bhishti each 0.8000 116.67 93.34
MATERIAL :
cement mortar 1:4
(1 cement :4 sand):
cum. 0.0380 2528.15 96.07
LABOUR :
Mason 2nd Class each 2.0000 158.67 317.34
Beldar each 2.0000 116.67 233.34
PLASTERING, POINTING, WHITE WASHING, COLOUR WASHING, DISTEMPERING & OTHER
FINISHES
MATERIAL :
lime surkhi mortar 1:2
(1 lime putty: 2 surkhi)
MATERIAL :
lime surkhi mortar 1:2
(1 lime putty: 2 surkhi)
MATERIAL :
lime surkhi mortar 1:2
(1 lime putty: 2 surkhi)
MATERIAL :
lime mortar1:3
PLASTERING, POINTING, WHITE WASHING, COLOUR WASHING, DISTEMPERING & OTHER
FINISHES
MATERIAL :
lime surkhi mortar 1:3
(1 lime :3 surkhi)
cum. 0.0230 2122.42 48.82
LABOUR :
Mason 2nd Class each 0.9000 158.67 142.80
Beldar each 0.9000 116.67 105.00
Bhishti each 0.8000 116.67 93.34
MATERIAL :
lime surkhi mortar 1:3
(1 lime :3 surkhi)
cum. 0.0380 2122.42 80.65
LABOUR :
Mason 2nd Class each 1.8000 158.67 285.61
Beldar each 1.8000 116.67 210.01
Bhishti each 0.8000 116.67 93.34
MATERIAL :
cement mortar 1:3
(1 cement :3 sand)
cum. 0.0230 3178.80 73.11
LABOUR :
Mason 2nd Class each 0.8500 158.67 134.87
Beldar each 0.8500 116.67 99.17
Bhishti each 0.8000 116.67 93.34
MATERIAL :
cement mortar 1:3
(1 cement :3 sand)
cum. 0.0230 3178.80 73.11
PLASTERING, POINTING, WHITE WASHING, COLOUR WASHING, DISTEMPERING & OTHER
FINISHES
MATERIAL :
cement mortar 1:3
(1 cement :3 sand)
cum. 0.0380 3178.80 120.79
LABOUR :
Mason 2nd Class each 1.8000 158.67 285.61
Beldar each 1.8000 116.67 210.01
Bhishti each 0.8000 116.67 93.34
MATERIAL :
cement mortar 1:4
(1 cement :4 sand):
cum. 0.0230 2528.15 58.15
LABOUR :
Mason 2nd Class each 0.8500 158.67 134.87
Beldar each 0.8500 116.67 99.17
Bhishti each 0.8000 116.67 93.34
MATERIAL :
cement mortar 1:4
(1 cement :4 sand):
cum. 0.0230 2528.15 58.15
LABOUR :
Mason 2nd Class each 0.9000 158.67 142.80
Beldar each 0.9000 116.67 105.00
Bhishti each 0.8000 116.67 93.34
MATERIAL :
cement mortar 1:4
(1 cement :4 sand):
cum. 0.0380 2528.15 96.07
LABOUR :
Mason 2nd Class each 1.8000 158.67 285.61
PLASTERING, POINTING, WHITE WASHING, COLOUR WASHING, DISTEMPERING & OTHER
FINISHES
LABOUR :
White Washer each 0.0100 128.33 1.28
Beldar Each 0.1300 116.67 15.17
Bhishti each 0.0400 116.67 4.67
MATERIAL :
Rate as per item no. : 17131000 1 Sqm 1.0000 0.15 0.15
MATERIAL :
Rate as per item no. : 17130000 10 sqm 1.0000 9.33 9.33
MATERIAL :
Rate as per item no. : 17130000 10 sqm 1.0000 9.33 9.33
MATERIAL :
Lime unslaked qtl. 0.0200 500.00 10.00
MATERIAL :
Lime unslaked qtl. 0.0100 500.00 5.00
MATERIAL :
lime unslaked qtl. 0.0100 500.00 5.00
MATERIAL :
chalk whiting kg. 2.0000 10.00 20.00
MATERIAL :
chalk whiting kg. 1.0000 10.00 10.00
MATERIAL :
lime unslaked qtl. 0.0200 500.00 10.00
MATERIAL :
Lime unslaked qtl. 0.0100 500.00 5.00
MATERIAL :
Cement : tonne 0.0010 4900.00 4.90
CARRIAGE :
Carriage of materials. L.S 1.00
LABOUR :
White Washer each 0.2000 128.33 25.67
MATERIAL :
Cement : tonne 0.0010 4900.00 4.90
LABOUR :
Beldar each 0.1600 116.67 18.67
Painter 2nd Class each 0.0500 128.33 6.42
TOTAL : 3.50
ADD FOR WATER CHARGES @ 1.5% : 0.05
TOTAL : 3.55
ADD FOR CONTRACTORS PROFIT @ 10% 0.36
ADD FOR OVER HEAD CHARGES @5% : 0.18
COST FOR 10.000 sq.m 4.09
COST PER sq.m 0.40
LABOUR RATE PER sq.m 0.40
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 3.50
TOTAL : 3.50
WATER CHARGES @ 1.5% : 0.05
TOTAL : 3.55
ADD FOR CONTRACTORS PROFIT @ 10% 0.36
ADD FOR OVER HEAD CHARGES @5% : 0.18
LABOUR FOR 10.000 sq.m 4.09
LABOUR RATE PER sq.m 0.40
MATERIAL :
Distemper primers: litre 0.8100 90.00 72.90
MATERIAL :
Distempers: kg. 1.0000 35.00 35.00
MATERIAL :
Distempers: kg. 0.6000 35.00 21.00
MATERIAL :
Distempers: kg. 0.4000 35.00 14.00
LABOUR :
Painter 1st Class each 0.0200 148.16 2.96
Beldar each 0.0100 116.67 1.17
LABOUR :
Painter 1st Class each 0.0100 148.16 1.48
Beldar each 0.0100 116.67 1.17
MATERIAL :
PLASTERING, POINTING, WHITE WASHING, COLOUR WASHING, DISTEMPERING & OTHER
FINISHES
MATERIAL :
(a)Priming coat with distemper
primer.
Distemper primer:
litre 0.8100 90.00 72.90
MATERIAL :
Distemper: Kg. 1.0000 45.00 45.00
CARRIAGE :
Carriage of materials. L.S 1.00
LABOUR :
Painter 1st Class each 0.4000 148.16 59.26
Beldar each 0.2000 116.67 23.33
MATERIAL :
Distemper: Kg. 1.0000 45.00 45.00
LABOUR :
Painter 1st Class each 0.0400 148.16 5.93
Beldar each 0.0200 116.67 2.33
MATERIAL :
Paints: kg. 3.0000 40.00 120.00
MATERIAL :
Paints: kg. 1.8000 40.00 72.00
LABOUR :
Painter 1st Class each 0.0400 148.16 5.93
Beldar each 0.0400 116.67 4.67
Bhishti each 0.0400 116.67 4.67
MATERIAL :
Paints: litre 1.2100 200.00 242.00
MATERIAL :
Paints: litre 0.7300 200.00 146.00
MATERIAL :
Paints: litre 0.4900 200.00 98.00
LABOUR :
Painter 1st Class each 0.0400 148.16 5.93
Beldar each 0.0400 116.67 4.66
Notes :
1 The rates include carriage of materials up to a distance of 100 meters on head-load and
one kilometer by mechanical transport.
2 The labor rates include water charges. Scaffolding and Sundries, etc. required for
the particular item.
3 The through rates include all wastage involved.
CHAPTER XVIII
REPAIRS TO BUILDING
MATERIAL :
1st.class Indian teak wood
Rate as per item No.1210201000.
1 Cum. 0.00015 95935 14.39
CARRIAGE :
LABOUR :
LABOUR :
LABOUR :
LABOUR :
LABOUR :
LABOUR :
LABOUR :
LABOUR :
LABOUR :
LABOUR :
LABOUR :
LABOUR :
LABOUR :
LABOUR :
LABOUR :
Total : 16099.33
LABOUR :
Total : 15853.00
LABOUR :
Total : 4662.58
LABOUR :
Total : 6562.84
LABOUR :
Total : 10007.49
Assuming that Timber shall become
unserviceable after being used
16 times.Hence cost for using once Each 1/16 10007.49 625.47
Total : 625.47
LABOUR :
TOTAL : 716.47
TOTAL : 142.06
18060103 Removal
MATERIAL :
1st.class deodar wood battens.
Rate as per itemNo.1210203000.
1 Cu.M. 0.3060 52465.00 16054.29
CARRIAGE :
1 KM BY MECH. TRANSPORT 1 Cum. 0.3060 110.95 33.95
100 MTRS BY HEAD LOAD 1 Cum 0.3060 36.25 11.09
Total : 16099.33
LABOUR :
Total : 10007.49
Assuming that Timber shall become
unserviceable after being used
16 times.Hence cost for using once Each 1/16 10007.49 625.47
Total : 625.47
LABOUR :
TOTAL : 716.47
TOTAL : 142.06
18060203 REMOVAL
MATERIAL :
1st.class kail wood
Beams -4x0.25x0.30m =0.300 cum.
Add for wastage@ 2% =0.006 Cum.
--------------------
Total : 0.306 Cum.
1 Cu.M. 0.3060 51660.00 15807.96
CARRIAGE :
1 KM BY MECH. TRANSPORT 1 Cum. 0.3060 110.95 33.95
100 MTRS BY HEAD LOAD 1 Cum 0.3060 36.25 11.09
Total : 15853.00
LABOUR :
Total : 10007.49
Assuming that Timber shall become
unserviceable after being used
16 times.Hence cost for using once Each 1/16 10007.49 625.47
Total : 625.47
LABOUR :
TOTAL : 716.47
TOTAL : 142.06
18060303 REMOVAL
MATERIAL :
Sal wood beam
Beams -4x0.25x0.30m =0.300 cum.
Add for wastage@ 2% =0.006 Cum.
--------------------
Total : 0.306 Cum.
1 Cu.M. 0.3060 15090.00 4617.54
CARRIAGE :
1 KM BY MECH. TRANSPORT 1 Cum. 0.3060 110.95 33.95
100 MTRS BY HEAD LOAD 1 Cum 0.3060 36.25 11.09
Total : 4662.58
LABOUR :
REPAIRS TO BUILDING
Total : 10007.49
Assuming that Timber shall become
unserviceable after being used
16 times.Hence cost for using once Each 1/16 10007.49 625.47
Total : 625.47
LABOUR :
TOTAL : 716.47
TOTAL : 142.06
18060403 REMOVAL
MATERIAL :
1st.class locally available wood
(chil wood) beams.
4.0x0.25x0.30m =0.300 Cum
Add for wastage @2%=0.006 Cum
----------------------
Total : 0.306 Cum.
1 Cu.M. 0.3060 21300.00 6517.80
CARRIAGE :
1 KM BY MECH. TRANSPORT 1 Cum. 0.3060 110.95 33.95
100 MTRS BY HEAD LOAD 1 Cum 0.3060 36.25 11.09
Total : 6562.84
LABOUR :
Total : 14823.16
Assuming that Timber shall become
unserviceable after being used
16 times.Hence cost for using once Each 1/16 14823.16 926.45
REPAIRS TO BUILDING
TOTAL : 1017.45
TOTAL : 214.67
18070103 REMOVAL
MATERIAL :
1st class deodar wood beams.
1x5.0x0.25x0.30m =0.375 Cum.
Add for wastage @ 2%=0.008 Cum.
-----------------
Total : 0.383 Cum.
1 Cu.M. 0.3830 52465.00 20094.10
CARRIAGE :
1 KM BY MECH. TRANSPORT 1 Cum. 0.3830 110.95 42.49
100 MTRS BY HEAD LOAD 1 Cum 0.3830 36.25 13.88
Total : 20150.47
LABOUR :
Total : 14823.16
Assuming that Timber shall become
unserviceable after being used
16 times.Hence cost for using once Each 1/16 14823.16 926.45
Total : 926.45
LABOUR :
TOTAL : 1017.45
TOTAL : 214.67
18070203 REMOVAL
MATERIAL :
1st.class kail wood beams.
1x5.0x0.25x0.30m =0.375 Cum.
Add for wastage @2%=0.008 Cum.
-----------
Total : 0.383 Cum.
1 Cu.M. 0.3830 51660.00 19785.78
CARRIAGE :
1 KM BY MECH. TRANSPORT 1 Cum. 0.3830 110.95 42.49
100 MTRS BY HEAD LOAD 1 Cum 0.3830 36.25 13.88
Total : 19842.16
LABOUR :
REPAIRS TO BUILDING
Total : 14823.16
Assuming that Timber shall become
unserviceable after being used
16 times.Hence cost for using once Each 1/16 14823.16 926.45
Total : 926.45
LABOUR :
TOTAL : 1017.45
TOTAL : 214.67
REPAIRS TO BUILDING
18070303 REMOVAL
MATERIAL :
Sal wood beams.
1x5.0x0.25x0.30m =0.375 Cum.
Add for wastage @2%=0.008 Cum.
-----------
Total : 0.383 Cum.
1 Cu.M. 0.3830 15090.00 5779.47
CARRIAGE :
1 KM BY MECH. TRANSPORT 1 Cum. 0.3830 110.95 42.49
100 MTRS BY HEAD LOAD 1 Cum 0.3830 36.25 13.88
Total : 5835.85
LABOUR :
Total : 14823.16
Assuming that Timber shall become
unserviceable after being used
16 times.Hence cost for using once Each 1/16 14823.16 926.45
Total : 926.45
LABOUR :
TOTAL : 1017.45
TOTAL : 214.67
18070403 REMOVAL
MATERIAL :
REPAIRS TO BUILDING
Total : 8214.28
LABOUR :