Beruflich Dokumente
Kultur Dokumente
Conditional Obligations
Held: No.
As contemplated in Article 1308 the stipulation
wherein Rodriguez shall pay the balance of the
purchase price when he has successfully negotiated
and secured a road right of way is not a condition on
the perfection of the contract nor on the validity of the
entire contract or its compliance.
It is a condition imposed only on respondents
obligation to pay the remainder of the purchase price.
Applying Article 1182, such a condition is not purely
1
potestative as petitioners contend. It is not dependent
on the sole will of the debtor but also on the will of the
third persons who own the adjacent land and from
whom the road right of way shall be negotiated. Such a
condition is likewise dependent on chance as there is
no guarantee that respondent and the 3 rd party
landowners would come to an agreement regarding the
road right of way. This type of mixed condition is
expressly allowed under Art 1182.
Facts:
On different dates, Lulu Jorge pawned several pieces of
jewelry with Agencia de R. C. Sicam located in
Paraaque to secure a loan. On October 19, 1987, two
armed men entered the pawnshop and took away
whatever cash and jewelry were found inside the
pawnshop vault. On the same date, Sicam sent Lulu a
letter informing her of the loss of her jewelry due to the
robbery incident in the pawnshop. Respondent Lulu
then wrote back expressing disbelief, then requested
Sicam to prepare the pawned jewelry for withdrawal on
November 6, but Sicam failed to return the jewelry.
2
indemnification for the loss of pawned jewelry and
payment of actual, moral and exemplary damages as
well as attorney's fees. The RTC rendered its Decision
dismissing respondents complaint as well as
petitioners counterclaim. Respondents appealed the
RTC Decision to the CA which reversed the RTC,
ordering the appellees to pay appellants the actual
value of the lost jewelry and AF. Petitioners MR denied,
hence the instant petition for review on Certiorari.
3
robbery was not only foreseeable, but actually foreseen
and anticipated. Sicams testimony, in effect,
contradicts petitioners defense of fortuitous event.
Moreover, petitioners failed to show that they were free
from any negligence by which the loss of the pawned
jewelry may have been occasioned. Robbery per se,
just like carnapping, is not a fortuitous event. It does
not foreclose the possibility of negligence on the part of
herein petitioners.
NPC vs CA
161 SCRA 334
FACTS: The plaintiff Engineering Construction, Inc.
(ECI), executed a contract with National Waterworks
and Sewerage Authority (NAWASA) for a project
involving two phases: a tunnel work and outworks at
both ends of the tunnel. On November 4, 1967, strong
winds, along with heavy rains, struck the project area
caused by typhoon Welming. Due to the continuous
heavy downpour, the water in the reservoir of the Angat
Dams reached its danger height of 212 meters above
sea level. This triggered National Power Corporation to
open the spillway gates. This resulted to the large
volume of water to hit the installations and construction
works of ECI which was washed away, lost or destroyed.
4
The Court stated that the happening of a fortuitous
event or an act of God, there concurs a corresponding
fraud, negligence, delay or violation or contravention in
any manner of the tenor of the obligation as provided
for in Article 1170 of the Civil Code, which results in loss
or damage, the obligor cannot escape liability.
5
participation in, or aggravating of the injury to the
creditor.
6
Overspeeding an act of negligence
Juntilla vs Fontanar
136 SCRA 624
7
the operation of its telephone service the electric light
posts of private respondent Camarines Sur II Electric
Cooperative, Inc. (CASURECO II) in Naga City. In
consideration therefor, petitioners agreed to install, free
of charge, ten (10) telephone connections for the use
by private respondent.
8
Basis in the exercise of the right of recission
9
It is evident that EMI had not rescinded the contract at
all. As observed by the CA, despite EMI s
pronouncement, it failed to surrender the HMO cards of
its employees although this was required by the
Agreement, and allowed them to continue using them
beyond the date of the rescission. The in-patient and
the outpatient utilization reports submitted by HCI
shows entries as late as March 1999, signifying that EMI
employees 1 were availing of the services until the
contract period were almost over. The continued use by
them of their privileges under the contract, with the
apparent consent of EMI, belies any intention to cancel
or rescind it, even as they felt that they ought to have
received more than what they got.
Plaintiffs failed to pay the last installment on its due date. Later
on, plaintiffs offered to pay the unpaid balance, which had
already been delayed by one and a half year. Dela Cruz did not
want to accept petitioners offer of payment and did not want to
execute a document of transfer in petitioners favor. On
September 23, 1995, defendant sold the same parcels of land
to intervenor Diogenes G. Bartolome
10
Petitioners justify the delay in payment by stating that they had
notice that Dela Cruz is not the owner of the subject land, and
that they took pains to rectify the alleged defect in Dela Cruzs
title.
Dela Cruz did not conceal from petitioners that the title to Lot
Nos. 2776, 2767 and 2769 still remained under Abelidas name,
and the Contract to Sell even provided that petitioners should
shoulder the attendant expenses for the transfer of ownership
from Abelida to Dela Cruz.
11
petitioner to introduce improvements on the subdivision
such as roads leading to the lots.
The Petitioner then replied that the cancellation of
the contracts is confirmed pursuant to the provisions of
both contracts. All the amounts paid in accordance with
the agreement together with the improvements on the
premises have been considered as rents paid and as
payment for damages suffered by your failure.
ISSUE:
Whether the Petitioners action to rescind the
contract due to Respondents default in payment is
valid
RULING:
No. The action to rescind the contract due to
respondents default in payment is not valid. The Court
decided the case by applying the broad principles of
equity and Justice. According to the SC, the respondent
paid an amount equating to more than the price of one
of the subdivision lots. The only balance due on both
lots was P1, 317.72, which was even less than the value
of one lot. The SC believes that awarding the
respondent one of the two lots in the subdivision
despite the slight breach in the contract is a decision
that is fair and just because it was a decision made in
favour of equity and justice.
The petitioners insist on their right of cancellation
under the "plainly valid written agreements which
constitute the law between the parties" as against "the
broad principles of equity and justice" applied by the
appellate court.
We find that plaintiff herein has not been
denied substantial justice, for, according to Art. 1234 of
said Code: 'If the obligation has been substantially
performed in good faith, the obligor may recover as
though there had been a strict and complete fulfillment,
less damages suffered by the obligee,'" and "that in the
interest of justice and equity, the decision appealed
from may be upheld upon the authority of Article 1234
of the Civil Code."
12
FACTS:
Petitioner Lorenzo Shipping Corporation is a
domestic corporation engaged in coastwise shipping
Respondent BJ Marthel International, Inc. is a business
entity engaged in trading, marketing, and selling of
various industrial commodities. It is also an importer
and distributor of different brands of engines and spare
parts.
Respondent supplied petitioner with spare parts
for the latters marine engines. Sometime in 1989,
petitioner asked respondent for a quotation for various
machine parts. Acceding to this request, respondent
furnished petitioner with a formal quotation. The
quotation also stated that delivery will be made 2
months after receipt of form order and there must be
payment of 25% upon delivery, balance payable in 5 bi-
monthly equal Instalment[s] not to exceed 90 days.
Petitioner issued purchase order No. 13839 and
14011 respectively for the procurement of the
cylinders. Both purchase order did not state the date of
the cylinder liners delivery. Petitioner issued post dated
checked as payment. Respondent deposited petitioners
check, however, the same was dishonored by the
drawee bank due to insufficiency of funds. The
remaining nine postdated checks were eventually
returned by respondent to petitioner. Respondent
thereafter placed the order for the two cylinder liners
with its principal in Japan, Daiei Sangyo Co. Ltd., by
opening a letter of credit on February 1990 under its
own name with the First Interstate Bank of Tokyo. On
April 1990 repondents sales manager, delivered the
two cylinder liners at petitioners warehouse.
Respondent thereafter demanded for full payment
the two cylinder liners by sending a Statement of
Account and a demand letter to petitioner. In reply,
petitioner sent respondent a letter offering to pay only
P150,000 for the cylinder liners. In said letter, petitioner
claimed that as the cylinder liners were delivered late
and due to the scrapping of the M/V Dadiangas Express,
it would have to sell the cylinder liners in Singapore and
pay the balance from the proceeds of said sale.
Respondent then sent another demand letter stating
the same conditions stated above plus payment for
damages.
The two parties were not able to settle their
dispute hence the respondents filed a case in court. In
its complaint, respondent alleged that despite its
13
repeated oral and written demands, petitioner
obstinately refused to settle its obligations. Petitioner
afterwards filed its Answer alleging therein that time
was of the essence in the delivery of the cylinder liners
and that the delivery on April 1990 of said items was
late as respondent committed to deliver said items
within two (2) months after receipt of firm order from
petitioner.
ISSUE:
Whether time is of the essence in the contract
between petitioner and respondent
RULING:
In determining whether time is of the essence in a
contract, the ultimate criterion is the actual or apparent
intention of the parties and before time may be so
regarded by a court, there must be a sufficient
manifestation, either in the contract itself or the
surrounding circumstances of that intention. Petitioner
insists that although its purchase orders did not specify
the dates when the cylinder liners were supposed to be
delivered, nevertheless, respondent should abide by the
term of delivery appearing on the quotation it
submitted to petitioner. Petitioner theorizes that the
quotation embodied the offer from respondent while the
purchase order represented its (petitioners) acceptance
of the proposed terms of the contract of sale. Thus,
petitioner is of the view that these two documents
cannot be taken separately as if there were two distinct
contracts. We do not agree.
It is a cardinal rule in interpretation of contracts
that if the terms thereof are clear and leave no doubt as
to the intention of the contracting parties, the literal
meaning shall control. However, in order to ascertain
the intention of the parties, their contemporaneous and
subsequent acts should be considered. While this Court
recognizes the principle that contracts are respected as
the law between the contracting parties, this principle is
tempered by the rule that the intention of the parties is
primordial and once the intention of the parties has
been ascertained, that element is deemed as an
integral part of the contract as though it has been
originally expressed in unequivocal terms.
14
Pacific Banking Corp vs. CA
173 SCRA 102 (1989)
FACTS:
Joseph and Eleanor Hart, herein private
respondents, organized Insular Farms, Inc. (IFI), a
business in line with cultivation of fish and saltmaking.
In need for financial assistance, sps Hart approached
John Clarkin. Joseph and John signed a Memorandum of
Agreement. One of the stipulations in the memorandum
was the division of shares outstanding, Clarkin has 510
shares and 490 shares for the Harts.
Insular Farms Inc., because of financial difficulties,
borrowed P 250,000.00 from Pacific Banking
Corporation sometime in July of 1956. On July 1956
Insular Farms Inc. executed a Promissory Note of P
250,000.00 to the bank payable in five equal annual
installments, the first installment payable on or before
July 1957. Said note provided that upon default in the
payment of any installment when due, all other
installments shall become due and payable.
This loan was effected without any security except
for the Continuing Guaranty of Clarkin. The business
floundered but PBC did not demand payment for the
initial July 1957 installment nor the entire obligation.
The business further deteriorated so Hart pledged all IFI
shares of stocks to PBC in lieu of additional collateral
and to insure an extension of the periods to pay the July
1957 installment. This was executed on February 1958.
On March 3, 1958, Pacific Farms Inc. (PFI) was
created and was engage in the same business as IFI.
The next day, PBC, wrote IFI that the entire obligation is
due in 48 hours. Subsequently, Hart received a notice
that the shares of stocks would be sold at a public
auction. On March 21, the 1,000 shares of stocks of IFI
were sold to PFI.
Hart filed a case. His contention was that there
was an indefinite extension of time to pay their
obligation under the PN and there was no demand
made by the bank, therefore the sale of the shares was
void. The trial court decided against the private
respondents but had a favorable judgment on appeal.
15
RULING:
We also note that the rule which states that there
can be no valid extension of time by oral agreement
unless the extension is for a definite time, is not
absolute but admits of qualifications and exceptions.
The general rule is that an agreement to extend
the time of payment, in order to be valid, must be for a
definite time, although it seems that no precise date be
fixed, it being sufficient that the time can be readily
determined. In case the period of extension is not
precise, the provisions of Article 1197 of the Civil Code
should apply. In this case, there was an agreement to
extend the payment of the loan, including the first
installment thereon which was due on or before July
1957.
16
ISSUE: Whether or not respondent is still bound to its
obligation to CVC.
17
Manlar filed a Complaint for sum of money against
Deyto and Ang before the RTC of Quezon City seeking
to hold Deyto and Ang solidarily liable on the rice
supply contract. TC ruled that both defendants should
be held solidarily liable for the unpaid and outstanding
Manlar account.
Upon appeal, the CA concluded that there is no legal
basis to hold Deyto solidarily liable with Ang for what
the latter may owe Manlar. The evidence failed to
indicate that Deyto had any participation in the
supposed transactions between her daughter and
Manlar. Petitioner filed a Petition for Review on
Certiorari to the Supreme Court.
Iniquitous Penalty
18
1989, but it was extended to October 31, 1989 with a
grace period until November 30, 1989.
19
SSS vs. Moonwalk Development and Housing
Corporation
20
HELD: No. There has been a waiver of the penal clause
as it was not demanded before the full obligation was
fully paid and extinguished.
21
gradually and perfect a social security system which
shall be suitable to the needs of the people throughout
the Philippines and (to) provide protection to employers
against the hazards of disability, sickness, old age and
death . . ."
22
wrote Pacific advising the latter of its intention to take
over the project and to hold said defendant liable for all
damages which it had incurred and will incur to finish
the project. Filinvest submitted its claim against
PHILAMGEN but PHILAMGEN refused because its
principal, Pacific, refused to acknowledge liability.
23
penalty up to the time all contracted works shall have
been actually finished, in addition to other damages.
Pacific became liable for delay when it did not finish the
project on October 15, 1979.
24
instances; 1. If the principal obligation has been partly
or irregularly complied; 2. Even if there has been no
compliance if the penalty is iniquitous or
unconscionable in accordance with Article 1229.
FACTS:
A suit for collection of a sum of money was filed by
private respondent against the petitioner spouses. The
court ruled in favor of Tan and thereon a writ of
attachment was issued by the trial court.
25
Petitioner spouses then delivered to the Deputy Sheriff
the total money judgment in check. However, private
respondent refused to accept the payment and instead
insisted that the garnished funds deposited be
withdrawn to satisfy the judgment obligation.
HELD:
NO. A check, whether it is a managers check or an
ordinary check, is not considered as a legal tender.
26
FACTS:
Petitioner and private respondent entered into a
contact where the former sells a piece of land. The
stipulation provides for a down payment of P23, 930
and the balance of P100, 000 plus 12% interest per
annum to be paid within 4 years from the execution of
the contract.
HELD:
No. The offer of a check is not a valid tender of
payment of an obligation under a contract which
stipulates that the consideration of the sale is in
Philippine Currency.
27
FORTUNADO V. COURT OF APPEALS
196 SCRA 269 (1991)
FACTS:
The Regional Trial Court rendered a judgment in a civil
case ordering respondent to pay damages to the
plaintiff. Pursuant to the said judgment, respondent
levied two parcels of land. The latter lot had already
been purchased by respondent National Steel
Corporation as of August 17, 1983, but had not yet
been registered in its name.
HELD:
YES. In this case, the tender of check is sufficient to
compel redemption but is not in itself a payment.
28
redemption, they remain liable for the payment of the
redemption price.
FACTS:
Private respondent entered into a contract with
petitioner for the latter to supply iron pressure pipes
worth P270,187.50 to be used in the construction of the
Anonoy Waterworks. Respondent paid in installments
which left a balance of P133,507.50 excluding interest.
HELD:
NO. There is no extraordinary inflation of the currency
that would justify an adjustment of NAWASAs unpaid
judgment obligation to petitioner.
29
obligation. (Tolentino Commentaries and Jurisprudence
on the Civil Code Vol. IV, p. 284.)
FACTS:
Respondent received two diamond rings in 1996 from
petitioner. In lieu of such, she issued separate receipts
in which she acknowledged that they had been
delivered to her for sale on commission and that they
would be returned upon demand if unsold. The said
rings were left unsold neither were they returned upon
demand by petitioner.
HELD:
NO. Article 1250 of the Civil Code provides that in case
an extraordinary inflation or deflation of the currency
stipulated should supervene, the value of the currency
at the time of the establishment of the obligation
should be the basis of payment, unless there is an
agreement to the contrary.
30
could not have reasonably foreseen and which has been
due to war and the effects thereof, or any unusual force
majeure or fortuitous event. (Civil Code of the
Philippines, Dean Capistrano, Vol. III, p. 186.)
Facts:
Petitioners Tolomeo Ligutan and Leonidas dela Llana obt
ained a loan in the amount of P120,000.00 from
respondent Security Bank and Trust
Company. Petitioners executed a promissory note
binding themselves, jointly and severally, with an
interest of 15.189% per annum upon maturity and to
pay a penalty of 5% every month on the outstanding
principal and interest in case of default and also a 10%
attorneys fees if the matter were indorsed to a lawyer
for collection.
31
Ruling: Although a court may not at liberty ignore the
freedom of the parties to agree on such terms and
conditions as they see fit that contravene neither law
nor morals, good customs, public order or public policy,
a stipulated penalty, nevertheless, may be equitably
reduced by the courts if it is iniquitous or
unconscionable or if the principal obligation has been
partly or irregularly complied with.
32
For being solidarily liable under the promissory note,
respondent corporation filed a complaint against
petitioner Palmares as the lone party-defendant,
allegedly by reason principal debtors insolvency
33
FACTS: Petitioner and respondent entered into a
contract of lease over a parcel of land in Quezon City
that was to be used by respondent as a gasoline service
station. Five years before the expiration of the lease
contract, petitioner asked respondent to adjust or
increase the amount of rentals citing that the country
was experiencing extraordinary inflation. In a letter,
respondent refused petitioner's request and declared
that the terms of the lease contract are clear as to the
rental amounts.
34
Although by petitioner's evidence there was a decided
decline in the purchasing power of the Philippine peso
throughout this period, we are hard put to treat this as
an "extraordinary inflation" within the meaning and
intent of Article 1250. Rather, we adopt with approval
the following observations of the Court of Appeals on
petitioner's evidence, especially the NEDA certification
of inflation rates based on consumer price index.
35
lease. However, petitioner brought an action for
reformation of contract before the RTC Makati. The RTC
ruled that Huibonhoa had not presented clear and
convincing evidence to justify the reformation of the
lease contract.
36
provided, however, was a clause which stated that in
case RCBC fails to exercise such option to buy, it would
forfeit all improvements it made (or will make) on said
land in favor of Serra.
In 1984, RCBC communicated to Serra that it now wants
to buy the said land. Serra however refused. RCBC sued
Serra. Serra now contends that the option to buy
was ineffective because it was not supported by any
consideration distinct from the price hence, it is not
binding upon him.
In the case at bar, the Supreme Court did not find the
situation to be inequitable because petitioner is a highly
educated man, who, at the time of the trial was already a
CPA-Lawyer, and when he entered into the contract, was
already a CPA, holding a respectable position with the
Metropolitan Manila Commission. It is evident that a man of
his stature should have been more cautious in transactions he
enters into, particularly where it concerns valuable
properties. Also, in the present case, the consideration is even
more onerous on the part of the lessee since it entails
transferring of the building and/or improvements on the
property to petitioner, should respondent bank fail to exercise
its option within the period stipulated.
Legaspi v CA
37
Bernardo B. Legaspi is the owner of two parcels of land
which he sold to his son-in-law, Leonardo B. Salcedo, for
of P25,000.00 with the right to repurchase the same
within five years from the execution of the deed of sale.
It was then alleged by Legaspi that he offered and
tendered to Salcedo the sum of P25,000.00 for the
repurchase of the two parcels of land; that the tender of
payment was refused by Salcedo without justifiable or
legal cause; that Salcedo refused to convey the
properties to Legaspi as requested by the latter;
Legaspi deposited in the Office of the Clerk of Court of
First Instance the amount of P25,125.00 as evidenced
by Official Receipt; that despite earnest efforts towards
a compromise after consignation of the repurchase
money had been made, Salcedo refused to reconvey
the properties in question.
38
preparatory to consignation as an attempt to make a
private settlement before proceeding to the solemnities
of consignation. Consignation is the act of depositing
the thing due with the court or judicial authorities
whenever the creditor cannot accept or refuses to
accept payment and it generally requires a prior tender
of payment. In instances where no debt is due and
owing, consignation is not proper
39
LUISA F. MCLAUGHLIN,
vs.
THE COURT OF APPEALS AND RAMON FLORES,
40
sale be rescinded. The trial Court favored herein
petitioner. The CA reversed the decision of the trial
court by favoring to the respondent.
41
seeks to obtain. Tender of payment may be
extrajudicial, while consignation is
necessarily judicial, and the priority of the
first is the attempt to make a private
settlement before proceeding to the
solemnities of consignation.
vs
SAMPAGUITA GARMENT CORPORATION,
42
compensation, and that it is plaintiff which owes
defendants US5, 799.57 due to the damages and losses
it incurred as a result of the breaches committed in the
previous shipments to Sears Roebuck.
Held: No, the Court said that the Civil Code lists
compensation as one of the modes of extinguishing the
obligations of persons who, in their own right, are
creditors and debtors of each other. Compensation may
be legal or conventional. Legal compensation takes
place ipso jure when all the requisites of law are
present, as opposed to conventional or voluntary
compensation which occurs when the parties agree to
the mutual extinguishment of their credits or to
compensate their mutual obligations even in the
absence of some of the legal requisites.
43
them which would have then set the automatic
operation of legal compensation in motion.
44
DBPs obligation to Union Bank had not arisen. In
addition, DBP sought to implead FW as third party-
defendant in its capacity as FIs assignee and, thus,
should be held liable to Union Bank. The RTC ruled in
favor of the Union Bank. But, CA ruled that DBP did not
default in its obligations to remit the subject rentals to
Union Bank precisely because it had yet to receive the
rental payments of FW; that the legal compensation
being alleged by the Union bank is denied. Hence, this
petition.
45
In this case, Union Bank filed a motion to seek
affirmation that legal compensation had taken place in
order to effectively offset (a) its own obligation to return
the funds it previously received from DBP as directed
under the September 6, 2005 Writ of Execution with (b)
DBPs assumed obligations under the Assumption
Agreement. However, legal compensation could not
have taken place between these debts for the apparent
reason that requisites 3 and 4 under Article 1279 of the
Civil Code are not present.
After the contract had been enforced for over ten (10)
years, private respondent filed against petitioners for
reformation of the contract with damages, on the
ground that it is too one-sided in favor of petitioners;
that justice and equity demand that the contract be
reformed to abolish the inequities thereon. As second
cause of action, private respondent alleged that
starting with the year 1981, petitioners have used 319
posts in the towns of Pili, Canaman, Magarao and
Milaor, Camarines Sur, all outside Naga City, without
any contract with it, and that petitioners had refused to
pay private respondent said amount despite demands.
And as third cause of action, private respondent
46
complained about the poor servicing by petitioners of
the ten (10) telephone units which had caused it great
inconvenience and damages to the tune of not less
than P100,000.00
Held: Yes, The Court said that Article 1267 of the New
Civil Code speaks of "service" which has become so
difficult. Taking into consideration the rationale behind
this provision, 9 the term "service" should be
understood as referring to the "performance" of the
obligation. In the present case, the obligation of private
respondent consists in allowing petitioners to use its
posts in Naga City, which is the service contemplated in
said article. Furthermore, a bare reading of this article
reveals that it is not a requirement thereunder that the
contract be for future service with future unusual
change.
47
the telephone wires/cables in the posts of private
respondent, resulting in disruption of their service to
the public; while private respondent, in consonance
with the contract will return all the telephone units to
petitioners, causing prejudice to its business. We shall
not allow such eventuality. Rather, we require, as
ordered by the trial court: 1) petitioners to pay private
respondent for the use of its posts in Naga City and in
the towns of Milaor, Canaman, Magarao and Pili,
Camarines Sur and in other places where petitioners
use private respondent's posts, the sum of ten (P10.00)
pesos per post, per month, beginning January, 1989;
and 2) private respondent to pay petitioner the monthly
dues of all its telephones at the same rate being paid
by the public beginning January, 1989.
48
Petitioner Alfredo Ong, Evangelines father, later went
to Land Bank to inform them about the sale and
assumption of mortgage. Land Bank Branch Head told
Alfredo that there was nothing wrong with agreement
with the Spouses Sy and provided him requirements for
the assumption of mortgage. Alfredo later found out that
his application for assumption of mortgage was not
approved by Land Bank.
Issues :
1) Whether or not the Court of Appeals erred in holding
that Art. 1236 of the Civil Code does not apply and in
finding that there is novation.
Ruling :
Yes, Art. 1236 should be applied in this case. Land
Bank contends that Art.1236 of the Civil Code backs
49
their claim that Alfredo should have sought recourse
against the Spouses Sy instead of Land Bank. The court
agreed with Land Bank on the point mentioned as to the
first part of paragraph 1 of Art. 1236. However, Alfredo
made a conditional payment so that the properties
subject of the Deed of Sale with Assumption of Mortgage
which Land Bank required from him would be approved.
Thus, he made payment not as a debtor but as a
prospective mortgagor. Furthermore, the contract
between Alfredo and LandBank was not perfected nor
consummated because of the adverse disapproval of the
proposed assumption.
The Supreme Court did not agree with the Court of
Appeals that there was novation in the contract between
the parties because not all elements of novation were
present. The court further stresses that the instant case
would not have been litigated had Land Bank been more
circumspect in dealing with Alfredo.
The bank chose to accept payment from Alfredo even
before a credit investigation was underway and also failed
to inform him of the disapproval. The court found that
there was negligence to a certain degree on the part of
Land Bank in handling the transaction with Alfredo. A
bank as a business entity should observe a higher
standard of diligence when dealing with the public which
Land Bank neglect to observe in this case.
50
casino chips from Subic Bay Legend Resorts and Casino
Inc. They were made to confess that the chips were
supplies by a casino employee, Michael Cabrera.
51
G.R. No. 120817 November 4, 1996
52
contrary to their agreement. So, Bermic wrote to
Eurotrust to hold the amounts in constructive trust for
the real owners. But Reyes continued to collect on the
other postdated checks. Upon her counsels advise,
Eleazar had the payment stopped. Hence, her checks
issued in favor of Eurotrust were dishonored.
53
legally take place. The mere circumstance of AFP-MBAI
receiving payments from respondent Eleazar who
assume the obligation of petitioner under the contract
of sale of securities, when there is clearly no agreement
to release petitioner from her responsibility, does not
constitute novation, but it only creates a juridical
relation of co-debtorship or suretyship on the part of
respondent Eleazar to the contractual obligation of
petitioner to AFP-MBAI and the latter can still enforce
the obligation against the petitioner.
54
the Land Bank Auditor, the contract entered into by the
cooperatives and REMAD, or the Cattle-Breeding and
Buy-Back Marketing Agreement did not contain a
provision authorizing prepayment.
In connection, the same employees including
petitioners, were also made respondents in a Complaint
filed by the COA Regional Office No. IX, Zamboanga
City, before the Office of the Ombudsman for Gross
Negligence and in violation of of Section 3(e) of
Republic Act (R.A.) No. 3019, otherwise known as
the Anti-Graft and Corrupt Practices Act.
55
The Land Bank Auditor were correct in pointing that the
contract does not contain a stipulation authorizing a
pre-payment scheme; and holding the petitioners
among others, clearly violated the procedure of
releasing loans contained in the Bank's Manual on Field
Office Guidelines on Lending Operations. Nowhere in
the records of the petition can one find a document
which embodies such a stipulation.
In addition, the Court noted on reliance of the terms of
the petitioners to CFP, allowing prepayments or
advancement of the payments prior to the delivery of
the cattle by the supplier REMAD. It appears, however,
that a CFP, even if admittedly a pro forma contract and
emanating from the Land Bank main office, is merely a
facility proposal and not the contract of loan between
Land Bank and the cooperatives. It is in the loan
contract that the parties embody the terms and
conditions of a transaction. If there is any agreement to
release the loan in advance to REMAD as a form of
prepayment scheme, such a stipulation should exist in
the loan contract. There is, nevertheless, no proof of
such stipulation as petitioners had failed to attach the
CFPs or the loan contracts relating to the present
petition.
56