Beruflich Dokumente
Kultur Dokumente
1.1 One of the Squadrons of Indian Air Force is positioned at Thoise, which is
approx. 130 Kms away from Ladhak (J&K). The location at Thoise serves as
a base camp for the Air Crafts going to Siachen Glacier to cater to the needs
of Defence Personnel positioned at the Glacier.
1.2 Thoise is at an altitude of 11500 Feet from mean sea level. Khardungla
Bypass, located at an altitude of 18500 Feet from mean sea level (worlds
highest motorable road) needs to be negotiated for mobilization of resources
at Thoise. It is remotely located location with extreme weather conditions
having temperature variation from (+) 16o C to (-) 20o C.
1.3 The total project cost was `.450.0 lacs. The working period in Thoise is limited
from June to September in a calendar year and the project was scheduled to
be completed in two working seasons i.e. 8 working months.
2.1 Before setting up of the facilities at Thoise, Aviation Fuel was transported
through Barrels from Ladhak to Thoise. The fuel was supplied directly from
Barrels to the Air Craft
2.2 Temporary storage of fuel in the barrels was posing serious threat to the
quality of the product and therefore a need was felt to provide bulk storage
facilities at Thoise itself so that fuel can be transported in Tankers from
Ladhak to Thoise.
3.1 Construction and successful commissioning of facility for receipt, storage and
delivery of Aviation Fuel to the Air Crafts operating from Thoise Air base of
Indian Air Force.
3.2 To ensure commissioning of the project within 8 working months without any
cost overrun.
3.3 Handing over of history cards of all equipments to the end user.
3.4 Handing over of all warranty related certificates to the end user
3.5 Impart training to operating persons for use of fire fighting facilities in case of
any emergency
IAF was a major stake holder. The connectivity from Leh to Thoise is only by
road which is not an all weather road. During winters, due to heavy snow fall,
the road gets blocked and the supply of fuel (which was earlier transported in
barrels by road) gets interrupted.
The Air base being an important strategically located for IAF, needed
uninterrupted fuel supply for its fighter planes. The storage facilities were
therefore required to be created to ensure availability of fuel for minimum of
three months requirement without receipt of any product.
Apart from IAF being one of the major customers of IOC(IOC catering to
approx. 88% of their fuel requirement), the project was taken up by IOC as a
part of its commitment to serve the nation. The project was conceived at a
very low IRR of 2.5%.
The developmental facilities at such remote locations indirectly leads to the economic
development of the region and as such J&K Government was also one of the stake
holders.
The Project was executed by Indian Oil for providing facilities for receipt, storage and
dispatch of Aviation Turbine Fuel for end user as Indian Air Force. The Project was
executed at Thoise which is Base camp for Flights to Siachin Glacier and therefore, is
of strategic importance.
Due to strategic importance for the security of the nation, the Ministry of Defence
took up with Ministry of Petroleum & Natural Gas to undertake this project, who in
turn entrusted the job to Indian Oil.
As a part of Indian Oils commitment towards the security of the nation, the
Project was taken up even with negative IRR
Planned Actual
S.no Mile Stone
Duration in weeks
1 Procurement of MS Steel Plate 8 8
2 Transportation of Plates 3 1
3 Finalization of Contract 8 10
4 Mobilization BY Contractor 2 1
5 Boundary Wall 4 4
6 Fabrication of Tanks 21 21
7 Installation of Tanks 14 13
8 Construction of Tank Lorry Shed 8 9
9 Pump House 7 8
10 Piping Works - Product Pipelines 7 6
11 Piping Works - Fire Fighting Pipelines 14 14
12 RCC Driveway 13 13
13 Electric Works 10 10
14 Automation Works 5 6
15 Administrative Building 8 9
16 Quality Control Lab 8 10
17 Trial Runs 1 1
18 Commissioning 1 1
6.1 To carry out pre-project activities to establish the feasibility of the project and
to prepare budgetary estimates so as to facilitate the Management to take the
decision for investment for the project.
6.2 Detailed Engineering and Design for various works viz., Civil, Structural,
Piping, Electrical and Instrumentation.
6.6 Fortnightly visits to site for assessing the physical progress and for
coordination with vendors and contractors
6.8 Ensuring checking, testing, trial run and successful commissioning of the
project
To mitigate the risk, one comprehensive package covering all the activities
was planned to ensure sufficient quantum of work to the contractor.
Indian Air Force was persuaded to provide shelter and food on chargeable
basis to the contractors supervisor & labour. The assurance of Indian Air
Force was spelt out in tenders and the same motivated the contractors to
come forward.
7.2 In the event of break out of war with China, Thoise is within the range of direct
shelling from China. In such a scenario, petroleum products are of vital
importance for Defence and therefore petroleum storage locations are the first
target of enemy.
7.4 All labour to be mobilized by contractor from plains due to non availability of
local workers. Workers falling sick due to hostile weather conditions leading to
delays.
Arrangements were made with Air Force for airlifting of sick workers to plain
areas and bringing additional labour.
Indian Army was regularly operating their transport aircraft IL-76 from
Chandigarh to Thoise to transport material for Defence needs. Liaisoning was
done with Indian Army to transport material required for the project on
chargeable basis.
7.6 Working period being limited from June to September and work was to be
completed within stiff target of 8 working months, any slippage in adhering to
completion schedule means contractor to de-mobilize in September and re-
mobilize again in June. This leads to minimum delay of ten months in real
sense.
8.1 Formats were developed to have well defined channel for communication to
all the stake holders.
8.2 As per the defined strategy, the Project Manager was to get weekly progress
report of all the activities undertaken. These weekly reports were also shared
with local IAF authorities. The weekly reports were to clearly define the
planned work vis-a-vis actual work executed at site, comparison with variance
and recovery plan for any short fall in progress.
Monthly review meetings were held at site by self along with IAF authorities
8.3 All meetings between Project Manager and Stake holders were documented
and Minutes of the Meeting were circulated to all concerned.
8.4 All decisions taken with regard to execution of work at site were documented
and conveyed to Site Engineers and E&P contractors.
8.5 The communication was by means of fax facility provided by IAF as there
was no mobile network / internet facility or any other means of
communication due to location being remote and security reasons of IAF.
8.6 The regular flow of feedback / information from site regarding progress of
work and difficulties encountered ensured timely completion.
9.1 Any decision with respect to change in scope of work was taken only after
deliberations with all the stake holders and all such changes were
documented.
9.2 Project Manager was also assigned the responsibility of Change Manager. It
was his responsibility to document all the changes approved by IAF and
General Manager of IOC. The document to be prepared by the Change
Manager included the likely impact on financial implication and completion
schedule.
9.3 A mandate was given by IAF that any change impacting the time schedule
should not be implemented, the same was strictly adhered to.
9.4 All stake holders were kept informed about the approved changes and action
plan to implement the same.
Decision was taken to augment the storage capacity by 200 KL. Before the
start of next working season, all approvals were obtained and the same was
communicated to Project execution group. The change did not affect the
completion schedule.
The cost over run was because of approved change for augmentation of
tankage by 200KL
Green belt was provided all along the periphery of the plot.
Oil Water Separator has been provided, OWS is designed to ensure that
oil content at the outlet side of the OWS is less than 10 PPM.
c) Positioning of material was well planned and it was ensured that all critical
material was positioned ahead of schedule.
d) Part fabrication of plates in terms of edge cutting and rolling was done at
Chandigarh to reduce fabrication time at site.
g) Start of work during early hours resulted in better efficiency especially for
welding works. Due to heavy wind speed after around 2o clock, it was
difficult to achieve radiography quality of welding.
Initially, tenders were invited based on the work packages viz., tank
fabrication, piping and civil works. Due to quantum of work limited to
approx. 150.0 lacs, and also extreme weather conditions and remote
location no party came forward to participate in the tendering process.
Inviting one tender for all the works could ensure participation by one
party.
In this project also, for driveway we should have considered heavy duty
paver blocks instead of RCC. The same would have resulted in less efforts
in mobilizing machinery and skilled labour for RCC.
14.1 After successful trial runs, the facilities were commissioned and were handed
over to IAF for its operation.
14.2 The contract was closed after making final bill to the vendor.
14.3 Report containing technical details of the facilities provided, their operation
manual and important contacts for maintenance / OEM were handed over to
IAF.
14.4 History cards and warranty related certificates of all equipments were
prepared and handed over to IAF.
14.5 The facilities were to be operated by IAF, their personnel were imparted
training for operating the facilities and for use of fire fighting facilities.
14.6 A detailed report was submitted to Aviation Group (our internal customer),
containing the details of facilities provided along with expenditure details vis-
-vis budgetary provisions.
***