EVALUATION OF PRECAST TECHNOLOGY ON


PROJECT PROFITABILITY
M. Madhu
PG Student, Civil Engineering Department,
KL University, Vaddeswaram 522 502, A.P

K. Hemanth Raja
Assistant Professor, Civil Engineering Department,
KL University, Vaddeswaram 522 502, A.P

ABSTRACT
Objectives: The objective of this paper is to compare the precast technology with conventional
construction and evaluate the precast technology on project profitability.
Methods: The methodology is to collect the data from precast and conventional construction
companies. And analyze the collected data to compare the cost details and duration of the project
of precast technology with conventional construction and evaluate the precast technology on
project profitability.
Findings: The cost of the project is more in precast technology than the conventional
construction, the duration of the project is less in precast technology than conventional
construction. The precast technology is faster than the conventional construction so it is very useful
in our country to grow the construction projects.
Key words: Precast Technology, Conventional Construction, Profitability.
Cite this Article: M. Madhu and K. Hemanth Raja, Evaluation of Precast Technology On Project
Profitability. International Journal of Civil Engineering and Technology, 8(1), 2017, pp. 281286.
http://www.iaeme.com/IJCIET/issues.asp?JType=IJCIET&VType=8&IType=1

1. INTRODUCTION
The molds used to manufacture precast components by filling of concrete and then curing can be
conducted, and shifted to the site where the components are assembled into place. Now a day the
construction boom in India is very fast1. It gives more opportunities in our country for an upcoming people
in the precast industry. In these days the precast construction is one of the advanced techniques in the
whole world, and its wide applicability, the total precast construction system is becoming a popular choice
in construction industry2. Precast construction components available in many sizes, shapes, including
electrical lines and plumbing lines3.

2. NECESSITY OF PRE-CAST CONSTRUCTION


The precast components usage is the new technique in the construction industry for constructing the
buildings in short time and also getting the good strengths. The main advantage of using pre-cast
components is its faster erection with more versatility and good flexibility4. The good Quality achieved by

http://www.iaeme.com/IJCIET/index.asp 281 editor@iaeme.com


M. Madhu and K. Hemanth Raja

these components. The longer spans easily constructed with precast components in a single stretch. In all
aspects, the precast construction is in lead to the ease of construction. The building/structure which is
constructed by the precast components is having good finishing. In precast construction, we dont use large
form works than conventional type construction. These components are durable and structurally efficient5.
The maintenance cost and also the labor cost of the project will be reduced by precast construction. The
main advantage of these components is environmental friendly6-7.

3. METHODOLOGY
3.1. General
This presents the comparison of conventional and precast construction of a double-storey residential
building.

3.2. Plan Preparation


The double storey building plan prepared for estimating of quantities of precast and conventional
construction and it showed in Figure 1.

3.3. Estimation of Quantities


The require materials in both conventional and precast construction by the estimation. The details were
collected from the related companies.

3.4. Project Duration


The construction duration details were collected from the similar companies. And the duration of the
project finds out by Primavera P6 with CPM (critical path method). And shown in Table.1

3.5. Cost Analysis


In cost analysis, we consider labor, material, machinery to compare the precast with conventional
construction of double-storey residential building.

4. RESULTS & DISCUSSIONS


The Floor plans are shown in Figure 1-2., The precast construction and also the conventional construction
duration find out by the collected data from related companies. And it is shown in three different stages.
The substructure completion time was same in both precast and conventional construction because the
same methodology for both constructions. But in the super-structures, the precast construction should
complete in short time than conventional construction, shown in Figure 3. and Table 1.

http://www.iaeme.com/IJCIET/index.asp 282 editor@iaeme.com


Evaluation of Precast Technology On Project Profitability

Figure 1 Ground floor plan

Figure 2 First floor plan

http://www.iaeme.com/IJCIET/index.asp 283 editor@iaeme.com


M. Madhu and K. Hemanth Raja

Figure 3 comparison of cost in 3 different stages for precast & conventional

Table 1 Duration of construction


S.NO Description Precast construction Conventional construction
1 Substructure 22 22
2 Superstructure 12 52
3 Finishing works 31 54
The variation is more in duration between precast and conventional. Itt is the main advantage of precast
construction.
on. Because the elements of staircase,, wall panels, and slab panels were manufacturing in the
factory and they had smooth surfaces and installed
installed with electric and plumbing lines.
lines The total duration of
precast construction is 65 Days. The total duration of conventional construction is 128 days. The duration
variation is 63 days of both methods.
methods. This graph represents the precast construction completed within a
short time than the conventional method. The time duration represents in three different stages they are
blue indicates substructure,, red indicates superstructure,, and green indicates finishing works,
works shown Figure
4. The precast construction
tion and also the conventional construction duration find out by the collected data
from related companies.. And it is shown in three different stages. The substructure completion time was
same in both precast and conventional construction because the same methodology for both constructions.
But in the super-structures, the precast construction should complete in short time than conventional
construction, shown in Figure 5. The variation is more in duration between precast and conventional. It is
the main advantage of precast construction.
constructi Because the elements of staircase,, wall panels, and slab panels
were manufacturing in the factory and they had smooth surfaces and installed with electric and plumbing
lines.. The total cost for precast construction is 73,00,000/-.The
73,00 total duration of conventional construction
is 60,19,000/-. The cost variation is 12,91,000/-
12,91,000/ both construction methods. This graph represents in the
precast construction spent more money
money than the conventional method, shown in Table 2. and FigureFigur 6. The
cost detail represents in three different stages they are blue indicates substructure, red indicates
superstructure,, and green indicates finishing works.

http://www.iaeme.com/IJCIET/index.
IJCIET/index.asp 284 editor@iaeme.com
Evaluation off Precast Technology On Project Profitability

Figure 4 comparison of total duration for precast & conventional

Figure 5 comparison of cost for precast & conventional in 3 different stages

Figure 6 comparison of total project cost for precast & conventional

Table 2 Total cost of construction


S.NO Description Precast construction Conventional construction
1 Super structure 526000/- 526000/-
2 Sub structure 2423000/- 1024000/
1024000/-
3 Finishing works 4351000/- 4469000/
4469000/-

http://www.iaeme.com/IJCIET/index.
IJCIET/index.asp 285 editor@iaeme.com
M. Madhu and K. Hemanth Raja

5. CONCLUSION
This paper represents to find out double-storey residential building project duration and project cost in both
construction methods, and compare the both precast construction and conventional construction method.
The building was completed within a short time by precast construction, easy to work and helpful in labor
shortage than the conventional construction. And the time of duration is reduced to 63 days by precast
construction. It is the main advantage of precast construction. But in the cost analysis, the conventional
construction was better than the precast construction in individual houses.

REFERENCES
[1] Nahmens I, Michael A. Mullens Lean Homebuilding: Lessons Learned from a Precast Concrete
Panelizer. Journal of architectural engineering. 2011 January; 17(4), 155-161.
[2] Neville B, Khalfan M A, Maqsood T. Off-Site Construction of Apartment Buildings. Journal of
Architectural engineering. 2013 March; 19(1), 51-57.
[3] Alistair G F G, Andrew R J D. Strategies for Integrating the Use of Off-Site Production Technologies in
House Building. Journal of Construction Engineering and Management. 2012 November; 138(11),
1331-1340.
[4] Warszawski A, Moshe A, Carmel D. Utilization of precast concrete elements in building. Journal of
American Society of Civil Engineers. 1984 December; 110(4), 476-485.
[5] Christian T, Lars H. Rethinking the business model in construction by the use of off-site "system
deliverance" the shaft project. Journal of Architectural Engineering. 2013 December; 19(4), 279-287.
[6] Jeong Y S, Eastman C M, Sacks R, Kaner I. Benchmark tests for BIM data exchanges of precast
concrete. Journal of Automation in Construction. 2009 July, 18(4), 469-484.
[7] Vacharapoom B, Nashwan D. Intelligence approach to production planning system for bespoke precast
concrete products. Automation in Construction. 2006 November; 15(6), 737-745.