Coal Mill

Coal Coal Coal Coal


Mill 1A Mill 1B Mill 2A Mill 2B
EMBEDED
Gear Box
Centerline Sole Plate Gear Box
Elevation check of sole plate
Gear Box
Leveling of sole plate gear box
Full grouting of gear box Sole
plate
Torqueing Anchor Bolt of Sole
Plate
Motor
Centerline Sole Plate Motor
Elevation check of sole plate
Motor
Leveling of sole plate Motor
Full grouting of Motor Sole plate
Torqueing Anchor bolt of motor
Sole Plate
Tie Rod
Centerline Sole Plate Tie Rod
Elevation check of sole plate Tie
Rod
Leveling of sole plate Tie Rod
Full grouting of Sole plate tie Rod
Torqueing Anchor bolt of Sole
NY NY
Plate tie Rod
SETTING
Gear Box
On basing Coal Mill Gear Box
Blue contact check and feeler gauge
Check between surface soleplate and
gear box base
Leveling check of gear box
Tightening of Gear Box bolt
Bottom Housing
Padding of bottom housing coal mill
On base of bottom housing coal mill
Center lining of Bottom Housing coal
mill
Leveling of Bottom housing coal mill
Elevation set of bottom housing coal
mill
Anchor Grouting of bottom Housing coal
mill

1 STG Mech Inspector


Full grouting of Bottom housing coal mill
Tightening Anchor of bottom housing
coal mill
Installation of Carbon Ring at bottom
housing
Driving Disc
On base of driving Disc
Clearance check between driving disc

and gearbox
Tightening of driving disc bolt
Scrapper Installation NY NY NY NY

Coal Mill
Coal Coal Coal Coal
Mill 1A Mill 1B Mill 2A Mill 2B
Grinding Ring and Nozzle ring
Tightening bolt lower of grinding ring
gap check between grinding ring and
driving disc

Housing of Coal Mill


On base of coal mill housing
Centerline of housing to tie rod center
Gap check between housing and driving
disc
Check of concentricity of housing
Welding of Housing to bottom housing

Grinding Roller
Cleaning of grinding roller part
On base of grinding roller
Aligning of roller to center mill
Check inclination of roller mill
Flush of roller oil NY NY NY NY
Filling oil to the roller NY NY NY NY

Loading Frame
On base of loading frame
Setting loading frame to the roller
Set the gap of loading frame to guiding
device
Install the tension rod
Connect tension rod to tie rod pedestal NY NY

Classifier
Install lower part of Classifier
Bolt tightening of Classifier lower part to

2 STG Mech Inspector


housing
Check of parallelism of upper to lower

of classifier
Check verticality of classifier
Welding between lower and upper
classifier

Instal reject Box

Instal the lubrication oil unit


Elevation Check of lubrication oil unit NY NY NY
Center line check of lubrication oil unit NY NY NY
Leveling check of lubrication oil unit NY NY NY

Coal Mill
Coal Coal Coal Coal
Mill 1A Mill 1B Mill 2A Mill 2B
Instal the hydraulic oil unit
Elevation Check of hydraulic oil unit NY NY NY
Center line check of hydraulic oil unit NY NY NY
Leveling check of hydraulic oil unit NY NY NY

Motor
On base motor
Pre alignment shaft motor and gear box

Install reject box

Install platform and rail NY NY NY NY

Motor Solo run NY NY

filling Oil to Gear Box NY NY NY NY

filling Oil to Lube Oil Unit NY NY NY NY

Filling oil to Hydraulic unit NY NY NY NY

Oil Flushing of Coal Mill System NY NY NY NY

Final alignment shaft NY NY NY NY

Mechanical Running Test NY NY NY NY

3 STG Mech Inspector


Note

NY = Not Yet

4 STG Mech Inspector