According to Master, at 0820hrs on 06th DEC., 2016 during the opening of all
cargo holds for checking condition of cargo, founded that the lashing wire were broken,
the equipments moved and damaged in cargo hold No3.
At 0420 hrs on 22ND, DEC. 2016 the M/V VICTORIA HARBOUR berth at the jetty
No4 Danang PORT.
From 0630hrs to 0730hrs 22ND, DEC. 2016 opening hatches cover, preparing for
discharging.
Before discharging, we observed that one wooden box of cargo in cargo hold
No3 was broken. Compared to pictures of cargo at loading port supplied by Chief
Officer, the wooden boxes of the cargo were shifted away from the original location, and
the lashing wire were replaced by chains.
After checking and taking the pictures of related evidences in the cargo hold and
at the time of discharging, we described the damage as follows( pictures attached):
-Initially, the wooden boxes with cargo insde were bound in cargo hold with
lashing wire. But during the voyage from Tianjin, China to Bayuquan, China under rough
sea condition and wind scale 7(Ships log book), the heavy cargo moved and the
lashing wire system couldnt stand the tension and was broken. After, the lashing wire
were replaced by chain.
-The lashing of the steel pipes under the damaged cargo box in normal condition.