Sie sind auf Seite 1von 24

3.

The doctrine of frustration

Introduction: initial and subsequent impossibility.

After the parties have concluded a contract, events beyond their control may occur which
frustrate the purpose of their agreement, or render it very difficult or impossible, or as
even illegal, to perform. An example of this is where a hall, which has been booked for
the performance of a play, is destroyed by fire, after the contract has been concluded, but
before the date of performance of the play. Some writers have seen a close resemblance
between this type of subsequent impossibility and the subject of common mistake (also
referred to as initial impossibility)
Both provide an important opportunity to define the strength of contractual obligation.
How absolute are they? Under what circumstances will a part be excused form
performing his contractual undertakings or from having to provide a remedy to the r
other.

In certain circumstances, it may by a fine, almost tenuous, dividing line between these
two different branches of contract law, in Amalgamated Investment & Property Co ltd v
John walker & sons Ltd [1976) 3 ALL ER 509, for example, the facts were:
The The defendants owned a commercial property which they advertised for sale as
being suitable for occupation or redevelopment. In July 1973 the plaintiffs agreed subject
to contract, to buy the property for $ 1,710,000. The defendants knew that the plaintiffs
purpose in purchasing the property was to redevelop it and that they would require
planning permission to do so. In their enquiries before entering into a binding contract,
the plaintiffs asked the defendants whether the property was designated (i.e. listed) as a
building of special architectural or historic interest. The defendants replied, on 141991
August that it was not. This was correct at the time. But in January 1973, unknown to the
parties officials at the Department of the Environment had included the property in a
provisional list of building to be listed as being of architectural or historic interest.
On 25 September, the parties signed the contract of sale on 26 September; the
Department of Environment wrote to the defendants and informed them that the property
had been included in the statutory list of buildings of special interest. (The list was given

Campus Bureau 1 Rose-


Janet Ayugi Masinde, 2012
legal effect the following day. It transpired that the property had been unconditionally
selected for inclusion in the list on 22 August. The value of the building without
redevelopment potential was one and a half million pounds less than the contract price!
The plaintiffs claimed rescission of the agreement on the basis of common mistake, or
alternatively, they sought a declaration that the agreement was void or avoidable and an
order rescinding the agreement.
The plaintiffs action was unsuccessful and specific performance was ordered against
them. The case could not be treated as one of common mistakes as the mistake did not
exist at the time the contract was concluded. It was after the contract was made that the
property was actually listed.
The alternative argument put forward by the plaintiffs was that the contract was
frustrated; that is, they had paid a high price for a property on the basis of its
redevelopment potential and subsequently found that this objective was not possible to
achieve. This contention was also rejected by the Court of Appeal, as the plaintiffs were
assumed to have taken the risk that the building may have been listed at some time after
the contract was concluded. They were very unlucky that it was listed at some time after
purchase, but this was an inherent risk in the ownership of buildings. In other words it
was foreseeable that the obtaining of planning permission, which was crucial to the
plaintiff, might be thwarted by the listing of the building.

Development of the doctrine of frustration


The doctrine of frustration is a means of dealing with situations where events occur, after
the contract had been concluded, which render the agreement illegal, or impossible to
perform, or even commercially sterile. The frustrating event must also not be the fault of
either party or foreseeable. Of course, the parties might expressly provide for the
consequences of a frustrating event by what is known as a force majeure clause. For
example, a building contract might provide for what will happen in the event of a strike.
In this way the parties themselves deal with the consequences of future events, which
might affect performance, and the doctrine of frustration will not apply. Certain types of
agreement, e.g. export sales, shipping, building or engineering contracts, are particularly
susceptible to disruption by unforeseen events. But in the absence of express provision by

Campus Bureau 2 Rose-


Janet Ayugi Masinde, 2012
the parties, the doctrine of frustration is a legal recognition of the fact that in some
instances it is just to excuse a party from his contractual obligations.

Until a little over a hundred years ago, the law was reluctant to excuse a party his
performance of a contract even in cases where superyening events rendered that
performance difficult or impossible. The rationale of this rule was that a party could
always make express provision for unforeseen events and, if he did not do so, he should
be bound by his contractual obligations. This is known as the absolute contracts rule,
which was clearly stated in the seventeenth century case of Paradine v Jane (1647). In
this case, P brought an action against D for the rent due on a lease. D argued that he had
been disposed of the land by force by an alien born, enemy to the king and kingdom
[who] had invaded the realm with an hostile army of men, D claimed that due to events
beyond his control he had lost the profits form the land and therefore, that he was not
liable for the rent. This plea was rejected by the court. D had undertaken an obligation to
pay rent under a contract and he was bound to fulfill this despite the supervening events.
He could always have expressly covered this contingency in his contract with P

This rigid approach has been mitigated, to some extent, by the gradual development of
the doctrine of frustration. However, it must be emphasized that the doctrine operated
within strict limits and does not provide an easy means of escape for those who have
simply made a bad bargain (see Amalgamated investment & Property Co Ltd John
Walker & Sons Ltd (1976) above. The famous case which marks the recognition of the
doctrine is Taylor v Caldwell (1863) 3 B & 826. The facts were as follows.

On 27 May 1861, Taylor entered into a contract with Caldwell which gave T the use of
Surrey Gardens and music hall on four separate days later that summer. T was to use the
premises for a series of four concerts, and for holding day and night fetes on the days in
question, and he was to pay $100 for each day. After the contract was concluded, but
before the date of the first concert, the music hall was destroyed by fire. The fire was not
the fault of either party and it made the performance of the concerts impossible. No

Campus Bureau 3 Rose-


Janet Ayugi Masinde, 2012
express provision had been made by the parties to cover this contingency. T claimed
damages for the money he had wasted in advertising the concerts.

It was held that the defendants were not liable and Ts claim for damages did not succeed.
This seems a fair decision, but how did the court circumvent the general rule that in a
contract to do a positive thing, a person must perform it or pay damages for failure to do
so? Blackburn J stated that this rule applies only where the contract is not subject to any
condition, either express or implied.

The judge held that the continued existence of the music hall was essential to the
performance of the contract and the parties contracted on this basis. Although there was
no express provision to this effect, the court implied one as a matter of construction. If
the parties had thought about it when making the contracts, they would have agreed to
such a condition. In other word the doctrine of frustration, as established in Taylor v
Caldwell, was based on an effort to give effect to the presumed intention of the parties.

The importance of the case is that it established the doctrine of frustration and made deep
inroads into the notion of absolute contractual obligations.

Once the doctrine of frustration had been established, its scope had to be determined.
Taylor v Caldwell (1863) dealt with the physical destruction of the subject matter of a
contract, and its result was unexceptionable. Similarly, where a contract is made to do
something, which subsequently becomes illegal (e.g. trading with a country against which
war is later declared), there is no difficulty in treating the contract as frustrated. But a
more common and problematic type of case is where the commercial purpose of a
contract is drastically affected by unforeseen events, whilst the performance of the
contract remains physically and legally possible. A good example is the famous case of
Krell v Henry [1903) 2 KB 740, where the facts were:

Henry (D) agreed to hire a flat in Pall Mall from Krell (P) for the days of 26 and 27
June. These were the days that the coronation processions of Edward VII were to take

Campus Bureau 4 Rose-


Janet Ayugi Masinde, 2012
place and the windows in the flat afforded good views of the procession route. D agreed
in writing, on 20th June, to pay $75 for the exclusive use of the flat on the two days of the
procession. The contract made no express reference to the coronation procession or to
any other purpose. A deposit of $ 25 was paid by D at the time of contracting and the
balance was to be paid the day before the procession s took place. Due to the Kings
illness, the processions did not take place on the proposed days. Krell claimed $50 from
Henry, who in turn counterclaimed for the return of the $25, which he had already paid
under the contract.

The Court of Appeal decided that the contract was frustrated despite the fact that its
performance was still physically possible. The doctrine is not strictly limited to cases in
which the event causing the impossibility of performance is the destruction or no-
existence of something which is the subject matter of the contract or of some condition or
state of things expressly specified as a condition of it (per Vaughan Williams LJ at 749)
Accordingly, the doctrine was applied in circumstances where some events, which must
reasonably be regarded as the basis of the contract, failed to take place. The flat in Pall
Mall could still have been used on the days in question, but the true purpose of the
contract was frustrated by the postponement of the precessions.

This was a potentially far-reaching and controversial decision. It extended the doctrine to
cases where the commercial object or purpose of the contract was frustrated. It raises
problems as to what exactly is the foundation for a particular contract.

Although the outcome of Krell v Henry seems fair, the courts have to be careful not to
allow a party a convenient means of escape form a contract simply because it turns out to
be a bad bargain. Krell v Henry represents perhaps, the furthest development of the
doctrine of frustration, and subsequent cases have suggested a rather narrower view.

An interesting contest to Krell v Henry provided by Herne Bay Steamboat Co v Hutton


(1903) The facts were that D agreed to hire the steamboat Cynthia form P for $250, on
28 and 29 June 1902, for the purpose of viewing the naval review and for a days cruise

Campus Bureau 5 Rose-


Janet Ayugi Masinde, 2012
round the fleet. A deposit of $50 was paid in advance. The royal naval review, which was
intended as part of the coronation festivities, was subsequently cancelled due to the Kings
illness. However, the fleet was still anchored at Spit head on 28 June. D did not use the
Cynthia on either of the agreed days and P sued for the balance of the hire charge. It was
held that P could recover the $200 form D and that the contract was not discharged on the
ground of frustration.

At first sight it might be difficult to see why the case was decided differently form Krell v
Henry. But on closer examination it is possible to distinguish it and to emphasize the
limited application of Krell v Henry. It was held by the Court of Appeal in Herne Bay,
that the taking place of the royal review was not the foundation of the contract, despite
the reference made to this event in the contract. It was still possible to cruise around the
fleet and therefore the whole purpose of the contract was not frustrated. It is also
significant that the contract was for the hire of a boat- something which is frequently
hired for a variety of purpose, whereas in Krell v Henry it was highly unusual for rooms
in Pall Mall to be let by the day.

The strict limits of the doctrine of frustration can be further illustrated by Tsakiroglou &
Co ltd v Noblee Thorl Gmbh (1962) the facts were as follows:
The appellants contracted to sell groundnuts to the respondents at a price which included
the carriage of the goods from the Sudan to Hamburg. Although no reference was made
to this in the contract, it was assumed that shipment of the goods would be via the Suez
Canal. The price of the nuts was calculated on this basis. After the contract was made, but
therefore its performance, the Suez Canal was closed to commercial traffic due to
political events. The alternatives route, via the Cape of Good Hope would have taken the
appellant more than twice as long to ship the goods and would have doubled the cost of
carriage. The appellants did not make the shipment and claimed that the contract had
been frustrated by the closure of the Suez Canal the house of Lords rejected this
argument. It was possible to ship the goods albeit at greater expense, and the contract was
not discharged. The court refused to imply a term that the goods were to be shipped by

Campus Bureau 6 Rose-


Janet Ayugi Masinde, 2012
the most direct route. The fact that the appellant had made what turned out to be a bad
bargain did not by itself lead to the doctrine of frustration being applied.
A court should not re-write the contract for the parties. The appellants were under a
contractual obligation to ship the goods to Hamburg by any reasonable route that was
available.

It was established that financial hardship alone is no reason for allowing a party to a
contract to rely on the doctrine of frustration. A clear statement to this effect was made by
the House of the Lords in Davis Contractors ltd v Fare ham UDC.
Davis Contractors agreed to build 78 housed for a local council, for the sum of $92,425
within an eight-month period. Due to serious shortages of skilled labour and material, the
work took 22 months to complete and cost Davis Contractors approximately $ 18,000
more that they had estimated. The contractors argued that the contract with Fare ham
council was frustrated due to the long delay, which was the fault of neither party. They
attempted to claim a larger sum than the agreed contract price as a fair reward for the
services they had performed for the council (i.e. they claimed on a quantum meruit basis.

The House of Lords rejected the argument of Davis Contractor; the contract was not
frustrates. The parties had contracted foe a specific number of houses, which had now
been built as agreed. There was not change in the basic obligations under the contract.
Mere hardship or inconvenience to one of the contracting parties was not enough to
frustrate a contract. Given the uncertainty in the supply of material and labour at that
time, the contractors could have made some express stipulation about this in the contract,
yet they failed to do so. They were not allowed to escape from a bad bargain by simply
arguing that the contract was frustrated.

Scope of the doctrine


Leases
It used to be argued that the doctrine of frustration could not apply to leases. This is
because a lease is not simply a contract enabling a tenant to make use of the land in

Campus Bureau 7 Rose-


Janet Ayugi Masinde, 2012
question; it creates a legal estate in the land. The argument ran that this legal estate
survives despite supervening events, which may prevent the use or enjoyment of the land
This is a rather technical view, which ignores the commercial reality of some leases
especially where the lease is short term and the tenant is concerned with the use to the
land for a specific purpose rather than in the creation of any legal estate. After some
judicial uncertainty on the subject. The leading case is now National carries Ltd v
Panalpina (Northern) Ltd (1981). The facts were as follows.
The appellant s had a 10-year lease of a warehouse form the respondents. After five and
a half years of the leas, the local authority closed the only access road to the warehouse
for a period of about 18 months. This closure of the road prevented the appellants form
using the warehouse for their business. As a result, the appellants stopped their payment
of rent to the respondents and claimed that the lease was frustrated.

The House of Lords decided that the closure of the access road was not a sufficiently
serious interruption to amount to a frustrating event. (This was in spite of the harm to the
appellants business caused by the closure) There was still a further three yeas of the lease
remaining when the road was opened again. The appellants were still liable for the rent
under the lease. But although the frustration claim in fact failed, the House of Lords held
that the doctrine is capable of applying to a lease. Their Lordships could see no reason
why, in principle, the doctrine should not apply to all types of contract.

Illegality
The doctrine of frustration will apply in circumstances where the performance of a
contract is contrary to some law passed after the contract is made.
This is often described as a case of supervening illegality. In such circumstances the
contract is not impossible to perform, nor have the obligations under the contract
(necessarily) been radically altered. It is more a question of public policy in ensuring that
the law is not broken. For this reason it is not possible for the parties to exclude the
operation of the doctrine, in relation to certain types of supervening illegality. (Such as
trading with the enemy) by express agreement.

Campus Bureau 8 Rose-


Janet Ayugi Masinde, 2012
An obvious example of a contracts frustration die to supervening illegality is where its
performance would involve trading with an enemy country at a time of war.

Other examples of supervening illegality are where new licensing regulations are
introduced after the parties have contracted, or where restrictions on the import or export
of certain goods are subsequently introduced.

Impossibility: destruction of subject matter


Appleby v Myers (1867(where P contracted to erect machinery on Ds premises. When
the work was well under way, but before it was completed, an accidental fire destroyed
Ds premises and the machinery that had been erected so far. Ps claim to recover damages
for the work already done and the cost of materials failed as the destruction of Ds
premises discharged both parties form their obligations under the contract.
The court s view was that the contract did not include an absolute undertaking by D that
his premises would remain unaltered so as to permit P to complete the work contracted
for. D had not assumed the risk of the accidental destruction of the premise.

Cases can occur where the subject matter of the contract is badly damaged by accident,
but not totally destroyed. For example, in as far v Blundell [1896} 1 QB 123, a ship with
a cargo of dated sank and was refloated after a few days. On arrival, it was found that the
cargo was badly affected by the accident. It was held that the cargo owner was not liable
to pay freight as the goods, in a commercial sense, had perished. It did not matter that the
goods could still be put to some other commercial use, such as distillation into spirit; their
nature had changed to such a degree that they could no longer be classified as dates.

Impossibility: sale of goods.


Where a contract involves the sale of goods, we have to look at the particular rules
relating to this subject in addition to the common law principles. A contract for the sale of
goods may be frustrated for reasons that we have already considered, such a supervening
illegality. But reference should also be made to the relevant provisions of the Sale of
goods Act 1979. Section 7 states that.

Campus Bureau 9 Rose-


Janet Ayugi Masinde, 2012
Where there is an agreement to sell specific goods, and subsequently the goods, without
any fault on the part of the seller or buyer, perish before the risk passes to the buyer, the
agreement. Is avoided.

So if S agrees to sell to B goods which are identified at the time the contacts is made and
those goods subsequently perish before the risk passes to B, the contract is frustrated (or
avoided)
Impossibility: death or illness.
Most commercial contracts do not require performance by a particular person and no
other. Therefore, death or illness does not normally prevent performance of the contract.
But where a contract is for some personal service, to be rendered by a party to the
contract, the death or incapacity of the party will make performance impossible.
Whincup v Hughes (1871) for example, the plaintiffs son was apprenticed to a
watchmaker for a six- year period at a premium of $25, but the watchmaker died after
just one year. The contract, which was for a skilled and personal service, was obviously
frustrated. In Robinson v Davison (1871) a contract was held to be frustrated when a
person who had been engaged to play the piano at a concert on a particular day, was
unable to do so because of illness. Notcutt v Universal Equipment Co (London) Ltd
(1986) a contract of employment was brought to an end, under the doctrine, as a result of
the employees chronic illness and his inability ever again to perform his contractual
obligations.

Impossibility: due to unavailability.


In some circumstances the subject matter of a contract, whilst still in existence, may
simply not be available for the purpose that was the contracted for.

In many cases the unavailability of the subject matter will only be temporary. If the
contract specifies performance within a particular time, or on a certain date, then the
unavailability of the subject matter at the crucial time will frustrate the contract. But it
may obvious whether there is a time limit on performance of the contract; In Jackson v
Union Marine insurance Co Ltd (1874) LR 10 CP 125 the facts were as follows:

Campus Bureau 10 Rose-


Janet Ayugi Masinde, 2012
Jacksons ship was chartered to go, in January 1872 directly form Liverpool to Newport
and there to load a cargo of iron rails to be shipped to San Francisco. Jackson took out
insurance on the chartered freight for the voyage. On the way to Newport, on 2 January
the ship ran aground in Caernarfon Bay. It took a month to free the ship and a future six
months for repairs to be carried out. Meanwhile, the chatterers had chartered another ship
as a replacement. Jackson claimed against the defendant insurance company for a total
loss of the freight to be earned under the contract, by perils at sea. To succeed with such a
claim, it was essential to decide whether the contract between Jackson and the chartered
was frustrated, or whether he could have successfully sued the chartered for not loading
the goods, in other words, did the chartered have the right to treat the contract with
Jackson as discharged.

It was held that a voyage undertaken after the ship had been repaired would have been a
very different adventure forms the one, which the parties had contracted for. A condition
could be implied that the ship would arrive in Newport in time for the particular voyage.
Its failure to do so within a reasonable time put an end to the contract. The long delay for
repairs meant that the contract was frustrated.

The court will sometimes have to decide whether a contract covering a lengthy period is
frustrated by supervening events, which cover part of the period. Typical examples of this
include the effects of a strike on a shipping contract or the requisition of a commercial
ship by the government at a time of war. Delay will frustrate a contract if it defeats the
commercial venture, but this can be difficult question to decide upon. In such instances
the court must look at both the length of the contract and the length of the interference,
which causes the unavailability of the subject matter. It should be noted that the courts are
supposed to judge the situation as at the date of the frustrating event and not with the
benefit of hindsight. This can lead to odd results. Tamplin Steamship Co Ltd v Anglo
Mexican petroleum products Co (1916).
A tanker was chartered from December 1912 for a five-year period. In February 1915,
the vessel was requisitioned as a troop ship. The owners of the ship claimed that the
contract was frustrated by this supervening event.

Campus Bureau 11 Rose-


Janet Ayugi Masinde, 2012
The House of the Lords decided that the commercial object of the contract was not
frustrated as, at the time of the event in question, it appeared likely that the ship would
still be available to fulfill a substantial part of the contract after the war ended. As it
turned out, the House of Lords was wrong in its assumption, because the war did not end
until 1918. But the case illustrated the difficulty in judging the likely effect on a contract
of some event, which causes the temporary unavailability of the subject matter.

Impossibility not just financial hardship


It was stated by Lord Radcliffe in Davis Contractors Ltd v Fare ham UDC [1956] AC 696
at 729: [I] t is not hardship or inconvenience or material loss itself which calls the
principle of frustration into play. There must be such a change in the significance of the
obligation that the thing undertaken would, if performed, be a different thing from that
contracted for.

In the example of Tsakiroglou & Co ltd v Noblee Thorl GmbH (1962(


The court refused to imply a term that the goods were to be shipped by the customary and
cheapest route.

Tsakiroglou shows the reluctance of our courts to extend the doctrine to cover cases of
impracticability or extreme financial hardship. But one case which offeres some, albeit,
slender, support for a wider application of the doctrine id Staffordshire Area Health
Authority v South Staffordshire Waterworks Co [1978] ALL ER 769. The facts were:

In 1929, the plaintiff hospital authority entered into a contract with the defendant water
company which provided that all times hereafter the hospital was to receive 5,000
galloons of water per day free, and all the additional water it needed at a rate of 7 d (later
agreed as 2.9p) per 1,000 gallons. This supply of water was in exchange for the hospital
having given up its right to take water from its own nearby well. By 1975m the provision
of water to the hospital at the agreed rate was clearly uneconomic; the normal rate
charged by the defendant was 45p per 1,000 gallons. The company wrote to the hospital

Campus Bureau 12 Rose-


Janet Ayugi Masinde, 2012
authority on 30 September 1975, giving six months notice of its intention to terminate the
1929 agreement. The company would still supply 5,000 gallons per day without charge,
but the excess would be provided at the normal (economic) rates. The hospital refused to
accept this notice and argued that the 1929 agreement was expressed as applying at all
times hereafter.

The court of Appeal rejected the hospital authority argument, and ruled that the defendant
companys notice was effective. The majority did not rely on the doctrine of frustration,
which explains why the case offers only slender authority for a wider interpretation of the
doctrine on the grounds of financial hardship. The court simply decided that the contract
could be brought to an end by giving reasonable notice. The judge did not think that the
hospital should be permitted to go on receiving its water at one-fifteen of the economic
rate.

Effects of express provision for frustrating event


The doctrine of frustration has developed as a means of dealing with subsequent,
unforeseen events which render performance of a contract impossible, or illegal, or which
fundamentally change the nature of the contractual obligations undertaken by the parties.
However, the parties may make express provision dealings with certain supervening
events and, in so doing, effectively preclude the operation of the doctrine. The original
theory behind the doctrine, as explained in Taylor v Caldwell (1863) was that it was
based on an effect to the presumed intention o the parties. In other words, it could not
operate if the parties had dealt with a particular contingency by express provision.

One obvious exception, as we have seen, is that frustration on the ground that the
contract involves trading with an enemy country cannot be excluded by express
provision. This is for reasons of public policy and is not exceptionable. But, generally, the
parties may make express provision for other types of supervening events, such as strikes,
closure of shipping rout, illness, floods, fires and other disaster. Thus the parties can
allocate the risk of such events as they see fit. They may, for example, expressly provide.
For an extension to the period of performance of the contractual obligation. They may

Campus Bureau 13 Rose-


Janet Ayugi Masinde, 2012
further provide that should the interference with the contract continue beyond a specified
period, then either party is entitled to terminate the contract. The parties can expressly
decide that neither party is entitled to compensation in the event of these contingencies.
Such forward planning is particularly useful for those involved in international trade,
where the threat of disruption is more likely.

Although the doctrine of frustration is limited to supervening events, which are not
expressly provided for in the contract, the court might interpret an express provision in
such a way that the doctrine may still operate. In Jackson v Union maritime Insurance
Co. Ltd (1874) a contract for the hire of a ship stated that the vessel was to proceed with
all possible spread (dangers and accidents of navigation excepted) from Liverpool to
Newport, in order to load a cargo of iron for San Francisco. The ship ran aground, not far
from Liverpool, and was delayed for eight months. It was held that notwithstanding the
express exception of dangers and accidents of navigation, the contract was frustrated. The
words of exception appeared to cover the contingency which in fact occurred, but the
court found a way of limiting their application because it clearly felt that a voyage
undertaken after the repair to the ship would have been a different adventure altogether.
Accordingly, the express provisions was given a restrictive interpretation by the court; it
would excuse the owner of the ship and protect him from an action for breach of contract,
but it would not deprive the charterer of the right to treat his contractual undertakings as
discharge.

Frustration does not apply to foreseeable events


The doctrine of frustration does not generally apply to situations where the supervening
event was foreseen or foreseeable. If the parties foreseeable that a particular event might
occur, which may affect their performance of the contract, it will be assumed that they
contracted in accordance with the risk. For example, in Davis Contractors ltd v Far ham
UDC [1956] AC 696, the House of Lords rejected the companys claim that the contract,
for the construction of 78 houses within a period of eight months for a fixed price, was
frustrated by shortages of labour and materials which increased the cost of the work. The

Campus Bureau 14 Rose-


Janet Ayugi Masinde, 2012
basic obligations under the agreement remained uncharged and financial hardship to one
of the parties was not sufficient reason for invoking the doctrine

The Davis Contractors decision can be defended on the basis that the risk of increased
costs due to various shortages, was clearly foreseen by the company. It must therefore be
assumed that it accepted that risk at the time of contracting.

Frustration cannot be self-induced


The doctrine of frustration applies only in circumstances where the supervening event is
beyond the control of the parties to the contract. It follows that where the alleged
frustrating event is caused by the deliberate act or decision of one of the parties, or by his
negligence, the doctrine will not apply. Whichever theory lies behind the doctrine-
whether it is simply a fair solution imposed by the courts- it is not possible to justify its
application to subsequent events, which are self, induced. An example of this rule is
provided by Ocean Tramp Tankers Corpn v V/O Sofracht, the Eugenia (1964) where the
facts were:
The Eugenia was let out to the charterers to go from Genoa to the Black
Sea to load cargo, and thence to India to unload cargo. Having loaded, the ship proceeded
on its route to India, which took it via Suez. In breach of contract, the chatterers allowed
the ship to enter a war zone. (The contract contained a war clause, which prohibited the
chatterer from sailing the ship into a dangerous zone without the owners permission) The
ship entered the Suez Canal and was trapped when the canal was closed. The chatterers
tried to rely on the detention of the ship as a frustrating event.

The Court of Appeal held that the charterers could not rely on the fact that the ship was
trapped in the canal, as this was their own fault, They were in breach of contract by
allowing the ship to enter a war zone and therefore, the alleged frustrating event was self-
induced.
Similar issues were raised in the House of Lords in Paal Wilson & Co A/S v
Partenreederei Hannaj Blumenthal, The Hannah Blumenthal [1983) I ALL ER 34. The
case concerned the sale of a ship under a contract, which provided that any dispute

Campus Bureau 15 Rose-


Janet Ayugi Masinde, 2012
arising out of the sale was to be settled by arbitration. Disputes arose about the vessel,
and the buyers commenced arbitration proceedings. As originally agreed, both parties
appointed. In all, there was a period of over seven years delay in the arbitration. The
question arose whether the arbitration agreement was frustrated as a result of the long
delay. Which was fault of both parties. The house of Lords held that in such
circumstances, the fact that the parties were under a mutual obligation to keep the
arbitration process moving meant that neither party could rely on the delay for the other
as a ground for claiming frustration of the agreement to arbitrate.

However, if the fault of a party to a contract is merely of a minor nature, he may still be
able to rely on the doctrine. It will be a question of degree as to whether the particular
fault or default amounts to self-induced frustration. For example, would a contract for
some personal performance be frustrated if the person concerned became incapacitated
by his own carelessness. - Such a professional acrobat who sustains injury on a private
skiing expedition and as a result, is unable to perform his act? This type of problem was
acknowledged, without being resolved, in Joseph Constantine Steamship Line Ltd v
Imperial smelting Corpn Ltd.
There seems to be no reason, in principle why events brought about by a partys own
negligence should not be regarded as self- induced and thus preclude the application of
the doctrine.

It should be noted that, where self-induced frustration is alleged, the onus of proof falls
on the party making the allegation. In Joseph Constantine, the owners of a steamship
(The kingwood) chartered the vessel to the respondents, to go to Australia and load a
cargo there. Before the cargo was loaded, an explosion occurred in the boiler of the ship,
preventing the contract form being carried out. The respondents sued the owners for
damages and the owners claimed that the explosion frustrated the contract. The
respondents argued that the owners of proof rested on the owners to show that the
explosion was not their fault. The House of Lords held that the contract was frustrated.
The cause of the explosion was not clear, but the respondents had failed to prove that the

Campus Bureau 16 Rose-


Janet Ayugi Masinde, 2012
frustrating event was the owners fault. The burden of proof was not on the owners to
disprove negligence on their part.

Effects of the doctrine


We must now consider the practical consequences that arise when the parties are
discharged under the doctrine. Unless the law provides for a fair distribution of the loss
resulting form the supervening event, it may not be satisfactory simply to hold that the
contract is frustrated. For example a party may have incurred considerable expenditure in
reliance upon the contract before the frustrating event occurred.

It is well settled that frustration automatically brings the contract to an end at the time of
the frustrating event.
This is in contrast to discharge by breach of contract where the innocent party can choose
whether to treat the contract as repudiated. Moreover, a contract, which is discharged by
frustration, is clearly different from one, which is void for mistake. A frustrated contract
is valid until the time of the supervening event but is automatically ended thereafter,
whereas a contract void on the grounds of mistake is a complete nullity form the
beginning. A clear statement about the legal effect of frustration on a contract can be
found in Hirhi Mulji v Cheong Yue Steamship Co Ltd [1926] AC, 497, where the facts
were:
The respondent owners of a ship, The Singaporean, agreed by a charter party of
November 1916 to hire their vessel to the appellants from 1 March 1917. The appellants
agreed to use the ship for 10 months from the date do delivery, Before 1 march 1917, the
ship was requisitioned by the government and not released until February 1919.when the
ship was requisitioned, the owners, thinking that se would soon be released, asked the
appellants if they were still willing to take up the charter (i.e. a little later). The
Appellants said that they would do so, but when the ship was finally released (later than
expected) in February 1919, they refused to accept it. The owners argued that the
appellants could not rely on the doctrine of frustration, despite the supervening event, as
they had chosen to affirm the contract.

Campus Bureau 17 Rose-


Janet Ayugi Masinde, 2012
On appeal from the Supreme Court of Hong Kong, the Privy Council held that the
contract was frustrated in 1917. This meant that the obligations under the contract
brought to an end immediately and automatically at the time of the frustrating event. The
application of the doctrine did not rely upon the election of the parties. So eve where the
parties continue to treat the contract as subsisting for a period of time after the
supervening event, the court may declare it to be frustrated.

As a consequence of the rule that a contract is valid until the time of the frustrating
event, and is determined automatically thereafter, certain other rules were said to follow.
The common law position was encapsulated in the slight enigmatic expression that the
loss lies where it falls. For example, where money was paid under a contract, which was
later frustrated, it was not recoverable. This was because parties remained liable for
contractual obligations, which fell due before the supervening event. On the other hand,
the parties escaped form performing those obligations, which had not yet fallen due to the
time of frustration. The potential for unfairness decisions in Chandler v Webster [1904] 1
KB the facts were;
The plaintiff contracted to hire a room in Pall Mall from the defendant for the purpose of
watching the coronation procession on 26 June 1902. The price for the hire of the room
was $141 15s and it was payable immediately. The plaintiff paid $ 100, but before he paid
the balance the procession was canceled due to the illness of the king. The plaintiff
sought to recover back the money he had paid.
The Court of Appeal held that his claim could not succeed. Moreover, he was liable for
the remaining $41 15s as this obligation had fallen due before the frustrating event
occurred. Despite receiving no actual benefit whatsoever, the plaintiff was still liable for
the hire of the room.

The harsh results of this rule as laid down by Chandler v Webster (1904) were not
surpricingly, subjected to considerable criticism, The law Revision Committee suggested
that the rule should be changed but, before any implementation to this report took place,
Chandler v Webster was overruled by Fibrosa Spolka Akcyjna b Fairbairn Lawson
Combe Barbour Ltd [Ltd} AC 32 (the Fribrosa case) The case involved a contract under

Campus Bureau 18 Rose-


Janet Ayugi Masinde, 2012
which the respondents an English company, were to manufacture certain machinery for
the appellants, a Polish company, and deliver it to Gdynia. The appellant were to pay
$4,800 for the machinery, a third of which (ire $ 1,600) was to be paid with the order. In
fact only $1,000 was paid with the order. Subsequently, Germany invaded Poland and
occupied Gdynia. At this time, none of the machinery had been delivered. For reasons,
which we have considered earlier, the contract was frustrated and the appellants sued for
the return of the $1,000.

The Court of Appeal followed the rule in Chandler v Webster and held the money was
irrecoverable. But the House of Lords decided that there had been a total failure of
consideration and that the appellants were entitled to recover $ 1,000 for the respondents.

The decision in the Fibrosa case was an improvement on the harshness of Chandler v
Webster, but was not a complete solution to the problem of money paid under a contract,
which was then frustrated. This was freely acknowledged by their Lordships in the course
of their judgments (see [1943} AC 32 at 49-50, 54-5 and 71-2). Recovery of money paid
depended on there having been a total failure of consideration the performance of a part
of the consideration would thus prevent such a claim form succeeding.

Furthermore, the decision in the Fibrosa case made no allowance for the expenses, which
were incurred under the contract by the payee. In other words, it was rely a fair solution
to both parties it provided for the return of the prepayment, but it did not compensate the
recipient for the expenditure that it had incurred whilst partially carrying out the contract.
In the Fibrosa case itself, the $ 1,000 was recoverable, but the English company received
nothing for the considerable amount of work it had done on the machinery before the
frustrating event. The common law did not allow the appointment of the prepaid sum in
this situation. To deal with these obvious defects in the law, the law reforms (frustrated
Contracts) Act 1943 was enacted soon after the fibrosa case.

Campus Bureau 19 Rose-


Janet Ayugi Masinde, 2012
The law Reform (frustrated contracts) Act 1943
General

The law reforms (frustrated Contracts) Act 1943 was introduced in an attempt to provide
for a fair solution between the parties when their contract had been frustrated. It aimed at
preventing the unjust enrichment of either party to the contract at eh expense of the other.
It deals only with situations where contracts have become impossible of performance or
been otherwise frustrated and the parties have consequently been discharged from further
performance (s1 (10. It should be noted that the Act does not lay down the general
principles under which the doctrine will be invoked and this question is still dealt with
under the common law rules that we have considered earlier in this chapter. Also the
parties may themselves have made express provision for the frustrating event which has
occurred, in which case, under s 2(3) the court is to give effect to the parties intentions
and the Act is excluded by their contrary agreement.

LR (FC) 1943 does not apply to all types of contract. Section 2(5) states that the Act is
not applicable to the following.
(a) Any charter party, except a time charter party or to any contract (other than a
charter party) for the carriage of goods by sea: or
(b) Any contract of insurance
(c) Any contract to which section 7 of the sale of goods Act (now 1979) applies, or to
any other contract for the sale, or for the sale and delivery, of specific goods, where
the contract is frustrated by reason of the fact that the goods have perished.

The main changes introduced by the Act.

All sums paid or payable to any party in pursuance of the contract before the time when
the parties were discharge (in this Act referred to as the time of discharge) shall, in the
case of sums so payable, cease to be so payable.

Campus Bureau 20 Rose-


Janet Ayugi Masinde, 2012
In other words this subsection enacts that advance payments made in pursuance of the
contract before the supervening event are recoverable.
It also provides that money which is payable under the contract before the frustrating
event, but not yet paid, ceases to be payable. Of course, there will be cases where the
recipient of the advance payment has incurred expenses before the contract was
frustrated. It may well be that the parties agreed on some advance payment for this very
reason. If the whole sum is recoverable, on discharge, then this reason, the new
provisions are subject to the following important proviso, which is appended as to s 1(2)

Provided that if the party to whom the sums were so paid or payable incurred expenses
before the time of discharge in or for the purpose of, the performance of the contract, the
court may, if it considers it just to do so having regard to all the circumstances of the
case, allow him to retain or, as the case may be, recover the whole or any part of the sums
so paid or payable, not being an amount in excess of the expenses so incurred.
This award of expenses can be made only where an advance sum was either paid or
payable before the frustrating event.

A party has incurred expenses in the performance of the contract may be awarded his
expenses up to a limit of the sums paid or payable to him under the contract the
frustrating event. Such an award will be made where the court considers it just to do so
having regard to all the circumstances of the case. - In other words any award is at the
discretion of the court.

The more recent case of Gamerco SA v ICM/Fair Warning (Agency) Ltd [1995) 1 WLR
1226 provides a rare judicial discussion of the application of LR (FC) a 1943, s 1(2).
The facts were that, in 1992, the plaintiff concert promoters (p) agreed to promote a pop
groups (Ds) concert at a football stadium in Madrid on a specific date, as part of that
groups European tour. Shortly before the date of the concert, but after the contract was
made by the parties, engineers discovered that the stadium was unsafe and its use was
subsequently prohibited by the local authorities. Thus, Ps permit to hold the concert was
withdrawn and, as not other suitable venue was available at this time, the concert was

Campus Bureau 21 Rose-


Janet Ayugi Masinde, 2012
cancelled. P had paid $412,500 to D in advance, and both parties had incurred some
expenditure in preparing for the concert. The action involves Ps claim to recover the
advance payment under s 1(2) of the act, and D s Counterclaim for breach of contract by
P for failing to secure the requirement permit for the performance.

The judge, Garland J, in the High court held that the contract was frustrated due to the
stadium being unsafe and its use for the contract being banned. Ds counterclaim was
unsuccessful, as P was not required to ensure that the permit, once obtained, would
remain in force. More significantly, it was decided to allow Ps claim in its entirety, with
the judge ordering the repayment of the whole sum paid in advance despite the fact that D
had incurred some expenditure in advance of the proposed performance, justice would be
done by making no deduction form the ordered repayment under the proviso. It seems
that the precise nature of Ds expenses was not very clear and the judge found it
impossible to determine an accurate amount.
Presumably it was felt that p expenses were heavier and more calculable than those of the
defendant pop group.

Another important innovation introduced by LR (FC) a 1943 is contained in s1 (3) which


states

Where any party to the contract has by reason of anything done by any other party thereto
in or for the purpose of, the performance of the contract, obtained a valuable benefit
(Other than a payment of money to which [section 1(2) applies) before the time of
discharge, there shall be recoverable form him by the said other party such sum (if any)
not exceeding the value of the said benefit to the party obtaining it as the court considers
just, having regard to the circumstances of the case and in particular-
(a) The amount of any expenses incurred before the time of discharge by the benefited
party in or for the purpose of, the performance of the contract, pursuance of the
contract and retained or recoverable by that party under [section 1 (2) and
(b) The effect in relation to the said benefit of the circumstances giving rise to the
frustration of the contract.

Campus Bureau 22 Rose-


Janet Ayugi Masinde, 2012
20.52 An illustration of the potential usefulness of LR (FC) a 1943, s 1(3) is provided by
the old case of cutter v Powell (1975). The second mate of a ship, the Governor party,
was promised 30 guineas for the completion of a voyage form Kingston (Jamaica) to
Liverpool. The sailor died after seven weeks of the voyage and his widow (the executrix)
claimed a proportion of his wages, on a quantum meruit basis, for the work he had done
on the voyage before his death. The court rejected the widow claim; the contract
stipulated that the voyage had to be completed. This sometimes referred to as the doctrine
of strict performance.

It is possible that the outcome of Cutter v Powell would be different today under s 1(3)
and that the widow could recover from the defendant for the valuable benefit which he
had obtained form the sailors labour. But it is also possible that the Act would have been
excluded by the contrary agreement of the parties, as provided for by s 2(3) this might
depend on the construction of their agreement. Did they agree for example that there was
to be not payment whatsoever unless the entire voyage was completed by the sailor.

The first major case to be decided on the law reform (frustrated contracts) Act 1943 was
BP Exploration Co (Libya) Ltd v Hunt The facts were as follows.
Nelson Hunt had been granted an oil concession in Libya by the government of that
country. He entered into an agreement with a larger oil company, BP, to exploit the oil
concession, as he lacked the resources to go ahead on his own. BP were to do the
exploratory work, which they would finance, and in return they would get a half share of
Hunts concession. Thy also had to make certain farm- in payments to Hunt in cash and
oil. As soon as the oil field become productive, BP were to receive half of all the oil
produced from it, together with reimbursement oil (taken form Hunts share) to meet the
cost of the companys farm-in payments and to cover Hunts share of eh development
expenses. Thus BP were to bear the principal risk of failure risk of failure in their
combined venture. After much expenditure, a large oil field was discovered, which
became productive in 1967. But in 1971 BPs half share in the concession was
expropriated by the new Libya n government, following a revolution in that country. The

Campus Bureau 23 Rose-


Janet Ayugi Masinde, 2012
same fate befell Hunts half share in 1973. At the time of the frustrating event, BP had
received about one-third of the reimbursement oil to which they were entitled. The
company brought a claim under s 1(3) of the act for an award of a just sum.

The claim was allowed by Robert Goff J and he awarded BP a just sum under s 1(3) of
the act. The precise calculation of the amount is a complex matter, which will not be
elaborate here. Hunts appeals t both the court of Appeal and the House of the Lords were
successful, the main judgment on the scope of s 1(3) is that of the trial judge. (In the
House of Lords, their lordships dealt with fairly minor, technical values of the oil
concession as a result of BPs work. It should be noted, however, that the value of this
benefit was substantially reduced by the circumstances giving rise to the frustration of the
contract, namely the expropriation of the parties interests in the oil field.

Campus Bureau 24 Rose-


Janet Ayugi Masinde, 2012

Das könnte Ihnen auch gefallen