ThepurposeofthisdocumentistoexplainthebasicsofMRParea,steps
involvedinactivatingMRPareaandtouseitindifferentpossibleways.
AsweknowMRPrunsatplantlevel(centralized),butasperbusinessneed
wemayhavetoplanMRPforindividual&independentplanningareas
(decentralized).ThiscanbeachievedbyactivatingMRPareas.TheseMRP
areasarefullyconfigurableorganizationalunitswithinECCwhereMRPcanbe
runindividually.SowecanbroadlyclassifyrunningMRPin2majorways.
https://blogs.sap.com/2015/07/01/basicsofmrparea/ 1/22
22/11/2016 BasicsofMRPAreaSAPBlogs
MRPatplantlevel:Thesystemaddstogetherstocksfromallof
theindividualstoragelocationstodeterminetotalplantstock.The
requirementsarecombinedintheplanningrunandprocurement
elementsarecreatedforthesepeggedrequirementswithunknown
sources.Individualstoragelocationscanbeplannedseparatelyorbe
excludedfromplanning.
Illustration:
MRParealevel:Onlythestocksfromthestoragelocationsor
subcontractorassignedtotherespectiveMRPareaaretakeninto
account.TherequirementsinthisparticularMRPareaarecombined
andprocurementelementsarecreatedforthem.Thisenablesustoplan
materialrequirementsspecificallyforcertainareas(MRPareas).
https://blogs.sap.com/2015/07/01/basicsofmrparea/ 2/22
22/11/2016 BasicsofMRPAreaSAPBlogs
Illustration:
YoucandefineMRPareaswithinaplantandcarryoutMRPspecifically
forthatparticulararea,forexampleinaboveillustration,forMRParea
M0001canbeplannedindependentlywithoutrunningMRPforplant
FP01.
IneachMRPareayoucancontrolstagingandprocurementofpartsthat
areproducedinhouseorexternally.AllMRPproceduresaresupported
byMRPareasandonecandisplaytheresultofMRPrunforeachMRP
area.
MRPArea(definition):
AsperSAP,MRPArearepresentsanorganizationalunitforwhich
materialrequirementsplanningiscarriedoutindependently
MRPAreaisfunctionalityforspecialplanningprocessthatenablesyou
tocarryoutplanningnotonlyatplantlevelbutalsoatdifferentplanning
levels(eg,storagelocation&subcontractors).Thereare3typesof
MRPareasinSAP
PlantMRPArea
MRPAreasforstoragelocation
MRPAreasforSubcontractors
PlantMRParea:
https://blogs.sap.com/2015/07/01/basicsofmrparea/ 3/22
22/11/2016 BasicsofMRPAreaSAPBlogs
MRPareacanbecreatedatplantlevel.Ondoingso,systemcombinesallits
storagelocationsandstockwithsubcontractorsunderthatMRParea.When
youdefineMRPareasforstoragelocationsandforsubcontractorsandassign
materialtonewlycreatedMRPareaswithinplantthentheplantMRParea
getsreducedbyexactlythenumbersofsubcontractorsandstoragelocations.
ThisisbecausetheywillnowbeplannedseparatelyinnewMRPareas.
MRPareaforstoragelocation:
MRPareacanalsobedefinedforstoragelocationormultiplestorage
locations.Materialrequirementsforthisstoragelocationarethenplanned
separatelyfromtherestoftheplant.Importantpointtonotehereisthatyou
canassign1storagelocationtoonly1MRPareabutyoucanhavemultiple
storagelocationsundersingleMRParea.ItsaNto1relationship.
MRPAreasforSubcontractors:
YoucanalsodefineanMRPareaforeachsubcontractor.Importantpointto
notehereisthatasubcontractorcanbeassignedtoonlyoneMRPareaina
plant.AnMRPareaofthesubcontractortypecanonlycontainone
subcontractor.Itsa1to1relationship.
HowtosetupMRPareainSAP
Thereare2aspectsofsettingupMRParea.Firstoneistoactivateitin
customizingandsecondpartittosetupmasterdata(i.e.adding
materialstothatparticularMRPareainmaterialmaster).
MRPwithMRPareaisnotoperationaluntilyouassignMRPareatoa
particularmaterialinmaterialmasterorinorderwordscreateaMRP
areasegment.IfyouhavenotassignedamaterialtoanMRParea,that
https://blogs.sap.com/2015/07/01/basicsofmrparea/ 4/22
22/11/2016 BasicsofMRPAreaSAPBlogs
is,youhavenotcreatedanMRPareasegmentinthematerialmaster,
thematerialwillcontinuetobeplannedintheplantMRPareaonly.
Step1ConvertingPlanningfileentries
Path:SPRO>Production>MaterialRequirementPlanning>
MasterData>MRPAreas>ConvertPlanningfileentriesfor
MRPareasOM0ForSE38programRMDBVM00
WhenweconvertplanningfileentriesforMRParea,systemcreatesplant
MRPareaforeachplant.Followingentriesfrombelowtablesareconverted.
PlanningfileentriesaremaintainedinMRPfilewhichareconvertedtoMRP
areafileinbelowtables.
PlanningfileentriesinMDVMareconvertedtoDBVM
PlanningfileentriesinMDVLareconvertedtoDBVL
PlanningfileentriesinKDVMareconvertedtoKBVM
PlanningfileentriesinKDVLareconvertedtoKBVL
Ifyouarerunningconvertingplanningfilesforthefirsttimethensystem
willautomaticallycreateplantMRPareas.Thesenewentriescanbe
seeninOMIZunderplantMRPareawithareatype01.
https://blogs.sap.com/2015/07/01/basicsofmrparea/ 5/22
22/11/2016 BasicsofMRPAreaSAPBlogs
IMPnote:Aftertheconversion,contentsofMDVM/MDVL/KDVM/KDVL
aredeletedandentriesarecreatedinDBVM/DBVL/KBVM/KBVL.
Step2DefineMRPareainSPROOMIZ
Path:SPRO>Production>MaterialRequirementPlanning>
MasterData>MRPAreas>DefineMRPareas
MRPareahas3types(01,02&03)andsystemwillallowyoutohaveMRP
areasinbelowtypesonly(Plant,StoragelocationorSubContractor)
PlantMRPareashouldhavesamenameasplantsoyoucanhaveonly
oneentryforplantMRParea.Forexampleplant1000willhaveplant
MRPareaas1000.
Inordertomaintainconsistencyanduniformity,onlyMRPareasofthe
typeplantareallowedtohave14digitskey.SlocMRPareashould
haveminimumof5digits.ExampleM0001etc
Youcanonlyhave1subcontractorvendorassignedto1MRParea.
MultiplevendorscannotbegroupedtogetherinasingleMRParea.
https://blogs.sap.com/2015/07/01/basicsofmrparea/ 6/22
22/11/2016 BasicsofMRPAreaSAPBlogs
Youcanhavemultiplestoragelocationscombinedtogetherinasingle
MRParea.
YoucanonlyoneentryforplantinplantMRParea.Multipleplants
cannotbegroupedtogetherinasingleMRParea.
OnceMRPareaisdefined,nextstepistoActivateMTParea
Step3ActivatingMRPAreasOM01
Path:SPRO>Production>MaterialRequirementPlanning>
MasterData>MRPAreas>ActivateMRPforMRPareas
NOTE:MRPareasareactivatedatclientlevel.Onceyouactivateit,itwillbe
availableforallplantsandMRPareasfeatureswouldbeavailabletouse.
ThissumsupsettingupMRPareaconfigurationinSAPcustomizing.
YoucanfindfollowingchangesduetoactivationofMRParea.Theseare
justfewforexample
MD61PlRcreation
https://blogs.sap.com/2015/07/01/basicsofmrparea/ 7/22
22/11/2016 BasicsofMRPAreaSAPBlogs
MRP
MaterialMaster
StockRequirementlist
https://blogs.sap.com/2015/07/01/basicsofmrparea/ 8/22
22/11/2016 BasicsofMRPAreaSAPBlogs
Step4:MasterdataforMRParea
ThematerialwillnotbeconsideredinMRPareaplanninguntilitsextendedto
MRParea.FollowingstepsshowshowtoextendamaterialinMRParea.You
canextendamaterialtomultipleMRPareasbasedontheneed.
GotochangematerialmasterunderMRP1screenandassignMRPareaas
shownbelow:
YouwillhaveadditionalviewsforMRP1,MRP2,Forecast&Consumption
values.Youneedtofillrequiredfieldsasperyourneed.
https://blogs.sap.com/2015/07/01/basicsofmrparea/ 9/22
22/11/2016 BasicsofMRPAreaSAPBlogs
WhenyouassignamaterialtoanewMRParea,anewrecordforthis
assignmentgetsaddedintheplanningfile.Youhaveanoptiontodefine
individualMRPandforecastparametersforeachMRPareathatyou
assigntoamaterial.Theseparameterscandifferfromthosedefinedin
thematerialmasteratplantlevel.Asanexample,youcanhavedifferent
MRPcontrollers,lotsizeorMRPtypeforeachindividualMRPareasthat
isassignedtoamaterial.
Userscansetupdifferentforecastmodelandconsumptionvaluesin
MARareatabs.OnceMRPwithMRPareaisactivated,ATPcheckis
alsoactivatedatMRParealevel.
ScopeofplanningwithMRParea
Youcancreatescopeofplanningrunifyouwanttocarryouttotal
planningforlimitedMRPareas.IncaseyoudonotgiveanyMRParea
intotalplanningrun,systemwillconsiderallMRPareasunderaplant
andplanforthemintotalplanning.
Forsingleitemplanningsystem,inMD02&MD03systemplansa
materialonlyinthespecifiedMRParea.
SampleScenario:
LetsconsideramaterialAssemblymaintainedinplantZSY1under2storage
locations(ZSY3&ZSY4)
SlocZSY3maintainedinMRPareaMA001.AssemblyisextendedtoMA001
withfollowingstocksituation
ZSY3100(understoragelocationMRPareaMA001)
ZSY4150(underPlantMRPareaZSY1)
https://blogs.sap.com/2015/07/01/basicsofmrparea/ 10/22
22/11/2016 BasicsofMRPAreaSAPBlogs
LotsizeforsamematerialismaintainedasFX(fixedlotsize)inMA001MRP
areaandEXinplantMRPareaZSY1
TotalstockMMBE
MD04MRPAreaZSY1
https://blogs.sap.com/2015/07/01/basicsofmrparea/ 11/22
22/11/2016 BasicsofMRPAreaSAPBlogs
MD04MRPAreaMA001
LetshaverequirementfromaSalesorderforplantZSY1,itwillcomeunder
plantMRPareaZSY1
Fortesting,wecanalsohavePIRcreatedforspecificMRPareaMA001
HereisthestocksituationofMD04withsalesorderinPlantMRParea
StockrequirementforMRPareaMA001:
https://blogs.sap.com/2015/07/01/basicsofmrparea/ 12/22
22/11/2016 BasicsofMRPAreaSAPBlogs
IfwerunMD02forplantZSY1,systemwillonlyconsiderplantMRParea
andwillnotplanforMRPareaMA001asitsaseparateplanningarea
MRPareaMA001isuntouched:
AfterrunningMRPforMA001systemcreatesplannedorderfor200
quantities
MaterialAssemblywasmaintainedasEXlotsizeinplantMRPareaand
withfixedlotsize200inMA001henceplannedorderof200Qtycreated
inMA001.Inthiswayseparateplanningparameterscanbemaintained
torunrequirementplanningusingMRPareas.
~~~~~~~~~~~~~~~
https://blogs.sap.com/2015/07/01/basicsofmrparea/ 13/22
22/11/2016 BasicsofMRPAreaSAPBlogs
Thankyouforreadingthisdocument.Pleasefeelfreetosuggestany
changeandmodificationneededtoimprovethedocument.
*ScenariosrelatedtoMRPareaswillbecoveredinaseparate
document.Thelinkwillbeaddedbelowoncecompleted
AlertModerator
27Comments
AmitSharma
July3,2015at2:17pm
HelloRohit,
Againaverywellexplainedandinformativedocumentfromyou.
Thanxalotforsharing!!!
Regards,
AmitSharma
RohitSingh Postauthor
July3,2015at4:49pm
HelloAmit,
Thankyouforthecomments.Theintentistokeepthemaseasyas
possibletohelpconsultantsofanydomian.
Regards,
Rohit
https://blogs.sap.com/2015/07/01/basicsofmrparea/ 14/22
22/11/2016 BasicsofMRPAreaSAPBlogs
SagarMane
July6,2015at7:15am
HiRohit,
Asalwaysgreatworkfromyou.
Reallyeasyandsimpledocumenttounderstand.
Regards,
Sagar
RohitSingh Postauthor
July6,2015at8:34am
HiSagar,
Thankyouforthecomments.Iamplanningtoaddfewmore
samplescenariosinthisdocumenttodemonstrateremaining
functionalityofMRParea.
Regards,
Rohit
akshaysonurkar
July6,2015at12:04pm
HiRohit,
Greatpieceofwork.Keepitup.
Regards
Akshay
akshaysonurkar
July6,2015at12:06pm
HiRohit,
Goodjob.Expectingfewmoresuchvaluableinformationinfuture.
https://blogs.sap.com/2015/07/01/basicsofmrparea/ 15/22
22/11/2016 BasicsofMRPAreaSAPBlogs
Regards,
Akshay
RohitSingh Postauthor
July6,2015at12:14pm
HiAkshay,
Thankyouforyourfeedback.Willdefinitelybeaddingmore
documentsinthisspace.
Regards,
Rohit
SureshM
July6,2015at12:10pm
GreatWorkRohit.
SuperbexplanationonMRPArea.
ThanksforsharingtheGoodKnowledge.
Regards
Suresh.M
RohitSingh Postauthor
July6,2015at12:16pm
HiSuresh,
Thankyouforthenicefeedback.Iwillbesharingmoresuch
documentsincomingdays.
Regards,
Rohit
SureshM
https://blogs.sap.com/2015/07/01/basicsofmrparea/ 16/22
22/11/2016 BasicsofMRPAreaSAPBlogs
June26,2016at6:33pm
HiRohit
Instep1mentionedSPROpathiswrongandT.code&
Programarecorrect.
PathisSPRO>IMG>Production>Material
RequirementsPlanning>PlanningFileEntries>
ConvertPlanningFileEntriesforMRPAreas.
Kindlychangeit.
Regards
Suresh.M
NitinSharma
July8,2015at7:05am
HiRohit
Veryhelpfuldocumentthanks.
Butihavesamequeryinthebelow.
IfiwantthatsaleorderalsowillcomeintheMRPareaOnly.
Exp:WehavecustomerXXXandtherequirementwillcomeintheformofSale
order.Andforthiscustomerwehave1vendorfordoingAssembly.Quantityof
FGMaterial:130
Astakehelpofyourdocument.IcreateOneMRPareaforthiscustomerandiwant
myallrequirementwillcomeinthisMRPAreaonly.SaleorderandPIRifany
andavailablestock.
Pleaseguide
Thanks
RohitSingh Postauthor
July14,2015at10:29am
HiNitin,
Thankyouforthecomments.
https://blogs.sap.com/2015/07/01/basicsofmrparea/ 17/22
22/11/2016 BasicsofMRPAreaSAPBlogs
Ifyouwantasalesorderrequirementtobeconsideredina
perticularSlocMRPareathenyouhavetoenterstoragelocationin
SalesOrder.IfaSlocisnotmaintained,systemwillconsideritin
PlantMRParea.
InordertohaveitconsideredinaperticularstoragelocationMRP
area,youneedtomentionSlocinitemdetailsundershipping.
Regards,
Rohit
SAPERP
July8,2015at7:26am
DearRohit,
Thankyouforthishelpfuldocument
RohitSingh Postauthor
July14,2015at10:29am
HiThere,
Thankyouforthecomments.
Regards,
Rohit
DebrajBhaduri
July16,2015at3:13am
DearRohit,
Itsreallyaverygooddocument.
Regards
Debraj
https://blogs.sap.com/2015/07/01/basicsofmrparea/ 18/22
22/11/2016 BasicsofMRPAreaSAPBlogs
RohitSingh Postauthor
July16,2015at5:11am
DearDebraj,
Thankyouforthefeedback.
Regards,
Rohit
SAPCONS
August11,2015at12:19pm
HiRohit,
WonderfuldoconMRParea.Wearewaitingforvariousbusinessscenarioson
MRParea.
Regards,
SAPCONS
RohitSingh Postauthor
August12,2015at12:24pm
ThankYouSAPCONS,
Iamlittleoccupiedinmycurrentassignmentandnotabletoprepare
otherscenariosbutIwillbepostingthemsoon.
Regards,
Rohit
VibinVJoseph
August12,2015at11:42am
DearRohit,
MarvelousandThingshasbeenexplainedinwelldetail.Thanksforsharing.
https://blogs.sap.com/2015/07/01/basicsofmrparea/ 19/22
22/11/2016 BasicsofMRPAreaSAPBlogs
Regards,
Vibin.V.Joseph
RohitSingh Postauthor
August12,2015at12:26pm
DearVibin,
Thankyouforthecomments.
Regards,
Rohit
AnanthSuryaNarayanaMurtyDulipala
March22,2016at5:26pm
HelloRohit,
Informativedocument,thanksforthis.CanweuseVendorlevelMRParea
conceptinISAUTO??
Thanks&Regards
Ananth
nawfelkefi
April18,2016at12:29pm
thankyousomuchfortheveryusefuldocument
sushantkatekar
June14,2016at12:41pm
thankyouRohitforsuchincredibledoc,Ihaveonedoubt,
https://blogs.sap.com/2015/07/01/basicsofmrparea/ 20/22
22/11/2016 BasicsofMRPAreaSAPBlogs
MRPareaM0001containsubcontractorV001andMRPareaM0002contain
samesubcontractorV001.Myquestioniscanweassignonesubcontractor
(V001)tomultileMRPareas?
Thanks,
SushantKatekar
RohitSingh Postauthor
June14,2016at1:47pm
HiSushant,
Thankyouforsuggestingthiscorrection.Actuallyitshouldnotbe
sameVendorin2differentMRPAreas.Ihavemadecorrectionin
thisdocumentandpublishedwithnewversion.
BestRegards,
Rohit
RaviKumar
June24,2016at5:19am
HiRohit,
Informativedocument
GoodWork
Regards
@KRK@
RangaDavala
June26,2016at7:14am
HiRohit,WelldocumentedonthestepstobefollowedtorunbusinesswithMRP
areaconcept.GoingforwardwithS/4HANAMRP,planninghappensatplantor
MRParealevelandnotatstoragelocationMRPlevel.withthechangein
https://blogs.sap.com/2015/07/01/basicsofmrparea/ 21/22
22/11/2016 BasicsofMRPAreaSAPBlogs
design,allimplementationneedtoactivateMRPareaeitheratplant(default),
storagelocationorsubcontractorlevel.
Thankyou.
VivekP
November12,2016at10:16pm
GreatworkRohit.
Couldyoupleasechecklast2linesinendofthedocument.
MaterialAssemblywasmaintainedasEX(FX)lotsizeinplant(S.Loc)MRP
areaandwithfixedlotsize200inMA001henceplannedorderof200Qty
createdinMA001
Thankyou
AddComment
https://blogs.sap.com/2015/07/01/basicsofmrparea/ 22/22