Beruflich Dokumente
Kultur Dokumente
Chapter 15
Operations As a Competitive
Weapon
Operations Strategy
Project Management Process Strategy
Process Analysis
Process Performance and Quality
Constraint Management
Process Layout Supply Chain Strategy
Lean Systems Location
Inventory Management
Forecasting
Sales and Operations Planning
Resource Planning
Scheduling
Products with many levels Capacity is leveraged to Using system as catalyst for
of components, and more control bottlenecks and continuous improvement
customization entire system flow Small lot sizes, consistent
Lumpy demand, often with Simpler product structures quality, reliable suppliers,
larger batch sizes and more standardized and flexible workforce
Make-to-order, assemble- products Assemble-to-order or make-
to-order, and make-to-stock Assemble-to-order or make- to-stock strategy
strategies to-stock strategy High volumes and well-
Lower and intermediate Relatively higher volumes, balanced line flows
volumes, with flexible flows with flexible flows
transitioning to line flows
2007 Pearson Education
Material
Requirements Planning
Material requirements planning (MRP): A
computerized information system developed specifically to
help manufacturers manage dependent demand inventory and
schedule replenishment orders.
Authorized Other
master production sources
schedule of demand
Engineering
Inventory Inventory MRP Bills of
and process
transactions records explosion materials
designs
Material
requirements
plan
Back Front
legs legs A
Ladder-back
chair
A Ladder-back
chair
J (4)
Seat-frame boards
2007 Pearson Education
Master
Production Schedule
Master production schedule (MPS): A part of the material
requirements plan that details how many end items will be
produced within specified periods of time.
MPS for a Family of chairs
April May
1 2 3 4 5 6 7 8
Aggregate
production plan 670 670
for chair family
2007 Pearson Education
Master Production
Scheduling Process
Operations must first create a prospective MPS to test
whether it meets the schedule with the resources.
MPS for
Weeks 1 & 2
Forecast is less than
booked orders in week 1;
projected on-hand inventory
balance = 55 + 0 38 = 17.
Forecast 30 30 30 30 35 35 35 35
Customer
38 27 24 8 0 0 0 0
orders booked
Projected
on-hand 17 137 107 77 42 7 122 87
inventory
Available-to-
promise (ATP) 17 91 150
inventory
The
Thetotal
totalofofcustomer ordersbooked
customer orders booked until
until thethe next
next MPSMPS receipt
receipt is 38is 27
+ units.
24
2007 Pearson + 8The ATP
= 59
Education = 55 (on-hand)
units. The ATP += 0150
(MPS
(MPSquantity) 38 =
quantity) 17.
59 = 91 units.
MPS for Product A
Application 15.1
1 2 3 4 5 6 7 8
Gross
150 0 0 120 0 150 120 0
requirements
Scheduled
receipts 230 0 0 0 0 0 0 0
Projected
on-hand 37 117 117 117 227 227 77 187 187
inventory
Planned
230 230
receipts
Planned order
230 230
releases
Projected
Scheduled
Gross
Planned on-hand
Receipts
requirements:
order inventory:
release: (open
The total
An that An
orders) estimate
demand
indication are ofan
orders
derived
ofyet
when the
thatamount
have
from
order all of
been
forparent
a
Planned
inventory receipts:
available Orders
each week are not released to the shop
placed
specified but
production
or the not yetofcompleted.
quantity
plans.
supplier. an item is toafter gross requirements have
be issued.
been satisfied.
2007 Pearson Education
2007 Pearson Education
Item: C Lot Size: 230 units
Description: Ladder-back Chair Seat subassembly Lead Time: 2 weeks
Week
1 2 3 4 5 6 7 8
Gross
150 0 0 120 0 150 120 0
requirements
Scheduled
receipts 230 0 0 0 0 0 0 0
Projected
on-hand 37 117 117 117 227 227 77 187 187
inventory
Planned
230 230
receipts
Planned order
230 230
releases
The first aplanned
Without plannedreceipt
receiptlasts until 4,
in week week 7, whenofprojected
a shortage inventory
3 units will would
occur: 117 + 0drop
+0
120
to 77 +=03 120
+ 0units. = 43the
Adding units. Adding
planned the second
receipt bringsplanned receipt
the balance brings
to 117 + 0the
+
230 120
balance to =77227
+ 0units. 120 = 187
+ 230Offsetting for aunits.
2-weekThelead
corresponding
time puts theplanned order
corresponding
release
plannedisorderfor week 5 (or
release week
back to 7 minus
week 2. 2 weeks).
2007 Pearson Education
2007 Pearson Education
Planning Factors
Week
1 2 3 4 5 6 7 8
Gross
requirements 150 120 150 120
Scheduled
receipts 230 (120 + 0 + 150) - 117 = 153
Projected
on-hand 37 117 117 117 150 150 0 0 0
inventory
Planned
153 120
receipts
Planned order
153 120
releases
2007 Pearson Education
H10-A Using POQ
Application 15.3
1 2 3 4 5 6 7 8
Gross
requirements 150 120 150 120
Scheduled
receipts 230 (120 + 0 + 0) - 117 = 3
Projected
on-hand 37 117 117 117 0 0 0 0 0
inventory
Planned
3 150 120
receipts
Planned order
3 150 120
releases
2007 Pearson Education
H10-A Using L4L
Application 15.4
Ladder-back Chair
Seat subassembly
MRP
explosion
Planned
Two order
planned
Projected releases
order
on-hand are sized
releases
inventoryof 230tounits
remains gross requirements.
are
at zero.scheduled. LOT SIZE = L4L
Seat Cushions LEAD TIME = 1 week
Weeks 1 2 3 4 5 6 7 8
Gross Requirements
Gross Reqirements 230 230
Scheduled Receipts
Projected on-hand Inv. = 0 0 0 0 0 0 0 0 0
Planned Receipts 230 230
Planned
2007 order
Pearson Releases
Education 230 230
2007 Pearson Education
Material Requirements Plan LOT SIZE = 230 Units
SEAT SUBASSEMBLY LEAD TIME = 2 Weeks
Weeks 1 2 3 4 5 6 7 8
Gross Requirements
Reqirements 150 120 150 120 0
Scheduled Receipts 230
Projected on-hand: 37 117 117 117 227 227 77 187 187
Planned Receipts 230 230
Planned order Releases 230 230
Market Demand
650 units/week
Level 6
Preoperative care Level 6
(Angiogram) Preoperative care
(Angiogram)
Level 7
Preoperative care
Pharmacy (Testing)
Nurse MD Therapy Bed Lab Kitchen
(10
(6 hr) (1 hr) (1 hr) (24 hr) (3 tests) (1 meal)
medicines)
If there is no existing
A
inventory, how many
LT = 1 units of items G, E, and
D must be purchased to
produce five units of end
B (3) C (1) item A?
LT = 2 LT = 3
LT = 3 LT = 6 LT = 1 LT = 3
5 units of item G
G (1) 30 units of item E
LT = Lead time
LT = 3 20 units of item D
2007 Pearson Education
Solved Problem 3
A
The MPS for product A calls for the assembly
department to begin final assembly according LT = 2
to the following schedule: 100 units in week 2;
200 units in week 4; 120 units in week 6; 180
units in week 7; and 60 units in week 8. B (1) C (2)
Develop a material requirements plan for the
next eight weeks for items B, C, and D.
LT = 1 LT = 2
ITEM
DATA CATEGORY B C D D (1)
Lot-sizing rule POQ (P=3) L4L FOQ = 500 units
Lead time 1 week 2 weeks 3 weeks LT = 3
Scheduled receipts None 200 (week 1) None
Beginning (on-hand) 20 0 425
inventory
1 2 3 4 5 6 7 8 9 10
Gross
100 200 120 180 60
requirements
Scheduled
receipts
Projected
on-hand 20 20 200 200 0 0 240 60 0 0 0
inventory
Planned 280 360
receipts
Planned
order 280 360
releases
2007 Pearson Education
2007 Pearson Education
Solved Problem 3
Item: C Lot size: L4L
Description: Lead time: 2 weeks
Week
1 2 3 4 5 6 7 8 9 10
Gross
200 400 240 360 120
requirements
Scheduled
200
receipts
Projected
on-hand 0 200 0 0 0 0 0 0 0 0 0
inventory
Planned 400 240 360 120
receipts
Planned
order 400 240 360 120
releases
2007 Pearson Education
2007 Pearson Education
Solved Problem 3
Item: D Lot size: FOQ = 500 units
Description: Lead time: 3 weeks
Week
1 2 3 4 5 6 7 8 9 10
Gross
400 240 360 120
requirements
Scheduled
receipts
Projected
on-hand 425 425 25 25 285 425 305 305 305 360 305
inventory
Planned 500 500
receipts
Planned
order 500 500
releases
2007 Pearson Education
2007 Pearson Education