HOW CHIN ENGINEERING

Job Safety Analysis

JOB DESCRIPTION

TYPES OF WORK : Install poly pipe for eye washer at receiving manifold area
LOCATION OF WORK: Manifold area

REQUIRED WORKERS PROTECTIVE EQUIPMENT

x Safety Helmet x Cotton Glove Work Vest


x Safety Shoes / Boots Rubber Glove Safety Vest
x Safety Glasses Leather Gloves Safety Harness / Belt
Face / Welding Shield Leather Apron Face Mask
Goggles Gauntlets Ear Protection
Life Jackets Dust Mask Others (Specify): _________________

OTHER SAFETY EQUIPMENT / REQUIREMENTS

Fire Extinguisher Tag Out / Lock Out


Gas Detector x Work Permit
Safety Signs Competency Certificate
Barricades Respirator
Lifeline First Aid Equipment

JSA DEVELOPED BY :
Name Position
Jayammohan Safety Supervisor
Balachandaram
Kit Yew Sin Safety Manager
Aris Hooi General Manager
N Activity Potential Hazard Control/ Recovery Measures Responsib
HOW CHIN ENGINEERING

le/ Action
o ( Job Steps )
By
1. Work permit Unauthorized Authorized lead-operator / in-charge shall ensure obtaining and Lead-
from Client commencement of maintaining valid work permit. operator
to be works may result in The worksite supervisor responsible for this activity has to check
obtained. exposing workers the PPE of his staff to ensure that all required items are available Supervisor
and or potential to and properly used.
harm or danger Inform all workers regarding permit condition before work starts.
Worksite supervisor shall conduct toolbox talks about nature of
works and associated potential hazards and their essential
precautionary measure.
2. Use of hand Broken or All tools and equipment must be inspected. Any tool or piece of Supervisor
tools Unauthorized Tools equipment deemed unsatisfactory will be tagged and removed
from the worksite. Workers
3. Removing Supervisor
the broken Biological hazards like Always wear steel toe shoes and appropriate gloves
pipe from lizards, snakes or Do not kill the animals intentionally unless it harms Workers
soil iguana and soil bugs Immediately notify supervisor if noticed the animals
Slip/ fall Plan the movement of personnel
Handle the tools and materials (pipe) carefully
4. Clean up Once the job done, Proper lifting techniques, Supervisor
after job clean things up, put Be aware, know surroundings.
/House- away Wear appropriate PPE Workers
keeping

Prepared By : Reviewed By : Date : AUGUST


2016
Contractor / Contractor Representative Lead-operator / In-charge