MECHANIKAL AND ELECTRICAL WORK

PLTMG ARUN
ID Task Name Duration Start Finish 01 March
16/03
1
2
3
Preparation 31,63 days Mon 24/03/14 Mon 28/04/14
4
Mobilization 21 days Mon 24/03/14 Wed 16/04/14
5
site office 14 days Sun 13/04/14 Mon 28/04/14
6
Construction Work 185,5 days Thu 01/05/14 Mon 24/11/14
7
Structure Work 56 days Thu 01/05/14 Wed 02/07/14
8
Steel Structure Engine hall 1 17 days Thu 01/05/14 Tue 20/05/14
9
Rofe & Wall Cladding 10 days Mon 26/05/14 Thu 05/06/14
10
Steel Structure Engine hall 2 17 days Mon 26/05/14 Fri 13/06/14
11
Rofe & Wall Cladding Engine hall 2 10 days Wed 18/06/14 Sun 29/06/14
12
Structure Electrical Eq Building 5 days Wed 18/06/14 Mon 23/06/14
13
Rope & Wall Cladding 2 days Wed 25/06/14 Thu 26/06/14
14
Steel Structure Mislenues 7 days Wed 25/06/14 Wed 02/07/14
Task External Milestone Manual Summary Rollup
Split Inactive Task Manual Summary

GKM Project Engineer Milestone Inactive Milestone Start-only


Date: Fri 14/03/14 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 1
MECHANIKAL AND ELECTRICAL WORK
PLTMG ARUN
ID Task Name Duration Start Finish 01 March
16/03
15
16
Tank Work 52 days Wed 14/05/14 Fri 11/07/14
17
Tank Erection 42 days Wed 14/05/14 Mon 30/06/14
18
Top Coat Painting 10 days Tue 01/07/14 Fri 11/07/14
19
Mechanical Work 128,38 days Sun 01/06/14 Wed 22/10/14
20
Engine Installation 1St ship 14 days Sun 01/06/14 Mon 16/06/14
21
Leveling / pre alignment 10 days Thu 19/06/14 Mon 30/06/14
22
Final Alignment 8 days Thu 03/07/14 Fri 11/07/14
23
Radiator Installation 23 days Mon 09/06/14 Fri 04/07/14
24
Engine Installation 2rd ship 14 days Fri 01/08/14 Sun 17/08/14
25
Leveling / pre alignment 10 days Thu 21/08/14 Mon 01/09/14
26
Final Alignment 10 days Thu 04/09/14 Mon 15/09/14
27
Radiator Installation 20 days Thu 10/07/14 Fri 01/08/14
28
HVAC Dan ventilations 20 days Tue 30/09/14 Wed 22/10/14
Task External Milestone Manual Summary Rollup
Split Inactive Task Manual Summary

GKM Project Engineer Milestone Inactive Milestone Start-only


Date: Fri 14/03/14 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 2
MECHANIKAL AND ELECTRICAL WORK
PLTMG ARUN
ID Task Name Duration Start Finish 01 March
16/03
29
Bop Equipment 20 days Mon 15/09/14 Tue 07/10/14
30
31
Electrical work 126 days Mon 07/07/14 Mon 24/11/14
32
Cable tray fabrication & erection 22 days Wed 16/07/14 Sun 10/08/14
33
DC system . LV switch gear, Transformer8 days Mon 07/07/14 Tue 15/07/14
34
MV Panel 6 days Sun 20/07/14 Fri 25/07/14
35
Sub station Control Panel 10 days Wed 30/07/14 Sun 10/08/14
36
Trafo Accessories, Purifying 10 days Wed 20/08/14 Sun 31/08/14
37
Pulling cable 46 days Sun 10/08/14 Tue 30/09/14
38
Termination 23 days Wed 01/10/14 Sun 26/10/14
39
Electrical BOP 18 days Sun 12/10/14 Fri 31/10/14
40
Building ligthing /comunication system 22 days Fri 31/10/14 Mon 24/11/14
41
piping work 104 days Fri 25/07/14 Tue 18/11/14
42
Spoll fabrication 45 days Fri 25/07/14 Sun 14/09/14
Task External Milestone Manual Summary Rollup
Split Inactive Task Manual Summary

GKM Project Engineer Milestone Inactive Milestone Start-only


Date: Fri 14/03/14 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 3
MECHANIKAL AND ELECTRICAL WORK
PLTMG ARUN
ID Task Name Duration Start Finish 01 March
16/03
43
Pipe Erection 84 days Mon 11/08/14 Wed 12/11/14
44
NDT 7 days Tue 11/11/14 Tue 18/11/14
45
Instrument Work 21,63 days Thu 09/10/14 Sun 02/11/14
46
Field instrument Installation 12 days Thu 09/10/14 Wed 22/10/14
47
Scada hadrware installation 10 days Wed 15/10/14 Sun 26/10/14
48
Termination/ conection 7 days Sun 26/10/14 Sun 02/11/14
49
Precom & Commissioning 43,38 days Sun 02/11/14 Fri 19/12/14
50
Leak test/ Preaser test 13 days Sun 02/11/14 Sun 16/11/14
51
Cleaning, blowing flashing 16 days Mon 01/12/14 Thu 18/12/14
52
oil filling up 7 days Thu 20/11/14 Thu 27/11/14
53
Merger 9 days Tue 02/12/14 Thu 11/12/14
54
Loop test 11 days Mon 08/12/14 Fri 19/12/14

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

GKM Project Engineer Milestone Inactive Milestone Start-only


Date: Fri 14/03/14 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 4
MECHANIKAL AND ELECTRICAL WORK
PLTMG ARUN
21 March 11 April 01 May 21 May 11 June 01 July 21 July
23/03 30/03 06/04 13/04 20/04 27/04 04/05 11/05 18/05 25/05 01/06 08/06 15/06 22/06 29/06 06/07 13/07 20/07 27/

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

GKM Project Engineer Milestone Inactive Milestone Start-only


Date: Fri 14/03/14 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 5
MECHANIKAL AND ELECTRICAL WORK
PLTMG ARUN
21 March 11 April 01 May 21 May 11 June 01 July 21 July
23/03 30/03 06/04 13/04 20/04 27/04 04/05 11/05 18/05 25/05 01/06 08/06 15/06 22/06 29/06 06/07 13/07 20/07 27/

By Others

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

GKM Project Engineer Milestone Inactive Milestone Start-only


Date: Fri 14/03/14 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 6
MECHANIKAL AND ELECTRICAL WORK
PLTMG ARUN
21 March 11 April 01 May 21 May 11 June 01 July 21 July
23/03 30/03 06/04 13/04 20/04 27/04 04/05 11/05 18/05 25/05 01/06 08/06 15/06 22/06 29/06 06/07 13/07 20/07 27/

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

GKM Project Engineer Milestone Inactive Milestone Start-only


Date: Fri 14/03/14 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 7
MECHANIKAL AND ELECTRICAL WORK
PLTMG ARUN
21 March 11 April 01 May 21 May 11 June 01 July 21 July
23/03 30/03 06/04 13/04 20/04 27/04 04/05 11/05 18/05 25/05 01/06 08/06 15/06 22/06 29/06 06/07 13/07 20/07 27/

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

GKM Project Engineer Milestone Inactive Milestone Start-only


Date: Fri 14/03/14 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 8
MECHANIKAL AND ELECTRICAL WORK
PLTMG ARUN
July 11 August 01 September 21 September 11 October 01 November 21 November
27/07 03/08 10/08 17/08 24/08 31/08 07/09 14/09 21/09 28/09 05/10 12/10 19/10 26/10 02/11 09/11 16/11 23/11 30/

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

GKM Project Engineer Milestone Inactive Milestone Start-only


Date: Fri 14/03/14 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 9
MECHANIKAL AND ELECTRICAL WORK
PLTMG ARUN
July 11 August 01 September 21 September 11 October 01 November 21 November
27/07 03/08 10/08 17/08 24/08 31/08 07/09 14/09 21/09 28/09 05/10 12/10 19/10 26/10 02/11 09/11 16/11 23/11 30/

By Others

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

GKM Project Engineer Milestone Inactive Milestone Start-only


Date: Fri 14/03/14 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 10
MECHANIKAL AND ELECTRICAL WORK
PLTMG ARUN
July 11 August 01 September 21 September 11 October 01 November 21 November
27/07 03/08 10/08 17/08 24/08 31/08 07/09 14/09 21/09 28/09 05/10 12/10 19/10 26/10 02/11 09/11 16/11 23/11 30/

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

GKM Project Engineer Milestone Inactive Milestone Start-only


Date: Fri 14/03/14 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 11
MECHANIKAL AND ELECTRICAL WORK
PLTMG ARUN
July 11 August 01 September 21 September 11 October 01 November 21 November
27/07 03/08 10/08 17/08 24/08 31/08 07/09 14/09 21/09 28/09 05/10 12/10 19/10 26/10 02/11 09/11 16/11 23/11 30/

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

GKM Project Engineer Milestone Inactive Milestone Start-only


Date: Fri 14/03/14 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 12
MECHANIKAL AND ELECTRICAL WORK
PLTMG ARUN
ember 11 December 01 January 21 January 11 February 01 March 21 March
30/11 07/12 14/12 21/12 28/12 04/01 11/01 18/01 25/01 01/02 08/02 15/02 22/02 01/03 08/03 15/03 22/03 29/03 05/

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

GKM Project Engineer Milestone Inactive Milestone Start-only


Date: Fri 14/03/14 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 13
MECHANIKAL AND ELECTRICAL WORK
PLTMG ARUN
ember 11 December 01 January 21 January 11 February 01 March 21 March
30/11 07/12 14/12 21/12 28/12 04/01 11/01 18/01 25/01 01/02 08/02 15/02 22/02 01/03 08/03 15/03 22/03 29/03 05/

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

GKM Project Engineer Milestone Inactive Milestone Start-only


Date: Fri 14/03/14 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 14
MECHANIKAL AND ELECTRICAL WORK
PLTMG ARUN
ember 11 December 01 January 21 January 11 February 01 March 21 March
30/11 07/12 14/12 21/12 28/12 04/01 11/01 18/01 25/01 01/02 08/02 15/02 22/02 01/03 08/03 15/03 22/03 29/03 05/

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

GKM Project Engineer Milestone Inactive Milestone Start-only


Date: Fri 14/03/14 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 15
MECHANIKAL AND ELECTRICAL WORK
PLTMG ARUN
ember 11 December 01 January 21 January 11 February 01 March 21 March
30/11 07/12 14/12 21/12 28/12 04/01 11/01 18/01 25/01 01/02 08/02 15/02 22/02 01/03 08/03 15/03 22/03 29/03 05/

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

GKM Project Engineer Milestone Inactive Milestone Start-only


Date: Fri 14/03/14 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress