ROXAS SUBSTATION Mobilization Temfacil Stake Out

Project Start
Start: Tue 12/13/16ID: 0 Start: Tue 12/13/16 ID: 3 Start: Wed 12/14/16ID: 4 Start: Fri 12/16/16 ID: 5
Finish: Thu 9/14/17Dur: 276 days Milestone Date: Tue 12/13/16 Finish: Tue 12/13/16Dur: 1 day Finish: Thu 12/15/16Dur: 2 days Finish: Fri 12/16/16 Dur: 1 day
Comp: 0% ID: 1 Res: Res: Res:

Layoutting Board Up
Start: Fri 12/16/16 ID: 6 Start: Sat 12/17/16 ID: 7
Finish: Fri 12/16/16 Dur: 1 day Finish: Fri 12/30/16 Dur: 14 days
Res: Res:

Completion of Construction of
Temfacil and Board Up
Milestone Date: Fri 12/30/16
ID: 8

Supply and Installation of Substation Steel Structure ( Switchyard


SupplyArea
and) Installation of Switchyard Overhead Conductors and Hardwares
Start: Wed 12/14/16ID: 20 Start: Sun 3/19/17 ID: 49
Finish: Sat 3/18/17 Dur: 95 days Finish: Sat 4/1/17 Dur: 14 days
Res: Res:

Construction of Power House Construction of Guard House Lighting and Power System
Start: Wed 12/14/16ID: 32 Start: Sat 4/8/17 ID: 33 Start: Tue 3/14/17 ID: 52
Finish: Fri 5/12/17 Dur: 150 days Finish: Fri 5/12/17 Dur: 35 days Finish: Fri 5/12/17 Dur: 60 days
Res: Res: Res:

Airconditioning System
Start: Sat 4/22/17 ID: 34
Finish: Fri 5/12/17 Dur: 21 days
Res:

Plumbing System
Start: Sat 4/29/17 ID: 35
Finish: Fri 5/12/17 Dur: 14 days
Res:

Water Line System


Start: Sat 4/29/17 ID: 36
Finish: Fri 5/12/17 Dur: 14 days
Res:

Power House & Guard House


Completed
Milestone Date: Fri 5/12/17
ID: 37

Detailed Engineering
Start: Wed 2/22/17 ID: 2
Finish: Fri 4/7/17 Dur: 45 days
Res:

Construction of 115kV Substation Equipment Foundation ( Switchyard Area ) 50MVA Power Transformer Completion of Equipment
Start: Sat 12/17/16ID: 9 Start: Sat 12/17/16 ID: 10 Foundation
Finish: Sun 2/26/17Dur: 72 days Finish: Fri 12/30/16 Dur: 14 days Milestone Date: Sun 2/26/17
Comp: 0% Res: ID: 19

69kV A-Frame, Foundation 69kV H-Frame, Foundation


Start: Mon 12/26/16ID: 11 Start: Mon 12/26/16ID: 12
Finish: Sun 1/22/17 Dur: 28 days Finish: Fri 1/27/17 Dur: 33 days
Res: Res:

69kV Power Circuit Breaker, Deadtank 69kV Disconnect Switch 69kV Surge Arrester 69kV Potential Transformer 69kV Current Transformer 69kV Post Insulator
Start: Mon 1/16/17 ID: 13 Start: Thu 1/19/17 ID: 14 Start: Mon 1/23/17 ID: 15 Start: Mon 1/30/17 ID: 16 Start: Fri 2/3/17 ID: 17 Start: Mon 2/6/17 ID: 18
Finish: Fri 1/27/17 Dur: 12 days Finish: Thu 2/2/17 Dur: 15 days Finish: Tue 2/7/17 Dur: 16 days Finish: Sat 2/11/17 Dur: 13 days Finish: Sun 2/12/17 Dur: 10 days Finish: Sun 2/26/17 Dur: 21 days
Res: Res: Res: Res: Res: Res:

Site Development Grading Ground leveling and gravel surfacing


Start: Wed 1/4/17 ID: 21 Start: Mon 2/27/17 ID: 22 Start: Mon 3/13/17 ID: 23
Finish: Sat 6/24/17 Dur: 172 days Finish: Sun 3/12/17 Dur: 14 days Finish: Sun 3/26/17 Dur: 14 days
Comp: 0% Res: Res:

Completion of Site Development

Milestone Date: Sat 6/24/17


ID: 31

Construction of Perimeter CHB Seclusion Fence Drainage system


Start: Wed 1/4/17 ID: 24 Start: Fri 2/3/17 ID: 25
Finish: Wed 4/5/17 Dur: 92 days Finish: Thu 3/23/17 Dur: 49 days
Res: Res:

Structural excavation/fill, concreting of cable trenches including


Concrete
steel plate
Ductbank
cover and cable trays Concrete Pedestal
Start: Wed 2/1/17 ID: 26 Start: Mon 2/6/17 ID: 27 Start: Mon 2/27/17 ID: 28
Finish: Sat 6/24/17 Dur: 144 days Finish: Sun 2/26/17 Dur: 21 days Finish: Sun 3/12/17 Dur: 14 days
Res: Res: Res:

Concrete Pavement Access Road Network


Start: Mon 2/27/17 ID: 29 Start: Mon 3/13/17 ID: 30
Finish: Sun 3/12/17 Dur: 14 days Finish: Sun 3/19/17 Dur: 7 days
Res: Res:

Installation of Switchyard Electrical Equipment 69kV Power Circuit Breaker, Deadtank 69kv MVSG( 8 Vertical sections) 69kV Control Panel
Start: Fri 2/3/17 ID: 38 Start: Wed 3/15/17 ID: 39 Start: Mon 7/31/17 ID: 45 Start: Mon 8/14/17 ID: 46
Finish: Mon 8/14/17Dur: 193 days Finish: Wed 3/15/17Dur: 1 day Finish: Sun 8/13/17 Dur: 14 days Finish: Mon 8/14/17Dur: 1 day
Comp: 0% Res: Res: Res:

Completion of Equipment
Installation
Milestone Date: Mon 8/14/17
ID: 47

69kV Disconnect Switch


Start: Fri 2/3/17 ID: 40
Finish: Fri 2/3/17 Dur: 1 day
Res:

69kV Surge Arrester


Start: Wed 2/8/17 ID: 41
Finish: Wed 2/8/17 Dur: 1 day
Res:

69kV Potential Transformer


Start: Sun 2/12/17 ID: 42
Finish: Sun 2/12/17 Dur: 1 day
Res:

69kV Current Transformer


Start: Mon 2/13/17 ID: 43
Finish: Mon 2/13/17Dur: 1 day
Res:

69KV Post Insulator


Start: Mon 2/27/17 ID: 44
Finish: Mon 2/27/17Dur: 1 day
Res:

Supply and Installation of Equipment Grounding System Completion of Substation


Project Finish
Start: Wed 2/22/17 ID: 48 Electrical Works
Finish: Sat 4/22/17 Dur: 60 days Milestone Date: Thu 9/14/17 Milestone Date: Thu 9/14/17
Res: ID: 54 ID: 55

Assembly of One (1) 50MVA Power Transformer and Oil Filling Power and Control Cables and Accesssories Testing and Commissioning of Substation
Start: Wed 2/15/17 ID: 50 Start: Tue 8/15/17 ID: 51 Start: Tue 9/5/17 ID: 53
Finish: Tue 2/28/17 Dur: 14 days Finish: Mon 9/4/17 Dur: 21 days Finish: Thu 9/14/17 Dur: 10 days
Res: Res: Res:

Critical Critical Milestone Critical Summary Critical Inserted Critical Marked Critical External Project Summary Highlighted Noncritical
Project: ROXAS SUBSTATION
Noncritical Milestone Summary Inserted Marked External Highlighted Critical
Date: Wed 2/22/17
Page 1