Beruflich Dokumente
Kultur Dokumente
: 1000
PROCESS ENGINEERING PRACTICE Page: 1 of 1
Revision: 8
Date: May. 20, 2009
______________________________________________________________________
INDEX
All items posted to this Index have been reviewed for current applicability and were
found to be correct and complete.
APPROVED: _____________________________________
Director - Process Engineering
/var/www/apps/conversion/tmp/scratch_3/348497161.doc
FOSTER WHEELER USA CORPORATION PEP No.: 1001
PROCESS ENGINEERING PRACTICE Page: 1 of 1
Revision: 4
Date: Mar. 6, 2006
Date: Mar. 6, 2006
______________________________________________________________________
PEP-1001
Comments and corrections, along with changes as time passes, will require revisions.
Revision numbers with dates of issue will be indicated underneath the page number.
The PEP Table of Contents page will normally show the date of the latest issue.
Specific exceptions may be taken from the PEP's when the rules listed are counter to
standard design practice for specific applications. The engineer should be prepared to
justify his exception.
These PEP's are general for all projects. Job specific PEP's will be issued with a job
specific reference number where client requirements or other requirements dictate.
/var/www/apps/conversion/tmp/scratch_3/348497161.doc
FOSTER WHEELER USA CORPORATION PEP No.: 1002
PROCESS ENGINEERING PRACTICES Page: 1 of 6
Revision: 5
Date: Feb 24, 2009
______________________________________________________________________
PEP-1002
A. FLOW
1. When required, job specific PEP's will be issued to all process engineers
assigned to a contract, as well as the FW Project Engineering Managers.
All other Process Design correspondence for the project within FW will be
over the signature of the Process Manager or the Lead Engineer as
appropriate.
4. All correspondence to the Client shall follow the job specific coordination
procedure. Unless otherwise indicated, correspondence shall be over the
signature of the Project Manager.
/var/www/apps/conversion/tmp/scratch_3/348497161.doc
FOSTER WHEELER USA CORPORATION PEP No.: 1002
PROCESS ENGINEERING PRACTICES Page: 2 of 6
Revision: 5
Date: Feb 24, 2009
______________________________________________________________________
PEP-1002 (Cont'd)
B. MAINTENANCE
1. Desk Files
Originals Book:
This book shall also note the location (Directory) for the electronic
files stored on the network. See below regarding use of the original
as the Process Master.
B. MAINTENANCE
1. Desk Files
Design Pressure/Temperature
Plot Plan.
/var/www/apps/conversion/tmp/scratch_3/348497161.doc
FOSTER WHEELER USA CORPORATION PEP No.: 1002
PROCESS ENGINEERING PRACTICES Page: 4 of 6
Revision: 5
Date: Feb 24, 2009
______________________________________________________________________
PEP-1002 (Cont'd)
B. MAINTENANCE
1. Desk Files
The Lead Process Engineer shall keep a copy of all issues of the
flow diagrams listed above in his office. These may be discarded
when the contract is completed.
a. Specifications
/var/www/apps/conversion/tmp/scratch_3/348497161.doc
PEP-1002 (Cont'd)
B. MAINTENANCE
a. Specifications (Contd)
b. Correspondence
FOSTERWHEELER
FOSTER WHEELERUSA
USACORPORATION
CORPORATION
HOUSTON, TEXAS
CLINTON, NEW JERSEY
DISTRIBUTION COPIES
MEMO ATT'S MATERIAL TRANSMITTED
Process File XX-XXXX 1 1
Process Manager 1 1 Process Flow Diagrams
Chief Process Eng. 1 1 Engineering Flow Diagrams
1 1 Equipment List
Lead Process Eng. 1 1+orig Vessels
Project Manager 1 1 Exchangers
Project Eng. Mngr. 1 1 Instruments
1 1 Compressors
1 1 Fired Heaters
Pumps
NOTES:
By
The following is a sample Process File Index. A job specific index is to be prepared by the
Chief Process Engineer or designee and issued for each project. Refer to Engineering
Practice EP 6-1.
PROJECT XYZ
1.1 Proposal
1.2 Contract
1.3 Contract Changes
2.1 FW to Client
2.2 Client to FW
2.3 Standard Engineering Transmittal Letters to Client
2.4 Standard Procurement Transmittal Letters to Client
2.5 To Licensors and Vendors
2.6 From Licensors and Vendors
4.1 Estimates
Use Section 8 to also file Engineering data sheets, requisitions, vendor drawings,
etc. Use same file suffixes as Section 7 (for example Engineering Data on pumps
would be filed under 8.31)
Use Section 11 to file process calculations. Use same file suffixes as Section 7 (for
example drum calculations would be filed under 11.13)
12.10 Vessels
12.20 Exchangers
12.30 Machinery
12.50 Piping/P&IDs
12.60 Instruments
13.0 DRAWINGS
PEP-1004
EQUIPMENT LISTS
Vessels
Towers (T- )
Reactors (R- )
Drums (D- )
Tanks (TK- )
Mechanical Equipment
Pumps (P- )
Compressors (C- )
Miscellaneous (eg. DS, F, M, S, X)
in same order as code of accounts
D-101
D-102
P-101A (Main)
P-101B (Spare)
FOSTER WHEELER USA CORPORATION PEP No.: 1004
PROCESS ENGINEERING PRACTICES Page: 2 of 2
Revision: 4
Date: Mar. 6, 2006
___________________________________________________________________________________________________________
____
Form No. 110-330 17 Feb 1999 NAME: STANDARD FORM (If Modified, rename form)
FOSTER WHEELER USA CORPORATION PEP No.: 1005
PROCESS ENGINEERING PRACTICE Page: 1 of 5
Revision: 4
Date: Mar. 6, 2006
______________________________________________________________________
PEP-1005
3. PFD's will not have material balance tables provided on drawings unless required
for the project. Material balances will be provided separately on diamond
sheets. A typical sample is attached.
5. All major items of equipment must be shown on the PFD. Adjacent to each item
shown, the underlined item number must be provided. Underneath the item
number, the item name shall appear exactly as indicated on the equipment list.
6. Do not indicate spares for pumps, (e.g. show P-801, not P-801 A/B).
/var/www/apps/conversion/tmp/scratch_3/348497161.doc
FOSTER WHEELER USA CORPORATION PEP No.: 1005
PROCESS ENGINEERING PRACTICE Page: 2 of 5
Revision: 4
Date: Mar. 6, 2006
______________________________________________________________________
PEP-1005 (Cont'd)
Flow orifices are not to be shown on the PFD. Examples of instrumentation are
shown below.
FC
M TC
LC
FI
9. Each PFD must contain an explanatory legend with the information shown below.
Additional symbols and notes may be shown as necessary to clarify the
flowsheet:
/var/www/apps/conversion/tmp/scratch_3/348497161.doc
FOSTER WHEELER USA CORPORATION PEP No.: 1005
PROCESS ENGINEERING PRACTICE Page: 3 of 5
Revision: 4
Date: Mar. 6, 2006
______________________________________________________________________
PEP-1005 (Cont'd)
10. Provide battery limit temperatures and pressures for all process streams (in and
out) and indicate destination of material, intermediate tankage. Name all
streams.
/var/www/apps/conversion/tmp/scratch_3/348497161.doc
FOSTER WHEELER USA CORPORATION PEP No.: 1005
PROCESS ENGINEERING PRACTICE Page: 4 of 5
Revision: 4
Date: Mar. 6, 2006
______________________________________________________________________
PEP-1005 (Cont'd)
12. The initial issue of the PFD is to be Issue A with subsequent issues in
alphabetical order. Each issue shall be designated as indicated below:
REV. A April, 1995 Initial IssueInit. Contract No. XX-XXX Dwg. No. xxxx-x-xx-xx A
/var/www/apps/conversion/tmp/scratch_3/348497161.doc
FOSTER WHEELER USA CORPORATION PEP No.: 1005
PROCESS ENGINEERING PRACTICE Page: 5 of 5
Revision: 4
Date: Mar. 6, 2006
_____________________________________________________________________
STREAM NO. 1 2 3 4 5 6
OP ERA TING CA SE
FLUID STA TE
P RESSURE, P SIG
TB P CUT RA NGE, F
TOTA L B P SD
A P I
LIQUID, LB /HR
VA P OR, LB /HR
SOLID, LB /HR
TOTA L, LB /HR
H 2O
TOTA L
FOSTER WHEELER USA CORPORATION PEP No.: 1006
PROCESS ENGINEERING PRACTICE Page: 1 of 3
Revision: 4
Date: Mar. 6, 2006
______________________________________________________________________
PEP-1006
1. Engineering flow diagrams (EFD's) shall be drawn on drawing size No. 2, according
to normal FW engineering practice. The title box shall be in accordance with the
enclosed sample (page 3).
On each EFD, a column along the right side, directly above the title box, will be used
for Notes and Holds.
A chart along the bottom of each EFD will be used to provide the required equipment
data.
2. The following non-standard pipe sizes shall not be used: 3/8", 1-1/4", 2-1/2", 3-1/2",
5" or 7", etc.
In the event that these sizes are required for equipment connections, they shall be
changed as soon as feasible to the connecting pipe size.
Minimum pipe sizes shall be 1" for both process and utility piping, except for
connections to equipment which vendors supply or for sample lines to and from
analyzers.
3. Unless the process, client or vessel code dictates otherwise, relief valve nozzle
connections shall not be located on vessels but on overhead piping without
appropriate justification.
4. Silencers for vents, when provided, shall be numbered and shall be included on the
equipment list.
5. In general, air coolers are to be provided with louvers, where required for
supplemental (start-up and shutdown) freeze/pour point protection, with control of the
air temperature by the forced-draft or induced draft fans. The process outlet
temperature from each bay is to be monitored. In general, steam coils will be
provided for air coolers, when required for start-up and shutdown purposes.
6. Turbines shall be provided with full capacity relief valves mounted in the exhaust
steam piping and relieving to atmosphere.
/var/www/apps/conversion/tmp/scratch_3/348497161.doc
FOSTER WHEELER USA CORPORATION PEP No.: 1006
PROCESS ENGINEERING PRACTICE Page: 2 of 3
Revision: 4
Date: Mar. 6, 2006
______________________________________________________________________
PEP-1006 (Cont'd)
7. Insulation
8. Relative elevations of vessels, loop seals, exchangers and thermosyphon circuits are
to be indicated on the EFD's. For vessels, show elevation above grade of bottom
tangent line on vertical vessels, or bottom on horizontal drums.
9. The following must be shown in detail on the EFD's: number of passes for each coil
for fired heaters, number of shells or bays for exchanger services. These are to be
estimated by the process or heat transfer engineers.
10. The initial issue of the EFD's is to be Issue A and designated as shown on the
attached Sample Title Box. With the second issue of EFDs (Rev.B) the Process
Engineer relinquishes control to the Project Department. Therefore, this issue will not
be made until specifically approved by the Chief Engineer.
/var/www/apps/conversion/tmp/scratch_3/348497161.doc
PEP-1006 (Cont'd)
THIS COLUMN RESERVED FOR NOTES AND HOLDS FROM THE TOP OF TITLE BOX TO
TOP OF DRAWING
ITEMS NOS.
THIS ENGINEERING FLOW DIAGRAM
DRAWING SOUR WATER STRIPPING UNIT
UNIT 600
SOUR WATER STRIPPER
CUSTOMER ABC
Customer ABC Location
REV. A April, 1995 PROCESS ISSUEINITIALS Contract No. XX-XXXX DWG. NO. XXXX-2-50-01 A
FOSTER WHEELER USA CORPORATION PEP No.: 1007
PROCESS ENGINEERING PRACTICE Page: 1 of 6
Revision: 5
Date: Aug. 9, 2007
______________________________________________________________________
PEP-1007
Pump Piping
1. A pressure gauge shall be installed between centrifugal pumps and check valves,
and a 3/4" valved bleed connection shall be provided between the check valve
and block valve.
2. For all single stage pumps operating above 500F (260 C) and all multistage
pumps operating above 400F (204 C), a 1" warm-up line with globe valve shall
be installed. The warm-up line is to be routed around the check valve only.
3. The casing vents of LPG pumps will be hard-piped to the flare system using
double blocks and bleeds.
Compressor Piping
The following piping items shall be provided at each compressor or compressor cylinder
for purging, maintenance, etc.:
- fittings inside block valves for connections to nitrogen system or cylinders for
purging
Nitrogen Piping
PEP-1007 (Cont'd)
Exchanger Piping
Cooling
gWater
Return
PSV -
XXX
Set @ xx psig 3/4"
Size Vent
Cooling
Water ~
Supply ~
3/4"
To Grade at
Drain
Safe Location
Back flushing, chemical cleaning and 1" winterizing line requirements are at the client's
option and are not included in this detail.
Furnace Piping
Inlet and outlet piping for heaters which are to be steam air decoked should have
removable spool pieces on the inlet and the outlet piping. Locate the heater inlet
PI downstream of the inlet line spool; locate an outlet coil TI upstream of the
outlet line spool.
FOSTER WHEELER USA CORPORATION PEP No.: 1007
PROCESS ENGINEERING PRACTICE Page: 3 of 6
Revision: 5
Date: Aug. 9, 2007
______________________________________________________________________
PEP-1007 (Cont'd)
2. If manually operated globe valves are used to regulate the flow in multiple pass
furnaces, such valves shall be located at ground level and each pass shall be
provided with an outlet temperature indicator visible from the valves.
3. The superheated steam piping design temperature from each heater superheat
5 coil shall be established after heater vendor data is available (by the detailed
engineering contractor). A note should be placed on the EFD to indicate this.
4. In general, piping for furnaces equipped with superheat stripping steam coils
should have:
5. A local PI should be on the inlet line to each process coil. Locate the PI
downstream of the heater inlet control valve (if any).
FOSTER WHEELER USA CORPORATION PEP No.: 1007
PROCESS ENGINEERING PRACTICE Page: 4 of 6
Revision: 5
Date: Aug. 9, 2007
______________________________________________________________________
PEP-1007 (Cont'd)
Vessel Piping
(refers to towers and drums only)
1. The gas vent line from drums such as overhead receivers and the product
separators shall have a vent line to the flare.
2. All vessels must be provided with a high point vent, low point drain and steamout
connection. Vents are to be on the top of the vessel. Drains are to be on the
bottom piping. Separate steamout connections are not required for vessels
which already have stripping steam connections or clean water vessels and
steam drums or kettles.
Auxiliary nozzles for all vessels (including towers) are to be sized in accordance
with the Process Standard on drums.
Board mounted PDI's shall be provided on the main sections of the towers.
Control Valves
For line sizes 2" or less, blocks and by-passes shall be provided around control valves.
In addition, blocks and by-passes shall be installed around any critical service control
valve whose malfunction would cause unit shutdown mode or prevent continuous
operation of unit. Blocks and bypasses will also be provided for erosive services or
services with a pressure drop above 150 psi. For line sizes greater than 2", control
valves in non-critical services shall be provided with a manually operated hand wheel
jack with valve opening indicator, without by-pass. Upstream control valve bleeds are
to be shown on the EFD's. If the control valve size sets a PSV load, the bypass valve
CV should be less than or equal to the control valve C V.
Relief Valves
1. Relief valves requiring periodic testing shall be provided with Car Seal Open
(CSO) isolation valves and a 3/4" bleed valve. A bypass line with a normally
closed (NC) valve and a 3/4" PI tap, for use when the valve is being tested, shall
be provided around the relief valve(s) and isolation valves.
FOSTER WHEELER USA CORPORATION PEP No.: 1007
PROCESS ENGINEERING PRACTICE Page: 5 of 6
Revision: 5
Date: Aug. 9, 2007
______________________________________________________________________
PEP-1007 (Cont'd)
2. Relief valve discharge lines to atmosphere shall be provided with " weep holes.
The weep hole drain lines shall be piped to a "safe location".
Sample Connections
SC
for sample connection without cooling.
In general, draw B.L. connections as shown below. Battery limits may only be shown at
top or bottom of the EFD.
PI
B.L.
B.L.
PEP-1007 (Cont'd)
All lines extended from one EFD to another must be labeled and designated by source
(if entering) or destination (if leaving) as in the example below.
FOSTER WHEELER USA CORPORATION PEP No.: 1008
PROCESS ENGINEERING PRACTICES Page: 1of 1
Revision: 4
Date: Mar. 6, 2006
______________________________________________________________________
PEP-100
8 EFD #02 EFD #03
55 55
54 54
SOUR WAT ER SOUR WAT ER
53 53
TO D-1501 FROM P-1501
52 52
51 51
50 50
Utility connections on EFDs will be shown by balloons. A set of balloons for this
project will be included on one of the General Notes and Symbols EFD for each unit.
Under no circumstances should additional balloons be included by an engineer without
approval by the project manager.
The purpose of utility balloons is to enable geographic layout of utility flow diagrams
(UFDs) for each unit. They are not to be used for injection facilities such as inhibitor,
ammonia or similar connections.
FOSTER WHEELER USA CORPORATION PEP No.: 1009
PROCESS ENGINEERING PRACTICES Page: 1 of 3
Revision: 5
Date: Aug. 9, 2007
______________________________________________________________________
PEP-1009
INSTRUMENTATION
1. In general, all vessels containing vapor and liquid shall be equipped with high
and low level alarms.
6. In general, all level instruments shall be mounted separately. Standpipes will not
be used. The process engineer will define the normal operating range by setting
approximate High and Low Liquid Levels (HLL & LLL) in vessels. These values
set the end points for both visible level indications (gauge glasses) and
transmitter range. Extreme high or low level shut-down points or alarms may be
set beyond these range limits, using level switches. For such extreme levels,
either a separate gauge glass or an extension of coverage by the full range glass
5 shall be provided. The minimum setting for hard piped low- low level switch on
vertical vessels is 1'-5" above vessel bottom tangent line or consult with the
Automation and Controls Group. (See also PEP 1010).
8. In general, relief valves for liquid thermal expansion shall be provided on the
water side of water-cooled exchangers. Thermal relief valves shall also be
provided on the cold side of all exchangers that can be blocked in. Blocked in
circuits in LPG, where atmospheric conditions are a problem, also require a PSV.
Liquid C2, C3 and C4 circuits, which can expand and/or vaporize when heated by
ambient conditions, also require a PSV.
FOSTER WHEELER USA CORPORATION PEP No.: 1009
PROCESS ENGINEERING PRACTICES Page: 2 of 3
Revision: 5
Date: Aug. 9, 2007
______________________________________________________________________
PEP-1009 (Cont'd)
INSTRUMENTATION
9. Provisions for oxygen analyzers are required on all heater stacks. Continuous
analyzers are to be provided only where the information will require operators to
make process changes, and not for monitoring only.
INSTRUMENTATION
b. Indicate destination of discharge and EFD number for each relief valve on
the FW relief valve standard form.
For all PSV's discharging to the flare, loads must be supplied on the flare sheets
for block, power failure, fire, instrument air failure and cooling water failure. If no
load exists for any particular contingency, the word "none" should be listed in the
load row.
14. The allowable accumulation to be used for a PSV load due to exposure to fire
shall be "per code," 16% for a single relief valve, or 21% for multiple relief valves.
15. If the liquid filled cold side of a shell and tube exchanger requires protection
against thermal expansion and against exposure to fire, and if the thermal
expansion load requires a relatively small PSV, whereas the fire load requires a
relatively large PSV, then two PSV's shall be provided:
16. For vacuum protection, the accumulated vacuum relief pressure is often in
excess of 10 or 21% (as typical for Pressure Relief Valves) and sometimes as
high as 100%. It is important to note that the accumulated vacuum pressure may
not exceed the vacuum rating of the associated vessels.
FOSTER WHEELER USA CORPORATION PEP No.: 1010
PROCESS ENGINEERING PRACTICE Page: 1 of 3
Revision: 5
Date: Aug. 9, 2007
______________________________________________________________________
PEP-1010
VESSELS
1. Pressure vessels with relief valves shall be designed for a minimum internal
pressure of at least 10% or 25 psi (1.72 Bar); whichever is greater, above the
maximum specified operating pressure in psig at the top. Minimum design
pressure, at the top, is to be 50 psig (3.45 Barg). Minimum design metal
temperature is to be specified where required by Process (i.e. auto-refrigeration).
2. Vessels without pressure relieving devices shall be provided with an outlet which
cannot be completely blocked off. The minimum outlet opening shall be sized so
that the maximum pressure which can be developed in the vessel is not greater
than the design pressure.
5. The title box shall be in accordance with the sample shown below. The initial
issue of the process vessel specification drawing is to be Revision 0 with
subsequent issues in numerical order. Each issue shall be designated on the
vessel sketch (see sample title box below).
CHECKED
APPROVED
REQUISITION NUMBER
1 15APR96 PEM CLIENT SPLITTER T-101
COMMENTS
PEP-1010 (Cont'd)
VESSELS
6. The following liquid surge capacities are to be used for this project. They are
summarized from the appropriate Foster Wheeler Standards.
Low-Liquid Level
(Note: Use of a level transmitter, if permitted by client standards, can allow the
Low, Low Level set-point to be as low as 0-6 above BTL.)
Reflux to Tower 5
Product to Storage 2
PEP-1010 (Cont'd)
VESSELS
In case surge must be provided for both product and reflux, the larger volume is
used (not the sum of the two volumes).
- on Level Control 5
- on Flow Control 15
Feed to fired coil reboilers: sum of 5 minutes on vaporized portion and 2 minutes
on product. It is normally desirable that 5 minutes on vaporized portion be
employed to establish NLL, the subsequent 2 minutes on product used to
establish the HLL (NLL to HLL, minimum of l ft.).
FOSTER WHEELER USA CORPORATION PEP No.: 1011
PROCESS ENGINEERING PRACTICE Page: 1 of 3
Revision: 4
Date: Mar. 6, 2006
______________________________________________________________________
PEP-1011
FIRED HEATERS
The following notes are generally applicable to fired heaters in conventional services.
Some of these notes may not apply to special heaters such as coker heaters or
reformers.
2. The process engineer should indicate the minimum design pressure, but the
design metal temperature must be left blank.
3. Burner type shall be specified for all heaters. In accordance with the BEDD
sheets, burners specified for liquid fuels require pilot burners to be specified.
Burner location shall not normally be specified by the process engineer.
5. The following notes should be included in the process specification for each
heater where applicable. Additional notes may be added as required, e.g.:
PEP-1011 (Cont'd)
FIRED HEATERS
d. Vendor shall provide the following with regard to soot blowers, (applies
only for fuel oil/combination firing with a convection section.)
8. Process data and cost of available fuels will be provided on the Basic
Engineering Data sheets.
9. Given below are guidelines to be used in estimating utility line sizes and utility
requirements for fired heaters (at least until vendor requirements are confirmed).
l) 100 to 200 lbs. steam per MMBtu (180 to 360 Kg steam per
MMkcal) (liberated)
b. Coil Steamout:
l) use 5 lb/sec. ft2 (24.4 Kg/sec.-m2) for steam mass velocity through
coil
PEP-1011 (Cont'd)
FIRED HEATERS
c) Atomizing Steam:
2) use M.P. steam or a steam with at least 30 psi (2.1 Bar) higher than
fuel oil pressure.
d) Soot Blowers:
10. The following items must be shown on engineering flow diagrams for each fired
heater:
- TI's for radiant zone, arch, convection section, stack and crossovers.
Fired heaters will be specified for stable operation without the air blower and with
automatic switchover to natural draft. Vendors will be instructed to advise
turndown required for natural draft operation.
FOSTER WHEELER USA CORPORATION PEP No.: 1012
PROCESS ENGINEERING PRACTICE Page: 1 of 8
Revision: 6
Date: Feb. 11, 2009
______________________________________________________________________
PEP-1012
HYDRAULICS
Below are some general rules for line sizing. These rules should cover most
normal situations, but may not be suitable for all cases, especially revamps. For
critical services or long headers, the process engineer is to carry out a hydraulic
study of the system to confirm the total pressure drops and the pressure balance,
regardless of whether the lines meet the allowable pressure drop and velocity
criteria as given in this PEP.
The process engineer should also refer to Process Standard 201, Fluid Flow
6
Single Phase, and Standard 202, Fluid Flow Two Phase. In case of any conflicts
with the process standards, this Process Engineering Practice shall govern.
Reference the FW Process Standards 103, section 3.0. The minimum drawoff
box depth shall be one and one-half times the nominal drawoff size, but not less
6 than 9 inches. In case of any conflicts with the Process Standard 103, this
Process Engineering Practice shall govern.
Pipe Diameters 8" and less Pipe Diameters more than 8"
Note: Gas blanketed liquids are to be considered as boiling liquids for line sizing,
pump calculations, specifications, etc.
FOSTER WHEELER USA CORPORATION PEP No.: 1012
PROCESS ENGINEERING PRACTICE Page: 2 of 8
Revision: 6
Date: Feb. 11, 2009
______________________________________________________________________
PEP-1012 (Cont'd)
HYDRAULICS
0.5 to 1.0 psi/100 feet maximum for long headers (800 equivalent feet and
greater)
Approximate Velocity
Reboiler Trap-out
Reboiler Return
PEP-1012 (Cont'd)
HYDRAULICS
Approximate Velocity
Allowable Velocities
Maximum for gas = 100/ Dg ft./sec, where Dg is density of gas in lb/cu. ft.
FOSTER WHEELER USA CORPORATION PEP No.: 1012
PROCESS ENGINEERING PRACTICE Page: 4 of 8
Revision: 6
Date: Feb. 11, 2009
______________________________________________________________________
PEP-1012 (Cont'd)
HYDRAULICS
For critical two-phase lines, detailed calculations must be made for pressure
drop and flow required.
Allowable Velocity
PEP-1012 (Cont'd)
HYDRAULICS
Allowable Velocity
Maximum Allowable
Pipe Material Fluid Velocity, ft/sec
Carbon Steel Sour Water/Hydrocarbon Mixture 20
Sour Water > 250F 5
Sour Water 250F 10
Stainless Steel Sour Water at all 20
temperatures
Allowable Velocity
Maximum Allowable
Pipe Material Fluid Velocity, ft/sec
PEP-1012 (Cont'd)
HYDRAULICS
Line sizing shall generally be in accordance with API RP 520, Part I and
Part II, and RP-521.
Where:
Both the controlled bypass lines around the condenser and the vent line
from the accumulator drum are sized for a minimum of 10% of the tower's
gross overhead flow. Refer also to Process Standard 507, Section 4.0 for
more conservative sizing criteria.
Open balance lines in total condenser services should be sized for 25% of
the tower gross overhead flow or shall be sized to pass any relief flows,
whichever case controls.
PEP-1012 (Cont'd)
HYDRAULICS
a) Velocity criteria for line sizing: To avoid settling in lines, design for a
minimum allowable velocity of 3 ft/sec in normal operation. To
avoid abrasion and excessive wear in the lines, design for
maximum normal velocity of 7 ft/sec.
PEP-1012 (Cont'd)
HYDRAULICS
Generally, the pressure drop assigned to the control valve for the pump, at
normal operating capacity, shall be equal to either 10% of the system
operating pressure in psig at pump destination, up to 1000 psig, or 33% of
the frictional loss in the system excluding the pressure drop assigned to
the control valve, whichever is greater. For systems where high frictional
losses are taken, i.e., crude preheat circuits, 10% of the estimated pump
destination pressure should be adequate; but in no case shall the
assigned control valve pressure drop for the pump design case be less
than 10 psi. For systems operating above 1000 psig, the control valve
may take less than 10% of the system pressure, depending on process
and control considerations.
2.2 Other Liquid Services (Gravity flow, cascading from one pressure level to
another, etc.)
Generally, for other gas services, the pressure drop assigned to the gas
control valve shall not be less than 10% and not greater than 85% of the
pressure differential available for frictional loss.
FOSTER WHEELER USA CORPORATION PEP No.: 1013
PROCESS ENGINEERING PRACTICE Page: 1 of 3
Revision: 4
Date: Mar. 6, 2006
______________________________________________________________________
PEP-1013
EXCHANGERS
1. Air cooled exchangers typically are forced draft, usually with a minimum of two
fans per bay.
2. If both the cold side inlet and outlet of an exchanger require block valves, a relief
valve shall be provided on the cold side inlet to prevent excessive thermal
expansion. In no case, should this relief valve be set lower than the highest
pump shut-off pressure to which it may be subjected, or higher than the
exchanger design pressure.
3. The general order of priority to establish the tubeside fluid is listed below. This
listing is for guidance only and should not be considered inflexible.
(ii) A corrosive fluid or a fluid likely to deposit coke, sediment or other solids
such as catalyst.
(iv) The less viscous of the two fluids, where large differences exist.
(v) The fluid under higher pressure, where large differences exist.
Condensing vapors are usually located on the shell side. Also, if the temperature
change of a fluid in an exchanger is very large, for example, several hundred
degrees, it is often better to pass this fluid through the shell. Otherwise multiple
bundles may be required to avoid excessive temperature stresses on the
tubesheets.
FOSTER WHEELER USA CORPORATION PEP No.: 1013
PROCESS ENGINEERING PRACTICE Page: 2 of 3
Revision: 4
Date: Mar. 6, 2006
______________________________________________________________________
PEP-1013 (Contd)
EXCHANGERS
The following additional provisions are required for freeze protection, where
applicable, during start-up and shutdown:
- Self draining, steam coils and louvers shall be provided on air cooled
exchangers handling high pour materials, water or hydrocarbon/water
mixtures.
5. The specified fouling resistance shall be in accordance with the latest TEMA
standards. The following fouling resistances shall be specified for utility streams
regardless of velocity or temperature:
Steam 0.0005
Boiler Feedwater 0.001
Condensate 0.001
Cooling Water 0.002
Lean Amine 0.002
Rich Amine 0.002
FOSTER WHEELER USA CORPORATION PEP No.: 1013
PROCESS ENGINEERING PRACTICE Page: 3 of 3
Revision: 4
Date: Mar. 6, 2006
______________________________________________________________________
PEP-1013 (Cont'd)
EXCHANGERS
6. The suggested minimum design pressure for shellside and tubeside shall be
specified by the process engineer. This value shall be the greater of:
- Maximum pump shutoff pressure, when exchanger can be blocked off and
exposed to pump shutoff.
- 50 psig
9. Suggested minimum design temperature for shellside and tubeside fluids shall be
specified by the process engineer. This value shall be the greater of:
10. Where applicable, limiting transfer rates and exchanger type shall be indicated.
FOSTER WHEELER USA CORPORATION PEP No.: 1014
PROCESS ENGINEERING PRACTICE Page: 1 of 3
Revision: 4
Date: Mar. 6, 2006
______________________________________________________________________
PEP-1014
1. Overcapacity Factors
a. Pumps
b. Compressors
Centrifugal 1.2
3. For pumps specified for bubble point fluids show "B.P." on the pump specification
sheet rather than the actual vapor pressure. Note that this also applies to fluids
containing dissolved/entrained gas.
MSP (Max. Suction Pressure) = static head measured from maximum tank
liquid level (zero frictional line loss)
PEP-1014 (Contd)
PSP (Pump Shutoff Pressure) = MSP plus 1.2 x (pump differential at maximum
specified specific gravity).
5. Minimum flow requirements must be specified for each pump, to cover such
conditions as start-up, shutdown, turndown, regeneration, etc.
6. Pump calculations for NPSH and power consumption are to be made at the
design flowrate.
8. The following note is to be affixed to the specification for all equipment having a
design pressure determined by pump shutoff.
9. Spare Capacity
a. 100% spare capacity shall be specified for all pumps in critical service.
c. Single speed electric motors are preferred drivers for primary and spare
pumps, as well as for compressors. Steam turbine drivers may be
selected based on special process, utility or mechanical considerations.
FOSTER WHEELER USA CORPORATION PEP No.: 1014
PROCESS ENGINEERING PRACTICE Page: 3 of 3
Revision: 4
Date: Mar. 6, 2006
______________________________________________________________________
PEP-1014 (Contd)
11. Drivers for air blowers shall be designed for cold air operation.
FOSTER WHEELER USA CORPORATION PEP No.: 1015
PROCESS ENGINEERING PRACTICE Page: 1 of 15
Revision: 0
Date: Sep. 12, 2008
______________________________________________________________________
PEP-1015
1 SCOPE
This work practice outlines the requirements for preparing and maintaining a Process
Dept Detailed Work Plan, including the Work Plan Summary Sheet (WPSS), covered in
EP 8-1, for typical projects. Special considerations may require deviation from this
work practice with the approval of the Director-Process Engineering.
2 GENERAL
2.1 This PEP is applicable to all projects ranging from Process Design Packages to full
EPCM projects, with the understanding that progress milestones and weighting
values (percentages) will vary between the types of projects handled.
2.2 The Lead Process Engineer shall prepare the detailed work plan and corresponding
WPSS used to track the progress of all equipment items, studies and/or work
products assigned to the Process Department for the given project. The Chief
Process Engineer may elect to assign another Process engineer to prepare and
maintain the work plan, however, it shall be the Lead Process Engineers
responsibility to ensure that the plans accuracy as well as the requirements of this
PEP and other practices referenced herein are followed in the preparation and
maintenance of the detailed work plan and WPSS.
2.3 The purpose of the work plan is to plan, execute and report progress by achieving
specific activity milestones for each tagged equipment or, study, activity and/or work
product. Partial earned credit may be taken, as defined in paragraph 7.3, for these
milestones. The work plan also reports hours earned as well as total percent
complete per item or activity.
2.4 A template Workplan and WPSS, Form No. 210901, is located on the Process
department webpage of the Foster Wheeler Intranet in the Workplan Template
directory. The file is a single Excel Workbook that includes the WPSS and
Workplan. The Process Work Plan Template workbook contains the following tabs:
2.4.1 WPSS is the first tab and is clearly labeled WPSS ROLLUP (typical for all
department WPSS practices). The Department WPSS Form contains
company-wide Earned Value and Productivity Calculations that are
password protected for consistency across the organization.
2.4.2 An overall summary is the second tab. The overall summary is auto-
populated from the Progress report sheet (see paragraph 2.4.3).
FOSTER WHEELER USA CORPORATION PEP No.: 1015
PROCESS ENGINEERING PRACTICE Page: 2 of 15
Revision: 0
Date: Sep. 12, 2008
______________________________________________________________________
PEP-1015 (Contd)
2.4.3 The detailed work plan is provided in the third tab, labeled Progress report.
The detailed work plan lists all of the activities defined in the WPSS with a
further detailed breakdown. For example, the WPSS has an activity,
Process Specifications (job class 6) while the work plan lists each major
piece of equipment by tag number.
2.4.4 Variances are summarized in the fourth tab, labeled Variances. Variances
are further discussed in paragraph 7.2.
Job Class the Job Classes are the standard Job Classes for the Process
department.
Unit of Measure these are the units that are used to provide more objective
measuring tools in determining the earned value of the project.
Unit Counts (Original, Approved and Forecast) this is a value for the number of
items (see Unit of Measure) that are required for each Job Class. The Original
number is the initial number from the original estimate for the project. The
Approved number would include the Original number plus all approved quantities
due to client approved Change Orders. The Forecast number includes the
Approved number plus submitted variances that have not been approved or
detected variances that have not been submitted.
Budget Hours (Original, Approved and Forecast) this is a value for the number of
hours that are required for each Job Class. The Original number is the initial
number of hours from the original estimate for the project. The Approved number
would include the Original Number of hours plus all approved hours due to client
approved Change Orders. The Forecast number includes the Approved hours
plus submitted variances that have not been approved or detected variances that
have not been submitted.
Earned Hours a calculation of the earned hours for effective hours for each Job
Class.
FOSTER WHEELER USA CORPORATION PEP No.: 1015
PROCESS ENGINEERING PRACTICE Page: 3 of 15
Revision: 0
Date: Sep. 12, 2008
______________________________________________________________________
Earned Value (EV%) is the percent of the hours or units earned for each Job
Class. This is summed up to provide the total percent complete for all activities on
the project.
2.6 The Lead Process Engineer or designee shall submit the completed work plan,
including the WPSS, to the Chief Process Engineer for review and approval prior to
distribution to the Project Manager or as directed by the Project Manager. The Chief
Process Engineer shall signify approval of the work plan and WPSS by returning a
signed copy of the WPSS to the Lead Process Engineer.
3.1 The following list defines the information needed by the Lead Process Engineer in
order to prepare the work plan and WPSS.
3.1.1 Equipment List with item tag numbers and descriptions or preliminary
process flow diagram.
3.1.3 Approved Contract Budget Manhours for the Process Department including
breakdowns by activity if available.
4.1 The work plan must be created by making a copy of the department work plan
template located on the Process Dept. Intranet web page, and saving to the project
folder. DO NOT copy an existing work plan from another project. The electronic file
name for the work plan shall follow the convention given in EP 8-1.
4.2 Modify the work plan by inserting the project item tag numbers, descriptions,
activities and budget man hours with scheduled dates for completion. (Refer to
Attachment A and paragraphs 5.1 through 5.5 below)
4.3 Activity milestones not applicable due to the scope of the project may be zeroed out
on the WPSS form. However, the milestone activities will still be listed.
FOSTER WHEELER USA CORPORATION PEP No.: 1015
PROCESS ENGINEERING PRACTICE Page: 4 of 15
Revision: 0
Date: Sep. 12, 2008
______________________________________________________________________
PEP-1015 (Contd)
4.4 Additional milestones, not contained within the template, shall not be added without
prior consultation with the Chief Process Engineer(s) and Director-Process
Engineering.
4.5 The weighting value associated with each milestone, as given in paragraph 6.2,
shall not be modified without prior consultation with the Chief Process Engineer
and/or Director-Process Engineering.
4.6 The work plan is divided into several tabs within the electronic file, as described in
paragraph 2.4. Typically, one work plan is produced per project, regardless of how
many units are in that project. However, if the client and/or Project Manager require
separate tracking for each unit, then individual work plans or separate Progress
report tabs linked to a single overall summary and WPSS ROLLUP tabs, may need
to be created.
4.7 If the activity and/or milestones do not apply for a particular project, they will be left
blank on the WPSS ROLLUP tab. The activities are fixed and rows cannot be
added or deleted nor can activity names be changed.
4.8 After the set up process, all formulas shall be reviewed to insure that they are
functioning properly. The template can be used to assist in correcting any cells that
may have been accidently modified during set up.
5.1 The WPSS shall be set-up based on Job Class/Activity. Job Classes shall consist of
the following activities listed below with their respective unit of measure.
PEP-1015 (Contd)
5.2 The Unit Count and Budget Hours associated for each Job Class shall be
determined from the values located in the work plan. During the initial set up, the
values for the Original Plan, Approved Contract Budget and Current Forecast shall
all be the same.
5.3 The Activity Milestones and their Weighting for each Job Class shall be taken from
the work plan without modification.
5.4 The primary document for forecasting and measuring progress is the Progress
report tab in the work plan workbook. The Progress report is customized to each
project and will list each activity by drawing number, tag number, study, etc., as
shown on the template in Form 210901 on the Process Department Intranet web
page. While certain fields in the Progress report worksheet are protected because
there is a formula, the number of rows may be increased or decreased as required.
FOSTER WHEELER USA CORPORATION PEP No.: 1015
PROCESS ENGINEERING PRACTICE Page: 7 of 15
Revision: 0
Date: Sep. 12, 2008
______________________________________________________________________
PEP-1015 (Contd)
5.5 The overall summary tab of the workbook will be automatically populated with the
data from the Progress report tab. The cells in this worksheet are protected to
prevent an individual from writing over the formulas.
5.6 The WPSS ROLLUP tab has some fields auto-populated from the overall summary
worksheet but the following fields must be input by the Lead Process Engineer:
5.6.1 Unit Count, Original plan the number of units for each activity is input.
Currently, this is a manual function where the Lead Process Engineer has
to count the number of units from the Progress report summary. Units are
defined in paragraph 5.1.
5.6.2 Budget Hours, Current forecast typically this will be equal to the Approved
Budget Hours; however, if there were any variances that have not been
approved or submitted for approval, these hours would be reflected in this
column.
5.6.4 Milestone units the number of units for each activity completed for each
milestone is manually entered. In some categories, for example, process
specifications, this number may have to be adjusted from the actual number
in order to match the number of manhours completed from the Progress
report worksheet. This is because for this category, different equipment
types (towers, exchangers, pumps, etc.) have different manhours per item
assigned and when the unit totals are combined, the result may differ from
the Progress report summary. If this occurs, the Lead Process Engineer
has to manually adjust the unit number until the earned manhours agree
with the manhours on the Progress report worksheet.
5.5 After the set up process, the formulas shall be reviewed to insure that they are
functioning properly. The template can be used to assist in correcting any cells that
may have been accidentally modified during set up.
6 ACTIVITY MILESTONES
6.1 The primary Activity Milestones to be used on the work plan and WPSS, and their
definitions, are given below:
FOSTER WHEELER USA CORPORATION PEP No.: 1015
PROCESS ENGINEERING PRACTICE Page: 8 of 15
Revision: 0
Date: Sep. 12, 2008
______________________________________________________________________
PEP-1015 (Contd)
6.1.1 Basis of Design The Process department is responsible for preparing the
Basis of Design for a project. The Basis of Design incorporates relevant
data from the following: Client requirements; Basic Engineering Data (BED)
sheets; contractual requirements; Process Coordination Procedure; and
Process technology requirements.
6.1.2 Basic Heat & Material Balance In accordance with Process Department
Procedures, the Process Department is responsible for establishing the
material balance flows to and from the unit as well as establishing all
intermediate stream flows. The material balance then sets the associated
energy balance. Stream flows are captured on Material Balance Sheets
(also known as Diamond Sheets). Each stream has a number that is
referenced on the Process Flow Diagram of the associated process unit.
6.1.4 Process Flow Diagrams Process Flow Diagrams (PFDs) are created and
maintained by the Process in accordance with Process Department
Procedures and the Process Engineering Practices (PEPs), and show all
equipment, stream numbers, temperatures and pressures that results from
the design necessary to meet the requirements established in the Basis of
Design.
6.1.5 Material Balance Summary Sheets This form is used to capture the unit
material balance. The Process Flow Diagram reference stream numbers
with a diamond symbol. The Material Balance Summary Sheets (also
known as Diamond Sheets) list the appropriate stream data for each
referenced stream. The Material Balance Summary Sheets can be found
in the Forms directory on the Process home page. These sheets are also
linked to the EZ Diamond program to easily populate diamond sheets from
a ProII simulation.
FOSTER WHEELER USA CORPORATION PEP No.: 1015
PROCESS ENGINEERING PRACTICE Page: 9 of 15
Revision: 0
Date: Sep. 12, 2008
______________________________________________________________________
PEP-1015 (Contd)
6.1.7 Engineering Flow Diagrams All equipment, line sizes, valves, relief valves,
elevation requirements and all other specific information necessary to
design a specific unit or system is reflected on the Engineering Flow
Diagrams (EFDs). Content and ownership of the EFDs is outlined in the
Engineering Practices (EPs). In general, the Process Department
originates the EFDs and controls them up to the B issue, where Process
releases control of the EFDs to the Project Department and all subsequent
issues are by the Project Department. EFDs are often referred to as P&IDs
(Piping and Instrument Diagrams).
PEP-1015 (Contd)
6.1.12 Process Technical Specifications Also known as the Tech Spec, Spec
Book or PDP Package, this write-up is a compilation of all Project
deliverables set forth in the contract. The Process Technical Specification
often includes deliverables developed and issued by other disciplines (such
as the Material of Construction Diagram, Plot Plan, Design Pressure/Design
Temperature Diagram, etc). This is often the final deliverable to the client.
PEP-1015 (Contd)
6.1.15 Hydraulic Checks In accordance with the PEPs and the Process
Standards, hydraulic checks are the responsibility of the Process
Department. As required, and depending on the contract deliverables and
scope of the project, Process shall request all necessary supporting
information (such as isometric drawings) to evaluate, confirm and finalize
line sizes, equipment elevations, relief valve set pressures, piping
configurations, thermosyphon hydraulics, gravity flow circuits, and other
critical circuits to ensure that the final design, construction and operation of
the unit or system will achieve its objectives and the contract throughput
rate.
PEP-1015 (Contd)
6.2 The project scope will have a direct effect on the weighing factors applied to each
Activity Milestone. For example, PDPs will have fewer milestones with different
weightings than EPC projects. For full EPC projects, the following weighting factors
shall be used.
EPC Projects
Milestone 1 2 3 4 5 6
Design Basis / Kick-off 40% 40% 20%
Meeting
Yields 50% 50%
Simulation Modeling 25% 50% 25%
Heat and Material Balance 25% 50% 25%
Process Studies 35% 50% 15%
Process Specifications 25% 25% 35% 10% 5%
Equipment List 50% 50%
Process Description 50% 50%
Utility Summary & Effluent 50% 50%
Emissions
Instrument Process Data 25% 25% 25% 15% 10%
Interlocks 25% 25% 25% 15% 10%
PSV (includes Flare Summary) 25% 25% 25% 25%
Line Sizing 30% 30% 30% 10%
Hydraulics 30% 30% 30% 10%
PFDs 25% 25% 25% 10% 10% 5%
EFDs 40% 20% 20% 10% 5% 5%
Materials of Construction 50% 50%
(MOC)
Design Pressure & 50% 50%
Temperature (DPDT)
Process Writeups (PDP) 33% 33% 34%
Progress Reports / 100%
Coordination
Operating Guides (with list of 33% 33% 34%
Analytical procedures)
HAZOP 100%
Review of Critical Documents 100%
Requisition Review 100%
Vendor Quotes 100%
Instrument Support 100%
Project Support (P&I) 100%
Model Review 100%
FOSTER WHEELER USA CORPORATION PEP No.: 1015
PROCESS ENGINEERING PRACTICE Page: 13 of 15
Revision: 0
Date: Sep. 12, 2008
______________________________________________________________________
PEP-1015 (Contd)
EPC Projects
Milestone 1 2 3 4 5 6
Follow up / Coordination 100%
Hydraulic Checks (ISOs) 100%
Variances (Approved) 100%
6.3 For those projects whose scope is less than full EPC or for projects for which the
milestones do not apply, the appropriate milestones and the weighing factors will be
modified from those given in paragraph 6.2. The Lead Process Engineer shall
consult with the Chief Process Engineer and/or Director of Process Engineering and
assign the weighing factors to the milestones in the work plan and WPSS.
7.1 In order for the work plan and WPSS to be most effective, they must be updated
frequently and diligently. The frequency of update shall be not longer than once per
week. The Lead Process Engineer shall submit the approved Workplan and WPSS
to meet Project Controls Reporting Period Requirements, which is normally twice
monthly.
7.2 Variances shall be reported immediately and recorded on the detailed work plan
along with the requested manhours.
7.2.1 The variance associated with the tagged item shall be listed below the tag
number on the work plan. The hours in the variance assigned to that tag
number shall be input in the Forecast column. (See Attachment A)
7.2.2 After Project Controls has issued the notification that the variance has been
approved, the hours shall be added to the Client Approved Budget Hours.
FOSTER WHEELER USA CORPORATION PEP No.: 1015
PROCESS ENGINEERING PRACTICE Page: 14 of 15
Revision: 0
Date: Sep. 12, 2008
______________________________________________________________________
PEP-1015 (Contd)
7.3 Since work plans are to be updated on a weekly basis, and considering the time
durations needed to complete some of the milestones, partial credit shall be claimed
for any milestone meeting the criteria set forth in Attachment A. All other milestone
activities are to be reported on an all or nothing basis.
7.3.1 Partial credit may be claimed for Heat and Material Balances based upon
the number of cases to be presented. For example, if 3 cases are to be
presented and only one has been completed, then 33% credit may be
claimed.
7.3.2 Partial credit may be claimed for Process Studies based upon the number
of studies. For example, if 3 studies are considered part of the scope of the
project and only one has been completed, then 33% credit may be claimed.
7.3.3 Partial credit may be claimed for Process Specifications based upon the
number of equipment items. For example, if there are 50 pieces of
equipment and only ten have been completed, then 20% credit may be
claimed.
7.3.4 Partial credit may be claimed for Instrument Process Data based upon the
number of instrument datasheets. For example, if there are 100 tagged
instrument items that require a datasheet, and only 25 have been
completed, then 25% credit may be claimed.
7.3.5 Partial credit may be claimed for PSVs based upon the number of PSVs.
For example, if there are 10 relief valves and only 3 have been completed,
then 33% credit may be claimed.
7.3.6 Partial credit may be claimed for PFDs based upon the number of drawings.
For example, if there are 10 PFDs and only 2 have been completed, then
20% credit may be claimed.
7.3.7 Partial credit may be claimed for EFDs based upon the number of drawings.
For example, if there are 50 EFDs and only ten have been completed, then
20% credit may be claimed.
7.3.8 Partial credit may be claimed for MOC diagrams based upon the number of
drawings. For example, if there are 10 MOC drawings and only 2 have
been completed, then 20% credit may be claimed.
7.3.9 Partial credit may be claimed for DPDP diagrams based upon the number
of drawings. For example, if there are 10 drawings and only 2 have been
completed, then 20% credit may be claimed.
FOSTER WHEELER USA CORPORATION PEP No.: 1015
PROCESS ENGINEERING PRACTICE Page: 15 of 15
Revision: 0
Date: Sep. 12, 2008
______________________________________________________________________
PEP-1015 (Contd)
7.3.10 Partial credit may be claimed for Review of Critical Documents based upon
the number of documents to be reviewed. For example, if there are 50
critical documents and only ten have been completed, then 20% credit may
be claimed. Critical documents will be defined in the project kick-off.
7.3.11 Partial credit may be claimed for Requisition Review based upon the
number of requisitions. For example, if there are 50 requisitions and only
ten have been completed, then 20% credit may be claimed.
7.3.12 Partial credit may be claimed for Vendor Quotes based upon the number of
documents to be reviewed. The total number of documents to be submitted
by the vendor shall be established at the time the equipment has been
awarded to the vendor and this number shall be the basis for determining
partial credit.
8.1 The work plan and WPSS are designed to function as the Process Disciplines
primary progress reporting vehicle and is to be submitted to the designated Project
Controls Manager for the project(s) being reported on. The Chief Process Engineer
and Director-Process Engineering shall be copied at every reporting period, as
defined in paragraph 7.1.
8.2 The work plan and WPSS will indicate Productivity and Earned Value (EV) on
accomplished work utilizing a quantity based tracking system. Manhours are
earned when progress is recorded against each of the milestone activities.
8.3 Productivity values of 1.0 or less indicate efficient execution of the project.
Productivity values exceeding 1.0 indicate too many manhours are being charged
for the milestone activities reached. If this is the case, the root cause of the high
productivity value shall be determined and addressed in order to avoid exceeding
the budget for the project and maintain overall project schedules.
8.4 If the high productivity values result from an increased scope, or rework due to
influences outside the Process or Project Management departments, variances shall
be written and submitted to the Project Manager as soon as the change to the
original or planned scope of work occurs.
FOSTER WHEELER USA CORPORATION PEP No.: 1015
PROCESS ENGINEERING PRACTICE Page: 16 of 15
Revision: 0
Date: Sep. 12, 2008
______________________________________________________________________________________________________
ATTACHMENT A
FOSTER WHEELER USA CORPORATION PEP No.: 1016
PROCESS ENGINEERING PRACTICE Page: 1 of 17
Revision: 0
Date: Feb. 11, 2009
______________________________________________________________________
PEP -1016
Purpose:
This review is organized and conducted by the Chief Process Engineer or designee. A
Chiefs Review conducted by a designee of the Chief Process Engineer requires the
approval of the Director-Process Engineering.
Documentation Required
The revision A issue of the EFDs typically occurs approximately 2 weeks prior to the
Chiefs Review in accordance with Engineering Practice EP 9-1. It is this set of EFDs
that will be reviewed during the Chiefs Review. Early issue of the revision A EFDs
allows time for the other disciplines to review the EFDs and bring their comments to the
Chiefs Review in an organized manner.
In addition to the EFDs, the Process Masters for all equipment shall be available in the
meeting room. By the time of the Chiefs Review, Process Specifications for all
equipment shall have been issued. Only in extenuating circumstances is it permitted to
release the initial issue of Process Specifications during or after the Chiefs Review.
Process Calculation Books (Line Sizing, etc.) shall also be available in the meeting
room, as requested by the Chief Process Engineer.
Scheduling:
The Chief Process Engineer or designee shall send out notification of an upcoming
Chiefs Review to the engineers assigned to the positions listed below. It is expected
that the non full-time invitees visit the Chiefs Review room during the first half-day of
the review to assess their overall involvement and when and if they may be needed
during the review.
The Director Process Engineering shall be informed of all upcoming Chiefs Reviews.
FOSTER WHEELER USA CORPORATION PEP No.: 1016
PROCESS ENGINEERING PRACTICE Page: 2 of 17
Revision: 0
Date: Feb. 11, 2009
______________________________________________________________________
Attendees:
The Chief Process Engineer shall notify the following assigned engineering positions to
the Chiefs Review. Attendance for all disciplines other than Process shall be
coordinated and set by the Project Manager, Project Engineering Manager, or designee.
Process attendees:
The attached Chiefs Review Checklist, Table 1016-1, shall be used by the Chief
Process Engineer and attendees as a guide during the Chiefs Review to ensure that
each and every item on the checklist has been fully addressed or deemed to be not
applicable.
The full name and initials of all participants shall be captured on the Chiefs Review
Checklist.
It is understood that each and every necessary review required for a specific project
may not be listed on the Chiefs Review Checklist. It is, however, the responsibility of
the Chief Process Engineer to ensure that all documents listed above under Purpose
are fully addressed for completeness, continuity, and consistency and that the design of
the unit is safe, environmentally sound, fully operable and will ultimately lead to a
successful start-up and operation of the respective operating unit or system.
FOSTER WHEELER USA CORPORATION PEP No.: 1016
PROCESS ENGINEERING PRACTICE Page: 3 of 17
Revision: 0
Date: Feb. 11, 2009
______________________________________________________________________
At the start of the Chiefs Review, the Process Master set of the EFDs shall be put up
on the wall for review. In addition to the Process Master Stamp the following
information shall be included on the EFDs:
A copy of the Chiefs Review Checklist shall also be posted in the conference room
where the Chiefs Review is being held. The initials of the Process Engineer assigned
the responsibility to review a specific item on the checklist shall be entered on the
checklist once the Chief Process Engineer has reviewed for completeness and
accuracy.
Items that are the responsibility of other departments shall be reviewed in accordance
with their department practices and procedures. Engineers assigned to the Chiefs
Review from other departments that have a responsibility to complete specific checklist
items shall also put their initials next to the checklist items completed. To ensure
consistency in design, the Process Flow Diagrams (PFDs) for the unit must also be
marked up simultaneously with the EFDs.
At the completion of the Chiefs Review, the marked-up set of Revision A EFDs will be
sent to CAD Drafting. A log of drawings submitted to CAD shall be kept, indicating
dates submitted and dates received back from CAD.
The Chief Process Engineer, or designee, shall back-check the EFDs as they come
back from drafting to ensure the accuracy of the drafting. This is not the time to make
additional improvements to the EFDs. Any errors noticed during the back-checking of
the EFDs shall be brought to the attention of the Chief Process Engineer for resolution.
FOSTER WHEELER USA CORPORATION PEP No.: 1016
PROCESS ENGINEERING PRACTICE Page: 4 of 17
Revision: 0
Date: Feb. 11, 2009
______________________________________________________________________
Changes made during back-checking shall be recorded on the Chiefs Review master
copy in a separate color, and/or back-circled and dated to indicate that these specific
changes were post-Chiefs Review comments.
The Chiefs Review Checklist shall be scanned for electronic storage within the Process
Files. The hard copy shall be filed along with the Chiefs Review copy of the EFDs in
the Process Library.
The Chiefs Review EFDs must not be discarded as they too shall be scanned for
electronic storage. It is not required that intermediate CAD copies of the EFDs be
saved. Once all EFDs have been accurately drafted, Process shall notify the Project
Manager that the Revision B EFDs are ready for issue per the Document Distribution
Matrix.
The Revision B issue of the EFDs releases control of the EFDs to Project Engineering
for further development. The Lead Process Engineer shall maintain a Process Master
set of EFDs at all times, regardless of the EFD revision.
Following the Chiefs Review, the Process group shall also update and issue any
modified Process Specifications that changed as a result of the Chiefs Review.
FOSTER WHEELER USA CORPORATION PEP No.: 1016
PROCESS ENGINEERING PRACTICE Page: 5 of 17
Revision: 0
Date: Feb. 11, 2009
______________________________________________________________________
1.2 Pumps
- Rated capacity & head
- Estimated shut-off pressure
- Number of pumps / sparing philosophy
- EIV / MOV
- Provision of temporary suction strainer (TS)
- Flushing oil connection and details
- Suction pressure instruments
- Discharge pressure instruments and check valve
- Power
- Insulation / Tracing
- Warm up provisions
- Coke Crushing Impeller noted (as required)
- Vent
- Drain
- Steam Turbine Assembly (Lines, Control, PSV.)
- Overpressure Protection (PSV) at discharge -
Positive Displacement Pumps
- Frieze Data
FOSTER WHEELER USA CORPORATION PEP No.: 1016
PROCESS ENGINEERING PRACTICE Page: 6 of 17
Revision: 0
Date: Feb. 11, 2009
______________________________________________________________________
1.5 Exchangers
FOSTER WHEELER USA CORPORATION PEP No.: 1016
PROCESS ENGINEERING PRACTICE Page: 7 of 17
Revision: 0
Date: Feb. 11, 2009
______________________________________________________________________
1.7 Reactors
FOSTER WHEELER USA CORPORATION PEP No.: 1016
PROCESS ENGINEERING PRACTICE Page: 8 of 17
Revision: 0
Date: Feb. 11, 2009
______________________________________________________________________
2.0 Packages
FOSTER WHEELER USA CORPORATION PEP No.: 1016
PROCESS ENGINEERING PRACTICE Page: 9 of 17
Revision: 0
Date: Feb. 11, 2009
______________________________________________________________________
2.3 Heaters
- Duty
FOSTER WHEELER USA CORPORATION PEP No.: 1016
PROCESS ENGINEERING PRACTICE Page: 10 of 17
Revision: 0
Date: Feb. 11, 2009
______________________________________________________________________
5.0 Material balances [Also note meter Tag numbers and PFD stream numbers]
FOSTER WHEELER USA CORPORATION PEP No.: 1016
PROCESS ENGINEERING PRACTICE Page: 13 of 17
Revision: 0
Date: Feb. 11, 2009
______________________________________________________________________
5.7 Off-gas
6.4 Condensate
FOSTER WHEELER USA CORPORATION PEP No.: 1016
PROCESS ENGINEERING PRACTICE Page: 16 of 17
Revision: 0
Date: Feb. 11, 2009
______________________________________________________________________
Process Operations
6.6 Fuel Gas
FOSTER WHEELER USA CORPORATION PEP No.: 1016
PROCESS ENGINEERING PRACTICE Page: 17 of 17
Revision: 0
Date: Feb. 11, 2009
______________________________________________________________________