Beruflich Dokumente
Kultur Dokumente
Reference Books
Jha, K.N. (2011), Construction Project Management - Theory and Practice, Pearson
Education, New Delhi.
Project Management Body of Knowledge (PMBOK), (5th Ed.), Published by Project
Management Institute, USA, (2013).
Apfelbaum, A. (2005), Construction Cost Management: Cost Engineering, Cost Controls
and Controlled Bidding, Author House
Schexnayder, C. and Mayo, R.E. (2004), Construction Management Fundamentals,
McGraw Hill.
RICS Black Book
Potts, K. (2008), Construction Cost Management: Learning from Case Studies, Taylor
and Francis
Construction Cost Management System in China, A report by RICS, 2012
Delhi Schedule of Rates
Session Plan
CM 643: Construction Cost Management Systems
Assignment CT/QUIZ
Week Module Lecture Theme
Mensuration and course basics
Week 1 1 Introduction to Measurements and Costs
Week 9 3 Markup
Week 11 4 EVM
- No re-test would be conducted for Quiz and the class test. If you are unable to
make it to the quiz/test, please inform the concerned faculty and seek prior
permission for taking the test on a later date.
- Assignments would be shared during the course of the semester.
Course Pre-requisites
CM 643: Construction Cost Management Systems
Please read the additional reading material posted on LMS and complete the
mensuration problems (Tutorial 1)
What is meant by cost management?
Cost Management
CM 643: Construction Cost Management Systems
Different stakeholders will measure project costs in different ways and at different
times. For example, the cost of an acquired item may be measured when the
acquisition decision is made or committed, the order is placed, the item is delivered,
or the actual cost is incurred or recorded for project accounting purposes.
Rainforcement
Concrete
De-shuttering
Curing
Element Trades Wall Finishes
Earthwork Excavation Brick Screeding
backfilling (A) Load Mortar Tiles
(A) Floor
sub-structure Excavation bearing (4.5 Concrete Mortar
finishes
foundation Soling inch & 9 inch) Rainforcement Adhesive
AAC blocks Wood
PCC
Brick Mortar
Water proofing Mortar Gypsum
concrete Concrete POP
shuttering Rainforcement (B)Wall finishes White wash
De-shuttering (B) Partition or AAC blocks Paint
rainforcement Non load Fly ash brick Distamper
ATT bearing wall Plaster board Wallpapers
Aluminium sheet Mortar
backfilling
Glasses POP
column Below column Plywood Gypsum
column at ground level Adhesive White wash
(C)Ceiling
column at upper floors ceiling Mortar Paint
finishes
Slab Soling POP False ceiling
Concrete Gypsum Plaster board
White wash Steel framing
Rainforcement
False ceiling Adhesive
Shuttering
Plaster board
De-shuttering Steel framing
Adhesive
Wood
CM 643: Construction Cost Management Systems
17
Quantity-Takeoff
CM 643: Construction Cost Management Systems
Owner perspective:
Initial (preliminary) estimate of the project costs at the different stages of the project.
Preparing the BOQ as a requirement of the contract documents.
Estimating the work done for issuing the contractor payments.
Pricing different work items.
Identifying the needed resources (Labor, Equipment, etc.).
Project schedule.
Preparing invoices for work done.
Subcontractors payments.
Review and control of crews production rates.
Taking off quantities
CM 643: Construction Cost Management Systems
Quantities of work are measured net in place in a takeoff for a cost estimate.
Quantities are calculated using the sizes and dimensions indicated on the drawings with
no adjustments to the values obtained for waste factors etc.
Consider the item 12 mm Plywood floor sheathing that is shown on the drawings applied
to a floor 40 feet long and 34 feet wide. Multiplying these dimensions gives a net quantity
of 1360 square feet.
The takeoff quantity will remain as 1360 square feet, and prices for the labor and any
equipment associated with this item of work will be applied to the quantity at a later stage
of the estimating process to establish the estimated cost of this item. When the material
component of this item is priced, however, a waste factor will be added to allow for cutting
and waste on the material.
If this item were measured so that plywood materials can be ordered for the floor under
construction, the person ordering the material will include in the calculations a waste factor
that will result in a gross quantity of, say, 1408 square feet. This inflated amount takes
into account the cutting and wastage of the material involved
Measuring Net in Place
CM 643: Construction Cost Management Systems
1. Dimensions are rounded to the nearest whole inch. However, to avoid compounding
rounding errors, fractions of an inch are not rounded in side calculations until the end
result of the calculation is obtained.
2. Use dimensions obtained directly from drawings, or calculated from figured
dimensions, in preference to scaled dimensions. The estimator should use drawings to
obtain dimensions only as a last resort because drawings are not always accurately
drawn to scale
3. Deductions listed with the dimensions are written in red or enclosed in brackets < >
and noted as deductions
CM 643: Construction Cost Management Systems
IS Code
28
Different Parts of IS 1200
CM 643: Construction Cost Management Systems