This agreement entered into on this the ------- day of ----------Two thousand and
____ at ______ between (Name of the RSETI) established under the Aegis of
administrators)
And:
Contractor, which expression shall mean and include, wherever the context
so
WITNESSES AS FOLLOWS:
I. WHEREAS the Institute established under the Aegis of the (Name of the trust)
,
respect of civil works for proposed construction of Building for SIRD at (Place)
Now this agreement witnesses that in consideration of the above and of the
covenants of the parties contained herein, the Institute hereby engages (Name
of
the contractor), as its contractor for performing work, the scope of which is
1. ENGAGEMENT
The Institute hereby engages (Name of the contractor), the Contractor above
/ tender and employing labour perform the said works in respect of proposed
The engagement of the contractor by the Institute under this agreement shall
3.1 The contractor shall perform all the works specified in Annexure I / contract
document / tender to this agreement and may engage contract labour for the
3.2 The contractor shall and hereby agrees and confirms to comply with all the
employed thereof.
3.3 The contractor shall apply for and obtain license as provided for under
3.4 The contractor shall apply for and obtain license as provided under section
12 of contract labour (regulation and Abolition) Act, 1970 for each contract
separately.
3.5 The contractor shall strictly comply with all the terms and conditions that
the
licensing authority may impose at the time grant of license and the Institute
3.6 The contractor shall be solely responsible for the payment of wages,
including overtime wages to the workmen and ensure its timely payment
thereof.
3.7 The contract shall duly maintain a register giving particulars of the contract
legislations:
(iv) Workmens compensation Act, if the ESI Act does not apply*.
3.9 The contractor shall obtain an independent code number under the
3.10 The contractor shall ensure that the compliance with the provisions of the
contract labour (regulation and abolition) Act, 1970 and other labour
3.11 The contractor shall be solely responsible to adhere to all the rules and
3.12 The contractor or its workmen shall not at any point of time have any
claim
3.13 The contractor shall indemnify the Institute in so far as liability incurred by
3.14 Neither the contractor nor his workmen can be treated as employees of
the
Institute for any purposes. They are not entitled for any claim, right,
3.15 If the contractor fails to discharge his duties or neglects to perform the
terminate this agreement as per clause 6 and get the work done by / through
damages for the loss incurred on account of failure on the part of the
agreement.
4. REMUNERATION
4.1 The Institute shall pay the contractor, remuneration for services rendered
remuneration shall be payable only if the contractor has duly performed all
its obligations and covenants under this agreement and has discharged all
/ tender.
5. MISCELLANEOUS
5.1 The contractor shall not assign, delegate, transfer, etc., any of their right/s
and / or obligation/s under this agreement to any third person/s, concern/s,
5.2 The contractor shall at all times during the agreement and thereafter,
indemnify and keep indemnified the Institute, its officers, employees and
which the Institute, its officers, employees and representatives may or are
this agreement.
5.3 Any amendment and/or modifications to this agreement shall be valid and
for any reason, that provision shall be severed from this agreement and the
the same shall be dealt with in accordance with the latest IBA construction
If the contractor, in the opinion of the Institute, fails or neglects to fulfill any or
all terms and conditions of the agreement, the Institute shall be entitled to
of thirty (30) days to the contractor and the contractor shall not have any right
to claim any damage / compensation from the Institute for the same.
7. NOTICES
laws of India. The courts is __________ district alone, to the exclusion of all
other courts elsewhere in India, shall have jurisdiction to try any dispute
9. DISPUTE RESOLUTION
thereof then at the option of the Institute, the same shall be referred to
the Trust/Society) at (Place). The decision of the sole arbitrator shall be final
and binding on the Parties. The provisions of the Arbitration and Conciliation
In witness where of the parties hereto have here unto set their hands the day
Signature
Signed and delivered by the Director, (Name of the RSETI) by the hands of
1. 2.
Signature
Supplementary Information
Tender for:
The closing date and time for the receipt of the tender is:
at the
Office of Finance & Business Services
The Contract is a Lump Sum Fixed Price not subject to adjustment for Rise and Fall in costs.
Form of Tender
I / We, the undersigned, do hereby tender to provide all materials and labour and perform all
works
required in and about and in connection with the full and proper construction of
strictly in accordance with the Tender Documents and subject to the General Conditions of
Contract and
the General Conditions of Tendering issued by the Principal at or for the bulk or lump sum of
TOTAL $__________________________________________
Dated at
this day of 20
Address
ABN Registration No
Builders Licence
No__________________________________________________________________
Should the foregoing tender be accepted, *I/we the undersigned hereby agree that *I/we will
within
fourteen (14) days after the date of notice in writing by the Director, Campus Life, Griffith
University, to
*me/us of the acceptance of the acceptance of the tender, deposit with the said Director a
security for
the due performance of the Contract arising out of the said acceptance, in the amount and form
prescribed by the General Conditions of Contract, and will within fourteen (14) days after the
receipt of
the Form of Agreement from the Director, enter into with The Principal an indenture for the due
performance of the said contract in accordance with the Drawings, Specifications and General
Conditions of Contract.
Signature
Witness
Name of Witness
You are invited to submit a Tender for the execution and completion of the works
described
below in accordance with the Drawings and Specification (if any) supplied herewith,
the
Griffith University Conditions of Tender & Conditions of Contract for Minor Works
herein, and
any other information issued by the Principal for the purposes of tendering.
Closing date and time for the receipt of the tender is:
Date: (day/month/year)
Tender for:
The Contract is a Lump Sum Fixed Price not subject to adjustment for rise and fall
in
costs.
Retention: 10% of the value of work completed until 5% of the Contract Sum is held
Geoff Smith
Date: (day/month/year)
FORM OF TENDER
I/We the undersigned, do hereby tender to Griffith University to provide all materials
and
labour and perform all works required in and about and in connection with the full and
proper
construction of -
Project No.:
Description of Works:
Campus:
This tender is strictly in accordance with the Tender Documents, and subject to the
Griffith
University Conditions of Tender & Conditions of Contract for Minor Works issued by
the
I/We acknowledge receipt of the following Addenda to the Tender Documents and
my/our
whichever not applicable). If no deletion is made then the Contractor shall be deemed to
have
variations under the Contract. If no figure given, then 10% will apply.
Name: ....
Address: ...
Date: ././..
Specification General
added to by other forces, the Contractor shall liaise with the other forces and
the applicable
Utility Company to ensure that there are no undue delays to the scheduling.
Particular care
are installed by the other forces in advance of the final embankment finishing.
service and detour lighting will be made with the Utility Company by the
Consultant.
General
When any work is undertaken within the limits of the railway right-of-way
including, but not
operations with the railway company and shall ensure that the following
precautionary measures
are observed.
which may be required for the protection of their personnel and facilities,
including any
Insurance.
The cost of this insurance coverage will not be paid for separately, but shall be
considered
protect the trains and operating equipment. Normally the railway company will
provide the
flagperson is required and the railway company does not provide one, the
Contractor shall
supplies the flagperson, the Department will pay the cost of the flagperson(s).
The Contractor shall schedule and coordinate flagging requirements with the
applicable
- The number of hours per day the Contractor requested flagging by the
Railway due to
- The number of hours per day the Railway Company provided flagging;
Section 1 Specification
General
DECEMBER 2010 48
(d) A temporary mat shall be placed over the rails to facilitate the movement of
tracked
equipment.
(e) The railway shall be maintained free of dirt, debris and obstructions at all
times.
(f) The crossing shall not be used for other than the purpose herein provided.
(g) The Contractor shall determine the exact location and depth of any
underground railway
No extra payment will be made or charges allowed for work done in connection
with
locating the cables. Additionally, the Contractor shall be held wholly and solely
responsible
for any damages to these cables that may be attributed to his operations.
(h) The Contractor shall be fully responsible for his work operations adjacent
to the rail line
when working within the railway right-of-way and indemnify and hold harmless
the
Department in accordance with Section 1.2.42, Due Care, Claim Settlement and
Hold
Harmless.
with such legislation and regulations, including, but not limited to, the
provincial Environmental
Protection and Enhancement Act and Water Act, and the federal Fisheries Act
and Navigable
and authorizations issued for the project that pertain to the Contractors work.
The Contractor
The Contractor shall provide the Department with written confirmation of his
full compliance with
all approvals, permits, licences and/or written authorizations before the full
amount of holdback
will be released.
System Manual.
General
DECEMBER 2010 49
1.2.50.2 Environmental Construction Operations Plan
Protection Plan for the Planning and Construction of Water and Transportation
Projects;
control measures under the control of the Contractor during construction; not
permanent or long
The Contractor shall submit his ECO Plan to the Consultant at least 14-
calendar days prior to
the pre-construction meeting. The Consultant will review the ECO Plan and
communicate any
Contractor shall address any issues or concerns with regard to the proposed
ECO Plan to the
The finalization of the ECO Plan to the mutual satisfaction of the Consultant
and the Contractor
By Fax
(Fax No.: )
[Name and Address of Supplier / Service Provider]
[Date]
Our ref.:
building.
Item Description
Validity of Tender
The tender shall be valid for at least 6 months from the date of
the tender.
Submission of Tender
Please submit the duly completed and signed Form of Tender
(Appendix 4) and Declaration
Yours faithfully,
Mandatory Requirements
1. A minimum number of years experience providing the required
service.
8. Job and client reference for similar service for the last three
years.
only (HK$ ).
Description of Goods
Quantity
Manufacturer / Origin
Unit Cost
Delivery Schedule
Payment Terms
receive.
in the capacity of
duly authorized to sign tender for and on behalf of
Date
Witness (signature)
Name
Address
below and the aforesaid mentioned terms and conditions for the
sum of Hong Kong Dollars
only (HK$ ).
Description of Services
Frequency of Service*
Client Reference*
Cost
Payment Terms
receive.
in the capacity of
Date
Witness (signature)
Name
Address
Instructions to Tenderers
University of Aberdeen Tender for:
Instructions to Tenderers
Form of Tender
Tenders must be submitted with the enclosed Form of Tender, and must
be supplemented
Tenderers should note that all attachments and appendices to the Form
of Tender shall
Submission of Tenders
University of Aberdeen
Kings College
Aberdeen
AB24 3FX
The name of the tendering firm must not appear on the envelope, nor
must it be visible
through the envelope.
The Tender must not arrive later than ##. The Tender shall be valid for
acceptance for a
The University reserves the right to award the contract for goods and
services as detailed in
this invitation as it sees fit, and may reject any or all of the Tenders
received with no obligation to disclose its reasons.
basis.
This date may become critical and influence our selection; please
consider this when
calculating lead times. Please include a detailed schedule which you will
implement in
Your offer must include all delivery and on-site installation costs
including adequate
insurances.
Proposed Sub-contractors
Instructions to Tenderers
Fitness for Purpose
University at no charge.
to be included.
Alternative Proposals
In the event that after the date of this Invitation to Tender and prior to
the award of any
circulated as necessary.
PERFORMANCE BONDS
1. The contract documents for all buildings let by the County Council which
bond. However, the successful Contractor may elect to deposit with the
Security will be 10% of the Contract Sum and the Contractor will be required to
If the Contractor does not procure execution and delivery of the bond (or a
or for stating that the Contractor will enter into a Deposit by Way of Security
Appendix A
3. Tenderers are required at the time of tendering to state the name and
address of the Surety with whom they propose to enter into a bond and the
into a bond or a Deposit by Way of Security, the name and address of the
Tenderers are expected to ensure that their Surety will accept the Councils
so and which results in any increase in the cost of a bond (to the successful
E339
be made that the cost of the bond (where a Deposit by Way of Security will
not be entered into has been shown separately from other costs and, if not, a
CB 516
Construction project management 1
Agreement.............................................................................................................. 2
General conditions..................................................................................................3
Particular condition.................................................................................................4
specifications..........................................................................................................5
drawings.................................................................................................................6
method of measurement.........................................................................................7
invitation to tender.................................................................................................8
instruction to tenderers..........................................................................................9