Beruflich Dokumente
Kultur Dokumente
11259 19-1 Supplying and fixing of 24 mm dia rivets confirming to the latest IS Code including 151.70 Nos.
7 all labour, material, riveting gun, T&P etc. required for proper completion of the
work.
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL03 Blacksmith 1st class/Electrician 2.50 546.00 day 1,365.00
2 PL15 Beldar/mazdoor (unskilled) 7.00 300.00 day 2,100.00
3 PL56 Riveter 2.50 558.00 day 1,395.00
4 PL57 Hammerman 2.50 330.00 day 825.00
Machine Group
1 PMC001 Air Compressor 210 cfm 10.00 414.00 hours 4,140.00
2 PMC140 Rivet Gun 10.00 41.40 hours 414.00
Material Group
1 PM0105 Nuts, Bolts and Rivets 38.72 77,964.68 tonne/kilogra 3,018.79
m
Total Resource Amount 13,257.79
Over Heads
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 1,668.54
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 150.17
Total Cost for 100.00 Nos. = Resource Cost + Overhead Cost 15,167.07
11259 19-2 Supplying and fixing of 22 mm dia rivets confirming to the latest IS Code including 149.50 Nos.
8 all labour, material, riveting gun, T&P etc. required for proper completion of the
work.
Over Heads
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 1,644.81
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 148.03
Total Cost for 100.00 Nos. = Resource Cost + Overhead Cost 14,951.29
Specification:
11260 22-1 Clearance of land slides in soil and ordinary rock by a bull-dozer D 80 A-12, 180 71.60 cu.m
4 HP and disposal of the same on the valley side
Over Heads
82. Contractor's Profit Including Over Head 12.5% on (All Resource) 788.15
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 70.93
Total Cost for 100.00 cu.m = Resource Cost + Overhead Cost 7,164.24
11260 22-2 Clearing of land slide in hard rock requiring blasting for 50 per cent of the boulders 118.80 cu.m
5 and disposal of the same on the valley side(Using bull-dozer)
Over Heads
82. Contractor's Profit Including Over Head 12.5% on (All Resource) 1,307.47
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 117.67
Total Cost for 100.00 cu.m = Resource Cost + Overhead Cost 11,884.89
11260 22-3 Slip clearance (by manual means) of loose earth and other small loose materials 170.50 cu.m
6 including disposal as directed by the Engineer-in-charge.
Over Heads
82. Contractor's Profit Including Over Head 12.5% on (All Resource) 531.64
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 47.85
Total Cost for 28.34 cu.m = Resource Cost + Overhead Cost 4,832.61
11260 22-4 Slip clearance (by manual means) of earth and boulders including disposal as 171.30 cu.m
7 directed by the Engineer-in-charge.
Over Heads
82. Contractor's Profit Including Over Head 12.5% on (All Resource) 533.93
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 48.05
Total Cost for 28.34 cu.m = Resource Cost + Overhead Cost 4,853.38
11260 22-5 Slip clearance (by manual means) of boulders only including disposal as directed by 183.30 cu.m
8 the Engineer-in-charge.
Over Heads
82. Contractor's Profit Including Over Head 12.5% on (All Resource) 571.43
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 51.43
Total Cost for 28.34 cu.m = Resource Cost + Overhead Cost 5,194.25
Specification:
Chapter Name Setting Out(Construction of Reference Pillars, Back Pillars and Job Pillars with per no. rates)
Amount And Rate In (Rs)
Item Description Rate Unit
11261 26-1 Construction of reference pillars(totally under ground) of length 200mm, width 72.00 Nos.
2 200mm and height 300mm) as per Fig. 1600.1 (b) and Technical Specification
Clause 1602.1 of MORD specifications for rural roads.
S.No. Item Code Item Description Quantity Rate Unit Amount
Over Heads
24. White Washing, Lettering and Painting, etc. 5% on ( Resource Cost + Over Head Cost + Child Item Amount) 342.90
Total Cost for 100.00 Nos. = Sub Items Cost + Overhead Cost 7,200.98
11261 26-2 Construction of back pillars , of length 300mm, width 300mm and height 400mm of 255.30 Nos.
3 which 100 mm shall be below ground level as per Fig. 1600.1 (b) and Technical
Specification Clause 1602.3 of MORD specifications for rural roads.
S.No. Item Code Item Description Quantity Rate Unit Amount
2 11-6-1-2 Stone Masonry In 1:4 cement mortar 3.60 4,974.70 cu.m 17,908.92
Over Heads
24. White Washing, Lettering and Painting, etc. 5% on ( Resource Cost + Over Head Cost + Child Item Amount) 1,215.83
Total Cost for 100.00 Nos. = Sub Items Cost + Overhead Cost 25,532.48
11261 26-3 Construction of Job pillers of length 400mm, width 400mm and height 600mm of 644.00 Nos.
4 which 100 mm shall be below ground level as per Fig. 1600.1 (d) and Technical
Specification Clause 1602.4 of MORD specifications for rural roads.
S.No. Item Code Item Description Quantity Rate Unit Amount
Over Heads
24. White Washing, Lettering and Painting, etc. 5% on ( Resource Cost + Over Head Cost + Child Item Amount) 3,066.79
Total Cost for 100.00 Nos. = Sub Items Cost + Overhead Cost 64,402.63
Specification:
11261 29-1 Dense graded bituminous macadam for grading I 37.5mm nominal size (bitumen @ 10,264.70 cu.m
6 4.25% by weight of total mix has been taken for analysis purpose)
Over Heads
82. Contractor's Profit Including Over Head 12.5% on (All Resource) 2,20,200.29
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 19,818.03
Total Cost for 195.00 cu.m = Resource Cost + Overhead Cost 20,01,620.59
11261 29-2 Dense graded bituminous macadam for grading II 26.5 mm nominal size(bitumen @ 8,921.00 cu.m
7 4.25% by weight of total mix has been taken for analysis purpose)
Over Heads
82. Contractor's Profit Including Over Head 12.5% on (All Resource) 1,91,374.01
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 17,223.66
Total Cost for 195.00 cu.m = Resource Cost + Overhead Cost 17,39,589.78
Specification: