Beruflich Dokumente
Kultur Dokumente
Grout shall be mixed from ordinary Portland cement and clean water
supplied from the public mains.
The proportions of grout and the minimum strength of work cubes shall
comply with the following requirements:
Two sets of three test cubes shall be taken for one batch of soil nails
grouted for testing purpose. Three test cubes shall be tested at 7 days
and the remaining cubes at 28 days after casting. The characteristic
strength of the grout shall be 21 N/mm2 and 30 N/mm2 at 7 days and
28 days.
All steel reinforcement bars and BRC delivered to site shall possess a
valid mill certificate. Three (3) samples of Y40 rebars shall be sent for
tensile testing to confirm the strength.
Equipment Required :
o Shotcrete/Gunite machine.
o Air compressor-Minimum 390 cfm.
o Water pump-Air / motor driven.
o Cement Mixer