Beruflich Dokumente
Kultur Dokumente
ON
Construction Of
SEPTIC TANK for
10 USERS
at
MAATI
lucknow
SUBMITTED BY APPROVED BY
ER. P. D. GUPTA
1. SANTOSH KUMAR
(HOD Civil Engg.)
SIMT LUCKNOW
Year 2016
PROJECT REPORT
Page 1 of 68
ON
Construction Of
SEPTIC TANK for
10 USERS
at
MAATI
lucknow
S.No Name Membershp Course
1. SANTOSH KUMAR 78590 T. Engg. Civil II
S. Name Membership
No.
Page 2 of 68
1. SANTOSH KUMAR 78590
APPROVED BY:
P.D. Gupta.
H.O.D Civil Engg. S.I.M.T LUCKNOW
ACKNOWLEDGEMENT
Behind any successful work there is not only
individual labour perseverance and diligence but also a lot of
guidance help and co- operation of our well wisher words are
insufficient to record my deep sense of gratitude in my work
which leads to purposeful completion of project work.
Page 3 of 68
I have no words to express my thanks to SHRI PD.
GUPTA (H.O.D. Civil Engg.) S.I.M.T. and SHRI J.C. Jaggi
(lecturer civil Engg.) S.I.M.T. for their vart knowledge, deep
insight and tireless, spared no pains in supervising our
assignment to an abundant conclusion. They have thankful to
them for solving all queries and problems very kindly and
patiently.
CERTIFICATE
E r. P.D Gupta
(H.O.D. Civil Engg. S.I.M.T.
Lucknow)
CONTENT
Page 5 of 68
S.No. Description Page No.
1. Introduction
7
2. Literature review 10
3. Objective of the study 12
4. Planning 14
5. Survey 17
6. Specification 24
7. Need for Sanitary Work 45
8. Constructional Features 48
9. Design 52
10. Estimating 55
11 Abstract Of Cost 60
Conclusion and
12.
Recommendation 62
13. Statement of Problem 65
14. Appendix 68
PROJECT REPORT
ON
Construction Of
SEPTIC TANK for
10 USERS
at
Page 6 of 68
MAATI
lucknow
INTRODUCTION
INTRODUCTION
Chapter-1 Literature review:-
Page 7 of 68
In this chapter planning of various construction activities
it is an administrative process. It means the fanatical function
which decided by a person What to do a job.
Chapter-5 Design:-
Page 8 of 68
In this chapter conclusion and recommendation on
various topics. The total cost of the project is Rs. 53500.00
Rates of various types of items as per latest P.W.D rate.
PROJECT REPORT
ON
Construction Of
SEPTIC TANK for
10 USERS
at
MAATI
Page 9 of 68
lucknow
LITURAURE REVIES
LITERATURE REVISE
Punmia, B.C. etal (1998) have explained various
methods in design of R.C.C. structure that can be adopted
while designing a Septic Tank.
Page 10 of 68
PROJECT REPORT
ON
Construction Of
SEPTIC TANK for
10 USERS
at
MAATI
lucknow
Page 11 of 68
OBJECTIVE OF THE STUDY
Page 12 of 68
PROJECT REPORT
ON
Construction Of
SEPTIC TANK for
10 USERS
at
MAATI
lucknow
PLANNING
Page 13 of 68
PLANNING
It means the managical function which decided by a
person What to do a job.
RAW MATTRAIL:-
ORGANIZATION:-
JOINT EFRORTS:-
COMMUNICATION:-
Page 14 of 68
For execution of project and effective communication of
institution ordered or any changes in the plan design is must
essential in an organization.
TRANSPORTATION:-
ESTIMATING:-
Page 15 of 68
PROJECT REPORT
ON
Construction Of
SEPTIC TANK for
10 USERS
at
MAATI
lucknow
SURVEY
Page 16 of 68
SURVEY
RECONNISAISANCE SURVEY:-
PRELICINARY SURVEY:-
DETAILED SURVEY:-
Page 17 of 68
2-CONTOUR SURVEY:-
We prepare the contour map by contour survey finding out reduced
level of main points. In contouring survey we selected the main station at the
distance of about 10m distance. In this survey the following apparatus are
used-
DRAINGING:-
During survey we founded that high level is 60cm. down from the
ground level.
TYPE OF SOIL:-
Page 18 of 68
The soil of selected site is sandy alluvial and its bearing capacity is 15
T/m 2
ELECTRICITY:-
WATER SUPPLY:-
There is no problem for water supply. The ground water level is not so
down.
SURVEY RESULT:-
Page 20 of 68
10
25
R1 M 1.195 99.915
20
26
R2 M 1.220 99.890
30
27
R3 M 1.250 99.860
40
28
R4 M 1.340 99.770
29 C3 30 1.280 99.830
30 L1 10M 1.230 99.880
31 L2 20M 1.245 99.865
32 L3 30M 1.285 99.825
33 L4 40M 1.245 99.865
10
34
R1 M 1.150 99.960
20
35
R2 M 1.330 99.780
30
36
R3 M 1.380 99.730
40
37
R4 M 1.370 99.710
38 C4 40 1.450 99.660
39 L1 10M 1.305 99.805
40 L2 20M 1.335 99.775
41 L3 30M 1.240 99.870
42 L4 40M 1.200 99.910
10
43
R1 M 1.245 99.865
20
44
R2 M 1.320 99.790
30
45
R3 M 1.330 99.780
40
46
R4 M 1.410 99.700
47 C5 50 1.395 99.715
48 L1 10M 1.300 99.810
49 L2 20M 1.410 99.700
50 L3 30M 1.220 99.890
Page 21 of 68
51 L4 40M 1.370 99.740
10
52
R1 M 1.280 99.830
20
53
R2 M 1.425 99.685
30
54
R3 M 1.395 99.715
40
55
R4 M 1.360 99.750
56 C6 60 1.320 99.790
57 L1 10M 1.390 99.720
58 L2 20M 1.220 99.890
59 L3 30M 1.245 99.865
60 L4 40M 1.195 99.915
10
61
R1 M 1.390 99.720
20
62
R2 M 1.410 99.700
30
63
R3 M 1.435 99.675
40
64
R4 M 1.400 99.710
65 C7 70 1.230 99.880
66 L1 10M 1.115 99.960
67 L2 20M 1.295 99.815
68 L3 30M 1.320 99.790
69 L4 40M 1.355 99.775
10
70
R1 M 1.355 99.775
20
71
R2 M 1.365 99.745
30
72
R3 M 1.380 99.730
40
73
R4 M 1.375 99.715
74 C8 80 1.300 99.810
75 L1 10M 1.250 99.860
76 L2 20M 1.220 99.890
77 L3 30M 1.210 99.900
Page 22 of 68
78 L4 40M 1.290 99.820
10
79
R1 M 1.240 99.870
20
80
R2 M 1.320 99.790
30
81
R3 M 1.365 99.755
40 1.4
82
R4 M 2 99.690
Arithmetical check
BS~F.S=1st R.L-Last R.L
1.110-1.420=100-99.690
0.31=0.31
PROJECT REPORT
ON
Construction Of
SEPTIC TANK for
Page 23 of 68
10 USERS
at
MAATI
lucknow
SPECIFICATIONS
(3)- Side of the trenches shall be vertical and its bottom shall
be perfectly leveled, both longitudinally and transversely.
Page 24 of 68
(4)- During excavation rocky are soils are found these shall be
leveled as for as possible and the small spaces which are
difficult to level shall be filled in with concrete.
(10)- The cost of all materials and labours required for fencing
in and protection against risk of accidents due to open
exaction shall be provided.
Page 25 of 68
CEMENT CONCRETE
(A) MATERIALS:-
(3) CEMENT:-
Page 26 of 68
(4) WATER:- Water used shall be clean and reasonably free
from injurious quantities of deleterious material such as oils,
acids, alkalis, salts and vegetable growth generally potable
water shall be used.
(B) PROPORTIONING:-
(C) MIXING:-
(1) HAND MIXING:-
Page 27 of 68
operation may be done. This shall be mixed at least three
times by shoveling and turning over by twist from centre to
side then back to the centre. A hollow shall be made on the
middle of the mixed pile. Three quarters of the total quantity
water required shall be added while the material is turned in
awards the centre with spades.
(D) CONSISTENCY:-
Page 28 of 68
The quantity of water to be used for each mix of 50
kg cement to give required consistency shall not be more
than 27 liters for 1:1 1/2:3 and vibrate concrete; the limit
specified may be suitably reduced to avoid segregation. The
quantity of water shall be regulated by carrying out regular
slump tests.
(E) LAYING:-
(G) FORMWORK
(A) MATERIALS:-
(B) MIXING:-
Page 31 of 68
(D) LAYING:-
(E) CURING:-
First-class Bricks :-
Page 32 of 68
Bricks should be molded from good earth, free from all
should be hard, sound and of uniform sizes and shape having each two
adjacent plane surfaces at true right angles. The bricks should be free
from cracks, chips, flaws, or humps of any kind. They should not show
on being struck. Dry bricks should not absorb more than one-sixth of
their weight when immersed in water for one hour. They should not
break when two bricks in two hands are struck together or when
Cement :-
The cement used for reinforced concrete works shall be ordinary
269 should be 175 kg/cm2 after 7 days and the minimum tensile
should not be less than 30 minutes and the final setting time should not
Sand:-
The fine aggregate (sand) shall conform to either I.S. 383-1963 or
I.S. sieve No. 480 (approximately 4.75 mm) and retain on No. 15 sieve
successively through S. sieves No. 480 No.240 No. 120 No.60 No. 15.
plinth, where specified may be done with fine sand. The fineness
Cement Plastering :-
(a) Materials : Cement shall be fresh Portland cement and sand shall
then shall be mixed wet adding water slowly and gradually for at
prepared at a time as can be used within the initial setting time (30
minutes) of cement.
Page 35 of 68
lightly roughened, cleaned, washed and wetted. To ensure uniform
mortar.
(d) Laying :- The plastering shall be started from the top and worked
towards the ground. The whole surface shall be made flush with
after 12 hours for at least 7 days and shall be protected from rain
or sun.
Page 38 of 68
LayingBefore laying the concrete, the shuttering shall be clean, free from
dust, dirt and other foreign .matters. The concrete shall be deposited (not
dropped) in its final position. In case of columns and walls it is desirable to
place concrete in full height if practical so as to avoid construction joints but
the progress of concreting in the vertical direction shall be restricted to one
meter per hour. Care should he taken that the time between mixing and
placing of concrete shall not exceed 20 minutes so that the initial setting
process is not interfered with. During winters concreting shall not be done if
the temperature falls below 4C. Concrete shall be protected by frost and
concrete affected by frost shall be removed and work redone.
Page 39 of 68
and the fresh concrete shall, be laid. For successive layer the upper layer shall
be laid before the lower layer has set.
Page 40 of 68
All drainage and sewer pipes shall be laid sockets leading uphill. Preferably
the pipes shall rest on solid and even foundations for the full length of the
barrel. However, the pipe manufacturer's instruction as approved by the
Engineer shall be followed in the matter of support and jointing.
For entry of the pipelines into any building or structure suit-able conduits
under the structure or sleeves shall be used. The conduits and sleeves shall be
such as to allow easy repairs and replacement of the pipes. When openings or
chases are required to be made in the structure for entry of pipelines,
locations and sizes shall be marked and checked by the Engineer. After laying
of the pipeline the openings and chases shall be mended.
Pipes for carrying off the waste from water closed and waste water and
overflow water from baths, wash basins, sinks to drains shall be trapped
immediately beneath such fixtures. Traps shall have minimum water seal of
50 mm and shall be ventilated whenever such ventilation is necessary to
maintain water seal of the trap. Ventilating pipes shall be carried up vertically
form the drain to a height of at least 600 mm above the outer covering of the
roof of the building or as shown on drawings. All vertical ventilating, anti-
Page 41 of 68
syphonage and similar pipe shall be covered on top with a cowl. The cowl
shall be made of C.I. unless desired otherwise by the Engineer.
Jointing
(a) Cast Iron Pipes : Socket and spigot pipes be joined by cast lead shall
joints. The 'spigot shall be centred in the socket of the next pipe by tightly
caulking in sufficient turns of tarred gasket or hemp yarn to have unfilled half
depth of socket. When the gasket or hemp yarn has been caulked tightly a
jointing ring shall be placed round the barrel and tightened against the face of
the socket to prevent airlock. Molten lead shall then be poured into fill the
remainder of the socket and caulked with suitable tools right round the joint
to make up for shrinkage of the molten metal on cooling and shall be finished
3 mm behind the socket face.
Page 42 of 68
In special cases if flanged joints are accepted by the Engineer the joints shall
be made leakproof by inserting approved type of rubber or other gaskets not
less than 1.5 mm thick. The -bolts shall be secured in stages to avoid uneven
strain. Damaged gaskets shall be replaced.
(b) Glazed Stoneware Pipes: Tarred gasket or hemp yarn soaked in thick
cement slurry shall first be placed round the spigot of each pipe and the
spigot shall then be placed into the socket of the pipe previously laid. The
pipe then shall be adjusted and fixed in the correct position and the gasket
caulked tightly so as not to rill more than 1/4 of the total depth of the socket.
The remainder of the socket shall be filled with a stiff mixture of cement
mortar of 1 : 1 proportion. When the socket is filled, a fillet shall be formed
round the joint with a trowel, forming an angle of 45 with the barrel of the
pipe. The newly made joints shall be protected, until set, from use and rain
and shall be covered with damp sacking or other suitable materials.
(c) G I Pipes: Threads shall be cut with sharp tools, and before jointing all
scales shall be removed from pipes by suitable means. The screw threads of
the pipe shall be cleaned out and the joints mode by screwing the fittings after
treating the thread with approved pipe jointing compound. Once a joint has
been screwed up it shall not be backed off unless the threads are recleaned
and new compound applied.
Page 43 of 68
(d) Jointing Cast Iron Pipes with Stoneware Pipes: Where any cast iron
soil pipe, ventilating pipe or trap is connected with a stoneware or semi-
verified waste pipe or drain communicating with a sewer, the beaded spigot
and of such cast iron soil pipe, waste or ventilating or trap shall be inserted
into a socket of such stoneware pipe or drain and the joint made with mortar
consisting of one part of cement and one part of clean, sharp, and after
placing a tarred gasket or hemp yarn soaked in neat cement slurry found the
joint and inserted in it by means of a caulking tool.
(e) Jointing Stoneware with Cast Iron Pipes: Where any water closet pan
or earthenware trap connected to such a pan is to be jointed with a cast iron
soil pipe, the joint between the stoneware spigot and the cast iron socket shall
always be of a flexible nature, such joint shall be made with a mixture of
bitumen and chopped asbestos fire.
Trenches and other Excavation Width of the trench at the bottom shall be
such as to provide 200 mm clearance on either side of the pipe for facility of
laying and jointing.
Page 44 of 68
PROJECT REPORT
ON
Construction Of
SEPTIC TANK for
10 USERS
at
MAATI
lucknow
SANITARY WORKS
Sanitary works usually consists of providing flush type latrines and connecting with Sewer
lines of septic tank. For estimating the numbers of different fittings are found out and rates
are taken per number for supply and fixing in position. The latrine scat with flushing
cistern, flushing pipe, etc., are usually taken as one set, and rate per set for the complete
work is taken in the estimate. Flushing cistern, with flushing pipe may also be taken
separately. Wash-hand basins, Bath tubs, Urinals, etc. are also estimated per number for
the complete work. The fittings as Mica valve, Cowl, Gully trap Master trap, etc., are also
estimated number wise. The pipe lines of different materials of different diameters are
estimated on running metre (r ft) basis for the Complete work, supplying and fixing in
position including excavation, refilling, jointing etc. together with lime concrete bedding
as per specification. Fittings as bends, junctions etc. are not measured separately. Length
shall be measured along the centre line of pipes and fittings. Masonry Manholes and
Inspection Chambers are estimated per number for different sizes fitted with GI manhole
for the complete work. Detailed estimates for Manholes and Inspection chamber may also
be prepared if required. Latrine seat, syphon. footrests, flushing cistern, flushing pipe etc.
each may be taken separately and estimated per number.
Page 46 of 68
SEPTIC TANK
In rural areas, in factories and in unsewered urban and semi-urban areas where adequate
water supply is available from pipe, well or any other source, septic tank is suitable for
disposal of night soil. Water is required for the flow of the night soil from latrine to the
septic tank and for tile functioning of septic tank. Septic tank is so designed that the
sewage is retained in the tank for 24 hours during which period certain biological
decomposition by the action of anaerobic bacteria takes place which breaks and liquifies
the night soil leaving small quantity of solid which settles in the form of sludge at the
bottom of the tank and clear water flows out of the septic tank. The effluent from the
domestic septic tank is usually disposed by absorption in soil through soakpit or subsoil
drains. In bigger septic tank the effluent from the tank should further be treated or purified
by sprinkling or contact bed filter cir by aeration and then let off into 'nala' or drain. The
effluent of the septic tank may also be discharged into open drain after disinfection by
treating with chlorine or bleaching powder in a small chamber outside the septic tank. No
disinfectant as bleaching powder. phenyl. etc., should be used in cleaning latrines as the
disinfectant entering the septic tank kills the bacteria growth and retard the action of
biological decomposition. After every use of the latrine it should be flushed with about 14
litres (3 gallons) of water from a flushing cistern or by sudden hand pouring of a bucket of
water. Domestic water. paper, kitchen water and surface water should not be allowed to
drain into the septic tank.
Page 47 of 68
PROJECT REPORT
ON
Construction Of
SEPTIC TANK for
10 USERS
at
MAATI
lucknow
CONSTRUCTIONAL
FEATURES
Page 48 of 68
SEPTIC TANK
Size of septic tank:- The capacity of the septic tank depends on the interval of sludge
removal or cleaning. Normally sludge may be removed once in every two years and the
liquid capacity of 'septic tank may be taken as 0.13 cu m (1301itre) per head (5 cu ft per
head) to 0.07 cu m (701itre) per head (2.5 cu ft per head). For small number of users 0.13
cu m (130 litre) per head and for large number of users 0.07 cu m (70 litre) per head may
be taken as capacity of the tank. Septic tank shall have a minimum width of 60 cm (2-0")
and a minimum liquid depth of one metre (3'-3") below water level with a minimum free
board (open space) of 30 cm (1 ft) above water level. The septic tank is usually consists of
two chambers (compartments) with a partition wall at a distance of about 1/2 length of the
tank from the inlet end. The partition wall is raised above the liquid surface by 15 cm (6")
and a hole of 15 cm x 15 cm (6"x6") is made at a height of 45 cm (1-6") from the bed of
the tank to connect the two chambers. Small tanks may be made of one chamber with
hanging baffle wall at a distance of 1/ 2 to 1/5 distance from the inlet end. Total combined
length of the tank shall be 2 to 4 times the breadth. Design calculation of septic tank for 25
users and 20 users in metric system have been given in the following pages.
Septic tank is usually consists of brick wall in cement mortar not less than 20 cm
(9") thick and the foundation floor are of cement concrete 1:3:6 or 1:2:4. Both inside and
outside faces of wall and floor are plastered with a minimum thickness of 12 mm (1/2)
thick cement mortar 1: 3 and, inside corners are rounded. Floor should be given a slope of
about 1 in 20 for the convenience of collection and removal of sludge. Septic tank may
also be built with stone masonry, precast or cast in situ cement concrete of 1:2:4
proportion. The cover of the septic tank is of R.C.C. slab with suitable circular openings
with cast iron manhole cover for cleaning and inspection. For small septic tank precast
Page 49 of 68
R.C.C. stab in strips may be provided, one or two pieces may be removed for cleaning and
refitted.
Connecting pipe should be 100 mm (4") minimum diameter and may be of S.W.
pipe, R.C.C. or Hume pipe, or cast iron pipe. Inlet and outlet may be made through T-
junction pipe or baffle wall of precast R.C.C. may be provided at a distance 1/5 of length
of the septic tank so that inlet sewage may not disturb the working of the tank. Ventilation
pipe of 50 mm (2") minimum diameter are provided up to a height of 1.80 meter (6 ft). If
the septic tank is within 15 metre (50 ft) of a habitable building, the ventilating pipe should
be carried to a height of 1.80 metre (6 ft) above the roof of the building.
Starting of new septic rank:- A septic tank should be fitted with water to its outlet
level before night soil as allowed to enter the tank.. It should then be seeded with sludge
obtained from the septic tank in the neighbourhood. In the absence of the sludge a small
quantity of decaying organic matter such as decomposed cowdung may be introduced.
Desludging: Removal of sludge from the septic tank is required once in a year
or once in every two years. The quantity of dry sludge is about 70 gram per head per day
and the volume of the digested sludge is about 0.00021 cu m (0.21 l) per head per day. For
small domestic septic tank cleaning or removal of sludge may be done through the opening
at the top cover after dewatering. For large septic tank desludging or removal of sludge
may be done through sludge pipe and value placed at the lowest point of the tank
connected to a separate sludge chamber having its bed lower than the bed of the septic
tank. Desludging should not be done completely, a small quantity of sludge should be left
to act as seed for the quick growth of anaerobic bacteria. (In practice the septic tanks are
cleaned once in every 3 years or even more).
Page 50 of 68
Disposal of effluent by absorption: Disposal of effluent from the septic tank
may be done by absorption in soil by soak pit or by sub-soil drain. Their size and length
depend on the number of users and nature of soil. The soil absorption system should be at
least at a minimum distance of 7.5 metres (25 ft) from any source of drinking water and
should be at least at a minimum distance of 6 metres (20 ft) from the habitable building to
avoid damage to structure.
Page 51 of 68
PROJECT REPORT
ON
Construction Of
SEPTIC TANK for
25 USERS
at
S.I.M.T,
lucknow
DESIGN
L x B = 2.28m2
2.5 xB x B = 2.28m2
2 2.28 m2
B= =0.91 m
2.5 m2
Say B = 0.90m
Say 2.50 m
Page 53 of 68
Depth of the tank = 1.0 + 0.30 m = 1.30 m
Page 54 of 68
PROJECT REPORT
ON
Construction Of
SEPTIC TANK for
10 USERS
at
MAATI
lucknow
ESTIMATING
Septic Tank
i. Long wall
1st offset 2 3.20 0.30 0.60 1.15 There is no
deduction of
hole area
because area in
Page 56 of 68
less than 0.1
mm2
2nd offset 2 3.00 0.20 0.75 0.90
ii. Short wall
1st offset 2 0.90 0.30 0.60 0.33
2nd offset 2 0.90 0.20 0.75 0.27
iii. Partition wall 1 0.90 0.10 1.20 0.11
Total 2.76m3
6. 12 mm thick plaster 1:3
cement sand mortar
Inside Tank
Long wall 2 2.60 - 1.30 6.76
Short wall 2 0.90 - 1.30 2.34
Partition wall
Vertical wall 2 0.90 - 1.15 2.07
Top wall 1 0.90 0.10 - 0.09
Outside Tank
All Round wall
Bottom -2(3.20 + 1.50) = ( 9.40+ 8.60 )
1 1.45=13.05
9.40 2
m
Head 2 (3 +1.30) =8.6
0m
H = 0.60 + 0.10 + 0.75 =1.4
5
Head of wall 2 ( 3+0.90 ) 0.20=1.56
Total 25.87m2
Deduction 2 0.10 - 1.15 0.23
Total 0.23
Net total 25.64m2
7. Supply and Fixing of 2 - - - 2 N cm
Inlet and outlet C.I. pipe
T-junction 100 mm
Total 2 N Cm
PROJECT REPORT
Page 58 of 68
ON
Construction Of
SEPTIC TANK for
10 USERS
at
MAATI
lucknow
'
ABSTRCT OF COST
Page 59 of 68
foundations
2. Cement concrete in foundations
1:4:8 0.87 m3 6200.00 5394.00
3. Cement concrete in Floor 1:2:4 0.12 m3 7300.00 876.00
4. Precast R.C.C. slab 1:2:4
complete work 0.40 m3 9500.00 3800.00
5. First class brick work in
foundation and plinth 1:4 2.76 m3 7660.00 21528.00
6. 12 mm thick cement plaster 1:3
with compound 25.64 m3 430.00 11052.20
7. 100 mm dia A.C. pipe T-
Junction 2 Nm 490.00 980.00
8. S/F of 100 mm dia A.C. A.C.
pipe 3 m 510.00 1530.00
9. 50 mm dia vent pipe 1.80 m 990.00 1782.00
10. 50 mm dia C.I. cowl 1 Nm 250.00 250.00
11. C.I. Stair (4.5 kg) 4 Nm 90.00 360.00
12. Man hole cover 600 m x 45 cm 1 Nm 990.00 990.00
Total 50610.50
Add 5% contingencies charges and work charges establishment 2530.70
Grand Total 53141.20
Say Rs. 53500.00
PROJECT REPORT
ON
Construction Of
Page 60 of 68
SEPTIC TANK for
10 USERS
at
MAATI
lucknow
CONSOLATION AND
RECOMMENDATIONS
CONCLUSION
In the PLANNING, DESIGNING, ESTIMATING AND
COSTING OF CONSTRUTION OF SEPTIC TANK FOR 10
USERS AT MAATI, LUCKNOW project high factor of safety
is considered. In the CONSTRUTION OF SEPTIC TANK
FOR 10 USERS MAATI, LUCKNOW, I tried to provide all
essential safety to the in their need. The estimated cost of
the septic tank is Rs. 53500.00 as per Latest UP PWD
Page 61 of 68
schedule of Rates. Proper planning of the building reduces
the effort at the latter stage. Moreover, it makes the
structure economical and comfortable. During project work
I got a lot of knowledge and experience. Acquire capability
of tackling of problems. I find that to complete project work
in parts is easy as compared to carry out whole project
work at a time. There is no option of regroups labors.
During project work dedication and hard work is necessary.
Without proper supervision of supervisor it was not easy to
complete project.
RECOMMENDATION
1- Design data may be checked by the advance
computer software which is available in market and a
comparison should be made in the effort required.
Page 62 of 68
state method and comparison should be done in both
the methods keeping in view space and cost savings.
PROJECT REPORT
ON
Construction Of
SEPTIC TANK for
Page 63 of 68
10 USERS
at
MAATI
lucknow
STATEMENT OF THE
PROBLEM
BIOGRAPHY
1. B.C. Punmia, Ashok K. Jain, Arun K. Jani Surveying
vol- 1 Laxmi Publication Limited.
Page 65 of 68
3. B.N. Dutta (1996) Estimating and Costing in Civil
Engineering Theory and Practical, UBS Publisher's
Distributions Limited New Delhi.
PROJECT REPORT
ON
Construction Of
Page 66 of 68
SEPTIC TANK for
10 USERS
at
MAATI
lucknow
APPENDIX
Bio Data
Synopsis approval letter
LIST OF DRAWINGS
PLAN OF SEPTIC TANK
Page 67 of 68
FOR 10 USERS
SECTIONAL VIEW
Page 68 of 68