Quick construction model of mine in Shendong

Maosen Yi
Shendong Coal Co. LTD, Shenmu, Shanxi Provence, P.R. China

ABSTRACT: This paper introduces the form of the quick mine construction model and its main content by
analyzing the development process in Shendong mine area. It mainly expatiates the key technique such as incline
tunnel, non-panel arrangement, trackless ancillary conveyance, quick heading with continuous miner and bolt
support.

1 OVERVIEW scale of 600,000 t/a in 1987. According to the policy


adjustment for Shendong mine area from government
Shendong mine area, as one part of Shenfu and in 1991, the production scale of mine extended as
Dongshen coal field, is located at the north of Shenmu 3,000,000 t/a. In 1997, built up such ground living
County, Yulin City, Shanxi Provence, the east of welfare facilities as schools, kindergartens, workers
Fugu County, the south-east Zhungeer and Yijinhuolu, and staff club and eatery, habitation area and agricul-
Eerduosi, Inner Mongolia. It covers 3481 km2 with tural and trade market, the mine put into production
length of 3890 km from north to south, 3555 km with total investment of 1.118 billion RMB and with
from west to east and with geological reserves totaling construction period of 11 years. Although the main
35.4 billion tons. There are 13 minable coal seams conveyance system was designed to use continuous
with 12 , 22 , 31 , 42 and 52 as main minable belt conveyor, its conveyance ability was universally
seams with total average height of 1721 m and sin- low because of the small mine design capability. The
gle maximum height of 89 m. With high quality, coal ancillary conveyance system adopted traditional track
in main seam is non-caking coal and long-flame coal conveyance of haulage motor with stringing. It is
with low ash, low sulfur, low phosphorus, medium and severely limited the mine development and increasing
high caloric value. It can be high quality steam coal, benefit and decreasing manpower with low level of
chemical coal and domestic coal. The exploration is of technical equipments, large amount of panel division,
superior condition with stable seam, simple geological complex developing layout. The other mines such as
construction, smooth dip angle, shallow burying and Shangwan and Daliuta exist the analogue more or less.
low content of gas.
From the initial establish in 1985 to today, through
more than ten years construction, Shendong Com- 1.2 Construction late time
pany has become the largest coal production base and In 1998, the Group made the decision to unite the
important exporting base for high quality steam coal two Company of Shenfu and Dongshen as Shen-
in China at present. dong Coal Company, starting the depletion of mem-
ber from the Company office. In succession, for
changing nature advantage into production advan-
1.1 Construction prior period
tage, resources advantage into the benefit advantage
Though insisted on the principle of high start, high as soon as possible, based on the analyzing of coal
technology, high quality, high efficiency and high ben- market at home and abroad, new investment construc-
efit at the time to begin the construction in 1985, tion principle, aimed on world leading level, absorbed
Shendong Company was limited with a certain extent abroad advanced experience, relied on technology
by traditional mine construction and design thought. innovation, following the guideline of less investment,
There was the problem of more facilities, complex pro- quick effect self-accumulation and rolling develop-
duction system, long building period, and large initial ment, Shendong Company has built up early or late
investment, small production scale of mine, long life- Dahaize Mine (1,000,000 t/a, reconstruction period of
time, more manpower and low efficiency. For example, 38 days), Yujialiang Mine (8,000,000 t/a, construction
Bulianta mine started to construct with production period of 10 months), Sunjiagou Mine (8,000,000 t/a,

523

Copyright 2004 Taylor & Francis Group plc, London, UK


chap-102 10/8/2004 15: 2 page 524

reconstruction period of 8.5 months) to form a new realizes decreasing manpower and increasing benefit
mode for quick mine construction with Shendong in deed. Underground mining decreases environment
specialty. pollution and its production cost is less than open
mining with big entry arrangement in coal seam.
Continuous miner used in heading entry is not only
2 THE QUICK MINE CONSTRUCTION
of fast speed and high efficiency, but also enables
MODEL IN SHENDONG
lengthening the face advancing length as possible.
Introduced world advanced mining equipments not
2.1 The traditional mine construction model
only made a new step in high production and efficient
faces the rigorous challenge
mine construction achieves great economic benefit,
The traditional mine construction model in China, but also promotes the development of domestic mining
under the guidance of traditional design thought, equipments manufacture in certain degree.
is to carry out overall construction to ground pro-
duction system, preparation system and underground
2.2.2 Design creation is foundation
production with relative mature mining technology
Coal Industry Design Code prescribes that the design
and relative advanced equipments. This kind of con-
lifetime of mine with design ability above 1,200,000
struction mode causes large industry esplanade, com-
2,400,000 t/a, 3,000,0005,000,000 t/a, 6,000,000 t/a,
plete ground living facilities, complex production and
should be respectively more than 60, 70 and 80
preparation system underground and ground, large
years, the overall labor efficiency index is respectively
initial investment, more personnel, low efficiency
3.04.0 t/work, 4.06.0 t/work, 6.08.0 t/work. More-
and long construction period. At the beginning of
over, the mine is of smaller dimension in section, panel
80s in 20 century, the special large scale mines with
and face, more panel division, more quantity of mining
4,000,000 t/a, such as Dongtan mine in Yanzhou,
and heading face, complex entry arrangement system,
Qianjiayin mine in Kailuan, Changcun mine in Luan
large rock engineering, long lifetime, more workers
and Xieqiao mine in Huainan, started mine construc-
and staffs, bad safe condition and low efficiency. To
tion. All of their construction period is beyond 11
take the original design of Daliuta as a example, the
years. The main special large-scale mines started to
mine ability is 6,000,000 t/a with lifetime 118 years,
construct with the influence of that at 80s late in Shen-
overall labor efficiency 8 t/work, total persons 3547,
dong Company. The construction period also is long,
production workers 2837 and management staffs 275,
even the largest mine at that time Daliuta mine with
service persons 373 and others 62, administration and
8.5 years. To the traditional mine construction model,
common building area 125976 m2 . It severely affects
this period got the leading level at that time in whole
mine investment effect. As against, the foreign mine
country. Near 10 years construction speed could not
is of short equipments refresh period, simple ground
satisfy the need of quick development in Shendong.
facilities and showing shortening lifetime tendency.
With the fastigium of returning loan coming, Shen-
For example, Sellby mine in UK, the design ability is
dong is eager to quicken mine construction speed.
10,000,000 t/a with lifetime 40 years and Ense mine 3
The traditional mine construction model faces rigorous
in US, the design ability is 7,500,000 t/a with lifetime
challenge here.
25 years.
It is obvious that to quicken large and special large
2.2 Formation of quick construction of mine
modern mine construction speed, first of all the design
2.2.1 Concept innovation is the precondition thought must be transformed and created to overcome
On the searching of quick mine construction, there the deficiency in traditional design, establish stable
were several focus controversies at the starting stage: foundation for crossover development of Shendong.
the ancillary conveyance is to use track or track- Therefore, by borrowing mine design ideas from
less; mining method is open or underground mining; advanced mining country, innovation of and break
shearing manner is to adopt continuous mining or through our traditional design model, with considering
mechanized shearing; mining equipments is to select the comprehensive factor of mine area general
home-made or fetch in. Relying on concept creation plan, coal seam condition and equipment refresh
to bring technology innovation along and referring the period, Shendong Company designed and constructed
world advanced experience from producing coal coun- Dahaize, Yujialiang and Sunjiagou Mine. Their
tries, the Shendong people with innovation spirit took scale and lifetime were designed respectively as
first overall reformation in Daliuta mine which already 1,000,000 t/a, 8,000,000 t/a 8,000,000 t/a and 20, 25,
put into production. Proven in practice, the ancillary 25 years with rated person of 100, 280, 300. The
conveyance with trackless rubber tire vehicle not only mines only built up production system and necessary
increases the production ability and improves the safe simple office on surface with advanced continuous
condition, but also simples greatly production system miner tunneling process world advanced mechanized
and decreases the links in ancillary conveyance, then corollary equipments. Special large scale mine above

524

Copyright 2004 Taylor & Francis Group plc, London, UK


chap-102 10/8/2004 15: 2 page 525

5,000,000 t/a is constructed as one shaft and one work- 2.2.3.4 Continuous miner fast driving and bolt
ing face high production and efficiency mode with one support
mechanized and two continuous, the other facilities At construction initial stage of Shendong, the mas-
such as living, logistics and welfare rely on society to ter entry was cut with roadheader as main and blast
put off the function of enterprise doing the social work- heading as assistance, entry was supported mainly
ing completely. Shendong Company has started new with arching and anchoring and shotcreting, and the
design for large and special large scale mine in China. mine construction speed was extremely slow-moving.
After the application of monomer bolt support tech-
2.2.3 Technique innovation is key nique with large section full coal entry, advanced
The technique innovation is continuous power for continuous miner driving technique and equipment,
enterprises development. With new technology break- the entry driving speed was increased in large range
ing through traditional mode, building up techno- with the maximum single advance promoted from
logical dense mines instead of labor dense mines, 426 m/month with roadheader to 3273 m/month with
Shendong has established stable foundation for con- continuous miner, average single driving as above
structing high efficiency and benefit mine. 2000 m/month. It ensures mine quick construction.
2.2.3.1 Development of incline tunnel technology
For realizing the continuous conveyance from surface 2.2.4 Intension of quick construction mode
to working face with trackless rubber tire vehicle, The intension is to layout in reason production sys-
through abundant theoretical investigation and prac- tem underground and surface facilities system with
tice searching, Shendong Company points out new least link in whole mine system, reasonable facility
shaft concept of incline shaft. The new concept is that self-contained, ability matching and short construction
the shaft is of certain angle (less than 6 degree), the period, based on ascendant nature resource condition,
conveyance manner is promoted from track train to under the guidance of new whole design thought,
trackless rubber tire vehicle, so as to eliminate sta- depend on advanced construction technique.
tion and track line underground. Material, equipment
and personnel conveyance is just as in adit. That not
only improves the ancillary conveyance ability of shaft 2.3 Main contents of quick construction mode
and solves the bottle neck problem, but also simples 2.3.1 Centralized planning of living quarter
developing system and decreases rock engineering for Using construction experience of world modern coal
station and so on. enterprise for reference, the non-production facili-
ties on surface is made with whatever is available,
2.2.3.2 Trackless technique on ancillary conveyance
living quarter is centralized planned. The mine only
If traditional trackless conveyance is used along, there
establishes industry facilities and working areas with-
is no way to talk about quick mine construction. Even
out residential district to decrease the amount of
though the road railer which was the domestic
engineering on surface and shorten the construction
advanced equipment used at the construction prior
period. There is no individual living district in Daliuta,
period, could not meet the requirement of quick
Huojitu, Dahaize, Shangwan, Yujialiang and Halagou
mine construction. After successful application in
mine, all of employee reside in Daliuta and Shangwan
Daliuta, the use of trackless rubber tire vehicle is
town.
thorough extended and supplies whole new design
model for new mine construction and rebuilding small
mine, increases ancillary conveyance ability during 2.3.2 Cut short office facility in working quarter
construction and ensures quick mine construction Office facility is cut short in new constructing mine
powerfully. and the original facilities which can be used generally
only do simple repairs and maintenance in rebuilding
2.2.3.3 Mine arrangement with no panel small mine.There are only several single story building
The application of incline adit and trackless con- on surface as office without any living service facil-
veyance simplifies mine ancillary conveyance system ity which is not necessary to production in Yujialiang
and the introduction of advanced mechanized tech- and Dahaize mine. They put most power into mine
nique and equipment brings large scale of working face construction engineering to fasten construction speed.
parameters into possibility. With resource advantage of
stable seam and small dip angle, Shendong arranges 2.3.3 Integrated arrangement of master shaft
shaft area no panel to break through traditional shaft conveyance system with surface preparation
entry arrangement with working face connecting to system
main entry directly and cutting eye reaching to the edge First, the belt conveyor in master shaft conveyance
of shaft area. It decreases greatly preparing entry engi- system is lapped directly over raw coal storage to
neering with no panel division and no panel division eliminate drive unit room for master shaft belt con-
entry and shortens mine construction period. veyor, unloading room and belt conveyor to storage.

525

Copyright 2004 Taylor & Francis Group plc, London, UK


chap-102 10/8/2004 15: 2 page 526

Second, the surface crusher is associated with under- 2.3.8 Large scale operations of working face
ground belt conveyor to simplify surface preparation In China, the traditional advance length on high pro-
system.Yujialiang mine shortened construction period duction and efficient mechanized face is mostly about
with such arrangement. 2000 m; the longest is not beyond 3000 m with gen-
eral face length of 150 m200 m. For instance, 2211
first mining face is of advance length 1500 m with
2.3.4 Inclined tunnel development mode
face length 180 m in Bulianta mine and the advance
When designing mine, taking the advantage condition
length on mechanized face is 1300 m with face length
of coal seam into account and adopting new inclined
150 m in Wulanmulun mine. Under the situation of
tunnel development method, the main entry is arranged
ascendant seam condition, to exert sufficiently the
in seam to not or less drive rock tunnel as possible.
advantage of efficiency of introduced mechanized
Shaft directly gets through master entry in seam to
equipment, continuous miner faster driving and quick
eliminate station underground. The development mas-
conveyance of trackless vehicle, to reduce the move-
ter entry consists of one main conveying, 12 ancillary
ment of face, the working face parameter is carried
conveying and one air return entry to simplify main
out breaking through. Working face advance length is
and ancillary conveyance and ventilation system.
increased to 40006000 m with face length 220240 m
and minable coal 5,000,000 t8,000,000 t. The first
2.3.5 Ancillary conveyance with trackless rubber face advance length is 3730 m with late on length
tire vehicle 4211 m in Yujialiang mine and the late on mechanized
Personnel, material and equipment, even hydraulic face advance length is 5000 m with face length 240 m
support with complete weight of 30 t is transported in Bulianta mine.
directly from surface to working face. It carries out
continuity of ancillary conveyance and increases the
efficiency of ancillary conveyance with less interme- 2.3.9 Remote power supply of surface box
diate transferring link, convenient loading and unload- transformer assorted with mobile transformer
ing, fast speed, high ability, low cost and reliable underground
safety. Traditional mine power supply not only need build cen-
tral transformer station underground, but also need
build transformer station in panel. No matter mine
2.3.6 Continuous miner quick driving and bolt
construction engineering or installation engineering is
support
larger. Remote power supply method of surface box
With advanced continuous miner and its corollary
transformer assorted with mobile transformer under-
equipment as base, large section full coal entry bolt
ground reduces power supply links, depresses fault,
support technique and double entry layout form of
ensures the normal power supply request to mining and
conveyance and air return ensure driving and support-
driving machine, supplies the reliable power supply
ing parallel operation, satisfy the ventilation require-
for quick construction. There is no any underground
ment to long distance large section driving and attain
central transformer station and transformer station in
continuous miner quick driving.
panel, surface box transformer supply 10 KV to under-
ground mobile transformer directly. During the period
2.3.7 Non-panel layout of construction, there is only a simple transformer
The incline tunnel development method, trackless station in seam entry. This reduces the amount of engi-
ancillary conveyance and the solution of long large neering of building underground chamber, shortens
section driving, boost layout reformation of prepar- construction period of supply system and saves capital.
ing and gateway from traditional panel entry to main
entry with banding arrangement. Extracting face gets
to edge of coal field directly without panel and prepar-
ing entry. The traditional three stages division design 3 CONCLUSION
of mine panel (mining area) working face is
reformed to two stages of mine face to simplify Proven in practice recent years, based on key tech-
mine system and save shaft sinking and drifting. For niques such as incline tunnel development, trackless
example, Huojitu mine entirely cancels original 5 pan- ancillary conveyance, non-panel layout, continuous
els, face is layout along both side of main entry, the miner fast driving and bolt support, the quick mine
boundary of coal field is working face cutting eye with construction model in Shendong has been mature.
less driving preparing entry of 20000 m; From the time With the application in Shendong , it has not only cre-
of design, Yujialiand mine adopts non-panel layout. ated miracle one by one in world mine construction
After the entry formed of shaft and main entry, work- history, but also will greatly affect mine construction
ing face is directly arranged so as to decrease entry in China, so as to promote our coal industry develop
engineering and shorten construction period. at a certain extent.

526

Copyright 2004 Taylor & Francis Group plc, London, UK