Sie sind auf Seite 1von 1

Drawings Review Check List DOC ID:

DCL-<P.Num>-<YYMMDD>-nnnn
<YYMMDD>-nnnn

Part / Drawing description: Part / Drawing No.: Rev.

No Check / Action Check Deviation / Finding Fixed /


V, X, NA Rej.

ENGINEERING CHECKS
E1 Make sure that all required information is available
E1.1 - Mechanical
E1.2 - Electrical
E1.3 - Environmental
E1.4 - Materials + Finish + relevant standards
E1.5 - Other [ ]
E2 Check the design for interference issues
Check the design for components assembly and
E3 disassembly functionality.
Check the design for stress and strain when
E4 considerable force is to be applied.
E5 Conduct thermal analysis, if applicable.
Check that the general tolerance matches the part
E6 design style
Ensure manufacturability and maintainability
E7 considerations are addressed
E8 Any jigs needed to test the part?
E9 Any tests performed to verify the change?

GENERAL CHECKS
G1 Revision complies with required revision?
G2 Title is correct, same as in PDM / SAP / BOM
G3 Revision table is complete with DCN details
G4 Pack and Bag note exists? Is correct?
G5 Relevant standards are called out correctly?
G6 Interference issues between parts were resolved?
G7 Scale in the block matches the actual views scale?

PART DRAWINGS
P1 Material and finish are defined?
P2 Dimension balloons exists?
P3 No duplicate dimensions?
General Tolerance is defined and reasonable for the
P4 part
P5 For jigs is the P/N engraved on the part?

Summary / Result: Inspected / checked by: Signature:


PASS Date:

FAIL Corrected by:

Other Verified by:

Checklist ID: GD000000-15-7654 Rev: A Page: 1 of 1