XYZ Page 1 of 2

QC~PLAN.
Project No. & Name: Equipment Pre- Commissioning/ Commi
Name of Client/ Consultant: Doc. No.M & E QC~Plan- 03
SL. ACTIVITY CONTROLLING NATURE & EXTENT ACCEPTANCE CRITERIA PERSON RESP.
No. DOCUMENT OF INSP./TEST AT LOCATION
1 Chilled water pump Manufacturer instrucVisual / Physical Chilled water piping should be Engineer /
testing tion and contract verification, 100% completed and flushing should Foremen/
specification. be done. Required flow of water Quality Engineer
shall be adjusted and achieved.
2 Fan Coil Unit Manufacturer Physical verification, Unit installation should be as Engineer /
testing instruction and 100% per manufacturer instruction Foremen/
contract and approved shop drawing. Quality Engineer
specification Final connection of all required
services should be completed.
3 Air - Balancing Specificaton, Physical and visual All equipment and Air outlets Engineer /
Drawings, verification 100% shall be installed and should Foremen/
Manufacturer - be as per approved shop Quality Engineer
recommendation & drawing.
ASHRAE standard.
4 Split Unit testing specification. Physical verification, Unit installation should be as Engineer /
Manufacturer - 100% per manufacturer instruction Foremen/
recommendation & and contract specification and Quality Engineer
ASHRAE standard. ASHRAE standard.
5 Final inspection specification. Visual / Physical - As per Manufacturer's instructions Engineer /
Manufacturer - verification, 100% and Contract Specifications and Foremen/
recommendation & ASHRAE standard. Quality Engineer
ASHRAE standard.

Work Location: Quality Engineer: Engineer / Foremen:


Remarks: Date: Date:

349628769.xls Date: January 26, 2001


XYZ Page 2 of 2

QC~PLAN.
Equipment Pre- Commissioning/ Commissioning
Doc. No.M & E QC~Plan- 037/ REV. 0
RECORD

Pump test report


M & E QC~Form- 038-03/ REV.0

Fan Coil Unit Test Report.


M & E QC~Form- 039-01/ REV.0

Air-Balancing Report.
M & E QC~Form- 038-04/ REV.0

Split Unit Test report.


M & E QC~Form- 039-04/ REV.0

Inspection reports
M & E QC~Form- 038-01/ REV.0
M & E QC~Form- 038-02/ REV.0
M & E QC~Form- 039-02/ REV.0
M & E QC~Form- 039-03/ REV.0

349628769.xls Date: January 26, 2001