Sie sind auf Seite 1von 1

Claims and Disputes 331

Contractor 1. Noncompliance with specifications valuable tools for the defense of a claim are properly pre-
2. Schedule updates not done pared CPM schedules.
Delays are the most prevalent problem on construction
3. Reluctance to cooperate and
projects. A variety of factors in an ongoing project can lead
coordinate
to a delay. Typical types of delays that might be caused by an
4. Failure to meet milestone dates owner include the following:
5. Not following permit requirements
1. Late approval of shop drawings and samples
2. Late approval of laboratory tests
3. Delays in answers to field inquiries by the contractor
Compensable versus Noncompensable 4. Changes in the contractors method of doing the work
Delays 5. Variation in estimated quantities
6. Interference with the contractor during construction
A delay that is considered compensable is one where the
7. Owner-caused schedule changes
owner has failed to meet an obligation stated or implied in
the construction contract. If a delay is considered com- 8. Design changes
pensable, the owner must grant a time extension and reim- 9. Changes in inspection level
burse the contractor for the increased cost caused by the 10. Failure to provide for site access
delay. If a contractor experiences concurrent delays where 11. Lack of required rights-of-way
one is compensable and the other is merely excusable, no 12. Interference by other contractors or owners forces
compensation is allowed. Similarly, on concurrent delays
where one is caused by the contractor and the other by the A contractor may jeopardize its claim, however, by
owner, the delay is considered neither excusable nor com- being the cause of nonexcusable delays of its own. Such
pensable to the extent of the overlap or concurrency delays are frequently the result of any of the following
[Appeal of Rivera General Contracting, ASBCA No. 25888 causes:
(April 30, 1985)]. It should be stressed that these defini-
tions are general in nature. The parties have great latitude 1. Late submittal of shop drawings
to contractually determine whether or not the contractor 2. Late procurement of materials or equipment
will be entitled to additional compensation, an extension 3. Insufficient personnel
of time, or nothing at all. 4. Unqualified personnel
If an event delays an activity on the critical path, the 5. Inadequate coordination of subcontractors or other
project completion date will be delayed. To avoid delay, it is contractors
necessary to accelerate the performance of a subsequent crit-
6. Subcontractor delays
ical activity or adjust the sequence of work activities to com-
pensate for the delay. If a delay occurs to an activity not on 7. Late response to owner and architect/engineer inquiries
the critical path, however, the impact is cushioned by the 8. Construction not conforming to contract requirements,
available free-float time. Delays to a noncritical activity, making repeated reworking necessary
which do not exceed the amount of free-float for that activ-
ity, will not result in a delay to the completion date of a pro-
ject. If, however, a delay to a noncritical activity directly
Attendance at Site Visit
caused an increase in the contractors costs, such costs may From time to time, owners and architect/engineers feel that
be recovered by the contractor if the delay was the owners they will better protect the owners interests by requiring all
responsibility. This, of course, is a matter requiring very clear bidders to attend a prebid site visit. This is obviously based
proof to overcome the presumption that delays to noncriti- upon the presumption that the contractor might have a
cal activities do not result in delay-related costs. Although an stronger claim for differing site conditions if he or she failed
owner-caused delay to a noncritical activity that used only to attend a scheduled prebid site tour. However, it appears
free-float time may not be a justification for an extension of that the owner may not be as vulnerable as at first thought.
time, such delays may still be compensable when they cause In a 1986 case, the Comptroller General ruled that a con-
the contractor to accelerate the work, cause inefficiency or tractors failure to attend a prebid site visit is not a valid rea-
disruption, or delay some specific activity and thus cause son to reject an otherwise acceptable low bid [Matter of
extended costs, such as cost of equipment rental. In addition, Arrowhead Construction, Inc., Comp. Gen. No. B-220386
such delay is not necessarily measured from the time that the (January 8, 1986)].
contract documents required the project to be completed, In the subject case, the government requested bids for
but rather from the time that the contractor could have construction of a paint booth. The Notice Inviting Bids
completed the project, from a completion date earlier than required all bidders to attend a site visit on a designated date.
the one indicated in the contract documents [Metropolitan When the government announced its intention to award the
Paving Co. v. United States, 325 F.2d 241 (1963)]. The most contract to a bidder that did not attend the site visit, the

Das könnte Ihnen auch gefallen