Beruflich Dokumente
Kultur Dokumente
km 35 + 481
805 m
and Halle/Saale, the new federal mo-
km 36 + 286
65 180 56 56 56 56 56 56 56 56 56 46
torway (Bundesautobahn) A14 crosses
the river Saale and its adjacent flood
tioning
to Halle (Beesedau) to Magedburg
parti-
pier
plain near Bernburg near the village of
Beesedau. This bridge is 805 m-long Saale River
and is the longest structure along the
Top view
A14. Construction began in 1998 and
was completed in 2000.
R
=
The construction is divided into a 310 35
0
r
m-long river bridge and the 495 m-long
ve
Ri
foreshore bridge (Fig. 1). The gradient
A = 2000 m
A = 810
A = 810
ranges from a height of around 11 m to
R=
Saale
vibration
Bridge damper
60
are as follows:
900 900
Bogenachse
1200
~30
1800
19
zur
unmistakable character
10 10
20 t
0 R
the arch, because its structural ele- ~
250
1.70 1.40
2.5% 4% 2.5%
1.36 1.40
0.00 6.5% 0.00 4%
ly lifted into place by a 500-t mobile
R = 62.50
crane. Finally, the 46-m and 270-t mid-
30.00 75 75 75
3.10
75
A dle section of the arch was installed.
3.50 6.50 3.50 3.50 6.50 3.50 This middle section was welded to-
2.5% 2.5%
2.26 7.50 7.50 7.50 7.50 2.26 gether from 4 segments and 4 cross-
View A bars on a pontoon nearby and then
shipped to the construction site. The
pontoon was then turned sideways and
brought into position; the middle sec-
1.10
20.30 20.30
13.20 13.20
tion was lifted into place to connect
with the four ends of the arches by
Fig. 3: Cross section of bridge stranded wire pulleys.
attach to projecting bracket-like trans- partitioning pier (Fig. 5) was deliber-
verse beams. The suspension roads lie ately designed as a massive, solid slab.
in the plain of the arch and consist of The outer sides are bevelled in a point-
steel rounds with a circumference of ed surface, and their diagonal slope of
180 and 200 mm. The transverse beams 4:1 corresponds to the incline of the
for the suspenders are sickle-shaped in arch. The benchmark for the foreshore
order to emphasise the axial support. bridge was established at the pier be-
Conical cover plates form the end of cause of its massive structure. The lo-
the transverse beams and serve also as cation of the partitioning pier is em-
joint plates for the suspension rods. phasised for drivers by a small crows
nest. In accordance with the design
concept of the A14 the connecting
Foreshore Bridge pier is coated on the outer sides with Fig. 5: Dividing pier and regular piers
porphyry and on the inner sides with
A continuous beam was selected for a more economical brickwork in a Construction of the Composite
the foreshore bridge and consists of matching colour.
9 segments with the dimensions of 8
Steel Deck
The regular piers (Fig. 5) are specially
56 m and 1 46 m. The total length is
designed concrete slabs with large
495 m. The superstructure consists of The stiffening girders were transport-
openings. The diagonal slope of 4:1 is
2 concrete longitudinal and transverse ed by truck to the pre-construction site
adopted from the connecting pier and
prestressed one-celled hollow box behind abutment 0. Delivered in pre-
continued. The exposed surfaces of the
girders. The construction height was construction units divided lengthwise
regular piers consist of face-mix con-
set at 3.1 m corresponding to the main down the centre, the girders were weld-
crete in a formwork construction.
bridge. This results in a statically bene- ed together and prepared for position-
ficial and economical slenderness of ing. The uniform segments were approx-
L/H = 18. Construction of the Arches imately 22 m. Transfer was done via
4 props (arch props which had been
The arches were built (Fig. 6) by means partially taken down) and 2 installa-
Piers of 7 props, which were in some cases tion stations along with the installation
taken down after the successful partial station at the abutment 0. The two
The separation between the river construction of the arch. First, the adjacent steel stiffening girders were
bridge and the foreshore bridge is em- bases of the arches were measured, ad- inserted in a tandem push by a tension
phasised by the partitioning pier. The justed, and encased in concrete. Then, rail, which was installed along the main
The roadway was cast in 13 segments Fig. 7: Formwork carriage and foreshore bridge
in concrete, each with a length of
approximately 25 m. To minimise the Construction of the Foreshore In 2000, the completed motorway be-
tensions within the roadway surface, Bridge tween Magdeburg and Halle was
the segments were cast from the mid- opened to traffic. The Beesedau/Saale
dle of the section and the abutment Bridge forms a striking accent within
To construct the foreshore bridge a
towards the ends of the arch. the landscape and can be seen from
transfer carriage was employed (Fig. 7).
kilometers around (Fig. 8).
The transfer carriage was supported
on the span supports of the piers as
Damping the Vibration of the well as in the middle of the section.
Suspension Rails This was favourable for the deforma-
tion conditions during the construction
To prevent vibration induced by wind of the superstructure. For lengthwise
and rain, liquid-filled vibration dampers transfer the carriage was separated in
SEI Data Block
were installed. The size and number the middle, pulled apart, and trans-
of the damping units was determined ported to the next forward position. Owner:
by oscillation measurements taken on DEGES on behalf of Saxony-Anhalt
Concrete was poured section by sec-
the completed structure. Through the and Federal Republic of Germany
tion. The connection occurred at ap-
oscillation measurements, the natural
proximately L/5. During the pouring Tender design:
oscillation and damping decrement of
of concrete the transfer carriage was Schssler-Plan, Berlin, Prof. Laage u.
the individual suspension rods were
hung on the previously concreted seg- Partner, Hamburg
determined. Based on previous ex-
ment of the superstructure. The con- Execution design:
perience and model projections the
struction of the superstructure was Planungsgesellschaft Nord-West GmbH,
required damping decrements were
done in two-week cycles. Hannover, Dr. Schtz, Kempten
calculated, and the final number and
dimensions of the dampers were deter- The superstructure was concreted in Test engineer:
mined. Finally, in-situ measurements two sections, each approximately 350 m3. Prof. Dr.-Ing. U. Weyer, Dortmund
demonstrated the actual damping ca- First, the trough was poured, and then
Contractor:
pacity and the effectiveness of the about a week later, the roadway plates
ARGE Saalebrcke Beesedau
dampers was confirmed. were cast in concrete.
Dyckerhoff and Widmann AG, Magdeburg
Teerbau, Oebisfelde
Krupp Stahlbau Hannover GmbH
River bridge:
Steel (t): 4500
Concrete (m3): 3600
Concrete steel (t): 970
Foreshore bridge:
Concrete (m3): 11 600
Concrete steel (t): 1250
Prestressing steel (t): 490
Substructure:
Concrete (m3): 14 500
Concrete steel (t): 1170
Cost (USD millions): 29
Service date: 2000
Fig. 8: View of new Saale Bridge, Beesedau