Sie sind auf Seite 1von 3

Bridge across the River Saale, Beesedau, Germany

Winfried Glitsch, Civil Eng. DEGES, Berlin, Germany

Introduction General view

About halfway between Magdeburg

km 35 + 481
805 m
and Halle/Saale, the new federal mo-

km 36 + 286
65 180 56 56 56 56 56 56 56 56 56 46
torway (Bundesautobahn) A14 crosses
the river Saale and its adjacent flood

tioning
to Halle (Beesedau) to Magedburg

parti-

pier
plain near Bernburg near the village of
Beesedau. This bridge is 805 m-long Saale River
and is the longest structure along the
Top view
A14. Construction began in 1998 and
was completed in 2000.
R
=
The construction is divided into a 310 35
0

r
m-long river bridge and the 495 m-long

ve
Ri
foreshore bridge (Fig. 1). The gradient

A = 2000 m
A = 810
A = 810
ranges from a height of around 11 m to

R=
Saale

14 m over the site. At the bridge it in- intended expansion


dicates a longitudinal decline of 0.5% of the river Saale
towards the southeast. The river bridge
is laid out in a straight line, but de-
velops into a clothoid at the foreshore Fig. 1: Elevation and plan view
bridge.
View of the river bridge

vibration
Bridge damper

During the design process various


structures, including a deck bridge, a
tied arch bridge, a cable-stayed bridge, 19.00 13.02 17.58 9 13.20 = 118.80 17.58 13.02 19.00
and a true arch bridge with angled
piers were examined and compared 180.00 m
through computer simulation.
Arch cross section at the suspension rods Arch cross section at the crown
A true arch bridge with angled piers
1800
~40

was selected (Fig. 2). The main reasons 1800


~30

60
are as follows:
900 900
Bogenachse

1200
~30
1800

19
zur

the arch further the tradition of the


~30

existing old arch bridges over the


25
River Saale
variabel

its unusual form lends it a distinctive, Vibration damper


(Outer dimensions)
250

unmistakable character
10 10
20 t

driver can consciously experience 160 t


500

0 R
the arch, because its structural ele- ~
250

ments lie above the roadway. 180 ~


420
Fig. 2: Longitudinal section of bridge ~
180
The arched construction consists of
two outer reinforced arched plains in-
At the crossbars the width of the arch angled piers, channel back some of this
clining towards each other and secured
is a constant 1.8 m; from there to the force to the roadway surface.
with 6 crossbars. The roadway surface
base of the arch it widens to 3.6 m. The
is continuous and consists of separate The arches and angled piers are each
box width of the arch girders is a con-
hollow-box girders in composite-steel connected at the intersections with
stant 1.6 m. Angled piers are added at
construction with a height of 3.1 m the roadway through bend- and tor-
the lower extensions of the arch. These
(Fig. 3). The arch spans 180 m with sion-resistant box girders and are thus
provide additional structural support
a height of 38 m; the arch form was connected with one another (Fig. 4).
for the hollow box girders in the pe-
developed from a square parabola.
ripheral segments. The force of the The roadway is joined to the arches
arches is directed through the founda- through 10 suspension rods set apart
tion and straight into the ground. The at a distance of 13.2 m. The suspenders

234 Recent Bridges in Germany Structural Engineering International 4/2002


Cross section starting from the bases, the arch was
15.00 15.00
2.00 11.50 11.50 2.00
built up in segments with the help of
1.50 1.50 props. Individual segments were 20 m
to 25 m in length and had a weight of
4% A 120 t. These segments were individual-

1.70 1.40
2.5% 4% 2.5%

1.36 1.40
0.00 6.5% 0.00 4%
ly lifted into place by a 500-t mobile
R = 62.50
crane. Finally, the 46-m and 270-t mid-
30.00 75 75 75
3.10
75
A dle section of the arch was installed.
3.50 6.50 3.50 3.50 6.50 3.50 This middle section was welded to-
2.5% 2.5%
2.26 7.50 7.50 7.50 7.50 2.26 gether from 4 segments and 4 cross-
View A bars on a pontoon nearby and then
shipped to the construction site. The
pontoon was then turned sideways and
brought into position; the middle sec-

1.10
20.30 20.30
13.20 13.20
tion was lifted into place to connect
with the four ends of the arches by
Fig. 3: Cross section of bridge stranded wire pulleys.
attach to projecting bracket-like trans- partitioning pier (Fig. 5) was deliber-
verse beams. The suspension roads lie ately designed as a massive, solid slab.
in the plain of the arch and consist of The outer sides are bevelled in a point-
steel rounds with a circumference of ed surface, and their diagonal slope of
180 and 200 mm. The transverse beams 4:1 corresponds to the incline of the
for the suspenders are sickle-shaped in arch. The benchmark for the foreshore
order to emphasise the axial support. bridge was established at the pier be-
Conical cover plates form the end of cause of its massive structure. The lo-
the transverse beams and serve also as cation of the partitioning pier is em-
joint plates for the suspension rods. phasised for drivers by a small crows
nest. In accordance with the design
concept of the A14 the connecting
Foreshore Bridge pier is coated on the outer sides with Fig. 5: Dividing pier and regular piers
porphyry and on the inner sides with
A continuous beam was selected for a more economical brickwork in a Construction of the Composite
the foreshore bridge and consists of matching colour.
9 segments with the dimensions of 8
Steel Deck
The regular piers (Fig. 5) are specially
56 m and 1 46 m. The total length is
designed concrete slabs with large
495 m. The superstructure consists of The stiffening girders were transport-
openings. The diagonal slope of 4:1 is
2 concrete longitudinal and transverse ed by truck to the pre-construction site
adopted from the connecting pier and
prestressed one-celled hollow box behind abutment 0. Delivered in pre-
continued. The exposed surfaces of the
girders. The construction height was construction units divided lengthwise
regular piers consist of face-mix con-
set at 3.1 m corresponding to the main down the centre, the girders were weld-
crete in a formwork construction.
bridge. This results in a statically bene- ed together and prepared for position-
ficial and economical slenderness of ing. The uniform segments were approx-
L/H = 18. Construction of the Arches imately 22 m. Transfer was done via
4 props (arch props which had been
The arches were built (Fig. 6) by means partially taken down) and 2 installa-
Piers of 7 props, which were in some cases tion stations along with the installation
taken down after the successful partial station at the abutment 0. The two
The separation between the river construction of the arch. First, the adjacent steel stiffening girders were
bridge and the foreshore bridge is em- bases of the arches were measured, ad- inserted in a tandem push by a tension
phasised by the partitioning pier. The justed, and encased in concrete. Then, rail, which was installed along the main

Fig. 4: Angled base with angled piers Fig. 6: Arch construction

Structural Engineering International 4/2002 Recent Bridges in Germany 235


axis of the structure. The maximum
distance supported during the transfer
was 66 m. During the transfer over the
River Saale, the sickle-shaped trans-
verse stiffening girders were hung and
locked in their future positions. A stroke
lever was employed in order to miti-
gate the bending of the cantilever arm
and to ensure and secure arrival at the
first installation station.

Simultaneously, the suspension rods


were built and adjusted, first at the
arch, after complete positioning and
installation of the cross beams and also
at the cross beam plates.

The roadway was cast in 13 segments Fig. 7: Formwork carriage and foreshore bridge
in concrete, each with a length of
approximately 25 m. To minimise the Construction of the Foreshore In 2000, the completed motorway be-
tensions within the roadway surface, Bridge tween Magdeburg and Halle was
the segments were cast from the mid- opened to traffic. The Beesedau/Saale
dle of the section and the abutment Bridge forms a striking accent within
To construct the foreshore bridge a
towards the ends of the arch. the landscape and can be seen from
transfer carriage was employed (Fig. 7).
kilometers around (Fig. 8).
The transfer carriage was supported
on the span supports of the piers as
Damping the Vibration of the well as in the middle of the section.
Suspension Rails This was favourable for the deforma-
tion conditions during the construction
To prevent vibration induced by wind of the superstructure. For lengthwise
and rain, liquid-filled vibration dampers transfer the carriage was separated in
SEI Data Block
were installed. The size and number the middle, pulled apart, and trans-
of the damping units was determined ported to the next forward position. Owner:
by oscillation measurements taken on DEGES on behalf of Saxony-Anhalt
Concrete was poured section by sec-
the completed structure. Through the and Federal Republic of Germany
tion. The connection occurred at ap-
oscillation measurements, the natural
proximately L/5. During the pouring Tender design:
oscillation and damping decrement of
of concrete the transfer carriage was Schssler-Plan, Berlin, Prof. Laage u.
the individual suspension rods were
hung on the previously concreted seg- Partner, Hamburg
determined. Based on previous ex-
ment of the superstructure. The con- Execution design:
perience and model projections the
struction of the superstructure was Planungsgesellschaft Nord-West GmbH,
required damping decrements were
done in two-week cycles. Hannover, Dr. Schtz, Kempten
calculated, and the final number and
dimensions of the dampers were deter- The superstructure was concreted in Test engineer:
mined. Finally, in-situ measurements two sections, each approximately 350 m3. Prof. Dr.-Ing. U. Weyer, Dortmund
demonstrated the actual damping ca- First, the trough was poured, and then
Contractor:
pacity and the effectiveness of the about a week later, the roadway plates
ARGE Saalebrcke Beesedau
dampers was confirmed. were cast in concrete.
Dyckerhoff and Widmann AG, Magdeburg
Teerbau, Oebisfelde
Krupp Stahlbau Hannover GmbH

River bridge:
Steel (t): 4500
Concrete (m3): 3600
Concrete steel (t): 970
Foreshore bridge:
Concrete (m3): 11 600
Concrete steel (t): 1250
Prestressing steel (t): 490
Substructure:
Concrete (m3): 14 500
Concrete steel (t): 1170
Cost (USD millions): 29
Service date: 2000
Fig. 8: View of new Saale Bridge, Beesedau

236 Recent Bridges in Germany Structural Engineering International 4/2002

Das könnte Ihnen auch gefallen