Sie sind auf Seite 1von 21

ADR CASES 02-07-17 While blasting commenced on October 6, 1992, NPC and FUCC

were discussing the propriety of an extra work order and if such


SECOND DIVISION is in order, at what price should FUCC be paid.

[G.R. No. 148318. November 22, 2004.] Sometime in March 1993, NPC Vice President for Engineering
Construction, Hector Campos, created a task force to review
NATIONAL POWER CORPORATION, petitioner, vs. HON. FUCC's blasting works. The technical task force recommended
ROSE MARIE ALONZO-LEGASTO, as Presiding Judge, RTC that FUCC be paid P458.07 per cubic meter as such being the
of Quezon City, Branch 99, JOSE MARTINEZ, Deputy price agreed upon by FUCC.
Sheriff, RTC of Quezon City, CARMELO V. SISON, Chairman,
Arbitration Board, and FIRST UNITED The matter was further referred to the Department of Public
CONSTRUCTORSCORPORATION, respondents. [W]orks and Highways (DPWH), which in a letter dated May 19,
1993, recommended the price range of P500.00 to P600.00 per
DECISION cubic meter as reasonable. It further opined that the price of
P983.75 per cubic meter proposed by Lauro R. Umali, Project
TINGA, J p:
Manager of BACMAN II was high. A copy of the DPWH letter is
National Power Corporation (NPC) filed the instant Petition for attached as Annex "C", FUCC's Exhibit EEE-Arbitration.
Review 1 dated July 19, 2001, assailing the Decision 2 of the
In a letter dated June 28, 1993, FUCC formally informed NPC
Court of Appeals dated May 28, 2001 which affirmed with
that it is accepting the proposed price of P458.07 per cubic
modification the Order 3 and Writ of Execution 4 respectively
meter. A copy of the said letter is attached as Annex "D", FUCC's
dated May 22, 2000 and June 9, 2000 issued by the Regional
Exhibit L Arbitration.
Trial Court. In its assailedDecision, the appellate court declared
respondent First United Constructors Corporation (FUCC) In the meantime, by March 1993, the works in Botong area were
entitled to just compensation for blasting works it undertook in in considerable delay. By May 1993, civil works in Botong were
relation to a contract for the construction of power facilities it kept at a minimum until on November 1, 1993, the entire
entered into with petitioner. The Court of Appeals, however, operation in the area completely ceased and FUCC abandoned
deleted the award for attorney's fees having found no basis the project.
therefor.
Several written and verbal warnings were given by NPC to
The facts culled from the Decision of the Court of Appeals are FUCC. On March 14, 1994, NPC's Board of Directors passed
undisputed: Resolution No. 94-63 approving the recommendation of
President Francisco L. Viray to take over the contract. President
On April 14, 1992, NPC and FUCC entered into a contract for the
Viray's recommendation to take over the project was compelled
construction of power facilities (civil works) Schedule 1
by the need to stave-off huge pecuniary and non-monetary
1x20 MW Bacon-Manito II Modular Geothermal Power Plant
losses, namely:
(Cawayan area) and Schedule 1A 1x20 MW Bacon-Manito II
Modular Geothermal Power Plant (Botong area) in Bacon, (a) Generation loss estimated to be at P26,546,400/month;
Sorsogon (BACMAN II). The total contract price for the two
schedules is P108,493,966.30, broken down as follows: (b) Payment of steam penalties to PNOC-EDC the amount
estimated to be at P10,206,048.00/month;
SCHEDULE
(c) Payment of liquidated damages due to the standby of
1 Cawayan area P52,081,421.00 electromechanical contractor;

1A Botong area P56,412,545.30 (d) Loss of guaranteed protection (warranties) of all delivered
plant equipment and accessories as Mitsubishi Corporation,

electromechanical contractor, will not be liable after six months


P108,493,966.30 of delivery.

Appended with the Contract is the contract price schedule which To prevent NPC from taking over the project, on March 28, 1994,
was submitted by the respondent FUCC during the bidding. The FUCC filed an action for Specific Performance and Damages
price for grading excavation was P76.00 per cubic meter. with Preliminary Injunction and Temporary Restraining Order
before Branch 99, Regional Trial Court, Quezon City.
Construction activities commenced in August 1992. In the latter
part of September 1992 and after excavating 5.0 meters above Under paragraph 19 of its Complaint, FUCC admitted that it
the plant elevation, FUCC requested NPC that it be allowed to agreed to pay the price of P458.07 per cubic meter.
blast to the design grade of 495 meters above sea level as its
On April 5, 1994, Judge de Guzman issued a temporary
dozers and rippers could no longer excavate. It further requested
restraining order and on April 21, 1994, the trial court resolved to
that it be paid P1,346.00 per cubic meter similar to the rate of
grant the application for issuance of a writ of preliminary
NPC's project in Palinpinon.
injunction.
On July 7, 1994, NPC filed a Petition for Certiorari with Prayer for Complaint and Amended Complaint from the RTC, Br. 99 of
Temporary Restraining Order and Preliminary Injunction before Quezon City;
the First Division of the Court of Appeals asserting that no
injunction may issue against any government projects pursuant 5. Upon final resolution of the Arbitration, as hereunder
to Presidential Decree 1818. HCITAS prescribed, the parties shall immediately execute the proper
documents mutually terminating Plaintiff's contract for the civil
On July 8, 1994, the Court of Appeals through then Associate works of the BACMAN II Project (Contract No. Sp90DLM-918 (I
Justice Bernardo Pardo issued a temporary restraining order and & A);
on October 20, 1994, the said court rendered a Decision
granting NPC's Petition for Certiorari and setting aside the lower 6. Such mutual termination of Plaintiff's contract shall have the
court's Order dated April 21, 1994 and the Writ of Preliminary following effects and/or consequences: (a) the construction
Injunction dated May 5, 1994. works of Plaintiff at the Kawayan and Bolong sites, at its present
stage of completion, shall be accepted and/or deemed to have
However, notwithstanding the dissolution by the Court of Appeals been accepted by defendant; (b) Plaintiff shall have no more
of the said injunction, on July 15, 1995, FUCC filed a Complaint obligation to Defendant in respect of the BACMAN II Project
before the Office of the Ombudsman against several NPC except as provided in clause (e) below; (c) Defendant shall
employees for alleged violation of Republic Act No. 3019, release all retention moneys of plaintiff within a maximum period
otherwise known as the Anti-Graft and Corrupt Practices Act. of thirty (30) days from the date of final Resolution of the
Together with the complaint was an Urgent Ex-Parte Motion for Arbitration; (d) no retention money shall thenceforth be withheld
the issuance of a cease and [d]esist [o]rder to restrain NPC and by Defendant in its payment to Plaintiff under this Compromise
other NPC officials involved in the BACMAN II project from Agreement, and (e) Plaintiff shall put up a one-year guaranty
canceling and/or from taking over FUCC's contract for civil works bond for its completed civil works at the Kawayan site,
of said project. retroactive to the date of actual use of the plant by defendant;

Then on November 16, 1994, FUCC filed before the Supreme 7. Plaintiff's blasting works claims and other unresolved claims,
Court a Petition for Review assailing the Decision of the Court of as well as the claims of damages of both parties shall be settled
[A]ppeals dated October 20, 1994. In its Comment, NPC raised through a two stage process to wit:
the issue that FUCC resorted to forum shopping as it applied for
a cease and desist order before the National Ombudsman STAGE 1
despite the dissolution of the injunction by the Court of Appeals.
7.1 Plaintiff and Defendant shall execute and sign this
Pending the petition filed by FUCC before the Supreme Court, Compromise Agreement which they will submit for approval by
on April 20, 1995 the NPC and FUCC entered into a this Court. Under this Compromise Agreement both parties
Compromise Agreement. agree that:

Under the Compromise Agreement, the parties agreed on the xxx xxx xxx
following:
STAGE 2
1. Defendant shall process and pay the undisputed unpaid
billings of Plaintiff in connection with the entire project fifteen (15) 7.1 The parties shall submit for arbitration to settle: (a) the price
days after a reconciliation of accounts by both Plaintiff and of blasting, (b) both parties' claims for damages, delays,
Defendant or thirty (30) days from the date of approval of this interests, and (c) all other unresolved claims of both parties,
Compromise Agreement by the Court whichever comes first. including the exact volume of blasted rocks;
Both parties agree to submit and include those accounts which
7.2 The arbitration shall be through a three-member commission
could not be reconciled among the issues to be arbitrated as
to be appointed by the Honorable Court. Each party shall
hereunder provided;
nominate one member. The Chairman of the Arbitration Board
2. Plaintiff accepts and acknowledges that Defendant shall have shall be [a] person mutually acceptable to both parties,
the right to proceed with the works by re-bidding or negotiating preferably from the academe;
the project immediately upon the signing of herein Compromise
7.3 The parties shall likewise agree upon the terms under which
Agreement;
the arbitrable issues shall be referred to the Arbitration Board.
3. This Compromise Agreement shall serve as the Supplemental The terms of reference shall form part of the Compromise
Agreement for payment of plaintiff's blasting works at the Botong Agreement and shall be submitted by the parties to the
site; Honorable Court within a period of seven (7) days from the
signing of the Compromise Agreement;
4. Upon approval of this Compromise Agreement by the Court or
Plaintiff's receipt of payment of this undisputed unpaid billings
from Defendant whichever comes first, the parties shall
7.4 The Arbitration Board shall have a non-extendible period of
immediately file a Joint Manifestation and Motion for the
three (3) months within which to complete the arbitration process
withdrawal of the following Plaintiff's petition from the Supreme
and submit its Decision to the Honorable Court;
Court, Plaintiff's Complaint from the National Ombudsman, the
7.5 The parties agree that the Decision of the Arbitration Board The Court of Appeals gave primacy to the court-approved
shall be final and executory; Compromise Agreement entered into by the parties and
concluded that they intended the decision of the arbitration panel
7.6 By virtue of this Compromise Agreement, except as herein to be final and executory. Said the court:
provided, the parties shall mutually waive, forego and dismiss all
of their other claims and/or counterclaim in this case. Plaintiff For one, what the price agreed to be submitted for arbitration are
and defendant warrant that after approval by the Court of this pure issues of fact (i.e., the price of blasting; both parties' claims
Compromise Agreement neither party shall file Criminal or for damages, delay, interests and all other unresolved claims of
Administrative cases or suits against each other or its Board or both parties, including the exact volume of blasted rocks). Also,
member of its officials on grounds arising from the case. the manner by which the Arbitration Board was formed and the
terms under which the arbitrable issues were referred to said
The Compromise Agreement was subsequently approved by the Board are specified in the agreement. Clearly, the parties had left
Court on May 24, 1995. to the Arbitration Board the final adjudication of their remaining
claims and waived their right to question said Decision of the
The case was subsequently referred by the parties to the Board. Hence, they agreed in clear and unequivocal terms in the
arbitration board pursuant to their Compromise Agreement. On Compromise Agreement that said Decision would be
December 9, 1999 the Arbitration Board rendered its ruling the immediately final and executory. Plaintiff relied upon this
dispositive portion of which states: stipulation in complying with its various obligations under the
agreement. To allow defendant to now go back on its word and
WHEREFORE, claimant is hereby declared entitled to an award
start questioning the Decision would be grossly unfair
of P118,681,328.28 as just compensation for blasting works, plus
considering that the latter was also a party to the Compromise
ten percent (10%) thereof for attorney's fees and expenses of
Agreement entered into part of which dealt with the creation of
litigation.
the Arbitration Board. 6
Considering that payment in the total amount of P36,550,000.00
The appellate court likewise held that petitioner failed to present
had previously been made, respondent is hereby ordered to pay
evidence to prove its claim of bias and partiality on the part of
claimant the remaining sum of P82,131,328.28 for attorney's
the Chairman of the Arbitration Board, Mr. Carmelo V. Sison (Mr.
fees and expenses of litigation.
Sison). aIcCTA
Pursuant to the Compromise Agreement approved by this
Further, the Court of Appeals found that blasting is not part of the
Honorable Court, the parties have agreed that the decision of the
unit price for grading and structural excavation provided for in
Arbitration Board shall be final and executory.
the contract for the BACMAN II Project, and that there was no
SO ORDERED. perfected contract between the parties for an extra work order for
blasting. Nonetheless, since FUCC relied on the representation
On December 10, 1999 plaintiff FUCC filed a Motion for of petitioner's officials that the extra work order would be
Execution while defendant NPC filed a Motion to Vacate Award submitted to its Board of Directors for approval and that the
by the Arbitration Board on December 20, 1999. blasting works would be paid, the Court of Appeals ruled that
FUCC is entitled to just compensation on grounds of equity and
On May 22, 2000 Presiding Judge Rose Marie Alonzo Legasto promissory estoppel.
issued an order the dispositive portion of which states:
Anent the issue of just compensation, the appellate court took
"WHEREFORE, the Arbitration Award issued by the Arbitration into account the estimate prepared by a certain Mr. Lauro R.
Board is hereby APPROVED and the Motion for Execution filed Umali (Mr. Umali), Project Manager of the BACMAN II Project,
by plaintiff hereby GRANTED. The Motion to Vacate Award filed which itemized the various costs involved in blasting works and
by defendant is hereby DENIED for lack of merit. came up with P1,310.82 per cubic meter, consisting of the direct
cost for drilling, blasting excavation, stockpiling and hauling, and
Accordingly, let a writ of execution be issued to enforce the a 30% mark up for overhead, contractor's tax and contingencies.
Arbitration Award. This estimate was later changed to P983.75 per cubic meter to
which FUCC agreed. The Court of Appeals, however, held that
SO ORDERED." 5 (Bracketed words supplied) just compensation should cover only the direct costs plus 10%
for overhead expenses. Thus, it declared that the amount of
NPC went to the Court of Appeals on the lone issue of whether
P763.00 7 per cubic meter is sufficient. Since the total volume of
respondent judge acted with grave abuse of discretion in issuing
blasted rocks as computed by Dr. Benjamin Buensuceso, Jr. 8 of
the Order dated May 22, 2000 and directing the issuance of
the U.P. College of Engineering is 97,032.16 cubic meters,
a Writ of Execution.
FUCC is entitled to the amount of P74,035,503.50 as just
compensation.
In its assailed Decision, the appellate court declared that the
court a quo did not commit grave abuse of discretion considering
that the Arbitration Board acted pursuant to its powers under the
Compromise Agreement and that its award has factual and legal
bases.
Although the Court of Appeals adjudged FUCC entitled to of Republic Act No. 876 (R.A. 876) otherwise known as the
interest, 9 the dispositive portion of the assailed Decision 10 did Arbitration Law. Petitioner also questions the abrupt manner by
not provide for the payment of interest. Moreover, the award of which the decision of the Arbitration Board was released.
attorney's fees was deleted as there was no legal and factual
ground for its imposition. Petitioner avers that FUCC's claim for blasting works was not
approved by authorized officials in accordance with Presidential
Petitioner, represented by the Office of the Solicitor General in Decree No. 1594 (P.D. 1594) and its implementing rules which
the instant Petition, rehashes its submissions before the Court of specifically require the approval of the extra work by authorized
Appeals. It claims that the appellate court failed to pass upon the officials before an extra work order may be issued in favor of the
following issues: contractor. Thus, it should not be held liable for the claim. If at all,
only the erring officials should be held liable. Further, FUCC did
1. The Chairman of the Arbitration Board showed extreme bias in not present evidence to prove the actual expenses it incurred for
prejudging the case. the blasting works. What the Arbitration Board relied upon was
the memorandum of Mr. Umali which was neither identified or
2. The Chairman of the Arbitration Board greatly exceeded his authenticated during the arbitration proceedings nor marked as
powers when he mediated for settlement in the court of evidence for FUCC. Moreover, the figures indicated in Mr.
arbitration proceedings. Umali's memorandum were allegedly mere estimates and were
recommendatory at most.
3. The Chairman of the Arbitration Board committed serious
irregularity in hastily convening the Board in two days, which Petitioner likewise claims that its succeeding contractor, Phesco,
thereafter released its report. Inc. (Phesco), was able to excavate the same rock formation
without blasting.
4. The Arbitration Board Committed manifest injustice prejudicial
to petitioner based on the following: Finally, it asserts that the award of P763.00 per cubic meter has
no factual and legal basis as the sub-contract between FUCC
a. It rendered an award based on equity despite the mandatory
and its blasting sub-contractor, Dynamic Blasting Specialists of
provision of the law.
the Philippines (Dynamic), was only P430.00 per cubic meter.
b. The Board's decision to justify that equity applies herein
despite the fact that FUCC never submitted its own actual costs
for blasting and PHESCO, INC., the succeeding contractor, did In its Comment 13 dated October 15, 2001, FUCC points out
not employ blasting but used ordinary excavation method at that petitioner's arguments are exactly the same as the ones it
P75.59 per cubic meter which is approximately the same unit raised before the Arbitration Board, the trial court and the Court
price of plaintiff (FUCC). of Appeals. Moreover, in the Compromise Agreement between
the parties, petitioner committed to abide by the decision of the
c. It gravely erred when the Board claimed that an award of just
Arbitration Board. It should not now be allowed to question the
compensation must be given to respondent FUCC for what it has
decision.
actually spent and yet instead of using as basis P458.07 which is
the price agreed upon by FUCC, it chose an estimate made by FUCC likewise notes that Atty. Jose G. Samonte (Atty.
an NPC employee. Samonte), one of the members of the Arbitration Board, was
nominated by petitioner itself. If there was any irregularity in its
d. It gravely erred when it relied heavily on the purported letter of
proceedings such as the bias and prejudgment petitioner
NPC Project Manager Lauro R. Umali, when the same has not
imputes upon Mr. Sison, Atty. Samonte would have complained.
been identified nor were the handwritten entries in Annex ii
As it is, Atty. Samonte concurred in the decision of the Arbitration
established to be made by him.
Board and dissented only as to the award of attorney's fees.
5. The Arbitration Board gravely erred in computing interest at
As regards the issue of interest, FUCC claims that the case
12% and from the time of plaintiff's extrajudicial claim despite the
involves forbearance of money and not a claim for damages for
fact that herein case is an action for specific performance and
breach of an obligation in which case interest on the amount of
not for payment of loan or forbearance of money, and despite the
damages awarded may be imposed at the rate of six percent
fact that it has resolved that there was no perfected contract and
(6%) per annum.
there was no bad faith on the part of defendant.
Finally, FUCC asserts that its sub-contract agreement with
6. On June 25, 2000, NPC discovered the Sub-Contract
Dynamic is not newly-discovered evidence. Petitioner's lawyers
Agreement of FUCC with a unit price of only P430/per cubic
allegedly had a copy of the sub-contract in their possession. In
meter. 11 [Emphasis in the original]
any event, the unit price of P430.00 per cubic meter appearing in
Specifically, petitioner asserts that Mr. Sison exhibited bias and the sub-contract represents only a fraction of the costs incurred
prejudgment when he exhorted it to pay FUCC for the blasting by FUCC for the blasting works.
works after concluding that the latter was allowed to blast.
Petitioner filed a Reply 14 dated March 18, 2002 reiterating its
Moreover, Mr. Sison allegedly attempted to mediate the conflict
earlier submissions.
between the parties in violation of Section 20, 12 paragraph 2
The parties in the present case mutually agreed to submit to which the arbitrators may make a decision shall be deemed
arbitration the settlement of the price of blasting, the parties' applicable to the new arbitration to commence from the date of
claims for damages, delay and interests and all other unresolved the court's order.
claims including the exact volume of blasted rocks. 15 They
further mutually agreed that the decision of the Arbitration Board Where the court vacates an award, costs not exceeding fifty
shall be final and immediately executory. 16 pesos and disbursements may be awarded to the prevailing
party and the payment thereof may be enforced in like manner
A stipulation submitting an ongoing dispute to arbitration is valid. as the payment of costs upon the motion in an action.
As a rule, the arbitrator's award cannot be set aside for mere
errors of judgment either as to the law or as to the facts. Courts Section 25. Grounds for modifying or correcting an award. In
are generally without power to amend or overrule merely any one of the following cases, the court must make an order
because of disagreement with matters of law or facts determined modifying or correcting the award, upon the application of any
by the arbitrators. They will not review the findings of law and party to the controversy which was arbitrated:
fact contained in an award, and will not undertake to substitute
their judgment for that of the arbitrators. A contrary rule would (a) Where there was an evident miscalculation of figures, or an
make an arbitration award the commencement, not the end, of evident mistake in the description of any person, thing or
litigation. Errors of law and fact, or an erroneous decision on property referred to in the award; or
matters submitted to the judgment of the arbitrators, are
(b) Where the arbitrators have awarded upon a matter not
insufficient to invalidate an award fairly and honestly made.
submitted to them, not affecting the merits of the decision upon
Judicial review of an arbitration award is, thus, more limited than
the matter submitted; or
judicial review of a trial. 17
(c) Where the award is imperfect in a matter of form not affecting
However, an arbitration award is not absolute and without
the merits of the controversy, and if it had been a commissioner's
exceptions. Where the conditions described in Articles 2038,
report, the defect could have been amended or disregarded by
2039 and 2040 of the Civil Code 18 applicable to both
the court.
compromises and arbitrations are obtaining, the arbitrators'
award may be annulled or rescinded. 19 Additionally, judicial The order may modify and correct the award so as to effect the
review of an arbitration award is warranted when the intent thereof and promote justice between the parties.
complaining party has presented proof of the existence of any of
the grounds for vacating, modifying or correcting an award In this case, petitioner does not specify which of the foregoing
outlined underSections 24 and 25 of R.A. 876, viz: grounds it relies upon for judicial review. Petitioner avers that "if
and when the factual circumstances referred to in the provisions
Section 24. Grounds for vacating an award. In any of the aforementioned are present, judicial review of the award is
following cases, the court must make an order vacating the warranted." 20 From its presentation of issues, however, it
award upon the petition of any party to the controversy when appears that the alleged evident partiality of Mr. Sison is singled
such party proves affirmatively that in the arbitration out as a ground to vacate the board's decision.
proceedings:
We note, however, that the Court of Appeals found that petitioner
(a) The award was procured by corruption, fraud, or other undue did not present any proof to back up its claim of evident partiality
means; or cSATEH on the part of Mr. Sison. Its averments to the effect that Mr. Sison
was biased and had prejudged the case do not suffice to
(b) That there was evident partiality or corruption in the
establish evident partiality. Neither does the fact that a party was
arbitrators or any of them; or
disadvantaged by the decision of the arbitration committee prove
(c) That the arbitrators were guilty of misconduct in refusing to evident partiality. 21
postpone the hearing upon sufficient cause shown, or in refusing
According to the appellate court, "[p]etitioner was never deprived
to hear evidence pertinent and material to the controversy; that
of the right to present evidence nor was there any showing that
one or more of the arbitrators was disqualified to act as such
the Board showed signs of any bias in favor of FUCC. As
under section nine hereof, and willfully refrained from disclosing
correctly found by the trial court, this Court cannot find its way to
such disqualifications or of any other misbehavior by which the
support petitioner's contention that there was evident partiality in
rights of any party have been materially prejudiced; or
the assailed Award of the Arbitrator in favor of the respondent
(d) That the arbitrators exceeded their powers, or so imperfectly because the conclusion of the Board, which the Court found to
executed them, that a mutual, final and definite award upon the be well-founded, is fully supported by substantial evidence." 22
subject matter submitted to them was not made.
There is no reason to depart from this conclusion.
When an award is vacated, the court, in its discretion, may direct
However, we take exception to the arbitrators' determination that
a new hearing either before the same arbitrators or before a new
based on promissory estoppel per se or alone, FUCC is entitled
arbitrator or arbitrators to be chosen in the manner provided in
to just compensation for blasting works for the reasons
the submission or contract for the selection of the original
discussed hereunder.
arbitrator or arbitrators, and any provision limiting the time in
Section 9 of P.D. No. 1594, entitled Prescribing Policies, 7. Any Variation Order (Change Order, Extra Work Order or
Guidelines, Rules and Regulations for Government Supplemental Agreement) shall be subject to the escalation
Infrastructure Contracts, provides: formula used to adjust the original contract price less the cost of
mobilization. In claiming for any Variation Order, the contractor
SECTION 9. Change Order and Extra Work Order. A change shall, within seven (7) calendar days after such work has been
order or extra work order may be issued only for works commenced or after the circumstances leading to such
necessary for the completion of the project and, therefore, shall condition(s) leading to the extra cost, and within 28 calendar
be within the general scope of the contract as bid[ded] and days deliver a written communication giving full and detailed
awarded. All change orders and extra work orders shall be particulars of any extra cost in order that it may be investigated
subject to the approval of the Minister of Public Works, at that time. Failure to provide either of such notices in the time
Transportation and Communications, the Minister of Public stipulated shall constitute a waiver by the contractor for any
Highways, or the Minister of Energy, as the case may be. claim. The preparation and submission of Change Orders, Extra
Work Orders or Supplemental Agreements are as follows:
The pertinent portions of the Implementing Rules and
Regulations of P.D. 1594 provide: a. If the Project Engineer believes that a Change Order, Extra
Work Order or Supplemental Agreement should be issued, he
CI Contract Implementation: shall prepare the proposed Order or Supplemental Agreement
accompanied with the notices submitted by the contractor, the
These Provisions Refer to Activities During Project Construction,
plans therefore, his computations as to the quantities of the
i.e., After Contract Award Until Completion, Except as May
additional works involved per item indicating the specific stations
Otherwise be Specifically Referred to Provisions Under Section
where such works are needed, the date of his inspections and
II. IB Instructions to Bidders.
investigations thereon, and the log book thereof, and a detailed
CI 1 Variation Orders Change Order/Extra Work estimate of the unit cost of such items of work, together with his
Order/Supplemental Agreement justifications for the need of such Change Order, Extra Work
Order or Supplemental Agreement, and shall submit the same to
4. An Extra Work Order may be issued by the implementing the Regional Director of office/agency/corporation concerned.
official to cover the introduction of new work items after the
same has been found to strictly comply with Section CI-1-1 and b. The Regional Director concerned, upon receipt of the
approved by the appropriate official if the amount of the Extra proposed Change Order, Extra Work Order or Supplemental
Work Order is within the limits of the former's authority to Agreement shall immediately instruct the technical staff of the
approve original contracts and under the following conditions: Region to conduct an on-the-spot investigation to verify the need
for the work to be prosecuted. A report of such verification shall
a. Where there are additional works needed and necessary for be submitted directly to the Regional Director concerned.
the completion, improvement or protection of the project which
were not included as items of work in the original contract. c. The Regional Director concerned after being satisfied that
such Change Order, Extra Work Order or Supplemental
b. Where there are subsurface or latent physical conditions at Agreement is justified and necessary, shall review the estimated
the site differing materially from those indicated in the contract. quantities and prices and forward the proposal with the
supporting documentation to the head of
c. Where there are duly unknown physical conditions at the site office/agency/corporation for consideration. aEDCSI
of an unusual nature differing materially from those ordinarily
encountered and generally recognized as inherent in the work or d. If, after review of the plans, quantities and estimated unit cost
character provided for in the contract. of the items of work involved, the proper
office/agency/corporation committee empowered to review and
d. Where there are duly approved construction drawings or any evaluate Change Orders, Extra Work Orders or Supplemental
instruction issued by the implementing office/agency during the Agreements recommends approval thereof, the head of
term of contract which involve extra cost. office/agency/corporation, believing the Change Order, Extra
Work Order or Supplemental Agreement to be in order, shall
xxx xxx xxx approve the same. The limits of approving authority for any
individual, and the aggregate of, Change Orders, Extra Work
6. A separate Supplemental Agreement may be entered into for Orders or Supplemental Agreements for any project of the head
all Change Orders and Extra Work Orders if the aggregate of office/agency/corporation shall not be greater than those
amount exceeds 25% of the escalated original contract price. All granted for an original project.
change orders/extra work orders beyond 100% of the escalated
original contract cost shall be subject to public bidding except CI 3 Conditions under which Contractor is to Start Work under
where the works involved are inseparable from the original Variation Orders and Receive Payments
scope of the project in which case negotiation with the
incumbent contractor may be allowed, subject to approval by the
appropriate authorities.
1. Under no circumstances shall a contractor proceed to recommended blasting (Cf. Memorandum of Mr. Petronilo E.
commence work under any Change Order, Extra Work Order or Pana, Acting Manager of the Geoscience Services Department
Supplemental Agreement unless it has been approved by the and the report of the geologists who conducted the site
Secretary or his duly authorized representative. Exceptions to investigation; Exhs. "F" and "F-1").
the preceding rule are the following:
2. Claimant asked for clearance to blast the rock formation to the
a. The Regional Director, or its equivalent position in design grade (Letter dated 28 September 1992; Exh. "UU"). The
agencies/offices/corporations without plantilla position for the engineers of respondent at the project site advised claimant to
same, may, subject to the availability of funds, authorize the proceed with its suggested method of
immediate start of work under any Change or Extra Work Order extraction (Order/Instruction given by Mr. Reuel R. Declaro and
under any or all of the following conditions: Mr. Francis A. Paderna dated 29 September 1992; Exh. "C").

(1) In the event of an emergency where the prosecution of the 3. Claimant requested that the intended blasting works be
work is urgent to avoid detriment to public service, or damage to confirmed as extra work order by responsible officials of
life and/or property; and/or respondent directly involved in the BACMAN II Project (i.e., then
BACMAN II Project Manager, Mr. Lauro R. Umali and Mr.
(2) When time is of the essence; provided, however, that such Angelito G. Senga, Section Chief, Civil Engineering Design of
approval is valid on work done up to the point where the respondent's Design Department which bidded the
cumulative increase in value of work on the project which has project). These officials issued verbal instructions to the
not yet been duly fully approved does not exceed five percent effect: (a) that claimant could blast the rock formation down to
(5%) of the adjusted original contract price, or P500,000 the design grade of 495 masl;(b) that said blasting works would
whichever is less; provided, further, that immediately after the be an extra work order; and (c) that claimant would be paid for
start of work, the corresponding Change/Extra Work Order shall said blasting works using the price per cubic meter for similar
be prepared and submitted for approval in accordance with the blasting works at Palinpinon, or at P1,346.00 per cubic meter.
above rules herein set. Payments for works satisfactorily
accomplished on any Change/Extra Work Order may be made 4. Claimant sent two (2) confirmatory letters to respondent, both
only after approval of the same by the Secretary or his duly addressed to its President, one dated 30 September 1992, and
authorized representative. sent through Mr. Angelito Senga, Chief Civil Design Thermal,
the other dated 02 October 1992, and sent through Mr. Lauro R.
b. For a Change/Extra Work Order involving a cumulative Umali, Project Manager-BacMan II (Exhs. "D" and "E"; Testimony
amount exceeding five percent (5%) of the original contract price of witness Dumaliang, TSN, 28 October 1996, pp. 4349). The
or original adjusted contract price no work thereon may be identical letters read:
commenced unless said Change/Extra Work Order has been
approved by the Secretary or his duly authorized representative. We wish to confirm your instruction for us to proceed with the
[Emphasis supplied] blasting of the Botong Plant site to the design grade pending
issuance of the relevant variation order. This is to avoid delay in
It is petitioner's submission, and FUCC does not deny, that the the implementation of this critical project due to the urgent need
claim for payment of blasting works in Botong alone was to blast rocks on the plant site.
approximately P170,000,000.00, a figure which far exceeds the
original contract price of P80,000,000.00 for two (2) project sites. We are confirming further your statement that the said blasting
Under the foregoing implementing rules, for an extra work order works is an extra work order and that we will be paid using the
which exceeds 5% of the original contract price, no blasting work price established in your Palinpinon contract with Phesco.
may be commenced without the approval of the Secretary or his
duly authorized representative. Moreover, the procedure for the Thank you for your timely action and we look forward to the
preparation and approval of the extra work order outlined under immediate issuance of the extra work order.
Contract Implementation (CI) 1(7) above should have been
complied with. Accordingly, petitioner's officials should not have We are now mobilizing equipment and manpower for the said
authorized the commencement of blasting works nor should work and hope to start blasting next week.
FUCC have proceeded with the same.
5. Respondent received the letters but did not reply thereto nor
The following events, culled from the decision of the Arbitration countermand the earlier instructions given to claimant to proceed
Board and the assailed Decision, are made the bases for the with the blasting works. The due execution and authenticity of
finding of promissory estoppel on the part of petitioner: these letters (Exhs. "D-1" and "E-1") and the fact of receipt
(Exhs. "D-2" and "E-2") were duly proved by claimant (Testimony
1. After claimant [respondent herein] encountered what it of witness Dumaliang, TSN, 28 October 1996, 4349).
claimed to be massive hard rock formation (Testimony of witness
Dumaliang, TSN, 28 October 1996, pp. 4142; Testimony of 6. In mid-October 1992, three (3) Vice-Presidents of respondent
witness Lataquin, 28 November 1996, pp. 23; 2023; Exh. "JJJ" visited the project site and were informed of claimant's blasting
and sub-markings) and informed respondent [petitioner activities. While respondent claims that one of the Vice-
herein] about it, respondent's own geologists went to the Botong Presidents, Mr. Rodrigo Falcon, raised objections to claimant's
site to investigate and confirmed the rock formation and blasting works as an extra work order, they instructed claimant to
speed up the works because of the power crisis then hounding
the country. Stipulation no. 24 of the Joint Stipulation of Facts of Mr. Campos to Mr. Paderna at the project site that the variation
the parties which reads: "24. In mid-October 1992, three (3) order was being processed and that payment to claimant was
Vice-Presidents of respondent, namely: Mr. Hector N. Campos, forthcoming (Exhs. "AAA" and "BBB").
Sr., of Engineering Construction, Mr. C.A. Pastoral of
Engineering Design, and Mr. Rodrigo P. Falcon, visited the 12. Respondent asked the Department of Public Works and
project site and were likewise apprised of claimant's blasting Highways (DPWH) about the standard prices for blasting in the
activities. They never complained about the blasting works, projects of the DPWH. The DPWH officially replied to
much less ordered its cessation. In fact, no official of respondent respondent's query in a letter dated 19 May 1993 but the task
ever ordered that the blasting works be stopped." force still failed to seek Board approval for claimant's variation
order. The task force eventually recommended that the issue of
7. After visiting Botong, Mr. Hector N. Campos, Sr., then Vice grading excavation and structural excavation and the unit prices
President of Engineering Construction, instructed Mr. Fernando therefor be brought into voluntary arbitration (Testimony of
A. Magallanes then Manager of the Luzon Engineering Projects witness Dumaliang, 7 November 1996, pp. 3057).
Department, to evaluate claimant's blasting works and to submit
his recommendations on the proper price therefor. In a 13. Claimant thereafter saw Mr. Francisco L. Viray, the new NPC
memorandum dated 17 November 1992 (Exh. "G" and sub- President, who proposed that claimant accept the price of
markings), Mr. Magallanes confirmed that claimant's blasting P458.07 per cubic meter for its blasting works with the balance
works was an extra work order and recommended that it be paid of its claim to be the subject of arbitration. Claimant accepted the
at the price for similar blasting works at Palinpinon, or at offer and sent the letter dated 28 September 1993 (Exh. "O") to
P1,346.00 per cubic meter. Mr. Campos concurred with the formalize said acceptance. However, no variation order was
findings and recommendations of Mr.Magallanes and instructed issued and the promised payment never came. (Testimony of
Mr. Lauro R. Umali, then Project Manager of BacMan II, to witness Dumaliang, 7 November 1996, p. 58).
implement the same as shown by his instructions scribbled on
the memorandum. 14. After some time, claimant met Mr. Viray on 19 October 1993
at the project site, and with some NPC officers in attendance,
particularly Mr. Gilberto A. Pastoral, Vice-President for
Engineering Design, who was instructed by Mr. Viray to prepare
8. Mr. Umali and the project team prepared proposed Extra the necessary memorandum (i.e., that claimant would be paid
Work Order No. 2 Blasting (Exh. "DDD" Memorandum of P458.07 per cubic meter with the balance of its claim to be the
Mr. Umali to Mr. Campos dated 20 January 1993 forwarding subject of arbitration) for the approval of the NPC
proposed Extra Work Order No. 2), recommending a price of Board. Claimant formalized what transpired during this meeting
P983.75 per cubic meter for claimant's blasting works. Claimant in its letter to Mr. Pastoral dated 22 October 1993 (Exhibit
agreed to this price (Testimony of witness Dumaliang, 7 "R"). But no action was taken by Mr. Pastoral and no variation
November 1996, p. 48). order was issued by respondent (Testimony of witness
Dumaliang, 7 November 1996, pp. 5758). 23 [Emphasis
9. On 19 February 1993, claimant brought the matter of its supplied and bracketed words]
unpaid blasting works to the attention of the then NPC Chairman
[also Secretary of the Department of Energy then] Delfin L. Promissory estoppel "may arise from the making of a promise,
Lazaro during a meeting with the multi-sectoral task force even though without consideration, if it was intended that the
monitoring the implementation of power plant projects, who promise should be relied upon and in fact it was relied upon, and
asked then NPC President Pablo B. Malixi what he was doing if a refusal to enforce it would be virtually to sanction the
about the problem. President Malixi thereafter convened perpetration of fraud or would result in other
respondent's vice-presidents and ordered them to quickly injustice." 24 Promissory estoppel presupposes the existence of
document the variation order and pay claimant. The vice- a promise on the part of one against whom estoppel is claimed.
president, and specifically Mr. Campos, pledged that the The promise must be plain and unambiguous and sufficiently
variation order for claimant's blasting works would be submitted specific so that the court can understand the obligation assumed
for the approval of the NPC Board during the first week of March and enforce the promise according to its terms. 25
1993. Claimant thereafter sent respondent a letter dated 22
February 1993 (Ex. "K") to confirm this pledge(Testimony of In the present case, the foregoing events clearly evince that the
witness Dumaliang, 7 November 1996, pp. 2830). promise that the blasting works would be paid was predicated on
the approval of the extra work order by petitioner's Board. Even
10. Mr. Campos created a task force (i.e., the Technical Task FUCC acknowledged that the blasting works should be an extra
Force on the Study and Review of Extra Work Order No. 2; Exh. work order and requested that the extra work order be confirmed
"FFF") to review claimant's blasting works. After several as such and approved by the appropriate officials. Notably, even
meetings with the task force, claimant agreed to the lower price as the extra work order allegedly promised to it was not yet
of P458.07 per cubic meter, in exchange for quick forthcoming, FUCC commenced blasting.
payment (Testimony of witness Dumaliang, 7 November 1996, p.
30). aSITDC The alleged promise to pay was therefore conditional and up to
this point, promissory estoppel cannot be established as the
11. However, no variation order was issued and no payment basis of petitioner's liability especially in light of P.D. 1594 and its
came, although it appears from two (2) radiograms sent by implementing rules of which both parties are presumed to have
knowledge. In Mendoza v. Court of Appeals, supra, we ruled that is the best evidence on record as it is supported by detailed cost
"[a] cause of action for promissory estoppel does not lie where estimates that will serve as basis to determine just
an alleged oral promise was conditional, so that reliance upon it compensation.
was not reasonable. It does not operate to create liability where
it does not otherwise exist." While the Arbitration Board found that FUCC did not present
evidence showing the amount it paid to its blasting sub-
Petitioner's argument that it is not bound by the acts of its contractor, it did present testimony to the effect that it incurred
officials who acted beyond the scope of their authority in allowing other costs and expenses on top of the actual blasting cost.
the blasting works is correct. Petitioner is a government agency Hence, the amount of P430.00 per cubic meter indicated in
with a juridical personality separate and distinct from the FUCC's Contract of Agreement with Dynamic is not controlling.
government. It is not a mere agency of the government but a
corporate entity performing proprietary functions. It has its own Moreover, FUCC presented evidence showing that in two (2)
assets and liabilities and exercises corporate powers, including other projects where blasting works were undertaken, petitioner
the power to enter into all contracts, through its Board of paid the contractors P1,346 per cubic meter for blasting and
Directors. disposal of solid rocks in the Palinpinon project and P1,144.51
per cubic meter for rock excavation in the Hermosa Balintawak
In this case, petitioner's officials exceeded the scope of their project. Besides, while petitioner claims that in a contract with
authority when they authorized FUCC to commence blasting Wilper Construction for the construction of the Tayabas sub-
works without an extra work order properly approved in station, the price agreed for blasting was only P96.13, petitioner
accordance with P.D. 1594. Their acts cannot bind petitioner itself did not present evidence in support of this claim. 32
unless it has ratified such acts or is estopped from disclaiming
them. 26 Parenthetically, the point raised by petitioner that its subsequent
contractor, Phesco, did not undertake blasting works in
However, the Compromise Agreement entered into by the excavating the same rock formation is extraneous and irrelevant.
parties, petitioner, being represented by its President, Mr. Guido The fact is that petitioner allowed FUCC to blast and undertook
Alfredo A. Delgado, acting pursuant to its Board Resolution No. to pay for the blasting works.
95-54 dated April 3, 1995, is a confirmatory act signifying
petitioner's ratification of all the prior acts of its officers. At this point, we hearken to the rule that the findings of the
Significantly, the parties agreed that "[t]his Compromise Arbitration Board, affirmed by the trial court and the Court of
Agreement shall serve as the Supplemental Agreement for the Appeals and supported as they are by substantial evidence,
payment of plaintiff's blasting works at the Botong site" 27 in should be accorded not only respect but finality. 33 Accordingly,
accordance with CI 1(6) afore-quoted. In other words, it is the amount of P763.00 per cubic meter fixed by the Arbitration
primarily by the force of this Compromise Agreement that the Board and affirmed by the appellate court as just compensation
Court is constrained to declare FUCC entitled to payment for the should stand.
blasting works it undertook.
As regards the issue of interest, while the appellate court
Moreover, since the blasting works were already rendered by declared in the body of its Decision "that interest which would
FUCC and accepted by petitioner and in the absence of proof represent the cost of the money spent be imposed on the money
that the blasting was done gratuitously, it is but equitable that actually spent by claimant for the blasting works," 34 there is no
petitioner should make compensation therefor, pursuant to the pronouncement as to the payment of interest in the dispositive
principle that no one should be permitted to enrich himself at the portion of theDecision even as it specifically deleted the award of
expense of another. 28 attorney's fees.

This brings us to the issue of just compensation.

The parties proposed in the terms of reference jointly submitted Despite its knowledge of the appellate court's omission, FUCC
to the Arbitration Board that should FUCC be adjudged entitled did not file a motion for reconsideration or appeal from
to just compensation for its blasting works, the price therefor its Decision. In failing to do so, FUCC allowed theDecision to
should be determined based on the payment for blasting works become final as to it.
in similar projects of FUCC and the amount it paid to its blasting
subcontractor. 29 They agreed further that "the price of the In Edwards v. Arce, 35 we ruled that in a case decided by a
blasting at the Botong site . . . shall range from Defendant's court, the true judgment of legal effect is that entered by the clerk
position of P76.00 per cubic meter as per contract to a maximum of said court pursuant to the dispositive part of its decision. The
of P1,144.00". 30 only portion of the decision that may be the subject of execution
is that which is ordained or decreed in the dispositive portion.
Petitioner contends that the Arbitration Board, trial court and the Whatever may be found in the body of the decision can only be
appellate court unduly relied on the memorandum of Mr. Umali considered as part of the reasons or conclusions of the court and
which was allegedly not marked as an exhibit. We note, serve only as guides to determine the ratio decidendi. 36
however, that this memorandum actually forms part of the record
of the case as Exhibit "DDD." 31 Moreover, both the Arbitration Even so, the Court allows a judgment which had become final
Board and the Court of Appeals found that Mr. Umali's proposal and executory to be clarified when there is an ambiguity caused
by an omission or mistake in the dispositive portion of the
decision. 37 In Reinsurance Company of the Orient, Inc. v. Court DECISION
of Appeals, 38 we held:
YNARES-SANTIAGO, J p:
In Republic Surety and Insurance Company, Inc. v. Intermediate
Appellate Court, the Court applying the above doctrine said: Assailed in this Petition for Review under Rule 45 of the Rules of
Court is the Decision 1 of the Court of Appeals dated May 15,
". . . We clarify, in other words, what we did affirm. What is 2003, which sustained the Order of the Regional Trial Court of
involved here is not what is ordinarily regarded as a clerical error Angeles City, Branch 61, dated June 28, 2001, and its
in the dispositive part of the decision of the Court of First subsequent Resolution dated August 3, 2003 denying petitioner's
Instance, which type of error is perhaps best typified by an error motion for reconsideration.
in arithmetical computation. At the same time, what is involved
here is not a correction of an erroneous judgment or dispositive European Resources and Technologies Inc. (hereinafter "ERTI"),
portion of a judgment. What we believe is involved here is in the a corporation organized and existing under the laws of the
nature of an inadvertent omission on the part of the Court of First Republic of the Philippines, is joined by Delfin J. Wenceslao as
Instance (which should have been noticed by private petitioner in this case. Ingenieuburo Birkhan + Nolte
respondent's counsel who had prepared the complaint), of what Ingiurgesellschaft mbh and Heers & Brockstedt Gmbh & Co. are
might be described as a logical follow-through of something set German corporations who are respondents in this case and shall
forth both in the body of the decision and in the dispositive be collectively referred to as the "German Consortium".
portion thereof : the inevitable follow-through, or translation into,
operational or behavioral terms, of the annulment of the Deed of The German Consortium tendered and submitted its bid to the
Sale with Assumption of Mortgage, from which petitioners' title or Clark Development Corporation ("CDC") to construct, operate
claim of title embodied in TCT 133153 flows." (Italics and manage the Integrated Waste Management Center at the
supplied) 39 Clark Special Economic Zone ("CSEZ"). CDC accepted the
German Consortium's bid and awarded the contract to it. On
In this case, the omission of the award of interest was obviously October 6, 1999, CDC and the German Consortium executed
inadvertent. Correction is therefore in order. However, we do not the Contract for Services 2 which embodies the terms and
agree with the Arbitration Board that the interest should be conditions of their agreement.
computed at 12%. Since the case does not involve a loan or
forbearance of money, goods or credit and court judgments The Contract for Services provides that the German Consortium
thereon, the interest due shall be computed at 6% per annum shall be empowered to enter into a contract or agreement for the
computed from the time the claim was made in 1992 as use of the integrated waste management center by corporations,
determined by the Arbitration Board and in accordance with local government units, entities, and persons not only within the
Articles 2209 and 1169 of the Civil Code. The actual base for the CSEZ but also outside. For waste collected within the CSEZ, the
computation of legal interest shall be on the amount finally German Consortium may impose a "tipping fee" per ton of waste
adjudged. 40 Further, when the judgment awarding a sum of collected from locators and residents of the CSEZ, which fees
money becomes final and executory, the rate of legal interest shall be subject to the schedule agreed upon by the parties and
shall be 12% per annum from such finality until its satisfaction, specified in the Contract for Services. For its operations outside
this interim period being deemed to be by then an equivalent to a of the CSEZ, the German Consortium shall pay CDC US$1.50
forbearance of credit. 41 per ton of non-hazardous solid waste collected. 3 The CDC shall
guarantee that nineteen thousand eighteen hundred (19,800)
WHEREFORE, the petition is GRANTED in part. The appealed tons per year of solid waste volume shall be collected from
decision is MODIFIED in that the amount of P74,035,503.50 inside and outside the CSEZ. 4 The contract has a term of
shall earn legal interest of six percent (6%) from 1992. A twelve twenty-five (25) years, 5 during which time the German
percent (12%) interest, in lieu of six percent (6%), shall be Consortium shall operate the waste management center on a
imposed on such amount upon finality of this decision until the day-to-day basis. 6
payment thereof. SIDEaA
Article VIII, Section 7 of the Contract for Services provides that
SO ORDERED. the German Consortium shall undertake to organize a local
corporation as its representative for this project. On April 18,
||| (National Power Corp. v. Alonzo-Legasto, G.R. No. 148318, 2000, the German Consortium entered into a Joint Venture with
[November 22, 2004], 485 PHIL 732-763) D.M. Wenceslao and Associates, Inc. ("DMWAI") and Ma. Elena
B. Villarama (doing business as LBV and Associates), embodied
in a Memorandum of Understanding 7 ("MOU") signed by the
parties. Under the MOU, the parties agreed to jointly form a local
FIRST DIVISION corporation to which the German Consortium shall assign its
rights under the Contract for Services. Pursuant to this
[G.R. No. 159586. July 26, 2004.]
agreement, petitioner European Resources and Technologies,
EUROPEAN RESOURCES AND TECHNOLOGIES, INC. and Inc. was incorporated. The parties likewise agreed to prepare
DELFIN J. WENCESLAO, petitioners, vs. INGENIEUBURO and finalize a Shareholders' Agreement within one (1) month
BIRKHAHN + NOLTE, Ingeniurgesellschaft mbh and HEERS from the execution of the MOU, which shall provide that the
& BROCKSTEDT GMBH & CO., respondents. German Consortium shall own fifteen percent (15%) of the equity
in the joint venture corporation, DMWAI shall own seventy ERTI to cease and desist from misrepresenting to third parties or
percent (70%) and LBV&A shall own fifteen percent (15%). In the the public that it has any right or interest in the waste
event that the parties fail to execute the Shareholders' management center at CSEZ. 14
Agreement, the MOU shall be considered null and void. 8
Petitioners filed their Opposition to the application for preliminary
On August 1, 2000, without the Shareholders' Agreement having injunction on February 7, 2001. The following day, February 8,
been executed, the German Consortium and petitioner ERTI 2001, petitioners sent respondents, through Mr. Holger Holst, a
entered into a Memorandum of Agreement (MOA) 9 whereby the letter demanding that the parties proceed to arbitration in
German Consortium ceded its rights and obligations under the accordance with Section 17 of the MOA. At the hearings on the
Contract for Services in favor of ERTI and assigned unto ERTI, application for injunction, petitioners objected to the presentation
among others, "its license from CDC to engage in the business of evidence on the ground that the trial court had no jurisdiction
of providing environmental services needed in the CSEZ in over the case since the German Consortium was composed of
connection with the waste management within the CSEZ and foreign corporations doing business in the country without a
other areas." 10 Likewise, the parties agreed that should there license. Moreover, the MOA between the parties provides that
be a disagreement between or among them relative to the the dispute should be referred to arbitration.
interpretation or implementation of the MOA and the collateral
documents including but not limited to the Contract for Services The trial court overruled the objection and proceeded with the
between the German Consortium and CDC, the dispute shall be hearing. On June 28, 2001, the trial court issued an Order
referred to a panel of arbitrators. 11 granting the writ of preliminary injunction. 15Petitioners filed a
motion for reconsideration, which was denied in a Resolution
On December 11, 2000, ERTI received a letter from BN dated November 21, 2001.
Consultants Philippines, Inc., signed by Mr. Holger Holst for and
on behalf of the German Consortium, 12 stating that the German On January 17, 2002, petitioners filed a petition for certiorari and
Consortium's contract with DMWAI, LBV&A and ERTI has been prohibition under Rule 65 of the Rules of Court before the Court
terminated or extinguished on the following grounds: (a) the of Appeals, assailing the trial court's Orders dated June 28, 2001
CDC did not give its approval to the Consortium's request for the and November 21, 2001.
approval of the assignment or transfer by the German
Consortium in favor of ERTI of its rights and interests under the Meanwhile, on February 11, 2002, the temporary restraining
Contract for Services; (b) the parties failed to prepare and order issued was lifted in view of respondents' failure to file
finalize the Shareholders' Agreement pursuant to the provision of sufficient bond. 16 On September 6, 2002, all proceedings in
the MOU; (c) there is no more factual or legal basis for the joint Civil Case No. 10049 were suspended until the petition
venture to continue; and (d) with the termination of the MOU, the for certiorari pending before the Court of Appeals shall have
MOA is also deemed terminated or extinguished. been resolved. 17

Attached to the letter was a copy of the letter of the On May 15, 2003, the Court of Appeals dismissed the petition
CDC, 13 stating that the German Consortium's assignment of an for certiorari. Petitioners' Motion for Reconsideration was denied
eighty-five percent (85%) majority interest to another party in a Resolution dated August 25, 2003.
violated its representation to undertake both the financial and
Hence, this petition arguing that the Court of Appeals committed
technical aspects of the project. The dilution of the Consortium's
reversible error in:
interest in ERTI is a substantial modification of the Consortium's
representations which were used as bases for the award of the (a) Ruling that petitioners are estopped from assailing the
project to it. DAEcIS capacity of the respondents to institute the suit for injunction
On February 20, 2001, petitioner ERTI, through counsel, sent a (b) Ruling that respondents are entitled to an injunctive writ.
letter to CDC requesting for the reconsideration of its disapproval
of the agreement between ERTI and the German Consortium. (c) Not holding that the dispute is covered by the arbitration
clause in the memorandum of agreement.
Before CDC could act upon petitioner ERTI's letter, the German
Consortium filed a complaint for injunction against herein (d) Issuing the writ of preliminary injunction that is tantamount to
petitioners before the Regional Trial Court of Angeles City, a decision of the case on the merits. 18
Branch 61, docketed as Civil Case No. 10049. The German
Consortium claimed that petitioner ERTI's continued The petition is partly meritorious.
misrepresentation as to their right to accept solid wastes from
third parties for processing at the waste management center will There is no general rule or governing principle laid down as to
cause irreparable damage to the Consortium and its exclusive what constitutes "doing" or "engaging in" or "transacting"
right to operate the waste management center at the CSEZ. business in the Philippines. Thus, it has often been held that a
Moreover, petitioner ERTI's acts destroy the Consortium's single act or transaction may be considered as "doing business"
credibility and undermine customer confidence in it. Hence, the when a corporation performs acts for which it was created or
German Consortium prayed that a writ of temporary restraining exercises some of the functions for which it was
order be issued against petitioner ERTI and, after hearing, a writ organized. 19 We have held that the act of participating in a
of preliminary injunction be likewise issued ordering petitioner bidding process constitutes "doing business" because it shows
the foreign corporation's intention to engage in business in the Philippine Courts a Philippine citizen or entity that had
Philippines. In this regard, it is the performance by a foreign contracted with and benefited from it.
corporation of the acts for which it was created, regardless of
volume of business, that determines whether a foreign Hence, the party is estopped from questioning the capacity of a
corporation needs a license or not. 20 foreign corporation to institute an action in our courts where it
had obtained benefits from its dealings with such foreign
corporation and thereafter committed a breach of or sought to
renege on its obligations. The rule relating to estoppel is deeply
Consequently, the German Consortium is doing business in the rooted in the axiom ofcommodum ex injuria sua non habere
Philippines without the appropriate license as required by our debet no person ought to derive any advantage from his own
laws. By participating in the bidding conducted by the CDC for wrong.
the operation of the waste management center, the German
Consortium exhibited its intent to transact business in the In the case at bar, petitioners have clearly not received any
Philippines. Although the Contract for Services provided for the benefit from its transactions with the German Consortium. In
establishment of a local corporation to serve as respondents' fact, there is no question that petitioners were the ones who
representative, it is clear from the other provisions of the have expended a considerable amount of money and effort
Contract for Services as well as the letter by the CDC containing preparatory to the implementation of the MOA. Neither do
the disapproval that it will be the German Consortium which shall petitioners seek to back out from their obligations under both the
manage and conduct the operations of the waste management MOU and the MOA by challenging respondents' capacity to sue.
center for at least twenty-five years. Moreover, the German The reverse could not be any more accurate. Petitioners are
Consortium was allowed to transact with other entities outside insisting on the full validity and implementation of their
the CSEZ for solid waste collection. Thus, it is clear that the local agreements with the German Consortium.
corporation to be established will merely act as a conduit or
extension of the German Consortium. To rule that the German Consortium has the capacity to institute
an action against petitioners even when the latter have not
As a general rule, unlicensed foreign non-resident corporations committed any breach of its obligation would be tantamount to
cannot file suits in the Philippines. Section 133 of the an unlicensed foreign corporation gaining access to our courts
Corporation Code specifically provides: for protection and redress. We cannot allow this without violating
the very rationale for the law prohibiting a foreign corporation not
SECTION 133. No foreign corporation transacting business in licensed to do business in the Philippines from suing or
the Philippines without a license, or its successors or assigns, maintaining an action in Philippine courts. The object of requiring
shall be permitted to maintain or intervene in any action, suit or a license is not to prevent the foreign corporation from
proceeding in any court or administrative agency of the performing single acts, but to prevent it from acquiring domicile
Philippines, but such corporation may be sued or proceeded for the purpose of business without taking the steps necessary to
against before Philippine courts or administrative tribunals on render it amenable to suits in the local courts. 24 In other words,
any valid cause of action recognized under Philippine laws. the foreign corporation is merely prevented from being in a
position where it takes the good without accepting the bad.
A corporation has legal status only within the state or territory in
which it was organized. For this reason, a corporation organized On the issue of whether the respondents were entitled to the
in another country has no personality to file suits in the injunctive writ, the petitioners claim that respondents' right is not
Philippines. In order to subject a foreign corporation doing in esse but is rather a future right which is contingent upon a
business in the country to the jurisdiction of our courts, it must judicial declaration that the MOA has been validly rescinded. The
acquire a license from the Securities and Exchange Commission Court of Appeals, in its decision, held that the MOA should be
(SEC) and appoint an agent for service of process. Without such deemed subject to a suspensive condition, that is, that CDC's
license, it cannot institute a suit in the Philippines. 21 prior written consent must be obtained for the validity of the
assignment.
However, there are exceptions to this rule. In a number of
cases, 22 we have declared a party estopped from challenging This issue must be resolved in a separate proceeding. It must be
or questioning the capacity of an unlicensed foreign corporation noted that the hearing conducted in the trial court was merely a
from initiating a suit in our courts. In the case of Communication preliminary hearing relating to the issuance of the injunctive writ.
Materials and Design, Inc. v. Court of Appeals, 23 a foreign In order to fully appreciate the facts of this case and the
corporation instituted an action before our courts seeking to surrounding circumstances relating to the agreements and
enjoin a local corporation, with whom it had a "Representative contract involved, further proof should be presented for
Agreement", from using its corporate name, letter heads, consideration of the court. Likewise, corollary matters, such as
envelopes, sign boards and business dealings as well as the whether either of the parties is liable for damages and to what
foreign corporation's trademark. The case arose when the extent, cannot be resolved with absolute certainty, thus rendering
foreign corporation discovered that the local corporation has any decision we might make incomplete as to fully dispose of
violated certain contractual commitments as stipulated in their this case. HcSaTI
agreement. In said case, we held that a foreign corporation
doing business in the Philippines without license may sue in More importantly, it is evident that CDC must be made a proper
party in any case which seeks to resolve the effectivity or
ineffectivity of its disapproval of the assignment made between the main case and seek a judgment without a full-blown trial as
petitioners and respondent German Consortium. Where, as in in the instant case.
the instant case, CDC is not impleaded as a party, any decision
of the court which will inevitably affect or involve CDC cannot be The Court of Appeals ruled that since petitioners did not raise
deemed binding on it. this issue during the hearing on the application for preliminary
injunction before the trial court, the same cannot be raised for
For the same reason, petitioners' assertion that the instant case the first time on appeal and even in special civil actions
should be referred to arbitration pursuant to the provision of the for certiorari as in this case.
MOA is untenable.
At the outset, it must be noted that with the finding that the
We have ruled in several cases that arbitration agreements are German Consortium is without any personality to file the petition
valid, binding, enforceable and not contrary to public policy such with the trial court, the propriety of the injunction writ issued is
that when there obtains a written provision for arbitration which is already moot and academic. Even assuming for the sake of
not complied with, the trial court should suspend the proceedings argument that respondents have the capacity to file the petition,
and order the parties to proceed to arbitration in accordance with we find merit in the issue raised by petitioners against the
the terms of their agreement. 25 In the case at bar, the MOA injunction writ issued.
between petitioner ERTI and respondent German Consortium
provided:

17. Should there be a disagreement between or among the Before an injunctive writ can be issued, it is essential that the
Parties relative to the interpretation or implementation of this following requisites are present: (1) there must be a right
Agreement and the collateral documents including but not limited in esse or the existence of a right to be protected; and (2) the act
to the Contract for Services between GERMAN CONSORTIUM against which injunction to be directed is a violation of such
and CDC and the Parties cannot resolve the same by right. 29 The onus probandi is on movant to show that there
themselves, the same shall be endorsed to a panel of arbitrators exists a right to be protected, which is directly threatened by the
which shall be convened in accordance with the process act sought to be enjoined. Further, there must be a showing that
ordained under the Arbitration Law of the Republic of the the invasion of the right is material and substantial and that there
Philippines. 26 is an urgent and paramount necessity for the writ to prevent a
serious damage. 30
Indeed, to brush aside a contractual agreement calling for
arbitration in case of disagreement between parties would be a Thus, it is clear that for the issuance of the writ of preliminary
step backward. 27 But there are exceptions to this rule. Even if injunction to be proper, it must be shown that the invasion of the
there is an arbitration clause, there are instances when referral right sought to be protected is material and substantial, that the
to arbitration does not appear to be the most prudent action. The right of complainant is clear and unmistakable and that there is
object of arbitration is to allow the expeditious determination of a an urgent and paramount necessity for the writ to prevent
dispute. Clearly, the issue before us could not be speedily and serious damage. 31At the time of its application for an injunctive
efficiently resolved in its entirety if we allow simultaneous writ, respondents' right to operate and manage the waste
arbitration proceedings and trial, or suspension of trial pending management center, to the exclusion of or without any
arbitration. 28 participation by petitioner ERTI, cannot be said to be clear and
unmistakable. The MOA executed between respondents and
As discussed earlier, the dispute between respondent German petitioner ERTI has not yet been judicially declared as rescinded
Consortium and petitioners involves the disapproval by the CDC when the complaint was lodged in court. 32 Hence, a cloud of
of the assignment by the German Consortium of its rights under doubt exists over respondent German Consortium's exclusive
the Contract for Services to petitioner ERTI. Admittedly, the right relating to the waste management center.
arbitration clause is contained in the MOA to which only the
German Consortium and petitioner ERTI were parties. Even if WHEREFORE, the decision of the Court of Appeals in CA-G.R.
the case is brought before an arbitration panel, the decision will SP No. 68923 dated May 15, 2003 is REVERSED and SET
not be binding upon CDC who is a non-party to the arbitration ASIDE. The Orders of the trial court dated June 28, 2001 and
agreement. What is more, the arbitration panel will not be able to November 21, 2001 are ANNULLED and SET ASIDE and Civil
completely dispose of all the issues of this case without including Case No. 10049 is DISMISSED for lack of legal capacity of
CDC in its proceedings. Accordingly, the interest of justice would respondents to institute the action. Costs against respondents.
only be served if the trial court hears and adjudicates the case in
a single and complete proceeding. SO ORDERED.

Lastly, petitioners question the propriety of the issuance of writ of ||| (European Resources and Techologies, Inc. v. Ingenieuburo
preliminary injunction claiming that such is already tantamount to Birkhahn + Nolte, G.R. No. 159586, [July 26, 2004], 479 PHIL
granting the main prayer of respondents' complaint without the 114-130)
benefit of a trial. Petitioners point out that the purpose of a
preliminary injunction is to prevent threatened or continuous
irremediable injury to some of the parties before their claims can SECOND DIVISION
be thoroughly studied and decided. It cannot be used to railroad
[G.R. No. 161957. February 28, 2005.] the Operating and Financial Accommodation Contract,
the Assignment, Accession Agreement, and the Memorandum of
JORGE GONZALES and PANEL OF Agreement. Petitioner Gonzales prayed for an unspecified
ARBITRATORS, petitioners, vs. CLIMAX MINING LTD., amount of actual and exemplary damages plus attorney's fees
CLIMAX-ARIMCO MINING CORP., and AUSTRALASIAN and for the issuance of a temporary restraining order and/or writ
PHILIPPINES MINING INC., respondents. of preliminary injunction to restrain or enjoin respondents from
further implementing the questioned agreements. He sought said
DECISION reliefs on the grounds of "FRAUD, OPPRESSION and/or
VIOLATION of Section 2, Article XII of the CONSTITUTION
TINGA, J p:
perpetrated by these foreign RESPONDENTS, conspiring and
Petitioner Jorge Gonzales, as claimowner of mineral deposits confederating with one another and with each other. . . ." 8
located within the Addendum Area of Influence in Didipio, in the
On 21 February 2001, the Panel of Arbitrators dismissed
provinces of Quirino and Nueva Vizcaya, entered into a co-
the Complaint for lack of jurisdiction. Petitioner moved for
production, joint venture and/or production-sharing letter-
reconsideration and this was granted on 18 October 2001, the
agreement designated as the May 14, 1987 Letter of Intent with
Panel believing that the case involved a dispute involving rights
Geophilippines, Inc, and Inmex Ltd. Under the agreement,
to mining areas and a dispute involving surface owners,
petitioner, as claimowner, granted to Geophilippines, Inc. and
occupants and claim owners/concessionaires. According to the
Inmex Ltd. collectively, the exclusive right to explore and survey
Panel, although the issue raised in the Complaint appeared to be
the mining claims for a period of thirty-six (36) months within
purely civil in nature and should be within the jurisdiction of the
which the latter could decide to take an operating agreement on
regular courts, a ruling on the validity of the assailed contracts
the mining claims and/or develop, operate, mine and otherwise
would result to the grant or denial of mining rights over the
exploit the mining claims and market any and all minerals that
properties; therefore, the question on the validity of the contract
may be derived therefrom.
amounts to a mining conflict or dispute. Hence, the Panel
On 28 February 1989, the parties to the May 14, 1987 Letter of granted the Motion for Reconsideration with regard to the issues
Intent renegotiated the same into the February 28, 1989 of nullity, termination, withdrawal or damages, but with regard to
Agreement whereby the exploration of the mining claims was the constitutionality of the Addendum Agreement and FTAA, it
extended for another period of three years. held that it had no jurisdiction. 9

On 9 March 1991, petitioner Gonzales, Arimco Mining Respondents filed their motion for reconsideration but this was
Corporation, Geophilippines Inc., Inmex Ltd., and Aumex denied on 25 June 2002. The Panel of Arbitrators maintained
Philippines, Inc. signed a document designated as that there was a mining dispute between the parties since the
theAddendum to the May 14, 1987 Letter of Intent and February subject matter of the Complaint arose from contracts between
28, 1989 Agreement with Express Adhesion Thereto (hereafter, the parties which involve the exploration and exploitation of
the Addendum Contract). 1 Under theAddendum Contract, minerals over the disputed area. 10
Arimco Mining Corporation would apply to the Government of the
Respondents assailed the orders of the Panel of Arbitrators via a
Philippines for permission to mine the claims as the
petition for certiorari before the Court of Appeals. ECTHIA
Government's contractor under a Financial and Technical
Assistance Agreement (FTAA). On 20 June 1994, Arimco Mining On 30 July 2003, the Court of Appeals granted the petition,
Corporation obtained the FTAA 2 and carried out work under the declaring that the Panel of Arbitrators did not have jurisdiction
FTAA. over the complaint filed by petitioner. 11 The jurisdiction of the
Panel of Arbitrators, said the Court of Appeals, is limited only to
Respondents executed the Operating and Financial
the resolution of mining disputes, defined as those which raise a
Accommodation Contract 3 (between Climax-Arimco Mining
question of fact or matter requiring the technical knowledge and
Corporation and Climax Mining Ltd., as first parties, and
experience of mining authorities. It was found that the complaint
Australasian Philippines Mining Inc., as second party) dated 23
alleged fraud, oppression and violation of the Constitution, which
December 1996 and Assignment, Accession
called for the interpretation and application of laws, and did not
Agreement 4 (between Climax-Arimco Mining Corporation and
involve any mining dispute. The Court of Appeals also observed
Australasian Philippines Mining Inc.) dated 3 December 1996.
that there were no averments relating to particular acts
Respondent Climax Mining Corporation (Climax) and respondent
constituting fraud and oppression. It added that since
Australasian Philippines Mining Inc. (APMI) entered into
the Addendum Contract was executed in 1991, the action to
a Memorandum of Agreement 5 dated 1 June 1991 whereby the
annul it should have been brought not later than 1995, as the
former transferred its FTAA to the latter. iatdcjur
prescriptive period for an action for annulment is four years from
On 8 November 1999, petitioner Gonzales filed before the Panel the time of the discovery of the fraud. 12 When petitioner filed
of Arbitrators, Region II, Mines and Geosciences Bureau of the his complaint before the Panel in 1999, his action had already
Department of Environment and Natural Resources, against prescribed. Also, the Court of Appeals noted that fraud and
respondents Climax-Arimco Mining Corporation (Climax-Arimco), duress only make a contract voidable, 13 not inexistent, hence
Climax, and APMI, 6 a Complaint 7 seeking the declaration of the contract remains valid until annulled. The Court of Appeals
nullity or termination of the Addendum Contract, the FTAA, was of the opinion that the petition should have been settled
through arbitration under Republic Act No. 876 (The Arbitration
Law) as stated in Clause 19.1 of the Addendum Contract. The iii.
Court of Appeals therefore declared as invalid the orders dated
18 October 2001 and 25 June 2002 issued by the Panel of WHETHER THE HONORABLE COURT OF APPEALS
Arbitrators. On 28 January 2004, the Court of Appeals denied DEPARTED FROM THE RULES AND ESTABLISHED
petitioner's motion for reconsideration for lack of merit. 14 JURISPRUDENCE WHEN IT HELD THAT THE COMPLAINT
FILED BY THE PETITIONER FAILED TO ALLEGE ULTIMATE
Petitioner filed on 22 March 2004 this Petition for Review on FACTS OR PARTICULARS OF FRAUD.
Certiorari Under Rule 45 assailing the decision and resolution of
the Court of Appeals. Petitioner raises the following issues: iv.

A. WHETHER THE HONORABLE COURT OF APPEALS


DEPARTED FROM THE RULES AND ESTABLISHED
PROCEDURAL GROUND JURISPRUDENCE WHEN IT HELD THAT PETITIONER AND
RESPONDENTS SHOULD SUBMIT TO ARBITRATION
THE HONORABLE COURT OF APPEALS SHOULD HAVE UNDER R.A. 876.
SUMMARILY DISMISSED RESPONDENTS' PETITION A
QUO FOR FAILURE TO COMPLY WITH PROCEDURAL v.
REQUIREMENTS.
WHETHER THE HONORABLE COURT OF APPEALS
i. DEPARTED FROM THE RULES AND ESTABLISHED
JURISPRUDENCE WHEN IT HELD THAT THE ACTION TO
WHETHER THE HONORABLE COURT OF APPEALS DECLARE THE NULLITY OF THE ADDENDUM CONTRACT,
DEPARTED FROM THE RULES AND ESTABLISHED FTAA, OFAC AND AAAA ON THE GROUND OF FRAUD HAS
JURISPRUDENCE WHEN IT DID NOT DISMISS THE PRESCRIBED.
PETITION A QUO DESPITE RESPONDENTS' FAILURE TO
COMPLY WITH THE RULES ON DISCLOSURE IN THE The issues for resolution in this petition for review are:
"VERIFICATION AND CERTIFICATION" PORTION OF THEIR
PETITIONA QUO. (a) Whether there was forum-shopping on the part of
respondents for their failure to disclose to this Court their filing of
ii. a Petition to Compel for Arbitration before the Regional Trial
Court of Makati City, Branch 148, which is currently pending.
WHETHER THE HONORABLE COURT OF APPEALS
DEPARTED FROM THE RULES AND ESTABLISHED (b) Whether counsel for respondent Climax had authority to file
JURISPRUDENCE WHEN IT DID NOT DISMISS THE the petition for certiorari before the Court of Appeals considering
PETITION A QUO FILED BY RESPONDENT CLIMAX DESPITE that the signor of the petition forcertiorari's Verification and
THE LACK OF THE REQUISITE AUTHORITY TO FILE THE Certification of Non-forum Shopping was not authorized to sign
PETITION A QUO. the same in behalf of respondent Climax.

B. (c) Whether the complaint filed by petitioner raises a mining


dispute over which the Panel of Arbitrators has jurisdiction, or a
SUBSTANTIVE GROUND judicial question which should properly be brought before the
regular courts.
THE HONORABLE COURT OF APPEALS ERRED IN
GRANTING THE PETITION A QUO FILED BY RESPONDENTS (d) Whether the dispute between the parties should be brought
AND IN DENYING MOTION FOR RECONSIDERATION FILED for arbitration under Rep. Act No. 876.
BY PETITIONER FOR UTTER LACK OF BASIS IN FACT AND
IN LAW. Let us deal first with procedural matters.

i. Petitioner claims that respondents are guilty of forum-shopping


for failing to disclose before this Court that they had filed
WHETHER THE HONORABLE COURT OF APPEALS a Petition to Compel for Arbitration before the RTC of Makati
DEPARTED FROM THE RULES AND ESTABLISHED City. However, it cannot be determined from petitioner's mere
JURISPRUDENCE WHEN IT HELD THAT PETITIONER CEDED allegations in the Petition that the Petition to Compel for
HIS CLAIMS OVER THE MINERAL DEPOSITS LOCATED Arbitration instituted by respondent Climax-Arimco, involves
WITHIN THE ADDENDUM AREA OF INFLUENCE. CHDaAE related causes of action and the grant of the same or
substantially the same reliefs as those involved in the instant
ii. case. Petitioner did not attach copies of the Petition to Compel
for Arbitration or any order or resolution of the RTC of Makati
WHETHER THE HONORABLE COURT OF APPEALS
City related to that case. HIAESC
DEPARTED FROM THE RULES AND ESTABLISHED
JURISPRUDENCE WHEN IT HELD THAT THE PANEL OF
ARBITRATORS IS BEREFT OF JURISDICTION OVER THE
SUBJECT MATTER OF CASE NO. 058.
Furthermore, it can be gleaned from the nature of the two rights of the parties are with respect to the matter in
actions that the issues in the case before the RTC of Makati City controversy. 19
and in the petition for certiorari before the Court of Appeals are
different. A petition for certiorari raises the issue of whether or On the other hand, a mining dispute is a dispute involving (a)
not there was grave abuse of discretion, while the Petition to rights to mining areas, (b) mineral agreements, FTAAs, or
Compel for Arbitration seeks the implementation of the permits, and (c) surface owners, occupants and
arbitration clause in the agreement between the parties. claimholders/concessionaires. 20 Under Republic Act No. 7942
(otherwise known as the Philippine Mining Act of 1995), the
Petitioner next alleges that there was no authority granted by Panel of Arbitrators has exclusive and original jurisdiction to hear
respondent Climax to the law firm of Sycip Salazar Hernandez & and decide these mining disputes. 21 The Court of Appeals, in
Gatmaitan to file the petition before the Court of Appeals. There its questioned decision, correctly stated that the Panel's
is allegedly no Secretary's Certificate from respondent Climax jurisdiction is limited only to those mining disputes which raise
attached to the petition. The Verification and Certification only questions of fact or matters requiring the application of
contains a statement made by one Marianne M. Manzanas that technological knowledge and experience. 22
she is "also the authorized representative of [respondent
Climax]" without presenting further proof of such authority. In Pearson v. Intermediate Appellate Court, 23 this Court
Hence, it is argued that as to respondent Climax, the petition observed that the trend has been to make the adjudication of
filed before the Court of Appeals is an unauthorized act and the mining cases a purely administrative matter. 24Decisions 25 of
assailed orders of the Panel of Arbitrators have become final. the Supreme Court on mining disputes have recognized a
distinction between (1) the primary powers granted by pertinent
Under Section 3, Rule 46 of the Rules of Court, a petitioner is provisions of law to the then Secretary of Agriculture and Natural
required to submit, together with the petition, a sworn Resources (and the bureau directors) of an executive or
certification of non-forum shopping, and failure to comply with administrative nature, such as granting of license, permits, lease
this requirement is sufficient ground for dismissal of the petition. and contracts, or approving, rejecting, reinstating or canceling
The requirement that petitioner should sign the certificate of non- applications, or deciding conflicting applications, and (2)
forum shopping applies even to corporations, the Rules of Court controversies or disagreements of civil or contractual nature
making no distinction between natural and juridical persons. The between litigants which are questions of a judicial nature that
signatory in the case of the corporation should be "a duly may be adjudicated only by the courts of justice. This distinction
authorized director or officer of the corporation" who has is carried on even in Rep. Act No. 7942. 2005cdasia
knowledge of the matter being certified. 15 If, as in this case, the
petitioner is a corporation, a board resolution authorizing a The Complaint charged respondents with disregarding and
corporate officer to execute the certification against forum- ignoring the provisions of the Addendum Contract, violating the
shopping is necessary. A certification not signed by a duly purpose and spirit of the May 14, 1987 Letter of
authorized person renders the petition subject to dismissal. 16 Intent and February 28, 1989 Agreement, and acting in a
fraudulent and oppressive manner against petitioner and
On this point, we have to agree with petitioner. There appears to practicing fraud and deception against the
be no subsequent compliance with the requirement to attach a Government. 26 Petitioner alleged in his Complaint that under
board resolution authorizing the signor Marianne M. Manzanas the original agreements (the May 14, 1987 Letter of
to file the petition in behalf of respondent Climax. Respondent Intent and February 28, 1989 Agreement) respondent Climax-
also failed to refute this in its Comment. 17 However, this latter Arimco had committed to complete the Bankable Feasibility
issue becomes irrelevant in the light of our decision to deny this Study by 28 February 1992, but the same was not
petition for review for lack of jurisdiction by the Panel of accomplished. Instead, respondent Climax-Arimco, through false
Arbitrators over the complaint filed by petitioner, as will be and insidious representations and machinations by alleging
discussed below. technical and financial capacity, induced petitioner to enter into
the Addendum Contract and the FTAA in order to repeatedly
We now come to the meat of the case which revolves mainly extend the option period within which to conduct the feasibility
around the question of jurisdiction by the Panel of Arbitrators: study. In essence, petitioner alleges that respondents, conspiring
Does the Panel of Arbitrators have jurisdiction over the complaint and confederating with one another, misrepresented under
for declaration of nullity and/or termination of the subject the Addendum Contract and FTAA that respondent Climax-
contracts on the ground of fraud, oppression and violation of the Arimco possessed financial and technical capacity to put the
Constitution? This issue may be distilled into the more basic project into commercial production, when in truth it had no such
question of whether the Complaint raises a mining dispute or a qualification whatsoever to do so. By so doing, respondents
judicial question. have allegedly caused damage not only to petitioner but also to
the Republic of the Philippines. 27
A judicial question is a question that is proper for determination
by the courts, as opposed to a moot question or one properly It is apparent that the Panel of Arbitrators is bereft of jurisdiction
decided by the executive or legislative branch. 18 A judicial over the Complaint filed by petitioner. The basic issue in
question is raised when the determination of the question petitioner's Complaint is the presence of fraud or
involves the exercise of a judicial function; that is, the question misrepresentation allegedly attendant to the execution of
involves the determination of what the law is and what the legal the Addendum Contract and the other contracts emanating from
it, such that the contracts are rendered invalid and not binding
upon the parties. It avers that petitioner was misled by The Complaint is also not what is contemplated by Rep. Act No.
respondents into agreeing to the Addendum Contract. This 7942 when it says the dispute should involve FTAAs.
constitutes fraud which vitiated petitioner's consent, and under The Complaint is not exclusively within the jurisdiction of the
Article 1390 of the Civil Code, is one of the grounds for the Panel of Arbitrators just because, or for as long as, the dispute
annulment of a voidable contract. Voidable or annullable involves an FTAA. The Complaint raised the issue of the
contracts, before they are set aside, are existent, valid, and constitutionality of the FTAA, which is definitely a judicial
binding, and are effective and obligatory between the question. The question of constitutionality is exclusively within
parties. 28 They can be ratified. 29 the jurisdiction of the courts to resolve as this would clearly
involve the exercise of judicial power. The Panel of Arbitrators
Petitioner insists that the Complaint is actually one for the does not have jurisdiction over such an issue since it does not
declaration of nullity of void contracts. He argues that involve the application of technical knowledge and expertise
respondents, by their lack of financial and technical competence relating to mining. This the Panel of Arbitrators has even
to carry out the mining project, do not qualify to enter into a co- conceded in its Orders dated 18 October 2001 and 25 June
production, joint venture or production sharing agreement with 2002. At this juncture, it is worthy of note that in a case, 31 which
the Government, in circumvention of and in patent violation of was resolved only on 1 December 2004, this Court upheld the
the spirit and purpose of the Constitution, particularly Section 2, validity of the FTAA entered into by the Republic of the
Article XII thereof. Petitioner relies on the Civil Code for Philippines and WMC (Philippines), Inc. and constitutionality
support: 30 of Rep. Act No. 7942 and DENR Administrative Order 96-
40. 32 In fact, the Court took the case on an original petition,
Art. 1409. The following contracts are inexistent and void from recognizing "the exceptional character of the situation and the
the beginning: paramount public interest involved, as well as the necessity for a
ruling to put an end to the uncertainties plaguing the mining
(1) Those whose cause, object or purpose is contrary to law,
industry and the affected communities as a result of doubts case
morals, good customs, public order or public policy;
upon the constitutionality and validity of the Mining Act, the
xxx xxx xxx subject FTAA and future FTAAs, and the need to avert a
multiplicity of suits." 33
(7) Those expressly prohibited or declared void by law.

xxx xxx xxx


Arbitration before the Panel of Arbitrators is proper only when
Petitioner asserts that for circumventing and being in patent there is a disagreement between the parties as to some
violation of the Constitution, the Addendum Contract, the FTAA provisions of the contract between them, which needs the
and the other contracts are void contracts. As such, they do not interpretation and the application of that particular knowledge
produce any effect and cannot be ratified. and expertise possessed by members of that Panel. It is not
proper when one of the parties repudiates the existence or
However, whether the case involves void or voidable contracts is validity of such contract or agreement on the ground of fraud or
still a judicial question. It may, in some instances, involve oppression as in this case. The validity of the contract cannot be
questions of fact especially with regard to the determination of subject of arbitration proceedings. Allegations of fraud and
the circumstances of the execution of the contracts. But the duress in the execution of a contract are matters within the
resolution of the validity or voidness of the contracts remains a jurisdiction of the ordinary courts of law. These questions are
legal or judicial question as it requires the exercise of judicial legal in nature and require the application and interpretation of
function. It requires the ascertainment of what laws are laws and jurisprudence which is necessarily a judicial function.
applicable to the dispute, the interpretation and application of
those laws, and the rendering of a judgment based thereon. Petitioner also disagrees with the Court of Appeals' ruling that
Clearly, the dispute is not a mining conflict. It is essentially the case should be brought for arbitration under Rep. Act 876,
judicial. The complaint was not merely for the determination of pursuant to the arbitration clause in theAddendum
rights under the mining contracts since the very validity of those Contract which states that "[a]ll disputes arising out of or in
contracts is put in issue. connection with the Contract, which cannot be settled amicably
among the Parties, shall finally be settled under R.A. 876." He
The Complaint is not about a dispute involving rights to mining points out that respondents Climax and APMI are not parties to
areas, nor is it a dispute involving claimholders or the Addendum Contract and are thus not bound by the
concessionaires. The main question raised was the validity of arbitration clause in said contract.
the Addendum Contract, the FTAA and the subsequent
contracts. The question as to the rights of petitioner or We agree that the case should not be brought under the ambit
respondents to the mining area pursuant to these contracts, as of the Arbitration Law, but for a different reason. The question of
well as the question of whether or not petitioner had ceded his validity of the contract containing the agreement to submit to
mining claims in favor of respondents by way of execution of the arbitration will affect the applicability of the arbitration clause
questioned contracts, is merely corollary to the main issue, and itself. A party cannot rely on the contract and claim rights or
may not be resolved without first determining the main obligations under it and at the same time impugn its existence or
issue. aCIHcD validity. Indeed, litigants are enjoined from taking inconsistent
positions. As previously discussed, the complaint should have
been filed before the regular courts as it involved issues which all the defendants pending the decision of the Arbitration
are judicial in nature. Committee, to wit:

WHEREFORE, in view of the foregoing, the Petition for Review WHEREFORE, the Court hereby orders:
on Certiorari Under Rule 45 is DENIED. The Orders dated 18
October 2001 and 25 June 2002 of the Panel of Arbitrators are (a) Home Bankers & Trust Co. to produce and permit plaintiff to
SET ASIDE. Costs against petitioner Jorge Gonzales. inspect, copy and/or photograph the checking account deposit
ledger of Victor Tancuan's Account No. 1803-00605-3;
SO ORDERED.
(b) The Motions to Dismiss filed by all defendants denied, for
||| (Gonzales v. Climax Mining Ltd., G.R. No. 161957, [February lack of merit; and ITaCEc
28, 2005], 492 PHIL 682-697)
(c) Proceedings in this case against all defendants be
suspended pending award/decision in the arbitration
proceedings against Home Bankers and Trust Co.
525 PHIL 238-251
SO ORDERED. 9 (Emphasis supplied)
FIRST DIVISION
The above Omnibus Order was amended by the trial court in its
[G.R. No. 141818. June 22, 2006.] October 1, 1992 Order, 10 the dispositive portion of which reads
as follows:
INSULAR SAVINGS BANK, petitioner, vs. FAR EAST BANK
AND TRUST COMPANY, respondent. WHEREFORE, the Omnibus Order dated 30 April 1992 is hereby
reconsidered by deleting the phrase "since the complaint also
DECISION seeks exemplary damages, attorney's fees, litigation expenses
and costs of suit against HBT," on page 4 thereof and par. C of
YNARES-SANTIAGO, J p:
its dispositive portion is amended to read:
This petition for review on certiorari 1 assails the November 9,
(c) "Procedings against Home Bankers and Trust Co. are
1999 Order 2 of the Regional Trial Court of Makati City, Branch
suspended pending award/decision in the arbitration
135, in Civil Case No. 92-145 which dismissed the petition for
proceedings while those against individual defendants be
review for lack of jurisdiction and its February 1, 2000
immediately reinstated and continued."
Order 3 denying reconsideration thereof.
HBT and Tancuan's separate Motions for Reconsiderations are
The antecedent facts are as follows:
hereby denied, for lack of merit.
On December 11, 1991, Far East Bank and Trust Company
SO ORDERED. 11
(Respondent) filed a complaint against Home Bankers Trust and
Company (HBTC) 4 with the Philippine Clearing House On February 2, 1998, the PCHC Arbitration Committee rendered
Corporation's (PCHC) Arbitration Committee docketed as its decision in favor of respondent, 12 thus:
Arbicom Case No. 91-069. 5Respondent sought to recover from
the petitioner, the sum of P25,200,000.00 representing the total IN VIEW OF ALL THE FOREGOING, judgment is hereby
amount of the three checks drawn and debited against its rendered in favor of the plaintiff and against the defendant
clearing account. HBTC sent these checks to respondent for sentencing the latter to pay the plaintiff the sum of P25.2 million
clearing by operation of the PCHC clearing system. Thereafter, as principal. In view of the fact, however, that this amount was
respondent dishonored the checks for insufficiency of funds and split between the plaintiff and the defendant in the course of the
returned the checks to HBTC. However, the latter refused to proceedings, the amount to be paid by the defendant to the
accept them since the checks were returned by respondent after plaintiff should only be P12,600,000.00 plus interest on this latter
the reglementary regional clearing period. 6 amount at the rate of 12% per annum from February 11, 1992,
the date when the total amount of P25.2 Million was split
Meanwhile, on January 17, 1992, before the termination of the between plaintiff and defendant up to the date of payment.
arbitration proceedings, respondent filed another complaint but
this time with the Regional Trial Court (RTC) in Makati City In view of the facts found by the committee, no attorney's fees
docketed as Civil Case No. 92-145 for Sum of Money and nor other damages are awarded. cAaTED
Damages with Preliminary Attachment. The complaint was filed
not only against HBTC but also against Robert Young, Eugene SO ORDERED. 13
Arriesgado and Victor Tancuan (collectively known as
Defendants), who were the president and depositors of HBTC The motion for reconsideration filed by petitioner was denied by
respectively. 7 Aware of the arbitration proceedings between the Arbitration Committee. 14 Consequently, to appeal the
respondent and petitioner, the RTC, in an Omnibus Order dated decision of the Arbitration Committee in Arbicom Case No. 91-
April 30, 1992, 8 suspended the proceedings in the case against 069, petitioner filed a petition for review in the earlier case filed
by respondent in Branch 135 of the RTC of Makati and
docketed as Civil Case No. 92-145. 15 In an order dated
January 20, 1999, the RTC directed both petitioner and agreement embedded in their contract wherein they consent that
respondent to file their respective memoranda, after which, said any future dispute or controversy between its PCHC participants
petition would be deemed submitted for resolution.16 involving any check would be submitted to the Arbitration
Committee for arbitration. Petitioner and respondent are
Both parties filed several pleadings. On February 8, 1999, members of PCHC, thus they underwent arbitration proceedings.
respondent filed a Motion to Dismiss Petition for Review for Lack
of Jurisdiction, 17 which was opposed by the The PCHC has its own Rules of Procedure for Arbitration (PCHC
petitioner. 18 Respondent then filed its Reply to the Rules). However, this is governed by Republic Act No. 876, also
opposition, 19 to which petitioner filed a Rejoinder. 20 On August known as The Arbitration Law 26 and supplemented by the
16, 1999, respondent submitted its Surrejoinder. 21 Rules of Court. 27 Thus, we first thresh out the remedy of
petition for review availed of by the petitioner to appeal the order
On November 9, 1999, the RTC rendered the assailed Order of the Arbitration Committee.
which held, thus:
Sections 23, 24 and 29 of The Arbitration Law, and Section 13 of
Acting on plaintiff Far East Bank and Trust Company's "Motion the PCHC Rules, provide:
To Dismiss Petition For Review For Lack Of Jurisdiction",
considering that the petition for review is a separate and distinct SEC. 23. Confirmation of award. At any time within one month
case, the same must comply with all the requirements for filing after the award is made, any party to the controversy which was
initiatory pleadings for civil actions before this Court so that since arbitrated may apply to the court having jurisdiction, as
the commencement of the subject petition lacks the mandatory provided in Section 28, for an order confirming the award;
requirements provided for, except the payment of docket fees, and thereupon the court must grant such order unless the
for lack of jurisdiction, the petition for review is hereby dismissed. award is vacated, modified or corrected, as prescribed
herein. Notice of such motion must be served upon the adverse
SO ORDERED. 22 party or his attorney as prescribed by law for the service of such
notice upon an attorney in action in the same court.
The RTC denied petitioner's motion for
reconsideration, 23 hence, this petition on the sole ground, to SEC. 24. Grounds for vacating award. In any one of the
wit: following cases, the court must make an order vacating the
award upon the petition of any party to the controversy when
THE REGIONAL TRIAL COURT ERRED IN DISMISSING THE such party proves affirmatively that in the arbitration
PETITION OF PETITIONER FOR LACK OF JURISDICTION ON proceedings:
THE GROUND THAT IT SHOULD HAVE BEEN DOCKETED AS
A SEPARATE CASE. 24 (a) The award was procured by corruption, fraud or other undue
means; or
Petitioner contends that Civil Case No. 92-145 was merely
suspended to await the outcome of the arbitration case pending (b) That there was evident partiality or corruption in the
before the PCHC. Thus, any petition questioning the decision of arbitrators or any of them; or
the Arbitration Committee must be filed in Civil Case No. 92-145
and should not be docketed as a separate action. Likewise, (c) That the arbitrators were guilty of misconduct in refusing to
petitioner avers that had it filed a separate action, "this would postpone the hearing upon sufficient cause shown, or in refusing
have resulted in a multiplicity of suits, which is abhorred in to hear evidence pertinent and material to the controversy; that
procedure." HSDIaC one or more of the arbitrators was disqualified to act as such
under section nine hereof, and willfully refrained from disclosing
Meanwhile respondent avers that the RTC correctly dismissed such disqualification or of any other misbehavior by which the
the appeal from the award of private arbitrators since there is no rights of any party have been materially prejudiced; or
statutory basis for such appeal. Respondent argues that
petitioner's claim that the parties by agreement had conferred on (d) That the arbitrators exceeded their powers, or so imperfectly
the RTC appellate jurisdiction over decisions of private executed them, that a mutual, final and definite award upon the
arbitrators is erroneous because they cannot confer a non- subject matter submitted to them was not made. IEAaST
existent jurisdiction on the RTC or any court. Furthermore, the
petition for review filed by petitioner violated the rule on xxx xxx xxx
commencing an original action under Section 5, Rule 1, and the
raffle of cases under Section 2, Rule 20 of the Rules of Court, SEC. 25. Grounds for modifying or correcting award. In any
when it filed the same in Branch 135 of the RTC of Makati where one of the following cases, the court must make an order
there was already a pending original action, i.e., Civil Case No. modifying or correcting the award, upon the application of any
92-145. party to the controversy which was arbitrated:

The petition lacks merit.

The Philippine Clearing House Corporation was created to (a) Where there was an evident miscalculation of figures, or an
facilitate the clearing of checks of member banks. Among these evident mistake in the description of any person, thing or
member banks exists a compromissoire, 25 or an arbitration property referred to in the award; or
(b) Where the arbitrators have awarded upon a matter not Court with the Court of Appeals on questions of fact, of law, or
submitted to them, not affecting the merits of the decision upon mixed questions of fact and law. 35 Lastly, petitioner may file a
the matter submitted; or petition for certiorari under Rule 65 of the Rules of Court on the
ground that the Arbitrator Committee acted without or in excess
(c) Where the award is imperfect in a matter of form not affecting of its jurisdiction or with grave abuse of discretion amounting to
the merits of the controversy, and if it had been a commissioner's lack or excess of jurisdiction. Since this case involves acts or
report, the defect could have been amended or disregarded by omissions of a quasi-judicial agency, the petition should be filed
the court. in and cognizable only by the Court of Appeals. 36

The order may modify and correct the award so as to effect the In this instance, petitioner did not avail of any of the
intent thereof and promote justice between the parties. abovementioned remedies available to it. Instead it filed a
petition for review with the RTC where Civil Case No. 92-145 is
SEC. 29. Appeals. An appeal may be taken from an order pending pursuant to Section 13 of the PCHC Rules to sustain its
made in a proceeding under this Act, or from judgment entered action. Clearly, it erred in the procedure it chose for judicial
upon an award through certiorari proceedings, but such appeals review of the arbitral award.
shall be limited to questions of law. The proceedings upon
such an appeal, including the judgment thereon shall be Having established that petitioner failed to avail of the
governed by the Rules of Court insofar as they are applicable. abovementioned remedies, we now discuss the issue of the
jurisdiction of the trial court with respect to the petition for review
AMENDED ARBITRATION RULES OF PROCEDURE OF PCHC filed by petitioner.

Sec. 13. The findings of facts of the decision or award Jurisdiction is the authority to hear and determine a cause the
rendered by the Arbitration Committee or by the sole right to act in a case. 37 Jurisdiction over the subject matter is
Arbitrator as the case may be shall be final and conclusive the power to hear and determine the general class to which the
upon all the parties in said arbitration dispute. The decision proceedings in question belong. Jurisdiction over the subject
or award of the Arbitration Committee or of the Sole Arbitrator or matter is conferred by law and not by the consent or
of the Board of Directors, as the case may be, shall acquiescence of any or all of the parties or by erroneous belief of
be appealable only on questions of law to any of the the court that it exists. 38
Regional Trial Courts in the National Capital Region where
the Head Office of any of the parties is located. The appellant In the instant case, petitioner and respondent have agreed that
shall perfect his appeal by filing a notice of appeal to the the PCHC Rules would govern in case of controversy. However,
Arbitration Secretariat and filing a Petition with the Regional Trial since the PCHC Rules came about only as a result of an
Court of the National Capital Region for the review of the agreement between and among member banks of PCHC and
decision or award of the committee or sole arbitrator or of the not by law, it cannot confer jurisdiction to the RTC. Thus, the
Board of Directors, as the case may be, within a non-extendible portion of the PCHC Rules granting jurisdiction to the RTC to
period of fifteen (15) days from and after its receipt of the order review arbitral awards, only on questions of law, cannot be given
denying or granting said motion for reconsideration or new trial effect. HTDcCE
had been filed, within a non-extendible period of fifteen (15) days
from and after its receipt of the order denying or granting said Consequently, the proper recourse of petitioner from the denial
motion for reconsideration or of the decision rendered after the of its motion for reconsideration by the Arbitration Committee is
new trial if one had been granted. DEScaT to file either a motion to vacate the arbitral award with the RTC, a
petition for review with the Court of Appeals under Rule 43 of the
xxx xxx xxx (Emphasis supplied) Rules of Court, or a petition for certiorari under Rule 65 of the
Rules of Court. In the case at bar, petitioner filed a petition for
As provided in the PCHC Rules, the findings of facts of the review with the RTC when the same should have been filed with
decision or award rendered by the Arbitration Committee shall be the Court of Appeals under Rule 43 of the Rules of Court. Thus,
final and conclusive upon all the parties in said arbitration the RTC of Makati did not err in dismissing the petition for review
dispute. 28 Under Article 2044 29 of the New Civil Code, the for lack of jurisdiction but not on the ground that petitioner should
validity of any stipulation on the finality of the arbitrators' award have filed a separate case from Civil Case No. 92-145 but on the
or decision is recognized. However, where the conditions necessity of filing the correct petition in the proper court. It is
described in Articles 2038, 30 2039 31 and 2040 32 applicable to immaterial whether petitioner filed the petition for review in Civil
both compromises and arbitrations are obtaining, the arbitrators' Case No. 92-145 as an appeal of the arbitral award or whether it
award may be annulled or rescinded. 33Consequently, the filed a separate case in the RTC, considering that the RTC will
decision of the Arbitration Committee is subject to judicial review. only have jurisdiction over an arbitral award in cases of motions
to vacate the same. Otherwise, as elucidated herein, the Court
Furthermore, petitioner had several judicial remedies available at
of Appeals retains jurisdiction in petitions for review or in
its disposal after the Arbitration Committee denied its Motion for
petitions for certiorari. Consequently, petitioner's arguments, with
Reconsideration. It may petition the proper RTC to issue an
respect to the filing of separate action from Civil Case No. 92-
order vacating the award on the grounds provided for under
145 resulting in a multiplicity of suits, cannot be given due
Section 24 ofthe Arbitration Law. 34 Petitioner likewise has the
course.
option to file a petition for review under Rule 43 of the Rules of
Alternative dispute resolution methods or ADRs like WHEREFORE, in light of the foregoing, the petition is DENIED.
arbitration, mediation, negotiation and conciliation are The November 9, 1999 Order of the Regional Trial Court of
encouraged by the Supreme Court. By enabling parties to Makati City, Branch 135, in Civil Case No. 92-145 which
resolve their disputes amicably, they provide solutions that are dismissed the petition for review for lack of jurisdiction and the
less time-consuming, less tedious, less confrontational, and February 1, 2000 Order denying its reconsideration, are
more productive of goodwill and lasting relationships. 39 It must AFFIRMED.
be borne in mind that arbitration proceedings are mainly
governed by the Arbitration Law and suppletorily by the Rules of SO ORDERED.
Court.
||| (Insular Savings Bank v. Far East Bank & Trust Co., G.R. No.
141818, [June 22, 2006], 525 PHIL 238-251)

Das könnte Ihnen auch gefallen