EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?
NOTES: 1) SAEP-1160 Section 8 details Minimum Test Package Requirements for Projects (Plant Piping, Pipelines, Equipment). Usage of SAEP-
1160 is mandatory when referenced by Sch Q for contracts with December 2005 cut-off dates and later.
2) Pressure Test Packages are (an integral part of) Test Procedures (See SAES-A-004 definition). Both Contract Sch Q & SAEP-1160 require a
Pressure Testing Procedure, along with other procedures & a Test Package for effective/safe pressure testing work control.
3) Submit a single multiple document package as follows (30 days before the start of work per Sch Q) for Company approval:
a) Three mandatory Pressure Test Procedures (as applicable) can be combined into one (Hydrotest, Pneumatic Test,
Bubble Leak Test). b) Sample Test package with applicable QC records, Forms (per Attachment 1 of the Checklist and as
listed below). c) A Re-instatement Procedure and Checklist (Utilize SAIC-A-2006 & SATR-A-2011
or QC forms meeting SATR minimum content). d) Pressure Test System Matrix (Modified Piping Design Line Index)
per checklist as listed below. e) Pressure Test Package Database - Sample Status
Report (per checklist as listed below).
4) Sample Test Package System ID & Status Report (Database). This is mandatory on large projects. Procedures shall detail Organizational Control
responsibilities for test packages & have provisions for "lost packages" & other system controls for test packages from package design through
system completion (MCC) and the QC certification process including turnover of records.
5) Pressure Test Matrix is a modified line list showing all systems and proposed pressure test design for SA approval. Reduce review time significantly
& improve efficiency by performing a close review of Pressure Test Matrix & associated system information early on in major projects. "Critical Path" to
MCC is nearly always Test Package Completion. Delays are often due to inefficiency, poor organization and planning, a lack of dedicated manpower
solely for Pressure Test Package development, coordination, clearance, & inadequate test planning based on a system approach.
6) Test Package Format (Organization of Sections) shall be in the most efficient manner possible to eliminate package size and yet contain all
applicable/important test information and documents needed for safe and correct system pressure testing. Copies of any procedures (Pressure Test,
Leak Test, Reinstatement) shall only be provided with test packages on review for initial approval by Company. Procedure copies (Pressure Testing,
GI-2.102, etc) shall be kept at test sites (test manifolds) with associated Safe Work Permits. Combining QC forms is encouraged. SATR use is
required or alternatively, QC test reports shall contain SATR elements. Increase efficiency & eliminate waste.
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
Test Package Database & Format (Minimum Requirements)
A
Test Package Minimum Content is per Attachment 1
SAEP-1160,
A1 Note: This checklist details SAEP-1160 specific
Section 8
requirements
Pressure Test Matrix (Design) uses a modified system line list and
contains specific proposed test information such as system names, line
numbers, testing design data (system class, design/test pressures
proposed), proposed test medium, test type (Hydrostatic or Pneumatic SAEP-1160, Para.
A2 strength test, Service Test, Bubble Leak Test, flushing requirements, 5.1,
proposed Lay-up, special considerations/treatments, Chemical cleaning, Para. 5.2
mechanical cleaning, internal FBE coating, and other pressure test
design considerations within Remarks section. Submit this Matrix along
with a Sample Package
Page 1 of 7
Features of the database shall be compatible (linked = preference) with
other SAEP-1160 required databases such as Welding & NDT to allow
efficient test package clearance control practices on a system or line
designation basis. SAEP-1160, Para.
A4 Note: NDT & other special processes (PWHT, PMI, Coatings, etc) 5.1,
frequently hold up test package issuance. To improve efficiency, link Para. 5.2
databases to improve package coordination, prevent rework and
retesting, and identify/target outstanding special process work
Page 2 of 7
SAUDI ARAMCO ID/PID - REV 0- 18-May-05 (Standards Cutoff -March 2012) Rev 6 31-Mar-12
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
Index Page denotes Package Content and has specific signoffs for SAEP-1160,
A7
Quality Control/Assurance. This can be indexed by Section. Section 8
Detailed Weld Map (Isos for Plant Piping, pipelines use isos or sketch SAEP-1160,
C2
with detailed notes and legend as approved by Company) Section 8
NDE Records (MT, PT, RT, UT) showing extent, sequence on NDE and SAEP-1160,
C3
selection meeting project specifications Section 8
Page 3 of 7
SAUDI ARAMCO ID/PID - REV 0- 18-May-05 (Standards Cutoff -March 2012) Rev 6 31-Mar-12
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
SAEP-1160,
C6 Flange Joint Assembly Inspection Report (SATR-L-2001).
Section 8
SAEP-1160,
C7 Internal Cleanliness / Flushing Report (SATR-A-2008)
Section 8
SAEP-1160,
C8 Verification of System Readiness for Testing (SAIC-A-2004)
Section 8
SAEP-1160,
C9 Pressure Test Report Form (SATR-A-2001)
Section 8
SAEP-1160,
C11 Reinstatement Procedure QC form & Instructions.
Section 8
E System Lay-up
SAEP-1160,
E1 System Lay-Up Certificate Form (SATR-A-2009)
Section 8
REMARKS:
REFERENCE DOCUMENTS:
1. SAEP-1160 - Tracking and Reporting of Welding, NDT and Pressure Testing for Capital Projects. (10 July 2011)
Page 4 of 7
SAUDI ARAMCO ID/PID - REV 0- 18-May-05 (Standards Cutoff -March 2012) Rev 6 31-Mar-12
Page 5 of 7
SAUDI ARAMCO ID/PID - REV 0- 18-May-05 (Standards Cutoff -March 2012) Rev 6 31-Mar-12
Test Pack
Preparation Engineering Contractor QC
Pre-Test
Punch (NOTE: Use form SATR-A-2007)
Construction Contractor QC
Listing
Clear 'A'
Items Construction Contractor QC
S. Aramco
Pre-Test
Punch
SAPMT PID Proponent
Listing (By Request)
Clear
S. Aramco
Construction Contractor QC SAPMT PID
'A' Items
Flushing &
Cleanliness Construction Contractor QC SAPMT PID Proponent
(By
Request)
Pressure
Testing Construction Contractor QC SAPMT PID Proponent
System
Lay-Up Construction Contractor QC SAPMT PID Proponent
(By
Request)
Reinstate
System
S. Aramco
Final Insp for
MCC SAPMT PID Proponent
Page 7 of 7