OBJECTIVE
At the end of this course student acquires the capacity to assess the soil
condition at a given location in order to sugest suitable foundation and also gains
the knowledge to design various foundations.
UNIT I SITE INVESTIGATION AND SELECTION OF FOUNDATION 9
Scope and objectives Methods of exploration-auguring and boring Water boring and
rotatory drilling Depth of boring Spacing of bore hole - Sampling Representative
and undisturbed sampling sampling techniques Split spoon sampler, Thin tube
sampler, Stationary piston sampler Bore log report Penetration tests (SPT and
SCPT) Data interpretation (Strength parameters and Liquefaction potential)
Selection of foundation based on soil condition.
UNIT II SHALLOW FOUNDATION 9
Introduction Location and depth of foundation codal provisions bearing capacity of
shallow foundation on homogeneous deposits Terzaghis formula and BIS formula
factors affecting bearing capacity problems - Bearing Capacity from insitu tests (SPT,
SCPT and plate load) Allowable bearing pressure, Settlement Components of
settlement Determination of settlement of foundations on granular and clay deposits
Allowable settlements Codal provision Methods of minimising settlement, differential
settlement.
UNIT III FOOTINGS AND RAFTS 9
Types of foundation Contact pressure distribution below footings and raft - Isolated
and combined footings Types and proportioning - Mat foundation Types, applications
uses and proportioning-- floating foundation.
UNIT IV PILES 9
Types of piles and their function Factors influencing the selection of pile Carrying
capacity of single pile in granular and cohesive soil - Static formula - dynamic formulae
(Engineering news and Hileys) Capacity from insitu tests (SPT and SCPT) Negative
skin friction uplift capacity Group capacity by different methods (Felds rule,
Converse Labarra formula and block failure criterion) Settlement of pile groups
Interpretation of pile load test Forces on pile caps under reamed piles Capacity
under compression and uplift.
UNIT V RETAINING WALLS 9
Plastic equilibrium in soils active and passive states Rankines theory cohesionless
and cohesive soil - Coloumbs wedge theory condition for critical failure plane - Earth
pressure on retaining walls of simple configurations Graphical methods (Rebhann and
Culmann) - pressure on the wall due to line load Stability of retaining walls.
TOTAL: 45 PERIODS
TEXT BOOKS
1. Murthy, V.N.S, Soil Mechanics and Foundation Engineering, UBS Publishers
Distribution Ltd, New Delhi, 1999.
2. Gopal Ranjan and Rao, A.S.R. Basic and Applied Soil Mechanics, Wiley Eastern
Ltd., New Delhi (India), 2003.
REFERENCES
1. Das, B.M. Principles of Foundation Engineering (Fifth edition), Thomson Books /
COLE, 2003
2. Bowles J.E, Foundation analysis and design, McGraw-Hill, 1994
3. Punmia, B.C., Soil Mechanics and Foundations, Laxmi publications pvt. Ltd., New
Delhi, 1995.
4. Venkatramaiah,C.Geotechnical Engineering, New Age International Publishers,
New Delhi, 1995
Chapter -1
Scope:
Site investigations or subsurface explorations are done for obtaining the subsurface
conditions at the site of proposed construction.
It includes determination of soil profile at the site, taking samples and determining the
engineering properties of the soils, and in-situ testing of the soil.
Objectives:
Selection of the type and the depth of foundation suitable for a given structure.
Prediction of lateral earth pressure for structures like retaining walls, sheet pile
bulkheads, and braced cuts.
EXPLORATION PROGRAM:
The purpose of the exploration program is to determine, within practical limits, the
stratification and engineering properties of the soils underlying the site.
The principal properties of interest will be the strength, deformation, and hydraulic
characteristics.
The program should be planned so that the maximum amount of information can be
obtained at minimum cost.
STAGES IN EXPLORATION:
Sub surface explorations are generally carried out in three stages. They are:
Reconnaissance.
Preliminary exploration.
Detailed exploration.
Reconnaissance:
Site reconnaissance is the first step in the sub- surface exploration program.
It includes a visit to the site and to study the maps and other relevant records available.
It helps in deciding the method of exploration to be adopted, types of samples to be taken
and in-situ testing of soils.
Preliminary exploration:
The aim of the Preliminary Exploration is to determine the composition of each soil
stratum at the site. The depth of bed rock and ground water table is also determined.
It is done in the form of few borings or test bit to collect the soil.
Test are conducted with cone penetrometers and sounding rods to obtain information
about strength and compressibility of soils.
Geophysical method also used in preliminary exploration for locating the boundaries of
different strata.
DETAILED EXPLORATION:
The purpose of detailed exploration is to determine the properties of soil in different
strata.
It includes an extensive boring program sampling and testing of samples in laboratory.
Field test such as vane shear test, plate load test are conducted for heavy structures such
as bridges, dams, and multi storey buildings it is conducted to find the natural properties
of soil.
For small projects especially at sites where the soil structure is uniform detailed
investigation is not required.
METHODS OF EXPLORATION:
The available methods of exploration can be broadly classified into two categories:
Direct method.
Indirect method.
Direct Methods:
Open Excavation.
Boring Methods.
Indirect Methods:
Seismic Method.
Electric Resistivity Method.
METHODS OF BORING:
Auger boring.
Wash boring .
Rotary drilling.
Auger boring:
Soil auger is a device that is useful for advancing a bore hole into the ground.
Augers may be hand-operated or power-driven; the former are used for relatively small
depths (less than 3 to 5 m), while the latter are used for greater depths.
The soil auger is advanced by rotating it while pressing it into the soil at the same time.
It is used primarily in soils in which the bore hole can be kept dry and unsupported.
As soon as the auger gets filled with soil, it is taken out and the soil sample collected.
Two common types of augers, the post hole auger and the helical auger.
If the sides of the hole cannot remain unsupported, the soil is prevented from falling in by
means of a pipe known as shell or casing.
The casing is to be driven first and then the auger; whenever the casing is to be extended,
the auger has to be withdrawn, this being an impediment to quick progress of the work.
An equipment called a boring rig is employed for power-driven augers, which may be
used up to 50 m depth (A hand rig may be sufficient for borings up to 25 m in depth).
Casings may be used for sands or stiff clays. Soft rock or gravel can be broken by chisel
bits attached to drill rods. Sand pumps are used in the case of sandy soils.
Water boring:
Wash boring is commonly used for exploration below ground water table for which the
auger method is unsuitable.
This method may be used in all kinds of soils except those mixed with gravel and
boulders.
Initially, the hole is advanced for a short depth by using an auger. A casing pipe is pushed
in and driven with a drop weight.
A hollow drill bit is screwed to a hollow drill rod connected to a rope passing over a
pulley and supportedby a tripod.
Water jet under pressure is forced through the rod and the bit into the hole.
This loosens the soil at the lower end and forces the soil-water suspension upwards along
the annular surface between the rod and the side of the hole.
This suspension is led to a settling tank where the soil particles settle while the water
overflows into a sump. The water collected in the sump is used for circulation again.
The soil particles collected represent a very disturbed sample and is not very useful for
the evaluation of the engineering properties.
Wash borings are primarily used for advancing bore holes; whenever a soil sample is
required, the chopping bit is to be replaced by a sampler.
The change of the rate of progress and change of color of wash water indicate changes in
soil strata.
Rotatory drilling:
This method is fast in rock formations.
A drill bit, fixed to the lower end of a drill rod, is rotated by power while being kept in
firm contact with the hole.
Drilling fluid or bentonite slurry is forced under pressure through the drill rod and it
comes up bringing the cuttings to the surface.
Even rock cores may be obtained by using suitable diamond drill bits.
This method is not used in porous deposits as the consumption of drilling fluid would be
prohibitively high.
Depth of Borings:
In order to furnish adequate information for settlement predictions, the borings should
penetrate all strata that could consolidate significantly under the load of the structure.
This necessarily means that, for important and heavy structures such as bridges and tall
buildings, the borings should extend to rock.
For smaller structures, however, the depth of boring may be estimated from the results of
previous investigations in the vicinity of the site, and from geologic evidence.
Experience indicates that damaging settlement is unlikely to occur when the additional
stress imposed on the soil due to the weight of the structure is less than 10% of the initial
stress in the soil due to self-weight.
Based on this, recommended depths of borings for buildings are about 3.5 m and 6.5 m
for single- and two-storey buildings.
For dams and embankments, the depth ranges between half the height to twice the height
depending upon the foundation soil.
According to IS: 1892-1979: The depth of exploration required depends upon the type
of the proposed structure, its total weight, the size, shape and disposition of the loaded
area, soil profile and the physical properties of the soil stratum.
Spacing of bore hole:
The lateral extent of exploration and the spacing of bore holes depend mainly on the variation of
the strata in the horizontal direction.
The exploration should be extensive so as to reveal major changes in the properties of the sub-
surface strata.
For small and less important buildings, even one bore hole or trial pit in the centre may suffice.
But for compact buildings, covering an area of about 0.4 hectares, there should be at least 5 bore
holes, one at the centre and four near the corners. As shown in the fig.
For large, multistoried buildings the bore holes should be drilled at all the corners and also at
important locations.
The spacing between the bore holes is generally kept between 10 to 30 m, depending upon the
variation in the subsurface conditions and loading. As shown in the fig.
For highways, subsurface explorations are usually carried out along the proposed centre line or
along the propose ditch line.
The spacing of bore holes usually varies between 150 and 300 m. if the sub-strata is erratic the
spacing may be reduced to even 30 m.
In case of concrete dams, the spacing of bore holes generally varies between 40 and 80 m.
Sampling:
Soil Sampling is the process of obtaining samples of soil from the desired depth at the
desired location in a natural soil deposit, with a view to assessing the engineering
properties of the soil for ensuring a proper design of the foundation.
The ultimate aim of the exploration methods described earlier, it must be remembered, is
to obtain soil samples besides obtaining all relevant information regarding the strata. The
devices used for the purpose of sampling are known as soil samplers.
Determination of ground water level is also considered part of the process of soil
sampling.
Types of Samples
Broadly speaking, samples of soil taken out of natural deposits for testing may be classified as:
Disturbed sample
undisturbed samples,
depending upon the degree of disturbance caused during sampling operations.
Disturbed sample:
A disturbed sample is that in which the natural structure of the soil gets modified partly
or fully during sampling.
Disturbed samples may be further subdivided as:
(i) Non-representative samples
(ii) Representative samples.
Non-representative samples
Non-representative samples consist of mixture of materials from various soil or rock
strata or are samples from which some mineral constituents have been lost or got mixed
up.
Soil samples obtained from auger borings and wash borings are non-representative
samples. These are suitable only for providing qualitative information such as major
changes in subsurface strata.
Representative samples.
Representative samples contain all the mineral constituents of the soil, but the structure of
the soil may be significantly disturbed.
The water content may also have changed. They are suitable for identification and for the
determination of certain physical properties such as Atterberg limits and grain specific
gravity.
UNDISTURBED SAMPLES:
Undisturbed sample is that in which the natural structure and other physical properties
remain preserved.
Undisturbed, in this context, is a purely relative term, since a truly undisturbed sample
can perhaps be never obtained as some little degree of disturbance is absolutely inevitable
even in the best method of sampling devised till date.
Undisturbed samples may be defined as those in which the material has been subjected
to minimum disturbance so that the samples are suitable for strength tests and
consolidation tests.
Tube samples and chunk samples are considered to fall in this category.
Besides using a suitable tube sampler for the purpose, undisturbed samples may be
obtained as chunks from the bottom of test pits, provided the soil possesses at least
some cohesion.
Sample Disturbance
The design features of a sampler, governing the degree of disturbance of a soil sample are
the dimensions of the cutting edge and those of the sampling tube, the characteristics of
the non-return valve and the wall friction. In addition, the method of sampling also
affects the sample disturbance.
The walls of the sampler should be kept smooth and properly oiled to reduce wall friction
in order that sample disturbance be minimized. The non-return valve should have a large
orifice to allow the air and water to escape quickly and easily when driving the sampler.
Area ratio is the most critical factor which affects sample disturbance; it indicates the
ratio of displaced volume of soil to that of the soil sample collected.
If Ar is less than 10%, the sample disturbance is supposed to be small. Ar may be as high
as 30% for a thick wall sampler like split spoon and may be as low as 6 to 9% for thin
wall samplers like shelby tubes.
The inside clearance, CI, should not be more than 1 to 3%, the outside clearance Co
should also not be much greater than CI.
Inside clearance allows for elastic expansion of the soil as it enters the tube, reduces
frictional drag on the sample from the wall of the tube, and helps to retain the core.
Outside clearance facilitates the withdrawal of the sample from the ground.
The recovery ratio Rr = L/H
Where, L = length of the sample within the tube, and
H = depth of penetration of the sampling tube.
This value should be 96 to 98% for a satisfactory undisturbed sample. This concept is
more commonly used in the case of rock cores.
Sampling techniques:
Split spoon sampler,
Thin tube sampler,
Stationary piston sampler.
Split-Spoon Sampler
The split spoon sampler is basically a thick-walled steel tube, split length wise. The
sampler as Standardized by the I.S.I. (IS: 2131-1986Standard Penetration Test for
soils) is shown in Fig.
A drive shoe attached to the lower end serves as the cutting edge. A sample head may be
screwed at the upper end of split spoon.
The standard size of the spoon sampler is of 35 mm internal and 50.8 mm external
diameter.
The sampler is lowered to the bottom of the bore hole by attaching it to the drill rod.
The sampler is then driven by forcing it into the soil by blows from a hammer.
The assembly of the sampler is then extracted from the hole and the cutting edge and
coupling at the top are unscrewed. The two halves of the barrel are separated and the
sample is thus exposed. The sample may be placed in a glass jar and sealed, after visual
examination.
If samples need not be examined in the field, a liner is inserted inside the split spoon.
After separating the two halves, the liner with the sample is sealed with wax.
Thin tube sampler:
Thin-walled sampler, as standardised by the ISI (I.S.: 2132-1986 Code of Practice for
Thin-walled Tube Sampling of Soils), is shown in Fig.
The length of the tube is 5 to 10 times the diameter for sandy soils and 10 15 times the
diameter for clayey soils.
The diameter generally varies between 40 and 125 mm, and the thickness varies from
1.25 to 3.15 mm.
The sampler tube is attached to the drilling rod and lowered to the bottom of the bore
hole.
It is then pushed into the soil. Care shall be taken to push the tube into the soil by a
continuous rapid motion without impact or twisting.
The tube should be pushed to the length provided for the sample. At least 5 minutes after
the tube into its final position, the tube is turned 2 revolutions to shear off the sample at
the bottom before it is withdrawn.
The tube is taken out and its ends are sealed before the transportation. These are used for
obtaining undisturbed samples of clay.