Beruflich Dokumente
Kultur Dokumente
3, JULY 2012
AbstractThis paper presents a general fault-location method [10], [11], or even more terminals [12][14]. These multiter-
for large transmission networks which uses phasor measurement minal methods are less influenced by the fault resistance and re-
unit (PMU) voltage measurements where the injected current at mote terminal systems impedance, and are theoretically more
a fault point can be calculated by using the voltage change and its
relevant transfer impedance on any bus. A two-stage fault-location accurate.
optimization model is proposed, along with defining a matching de- Although existing multiterminal algorithms can achieve high
gree index. The first stage is the fault region identification stage, accuracy in locating faults, they are limited to a fault location
which uses the matching degree index to determine the suspicious in a transmission network where phasor measurement units
fault region in order to reduce the search area. The second stage is (PMUs) are installed with at least one terminal for every line.
used to identify the exact fault line and fault distance. A method to
determine optimal PMU placement is also proposed in this paper. Practically, PMUs cannot be installed with such density on
Case studies verify that the proposed fault-location algorithm and transmission networks due to budget restrictions. For scenarios
optimal PMU placement scheme can locate faults in large transmis- where many measurements are not available, these existing
sion networks quickly and accurately without requiring fault-type methods are no longer available. Therefore, a fault-location
classification or fault phase selection. methodology based on fewer measurements for large-scale
Index TermsBus-impedance matrix, fault location, matching transmission networks can be promising due to its low cost and
degree index, optimal phasor measurement unit (PMU) placement, practicality.
voltage measurements.
A number of groups have studied this capability gap
[15][18]. A fault-location method based on matching the
I. INTRODUCTION during-fault recorded waveforms with simulated waveforms
was described in [15]. However, the proposed approach needed
exhaustive simulations, and was heavily dependent on the
(4)
(5)
of line , and . The positive-sequence network
being energized by the fault current is shown in Fig. 1. The current injection is then derived as follows:
The equivalent circuit is utilized to model the transmission
lines. In Fig. 1, is the equivalent impedance of line . (6)
The effect of shunt capacitances is taken into account by means
From (6), the fault current injection can be calculated by
of admittances .
using the voltage change on any bus and its relevant transfer
Since the positive-sequence network is the only network ex-
impedance.
isting for all types of faults, it is used for the analysis in the
Suppose two PMUs are installed on two buses and . The
following discussions. All quantities, if not specifically labeled,
fault current injection calculated from these two buses should
refer to positive-sequence quantities.
be equal, i.e.,
In the prefault period, the bus-impedance matrix can be
calculated by inverting the bus-admittance matrix of the pre- (7)
fault network, where
Assuming there are PMUs available in the transmission
network, the following equations can be established on the fault
(1) bus, similar to (7)
(8)
In the during-fault period, the fault node- can be treated as where is defined as
an additional current injection bus, letting . Then,
a new bus-impedance matrix is obtained to represent the (9)
during-fault network. The dimension of is .
can be derived by modifying the corresponding elements of where represents the bus where a PMU is
matrix [19]. Then, the matrix has the form, as shown in placed.
(2) at the bottom of the page. The transfer impedances from It can be seen from (9) that is only dependent on the
the fault bus to other buses are measured voltage change and transfer impedance, and the latter
of particular interest for fault analysis, and are helpful for is the function of the fault-location variable . In other words,
estimating the fault location. is independent of fault resistance, fault type, and the pre-
From Fig. 1, the following nodal equation can be derived: fault loading condition. Therefore, is a function of fault
distance , where
(10)
(3) In this paper, is defined as the fault-location factor,
which provides an efficient index for locating the fault position
in the transmission network.
(2)
1646 IEEE TRANSACTIONS ON POWER DELIVERY, VOL. 27, NO. 3, JULY 2012
(11)
where .
Theoretically, the matching degree is equal to zero only at
the exact fault point. However, this may not occur because of
errors in measurements and computational processing. There-
fore, the fault-location problem is modeled as a 1-D optimiza-
tion problem where
(12)
The overall flowchart of the proposed fault-location algo- If a fault occurs at a bus such as , from (9), the fault-location
rithm is shown in Fig. 2. This algorithm consists of two stages: factor is calculated as
Stage 1) Fault region identification.
Stage 2) Exact fault location.
Stage 1) is used to find the suspicious fault region. Stage 2) (13)
is used to find the exact fault position by searching all possible
fault lines in the suspicious fault region. where is the element of the prefault impedance
Stage 1: Fault region identification matrix . In Fig. 3, the three PMUs are placed at buses
For a large-scale transmission network, searching every trans- and , so , and .
mission line is time-consuming. Hence, the purpose of Stage From (11) and (13), if a fault occurs at a bus, such as , then
1 is to narrow down the search region and reduce the search the matching degree is calculated as
time. Fig. 3 illustrates the process of identifying the possible
fault region.
In Fig. 3, the PMUs are at buses , and , and a fault has
occurred at point . From (11), the matching degree will be (14)
zero at the fault point if all errors are neglected. Furthermore,
it can be found that the calculated at bus or , which are near
fault point , is close to zero, while at bus or is much larger where .
than zero. Generally speaking, are small for buses which are In the case of a high impedance fault in a large system, some
near fault position and are large for buses which are far from voltage changes may be too small, which means the estimated
fault position . location may be wrong. Therefore, we only use partial PMUs
In order to identify the fault region, we first compute the voltage measurements to calculate the matching degree instead
matching degree at each bus in the network, and then sort of using all PMUs voltage measurements in a large system.
these matching degrees. Several buses whose matching degrees We select the data depending on the change of the bus voltage
are very small can be selected as suspicious candidates for the magnitude.
fault bus, and the lines connecting those suspicious buses are For a power system with buses and PMUs, the procedure
then considered as the fault region. of Stage 1 can be outlined as follows.
JIANG et al.: PMU-BASED FAULT LOCATION USING VOLTAGE MEASUREMENTS 1647
Here, .
6) The resulting and are the fault line and fault distance. (19)
1648 IEEE TRANSACTIONS ON POWER DELIVERY, VOL. 27, NO. 3, JULY 2012
(20)
(21)
(22) 1-2 may cause an estimated location on line 1-3 or on line 2-3.
That means faults on ring circuits cannot be estimated correctly
From (22), it can be concluded that the matching degree is without a PMU installed inside the ring circuit due to the com-
always zero at any point on line and the fault position plicated symmetry of the system. As a result, a PMU must be
cannot be obtained by solving (19). Therefore, it is impossible installed on bus 3 to ensure the proposed algorithm can accu-
to locate the fault distance on line when all PMUs are rately locate any faults taking place in the inner-ring circuits.
all located in the remaining network 2. In the IEEE 39-bus system, there indeed exists a trilateral-ring
However, if PMUs are located in both remaining net- circuit, which consists of buses 26-28-29 as shown in Fig. 7.
worksfor example, two PMUs are placed at bus and In actual systems, not only do trilateral-ring circuits exist, but
then the fault-location factor calculated from bus is quadrilateral-ring circuits also exist along with five-edge-ring
circuits and so on. Here, we talk about a five-edge-ring cir-
(23) cuit consisting of buses 42-43-45-44-73, which is the transmis-
sion network portion of the ZJP 76-busa network in Zhejiang
Province, China, where the voltage class is equal to or higher
Since varies with the fault position in a different func- than 525 kVshown in Fig. 8. Since this five-edge-ring circuit
tion , we can identify the fault location by solving the fol- has four inner nodes, at least two PMUs must be installed in the
lowing nonlinear equation: four inner nodes to properly locate a fault that occurs inside the
ring circuit. In Section VI, we will demonstrate the necessity of
(24) the constraint of edge-ring circuits.
that is
V. DETAILED IMPLEMENTATION OF THE PROPOSED PMU
(25) PLACEMENT SCHEME
TABLE I
RESULTS OF A LARGE NUMBER OF TESTS
TABLE II TABLE V
FIVE MOST SUSPICIOUS LOCATIONS FOR STAGE 2 SIMULATION RESULTS UNDER DIFFERENT FAULT
CONDITIONS FOR THE ZJP 76-BUS SYSTEM
TABLE III
LOCATION RESULTS OF FAULTS OCCURRING IN THE INNER OF THE
TRILATERAL-RING CIRCUIT IN THE IEEE 39-BUS SYSTEM
Some test results are shown in Table V, and the results of the
tests demonstrate the validity of the algorithm.
Note that when the fault line is 41-76 and there is no PMU
installed on bus 76, the proposed algorithm will fail to locate the
fault location. This is because the matching degree at any point
on line 41-76 is theoretically equal to zero, which was already
described in Section III, and, in fact, all of the degrees are
TABLE IV almost equal to one another and are very close to zero. In order
COMPUTATIONAL RESULTS UNDER DIFFERENT FAULT to avoid this problem, a PMU must be placed at bus 76, which
CONDITIONS IN THE IEEE 39-BUS SYSTEM
also serves to satisfy rule 2 of the PMU placement scheme.
Note that buses 42, 43, 45, 44, and 73 form a five-edge-ring
circuit. Several tests were made to validate the necessity of rule
3 of the proposed PMU placement scheme, and the results are
shown in Table VI. From Table VI, we can see that at least two
PMUs must be installed in the inner portion of the five-edge-ring
circuit. Otherwise, the fault-location algorithm may be wrong
even with one PMU installed on bus 44. Therefore, rule 3 of the
PMU placement scheme is necessary to guarantee the accuracy
of the proposed fault-location algorithm.
As mentioned before, the proposed algorithm is independent
of fault resistance. Here, some tests under different fault re-
sistance conditions are made and shown in Table VII. From
Table VII, we can see that the proposed algorithm can locate
the fault under different fault resistance. However, the accuracy
decreases when the fault resistance is very high. The reason
44, 50, 59, 60, 61, 62, 64, 65, 66, 67, 68, 69, 70, 71, 72, 75, is the voltages during the fault change little from the voltages
and 76 based on the three rules of the PMU placement scheme. of prefault. Generally, the proposed fault-location algorithm is
JIANG et al.: PMU-BASED FAULT LOCATION USING VOLTAGE MEASUREMENTS 1651
TABLE VI
COMPUTATIONAL RESULTS UNDER DIFFERENT PMU PLACEMENT CONDITIONS IN THE ZJP 76-BUS SYSTEM
TABLE VII
COMPUTATIONAL RESULTS UNDER DIFFERENT FAULT RESISTANCE CONDITIONS IN THE ZJP 76-BUS SYSTEM
TABLE VIII
COMPUTATIONAL RESULTS UNDER DIFFERENT PMU PLACEMENT CONDITIONS IN THE ZJP 543-BUS SYSTEM
ACKNOWLEDGMENT [17] Y. Liao, Fault location for single-circuit line based on bus-impedance
matrix utilizing voltage measurements, IEEE Trans. Power Del., vol.
The authors would like to thank Director M. Zhao and Senior 23, no. 2, pp. 609617, Apr. 2008.
Engineer H. Li, who are with the Power Design and Research [18] Y. Liao, New fault location approach using voltage measurements,
Institute of Zhejiang Province, since they provided the power in Proc. IEEE Southeast Conf., 2007, pp. 407412.
[19] J. Grainger and W. Stevenson, Power System Analysis. New York:
grid data for Zhejiang Province, China. McGraw-Hill, 1994.
[20] Z.-X. Wu and X.-X. Zhou, Power system analysis software package
REFERENCES (PSASP)An integrated power system analysis tool, presented at the
Int. Conf. Power Syst. Technol., Bejing, China, 1998.
[1] Y. Liao, Fault location utilizing unsynchronized voltage measure-
ments during fault, Elect. Power Compon. Syst., vol. 34, no. 12, pp. Quanyuan Jiang (M10) received the B.S., M.S.,
12831293, Dec. 2006. and Ph.D. degrees in electrical engineering from the
[2] K. Takagi, Y. Yomakoshi, M. Yamaura, R. Kondow, and T. Mat- College of Electrical and Electronic Engineering,
sushima, Development of a new type fault locator using the Huazhong University of Science and Technology
one-terminal voltage and current data, IEEE Trans. Power App. Syst., (HUST), Wuhan, China, in 1997, 2000, and 2003,
vol. PAS-101, no. 8, pp. 28922898, Aug. 1982. respectively.
[3] L. Eriksson, M. M. Saha, and G. D. Rockefeller, An accurate fault Currently, he is a Professor with Zhejiang Univer-
locator with compensation for apparent reactance in the fault resistance sity (ZJU), Hangzhou. His research interests include
resulting from remote-end indeed, IEEE Trans. Power App. Syst., vol. power system stability, control, and optimization.
PAS-104, no. 2, pp. 424436, Feb. 1985.
[4] J. Izykowski, E. Rosolowski, and M. M. Saha, Locating faults in par-
allel transmission lines under availability of complete measurements at
one end, Proc. Inst. Elect. Eng., Gen., Transm. Distrib., vol. 151, no.
2, pp. 268273, Mar. 2004.
[5] D. XinZhou and S. ShenXing, Optimizing solution of fault location Xingpeng Li was born in Shandong, China, in 1989.
using single terminal quantities, Sci. China. Ser. E-Tech. Sci., vol. 51, He received the B.S. degree in electrical engineering
no. 6, pp. 761772, Jun. 2008. from the College of Electrical Engineering, Shan-
[6] D. Novosel, D. G. Hart, E. Udren, and J. Garitty, Unsynchronized dong University, Jinan, in 2010, and is currently
two-terminal fault location estimation, IEEE Trans. Power Del., vol. pursuing the M.Sc. degree at the College of Electrical
11, no. 1, pp. 130138, Jan. 1996. Engineering, Zhejiang University, Hangzhou.
[7] A. Gopalakrishnan, M. Kezunovic, S. M. McKenna, and D. M. Hamai, His research interests are fault location and micro-
Fault location using distributed parameter transmission line model, grid energy management.
IEEE Trans. Power Del., vol. 15, no. 4, pp. 11691174, Oct. 2000.
[8] J.-A. Jiang, J.-Z. Yang, Y.-H. Lin, C.-W. Liu, and J.-C. Ma, An adap-
tive PMU based fault detection/location technique for transmission
linesPart I: Theory and algorithms, IEEE Trans. Power Del., vol.
15, no. 2, pp. 486493, Apr. 2000.
[9] E. G. Silveira and C. Pereira, Transmission line fault location using
two-terminal data without time synchronization, IEEE Trans. Power Bo Wang was born in Zhejiang, China, in 1985. He
Del., vol. 22, no. 1, pp. 498499, Feb. 2007. received the B.S. and M.S. degrees in electrical engi-
[10] A. A. Girgis, D. G. Hart, and W. L. Peterson, A new fault location neering from the College of Electrical Engineering,
technique for two-and three-terminal lines, IEEE Trans. Power Del., Zhejiang University, Hangzhou, in 2007 and 2010,
vol. 7, no. 1, pp. 98107, Jan. 1992. respectively.
[11] Y.-H. Lin, C.-W. Liu, and C.-S. Yu, A new fault locator for three-ter- Currently, he is with Ningbo Electric Company,
minal transmission linesUsing two-terminal synchronized voltage State Grid, Ningbo, China. His research interests are
and current phasors, IEEE Trans. Power Del., vol. 17, no. 2, pp. fault location in transmission networks and the appli-
452459, Apr. 2004. cation of wide-area measurement systems.
[12] M. Abe, N. Otsuzuki, T. Emura, and M. Takeuchi, Development of a
new fault location system for multi-terminal single transmission lines,
IEEE Trans. Power Del., vol. 10, no. 1, pp. 159168, Jan. 1995.
[13] S. M. Brahma, Fault location scheme for a multi-terminal transmis-
sion line using synchronized voltage measurements, IEEE Trans.
Power Del., vol. 20, no. 2, pt. 2, pp. 13251331, Apr. 2005. Haijiao Wang was born in Henan, China, in 1988.
[14] C.-W. Liu, K.-P. Lien, C.-S. Chen, and J.-A. Jiang, A universal fault He received the B.S. degree in electrical engineering
location technique for N-terminal (N 3) transmission lines, IEEE
from the College of Electrical Engineering, Zhejiang
University, Hangzhou, in 2009, where he is currently
Trans. Power Del., vol. 23, no. 3, pp. 13661373, Jul. 2008.
[15] M. Kezunovic and Y. Liao, Fault location estimation based on pursuing the Ph.D. degree in electrical engineering.
matching the simulated and recorded waveforms using genetic algo- His research interests are wide-area measurement
rithms, presented at the 7th Int. Conf. Develop. Power Syst. Protect., systems and the application of energy storage sys-
RAI, Amsterdam, the Netherlands, 2001. tems in power system.
[16] G. Zijad and A. Ali, Fault location using voltage measurements,
IEEE Trans. Power Del., vol. 17, no. 2, pp. 441445, Apr. 2002.