GUIDELINES ON THE
CONTENTS OF A ROAD
SAFETY AUDIT REPORT
FOREWORD
The following guideline is presented as a supplement to the Guidelines For The Safety
Audit Of Roads And Road Project In Malaysia produced by Public Works Department
Malaysia.
The contents of this guideline was presented and discussed at the Road Safety Auditors
Meeting on 3rd October 2006 at Bilik Mesyuarat Melati, Tingkat 6, Blok B, Kompleks
Kerja Raya, Jalan Sultan Salahuddin, 50582 Kuala Lumpur.
TABLE OF CONTENTS
PAGE NO
1. Introduction 1
2. Contents of An Audit Report
2.1. Format of the report cover 1
2.2. Table of contents for an audit report 1
2.3. Summary of Audit Findings & Recommendation 1
2.4. General layout of main report 1
2.5. Introduction to project 2
2.6. Information made available to auditor 2
2.7. List of relevant references/review technical guidelines 2
2.8 Details of the Road Safety Audit
2.8.1 Findings or Identification of safety deficiencies 3
2.8.2 Recommendation / corrective treatments 3
2.9 Conclusion 3
2.10 Details of the auditor & team member 3
2.11 Appendices 4
List of Appendices
1. Example of a Report Cover Appendix 1
2. Example Table of Contents Appendix 2
3. Example of Standard Format Summary
RSA Stage 1, 2 & 3 Appendix 3(i)
RSA Stage 3 Compliance Audit Appendix 3(ii)
RSA Stage 4 Part 1 Appendix 3(iii)
RSA Stage 4 Part 2 & 3 Appendix 3(iv)
RSA Stage 5 Appendix 3(v)
4. Example of Report Layout
Header, Footer, Page Number & Headings Appendix 4 (i)
Tables & figures Appendix 4 (ii)
Guidelines on the Contents of A Road Safety Audit Report
1. INTRODUCTION
An audit report should provide the client or other decision makers with full and
comprehensive statements of the road safety concerns and implications of the project
planning, design, construction and operation of new road or of an existing road. The
main objective of this guideline is to ensure uniformity & consistency in the
preparation of an audit report for JKR projects. Notwithstanding this, the Guidelines
For the Safety Audit of Roads and Road Project in Malaysia by PWD Malaysia
should be complied.
2.3 Summary of Audit Findings & Recommendation (to be included in the report)
- Standard Format Summary Of Audit (RSA Stage 1, 2 & 3) Appendix3(i)
- Standard Format Summary Of Audit (Compliance Audit) - Appendix 3(ii)
- Standard Format Summary Of Audit (RSA Stage 4 Part 1) - Appendix 3(iii)
- Standard Format Summary Of Audit (RSA Stage 4 Part 2 & 3) Appendix3(iv)
- Standard Format Summary Of Audit (RSA Stage 5) - Appendix 3(v)
2.9. Conclusion
- include:
Indicate adequacy of drawings & information provided at the time of audit
Indicate only general safety deficiencies not specific deficiencies
Specify the needs of any immediate amendments/corrective actions (e.g.
before next stage of audit, before construction etc.)
2.11. Appendices
- Include in the following order irrespective whether it is not applicable or not
provided.
Appendix:
Appendix A: A copy of the Auditor's accreditation certificate
Appendix B: Location plan of project
Appendix C: Strip map of the project
Appendix D: Photos of existing site
Appendix E: Decisions of the previous audit, e.g.
- Summary of Audit for previous audit with decisions of
meeting included Minutes of meeting
- Letters
Appendix F: List of drawings use for audit
Appendix G and onwards..
Safety Deficiencies & Recommendations
- If there are similar type of deficiencies (repetitive in
same/different locations), attaching an example in the
form of drawings/sketches will suffice with the locations
specified in the main report
- If there are different type of deficiencies, attaching all
relevant drawings / sketches is required
- The deficiencies need to be highlighted by clouding and
indicating what are the deficiencies in the drawings
- Should try as much as possible to use minimum numbers
of drawings as appendices without losing clarity and
content i.e. use shared drawings that contain
many/different deficiencies (where possible)
EXAMPLE OF REPORT
COVER
EXAMPLE OF REPORT COVER Appendix 1
KERAJAAN MALAYSIA
JABATAN KERJA RAYA MALAYSIA
Font : Times New Roman:
Saiz : 24 (Bold)
Ir Ismail b. Ahmad
JABATAN KERJA RAYA Acreditiation No : JKR/CJ/UKJ/028/07
Cawangan Jalan, 2005
Ibu Pejabat JKR Malaysia,
Jalan Sultan Salahuddin, Jitu Consultancy
50582 Kuala Lumpur No 100, Jalan Jitu 4
Font : Times New Damansara Utama
Roman Selangor
Design Consultant Saiz : 11
Syarikat Perunding XXX Tel No: 03-41078650
No 12, Jalan Liku Fax No: 03 41067854
32100 Shah Alam , Selangor Email :
Contractor
Bina Siap Sdn. Bhd.
No 176, Fasa II
Bandar Baru Puncak Alam
23100 Kuala Selangor
Selangor
APPENDIX 2
EXAMPLE TABLE OF
CONTENTS
Appendix 2
EXAMPLE TABLE OF CONTENTS
1 1
1.1 2
1.2 4
2 .. 5
2.1 6
2.2 6
List of Appendices
Standard Text
Standard Margin
Top : 1. 5
Bottom : 1
Left / Right : 1. 25
APPENDIX 3
STANDARD FORMAT
SUMMARY OF AUDIT
STANDARD FORMAT SUMMARY OF AUDIT (RSA STAGE 1, 2 & 3) Appendix 3 (i)
Summary Of Audit
Ir Ismail b. Ahmad Font : Times New Roman Font : Times New Roman June 2006
Saiz : 11 Saiz : 11 i
STANDARD FORMAT SUMMARY OF AUDIT (RSA STAGE 3 - COMPLIANCE AUDIT) Appendix 3 (ii)
No Item Auditors Comment Decision of stage 3 RSA Designers Compliance Auditors Compliance Audit
& Recommendation Meeting
in Stage 3
Verification Audit
Summary Of Audit
Ir Ismail b. Ahmad Font : Times New Roman Font : Times New Roman June 2006
Saiz : 11 Saiz : 11 i
STANDARD FORMAT SUMMARY OF AUDIT (RSA STAGE 5)
Appendix 3( v)
Summary Of Audit
Ir Ismail b. Ahmad
Font : Times New Roman Font : Times New Roman June 2006
Saiz : 11 Saiz : 11 i
APPENDIX 4
EXAMPLE OF REPORT
LAYOUT
Appendix 4(i)
EXAMPLE OF REPORT LAYOUT 1
Standard Number
1 MAJOR HEADING (Capital + Bold)
1.1 Minor Heading (Bold)
1.1.2 Subsequent Heading (Bold)
Standard Text
Font New Times Roman
Saiz 12
Sentence spacing : 1.5
Paragraph : 3.0
Standard Margin
Top : 1. 5
Bottom : 1
Left / Right : 1. 25