CONCRETE POUR RECORD - 030

PROJECT NAME: AL SHAHAD TOWER


DATE OF POUR February 17, 2016
CONCRETE GRADE: C40/20
STRUCTURE: RETAINING WALL @ BASEMENT 5

QTY BATCH
MIX No. / TICKET No. TRUCK No. ARRIVE TIME
(m3) TIME
ON SITE
13-1603486 23-211 8 6:08 PM 6:50 PM
13-1603487 23-239 8 6:33 PM 7:10 PM
13-1603490 23-205 8 6:58 PM 7:45 PM
13-1603491 23-219 8 7:20 PM 8:05 PM
13-1603492 23-218 8 7:56 PM 8:30 PM
13-1603493 23-248 8 8:16 PM 8:50 PM
13-1603495 23-211 8 8:35 PM 9:09 PM
13-1603496 23-205 8 8:58 PM 9:41 PM
13-1603497 23-219 8 9:19 PM 10:04 PM
13-1603498 23-218 8 9:38 PM 10:20 PM
13-1603499 23-248 8 10:05 PM 10:39 PM
13-1603500 23-211 8 10:37 PM 11:20 PM

TOTAL VOLUME OF CONCRETE = 96.00 m3 as per delivery receipt


8.00 m3 average volume of concrete
LENGTH OF RETAINING WALL: 35.80 m @ GRID A-F/ 1(above)
12.45 m @ GRID A/ 1(above) - 2
TOTAL LENGTH OF RETAINING WALL: 47.15 m
HEIGHT OF RETAINING WALL: 3.40 m as per ACROW CERTIFICATE
THICKNESS OF RETAINING WALL: 500 mm as per IFC DRAWING

TOTAL VOLUME CASTED = 80.16 m3


DURATION DEPARTURE
START FINISH SLUMP
OF PLACING in hrs TIME
PLACING PLACING (cm)
(mins) FROM SITE
6:54 PM 7:08 PM 0:14:00 0.2333 7:08 PM 195
7:17 PM 7:30 PM 0:13:00 0.2167 7:30 PM 200
7:52 PM 8:06 PM 0:14:00 0.2333 8:06 PM 200
8:15 PM 8:29 PM 0:14:00 0.2333 8:29 PM 190
8:37 PM 8:49 PM 0:12:00 0.2000 8:49 PM 200
8:58 PM 9:11 PM 0:13:00 0.2167 9:11 PM 190
9:17 PM 9:31 PM 0:14:00 0.2333 9:31 PM 195
9:45 PM 9:58 PM 0:13:00 0.2167 9:58 PM 200
10:09 PM 10:20 PM 0:11:00 0.1833 10:20 PM 195
10:26 PM 10:38 PM 0:12:00 0.2000 10:38 PM 195
10:44 PM 10:58 PM 0:14:00 0.2333 10:58 PM 200
11:26 PM 11:38 PM 0:12:00 0.2000 11:38 PM 195

TOTAL DURATION = 2:36:00 2.6000


0.2167 (average time of casting in hrs)

er delivery receipt 2.04 m3/m (volume of concrete per meter)


age volume of concrete 36.92 m3/hr (average discharge of concrete on the pump)
RID A-F/ 1(above)
RID A/ 1(above) - 2 0.46 m/hr (rate of the pump @ a span of 1 meter)

er ACROW CERTIFICATE
er IFC DRAWING
CONCRETE
AIR
TEMP. REMARKS
CONTENT
(oC)
25.3 2 cubes
25.6
25.7
26.1
25.3 2 cubes
25.4
24.9
25.3
25.4
25.6
25.1 2 cubes
25.4

asting in hrs)

e per meter)
e of concrete on the pump)

p @ a span of 1 meter)