Proyeto timeline
RMJM (Robert Matthew Johnson Marshall) is an international architectural firm founded in 1956 in Edinburgh, Scotland,
Notable awards
2012
Building and Design Awards, Best in category School & Education Builds Project of the
2011
Cityscape Dubai Awards, Winner of Best Overall Project category, [9] Abu Dhabi National
Cityscape Dubai Awards, Winner of Commercial and mixed use category, [9] Abu Dhabi National
Universal Design Award (Gold) from BCA ( Singapore Building & Construction Authority) Khoo
11th SIA Architectural Design Awards, Winner of Project of the Year category, [10] Khoo Teck Puat
Hospital , Singapore
11th SIA Architectural Design Awards, Winner of Best Institutional / Healthcare Building
American Architecture Awards, Winner of Tour Signal Design Competition, [eleven] Tour Signal Design
International Property Award, Best Architectural Project, [12] Varyap Meridian Grand Tower
Skyrise Greenery Award, First Prize - Completed Projects, [13] Khoo Teck Puat
Hospital , Singapore
Architectural Record China Awards, Best Residential Project, [14] Evian Town, Suzhou , China
2009
USGBC Maryland Chapter, Special Accomplishment Award, [fifteen] The Athenaeum at Goucher
College
Cityscape Abu Dhabi - Middle East Real Estate Awards - Best Commercial / Retail Project
Award, [16] Abu Dhabi National Exhibitions Company Capital Gate , Abu Dhabi
Cityscape Dubai Awards, Special Award - Islamic Architecture Category, [17] Al-Jami'a Al-
1 A reinforcing mesh
2 a mold around the mesh 3 closes the steel mesh
is filled with concrete
4 then the mold is moved up by the core to repeat the process
Concrete with high temperatures, and does not set well can be fractured, so it was decided to pour the concrete at
night, to have a correct setting. By growing the nucleus, it pumped more height, so subjected to rigorous consistency
and depression, to ensure it does not block the pipes. Furthermore a process of post tension, adding more
reinforcement to the core by a tensile-resistant filaments, and when the desired height is reached, voltage is applied is
added. Thus the core remains intact, and the additional reinforcement avoid dropping
To postensionar the Core, 146 steel tendons are woven through the concrete, each tendon is 20 meters long and runs
through 5-story building intertwined with each other. For maximum resistance.
The inclined thin and curved design causes problems in the assembly, so decided to use diagonal grids to evenly
distribute the weight and to have the desired shape. This design is called Diagrid
diagrid ( Acronym English diagonal grid - grid diagonal -) is the name (registered) to be given a design structural from engineering Y architecture to
build large buildings with frames steel (Or other material with similar qualities) based on beams and assembled into brackets triangular (Or
"bias"). This structural form requires less support material (eg less steel) so money, energy and time costs are saved and even more space
covered is possible in conventional constructions of the twentieth century or earlier times since the system is a exoskeleton . For example in the
construction of the Hearst
Tower from NY has allowed reportedly savings of 21% steel. He diagrid It has also avoided the use of large columns (mainly corner) and provides
better load distribution forces , Particularly useful in the case of construction that must withstand significant stresses. Among the buildings that
have been built with this method, in addition to the Hearst It is the one designed by Norman Foster , in the Avenue 30 St Mary Ax from London , And
it is known as " the Gherkin "( Gherkin) for his appearance.
720 cruciform pieces are designed to channel the forces and precisely connect with the other adjacent parts and the glass
facade. Thus each piece is different
Curves skyscraper be covered with flat shapes to avoid costs, the only way to cover the curved surface with flat
shapes, is with triangles as these can pivot in three directions, and when bound can complex surface shapes, but
as each area of the building is unique, 26000 triangular panels were needed to form the facade.
To give the hotel lobby the wow factor, architects plan to build an infinity pool and a restaurant hanging 100 meter from
the ground. The design requires a 2-story structure to hang without visible supports, but it was necessary
reinforcements, it becomes struts 22
steel.
While the tallest skyscraper arrives, the weight of her story begins to be a problem, so it is proposed to make an internal
atrium, reducing weight and minimizing the forces but this brings the problem that can not channel your weight to her
core , so you choose to make an internal network of steel. But this is a very small point to the core, then the core with 6
giant steel plates strut and connected to the reinforcing core have 8 meters
Almost reaching the top of the tower, Sheikh requires a helipad on the roof. What causes two problems, create new
forces and unpredictable winds create hazardous flying conditions. The solution is to reduce the height of the heliport,
and also reduces the additional forces and factors more favorable ratio of flight.
So the odds against the Capital gate is performed, although in one year but the finishing was made.