Field Instruments:
As per the scope of work of pumping station contractor at SDHO Drinking water tank area, RTU at each pumping
station 1/2/3 shall be connected to the control center via FOC(24 Fiber).However the integration of this signals to
SCADA will be by NWC contractor
RTU
1. All the Instruments & Vendor package items will be connected to the RTUS of the respective pumping
station (RTU 01/02/03).
Integration of Signal in SDHO Control Center: Not in the scope of pumping station contractor at SDHO Drinking
water tank. (By NWC contractor-Tecton Scope)
Concerns (Tecton):
Whether monitoring or control to be done from control center for the pumping stations at Drinking water
tank area.
Cabling from the pumping station RTU up to the NWC control center for integration will be done by
pumping station contractor at SDHO Drinking water tank area. However for termination of FOC and
integration of signals to SCADA at control center, FOC patch panel and Ethernet switches shall be
considered by Tecton.
Details regarding the Increment 2 Potable Water Tanks not mentioned on the received documents. As per
NWC H652 Scope 2 More tanks (Or Groups- To be confirmed) are there in increment 2 and the signals for
the tanks shall be integrated to Control center SCADA.
Mode of communication of Increment 2 Tank s with SDHO control center and the RTU signals details
required for the integration of signal to SCADA system
There is no control valve on the inlet side of the each potable water tanks at SDHO area.
Page 1 of 3
SEWER SYSTEM SDHO INCREMENT (To be confirmed whether it is the same sewer system mentioned on
Electrical and SCADA Specifications Page 94 of 128 -Integration Scope)
No of Pumping station: 2 Nos
Package system:
Field Instruments:
Details not available (No P&ID)
As per the scope of work of sewer pumping station contractor at SDHO, RTU at each pumping station 1/2 shall be
connected to the control center via FOC (24 Fiber).However the integration of this signals to SCADA will be by NWC
contractor
RTU
Vendor package items will be connected to the RTUs of the respective pumping station (RTU 01/02)
Integration of Signal in SDHO CoC: Not in the scope of pumping station contractor at SDHO.(By NWC contractor)
Concerns(Tecton):
Whether monitoring or control to be done from control center for the sewer pumping stations
Cabling from the sewer pumping station RTU up to the NWC control center for integration will be done by
sewer pumping station contractor at SDHO . However for termination of FOC and integration of signals to
SCADA at control center, FOC patch panel and Ethernet switches shall be considered by Tecton.
P&ID is not available for the Sewer system.
RTU signals of sewer stations required for the integration of signal to SCADA system.
Page 2 of 3
TREATED EFFLUENT TANKS SDHO INCREMENT 1
No of Pumping station: 7 Nos
Concerns:
Whether monitoring or control to be done from control center for the Treated effluent tanks.
P&ID is not available for the Treated effluent tanks and pumping station in the received documents
Design basis only mention about the number of pumping station. Detail regarding the number of tanks &
related instruments in each pumping station is not mentioned on the received documents.
RTU & Signal details required for the pumping station for integrating the signal to main control center.
Details regarding the mode and type of communication between the RTU and control system required for
the integration of signal to main control center.
Concerns:
Whether monitoring or control to be done from control center for the Treated effluent tanks.
P&ID is not available for the Treated effluent tanks and pumping station in the received documents
RTU & Signal details required for integrating the signal to main control center.
Details regarding the mode and type of communication between the RTU and control system required for
the integration of signal to main control center.