REPUBLIC CEMENT STANDARD JOB PLAN

STD JO No.:

Equipment Name.:
TOTAL EQUIPMENT Date Prepared:
Equipment No.: Section:
May 11, 2016
Planned Actual Usage
Description Cap. Qty. Units Description Qty. Units
JOB TITLE:
Welding Installation
machine 200ofANew Life1Ring Box/Holder
set @ PH Area/Jetty

Cutting tool 1 pc
Hand drill 1 SAFETY
pc PRECAUTION:
grinder 1 pc
HAZARDS CONTROL MEASURES

Un-Authorized Entry As a standard operating procedure,


coordinate to the area owner for the
possible isolation of the work area.
Mobilization and Lifting works Check lifting gear condition prior to use./
*use of boom truck keep safe distance during lifting activity./
*manual lifting Engage outrigger jack both sides at stable
ground prior to start lifting./install wheel
stopper when unit at halt./ Proper work
coordination between operator & signalman
during lifting activity.
Traffic hazard Assign authorized driver. Follow traffic rules
& regulation. Isolate work area.
Sharp edges, cuts and scrapes Proper use of PPE, use of rubberized palm
working gloves.
Exposed to extreme heat of sunlight Micro breaks. Prepare adequate of drinking
water readily available at site.
Manual handling/lifting Proper lifting procedure, assistance from
others. / Use appropriate lifting equipment.
Use of push carts for heavy loads.
Removal of existing life ring box/holder Isolate work area. Ensure all requirements
*use of cutting tool/ grinder for doing hot works met. Tools inspection
required.
Installation of new life ring station Ensure all requirements on doing hot works
*use of welding machine applied. Complete hot work permit.
*use of electric hand drill Do not run power cables on access area.
*use of portable grinder Check electrical tools condition before use.
Wear appropriate personal protective
equipment - PPE

Dust particles. Wear dust mask and safety goggles.

DETAILED DESCRIPTION OF WORK:

DURATION
STEPS (hour)
QUALITY CHECK

Preparation of needed tools and equipment 30 min


Moving to site 5 min
Conduct toolbox meeting 15 min
Area preparation 2hrs
*removal of existing life ring box/holder
*use of cutting tool
*use of grinder
Installation of new life ring station 2hrs
*use of welding machine
Painting of newly installed life ring station 1hr

Housekeeping and disposal of waste 30 min

MANPOWER

Planned Manpower Actual Manpower


ETDevocion

RCII Project In-charge