Sie sind auf Seite 1von 17

Labour's Productivity Rates

Carpentry Work

Production Rate
# Descraption Location Crew Size Remarks
(ML. Per Hour)
2 CARPENTERS, 1
1 Formwork to footings 12
HELPER
2 CARPENTERS, 1
2 Formwork to isolated footings 16
HELPER
2 CARPENTERS, 1
3 Formwork to rafts 14
HELPER
2 CARPENTERS, 1
4 Formwork to rafts D>0.75m 18
HELPER
2 CARPENTERS, 1
5 Formwork to tie beams 10
HELPER
2 CARPENTERS, 1
6 Formwork to high level tie beams D>0.45M 12
HELPER
2 CARPENTERS, 1
7 Formwork to Neck Columns 4
HELPER
2 CARPENTERS, 1
8 Formwork to U/G Water tank 6
HELPER
2 CARPENTERS, 1
9 Formwork to basement retaining walls 9
HELPER
2 CARPENTERS, 1
10 Formwork to columns (small size) 7
HELPER
2 CARPENTERS, 1
11 Formwork to Columns (large size) 9
HELPER
2 CARPENTERS, 1
12 Formwork to D/S beam internal (shallow) 6
HELPER
2 CARPENTERS, 1
13 Formwork to D/S beam external (Deep) 7
HELPER
2 CARPENTERS, 1
14 Formwork to D/S beam external (Shallow) 4
HELPER
2 CARPENTERS, 1
15 Formwork to D/S beam external (Deep) 6
HELPER
2 CARPENTERS, 1
16 Formwork to lift walls single core 6
HELPER
2 CARPENTERS, 1
17 Formwork to lift walls multi core 8
HELPER
2 CARPENTERS, 1
18 Formwork to slab decking (10ft) hourdi 16
HELPER
to slab decking (>10ft) hourdi D/S 2 CARPENTERS, 1
19 Formwork 12
beams HELPER
2 CARPENTERS, 1
20 Formwork 2 CARPENTERS, 1 HELPER 12
HELPER
2 CARPENTERS, 1
21 Formwork to slab decking (>10ft) hourdi to slab decking (>10ft) hourdi 10
HELPER
2 CARPENTERS, 1
22 Formwork to staircase (non spiral) 4
HELPER
2 CARPENTERS, 1
23 Formwork to balcony parapets 6
HELPER
2 CARPENTERS, 1
24 Formwork to roof parapets 8
HELPER

D = DEPTH
U. GR. = UNDERGROUND
D/S = DECK - SLAB
> = GREATER THAN
< = LESS THAN
Labour's Productivity Rates

Block Work & Plaster Work

Production Rate
# Descraption Location Crew Size
(ML. Per Hour)
MASONARY WORKS

1 Hollow Blockwork (100, 150 & 200 mm) - 1 MASON, 1 HELPER 120 NR

2 Hollow Blockwork (large panels) - 1 MASON, 1 HELPER 140 NR

3 Solid blockwork - 1 MASON, 1 HELPER 95 NR

4 Solid Blockwork as Raft forms - 1 MASON, 1 HELPER 110 NR

PLASTERWORK

5 Plaster Final Coat Internal / walls 1 MASON, 1 HELPER 16 SM

6 Plaster Rush Coat Internal / walls 2 HELPER 150 SM

7 Plaster (internal), walls mesh Internal / walls 1 HELPER 100 SM

8 Plaster Hacking Internal / walls 1 HELPER 100 SM

9 Plaster (internal), walls guide point Internal / walls 1 MASON, 1 HELPER 100 SM

10 Plaster Corner Beads Internal / walls 1 MASON, 1 HELPER 100 SM

11 Plaster With Grooves External Walls 1 MASON, 1 HELPER 10 SM

12 Plaster Without Grooves External Walls 1 MASON, 1 HELPER 12 SM


13 Plaster Rsh Coat External Walls 2 HELPER 150 SM

14 Plaster (external), walls mesh External Walls 1 HELPER 100 SM

15 Plaster Hacking External Walls 1 HELPER 100 SM

16 Plaster Guide Points External Walls 1 MASON, 1 HELPER 100 SM

17 Plaster Crner Beads External Walls 1 MASON, 1 HELPER 100 SM

18 Plastering of Arches/Mullians Arches/Mullians 1 MASON, 1 HELPER 80

19 Screed 50mm thick Floor 1 MASON, 1 HELPER 20

20 Screed 100 mm thick Roof 1 MASON, 1 HELPER 15

21 Screed 25mm thick Floor 1 Mason + 1 Helper 6


Remarks
Labour's Productivity Rates

Concrete Work

Production Rate (ML. Per


# Descraption Location Crew Size Remarks
Remarks
Hour)
KERBING / BLOCK PAVING WORKS

1 P.C.C. Curve kerb base (to curves) 1 MASON, 1 HELPER 2,5 25 METRE

2 PCC to kerb base (Straight line) 1 MASON, 1 HELPER 3,0 30 METRE

3 Haunching to kerb base (Dumpes) 1 MASON, 1 HELPER 4 40 METRE

4 kerbstonse (Without PCC) 1 MASON, 1 HELPER 1,5 15 METRE


Interlock paving on pre prepared sub -
5 1 MASON, 1 HELPER 2 SM
base
6 Screed works including preparation 1 MASON, 1 HELPER 1,5 15 SM
Haunching ot Kerb Base (Mixing
7 1 MASON, 1 HELPER 10 M 100M
Truck)
MANHOLE/ DRAINAGE CONSTRUCTION

8 Excavation for drains / manholes 1 HELPER 5 CM

9 Backfill to drains / manholes 1 HELPER 10 CM

10 Blockwork to manholes 1 MASON, 1 HELPER 2 NOS

11 Plaster to manholes 1 MASON, 1 HELPER 2 NOS

12 Benching to manholes 1 MASON, 1 HELPER 4 NOS

13 Fix covers to manholes 1 MASON, 1 HELPER 2 NOS

14 Fix gulley traps 1 MASON, 1 HELPER 1 NO

15 Laying of P.V.C. sleeves 4" - 12" 4 HELPER 24M 240M


CONCRETE PLACEMENT WORKS
Concrete to PCC blinding (100 mm
16 1 MASON, 10 HELPERS 27 CM
thick)
6 MASONS, 18 HELPERS, 1
17 Concrete to slabs/beams, by pump 180 CM
CARPENTER
1 MASON, 6 HELPERS, 0.5
18 Concrete to slabs / beams by crane 8,10 27 CM
OPERATOR
4 MASONS, 16 HELPERS, 2
19 Concrete to walls / columns, by pump 1.2 81 CM
CARPENTERS
1 MASON, 12 HELPERS , 0.5
20 Concrete by site mix 1.6 9 CM
CARPENTER
21 Concrete Columns 8 HELPERS 1.4 10

22 Concrete suspended slab (pump) 3 MASONS + 6 HELPERS 1.8 150

23 Concrete parapets/staircases 8 HELPERS 1 7

24 Blinding concrete 50 mm (readymix) 1 MASON + 4 HELPER 8,0 80

25 Blinding concrete 50 mm (sitemix) 1 MASON + 8 HELPER 1 10

26 Concrete footings & pile caps 1 MASON + 4 HELPER 12 120

27 Concrete tiebeams, ground beams 1 MASON + 5 HELPER 6 60

28 Concrete column necks 8 HELPER 1.5 15

29 Concrete Ground slab 3 MASONS + 6 HELPER 1,5 15

30 Concrete to precast slabs, beams 2 MASONS + 1 HELPER 3m3 30 M 3


Labour's Productivity Rates

Miscellaneous Work

Production Rate (ML. Per


# Descraption Location Crew Size Remarks
Remarks
Hour)
MISCELLANEOUS LABOUR WORKS

1 Bitumen Paint Blockwork Surfaces 1 HELPER 40 SM

2 sealant (12 mm) Vertical 1 HELPER 25 METRE

3 sealant (12 mm) Horizontal 1 HELPER 50 EMTRE

4 Polythene sheet fixing General 1 HELPER 30

5 Shaping of Soil Blinding General 1 MASON + 1 HELPER 10M

6 Protection Board installation General 1 CARPENTER + 1 HELPER 80M 2

MISCELLANEOUS CARPENTARY WORKS

7 A/C subframe manufacture / fixing General 1 CARPENTER 5 NOS


Door subframe manufacture /
8 General 1 CARPENTER 4 NOS
fixing
9 Water bar fixing General 1 CARPENTER 20 METRE
Labour's Productivity Rates

Excavation Work

Production Rate (ML.


# Descraption Location Crew Size
Per Hour)

1 Manual Excavation General 1 HELPER 3M 3

2 Backfill + levelling General 1 HELPER 5M 3

Shaping of sloped earth for blinding for bases including


3 General 1 MASON + 2 HELPER 6 LM/Day
compaction
Remarks
Labour's Productivity Rates

Tilling Work

Production Rate
# Size Location Area Crew Size Remarks
(Sqm. Per day)
1 Ceramic Tiles By Mortar 30 X 30 Floor Kitchen 1 Mason, 1 Helper 14

2 Ceramic Tiles By Mortar 30 X 30 Floor with pattern Corridor 2 Masons, 1 Helper 10

4 Ceramic Tiles By Mortar 20 X 20 Floor Store (small area) 1 Mason, 1 Helper 10

6 Ceramic Tiles By Mortar 30 X 30 Floor + Wall Bathroom 2 Mason, 1 Helper 5

8 Ceramic Tiles By Mortar 30 X 60 Wall Corridor 1 Mason, 1 Helper 14-15

9 Ceramic Tiles By Mortar 30 X 30 Wall Bathroom 2 Mason, 1 Helper 7

10 Terrazzo Tiles By Mortar 30 X 30 Floor Roof 2 Mason, 1 Helper 16

Marble Tiles By Mechanical


11 Wall Elevations 2 Masons, 1 Helper 5
Methode 30 X 60

12 Ceramic Tiles Cutted Pieces Floor General 1 MASON 20

13 Marble Tiles By Mortar Floor General 1 Mason, 1 Helper 6

Notes:
1 - One Day = 10 Houres
Labour's Productivity Rates

Reinforcement Work

Production Rate
# Descraption Location Crew Size Remarks
(ML. Per Hour)
1 Fix Rebar Footings & Tie Beams 1 STEEL FIXER 25
Walls, Columns,
2 Fix Rebar 1 STEEL FIXER 20
Beams, Solid Slabs
3 Fix rebar Ribs of Hourdi Slab 1 STEEL FIXER 18
4 Fix rebar Mesh Reinforcement 1 STEEL FIXER 15
5 Fix rebar Hidden Beams 1 STEEL FIXER 20

6 Steel cutting and bending 18.25 mm - 1 STEEL FIXER 50

7 Steel cutting and bending 8 - 16 mm - 1 STEEL FIXER 40

Notes: