Beruflich Dokumente
Kultur Dokumente
Carpentry Work
Production Rate
# Descraption Location Crew Size Remarks
(ML. Per Hour)
2 CARPENTERS, 1
1 Formwork to footings 12
HELPER
2 CARPENTERS, 1
2 Formwork to isolated footings 16
HELPER
2 CARPENTERS, 1
3 Formwork to rafts 14
HELPER
2 CARPENTERS, 1
4 Formwork to rafts D>0.75m 18
HELPER
2 CARPENTERS, 1
5 Formwork to tie beams 10
HELPER
2 CARPENTERS, 1
6 Formwork to high level tie beams D>0.45M 12
HELPER
2 CARPENTERS, 1
7 Formwork to Neck Columns 4
HELPER
2 CARPENTERS, 1
8 Formwork to U/G Water tank 6
HELPER
2 CARPENTERS, 1
9 Formwork to basement retaining walls 9
HELPER
2 CARPENTERS, 1
10 Formwork to columns (small size) 7
HELPER
2 CARPENTERS, 1
11 Formwork to Columns (large size) 9
HELPER
2 CARPENTERS, 1
12 Formwork to D/S beam internal (shallow) 6
HELPER
2 CARPENTERS, 1
13 Formwork to D/S beam external (Deep) 7
HELPER
2 CARPENTERS, 1
14 Formwork to D/S beam external (Shallow) 4
HELPER
2 CARPENTERS, 1
15 Formwork to D/S beam external (Deep) 6
HELPER
2 CARPENTERS, 1
16 Formwork to lift walls single core 6
HELPER
2 CARPENTERS, 1
17 Formwork to lift walls multi core 8
HELPER
2 CARPENTERS, 1
18 Formwork to slab decking (10ft) hourdi 16
HELPER
to slab decking (>10ft) hourdi D/S 2 CARPENTERS, 1
19 Formwork 12
beams HELPER
2 CARPENTERS, 1
20 Formwork 2 CARPENTERS, 1 HELPER 12
HELPER
2 CARPENTERS, 1
21 Formwork to slab decking (>10ft) hourdi to slab decking (>10ft) hourdi 10
HELPER
2 CARPENTERS, 1
22 Formwork to staircase (non spiral) 4
HELPER
2 CARPENTERS, 1
23 Formwork to balcony parapets 6
HELPER
2 CARPENTERS, 1
24 Formwork to roof parapets 8
HELPER
D = DEPTH
U. GR. = UNDERGROUND
D/S = DECK - SLAB
> = GREATER THAN
< = LESS THAN
Labour's Productivity Rates
Production Rate
# Descraption Location Crew Size
(ML. Per Hour)
MASONARY WORKS
1 Hollow Blockwork (100, 150 & 200 mm) - 1 MASON, 1 HELPER 120 NR
PLASTERWORK
9 Plaster (internal), walls guide point Internal / walls 1 MASON, 1 HELPER 100 SM
Concrete Work
1 P.C.C. Curve kerb base (to curves) 1 MASON, 1 HELPER 2,5 25 METRE
Miscellaneous Work
Excavation Work
Tilling Work
Production Rate
# Size Location Area Crew Size Remarks
(Sqm. Per day)
1 Ceramic Tiles By Mortar 30 X 30 Floor Kitchen 1 Mason, 1 Helper 14
Notes:
1 - One Day = 10 Houres
Labour's Productivity Rates
Reinforcement Work
Production Rate
# Descraption Location Crew Size Remarks
(ML. Per Hour)
1 Fix Rebar Footings & Tie Beams 1 STEEL FIXER 25
Walls, Columns,
2 Fix Rebar 1 STEEL FIXER 20
Beams, Solid Slabs
3 Fix rebar Ribs of Hourdi Slab 1 STEEL FIXER 18
4 Fix rebar Mesh Reinforcement 1 STEEL FIXER 15
5 Fix rebar Hidden Beams 1 STEEL FIXER 20
Notes: