Beruflich Dokumente
Kultur Dokumente
Construction
Management
2
Copyright 2015 UTAR
CONSTRUCTION SITE MANAGEMENT
1 Introduction
3
Site Layout Design
4
Site Productivity
3
Copyright 2015 UTAR
2.1 INTRODUCTION
Extensive time loss and cost overruns could result in large projects
if there is no effective and systematic approach to site planning and
controls on site productivity.
4
Copyright 2015 UTAR
CONSTRUCTION SITE MANAGEMENT
2 On-Site Main Equipment
5
Copyright 2015 UTAR
2.2 ON-SITE MAIN EQUIPMENT
Equipment and tools which are essential and required for carrying
out construction works
Hoes Trucks & hauling equipment
Loaders Compaction equipment
Backhoe-loaders Asphalt pavers
Cranes
Dozers
Scrapers
Finishing equipment
Crawler-tractor loader
(All images shown are for illustration purposes only) 8
Copyright 2015 UTAR
2.2 ON-SITE MAIN EQUIPMENT
BACKHOE-LOADERS
Have the combination of backhoe
functions and loader functions.
An excellent excavator for digging
loosely packed moist clay or sandy
clay to hard clay.
Capable of working in unstable
ground conditions due to its four
four-wheel-drive capability.
Loader
Backhoe
Tower cranes
Mobile cranes
(All images shown are for illustration purposes only) 10
Copyright 2015 UTAR
2.2 ON-SITE MAIN EQUIPMENT
Mobile Cranes
Crawler cranes need large ground contact area, levelled and stabilised
ground condition to prevent failure
Tower Cranes
14
Copyright 2015 UTAR
2.2 ON-SITE MAIN EQUIPMENT
DOZERS
Crawler Dozer
SCRAPERS
Underslung launcher
Overhead launcher
25
Copyright 2015 UTAR
2.3 SITE LAYOUT DESIGN
26
Copyright 2015 UTAR
2.3 SITE LAYOUT DESIGN
A detailed planning of the site layout and location of
temporary facilities.
27
Copyright 2015 UTAR
2.3 SITE LAYOUT DESIGN
28
Copyright 2015 UTAR
2.3 SITE LAYOUT DESIGN
34
Copyright 2015 UTAR
2.3 SITE LAYOUT DESIGN
Factors to consider when planning a site design layout:
1) SAFETY
2) SITE ACCESSIBILITY
3) SIGNAGE
4) ACCOMMODATION
5) SECURITY
6) OFFICES
7) WATER SUPPLY & SANITATION
8) MATERIAL HANDLING AND STORAGE
9) SITE CLEANING
10) BATCH PLANT & FABRICATION SHOPS
35
Copyright 2015 UTAR
Signs and Notices
2.3 SITE LAYOUT DESIGN
Main Features Around a Construction Site
Hoarding Access and Exits
Existing Services
Workers Accommodation
Administration / Site office
Health &
Environment
Plant and
Equipment Workshops
Temporary
Services
(All images shown are for illustration purposes only) 36
Copyright 2015 UTAR
CONSTRUCTION SITE MANAGEMENT
4
Site Productivity
37
Copyright 2015 UTAR
2.4 SITE PRODUCTIVITY
Construction is a labour intensive process
38
Copyright 2015 UTAR
2.4 SITE PRODUCTIVITY
WHAT AFFECTS PRODUCTIVITY?
Constructability
Weather of Design
Workday Duration
Labour &
Equipment
AUTHORITY
Day vs Night
Work
OWNER
Government TEAM
regulations
PRODUCTIVITY Efficiency of
Tools &
Equipment
CONSTRUCTION
TEAM DESIGN
Work TEAM
space area
Materials
Level of Training of Effort Availability
Workforce expended by 39
(All images shown are for illustration purposes only)
Copyright 2015 UTAR
workforce
2.4 SITE PRODUCTIVITY
where
Input = Labour + Material + Equipment + Energy + Capital
40
Copyright 2015 UTAR
2.4 SITE PRODUCTIVITY
41
Copyright 2015 UTAR
2.4 SITE PRODUCTIVITY
42
Copyright 2015 UTAR
2.4 SITE PRODUCTIVITY
43
Copyright 2015 UTAR
2.4 SITE PRODUCTIVITY
Time Study
Determines the time required to perform a task so that
an output standard of production for a worker and/or
machine may be established.
Such information is required in the estimating process
and in setting financial incentives
Used to monitor actual production performance against
the standard expected.
Not suited for variable and short-term nature of
construction projects
Motion Study
Originated in the manufacturing industry
Determines the best way to accomplish a task
44
Copyright 2015 UTAR
MODEL FOR CONTINUOUS SYSTEMS
Quality Management
IMPROVEMENT IN Benchmarking
PRODUCTIVITY Lean Production
PERFORMANCE MONITORING
Performance Level
Work Sampling
Key performance indicators
RAISING PRODUCTIVITY
Earlier finish
Improved health and safety
Less waste/environmental change
Sustainable construction
Lower costs
Improved quality
Higher salaries
Better market standing
(All images shown are for illustration purposes only) 45
Copyright 2015 UTAR
(A) MANAGEMENT SYSTEMS
47
Copyright 2015 UTAR
TO BE CONTINUED IN NEXT
ONE HOUR
48
(A) MANAGEMENT SYSTEMS
A.3 Lean Production is a philosophy based on the concepts of lean
manufacturing. It is about managing and improving the
production process to profitably deliver what the owner needs.
A.3.1 Design
A.3.2 Procurement
A.3.3 Planning
A.3.4 Logistics
A.3.5 Production
49
Copyright 2015 UTAR
(B) MANAGEMENT PROCESSES (BSI (2002), BS 6079-1:2002)
50
Copyright 2015 UTAR
B.1.1 CONCURRENT ENGINEERING
51
Copyright 2015 UTAR
B.1.3 RE-ENGINEERING
52
Copyright 2015 UTAR
B.1.4 VALUE MANAGEMENT (VM)
53
Copyright 2015 UTAR
B.1.4 VALUE MANAGEMENT (VM) contd.
Feedback
Rank functions
Feedback
3) 4-step approach
a) Risk identification
b) Risk analysis/assessment
c) Risk response
d) Install and maintain
55
Copyright 2015 UTAR
B.1.5 RISK MANAGEMENT (ISO Guide 73:2009) contd.
3a) Risk identification
This step begins with brainstorming sessions involving manager and his
team for particular segments of investigation, directed towards
identifying and listing potential risks or hazards and likely impacts.
Some of the risks include:
Staff - Would you find the right mix of people and skills
Equipment - Is appropriate equipment available locally?
Would you hire or buy?
Contract Document - Any risks assigned by contract to various parties
that do not have the ability to control these
risks
External factors - Extent to which success of project hinges on
external factors such as suppliers, government,
sub-contractors, consultants, etc.
Innovation of project - Extent of project that involves new and
innovative work
Health & Safety hazards
56
Copyright 2015 UTAR
B.1.5 RISK MANAGEMENT (ISO Guide 73:2009) contd.
3b) Risk analysis/assessment
57
Copyright 2015 UTAR
B.1.5 RISK MANAGEMENT (ISO Guide 73:2009) contd.
3c) Risk response
Risk avoidance
Risk transfer
Risk retention
HSE
58
Copyright 2015 UTAR
B.1.5 RISK MANAGEMENT (ISO Guide 73:2009) contd.
3d) Install and maintain
Install the proposed actions with the subsequent out-turn costs for
each of the identified risks, evaluated and recorded.
Feedback information is redirected back into the earlier steps to help
inform and adjust the contingencies or continuity plans and estimates
as necessary.
59
Copyright 2015 UTAR
B.1.6 BUILDING INFORMATION MODELLING (BIM)
60
Copyright 2015 UTAR
B.1.7 WASTE MANAGEMENT
61
Copyright 2015 UTAR
Total Materials Delivered to Site
62
Copyright 2015 UTAR
Typically, the construction sector does not place great emphasis on
waste management. They tend to have a poor understanding of
waste costs.
63
Copyright 2015 UTAR
Questions to ask when prioritising which material to target for
waste reduction:
Which waste is the most expensive to replace?
Which waste has the greatest recycle value?
Which waste is the easiest to collect?
Which on disposal has the greatest environment pollution
effect?
Is it a process that causes a nuisance to others?
Is the best method of work being utilised?
Are there obvious ways of reducing waste?
How easy to segregate the waste?
Are there recycle business available in the area to take away
the waste?
Is there another waste stream created in the process such as
production of effluent?
64
Copyright 2015 UTAR
B.1.7 WASTE MANAGEMENT
65
Copyright 2015 UTAR
END OF TOPIC 2
66
Copyright 2015 UTAR