1 / INTRODUCTION
Consultancy to architects
Definition of concept solutions
Detailed Design
Manufacturing
Installation
Maintenance
Spare parts supply
On site Technical supervising
1.3 Policy
1.3.1 Design
4
1.3.2 Safety
1.3.4 R&D
1.4 Certification
5
6
7
8
9
EUROPEAN NORM 1808 Main Directves
AESA EUROGONDOLAS S.L.
European Standard EN 1808 AESA
EN 292-1 Safety of machinery , basic concept, for design Basic terminology , Comply
Methodology
EN 292-2 Technical specification and principles Comply
EN 294 Safety distances to prevent danger zones being reached by the upper Comply
limbs
EN 418 Emergency stop equipement, functional aspect Comply
EN 614-1 Ergonomic design principle Comply
EN 954-1 safety of machinery safety related parts of control system Comply
EN 982 Safety requirements for fluid power system and their components Comply
EN 983 Safety requirement for pneumatis system Comply
EN 60204-1 Electrical equipement of machine Comply
EN 60529 Degrees of protection provided by enclosures Comply
EN 60947-5 Low voltage switchgear and controlgear, control circuit devices and Comply
switching element
EN 280 Mobile elevating work platform Comply
EN 1050 Safety of machinery , Risk assessment Comply
BUILDING Maintenance Unit EN 1808 AESA
3.4.1 Drum hoist : a hoist with a drum on to which the suspension ropes are Comply
reeled in one or more layer
3.4.6 Rated speed : the average speed mesasured during upward and downward Comply
hoisting travel of the platform.
3.4.7 Service break : a mechanical brake , automatically applied by stored Comply
energy until released with an external sustained power supply under the contol of
the operator or automatically
3.48 Secondary device : A device intented to stop the descent of the platform Comply
under emergency conditions, e.g. breaking of a suspension wire rope or failure of
hoist
3.4.8.2 Secondary brake : a brake acting directly on the drum, traction sheave, Comply
or final drive shaft, intented to stop the descent of the platform
3.4.9 Anti-tilt device : a device which detect when the longitudinal slope of a Comply
platform exceeds a pre-set angle
3.4.11 Manual lever/wheel/Handle : A device on the hoist which allows the Comply
platform to be lifted or lowered manually
3.4.12 Wire rope winder : A storage drum onto which wire rope is reeled Comply
3.4.16 Roof mounted hoist : a hoist which is mounted on the suspension rig or Comply
trolley
3.4.17 Overload detection device : a device which trips and acts automatically Comply
to stop the upward motion of a platform if the load in the suspension wire rope
reach the tripping limit
3.4.18 Tripping limit : the static load which causes the overload detection device Comply
to operate
10
Safety margin and directives EN 1808 AESA
6.2.1 Safety margin for the critical stresses , take the 3 modes into account Comply
1. Yield strenght exceeded
2. Critical load for buckling exceeded
3. Fatigue limit exceeded
6.2.1.1 Type of steel for which the ratio between the elestic yield limit OE and Comply
the breaking limit OR is less than 0,7
6.2.1.2 Checks against fatigue : for structure subjct to fatigue, the coventional Comply
number of cycles and load spectrum to take into account is 60000
6.2.2.2 Checks against fatigue and wear : for structure subjct to fatigue, the Comply
coventional number of cycles and load spectrum to take into account is 60000 or
4000 hours
6.3.2.2 Load capacity : the minimum load capacity of the deck shall be Comply
200kg/m.The deck shall withstand a load of 100 kg distributed over an area of
0,2 x 0,2 m
6.3.3 Wind load : wind pressure in operation 14 m/s non guided platform and 20 Comply
m/s for guided platform
6.3.4.3 Guard rail resistance : the guard rail or top edge of the rigid side shall be Comply
able to resist without permanent deflection a vertical load of 1kN
6.6.3 Rope termination : Rope termination shall resist not less than 80% of the Comply
minimum guaranteed breaking load of the rope
6.8 Working coefficient of chain : the working coefficient of chain including Comply
chain termination shall be at least 8
7.3.2 Side of BMU platform : The side of a BMU platform shall bem above the Comply
decking.
7.7.3 Suspension wire rope restrain system : the lowest restraint point shall not Comply
be more than 40 m above the lowest working level. The distance between
restraints above 40 m shall not exceed 20 m
7.8 Stabilizing device for platform : The platform shall be provided with facade Comply
protection resting against the facade which may take the form of buffers rollers or
strip
8.1.1 Minimum pitch diameter on pulleys, drums and traction sheaves is 20 Comply
times the diameter of the wire rope
8.1.6.3 Service brake : brake shall be capable of stopping the platform, Comply
travelling at rated speed and with 1,25 times the WLL (Working load limit)
within a distance of 10 cm
8.3.5.4 Overload device : shall be triggered at or before reaching a load of 1,25 Comply
times the RL (minimum load capacity) of the platform
8.3.5.6 Overload device once triggered shall continuously isolate all movement Comply
except lowering until the overload has been removed
8.3.5.8 The setting elements for the tripping limit of the overload device shall be Comply
protected against unauthorised adjustment
8.3.9 Anticollision device : an anticollision device which stops lowering of the Comply
platform when an obstruction is encountered.
8.3.10.1 Lifting limit switch are provided and positioned so taht they Comply
automatically stop the platform at the highest level.They are used also to allow
11
suspension rig slewing, luffing, or telescoping
8.3.10.2 Lowering limit switch. if the lowest level is ground level or safe Comply
surface, an anti collision device is regarding as a lowering limit switch.
8.3.10.3 Ultimate lifting or lowering switch, shall be provided and shall be Comply
adjusted by acompetent person
8.4.1 Safeguard against running off : the drum and its ancillary equipment shall Comply
be designed to ensure that the wire ropes cannot runoff the drum side ways, in
case of a slack wire rope situation
8.9.2 .2 Overspeed : seconday brake shall automatically engage in the event of Comply
overspeed (more than 0,5 m/s) on lowering the platform
8.10.5 Pulley groove : the depth of the groove of the pulley can not exceed 1,4 Comply
times the diameter of the wire rope
8.11.1 Wire rope : The platform shall be suspended by steel wire ropes which Comply
shall be galvanized or offer a similar corrosion resistance
8.11.2 Wire rope diameter : the minimu wire rope diameter shall be 6 mm. the Comply
secondary wire rope must be same diameter or more
9.1.1.1 travel limit of drive system : End stop shall be provided and positionned Comply
so that they stop the movement before reaching any dangerous position
9.9.1 Hydraulic drive system : Load holding cylinder shall be provided with a Comply
pilot operated valve which prevents fluid leaving the cylinder in case of pipe
failure (anti return valve)
9.2.1 Trolley unit : The trolley unit shall be provided with guide rollers or Comply
flanged wheels which ensure the trolley unit s position on the trackway
9.2.1.3 Overturning : if the trolley deviates from the trackway or a wheel Comply
assembly fails, a device shall be provided to prevent the trolley unit overturning
9.2.1.6 Powered traversing : The nominal traversing speed shall not exceed 0,3 Comply
m/s .
9.2.1.6.3 Audible signal : During traversing of the trolley unit, an audible signal Comply
shall warn person at roof level that the trolley unit is moving
9.2.1.6.4 Protection bar : shall be attached to the wheels units to prevent feet Comply
being trapped. The distance between the bars and the rail track must not exceed
2cm.
10.1.3 Wire rope with integrated electrical conductor : The conductor shall Comply
not be less than 0,5 m in cross sectional area and shall be adequately insulated
and protected
10.1.1 Measure to monitor 3 phases system : shall be provided to ensure that Comply
incorrect phase rotation of the power supply cannot result in an incorrect control
response
10.1.4 Electric cable reeler : a limit switch or other system must stop the Comply
movement of the machine before the electric cable is completly unwound from
the cable reeler
10.1.5 Degrees of protection : All electrical equipement shall comply with Comply
EN60529 and when exposed to open air shall have a protection degree of not less
than IP 54
D.1.1 Steel quality : Fe 37 C (St 37-3) Comply
12
1.5 Tools
1.5.1 Design
1.5.2 Manufacturing
1.5.3 Finishing
Sand blasting
Hot zinc projection equipment
Painting facilities in Ral Chart
1.5.4 Transport
13
2 / TECHNICAL CONCEPT
AESA suspended access systems are the result of 26 years experience, developed in the
national Spanish market on the first decade, then in the main countries of Europe, and quickly
through the world.
The BMUs have been developed following the requirement of the architect, due to a
multitude of building application, following the design, the norms and safeties.
AESA have installed more than two thousand of units worldwide, often under severe
climatic conditions.
Due to these hard conditions, AESA developed a special coating, based on a hot zinc
spray, and two lyres painting, colour to the choice of the client.
All components are in the majority treated against corrosion, respecting the mechanical
principle.
The roof trolleys run on three or four wheels depending of the weight, the track run way
and the movements of the machine
The grooved hoist drum, the lifting mechanism, assure a total horizontality of the cradle
and a complete security of the users. It guaranties a perfect winding and unwinding of the
four wire rope.
Safety is the most important target for AESA. The machines are equipped with safety
devices, like over speed system, overload detection and all requirement of the BMUs
norms.
The cradle are aluminium made, closed on the four side, with rubber protection and facade
rollers. The length of the cradle can be adjusted following the requirements .
2.2 Concept
The AESA machine are composed mainly with a roof trolley, including the drum hoist,
the three or four traversing wheels (track mounted or trackless), one control panel box, all
the movement safeties, the electric gear motors for all movements, the four wire rope
etc..... The accessibility to the roof trolley is indeed very easy.
The jibs, one or two unit depending of the configuration and the model, with different
length and design.
One aluminium cradle, offered in several length and design.
The design and installation complies with national regulations like ANSI 120.1 (USA),
DTU 95.1 (France), DIN (Germany), PNO 120 (NL).
The AESA machines are also conform to the EC 1808 standard, TUV (Germany).
14
2.3 Components
The roof trolley consists of steel chassis, structure and frame, supporting the rotating fixation
of the jibs , the traversing wheels, and all accessories like electric cable winder, the main
control panel box etc ...
The drum hoist and safeties are non accessible by non authorized personnel.
The machine are moving horizontally by three or four wheels, the two front wheels are
motorized . The roof trolley can be parapet mounted, running on two vertical steel
track, in this case , the two wheels located on the low steel track are motorized.
The motorized wheels are mounted on a strong welded pivoting cage, supporting four
wheel guide, the gear motor, and the steel traversing wheel itself.
The motor is equipped with a disc brake which securely hold the trolley in any position
along the steel rail. Each wheel is mounted with four strong claws that prevents the trolley
from lifting from the track.
The trackless machine is equipped with the same N of wheels, fixed to the roof trolley
with a strong axle, with ball bearing, and nut into a hub. The wheels are steel made, and
recovered by polyurethane tyre. The powered wheels are the same than described above.
In this case , the machine will be guided along the parapet by a steel L profile 10 x 10 cm
or a concrete guide 10 x 10 cm or by two castor wheels on the parapet.
The pivoting and sliding rear wheels are ensuring to the machine to be safe even into the
narrow curve.
The horizontal movement is stopped by two electric detectors installed on the extremities
of the run way.
The Drum is constructed with a heavy steel tube, supported by a transversal shaft,
crossing the drum. The shaft is welded into each end on two heavy steel closing the
extremity of the drum.
The grooved drum winds the four wire rope at the same speed, they are guided with a
spooling system synchronized by a chain to the drum ensuring a perfect and perpendicular
winding of these.
15
The diameter of the drum is calculated following the height of the building. The main size
are 300 mm ; 600 mm ; 900 mm.
The safeties mounted on the drum are : over speed detector, coupled to an electric switch ,
which switches off immediately the operation when activated, and with a centrifugal
device, which will activate a hydraulic brake , immobilizing the drum immediately.
In case of slack rope, the spooling mechanism is equipped with four slack rope device,
coupled to four electric switches , stopping the movement.
The jib support is made by a strong steel tube, supporting two special brackets at each
extremity, where are connected the two jib by four special shaft, locked and secured.
The jib support is moved by a electric spindle bar or by an hydraulic jack, depending of
the length of the jib or of the weight of the cradle.
The wire rope are guided by pulleys from the machine housing to the extremity of the jib.
The jib movement is limited by two electric switches, and secured by two auxiliary
switches.
The suspension wire rope run from the aluminium cradle to, over the jib head pulley, then
through the jib to the roof trolley housing , and then are wound on the grooved drum.
2.3.5 Cradle
The cradle, almost made in aluminium is composed by two aluminium end stirrup, or two
free way stirrup, depending of the requirement, one peripherical aluminium structure, one
anti -sliding floor, totally closed, with four holes to evacuate the rain water.
16
The cradle is completely closed on the vertical walls by aluminium sheet 3/10, a special
stair is previous for access into the cradle.
The four suspension rope are anchored to the cradle by two special devices coupled to two
electric switches, preventing overloading action.
The four wire rope are mounted on calibrated spring, two of them are supporting 60 % of
the weight (lifting wire rope), and the other two, are supporting 40 % of the weight (safety
wire rope).
The cradle can be guided along the facade by cradle restraint system, composed either by
roller installed into a continuous guide on the facade, or by punctual anchorage, bolted on
the facade. In the two case, the cradle or the wire rope, are guided on the entire height of
the facade.
The cradle is equipped with a low trip bar, to avoid to damage the opening windows
during the descent or to stop the machine in low position or on its parking position.
The four steel galvanized ropes are selected following the norms.
The core of each rope consists of either, fibre, or fibre and copper wire for the transfer of
the electrical control signal from the cradle to the roof trolley.
The copper conductor is used only for height bigger than 40 m, the electric cable is used
for the small building
AESA electrical system operate on worldwide electrical current rating, 220 V tri ; 380 V tri,
460 V tri ; 230 V, 50 HZ or 60 HZ
17
The user of the machine can operate only one function at once, by a movement selector.
Operation of the machine from the cradle, is achieved by turning a key located on the
main control panel box on the roof trolley .
Machine is also equipped of a main interrupter, on the roof trolley avoiding use by non
authorized person.
Electric components :
It is possible to control the cradle from the cradle, a second control panel box is available in
the basket.
Information :
Electric motors, ABB or Bonfiglioli, and the Control panel boxes are at least IP 55
18
3 / MACHINES
The kind of machine needed for every project will depend of the type of building. AESA is
specialized on giving solutions to every kind of building and profile. Also we are based on
different king of standard models of BMU.
TRAVERSING
JIB LUFFING
CRADLE HOISTING
JIB SLEWING
SPREADER BAR MOVEMENT
PANTOGRAPHS FOR BALCONIES AND RECESS AREA
The AESA machine are composed mainly with a roof trolley, including the drum hoist.
AESA offers height different type of machine adapted to the particularities of the building.
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
4 / TYPE OF CIRCUIT
34
4.1.1 Standard rail track
The rail tracks are usually laid directly on the roof. The machine are counter balanced and
do not require anchorage on the roof. This installation does not require drilling into the
roof slab, which avoid interference with the waterproofing.
If the roofing system cannot bear high compression loading, rail have to be firmly
anchored to the structure in order to reduce the stability and the total weight of the
machine.
The parapet machine is installed to a steel structure attaching to the upper and lower track.
The steel structure is bolted or welded to the parapet. this has the advantage of a complete
installation that occupies a little space on the roof.
Sometimes the parapet is too high to allow the jib to go over it, vertical rail is installed on
the parapet.
When the roof can be equipped of a concrete slab for the traversing of the machine, a
guide can installed at 0.25 m from the parapet, to allow the machine to move on rubber
wheels in this area.
35
36
4.2.1 L profile 100 x 100 x 10 mm.
Hot galvanized L profile, anchored every meters by hilti M 10x25, the profile will follow
the peripherie of the building.
This L profile can be also mounted on the parapet, to avoid waterproofing interference in
the slab.
Directly integrated to the slab, the machine will be guided , following the round of the
building.
In this case, the machine will be guided by two castor wheels mounted on the two front
wheels of the machine. It is used for roof where bolts are not allowed to be drilled in the
slab. In order to change the traversing direction, the machine is equipped with a steering
mechanism, and will be moved from the slab .
37
38
4.3 Rail switches
A rail switch ensures that the machine can traverse either on the same track or negociate a
curve up to 90
Turntables ensure that the rail track can be switched to different direction on the roof, it is
necessary when the free space on the terace is almost reduced to the free space run way of
the machine
39
5 / SAFETIES
5. Safety device
6 / OPTIONS
40
41
7 / PERFORMANCE
Our drawing are made by AutoCAD 2000, it is necessary for us to get the building
drawing on the same support, to be sure to send back the study into the normal delay
which is 2 or 3 weeks
42
AESA WORLDWIDE REFERENCES
43
4461 1998 AESA-10 PEEK+CLOPPENBURG BLDG AUSTRIA
44
3718 1998 AESA-40 375377 QUEENS ROAD EAST CHINA
45
6043 AESA-02 BEIJING NETWORK CENTER CHINA
46
3412 1998 AESA-40 HOSPITAL GEORGES POMPIDOU FRANCE
3731 1996 AESA-10 ZODIAC FRANCE
47
6205 AESA-15 ZAC CARNOT MASSY FRANCE
48
5972 2002 AESA-15 CITY TOWER GERMANY
49
3796 1999 AESA-10 INTER.AIRPORT BEIRUT LEBANON
50
6311 AESA-10 ED. A-7 SANTA FE MEXICO
51
3253 1995 AESA-15 TORRE DE ESCRITORIOS PORTUGAL
52
6464 2002 AESA-15 EDIFICIO PORTICO PORTUGAL
6660 AESA-10 IOSA LISBOA PORTUGAL
53
1391 1984 AESA-05 LA SUD AMERICANA SEGUROS SPAIN
54
1763 1986 AESA-05 VILLAROEL 106 SPAIN
55
2008 1990 AESA-05 PG. DE GRACIA, 9 SPAIN
56
2159 1989 AESA-05 HIPERCOR SPAIN
57
2359 1991 AESA-05 SKANDIA REPSOL SPAIN
58
2507 1992 AESA-10 VALLE HEBRON - TRAUMATOLIGIA SPAIN
59
2719 1993 AESA-05 EDIFICI OLIMPIC SPAIN
60
2990 1994 AESA-05 HOSPITAL RIO CARRION SPAIN
3177 2003 Perfil gua (L) GRUPO URIACH - ED. PALAU SPAIN
61
3250 AESA-10 RED ELECTRICA DE ESPAA S.A.- SPAIN
62
4104 1998 AESA-01 EDIFICIO BERTELSMANN SPAIN
63
4592 1988 AESA-05 C&A SPAIN
64
4720 1993 AESA-05 CENTRESERVEI ZONA FRANCA SPAIN
65
5326 2000 AESA-10 DELEGACION DE HACIENDA SPAIN
66
5767 2004 AESA-30 - PLANTA 12 TORRE AGBAR BARCELONA SPAIN
67
5995 2002 AESA-10 SANT JOAN NORD II SPAIN
68
6665 2002 AESA-30 TEKNON FASE II SPAIN
69
7213 2004 AESA-15 HOSPITAL CLINIC SUD SPAIN
7592 AESA-01 CORTE INGLES SAN CHINARRO SPAIN
8299 2005 gndola sitja SITJA ORDESA, Ctra. del Prat SPAIN
70
5638 2001 AESA-10 JIN-YEH HEADQUARTER TAIWAN
71
4202 1998 AESA-10 JEDDAH BUSINESSMEN CTR. UNITED ARAB
4651 1999 AESA-10 MHOL BIN KHA LEEFA BIN ZAYED UNITED ARAB
72
4602 1990 AESA-10 BBC I UNITED K
73
HIGH RISE BUILDING WORLDWIDE * (reference list)
AESA is one of the five nominated company for Burj Dubai project
which is 705 m high and the highest high rise building in the world
(year 2005)
74
10 / PROJECT
75
MONTEVETRO. LONDON. (UK)
4 UNITS AESA 25
USED ALSO FOR CONSTRUCTION OF CURTAIN WALL
TELESCOPIC IN 3 SECTIONS
HYDRAULIC SLEWING, HOISTING AND TELESCOPING
EACH WITH AUXILIARY HOIST FOR 1000 Kg.
76
BANK OF AMERICA. DALLAS. (USA)
77
CITYCORP. NEW YORK. (USA)
78
VISION CITY. KUALA LUMPUR. (MALAYSIA)
79
Some countries are not shown on the map, because catalogue has been finish three
years ago. We will update the catalogue very soon.
80
AESA COMPLEMENTARY ACCESSORIES
11.1 Restraint system
Following European Norms EN 1808, cradle must be guided along the facade.
There is two type of restraint system
Consists to have a skate or roller fitted on the cradle (see below) and sliding into a
aluminium profile integrated into the facade, installed by aluminium and curtain wall
company.
This solution is the safer solution. Aluminium profile must be installed every two
meter vertically along the faade.
81
11.1.2 Lanyard restraint system
This solution consists to install stainless steel 316 sockets into the faade. Fitted to the
aluminium cladding, every two meters horizontally and every 20 m vertically. The
first line of socket must be at 20 m maximum from the top of the building and the
last line must be located at maximum 40 m from the ground floor.
Pin and button, composed by a socket and a pin equipped with spring.
Mousqueton and socket composed by a mousqueton and a socket fitted either
into the aluminium cladding or to the concrete slab.
82
83
84
11.2 Davits and sockets
Davits and sockets are required on privates terraces, in where we cannot install
Gondolas. There is three types of davits:
Steel rotating davit heavy model, which allow transfer of the cradle
AESA 2 on the terrace
Steel davit light model which does not allow transfer of the cradle on the
terrace
Steel heavy and light model parapet mounted.
85
86
87
88
89
11.3 Aluminium Monorail AESA 50
Date; 29/01/2004
Ind; A
90
11.3.1 Table of contents
-Page 7 Brackets
-Page 8 Brackets
-Page 9 Brackets
91
11.3.2 AESA 50 Profile
A-50/400
100x60mm
2) Size; 100 x 60 mm
A 50/600
140x60 mm
2) Size; 140 x 60
92
11.3.3 Accessories
Rope 3m
93
11.3.3.2 Single motorized trolley ref A.50.9
Including
94
11.3.3.3Double motorized trolley ref A.50.10
Including:
95
11.3.3.4 Brackets
Holes: 18 mm.
96
Hat bracket (for gantries or suspended alu track) ref. A.50.21
Holes: 18 mm.
97
Bracket for curtain wall (maxi 600 mm) ref.: A.50.17
98
11.3.3.5 End stop plate. Ref A.50.1
99
11.4 STEEL TWIN RAIL AND L PROFILE
100
Fig 2 Guide L profile
101
Fig 1: Steel twin rail anchored:
On this picture, we can see the concrete plinths and anchorage of the steel track. Concrete
plinth will be calculated and installed by the contractor following our instruction, reactions
and load effort.
The most current used profiles are IPN 160, IPN 180, HEA 120 to 180 and HEB 160 to 220.
102
Fig 2: Guiding L profile:
When we propose very light machine (3 to 5 tons, with an acceptable wheel gauge), we
recommend to contractor or consultant to install a concrete slab, surrounded by a Guiding L
profile which is more discrete and less expensive. Indeed, the machine traverses on rubber
wheels.
103
11.5 AESA 2, Individual and 2 m aluminium permanent cradles
104
105