M EET ING R EC O R D

Project No: 6103-203


Project: Landside Construction Works for the New Delma Commercial Port
Subject: ESTIDAMA Requirements & Final Deliverables
Date: 16th Oct 2016

Attendees
HILALCO Green Consulting SUB-CONTRACTORS
Ajantha Yapa Zohaib Ali Ahmed El Bashir(EE)
Viswanath S.K Amitha R Mustafa Kamal(EE)
Aravindan TA(Redfort)
Albert Raj(MAPCO)

SR ACTION
ITEM DETAILS
NO BY
ESTIDAMA REQUIREMENTS
1 Green consultants (GC) discussed the concerns regarding the U-value
calculation report prepared by Emarat Europe.
- Highlighted that there are discrepancies between the submitted section
details, and the precast panel connection details provided at the start
EE
of the project. GC stated that Emarat Europe may be requested by UPC,
to provide further details regarding precast panel connections. Emarat
Europe agreed that details demonstrating compliance with the
envelope elevations will be provided upon request by UPC.
- EE stated that the revised envelope U-value calculation report will be
EE
released one day after the comments are received on the same.
- GC stated that comments on the envelope elevations would be released
GC
by COB 16.10.2016.
2 Hilalco highlighted that there may be a change in glass U-value from 1.1
GC,
W/m2K to 1.2W/m2K due to non-availability of glass to achieve a U value of
HILALCO
1.1. GC stated that this will result in lower energy savings and thus loss of

Page 1 of 2
M EET ING R EC O R D

points related to energy performance of the building.


- Hilalco suggested that alternate credits are targeted to compensate for
the loss. Hilalco stated that the number of points which need to be
achieved would be confirmed soon.
- Hilalco and GC agreed that recommendation for targeting additional
credit points can be made once the flow rates for the different water
fixtures are finalized.
GC requested to provide light power densities and water fixtures & Fittings
3 MAPCO
details
GC highlighted about the pending close out report for CEMP. In addition, GC
4 informed that no waste manifest has been received since the commencement HILALCO
of the construction. Hilalco to provide the same at the earliest
HILALCO,
GC reiterated that all Delivery notes and photographic evidence as well as
5 Mapco, EE
tracking sheets to be compiled during the course of the project
REDFORT
MAPCO confirmed that energy meters and water meters will be provided as
6 MAPCO
per the RE-R2 and PW-R2 requirements of Estidama.
FINAL DELIVERABLES
Hilalco discussed with S/c regarding the documents which sub-contractors
need to provide during the course of project
a. Shop drawing, material submittals, method statements, ITP, with final
approval from consultants/clients
b. Material delivery notes, material verification reports, independent lab
reports/factory certificate, country of origin certificates with code 1
Mapco, EE
7 approval
REDFORT
c. Inspection requests of installation, testing & commissioning with code
1 approval
d. As built drawings, O&M manuals, Warranty certificates (where ever
applicable).
e. Comments/snag list points to be attended prior handing over.
f. All documents to meet ESTIDAMA requirements

Page 2 of 2