Beruflich Dokumente
Kultur Dokumente
(1) IEEE Std 1313.1 1996 IEEE Standard for Insulation Coordination Definitions, Principles, and Rules.
MITSUBISHI ELECTRIC POWER PRODUCTS, INC.
2
POWER SYSTEM ENGINEERING SERVICES
Four Basic Considerations
Overvoltage
Abnormal voltage between two points of a system that is greater than
the highest value appearing between the same two points under
normal service conditions.2
Overvoltages are the primary metric for measuring and
quantifying power system transients and thus insulation
stress.
(2) IEEE Std C62.22 1991 IEEE Guide for the Application of Metal Oxide Surge Arresters for Alternating Current
Systems, 1991.
MITSUBISHI ELECTRIC POWER PRODUCTS, INC.
5
POWER SYSTEM ENGINEERING SERVICES
Vocabulary of Voltage
Source: IEEE Std 62.22-1997, IEEE Guide for the Application of Metal-Oxide Surge Arresters for AC Systems
seconds milliseconds
10-20 minutes microseconds
Power
Frequency
1. Surge Arresters
Need to be sized and located properly to clip overvoltages.
2. Pre Insertion Resistors/Inductors
Need to be sized according to equipment being switched (only help
during breaker operation) to prevent excessive overvoltages from
being initiated.
3. Synchronous Close/Open Control
Need to use independent pole operated (IPO) breakers and program
controller based on equipment being switched (only help during
breaker operation) to prevent excessive overvoltages from being
initiated.
4. Surge Capacitors
Need to be sized and located to slow the front of incoming surges
la = 23.47 la = 23.47
lb = 22.56 lb = 22.56
lc = 21.64 lc = 20.64
WEST 500 kV BUS
GWB06
la = 9.518
lb = 8.603 la,b,c = 8.323
la,b,c = 8.323 la,b,c = 19.59 la,b,c = 5.634
lc = 7.689
CB CB CB CB CB CB CB CB CB
G752E G952E G762E G962E G772E G872E G972E
Line Trap1
To Transformer
Gas-to- Surge
Air Arrester
Bushing
CCVT
To GIS
Gas-to-Air Bay #6
Bushing
550 kV GIS
Notes
To GIS
Bay (1) Line traps only on phase A and C for 500 kV lines. In
EMTP model, phase B has a 2.53 m section of
550 kV GIS conductor modeled in place of line trap.
350 MCM
Ground
Lead (38)
Step 1: A severe voltage surge was injected into the substation for various
operating configurations to screen for maximum potential overvoltages.
Screening Analysis
Step 2: The resulting overvoltages were compared to the Basic Lightning Impulse
Insulation Level (BIL) of the equipment and the protective margin1 for the
equipment was calculated.
Step 3: If overvoltages resulted in less than a 20% protective margin in the initial
Detailed Analysis
screening analysis for cases with the full system in or N 1 contingencies, a more
detailed analysis was performed to identify the protective margins resulting from a
reasonable upper bounds lightning surge based on the configuration of the
substation and connected transmission lines.
For the detailed analysis, specific details of the transmission lines such as conductor
characteristics, shielding design, ground resistivity, keraunic level, etc. are considered to
determine a reasonable upper bounds to place on the lightning surge impinging on the
substation.
MLFULL_halfSRC>MLSRCA(Type 1)
4000
3000
2000
1000
0
0 5 10 15 20
Time (us)
MLFULLB>G752WB(Type 1)
2000
1000
500
0
0 5 10 15 20
Time (us)
Applicable Criteria
Basic Switching Impulse Level (BSL)
Probability of Flashovers
Source-Side Voltage
cycle window
Case simulated with
200-400 energizations
3 = cycle 2 = 2.08 ms
Tclose
Shield Wire:
Alumoweld 7#8
14.5 14.5
Outside diameter = 0.385
RDC = 2.40 Ohm/mi
78
(63 at midpoint)
B C A
27 27 Phase Conductor:
ACSR Lapwing
2/c Bundle 18 spacing
Outside diameter = 1.504
RDC = 0.059 Ohm/mi
54 Thick/Diam = 0.375
(24 at midpoint)
Center
Line
Line Length (total) = 85 mi
Untransposed
Ground resistivity = 37 Ohm m
0%
1.00 1.50 2.00 2.50 3.00 3.50 4.00
Peak Overvoltage (Per Unit on a 500 kV Base)
0%
1.00 1.50 2.00 2.50 3.00 3.50 4.00
Peak Overvoltage (Per Unit on a 500 kV Base)
Applicable Criteria
ANSI/IEEE Inrush Current Limits
Basic Switching Impulse Level (BSL)
Breaker Capability Beyond Standards
IEEE Std 80 for grounding
Voltage on system
side of switching
First restrike
device
occurs and
current is re
established
Current is
interrupted
Voltage on capacitor
bank side of
switching device (DC
trapped charge)
Peak overvoltage
from 2nd restrike