for customer
Contents
1 Live network information...................................................................................................3
1.1 Live network topology............................................................................................3
1.2 Business volume.....................................................................................................3
1.3 Main existing problems..........................................................................................4
1.4 Remote access information.....................................................................................4
2 Purpose and Requirements..................................................................................................4
2.1 Change purpose.......................................................................................................4
2.2 Change scenario......................................................................................................4
2.3 Change scope & scale.............................................................................................4
2.4 Change Period.........................................................................................................5
3 Description of Change and Change Influence....................................................................5
3.1 NE list & version number or patch number before and after change.....................5
3.2 Surrounding NEs and version number involved by the change.............................5
3.3 Change relevance....................................................................................................6
3.4 Description of changed software............................................................................6
3.5 Description of changed hardware...........................................................................6
4 Change Preparations...........................................................................................................6
4.1 Composition of Change Team and Responsibility of Team Members...................6
Change Team of XX Company.................................................................................................6
Huawei Change Team...............................................................................................................6
Huawei Support & Guarantee Team.........................................................................................7
4.2 Check of Equipment Running................................................................................7
4.3 Change Risks and Countermeasures.......................................................................7
4.4 Check Before Change.............................................................................................8
5 Operation Steps for Change................................................................................................8
5.1 Change Steps...........................................................................................................8
5.2 Test and Verification...............................................................................................9
5.3 Solution for Changeback In the Case of Failure..................................................10
5.3.1 Definition of Change Failure..............................................................................10
Definition of Change Failure...............................................................................................10
Rollback decision..................................................................................................................10
5.3.2 Overall Description of Changeback..................................................................10
5.3.3 Information Collection Before Changeback.....................................................11
5.3.4 Changeback Steps..............................................................................................11
No main existing problems: Only software upgrade for the new version for Umniah
Technical support website: Technical support hotline: Page 4 of 11
http://support.huawei.com Fax:
Implementation Solution for Change
Phase13
Version After
NE Type NE Name Version Before Change
Change
BTS3900 BTS3000V100R009C00SP23 BTS3900
Sweiseh
GSM 0 V100R011C10SPC260
BTS3900 Bader_Ma3sara BTS3000V100R009C00SP23 BTS3900
GSM (G) 0 V100R011C10SPC260
BTS3900 BTS3000V100R009C00SP23 BTS3900
Mahis(n)
GSM 0 V100R011C10SPC260
Technical support website: Technical support hotline: Page 5 of 11
http://support.huawei.com Fax:
Implementation Solution for Change
Not Involved
We already changed BSC Software from R16 to R18 for this GSM BSC
Now we will also upgrade the BTSs under this BSC.
Not Involved
4 Change Preparations
4.1 Composition of Change Team and Responsibility of Team Members
00315488
S Result
Item
N
1 Existing alarm Normal
2 Network KPI Normal
3 Hardware running status Normal
4 Timing Task Normal
5
6
Possibilit
SN Risk Description Impact Countermeasure
y
Remote connection is
1 Low High Contact on call manager
broken
BTS3900
V100R011C10 (GBTS) Upgrade Guide (U2000-Based).doc
(1) The dial test shows that calls cannot be made through a certain office route.
(2) Charging amount is wrong.
Technical support website: Technical support hotline: Page 8 of 11
http://support.huawei.com Fax:
Implementation Solution for Change
Rollback decision
Customer
2 (optional) Sakher 06:30
BTS3900
V100R011C10 (GBTS) Upgrade Guide (U2000-Based).doc
No need.
Possibilit
SN Risk Description Impact Countermeasure
y
Clarify owners, provision time, and software and disks that shall be provided.
6.4 Training
N/A