WTP Reckit Benckiser Design program

Drafting Time Engineering Time My time


No (hrs) (hrs) (hrs)
1 WTP tank (CIP Collection, balance, CSAS, Effluent, Biosludge & Chemical sludge)
A Foundation 15 10 4
B WTP Tank Floor Plan 15 10 4
C WTP tank Roof Plan 15 10 4
D WTP Tank section & details 15 10 4
2 Blower & Control room
A Foundation 12 8 3
B Slab on Ground Plan, Section & Details 12 8 3
C Concrete Roof Plan & Sections 12 8 3
D Beam schedule 12 8 3
3 Belt press, filtrate & sludge cake room
A Foundation 12 8 3
B Slab on Ground Plan, Section & Details 12 8 3
C Roof Steelworks Plan & Elevations 12 8 3
D Roof Steelworks Section & Details 12 8 3
4 Chemical tank area
A Chemical Tank area fondation 15 10 4
B Chemical Tanbk Area Slab Plan & Sections 15 10 4
C Chemical Tank Area Roof Steelwork Plan, Elevation & Details 12 8 3

TOTAL (hrs) = 198 132 51