Beruflich Dokumente
Kultur Dokumente
Indias solar journey started with approval of Jawaharlal Nehru National Solar
Mission in 2010. Solar energy is important considering large environmental
benefits and countrys goal of energy independence. Under JNNSM Government
set a target of 20,000 MW solar power capacity by 2022. It was envisaged that
price of electricity from solar power plants will match that of grid electricity by
2022.
India has recently crossed the milestone of 5,000 MW solar power plant capacity.
Most of this capacity is utility scale solar power projects for sale of electricity to
grid. This power is procured by the process of Reverse Bidding where the
contract is signed with the bidders with the low electricity tariffs. Since 2009,
tariffs for solar power plant have rapidly fallen from Rs. 17.00 per unit in 2010 to
Rs. 4.34 per unit in 2016. To benefit from fall in prices, Government has recently
revised the targer under JNNSM from 20,000 MW to 1,00,000 MW by 2022. This
change has been because of following reasons:
Rapidly reducing capital cost solar power plants (Rs. Lakhs per MW)
1,700 1,690
1,442
1,000
800
691
606
501
None of the below Rs. 5 per unit have closed the financing from the
lenders
If developers are banking on the fact that module prices have been falling
and so will fall in the future, then this could work adversely for them since
module prices have already started stabilising
Indian developers may face challenge while procuring modules and
inverters due to depreciating rupee in last few months
Due to margin pressures EPC players may use sub-standard components
which may result in loss of generation in long term