Beruflich Dokumente
Kultur Dokumente
Fig. 1-c
1
CIV E 481 SOIL ENGINEERING
Fig.1-d
For such situation pile foundation could be appropriate to
reduce settlement and attain higher bearing capacity at
depth. The load transfer mechanism is mainly by shaft
resistance if the undrained shear strength is less than
100kPa.whereas both the shaft and toe resistance could be
accounted if the undrained shear strength is greater than
100kPa. However it is suggested that the final design be
supplemented with actual test loading.
Fig. 1-d If the clay is swelling type, the effect of uplift pressure
should be taken in to account. If uplift force is very high,
underreamed and multi-underreamed piles, and screw piles may have to be used.
Fig.1-e
Here it appears that the pile is driven close to the clay
layer. Such installations transfer the stress influence to
the clay soil and cause increased settlement.
Moreover there exists a possibility of punching failure of
the bearing dense sand layer into a lower weak clay
material.
It is generally desirable to contain the stress influence
Fig. 1-e zone (stress bulb) within the dense sand. Shallow
foundation could be better option in most common
situations.
Fig.1-f
This shows the most appropriate use of pile foundation.
The load transfer mechanism is mainly end bearing. The
concerns will be the downdrag when the soft clay layer
consolidates and/or the uplift force in case the clay is
swelling type.
Fig. 1-f
Fig.1-g
Inappropriate use of pile foundation, since the stress is
transferred to the clay layer which causes excessive
settlement. If the pile is limited in the sand layer both
friction and end bearing resistance from this layer could
be potentially used, provided that the pile is not close to
the clay layer(as in case Fig.1-e).Downdrag as the fill and
the clay layers consolidate is also a major concern. As an
option removal of the fill and construction of shallow
foundation on the sand layer may be considered.
Fig. 1-g
2
CIV E 481 SOIL ENGINEERING
2. Given:
Friction piles; length =12.5 m, D=0.3 m, Q = 2,800kN (includes pile cap weight)
Insensitive clay up to 35m depth with Cu= 50kPa
Factor of safety =3
Required: Selection of number and spacing of piles.
Solution: Using ethod, and assuming the empirical adhesion factor, =0.9,
Single pile capacity: It is determined from frictional resistance
2800
n= = 15.85 , => take 16 piles
176.71
3*d= 3*0.3 = 0.9m / 1m+d= 1+0.3 = 1.3m => lets take the spacing as 1.3m
4.2
1.30 0.15
4.2
= *Cu*2(Lg+Bg)*L
(Taking = 0.9)
1.30
= 0.9*50*2*(4.2+4.2)*12.5
= 9450 kN
0.15
3
CIV E 481 SOIL ENGINEERING
Solution:
Accounting for the soil strength parameter variability, lets take simply the average of the
two undrained shear strength values: Cu (avg) = 0.5*(40+30) = 35kPa
Moreover we may ignore the pile tip resistance, which still keep us on safe side.
A) Single Pile action:
Qult= Qf= CuAs = 0.6*35**0.3*15 = 296.88 kN.
Qall = Qult/FS = 296.88/3.0 = 98.96 kN.
Qtotal = n*Qall = 112*98.96 kN = 11083.52 kN.
4
CIV E 481 SOIL ENGINEERING
2/3Lp
Lp=15m
Bg=6.3m
2V:1H 2V:1H
15m
Bedrock
Fig. 3
Solution:
Average stress increment at:
i) Top ( 2/3 *15 = 10 m from pile cap base)
Qall 11083.52
top = = = 114.98kPa
B g * Lg 6.3 * 15.3
Qall 11083.52
mid = = = 26.88kPa
( B g + z1 )( L g + z1 ) (6.3 + 10)(15.3 + 10)
Qall 11083.52
bot = = = 11.94kPa
( B g + z 2 )( L g + z 2 ) (6.3 + 20)(15.3 + 20)
5
CIV E 481 SOIL ENGINEERING
5. Given: A bored ,cast in-place pile , underreamed (see the sketch in Fig.4)
Applied Load = 2500 kN
Q=2500 kN
Soil parameters as sketched below in Fig.4.
Overall Factor of safety = 2
Local overstressing factor of safety = 3
Dp=0.6m
= 0.45
Required: Comment on the adequacy of the pile 9.0m Variable sandy clay
Cu=60 kPa
Solution:
= 0.45
The pile resistance comes from both frictional part
and the tip resistance.
Till,
Qs = *Cu*As = 0.45*60**0.6*9.0=458 kN Cu=200 kPa
Qp= Nc* Cu Ap= 9.0 *200* (1.8)2/4=4580 k Db=3Dp
Fig. 4
(I) Qall(overall)=(458+4580)/2 = 2519 kN > Qapp = 2500 kN
(II) Qall(local) = 458+4580/3= 1984.7kN < 2500 kN
Since the applied load exceed the limit for the local overstressing, the tentatively selected
pile is not adequate. Therefore either the diameter of pile and base should be increased or
install the pile at sufficient depth into the till.