Beruflich Dokumente
Kultur Dokumente
t
ip
Dept. of Civil and Environmental Engineering, University Of Auckland, 20 Symonds
d cr
Street, Auckland 1142, New Zealand, E-mail: mjel010@aucklanduni.ac.nz
te s
di nu
Mohd Saleh Jaafar
ye a
Professor, Department of Civil Engineering, University Putra Malaysia, 43400 UPM-
op M
Serdang, Malaysia, E-mail: msj@eng.upm.edu.my
C ted
Abstract
Modularization and industrialization has been regarded as parts of an answer to a sustainable development
solution. As part of the overall industry goal of moving towards sustainability which has been emphasized
in the construction industry master plan of Malaysia, prefabrication and IBS are promoted however the
move towards IBS construction requires tools to make it more feasible. In addition there are many cases of
incomplete or failed IBS construction projects due to lack of technical expertise and knowledge.
Constructability is a concept with the goal of incorporating knowledge in to the construction procedure
which can make the IBS construction endeavor less problematic, more feasible, and easier to promote
within the Malaysian construction industry. On the other hand constructability being all about collaboration
communication and appropriate exchange of knowledge can provide a pre-emptive conflict management
approach by improving the flow of correct, sufficient and more transparent information and design
specifications which could cause potential conflict and dispute. Thus construction practitioners
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/20/13. Copyright ASCE. For personal use only; all rights reserved.
involvement and constructability application needs to be clearly investigated in different project phases. A
t
ip
questionnaire is designed to assess the application of constructability concepts in order to find out each the
constructability input of each phase to the IBS projects and furthermore evaluating different partys level of
d cr
application for different constructability concepts. The findings of this research indicate that
te s
constructability awareness and to some extent application is low amongst IBS project participants. Though
di nu
there is not much classified information of constructability within the Malaysian IBS industry, significant
numbers of IBS practitioners are applying the concepts discretely. There is lack of collaboration and a great
ye a
deal of mistiming involved in the application of constructability contracting approaches and strategies in
op M
addition legal boundaries need to change in order to solve these issues, and move towards greater
Introduction
N ce
Sustainable resources, technologies, manufacturing and buildings are the hot topic of
Ac
debate and research. Why is sustainability so important? And why is there an urge to
ongoing struggle of unsustainable development among the nations around the world
(UNFPA, 2001). Throughout the world and amongst different construction cultures it is
resources and accountable for generating large percentages of solid waste. Thus a
sustainability movement has been prompted within the construction sector (Nelms, et al.
2007). The dominant definition for sustainability in construction is the creation and
t
ip
regarded as the product of the construction industry and corresponds to both the human
d cr
and non-human inhabitants of the world extensively incorporates issues such as;
te s
di nu
maintenance and replacement of systems, the ultimate disposition of waste, building
activity more sustainable (CII, 1986). The process of prefabrication is facilitated via
Industrialized building systems (IBS) are systems in which structural components are
ot p
N ce
assembled into a structure with minimal additional site works (CIDB, 2001). IBS is the
Ac
construction sustainability. The need for well managed safer, even perhaps better value
for money sustainable constructions and built environment has inspired the building
for IBS construction in Malaysia (CIDB, 2001). Despite the realized benefits of IBS its
actual application in Malaysia is not thought to be significant due to many reasons. The
t
ip
to provide this boost in IBS application in Malaysia. Constructability was defined and
d cr
introduce by the Construction Industry Institute (CII) with the simple goal of
te s
di nu
feasible and constructible. The major problems with IBS implementation is thought to be
lack of communication and appropriate knowledge flow making these projects less
ye a
constructible, thus incorporation and application of constructability concepts and
op M
programs with the goal of providing technical, operational, contractual, or administrative
guidance for subsequent projects (Reuss & Tatum, 1993), may be influential in increasing
C ted
cleaner and tidier construction process, reducing the amount of waste and site labor by
Ac
shifting the work off site (Shaari, 2003). This shift of work to a more controlled and less
exposed environment allows for the jobs to be carried out by specialized trained workers
and technicians with a higher level of supervision. Consequently prefabrication and the
a lot of consideration and planning for their assembly and competent placing, this boosts
the performance and provides a more economic use of resources compared to traditional
IBS construction has led to many advances in the construction industry worldwide.
Abd.Rahman and Omar (2006) stated that reduction in variability; increase in ease of
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/20/13. Copyright ASCE. For personal use only; all rights reserved.
manufacturing and at the same time a decrease in the cost of manufacturing, production
t
ip
and erection is obtained through the major standardization of construction elements in the
d cr
process of IBS construction. This standardization will also contribute to the ultimate
te s
quality of work and reduction of waste material. For instance methods such as
di nu
Volumetric IBS which is now being widely used especially for highway hotels and fast
food chains can substantially decrease the completion time and make assembly easier. In
ye a
the United Kingdom McDonolds restaurant UK Ltd has adopted the volumetric
op M
construction method decreasing construction time from 115 days to only 15 days,
C ted
Technology (ACOTEC), which is a wall system designed and developed in Finland for
ot p
N ce
the first time. The principal benefits of ACOTEC are regarded to be speed of
construction, time efficiency, low wastage of material, minimal wet work, and also the
Ac
high quality of the final product. ACOTEC wall panels are currently manufactured and
Perhaps the most important feature contributing to sustainability is the fact that IBS
construction can reduce or even eliminate a large portion of construction waste (Jaillon,
onsite work, time decrease, cost reduction; increase in quality and improved health and
safety standers which are embedded in IBS construction can assist sustainability and the
development of a more sustainable built environment (Blismas, et al. 2005; Pasquire &
culture can also contribute to the promotion and utilization of sustainability notions
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/20/13. Copyright ASCE. For personal use only; all rights reserved.
t
ip
within the construction industry.
d cr
IBS construction in Malaysia
te s
Although IBS is a major revolution in the construction industry which enabled
di nu
incorporation of more sustainable features for the construction industry Hamid, et al.
ye a
(2008) have reported that the 15% level of IBS usage within the Malaysian construction
op M
industry has even decreased to only 10 % in 2006. This could be due to the traditional
mindset of the Malaysian construction sector. Obviously the designers may not be very
C ted
comfortable with the application of this system and may feel that the use of prefabricated
elements would bring limitations to their initial design. However unclear initiative for
ot p
future sustainable construction, lack of awareness towards the potential benefits of IBS,
N ce
decision making tools and developments in the IBS supply chain could all be some of the
Ac
One of the main reasons for this low application is the lack of knowledge and
appreciation of IBS and its advantages among the industry layers, according to
Warszawski (1999) there is not enough education and training on the issue for the
industry participants and engineers. The Malaysian construction sector is also suffering
from the same problem, there are many cases of incomplete IBS construction projects due
Abd.Rahman & Omar (2006) state, IBS construction is often seen as a prefabricated mass
t
ip
architectural appearance, and many other setbacks common in the 1960s. This made a
d cr
bad impression on the public and owners of construction projects. Some examples of
these improper endeavors are the Pekeliling Flats in Kuala Lumpur, Taman Tun Sardon,
te s
di nu
Geluger, and Penang. Because of the relatively costly and complicated procedure of
implementing IBS manufacturing plants and facilities it requires a certain financial and
ye a
proficiency capacity. This resulted in the lack of involvement of small contractors in the
op M
Malaysian IBS projects. These small contractors who account for a large portion of
industry practitioners were mostly familiar and comfortable with conventional methods
C ted
of construction (Abd.Rahman & Omar, 2006). The work force of the Malaysian
in fact 69% of the registered work force in 2007 (CIDB, 2008). The employment of these
N ce
cheap workers without the appropriate skills required for IBS construction could be
Ac
The Malaysian local government and housing ministry saw IBS as an answer to the
housing shortage problem due to the speed, quality, and economic advantage of this
Malaysia strongly supports labor reducing systems in order to reduce the construction
industries dependency to the foreign labor, which will stop the out flow of Ringgit and
also reduce their negative social and cultural impacts (Shaari, 2003). The IBS roadmap
has been formulated by the Malaysian government and CIDB with the vision of having
t
In late 1970s articles and papers were published on the importance of introducing
ip
construction experience and knowledge into the design phase which is the basic
d cr
foundation of constructability. This stimulated the establishment of the Construction
te s
Industry Institute (CII) in 1983, with a mission to improve the cost effectiveness, total
di nu
quality management and international competitiveness of the construction industry
ye a
(Griffith, et al. 1995). In order to achieve the aforementioned goal the concept of
op M
constructability was defined by the CII as the optimum use of construction knowledge
and experience in planning, design, procurement, and field operations to achieve overall
C ted
project objectives (CII, 1986). This concept basically intended to provide a base for
easier implementation and delivery of construction projects, the concept was also known
ot p
(1986) OConner et al. (1986) and OConner and Davis (1988) was implemented to look
into different phases of the project delivery process (conceptual planning phase, design
Ac
phase and field operation phase) for constructability and its surrounding issues during
each phase. The CII integrated the above studies and produced the constructability
concept files with fourteen concepts corresponding to each phase of the project delivery
process (CII, 1987). In 1993 CII added three more concepts to the previous concept file.
A total number of seventeen concepts were established that encompasses eight concepts
for the conceptual planning phase, eight for design and procurement phase and one
The integration of construction experience and knowledge gained from previous projects
goal. Therefore injecting constructability input to design is simply for making the
t
ip
appropriate decisions the first time about any design or construction related issues.
d cr
Pulaski and Horman (2005) have mentioned this will lead to effective utilization of
te s
constructability knowledge to achieve efficiency. The constructability concept file
di nu
developed for different construction phases can be an indication for making better
decision although it is not a roadmap. However in order to make the best decision in the
ye a
best time collaboration is needed, roles and responsibilities need to be defined and
op M
considered among different contractual parties. Designers and engineers are perceived to
C ted
very early stages of the project. In fact Fischer and Tatum (1997) believe that the
designers are the most important users of constructability knowledge. The designers are
ot p
N ce
normally more knowledgeable than the owners, meaning they can influence the
constructability part of the project delivery process, they understand the benefits of
constructability better (Nima, Abdul-Kadir, & Jaafar, 1999). The contractors are the
dominant authority on the building site and construction phase. They have a lot of power
and influence in taking measures, choosing the building systems and major construction
methods. This means that contractors have the power to positively or negatively affect the
constructability of projects.
As part of the overall industry goal of moving towards sustainability which has been
emphasized in the construction industry master plan (CIDB, 2006), prefabrication and
IBS is promoted however the move towards IBS construction requires tools to make it
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/20/13. Copyright ASCE. For personal use only; all rights reserved.
more feasible. One of these tools can be incorporating and utilizing the developed
t
ip
constructability concept files in the project delivery process. If IBS constructability is
d cr
enhanced, then utilization of these systems will increase in favor of industrys
te s
sustainability perspective. In order to enhance sustainability through prefabrication and
di nu
IBS, paying attention to constructability issues regarding these methods appears to be
crucial.
ye a
Lack of knowledge and understanding of the benefits of IBS is a major prohibiting factor
op M
in the application of IBS in Malaysian construction. This lack of knowledge may lead to
C ted
all sorts of problems form technical difficulties in the construction process to lack of
the construction procedure making the construction endeavor more feasible, perhaps
N ce
failed IBS projects resulting in improved outcomes and more publicity for IBS
construction. Developers are not utilizing IBS due to the presence of cheap foreign work
force this dependency on foreign labor is not sustainable and not in line with the future
subsequently better IBS practices may boost the awareness of potential IBS practitioners
especially developers, contractors and engineers. They may realize that the utilization of
cheap foreign labor will not always result in more efficient and sustainable outcomes.
ultimately sustainability.
approach for all sorts of construction projects. Some of the common causes of conflicts
t
ip
and disputes in construction projects are lack of transparency in the design process,
d cr
insufficient design information or in some cases misleading information in the design
te s
documents. Constructability is about appropriate knowledge flow and communication at
di nu
the right time, in fact Reuss and Tatum (1993) believed that constructability knowledge
or occurrence of a dispute incident requiring great deal of time and resources for placing
concept will set the scene for sustainable procurement of IBS construction projects.
One of the other important issues is each partys responsibility for implementing the
constructability concept file. Who is responsible for the applying and optimizing each
What sort of teams and who should be the team members for implementing
constructability concepts? are some of the questions that need to be answered. On the
other hand Paulson (1976) believes that contractual arrangements should be drawn to
assure that current construction and operations knowledge are injected in the design
process. Generally for better implementation of constructability concept file within IBS
construction there is a need for contract management and team building. Contract
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/20/13. Copyright ASCE. For personal use only; all rights reserved.
t
ip
management as illustrated in Figure 1 can make the incorporation of constructability
d cr
inputs to IBS easier leading to sustainable procurement of IBS projects, and a successful
IBS culture in favor of promoting sustainability. In other words more constructability and
te s
di nu
constructible IBS means a more sustainable built environment, thus there is a need to
Research performed in Malaysia illustrates that the Malaysian industry has yet to realize
engineers that constructability is beneficial but they do not really generalize the concepts
Ac
under the umbrella of constructability (Nima, 2001). On the other hand constructability
implementation as discussed could be beneficial for better IBS delivery and sustainable
dependent on collaboration of parties at the right time. This highlights the importance of
contracting approach and perhaps contract management strategies in achieving the best
different parties to constructability application and also their timing as part of contracting
strategies and management program can be vital for the success of IBS construction and
In this research the current application of constructability concepts and features are
t
ip
assessed. Basically the research intends to investigate the application status of the IBS
d cr
practitioner in comparison to each other and perhaps indicate which parties are more
te s
involved in constructability implementation during different construction phases.
di nu
Moreover the constructability application in different construction phases will also be
investigated in order to assess constructability inputs for each phase of IBS projects. The
ye a
primary goal of this research is to assess the status quo of constructability implementation
op M
in IBS projects. The findings of this research optimistically could be a step towards
C ted
identifying the current IBS construction problems and possibly impracticalities regarding
strategies may be applied to cover the weaknesses and strive towards prosperous IBS
ot p
N ce
constructability concepts file developed by Nima et al (2001) for Malaysia is used. The
Ac
concepts file comprises of 23 concepts for three main phases of construction (Appendix).
Methodology
A questionnaire was developed and sent based on the constructability concept file
on the issue of constructability and its definition. In section B a question is asked about
the application of the 23 constructability concepts for Malaysia, the question aims to
understand if IBS industry participants in Malaysia are actually applying these concepts
or not. All respondents were chosen from the Malaysian IBS practitioners. The best
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/20/13. Copyright ASCE. For personal use only; all rights reserved.
t
ip
source of gathering the data and information is the Construction Industry Development
d cr
Board (CIDB) of Malaysia, in fact the CIDB has an IBS center which evaluates and
classified IBS industry practitioners and companies. The bulk of data needed for this
te s
di nu
research has been acquired through CIDBs IBS center, comprising of companies which
technique. After the identification of the strata, the weight and importance of each
stratum in the population is determined. The sample size (n) is then divided based on the
weight of each stratum, and the members are selected randomly from each stratum to
ot p
N ce
form a consistent and representative sample (Fellows & Liu, 1997). In this research the
sample size is calculated using the formula developed by Cochran (Cochran, 1963):
Ac
( )
Formula 1 =
This formula is valid if is the sample size, is the abscissa of the normal curve that
cuts off an area at the tails (1 - equals the desired confidence level, e.g., 95%), is the
the population, and is 1- . The value used for p is a conservative value of 0.5 since we
had no previous information on the sample characteristics, this will give the maximum
sample size. 95% was chosen for the confidence level which was equivalent to a value
of 1.96, and based on similar research performed in the past an of 10% was used to
calculate the sample size. The sample size calculated for the research was 96 but due to
the low response the sample size also is often increased by 30% to compensate for this
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/20/13. Copyright ASCE. For personal use only; all rights reserved.
t
ip
lack of response and based on this number the questionnaires are sent out.
d cr
Results
te s
A number of 73 questionnaires out of a total of 81 returned questionnaires were
di nu
ultimately acceptable for the study. Some of the questionnaires were excluded due to
ye a
non-completion or inappropriate answering because the respondents were not senior
op M
members or well informed and well qualified engineers and some inconsistencies were
noticed in their responses. A low response rate of 27% was obtained from the
C ted
respondents over a period of three month, low response rate are common for mailed
questionnaires. In fact Fellows & Liu (1997) for postal questionnaires a usable response
ot p
rate of 25%-35% is the expected. Vast majority of the respondents work in the private
N ce
sector, around 21.9% of the them were characterized as designers, a majority of 61.6%
were contractors and only 16.5% were manufacturers or suppliers, this was expected
Ac
because the questionnaires were sent based on the population of each group involved in
IBS sector through stratified sampling. Most of the respondents were involved in
traditional design-bid-built and also the design-build contracts, revealing that the
types of construction projects which is important for the goal of this research.
Most of the respondents had over 10 years experience in the industry, 38.3% had more
than 20 years experience, around 28.8% had between 15 to 20 years of experience and
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/20/13. Copyright ASCE. For personal use only; all rights reserved.
t
ip
total of 11% of the respondents had 5 to 10 years experience and finally only 2.7% had
d cr
less than 5 years experience. Nevertheless the respondents experience in IBS is
te s
significantly lower, this lack of experience is due to the fact that it is only 10 years that
di nu
the government has decided to promote IBS seriously. Around 82.2% of the respondents
had not heard the definition of constructability before and only a minority of 17.8% had
ye a
actually heard the definition before, this is not a surprise due to low constructability
op M
research and education performed in the Malaysia. Previous studies in America Uhlik and
C ted
Lores (1998) showed that 65% of the respondents had heard the term constructability
before which shows that the American construction industry seems to be very well
Initially the general application score (AS) for each constructability concept is obtained
from all respondents which are based on how many of the respondents applied each
concept. Since all of the 73 respondents were included in the calculation, AS is within the
range of 0 to 73 for each concept and tabulated in Table 1. Twelve of the respondents
were manufacturers or suppliers; the AS for these respondents is within the range of 0
to12 and included in Table 2. A total of 16 designers took part in the research, which
implies the AS of each concept varies from 0 to 16 demonstrated in Table 3.The AS for
the contractors are calculated and tabulated in Table 4 out of a total of 45. All the tables
are drawn based on the three main construction phases (Conceptual planning phase,
Design and procurement phase, and Field operation phase) in line with the research
objective.
t
ip
Please insert Table2
d cr
Please insert Table3
te s
di nu
In order to find out in which of the construction phases, the application of constructability
is significantly higher than others first ANOVA statistics is used to establish if there is
ye a
any significant difference in the application scores (AS) of the three phases. The ANOVA
op M
test is conducted with SPSS software; used for this test is 0.05. If significant is
smaller than =0.05 then it could be concluded that the groups of data are significantly
C ted
different. To determine which of the construction phases have the significant differences
and also to verify the order of constructability application for the different phases the Post
ot p
Hoc comparison based on Tukeys theory is performed by SPSS. The analysis is first
N ce
conducted for the general constructability application scores of all respondents taken part
Ac
separate respondent groups of suppliers, designers and contractors are analyzed (Tables
2, 3 and 4).
The significant obtained from ANOVA test performed among all respondents (Table 1)
equals to 0.042 which is smaller than the =0.05 this indicates that there is significant
difference between the phases in terms of constructability application. The Post Hoc test
is applied and as a result the mean difference between the conceptual planning phase and
field operation phase is larger than Tukeys HSD denoting that the total application score
of all respondents in the conceptual planning phase is significantly higher than their
application score in the field operation phase. The ANOVA test performed on Table 2
t
ip
obtained is 0.071 which is larger than =0.05. This demonstrates no significant difference
d cr
between the constructability application score of construction phases corresponding to the
suppliers. The ANOVA test is again performed this time for the responses attained from
te s
di nu
the designers (Table 3). The test shows that the significant is 0.009 which is smaller
than =0.05 suggesting that there is a significant difference between the constructability
ye a
application scores of construction phases for designers. The Post Hoc test reveals that the
op M
application score in the conceptual planning phase is significantly higher than the
application score in the field operation phase for designers. The Post Hoc test also shows
C ted
that the designers application score of constructability concepts in the design and
procurement is significantly larger than the field operation phase. In another words the
ot p
planning and the design phase compared to the field operation phase. The ANOVA test
Ac
contractors responses. However the significant achieved from SPSS is 0.110 which is
In this section the results are rearranged based on the level of constructability application
for each respondent. This means that each one of the 73 respondents is given a level of
application (LA) for constructability. The level of application is simply the number of
concepts that each respondent applies based on section B of the questionnaire. The LA
for each respondent during all three phases of the project is a number between 0 and 23
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/20/13. Copyright ASCE. For personal use only; all rights reserved.
t
ip
because there are 23 constructability concepts, as demonstrated in Table 5 for all
d cr
respondent groups (suppliers, designers, contractors).
te s
di nu
Please insert Table6
ye a Please insert Table7
constructability concepts the LA results for each respondent in the different phases are
C ted
also classified and tabulated in Tables 8, 9 and 10. Consequently a comparison between
the constructability LA of each participating groups in which in this study are designers,
ot p
In the previous section the ANOVA statistics were used to compare the constructability
Ac
application scores (AS) of different construction phases among respondents, where the
independent variables were the three construction phases and the dependent variables was
this section once again ANOVA is employed to find any significant differences between
respondent groups (designers, contractors and suppliers) are the independent variables
and also the LA obtained for each respondent will be the dependent variable. This
analysis is carried out for the full construction process (including all phases) followed by
has seven concepts which are the first seven concepts in section B of the questionnaire
answer sheet, therefore the LA calculated for each respondent will range from 0 to 7
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/20/13. Copyright ASCE. For personal use only; all rights reserved.
t
ip
(Table 6). The number of constructability concepts included in the design and
d cr
procurement phase is eight thus the LA for each respondent is ranging from 0 to 8 (Table
7). For the field operation phase 8 concepts are included therefore LA for each
te s
di nu
respondent is within the margin of 0 to 8 (Table 8).
For the whole construction process including all phases (Table 5) ANOVA analysis
ye a
showed a significant of 0.00 which smaller than =0.05, this indicates that there is a
op M
significant difference among the respondent groups LA score, furthermore the Post Hoc
C ted
test signifies that the mean difference between contractors and designers LA score is
significant and is more than Tukeys HSD value at 0.05 level of significance, indicating
during all phases of IBS construction compared to designers but no significant difference
was indicated between the contractors and suppliers LA scores. The LA for each
Ac
respondent in the conceptual planning phase is tabulated in the Table 6, ANOVA test for
this set of data shows significant (0.005) is lower than (0.05) indicating a significant
difference in the LA scores between the three groups of contractor, designer, and supplier
in this phase. The Post Hoc reveals that the level of application of the constructability
concepts related to contractors is significantly larger than the designers in the early phase
of conceptual planning. Based on the data in Table 7 the ANOVA test is performed with
but the significant (0.476) was larger than (0.05), consequently no significant
design and procurement phase is indicated. For Table 8 the significant gained from the
SPSS analysis is 0.00 and is lower than 0.05, suggesting there is a significant difference
between the respondent groups on their LA scores. The Post Hoc test illustrates that
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/20/13. Copyright ASCE. For personal use only; all rights reserved.
t
ip
contractors have the highest mean and their level of application for constructability
d cr
concepts is significantly higher than the suppliers and designers in the field operation
phase. The Post Hoc test also indicates that the suppliers have a significantly higher level
te s
di nu
of application in this phase compared to the designers.
in different phases of IBS application. There is also significant differences between the
C ted
level of application of different parties involved in IBS projects, these results need to be
classified in a more comprehendible manner. Thus the results were structured in the form
ot p
of two separate matrixes one for constructability application between the construction
N ce
Phases (Figure 2), and the other for constructability level of application between
contracting parties (Figure 3). In these two matrixes the value 1 represents a significantly
Ac
for no significant difference. As it can be seen in Figure 2 among all the respondents
conceptual planning phase and the field operation phase, this is represented by the value
1 in the first row and the last column of the matrix, this could be illustrated as , = 1.
between the constructability application of conceptual planning phase and the field
operation phase. The same applies to Figure 3 and when , = 1 this indicates that the
contractors in the conceptual planning phase. The same notion can be used to interpret all
t
ip
the values of the two matrixes.
d cr
Please insert Figure 2
te s
Please insert Figure 3
di nu
Constructability in the conceptual planning phase has larger application than the field
operation phase and although it has a higher mean in comparison with the design and
ye a
op M
procurement phase, there is no significant difference between the phases which are
applying early constructability concepts more than the later ones. In general the
the designers.
The constructability concepts used for this research developed by Nima (2001) are
included in the appendixes; based on these concepts the suppliers are practicing some of
the early stage constructability concepts from the conceptual planning phase; for instance
supplier like any other party involved in construction projects have their own assignment
of project schedule and completion date to track their work progress and also to keep in
the project timeframe which is C5 in the constructability concept file however this does
not necessarily indicate that they are involved in the scheduling of the whole project in
fact there involvement is often very limited. The suppliers also study the site layout C7 in
the constructability concept file because they often are in charge of the delivery of the
IBS components. The contracting process normally is a prohibiting factor for best
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/20/13. Copyright ASCE. For personal use only; all rights reserved.
t
ip
practice constructability.
d cr
The contractors have the most influence in the construction process and are implementing
te s
most of the constructability concepts regardless of their source phase in the construction
di nu
and field operation process. For instance concepts such as C2, C3, C5, C6, and C7 which
maintenance. These concepts are being applied after site possession and commencement
The analysis demonstrates that designers involvement in the constructability of the field
N ce
operation phase is significantly low and they are mainly applying the concepts of the
Ac
conceptual planning phase and also the design and procurement phase because they are in
charge of the early project development and design but have less authority in the field
operation phase. The designers are very much involved in the standardization, technical
mostly concerned with these issues, and the designer carries out the design change or
alterations concepts demarked by C10, C11, and C12. The designers are also applying
C3, C5, C6 in the conceptual planning phase which are being separately applied by the
these concepts.
The IBS contractors in Malaysia are considered to have more experience in the IBS
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/20/13. Copyright ASCE. For personal use only; all rights reserved.
t
ip
industry than other parties involved. This experience is needed in the early project
planning and because the mass usage of IBS components is a relatively new in Malaysia
d cr
the designers and project owners do not possess much information on the subject. Despite
te s
the fact that constructability teams and meetings are not often conducted in the Malaysian
di nu
construction industry the owners and the designers of IBS are forced to invite some of the
ye a
contractors and experienced personnel in the IBS industry for evaluation and assessment
op M
meetings, as a result the IBS contractor is involved in early project development concepts
needed and if this is not possible in the near future, contract management techniques have
N ce
the project lifecycle. For instance in traditional procurement and contracting procedures
the contractors involvements in projects are often after the planning and design phase
and after the construction process begins the bond between the contracting party and the
designing party is very weak, in addition there is no legal or binding clause for
Malaysia for effective and in time knowledge and experience contributions of contracting
parties.
If there is regular constructability enhancement meetings among all parties and the
t
unnecessary concerns and conflict causes are resolved before manifestation of conflict
ip
and dispute. Constructability needs to be defined and classified for the parties involved in
d cr
the construction process; and its value as a conflict management strategy should be
te s
highlighted. The constructability concept file could be regarded as a manifest for
di nu
collaboration, knowledge flow and information sharing; insuring all parties are in the
loop and clarity of work is achieved. This clarity and constant cooperation will
ye a
effectively reduce consequences of conflicts and moves towards sustainable procurement.
op M
Generally for achieving successful IBS construction as part of the overall industry goal of
C ted
and more effective and efficient application of constructability concepts is needed. The
ot p
findings of this research indicate that constructability awareness and to some extent
N ce
although there is not much classified information of constructability within the Malaysian
Ac
IBS industry, significant number of IBS practitioners are applying the concepts
discretely. The problem with this kind of application is that because they are not
classically trained there is lack of collaboration and a great deal of mistiming involved in
forward in line with the sustainability goal and achieve more practical, constructible, and
t
ip
conceptual planning phase which shows most lack of constructability implementation is
d cr
needed. Also enhancement of information flow plus understandable and simple
te s
di nu
sustainable outcomes.
ye a
Reference
op M
Abd.Rahman, A. B., & Omar, W. (2006). Issues and challenges in the implementation of
Industrialized Building Systems in Malaysia. Paper presented at the The 6th Asia-
C ted
Butterworths.
Ac
Blismas, N. G., Pendlebury, M., Gibb, A., & Pasquire, C. (2005). Constraints to the Use
Cochran, W. G. (1963). Sampling techniques (second ed.). New York: John Wiley and
Sons, Inc.
t
ip
Industrialized Building Systems. Kuala Lumpur: CIDB.
d cr
Construction Industry Institute. (1986). Constructability A Primer. Publication 3-1.
te s
di nu
Construction Industry Institute. (1987). Constructability Concepts File. Publication 3-3.
ye a Austin, Texas: CII.
Fellows, R. F., & Liu, A. M. M. (1997). Research Methods for Construction: Blackwell
op M
Science Ltd, UK.
260.
ot p
Griffith, A., Sidwell, A. C., & Sidwell, T. (1995). Constructability in Building and
N ce
Hamid, Z. A., Kamar, K. A. M., Zain, M., Ghani, K., & Rahim, A. h. A. (2008).
Industrialised Building System (IBS) in Malaysia: The Current State and R&D
Jaillon, L., Poon, C. S., & Chiang, Y. H. (2009). Quantifying the waste reduction
Kibert, C. J. (1994). Principles of sustainable construction. Paper presented at the The 1st
t
ip
Nelms, C. E., Russell, A. D., & Lence, B. J. (2007). Assessing the performance of
d cr
sustainable technologies: a framework and its application. Building Research &
te s
di nu
Nima, M. A. (2001). Constructability factors in the Malaysian construction industry.
ye a University Putra Malaysia, Selangor, Malaysia.
Nima, M. A., Abdul-Kadir, M. R., & Jaafar, M. S. (1999). Evaluation of the engineers
op M
personnels role in enhancing the project constructability. Facilities, 17(11), 423-
430.
C ted
564.
N ce
112(4), 463-475.
Ogden, R. (2005). Offsite (IBS) in the UK Developers Perspective. Paper presented at the
Pasquire, C. L., & Gibb, A. G. F. (2002). Considerations for assessing the benefits of
t
ip
Pulaski, M., & Horman, M. (2005). Continuous Value Enhancement Process. Journal of
d cr
Construction Engineering and Management, 131(12), 1274-1282.
te s
di nu
Building and Environment, 29(4), 421-436.
Reuss, M. C., & Tatum, C. B. (1993). Requirements and tools for transferring
ye a
construction experience between projects: Stanford University. Center for
op M
Integrated Facility, Engineering.
Texas at Austin.
Ac
UNFPA. (2001). Chapter 3. The State of World Population 2001. Retrieved 20th of
t
3.Under what types of contracts do you usually work with:
ip
Traditional design-bid-build Design-build
Construction management Others please verify
d cr
4. In what type of projects your organization is mainly involved?
General building (commercial and industrial) Industrial
Civil (highway and heavy works)
te s
Others please verify
di nu
5. Years of experience in the construction industry:
0 5 years 10 15 years
5 10 years 15 20 years
More than 20 years
ye a
6. Years of experience in the Industrial Building Systems (IBS) industry:
0 5 years 10 15 years
op M
5 10 years 15 20 years
More than 20 years
C ted
C1, Documented constructability program should be prepared for all the project phases by
ot p
C4, The construction methods should be considered in determining the type and number of contracts
required
Yes No
C5, Project schedule and completion date should be assigned early and must be construction
sensitive.
Yes No
C6, Major construction methods should be discussed and analyzed in-depth as early as possible.
Yes No
C7, Site layout should be studied carefully to ensure efficient construction, operation, and
maintenance.
Yes No
C8, The construction schedule must be discussed and developed prior to the design development and
procurement schedule. Yes No
C9, Usage of information technology could overcome the problem of fragmentation between
specializations involved in construction. Yes No
C10, Design simplification by designers and design reviews by construction personnel, must be
configured.
Yes No
C11, Project elements should be standardized to an extent that will never effect the project cost
negatively.
Yes No
C12, The project technical specifications has to be simplified without sacrificing the level of
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/20/13. Copyright ASCE. For personal use only; all rights reserved.
t
efficiency.
ip
Yes No
C13, Modularization and preassembly design should be prepared to assist fabrication, transport and
installation.
d cr
Yes No
C14, Design should consider the construction personnel, materials, and equipments accessibility to
te s
site locations. Yes No
C15, Design should facilitate construction during adverse weather conditions. (The use of
di nu
prefabricated elements)
Yes No
C16, Field task should be organized to minimize damage, reworking or congestion of construction
personnel, material, and equipment. Yes No
ye a
C17, Innovations in using available temporary construction materials/systems which are not limited
op M
by the design and technical specifications. Yes No
C18: Incorporating innovation of new methods in using off-the-shelf hand tools, modification of
available tools, or introduction of new hand tools that reduce labor intensity or increase mobility,
safety, or accessibility.
C ted
Yes No
C19, Introduction of innovative methods in using the available equipment or modification of the
available equipment to increase their productivity. Yes No
C20, Using optional preassembly will lead to increase in productivity, reduction of scaffolding, and
ot p
C22, The work of contractors should be documented based on quality and time so future projects are
awarded based on these attributes and not just low bids. Yes No
C23, Evaluation, documentation, and feedback regarding constructability concepts during project
phases should be maintained as lessons learnt for future projects. Yes No
Ac
Journal of Legal Affairs and Dispute Resolution in Engineering and Construction. Submitted September 24, 2012; accepted March 29, 2013;
posted ahead of print May 4, 2013. doi:10.1061/(ASCE)LA.1943-4170.0000121
List of Figures
t
ip
d cr
te s
di nu
ye a
op M
C ted
ot p
N ce
Ac
Journal of Legal Affairs and Dispute Resolution in Engineering and Construction. Submitted September 24, 2012; accepted March 29, 2013;
posted ahead of print May 4, 2013. doi:10.1061/(ASCE)LA.1943-4170.0000121
Accepted Manuscript
Not Copyedited
Journal of Legal Affairs and Dispute Resolution in Engineering and Construction. Submitted September 24, 2012; accepted March 29, 2013;
posted ahead of print May 4, 2013. doi:10.1061/(ASCE)LA.1943-4170.0000121
Contractors 0 0
Field All -1 0
operation respondents
phase Suppliers 0 0
Designers -1 -1
Contractors 0 0
Accepted Manuscript
Not Copyedited
Journal of Legal Affairs and Dispute Resolution in Engineering and Construction. Submitted September 24, 2012; accepted March 29, 2013;
posted ahead of print May 4, 2013. doi:10.1061/(ASCE)LA.1943-4170.0000121
Contractors
Conceptual planning 1 0
phase
Design and 0 0
procurement phase
Field operation phase 1 1
All phases -1 0
Conceptual planning -1 0
Designers phase
Design and 0 0
procurement phase
Field operation phase -1 -1
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/20/13. Copyright ASCE. For personal use only; all rights reserved.
All phases 0 0
Conceptual planning 0 0
Suppliers
phase
Design and 0 0
procurement phase
Field operation phase -1 1
Accepted Manuscript
Not Copyedited
Journal of Legal Affairs and Dispute Resolution in Engineering and Construction. Submitted September 24, 2012; accepted March 29, 2013;
posted ahead of print May 4, 2013. doi:10.1061/(ASCE)LA.1943-4170.0000121
Table 1 All respondents constructability application scores (AS) according to different phases
C7 64 C14 54 C22 48
C15 28 C23 61
Accepted Manuscript
Not Copyedited
C5 12 C12 7 C20 6
C6 10 C13 11 C21 2
C7 12 C14 9 C22 5
C15 6 C23 10
Accepted Manuscript
Not Copyedited
C6 15 C13 13 C21 2
C7 13 C14 10 C22 3
C15 2 C23 8
Accepted Manuscript
Not Copyedited
C4 26 C11 35 C19 32
C5 45 C12 38 C20 36
C6 38 C13 35 C21 24
C7 39 C14 35 C22 40
C15 20 C23 43
Accepted Manuscript
Not Copyedited
Accepted Manuscript
Not Copyedited
Accepted Manuscript
Not Copyedited
Accepted Manuscript
Not Copyedited
Accepted Manuscript
Not Copyedited