Sie sind auf Seite 1von 43

Journal of Legal Affairs and Dispute Resolution in Engineering and Construction.

Submitted September 24, 2012; accepted March 29, 2013;


posted ahead of print May 4, 2013. doi:10.1061/(ASCE)LA.1943-4170.0000121

In Seek of Sustainability; Constructability Application and Contract

Management in Malaysian Industrialized Building Systems

Mostafa Babaeian Jelodar


Downloaded from ascelibrary.org by Istanbul Universitesi on 08/20/13. Copyright ASCE. For personal use only; all rights reserved.

t
ip
Dept. of Civil and Environmental Engineering, University Of Auckland, 20 Symonds

d cr
Street, Auckland 1142, New Zealand, E-mail: mjel010@aucklanduni.ac.nz

te s
di nu
Mohd Saleh Jaafar

ye a
Professor, Department of Civil Engineering, University Putra Malaysia, 43400 UPM-
op M
Serdang, Malaysia, E-mail: msj@eng.upm.edu.my
C ted

Tak Wing Yiu


ot p

Senior Lecturer, Dept. of Civil and Environmental Engineering, University Of Auckland,


N ce

20 Symonds Street, Auckland 1142, New Zealand, E-mail: k.yiu@auckland.ac.nz


Ac

Abstract

Modularization and industrialization has been regarded as parts of an answer to a sustainable development

solution. As part of the overall industry goal of moving towards sustainability which has been emphasized

in the construction industry master plan of Malaysia, prefabrication and IBS are promoted however the

move towards IBS construction requires tools to make it more feasible. In addition there are many cases of

incomplete or failed IBS construction projects due to lack of technical expertise and knowledge.

Constructability is a concept with the goal of incorporating knowledge in to the construction procedure

Copyright 2013 by the American Society of Civil Engineers

Journal of Legal Affairs and Dispute Resolution in Engineering and Construction


Journal of Legal Affairs and Dispute Resolution in Engineering and Construction. Submitted September 24, 2012; accepted March 29, 2013;
posted ahead of print May 4, 2013. doi:10.1061/(ASCE)LA.1943-4170.0000121

which can make the IBS construction endeavor less problematic, more feasible, and easier to promote

within the Malaysian construction industry. On the other hand constructability being all about collaboration

communication and appropriate exchange of knowledge can provide a pre-emptive conflict management

approach by improving the flow of correct, sufficient and more transparent information and design

specifications which could cause potential conflict and dispute. Thus construction practitioners
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/20/13. Copyright ASCE. For personal use only; all rights reserved.

involvement and constructability application needs to be clearly investigated in different project phases. A

t
ip
questionnaire is designed to assess the application of constructability concepts in order to find out each the

constructability input of each phase to the IBS projects and furthermore evaluating different partys level of

d cr
application for different constructability concepts. The findings of this research indicate that

te s
constructability awareness and to some extent application is low amongst IBS project participants. Though

di nu
there is not much classified information of constructability within the Malaysian IBS industry, significant

numbers of IBS practitioners are applying the concepts discretely. There is lack of collaboration and a great
ye a
deal of mistiming involved in the application of constructability contracting approaches and strategies in
op M
addition legal boundaries need to change in order to solve these issues, and move towards greater

sustainability of the built environment.


C ted

Keywords: Sustainability; Constructability; Industrialized Building systems (IBS); Contract

Management, Conflict Management,


ot p

Introduction
N ce

Sustainable resources, technologies, manufacturing and buildings are the hot topic of
Ac

debate and research. Why is sustainability so important? And why is there an urge to

achieve maximum sustainable practices in the construction sector? In fact there is an

ongoing struggle of unsustainable development among the nations around the world

(UNFPA, 2001). Throughout the world and amongst different construction cultures it is

observed that the process of construction, operation, and maintenance of traditional

buildings is responsible for the consumption of a significant percentage of the worlds

Copyright 2013 by the American Society of Civil Engineers

Journal of Legal Affairs and Dispute Resolution in Engineering and Construction


Journal of Legal Affairs and Dispute Resolution in Engineering and Construction. Submitted September 24, 2012; accepted March 29, 2013;
posted ahead of print May 4, 2013. doi:10.1061/(ASCE)LA.1943-4170.0000121

resources and accountable for generating large percentages of solid waste. Thus a

sustainability movement has been prompted within the construction sector (Nelms, et al.

2007). The dominant definition for sustainability in construction is the creation and

operation of a healthy built environment based on ecological principles and resource

efficiency(Kibert, 1994). However sustainability in the built environment which is


Downloaded from ascelibrary.org by Istanbul Universitesi on 08/20/13. Copyright ASCE. For personal use only; all rights reserved.

t
ip
regarded as the product of the construction industry and corresponds to both the human

d cr
and non-human inhabitants of the world extensively incorporates issues such as;

extraction of materials, manufacturing of products, assembly of products into buildings,

te s
di nu
maintenance and replacement of systems, the ultimate disposition of waste, building

systems and the building structure (Blismas, et al. 2005).


ye a
Different sustainable methods and technologies have been proposed including green
op M
construction and also prefabrication which plays a significant role in making construction
C ted

activity more sustainable (CII, 1986). The process of prefabrication is facilitated via

manufacturing and industrialization which has proved beneficial to most industries.

Industrialized building systems (IBS) are systems in which structural components are
ot p
N ce

prefabricated or manufactured in a factory on or off worksite, then transported and

assembled into a structure with minimal additional site works (CIDB, 2001). IBS is the
Ac

dominant conceptualization and terminology used for prefabricated construction in

Malaysia. Prefabrication, IBS and their design procedure are considered as an

opportunity to introduce sustainable features to the construction process and enhance

construction sustainability. The need for well managed safer, even perhaps better value

for money sustainable constructions and built environment has inspired the building

sector to take on the challenge of prefabrication, accordingly the Malaysian government

Copyright 2013 by the American Society of Civil Engineers

Journal of Legal Affairs and Dispute Resolution in Engineering and Construction


Journal of Legal Affairs and Dispute Resolution in Engineering and Construction. Submitted September 24, 2012; accepted March 29, 2013;
posted ahead of print May 4, 2013. doi:10.1061/(ASCE)LA.1943-4170.0000121

is regulating policies towards the improvement and promotion of infrastructure needed

for IBS construction in Malaysia (CIDB, 2001). Despite the realized benefits of IBS its

actual application in Malaysia is not thought to be significant due to many reasons. The

implementation and application of IBS needs to be boosted to move towards a more

sustainable construction environment. Constructability as a conceptual program may able


Downloaded from ascelibrary.org by Istanbul Universitesi on 08/20/13. Copyright ASCE. For personal use only; all rights reserved.

t
ip
to provide this boost in IBS application in Malaysia. Constructability was defined and

d cr
introduce by the Construction Industry Institute (CII) with the simple goal of

incorporating technical knowledge in projects to make the construction process more

te s
di nu
feasible and constructible. The major problems with IBS implementation is thought to be

lack of communication and appropriate knowledge flow making these projects less
ye a
constructible, thus incorporation and application of constructability concepts and
op M
programs with the goal of providing technical, operational, contractual, or administrative

guidance for subsequent projects (Reuss & Tatum, 1993), may be influential in increasing
C ted

efficient IBS culture.


ot p

Why is IBS construction sustainable?


N ce

Prefabrication and Industrialization in the construction industry can promise a faster,

cleaner and tidier construction process, reducing the amount of waste and site labor by
Ac

shifting the work off site (Shaari, 2003). This shift of work to a more controlled and less

exposed environment allows for the jobs to be carried out by specialized trained workers

and technicians with a higher level of supervision. Consequently prefabrication and the

industrialization procedures go through regular inspections which will improve the

quality of construction components. Prefabrication and industrialization normally entails

a lot of consideration and planning for their assembly and competent placing, this boosts

Copyright 2013 by the American Society of Civil Engineers

Journal of Legal Affairs and Dispute Resolution in Engineering and Construction


Journal of Legal Affairs and Dispute Resolution in Engineering and Construction. Submitted September 24, 2012; accepted March 29, 2013;
posted ahead of print May 4, 2013. doi:10.1061/(ASCE)LA.1943-4170.0000121

the performance and provides a more economic use of resources compared to traditional

cast on site constructions (Retik & Warszawski, 1994).

IBS construction has led to many advances in the construction industry worldwide.

Abd.Rahman and Omar (2006) stated that reduction in variability; increase in ease of
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/20/13. Copyright ASCE. For personal use only; all rights reserved.

manufacturing and at the same time a decrease in the cost of manufacturing, production

t
ip
and erection is obtained through the major standardization of construction elements in the

d cr
process of IBS construction. This standardization will also contribute to the ultimate

te s
quality of work and reduction of waste material. For instance methods such as

di nu
Volumetric IBS which is now being widely used especially for highway hotels and fast

food chains can substantially decrease the completion time and make assembly easier. In
ye a
the United Kingdom McDonolds restaurant UK Ltd has adopted the volumetric
op M
construction method decreasing construction time from 115 days to only 15 days,
C ted

reaching a record construction time from ground breaking to completion of only 48

hours (Ogden, 2005). Another prefabricated system is Advanced Construction

Technology (ACOTEC), which is a wall system designed and developed in Finland for
ot p
N ce

the first time. The principal benefits of ACOTEC are regarded to be speed of

construction, time efficiency, low wastage of material, minimal wet work, and also the
Ac

high quality of the final product. ACOTEC wall panels are currently manufactured and

utilized in construction projects of Germany, Japan, Korea, Taiwan, Philippines, Thailand

and Indonesia (Hui & Or, 2005).

Perhaps the most important feature contributing to sustainability is the fact that IBS

construction can reduce or even eliminate a large portion of construction waste (Jaillon,

et al. 2009). However features such as production in a controlled environment, reducing

Copyright 2013 by the American Society of Civil Engineers

Journal of Legal Affairs and Dispute Resolution in Engineering and Construction


Journal of Legal Affairs and Dispute Resolution in Engineering and Construction. Submitted September 24, 2012; accepted March 29, 2013;
posted ahead of print May 4, 2013. doi:10.1061/(ASCE)LA.1943-4170.0000121

onsite work, time decrease, cost reduction; increase in quality and improved health and

safety standers which are embedded in IBS construction can assist sustainability and the

development of a more sustainable built environment (Blismas, et al. 2005; Pasquire &

Gibb, 2002). Simplification, standardization, frequent inspection as part of the IBS

culture can also contribute to the promotion and utilization of sustainability notions
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/20/13. Copyright ASCE. For personal use only; all rights reserved.

t
ip
within the construction industry.

d cr
IBS construction in Malaysia

te s
Although IBS is a major revolution in the construction industry which enabled

di nu
incorporation of more sustainable features for the construction industry Hamid, et al.
ye a
(2008) have reported that the 15% level of IBS usage within the Malaysian construction
op M
industry has even decreased to only 10 % in 2006. This could be due to the traditional

mindset of the Malaysian construction sector. Obviously the designers may not be very
C ted

comfortable with the application of this system and may feel that the use of prefabricated

elements would bring limitations to their initial design. However unclear initiative for
ot p

future sustainable construction, lack of awareness towards the potential benefits of IBS,
N ce

unclear responsibilities in IBS and sustainability implementation, lack of research in

decision making tools and developments in the IBS supply chain could all be some of the
Ac

reasons for the low usage of IBS in Malaysia.

One of the main reasons for this low application is the lack of knowledge and

appreciation of IBS and its advantages among the industry layers, according to

Warszawski (1999) there is not enough education and training on the issue for the

industry participants and engineers. The Malaysian construction sector is also suffering

from the same problem, there are many cases of incomplete IBS construction projects due

Copyright 2013 by the American Society of Civil Engineers

Journal of Legal Affairs and Dispute Resolution in Engineering and Construction


Journal of Legal Affairs and Dispute Resolution in Engineering and Construction. Submitted September 24, 2012; accepted March 29, 2013;
posted ahead of print May 4, 2013. doi:10.1061/(ASCE)LA.1943-4170.0000121

to lack of necessary technical expertise and knowledge in Malaysia. The difficulties of

IBS implementation in Malaysia could be associated with misperceptions, lack of

facilities, and insufficient knowledge and expertise of the parties involved. As

Abd.Rahman & Omar (2006) state, IBS construction is often seen as a prefabricated mass

construction method resembling low quality, leakage, abandoned projects, unpleasant


Downloaded from ascelibrary.org by Istanbul Universitesi on 08/20/13. Copyright ASCE. For personal use only; all rights reserved.

t
ip
architectural appearance, and many other setbacks common in the 1960s. This made a

d cr
bad impression on the public and owners of construction projects. Some examples of

these improper endeavors are the Pekeliling Flats in Kuala Lumpur, Taman Tun Sardon,

te s
di nu
Geluger, and Penang. Because of the relatively costly and complicated procedure of

implementing IBS manufacturing plants and facilities it requires a certain financial and
ye a
proficiency capacity. This resulted in the lack of involvement of small contractors in the
op M
Malaysian IBS projects. These small contractors who account for a large portion of

industry practitioners were mostly familiar and comfortable with conventional methods
C ted

of construction (Abd.Rahman & Omar, 2006). The work force of the Malaysian

construction industry is largely comprised of foreign unspecialized workers which were


ot p

in fact 69% of the registered work force in 2007 (CIDB, 2008). The employment of these
N ce

cheap workers without the appropriate skills required for IBS construction could be
Ac

regarded as another problem in the way of industrialization.

The Malaysian local government and housing ministry saw IBS as an answer to the

housing shortage problem due to the speed, quality, and economic advantage of this

method of construction. The Construction Industry Development Board (CIDB) in

Malaysia strongly supports labor reducing systems in order to reduce the construction

industries dependency to the foreign labor, which will stop the out flow of Ringgit and

Copyright 2013 by the American Society of Civil Engineers

Journal of Legal Affairs and Dispute Resolution in Engineering and Construction


Journal of Legal Affairs and Dispute Resolution in Engineering and Construction. Submitted September 24, 2012; accepted March 29, 2013;
posted ahead of print May 4, 2013. doi:10.1061/(ASCE)LA.1943-4170.0000121

also reduce their negative social and cultural impacts (Shaari, 2003). The IBS roadmap

has been formulated by the Malaysian government and CIDB with the vision of having

an industrialized construction environment.

The concept of constructability


Downloaded from ascelibrary.org by Istanbul Universitesi on 08/20/13. Copyright ASCE. For personal use only; all rights reserved.

t
In late 1970s articles and papers were published on the importance of introducing

ip
construction experience and knowledge into the design phase which is the basic

d cr
foundation of constructability. This stimulated the establishment of the Construction

te s
Industry Institute (CII) in 1983, with a mission to improve the cost effectiveness, total

di nu
quality management and international competitiveness of the construction industry
ye a
(Griffith, et al. 1995). In order to achieve the aforementioned goal the concept of
op M
constructability was defined by the CII as the optimum use of construction knowledge

and experience in planning, design, procurement, and field operations to achieve overall
C ted

project objectives (CII, 1986). This concept basically intended to provide a base for

easier implementation and delivery of construction projects, the concept was also known
ot p

as buildability in some texts (Adams, 1989). A series of investigations by Tatum et al.


N ce

(1986) OConner et al. (1986) and OConner and Davis (1988) was implemented to look

into different phases of the project delivery process (conceptual planning phase, design
Ac

phase and field operation phase) for constructability and its surrounding issues during

each phase. The CII integrated the above studies and produced the constructability

concept files with fourteen concepts corresponding to each phase of the project delivery

process (CII, 1987). In 1993 CII added three more concepts to the previous concept file.

A total number of seventeen concepts were established that encompasses eight concepts

Copyright 2013 by the American Society of Civil Engineers

Journal of Legal Affairs and Dispute Resolution in Engineering and Construction


Journal of Legal Affairs and Dispute Resolution in Engineering and Construction. Submitted September 24, 2012; accepted March 29, 2013;
posted ahead of print May 4, 2013. doi:10.1061/(ASCE)LA.1943-4170.0000121

for the conceptual planning phase, eight for design and procurement phase and one

concept for field operation phase (Fischer & Tatum, 1997).

The integration of construction experience and knowledge gained from previous projects

into the construction process to achieve maximum efficiency is constructabilitys prime


Downloaded from ascelibrary.org by Istanbul Universitesi on 08/20/13. Copyright ASCE. For personal use only; all rights reserved.

goal. Therefore injecting constructability input to design is simply for making the

t
ip
appropriate decisions the first time about any design or construction related issues.

d cr
Pulaski and Horman (2005) have mentioned this will lead to effective utilization of

te s
constructability knowledge to achieve efficiency. The constructability concept file

di nu
developed for different construction phases can be an indication for making better

decision although it is not a roadmap. However in order to make the best decision in the
ye a
best time collaboration is needed, roles and responsibilities need to be defined and
op M
considered among different contractual parties. Designers and engineers are perceived to
C ted

be influential participants in implementing constructability since they are involved at

very early stages of the project. In fact Fischer and Tatum (1997) believe that the

designers are the most important users of constructability knowledge. The designers are
ot p
N ce

normally more knowledgeable than the owners, meaning they can influence the

constructability implementation programs and persuade the owners to make


Ac

constructability part of the project delivery process, they understand the benefits of

constructability better (Nima, Abdul-Kadir, & Jaafar, 1999). The contractors are the

dominant authority on the building site and construction phase. They have a lot of power

and influence in taking measures, choosing the building systems and major construction

methods. This means that contractors have the power to positively or negatively affect the

constructability of projects.

Copyright 2013 by the American Society of Civil Engineers

Journal of Legal Affairs and Dispute Resolution in Engineering and Construction


Journal of Legal Affairs and Dispute Resolution in Engineering and Construction. Submitted September 24, 2012; accepted March 29, 2013;
posted ahead of print May 4, 2013. doi:10.1061/(ASCE)LA.1943-4170.0000121

Potentials of constructability and contract management for IBS in Malaysia

As part of the overall industry goal of moving towards sustainability which has been

emphasized in the construction industry master plan (CIDB, 2006), prefabrication and

IBS is promoted however the move towards IBS construction requires tools to make it
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/20/13. Copyright ASCE. For personal use only; all rights reserved.

more feasible. One of these tools can be incorporating and utilizing the developed

t
ip
constructability concept files in the project delivery process. If IBS constructability is

d cr
enhanced, then utilization of these systems will increase in favor of industrys

te s
sustainability perspective. In order to enhance sustainability through prefabrication and

di nu
IBS, paying attention to constructability issues regarding these methods appears to be

crucial.
ye a
Lack of knowledge and understanding of the benefits of IBS is a major prohibiting factor
op M
in the application of IBS in Malaysian construction. This lack of knowledge may lead to
C ted

all sorts of problems form technical difficulties in the construction process to lack of

awareness of the potential benefits of IBS. Constructability aims to inject knowledge in to


ot p

the construction procedure making the construction endeavor more feasible, perhaps
N ce

constructability inputs can effectively reduce some of the aforementioned problems of

IBS construction in Malaysia. Including constructability concepts are likely to reduce


Ac

failed IBS projects resulting in improved outcomes and more publicity for IBS

construction. Developers are not utilizing IBS due to the presence of cheap foreign work

force this dependency on foreign labor is not sustainable and not in line with the future

development of Malaysia (IBS digest, 2005). Employing constructability concepts, and

subsequently better IBS practices may boost the awareness of potential IBS practitioners

especially developers, contractors and engineers. They may realize that the utilization of

Copyright 2013 by the American Society of Civil Engineers

Journal of Legal Affairs and Dispute Resolution in Engineering and Construction


Journal of Legal Affairs and Dispute Resolution in Engineering and Construction. Submitted September 24, 2012; accepted March 29, 2013;
posted ahead of print May 4, 2013. doi:10.1061/(ASCE)LA.1943-4170.0000121

cheap foreign labor will not always result in more efficient and sustainable outcomes.

Figure 1 shows the potential of constructability in success of IBS construction and

ultimately sustainability.

On the other hand constructability can provide a pre-emptive conflict management


Downloaded from ascelibrary.org by Istanbul Universitesi on 08/20/13. Copyright ASCE. For personal use only; all rights reserved.

approach for all sorts of construction projects. Some of the common causes of conflicts

t
ip
and disputes in construction projects are lack of transparency in the design process,

d cr
insufficient design information or in some cases misleading information in the design

te s
documents. Constructability is about appropriate knowledge flow and communication at

di nu
the right time, in fact Reuss and Tatum (1993) believed that constructability knowledge

provides technical, operational, contractual, or administrative guidance for subsequent


ye a
projects, this could contribute to the proactive approach of conflict and dispute
op M
management. Reactive approaches normally take place after full manifestation of conflict
C ted

or occurrence of a dispute incident requiring great deal of time and resources for placing

a resolution, whereas the proactive approach which may be enhanced by constructability

is always about sharing information collaboration and exchange of knowledge leading to


ot p
N ce

ongoing and non-stop management of conflicts. Ultimately incorporating a proactive

method of conflict management and processing through any technique, method or


Ac

concept will set the scene for sustainable procurement of IBS construction projects.

Please insert Figure 1

One of the other important issues is each partys responsibility for implementing the

constructability concept file. Who is responsible for the applying and optimizing each

concept? Which partys should be involved in constructability issues of each phase?

What sort of teams and who should be the team members for implementing

Copyright 2013 by the American Society of Civil Engineers

Journal of Legal Affairs and Dispute Resolution in Engineering and Construction


Journal of Legal Affairs and Dispute Resolution in Engineering and Construction. Submitted September 24, 2012; accepted March 29, 2013;
posted ahead of print May 4, 2013. doi:10.1061/(ASCE)LA.1943-4170.0000121

constructability concepts? are some of the questions that need to be answered. On the

other hand Paulson (1976) believes that contractual arrangements should be drawn to

assure that current construction and operations knowledge are injected in the design

process. Generally for better implementation of constructability concept file within IBS

construction there is a need for contract management and team building. Contract
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/20/13. Copyright ASCE. For personal use only; all rights reserved.

t
ip
management as illustrated in Figure 1 can make the incorporation of constructability

d cr
inputs to IBS easier leading to sustainable procurement of IBS projects, and a successful

IBS culture in favor of promoting sustainability. In other words more constructability and

te s
di nu
constructible IBS means a more sustainable built environment, thus there is a need to

investigate the application of constructability concepts in Malaysian Industrialized


ye a
Building Systems in seek of sustainability in construction.
op M
Current research
C ted

Research performed in Malaysia illustrates that the Malaysian industry has yet to realize

the full benefits of constructability implementation due to lack of classified knowledge


ot p

and constructability information regarding construction methods, elements and building


N ce

systems. A survey conducted in Malaysia shows there is a feeling between Malaysian

engineers that constructability is beneficial but they do not really generalize the concepts
Ac

under the umbrella of constructability (Nima, 2001). On the other hand constructability

implementation as discussed could be beneficial for better IBS delivery and sustainable

construction culture in Malaysia. Therefore the importance constructability research is

clear nevertheless practical and effective constructability implementation is largely

dependent on collaboration of parties at the right time. This highlights the importance of

contracting approach and perhaps contract management strategies in achieving the best

Copyright 2013 by the American Society of Civil Engineers

Journal of Legal Affairs and Dispute Resolution in Engineering and Construction


Journal of Legal Affairs and Dispute Resolution in Engineering and Construction. Submitted September 24, 2012; accepted March 29, 2013;
posted ahead of print May 4, 2013. doi:10.1061/(ASCE)LA.1943-4170.0000121

constructability inputs. Consequently assessing roles, responsibilities and contribution of

different parties to constructability application and also their timing as part of contracting

strategies and management program can be vital for the success of IBS construction and

sustainability initiative of the construction industry.


Downloaded from ascelibrary.org by Istanbul Universitesi on 08/20/13. Copyright ASCE. For personal use only; all rights reserved.

In this research the current application of constructability concepts and features are

t
ip
assessed. Basically the research intends to investigate the application status of the IBS

d cr
practitioner in comparison to each other and perhaps indicate which parties are more

te s
involved in constructability implementation during different construction phases.

di nu
Moreover the constructability application in different construction phases will also be

investigated in order to assess constructability inputs for each phase of IBS projects. The
ye a
primary goal of this research is to assess the status quo of constructability implementation
op M
in IBS projects. The findings of this research optimistically could be a step towards
C ted

identifying the current IBS construction problems and possibly impracticalities regarding

current constructability implementation may be identified, then contract management

strategies may be applied to cover the weaknesses and strive towards prosperous IBS
ot p
N ce

construction and ultimately sustainability in Malaysian construction. In this research the

constructability concepts file developed by Nima et al (2001) for Malaysia is used. The
Ac

concepts file comprises of 23 concepts for three main phases of construction (Appendix).

Methodology

A questionnaire was developed and sent based on the constructability concept file

developed by Nima (2001). The questionnaire consists of two sections; section A is

concerned with demographic information and requests the general respondent

Copyright 2013 by the American Society of Civil Engineers

Journal of Legal Affairs and Dispute Resolution in Engineering and Construction


Journal of Legal Affairs and Dispute Resolution in Engineering and Construction. Submitted September 24, 2012; accepted March 29, 2013;
posted ahead of print May 4, 2013. doi:10.1061/(ASCE)LA.1943-4170.0000121

information. A question is included in this section to assess the awareness of respondents

on the issue of constructability and its definition. In section B a question is asked about

the application of the 23 constructability concepts for Malaysia, the question aims to

understand if IBS industry participants in Malaysia are actually applying these concepts

or not. All respondents were chosen from the Malaysian IBS practitioners. The best
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/20/13. Copyright ASCE. For personal use only; all rights reserved.

t
ip
source of gathering the data and information is the Construction Industry Development

d cr
Board (CIDB) of Malaysia, in fact the CIDB has an IBS center which evaluates and

classified IBS industry practitioners and companies. The bulk of data needed for this

te s
di nu
research has been acquired through CIDBs IBS center, comprising of companies which

have achieved approval through IBSC Certification via this organization.


ye a
Three main respondent groups involved in the Malaysian IBS projects (designers,
op M
contractors and also manufactures or suppliers) were chosen via stratified sampling
C ted

technique. After the identification of the strata, the weight and importance of each

stratum in the population is determined. The sample size (n) is then divided based on the

weight of each stratum, and the members are selected randomly from each stratum to
ot p
N ce

form a consistent and representative sample (Fellows & Liu, 1997). In this research the

sample size is calculated using the formula developed by Cochran (Cochran, 1963):
Ac

( )
Formula 1 =

This formula is valid if is the sample size, is the abscissa of the normal curve that

cuts off an area at the tails (1 - equals the desired confidence level, e.g., 95%), is the

desired level of precision, is the estimated proportion of an attribute that is present in

the population, and is 1- . The value used for p is a conservative value of 0.5 since we

Copyright 2013 by the American Society of Civil Engineers

Journal of Legal Affairs and Dispute Resolution in Engineering and Construction


Journal of Legal Affairs and Dispute Resolution in Engineering and Construction. Submitted September 24, 2012; accepted March 29, 2013;
posted ahead of print May 4, 2013. doi:10.1061/(ASCE)LA.1943-4170.0000121

had no previous information on the sample characteristics, this will give the maximum

sample size. 95% was chosen for the confidence level which was equivalent to a value

of 1.96, and based on similar research performed in the past an of 10% was used to

calculate the sample size. The sample size calculated for the research was 96 but due to

the low response the sample size also is often increased by 30% to compensate for this
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/20/13. Copyright ASCE. For personal use only; all rights reserved.

t
ip
lack of response and based on this number the questionnaires are sent out.

d cr
Results

te s
A number of 73 questionnaires out of a total of 81 returned questionnaires were

di nu
ultimately acceptable for the study. Some of the questionnaires were excluded due to
ye a
non-completion or inappropriate answering because the respondents were not senior
op M
members or well informed and well qualified engineers and some inconsistencies were

noticed in their responses. A low response rate of 27% was obtained from the
C ted

respondents over a period of three month, low response rate are common for mailed

questionnaires. In fact Fellows & Liu (1997) for postal questionnaires a usable response
ot p

rate of 25%-35% is the expected. Vast majority of the respondents work in the private
N ce

sector, around 21.9% of the them were characterized as designers, a majority of 61.6%

were contractors and only 16.5% were manufacturers or suppliers, this was expected
Ac

because the questionnaires were sent based on the population of each group involved in

IBS sector through stratified sampling. Most of the respondents were involved in

traditional design-bid-built and also the design-build contracts, revealing that the

Malaysian construction industry is rather traditional in terms of contract management. A

good diversity of construction project involvement was exhibited in the respondents

Copyright 2013 by the American Society of Civil Engineers

Journal of Legal Affairs and Dispute Resolution in Engineering and Construction


Journal of Legal Affairs and Dispute Resolution in Engineering and Construction. Submitted September 24, 2012; accepted March 29, 2013;
posted ahead of print May 4, 2013. doi:10.1061/(ASCE)LA.1943-4170.0000121

denoting that respondents possess a mixture of experiences and knowledge on different

types of construction projects which is important for the goal of this research.

Most of the respondents had over 10 years experience in the industry, 38.3% had more

than 20 years experience, around 28.8% had between 15 to 20 years of experience and
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/20/13. Copyright ASCE. For personal use only; all rights reserved.

19.2% of the respondents stated they had 10 to 15 years experience in construction. A

t
ip
total of 11% of the respondents had 5 to 10 years experience and finally only 2.7% had

d cr
less than 5 years experience. Nevertheless the respondents experience in IBS is

te s
significantly lower, this lack of experience is due to the fact that it is only 10 years that

di nu
the government has decided to promote IBS seriously. Around 82.2% of the respondents

had not heard the definition of constructability before and only a minority of 17.8% had
ye a
actually heard the definition before, this is not a surprise due to low constructability
op M
research and education performed in the Malaysia. Previous studies in America Uhlik and
C ted

Lores (1998) showed that 65% of the respondents had heard the term constructability

before which shows that the American construction industry seems to be very well

informed on the issue.


ot p
N ce

Comparison of constructability application between the construction phases


Ac

Initially the general application score (AS) for each constructability concept is obtained

from all respondents which are based on how many of the respondents applied each

concept. Since all of the 73 respondents were included in the calculation, AS is within the

range of 0 to 73 for each concept and tabulated in Table 1. Twelve of the respondents

were manufacturers or suppliers; the AS for these respondents is within the range of 0

to12 and included in Table 2. A total of 16 designers took part in the research, which

implies the AS of each concept varies from 0 to 16 demonstrated in Table 3.The AS for

Copyright 2013 by the American Society of Civil Engineers

Journal of Legal Affairs and Dispute Resolution in Engineering and Construction


Journal of Legal Affairs and Dispute Resolution in Engineering and Construction. Submitted September 24, 2012; accepted March 29, 2013;
posted ahead of print May 4, 2013. doi:10.1061/(ASCE)LA.1943-4170.0000121

the contractors are calculated and tabulated in Table 4 out of a total of 45. All the tables

are drawn based on the three main construction phases (Conceptual planning phase,

Design and procurement phase, and Field operation phase) in line with the research

objective.

Please insert Table1


Downloaded from ascelibrary.org by Istanbul Universitesi on 08/20/13. Copyright ASCE. For personal use only; all rights reserved.

t
ip
Please insert Table2

d cr
Please insert Table3

Please insert Table4

te s
di nu
In order to find out in which of the construction phases, the application of constructability

is significantly higher than others first ANOVA statistics is used to establish if there is
ye a
any significant difference in the application scores (AS) of the three phases. The ANOVA
op M
test is conducted with SPSS software; used for this test is 0.05. If significant is

smaller than =0.05 then it could be concluded that the groups of data are significantly
C ted

different. To determine which of the construction phases have the significant differences

and also to verify the order of constructability application for the different phases the Post
ot p

Hoc comparison based on Tukeys theory is performed by SPSS. The analysis is first
N ce

conducted for the general constructability application scores of all respondents taken part
Ac

in the research illustrated in Table 1 regardless of their construction activities. Then

separate respondent groups of suppliers, designers and contractors are analyzed (Tables

2, 3 and 4).

The significant obtained from ANOVA test performed among all respondents (Table 1)

equals to 0.042 which is smaller than the =0.05 this indicates that there is significant

difference between the phases in terms of constructability application. The Post Hoc test

Copyright 2013 by the American Society of Civil Engineers

Journal of Legal Affairs and Dispute Resolution in Engineering and Construction


Journal of Legal Affairs and Dispute Resolution in Engineering and Construction. Submitted September 24, 2012; accepted March 29, 2013;
posted ahead of print May 4, 2013. doi:10.1061/(ASCE)LA.1943-4170.0000121

is applied and as a result the mean difference between the conceptual planning phase and

field operation phase is larger than Tukeys HSD denoting that the total application score

of all respondents in the conceptual planning phase is significantly higher than their

application score in the field operation phase. The ANOVA test performed on Table 2

based on suppliers constructability application scores revealed that the significant


Downloaded from ascelibrary.org by Istanbul Universitesi on 08/20/13. Copyright ASCE. For personal use only; all rights reserved.

t
ip
obtained is 0.071 which is larger than =0.05. This demonstrates no significant difference

d cr
between the constructability application score of construction phases corresponding to the

suppliers. The ANOVA test is again performed this time for the responses attained from

te s
di nu
the designers (Table 3). The test shows that the significant is 0.009 which is smaller

than =0.05 suggesting that there is a significant difference between the constructability
ye a
application scores of construction phases for designers. The Post Hoc test reveals that the
op M
application score in the conceptual planning phase is significantly higher than the

application score in the field operation phase for designers. The Post Hoc test also shows
C ted

that the designers application score of constructability concepts in the design and

procurement is significantly larger than the field operation phase. In another words the
ot p

IBS designers have a higher application of constructability during the conceptual


N ce

planning and the design phase compared to the field operation phase. The ANOVA test
Ac

is finally performed for the application scores included in Table 4 corresponding to

contractors responses. However the significant achieved from SPSS is 0.110 which is

larger than =0.05 meaning there is no significant difference in the application of

constructability concepts of different construction phases for the contractors.

Comparison of constructability level of application between contracting parties

Copyright 2013 by the American Society of Civil Engineers

Journal of Legal Affairs and Dispute Resolution in Engineering and Construction


Journal of Legal Affairs and Dispute Resolution in Engineering and Construction. Submitted September 24, 2012; accepted March 29, 2013;
posted ahead of print May 4, 2013. doi:10.1061/(ASCE)LA.1943-4170.0000121

In this section the results are rearranged based on the level of constructability application

for each respondent. This means that each one of the 73 respondents is given a level of

application (LA) for constructability. The level of application is simply the number of

concepts that each respondent applies based on section B of the questionnaire. The LA

for each respondent during all three phases of the project is a number between 0 and 23
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/20/13. Copyright ASCE. For personal use only; all rights reserved.

t
ip
because there are 23 constructability concepts, as demonstrated in Table 5 for all

d cr
respondent groups (suppliers, designers, contractors).

Please insert Table5

te s
di nu
Please insert Table6
ye a Please insert Table7

Please insert Table8


op M
Because every phase of the construction process as previously discussed has its own

constructability concepts the LA results for each respondent in the different phases are
C ted

also classified and tabulated in Tables 8, 9 and 10. Consequently a comparison between

the constructability LA of each participating groups in which in this study are designers,
ot p

contractors and suppliers involved in IBS can be made.


N ce

In the previous section the ANOVA statistics were used to compare the constructability
Ac

application scores (AS) of different construction phases among respondents, where the

independent variables were the three construction phases and the dependent variables was

AS obtained based on the frequency of each concepts application among respondents. In

this section once again ANOVA is employed to find any significant differences between

Level of Application (LA) associated with different construction participants. The

respondent groups (designers, contractors and suppliers) are the independent variables

Copyright 2013 by the American Society of Civil Engineers

Journal of Legal Affairs and Dispute Resolution in Engineering and Construction


Journal of Legal Affairs and Dispute Resolution in Engineering and Construction. Submitted September 24, 2012; accepted March 29, 2013;
posted ahead of print May 4, 2013. doi:10.1061/(ASCE)LA.1943-4170.0000121

and also the LA obtained for each respondent will be the dependent variable. This

analysis is carried out for the full construction process (including all phases) followed by

a phases by phase analysis as illustrated in tables 5 to 8. The conceptual planning phase

has seven concepts which are the first seven concepts in section B of the questionnaire

answer sheet, therefore the LA calculated for each respondent will range from 0 to 7
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/20/13. Copyright ASCE. For personal use only; all rights reserved.

t
ip
(Table 6). The number of constructability concepts included in the design and

d cr
procurement phase is eight thus the LA for each respondent is ranging from 0 to 8 (Table

7). For the field operation phase 8 concepts are included therefore LA for each

te s
di nu
respondent is within the margin of 0 to 8 (Table 8).

For the whole construction process including all phases (Table 5) ANOVA analysis
ye a
showed a significant of 0.00 which smaller than =0.05, this indicates that there is a
op M
significant difference among the respondent groups LA score, furthermore the Post Hoc
C ted

test signifies that the mean difference between contractors and designers LA score is

significant and is more than Tukeys HSD value at 0.05 level of significance, indicating

that the contractors in general have a significantly higher LA of constructability concepts


ot p
N ce

during all phases of IBS construction compared to designers but no significant difference

was indicated between the contractors and suppliers LA scores. The LA for each
Ac

respondent in the conceptual planning phase is tabulated in the Table 6, ANOVA test for

this set of data shows significant (0.005) is lower than (0.05) indicating a significant

difference in the LA scores between the three groups of contractor, designer, and supplier

in this phase. The Post Hoc reveals that the level of application of the constructability

concepts related to contractors is significantly larger than the designers in the early phase

of conceptual planning. Based on the data in Table 7 the ANOVA test is performed with

Copyright 2013 by the American Society of Civil Engineers

Journal of Legal Affairs and Dispute Resolution in Engineering and Construction


Journal of Legal Affairs and Dispute Resolution in Engineering and Construction. Submitted September 24, 2012; accepted March 29, 2013;
posted ahead of print May 4, 2013. doi:10.1061/(ASCE)LA.1943-4170.0000121

but the significant (0.476) was larger than (0.05), consequently no significant

difference in the level of constructability application between the respondents in the

design and procurement phase is indicated. For Table 8 the significant gained from the

SPSS analysis is 0.00 and is lower than 0.05, suggesting there is a significant difference

between the respondent groups on their LA scores. The Post Hoc test illustrates that
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/20/13. Copyright ASCE. For personal use only; all rights reserved.

t
ip
contractors have the highest mean and their level of application for constructability

d cr
concepts is significantly higher than the suppliers and designers in the field operation

phase. The Post Hoc test also indicates that the suppliers have a significantly higher level

te s
di nu
of application in this phase compared to the designers.

Discussions of the findings


ye a
op M
The results disclose that there are significant differences for constructability application

in different phases of IBS application. There is also significant differences between the
C ted

level of application of different parties involved in IBS projects, these results need to be

classified in a more comprehendible manner. Thus the results were structured in the form
ot p

of two separate matrixes one for constructability application between the construction
N ce

Phases (Figure 2), and the other for constructability level of application between

contracting parties (Figure 3). In these two matrixes the value 1 represents a significantly
Ac

higher relationship, the value of -1 represents a significantly lower relationship and 0 is

for no significant difference. As it can be seen in Figure 2 among all the respondents

involved there is a significant difference between the constructability application of

conceptual planning phase and the field operation phase, this is represented by the value

1 in the first row and the last column of the matrix, this could be illustrated as , = 1.

Copyright 2013 by the American Society of Civil Engineers

Journal of Legal Affairs and Dispute Resolution in Engineering and Construction


Journal of Legal Affairs and Dispute Resolution in Engineering and Construction. Submitted September 24, 2012; accepted March 29, 2013;
posted ahead of print May 4, 2013. doi:10.1061/(ASCE)LA.1943-4170.0000121

Consequently , = 1 means that among designers there is a significant difference

between the constructability application of conceptual planning phase and the field

operation phase. The same applies to Figure 3 and when , = 1 this indicates that the

level of constructability application for designers is significantly lower than the


Downloaded from ascelibrary.org by Istanbul Universitesi on 08/20/13. Copyright ASCE. For personal use only; all rights reserved.

contractors in the conceptual planning phase. The same notion can be used to interpret all

t
ip
the values of the two matrixes.

d cr
Please insert Figure 2

te s
Please insert Figure 3

di nu
Constructability in the conceptual planning phase has larger application than the field

operation phase and although it has a higher mean in comparison with the design and
ye a
op M
procurement phase, there is no significant difference between the phases which are

illustrated by the 0 values in Figure 2. Consequently the construction participants are


C ted

applying early constructability concepts more than the later ones. In general the

contractors application of constructability is higher than designers and suppliers


ot p

especially in the conceptual planning and field operation phases; difference of


N ce

constructability application between contractors and the designers is significant as

illustrated in Figure 3 by the 1 values associated to contractors in correspondence with


Ac

the designers.

The constructability concepts used for this research developed by Nima (2001) are

included in the appendixes; based on these concepts the suppliers are practicing some of

the early stage constructability concepts from the conceptual planning phase; for instance

supplier like any other party involved in construction projects have their own assignment

of project schedule and completion date to track their work progress and also to keep in

Copyright 2013 by the American Society of Civil Engineers

Journal of Legal Affairs and Dispute Resolution in Engineering and Construction


Journal of Legal Affairs and Dispute Resolution in Engineering and Construction. Submitted September 24, 2012; accepted March 29, 2013;
posted ahead of print May 4, 2013. doi:10.1061/(ASCE)LA.1943-4170.0000121

the project timeframe which is C5 in the constructability concept file however this does

not necessarily indicate that they are involved in the scheduling of the whole project in

fact there involvement is often very limited. The suppliers also study the site layout C7 in

the constructability concept file because they often are in charge of the delivery of the

IBS components. The contracting process normally is a prohibiting factor for best
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/20/13. Copyright ASCE. For personal use only; all rights reserved.

t
ip
practice constructability.

d cr
The contractors have the most influence in the construction process and are implementing

te s
most of the constructability concepts regardless of their source phase in the construction

di nu
and field operation process. For instance concepts such as C2, C3, C5, C6, and C7 which

entail issues such as comprehensive team building, involvement of experienced


ye a
knowledgeable personnel, project scheduling, in-depth analysis of major construction
op M
methods and studying site layout for incorporating efficient construction, operation and
C ted

maintenance. These concepts are being applied after site possession and commencement

of project construction phase in which contractors are more or less involved.


ot p

The analysis demonstrates that designers involvement in the constructability of the field
N ce

operation phase is significantly low and they are mainly applying the concepts of the
Ac

conceptual planning phase and also the design and procurement phase because they are in

charge of the early project development and design but have less authority in the field

operation phase. The designers are very much involved in the standardization, technical

specifications and simplification concepts of constructability because IBS construction is

mostly concerned with these issues, and the designer carries out the design change or

alterations concepts demarked by C10, C11, and C12. The designers are also applying

C3, C5, C6 in the conceptual planning phase which are being separately applied by the

Copyright 2013 by the American Society of Civil Engineers

Journal of Legal Affairs and Dispute Resolution in Engineering and Construction


Journal of Legal Affairs and Dispute Resolution in Engineering and Construction. Submitted September 24, 2012; accepted March 29, 2013;
posted ahead of print May 4, 2013. doi:10.1061/(ASCE)LA.1943-4170.0000121

contractors, instead of this separation collaboration needs to be incorporated for applying

these concepts.

Conclusions and recommendations

The IBS contractors in Malaysia are considered to have more experience in the IBS
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/20/13. Copyright ASCE. For personal use only; all rights reserved.

t
ip
industry than other parties involved. This experience is needed in the early project

planning and because the mass usage of IBS components is a relatively new in Malaysia

d cr
the designers and project owners do not possess much information on the subject. Despite

te s
the fact that constructability teams and meetings are not often conducted in the Malaysian

di nu
construction industry the owners and the designers of IBS are forced to invite some of the
ye a
contractors and experienced personnel in the IBS industry for evaluation and assessment
op M
meetings, as a result the IBS contractor is involved in early project development concepts

of constructability or constructability meetings. However one of the major prohibiting


C ted

factors of successful constructability application in IBS is the dated and traditional

contracting mindset. Changes in contracting procedures and legal settings of contracts is


ot p

needed and if this is not possible in the near future, contract management techniques have
N ce

to be operated to allow better collaboration and more involvement of different parties in


Ac

the project lifecycle. For instance in traditional procurement and contracting procedures

the contractors involvements in projects are often after the planning and design phase

and after the construction process begins the bond between the contracting party and the

designing party is very weak, in addition there is no legal or binding clause for

teambuilding or collaboration. Future research on the matter can focus on developing

contract management strategies or even changing the legal mindset of contracts in

Copyright 2013 by the American Society of Civil Engineers

Journal of Legal Affairs and Dispute Resolution in Engineering and Construction


Journal of Legal Affairs and Dispute Resolution in Engineering and Construction. Submitted September 24, 2012; accepted March 29, 2013;
posted ahead of print May 4, 2013. doi:10.1061/(ASCE)LA.1943-4170.0000121

Malaysia for effective and in time knowledge and experience contributions of contracting

parties.

If there is regular constructability enhancement meetings among all parties and the

content of the constructability concept file is discussed it is anticipated that a lot of


Downloaded from ascelibrary.org by Istanbul Universitesi on 08/20/13. Copyright ASCE. For personal use only; all rights reserved.

t
unnecessary concerns and conflict causes are resolved before manifestation of conflict

ip
and dispute. Constructability needs to be defined and classified for the parties involved in

d cr
the construction process; and its value as a conflict management strategy should be

te s
highlighted. The constructability concept file could be regarded as a manifest for

di nu
collaboration, knowledge flow and information sharing; insuring all parties are in the

loop and clarity of work is achieved. This clarity and constant cooperation will
ye a
effectively reduce consequences of conflicts and moves towards sustainable procurement.
op M

Generally for achieving successful IBS construction as part of the overall industry goal of
C ted

sustainability improvement, some restructuring in the contracting procedure plus better

and more effective and efficient application of constructability concepts is needed. The
ot p

findings of this research indicate that constructability awareness and to some extent
N ce

application is low amongst IBS project participants. Nevertheless interestingly enough

although there is not much classified information of constructability within the Malaysian
Ac

IBS industry, significant number of IBS practitioners are applying the concepts

discretely. The problem with this kind of application is that because they are not

classically trained there is lack of collaboration and a great deal of mistiming involved in

the application of constructability. The current status of constructability in Malaysian IBS

shows separate and unlinked application of constructability concepts in each partys

relevant phase of involvement without team building endeavors. In order to move

Copyright 2013 by the American Society of Civil Engineers

Journal of Legal Affairs and Dispute Resolution in Engineering and Construction


Journal of Legal Affairs and Dispute Resolution in Engineering and Construction. Submitted September 24, 2012; accepted March 29, 2013;
posted ahead of print May 4, 2013. doi:10.1061/(ASCE)LA.1943-4170.0000121

forward in line with the sustainability goal and achieve more practical, constructible, and

successful IBS projects constructability training and teambuilding with appropriate

contract management strategies should be acknowledged by the Malaysian construction

industry as critical components for best constructability application. Future investigations

on barriers of constructability application in all phases especially in the design and


Downloaded from ascelibrary.org by Istanbul Universitesi on 08/20/13. Copyright ASCE. For personal use only; all rights reserved.

t
ip
conceptual planning phase which shows most lack of constructability implementation is

d cr
needed. Also enhancement of information flow plus understandable and simple

classification of information can enhance constructability application and more

te s
di nu
sustainable outcomes.
ye a
Reference
op M
Abd.Rahman, A. B., & Omar, W. (2006). Issues and challenges in the implementation of

Industrialized Building Systems in Malaysia. Paper presented at the The 6th Asia-
C ted

Pacific Structural Engineering and Construction Conference (APSEC 2006).

Adams, S. (1989). Practical Buildability. London Boston Durban Singapore Sydney


ot p

Toranto Wellington: Construction Industry Research Information Association,


N ce

Butterworths.
Ac

Blismas, N. G., Pendlebury, M., Gibb, A., & Pasquire, C. (2005). Constraints to the Use

of Off-site Production on Construction Projects. Architectural Engineering and

Design Management, 1(3), 153-162.

Cochran, W. G. (1963). Sampling techniques (second ed.). New York: John Wiley and

Sons, Inc.

Copyright 2013 by the American Society of Civil Engineers

Journal of Legal Affairs and Dispute Resolution in Engineering and Construction


Journal of Legal Affairs and Dispute Resolution in Engineering and Construction. Submitted September 24, 2012; accepted March 29, 2013;
posted ahead of print May 4, 2013. doi:10.1061/(ASCE)LA.1943-4170.0000121

Construction Industry Development Board. (2006). Construction Industry Master Plan

2006-2015 (CIMP 2006-2015). Kuala Lumpur, Malaysia: CIDB.

Construction Industry Development Board. (2008). Malaysian Construction Outlook

2008 Presentation by Business Development Division, CIDB.

Construction Industry Development Board Malaysia. (2001). Manual for Assessment of


Downloaded from ascelibrary.org by Istanbul Universitesi on 08/20/13. Copyright ASCE. For personal use only; all rights reserved.

t
ip
Industrialized Building Systems. Kuala Lumpur: CIDB.

d cr
Construction Industry Institute. (1986). Constructability A Primer. Publication 3-1.

Austin, Texas: CII.

te s
di nu
Construction Industry Institute. (1987). Constructability Concepts File. Publication 3-3.
ye a Austin, Texas: CII.

Fellows, R. F., & Liu, A. M. M. (1997). Research Methods for Construction: Blackwell
op M
Science Ltd, UK.

Fischer, & Tatum. (1997). Characteristics of Design-Relevant Constructability


C ted

Knowledge. Journal of Construction Engineering and Management, 123(3), 253-

260.
ot p

Griffith, A., Sidwell, A. C., & Sidwell, T. (1995). Constructability in Building and
N ce

Engineering Projects. London: Macmillan.


Ac

Hamid, Z. A., Kamar, K. A. M., Zain, M., Ghani, K., & Rahim, A. h. A. (2008).

Industrialised Building System (IBS) in Malaysia: The Current State and R&D

Initiatives. Malaysian Construction Research Journal (MCRJ), 1(2), 1-11.

Hui, S. C. M., & Or, G. K. C. (2005). Study of Prefabricated Building Services

Components for Residential Buildings in Hong Kong. Paper presented at the

Hubei-Hong Kong Joint Symposium.

Copyright 2013 by the American Society of Civil Engineers

Journal of Legal Affairs and Dispute Resolution in Engineering and Construction


Journal of Legal Affairs and Dispute Resolution in Engineering and Construction. Submitted September 24, 2012; accepted March 29, 2013;
posted ahead of print May 4, 2013. doi:10.1061/(ASCE)LA.1943-4170.0000121

Jaillon, L., Poon, C. S., & Chiang, Y. H. (2009). Quantifying the waste reduction

potential of using prefabrication in building construction in Hong Kong. Waste

Management, 29(1), 309-320.

Kibert, C. J. (1994). Principles of sustainable construction. Paper presented at the The 1st

International Conference on Sustainable Construction.


Downloaded from ascelibrary.org by Istanbul Universitesi on 08/20/13. Copyright ASCE. For personal use only; all rights reserved.

t
ip
Nelms, C. E., Russell, A. D., & Lence, B. J. (2007). Assessing the performance of

d cr
sustainable technologies: a framework and its application. Building Research &

Information, 35(3), 237-251.

te s
di nu
Nima, M. A. (2001). Constructability factors in the Malaysian construction industry.
ye a University Putra Malaysia, Selangor, Malaysia.

Nima, M. A., Abdul-Kadir, M. R., & Jaafar, M. S. (1999). Evaluation of the engineers
op M
personnels role in enhancing the project constructability. Facilities, 17(11), 423-

430.
C ted

O'Connor, J., & Davis, V. (1988). Constructability Improvement During Field

Operations. Journal of Construction Engineering and Management, 114(4), 548-


ot p

564.
N ce

O'Connor, J., Larimore, M., & Tucker, R. (1986). Collecting Constructability


Ac

Improvement Ideas. Journal of Construction Engineering and Management,

112(4), 463-475.

Ogden, R. (2005). Offsite (IBS) in the UK Developers Perspective. Paper presented at the

CIDB-UKTI Industrialized Building Systems (IBS) Seminar.

Copyright 2013 by the American Society of Civil Engineers

Journal of Legal Affairs and Dispute Resolution in Engineering and Construction


Journal of Legal Affairs and Dispute Resolution in Engineering and Construction. Submitted September 24, 2012; accepted March 29, 2013;
posted ahead of print May 4, 2013. doi:10.1061/(ASCE)LA.1943-4170.0000121

Pasquire, C. L., & Gibb, A. G. F. (2002). Considerations for assessing the benefits of

standardisation and preassembly in construction. Journal of Financial

Management of Property and Construction, 7(3), 151-161.

Paulson Jr, B. C. (1976). Designing to reduce construction costs. Journal of Construction

Division, 102(4), 587592.


Downloaded from ascelibrary.org by Istanbul Universitesi on 08/20/13. Copyright ASCE. For personal use only; all rights reserved.

t
ip
Pulaski, M., & Horman, M. (2005). Continuous Value Enhancement Process. Journal of

d cr
Construction Engineering and Management, 131(12), 1274-1282.

Retik, A., & Warszawski, A. (1994). Automated design of prefabricated building.

te s
di nu
Building and Environment, 29(4), 421-436.

Reuss, M. C., & Tatum, C. B. (1993). Requirements and tools for transferring
ye a
construction experience between projects: Stanford University. Center for
op M
Integrated Facility, Engineering.

Shaari, S. N. (2003). IBS Survey 2003. Kuala Lumpur: Construction Industry


C ted

Development Board Malaysia.

Tatum, C. B., Vanegas, J. A., & Williams, J. M. (1986). Constructability improvement


ot p

during conceptual planning. Texas: Construction Industry Institute, University of


N ce

Texas at Austin.
Ac

Uhlik, & Lores. (1998). Assessment of Constructability Practices among General

Contractors. Journal of Architectural Engineering, 4(3), 113-123.

UNFPA. (2001). Chapter 3. The State of World Population 2001. Retrieved 20th of

August 2012, from http://www.unfpa.org/swp/2001/english/ch03.html#3

Warszawski, A. (1999). Industrialized and Automated Building Systems: A Managerial

Approach: Taylor & Francis.

Copyright 2013 by the American Society of Civil Engineers

Journal of Legal Affairs and Dispute Resolution in Engineering and Construction


Journal of Legal Affairs and Dispute Resolution in Engineering and Construction. Submitted September 24, 2012; accepted March 29, 2013;
posted ahead of print May 4, 2013. doi:10.1061/(ASCE)LA.1943-4170.0000121

APPENDIX; An example of the mailed questionnaire is included:

Section A: general respondent information:


Just check () the suitable option.

1. In which sector dose your organization work?


private Public
2. What best describes your construction activities
Designer Manufacturer or supplier
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/20/13. Copyright ASCE. For personal use only; all rights reserved.

contractor Others please verify

t
3.Under what types of contracts do you usually work with:

ip
Traditional design-bid-build Design-build
Construction management Others please verify

d cr
4. In what type of projects your organization is mainly involved?
General building (commercial and industrial) Industrial
Civil (highway and heavy works)

te s
Others please verify

di nu
5. Years of experience in the construction industry:
0 5 years 10 15 years
5 10 years 15 20 years
More than 20 years
ye a
6. Years of experience in the Industrial Building Systems (IBS) industry:
0 5 years 10 15 years
op M
5 10 years 15 20 years
More than 20 years
C ted

Section B: application of constructability concepts


Question: Does your organization use the concept in their construction practice? (Please check () Yes or
NO)

C1, Documented constructability program should be prepared for all the project phases by
ot p

participation of all project team members. Yes No


C2, A team of representatives from owner, engineer and contractor should consider projects
N ce

constructability issues. Yes No


C3, experienced & knowledgeable construction personnel should be involved in the early project
planning phase. Yes No
Ac

C4, The construction methods should be considered in determining the type and number of contracts
required
Yes No
C5, Project schedule and completion date should be assigned early and must be construction
sensitive.
Yes No
C6, Major construction methods should be discussed and analyzed in-depth as early as possible.
Yes No
C7, Site layout should be studied carefully to ensure efficient construction, operation, and
maintenance.
Yes No
C8, The construction schedule must be discussed and developed prior to the design development and
procurement schedule. Yes No

Copyright 2013 by the American Society of Civil Engineers

Journal of Legal Affairs and Dispute Resolution in Engineering and Construction


Journal of Legal Affairs and Dispute Resolution in Engineering and Construction. Submitted September 24, 2012; accepted March 29, 2013;
posted ahead of print May 4, 2013. doi:10.1061/(ASCE)LA.1943-4170.0000121

C9, Usage of information technology could overcome the problem of fragmentation between
specializations involved in construction. Yes No
C10, Design simplification by designers and design reviews by construction personnel, must be
configured.
Yes No
C11, Project elements should be standardized to an extent that will never effect the project cost
negatively.
Yes No
C12, The project technical specifications has to be simplified without sacrificing the level of
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/20/13. Copyright ASCE. For personal use only; all rights reserved.

t
efficiency.

ip
Yes No
C13, Modularization and preassembly design should be prepared to assist fabrication, transport and
installation.

d cr
Yes No
C14, Design should consider the construction personnel, materials, and equipments accessibility to

te s
site locations. Yes No
C15, Design should facilitate construction during adverse weather conditions. (The use of

di nu
prefabricated elements)
Yes No
C16, Field task should be organized to minimize damage, reworking or congestion of construction
personnel, material, and equipment. Yes No
ye a
C17, Innovations in using available temporary construction materials/systems which are not limited
op M
by the design and technical specifications. Yes No
C18: Incorporating innovation of new methods in using off-the-shelf hand tools, modification of
available tools, or introduction of new hand tools that reduce labor intensity or increase mobility,
safety, or accessibility.
C ted

Yes No
C19, Introduction of innovative methods in using the available equipment or modification of the
available equipment to increase their productivity. Yes No
C20, Using optional preassembly will lead to increase in productivity, reduction of scaffolding, and
ot p

improved constructability under adverse weather. Yes No


C21, Innovation of temporary facilities will help enhance constructability. Yes No
N ce

C22, The work of contractors should be documented based on quality and time so future projects are
awarded based on these attributes and not just low bids. Yes No
C23, Evaluation, documentation, and feedback regarding constructability concepts during project
phases should be maintained as lessons learnt for future projects. Yes No
Ac

Copyright 2013 by the American Society of Civil Engineers

Journal of Legal Affairs and Dispute Resolution in Engineering and Construction


)LJXUH&DSWLRQ/LVW

Journal of Legal Affairs and Dispute Resolution in Engineering and Construction. Submitted September 24, 2012; accepted March 29, 2013;
posted ahead of print May 4, 2013. doi:10.1061/(ASCE)LA.1943-4170.0000121

List of Figures

1. Figure 1: potential of constructability in achieving sustainability

2. Figure 2: constructability application between the construction Phases

3. Figure 3: constructability level of application between IBS practitioners


Downloaded from ascelibrary.org by Istanbul Universitesi on 08/20/13. Copyright ASCE. For personal use only; all rights reserved.

t
ip
d cr
te s
di nu
ye a
op M
C ted
ot p
N ce
Ac

Copyright 2013 by the American Society of Civil Engineers

Journal of Legal Affairs and Dispute Resolution in Engineering and Construction


ILJXUHSGI

Journal of Legal Affairs and Dispute Resolution in Engineering and Construction. Submitted September 24, 2012; accepted March 29, 2013;
posted ahead of print May 4, 2013. doi:10.1061/(ASCE)LA.1943-4170.0000121

Constructabil ity Contract


input management
Successful
IBS culture
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/20/13. Copyright ASCE. For personal use only; all rights reserved.

Increassed awarenesss & Proactive connflict


utilization of IBSS manageme ent
Sustainnable deliveryy of Susttainable procurement
constrruction projeccts of IBS proje
ects
Mooving towardss sustainabilitty in constructtion

Accepted Manuscript
Not Copyedited

Copyright 2013 by the American Society of Civil Engineers

Journal of Legal Affairs and Dispute Resolution in Engineering and Construction


ILJXUHSGI

Journal of Legal Affairs and Dispute Resolution in Engineering and Construction. Submitted September 24, 2012; accepted March 29, 2013;
posted ahead of print May 4, 2013. doi:10.1061/(ASCE)LA.1943-4170.0000121

Conceptual Design and Field


planning procurement operation
phase phase phase
Conceptual All 0 1
planning respondents
phase Suppliers 0 0
Designers 0 1
Contractors 0 0
Design and All 0 0
procurement respondents
phase Suppliers 0 0
Designers 0 1
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/20/13. Copyright ASCE. For personal use only; all rights reserved.

Contractors 0 0
Field All -1 0
operation respondents
phase Suppliers 0 0
Designers -1 -1
Contractors 0 0

Accepted Manuscript
Not Copyedited

Copyright 2013 by the American Society of Civil Engineers

Journal of Legal Affairs and Dispute Resolution in Engineering and Construction


ILJXUHSGI

Journal of Legal Affairs and Dispute Resolution in Engineering and Construction. Submitted September 24, 2012; accepted March 29, 2013;
posted ahead of print May 4, 2013. doi:10.1061/(ASCE)LA.1943-4170.0000121

Contractors Designers Suppliers


All phases 1 0

Contractors
Conceptual planning 1 0
phase
Design and 0 0
procurement phase
Field operation phase 1 1
All phases -1 0
Conceptual planning -1 0
Designers phase
Design and 0 0
procurement phase
Field operation phase -1 -1
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/20/13. Copyright ASCE. For personal use only; all rights reserved.

All phases 0 0
Conceptual planning 0 0
Suppliers

phase
Design and 0 0
procurement phase
Field operation phase -1 1

Accepted Manuscript
Not Copyedited

Copyright 2013 by the American Society of Civil Engineers

Journal of Legal Affairs and Dispute Resolution in Engineering and Construction


7DEOHV 0RVWDID%DEDHLDQ-HORGDU GRF[

Journal of Legal Affairs and Dispute Resolution in Engineering and Construction. Submitted September 24, 2012; accepted March 29, 2013;
posted ahead of print May 4, 2013. doi:10.1061/(ASCE)LA.1943-4170.0000121

Table 1 All respondents constructability application scores (AS) according to different phases

Conceptual Design and Field


planning procurement operation
phase phase phase
Concept AS Concept AS Concept AS
C1 48 C8 40 C16 46
C2 58 C9 34 C17 33
C3 65 C10 50 C18 41
C4 41 C11 52 C19 42
C5 71 C12 61 C20 50
C6 63 C13 59 C21 28
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/20/13. Copyright ASCE. For personal use only; all rights reserved.

C7 64 C14 54 C22 48
C15 28 C23 61

Accepted Manuscript
Not Copyedited

Copyright 2013 by the American Society of Civil Engineers

Journal of Legal Affairs and Dispute Resolution in Engineering and Construction


Journal of Legal Affairs and Dispute Resolution in Engineering and Construction. Submitted September 24, 2012; accepted March 29, 2013;
posted ahead of print May 4, 2013. doi:10.1061/(ASCE)LA.1943-4170.0000121

Table 2 Suppliers constructability application scores (AS) according to construction phases

Conceptual Design and Field


planning procurement operation
phase phase phase
Concept AS Concept AS Concept AS
C1 10 C8 10 C16 7
C2 6 C9 9 C17 4
C3 10 C10 5 C18 10
C4 7 C11 3 C19 6
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/20/13. Copyright ASCE. For personal use only; all rights reserved.

C5 12 C12 7 C20 6
C6 10 C13 11 C21 2
C7 12 C14 9 C22 5
C15 6 C23 10

Accepted Manuscript
Not Copyedited

Copyright 2013 by the American Society of Civil Engineers

Journal of Legal Affairs and Dispute Resolution in Engineering and Construction


Journal of Legal Affairs and Dispute Resolution in Engineering and Construction. Submitted September 24, 2012; accepted March 29, 2013;
posted ahead of print May 4, 2013. doi:10.1061/(ASCE)LA.1943-4170.0000121

Table 3 Designers constructability application scores (AS) according to construction phases.


Conceptual Design and Field
planning procurement operation
phase phase phase
Concept AS Concept AS Concept AS
C1 3 C8 4 C16 2
C2 11 C9 7 C17 4
C3 14 C10 14 C18 4
C4 8 C11 14 C19 4
C5 14 C12 16 C20 8
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/20/13. Copyright ASCE. For personal use only; all rights reserved.

C6 15 C13 13 C21 2
C7 13 C14 10 C22 3
C15 2 C23 8

Accepted Manuscript
Not Copyedited

Copyright 2013 by the American Society of Civil Engineers

Journal of Legal Affairs and Dispute Resolution in Engineering and Construction


Journal of Legal Affairs and Dispute Resolution in Engineering and Construction. Submitted September 24, 2012; accepted March 29, 2013;
posted ahead of print May 4, 2013. doi:10.1061/(ASCE)LA.1943-4170.0000121

Table 4 Contractors constructability application scores (AS) according to construction phases.

Conceptual Design and Field


planning procurement operation
phase phase phase
Concept AS Concept AS Concept AS
C1 35 C8 26 C16 37
C2 41 C9 21 C17 25
C3 41 C10 31 C18 27
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/20/13. Copyright ASCE. For personal use only; all rights reserved.

C4 26 C11 35 C19 32
C5 45 C12 38 C20 36
C6 38 C13 35 C21 24
C7 39 C14 35 C22 40
C15 20 C23 43

Accepted Manuscript
Not Copyedited

Copyright 2013 by the American Society of Civil Engineers

Journal of Legal Affairs and Dispute Resolution in Engineering and Construction


Journal of Legal Affairs and Dispute Resolution in Engineering and Construction. Submitted September 24, 2012; accepted March 29, 2013;
posted ahead of print May 4, 2013. doi:10.1061/(ASCE)LA.1943-4170.0000121

Table 5 LA for each constructability concept for all phases

Contractor Designers Supplier


s
11.00 23.00 18.00 22.00 11.00 10.00 18.00
15.00 23.00 22.00 22.00 10.00 16.00 19.00
16.00 23.00 16.00 19.00 12.00 12.00 17.00
17.00 14.00 11.00 11.00 10.00 12.00 22.00
12.00 18.00 21.00 15.00 12.00 12.00
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/20/13. Copyright ASCE. For personal use only; all rights reserved.

17.00 22.00 16.00 16.00 11.00 9.00


16.00 16.00 22.00 17.00 11.00 11.00
23.00 11.00 13.00 12.00 17.00 17.00
16.00 21.00 12.00 17.00 15.00 11.00
13.00 16.00 20.00 16.00 10.00 17.00
17.00 22.00 18.00 23.00 10.00 12.00
16.00 14.00 9.00

Accepted Manuscript
Not Copyedited

Copyright 2013 by the American Society of Civil Engineers

Journal of Legal Affairs and Dispute Resolution in Engineering and Construction


Journal of Legal Affairs and Dispute Resolution in Engineering and Construction. Submitted September 24, 2012; accepted March 29, 2013;
posted ahead of print May 4, 2013. doi:10.1061/(ASCE)LA.1943-4170.0000121

Table 6 . LA for each concept during the conceptual planning phase

Contractor Designers Suppliers


4.00 7.00 6.00 7.00 3.00 4.00 7.00
7.00 7.00 7.00 6.00 3.00 5.00 7.00
5.00 7.00 7.00 7.00 6.00 6.00 6.00
4.00 5.00 4.00 4.00 4.00 5.00 7.00
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/20/13. Copyright ASCE. For personal use only; all rights reserved.

3.00 6.00 7.00 7.00 5.00 5.00


7.00 7.00 6.00 5.00 5.00 4.00
7.00 7.00 7.00 4.00 3.00 4.00
7.00 4.00 5.00 3.00 5.00 7.00
6.00 7.00 5.00 7.00 5.00 4.00
4.00 6.00 5.00 7.00 6.00 7.00
4.00 7.00 7.00 7.00 4.00 5.00
7.00 5.00 4.00

Accepted Manuscript
Not Copyedited

Copyright 2013 by the American Society of Civil Engineers

Journal of Legal Affairs and Dispute Resolution in Engineering and Construction


Journal of Legal Affairs and Dispute Resolution in Engineering and Construction. Submitted September 24, 2012; accepted March 29, 2013;
posted ahead of print May 4, 2013. doi:10.1061/(ASCE)LA.1943-4170.0000121

Table 7. LA for each concept during design and procurement phase

Contractor Designers Suppliers


4.00 8.00 7.00 8.00 5.00 6.00 5.00
3.00 8.00 7.00 8.00 4.00 6.00 6.00
5.00 8.00 6.00 5.00 5.00 4.00 7.00
5.00 3.00 5.00 4.00 6.00 5.00 7.00
4.00 7.00 7.00 3.00 5.00 4.00
4.00 7.00 5.00 5.00 4.00 3.00
3.00 6.00 7.00 5.00 5.00 3.00
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/20/13. Copyright ASCE. For personal use only; all rights reserved.

8.00 5.00 3.00 4.00 6.00 6.00


3.00 7.00 2.00 4.00 5.00 3.00
5.00 5.00 3.00 3.00 4.00 6.00
5.00 7.00 5.00 8.00 5.00 4.00
6.00 5.00 3.00

Accepted Manuscript
Not Copyedited

Copyright 2013 by the American Society of Civil Engineers

Journal of Legal Affairs and Dispute Resolution in Engineering and Construction


Journal of Legal Affairs and Dispute Resolution in Engineering and Construction. Submitted September 24, 2012; accepted March 29, 2013;
posted ahead of print May 4, 2013. doi:10.1061/(ASCE)LA.1943-4170.0000121

Table 8 LA for each concept during the field operation phase


.
Contractor Designers Suppliers
3.00 8.00 5.00 7.00 3.00 0.00 6.00
5.00 8.00 8.00 8.00 0.00 5.00 6.00
6.00 8.00 3.00 7.00 1.00 2.00 4.00
8.00 6.00 2.00 3.00 0.00 2.00 8.00
5.00 5.00 7.00 5.00 2.00 3.00
6.00 8.00 5.00 6.00 2.00 2.00
6.00 3.00 8.00 8.00 3.00 4.00
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/20/13. Copyright ASCE. For personal use only; all rights reserved.

8.00 2.00 5.00 5.00 5.00 4.00


7.00 7.00 5.00 6.00 5.00 4.00
4.00 5.00 4.00 6.00 0.00 4.00
8.00 8.00 6.00 8.00 1.00 3.00
3.00 4.00 2.00

Accepted Manuscript
Not Copyedited

Copyright 2013 by the American Society of Civil Engineers

Journal of Legal Affairs and Dispute Resolution in Engineering and Construction

Das könnte Ihnen auch gefallen