Beruflich Dokumente
Kultur Dokumente
3 Accepted as submitted
Name: Sign:
Date:
Note: This sheet shall be the 1st cover page of all A3 & A4 documents.
This block will also form part of the A3 drawing template.
Revisi Description of Prepared By Verified By Approved Date
on Revision By
05/07/201
01R IFC Aws Mohamed Samer S. Firas A.
5
Page 1 of 5
Document No.:
Rev. No.
Procedure for Weld Identification and Weld Traceability
GENERAL
The scope and purpose of this procedure to define the organization for weld Joint
Identification and traceability management in order to make sure that all the
welding joints were properly traceable and reported as per the approved drawing for
the project.
The following terms and definitions are used in the preparation of any quality
related document:
QCP Quality Control Plan: prepared in accordance with the requirements specified in
contractual documentation. QCP includes all applicable ITP(s) and relevant
inspection and test report forms.
2.0 RESPONSIBILITIES
For project related welding activities the Superintendent/ Piping Engineer together
with the supported by the Quality Control Welding Inspector, shall ensure the
implementation of this procedure using the necessary resources and tools.
Fabrication of pipe spools and supports shall only commence after issue of Approved
for Construction (AFC) drawings. Subsequent revisions of AFC drawings will
supersede all previous drawings and the Contractors procedures shall ensure all
fabrication is carried out in accordance with latest revision of each drawing.
The Contractor shall verify drawing information and confirm all dimensions before
commencing fabrication.
The Contractor shall ensure the piping meets final assembly requirements as
specified on the piping layout drawings.
TRACEABILITY OBJECTIVES
Items and documents shall be marked to ensure means of:
Page 2 of 5
Document No.:
Rev. No.
Procedure for Weld Identification and Weld Traceability
b. Locating the quality records generated from purchasing, inspection and testing of
the item.
TRACEABILITY REQUIREMENTS
The Contractors fabrication procedures shall ensure that correct materials are used
during fabrication and these shall be submitted to the Superintendent for approval.
STORAGE
The Contractor shall be responsible for material and equipment received from the
Superintendent or warehouse stocks until the same is installed. Where Superintendent
supplied materials are delivered to the Contractor with documentation such as mill
certificates, these shall be incorporated into the Contractors quality records.
Materials received from the warehouse or Superintendent, are to be stored off the
ground on temporary racks or docks to prevent any deterioration until fabricated.
Pipes, fittings, valves and specialty items shall be suitably blanked to protect the ends
from damage and to prevent entry of foreign material.
Stainless steel material shall be kept separate from carbon steel during storage and
transport
Page 3 of 5
Document No.:
Rev. No.
Procedure for Weld Identification and Weld Traceability
All cuts shall be made at right angles to the longitudinal axis of the pipe. All pipe ends
shall be
remade to the full bore of the pipe.
All cuts shall be carefully bevelled and accurately matched to form a suitable groove for
welding
and to permit complete penetration of the welds at all points. Reference is to be made
to the
relevant section of the Code.
Defective or damaged weld ends shall be examined in order to determine the nature
and extent of
damage. Any bevelled edge of pipe that has been damaged shall be machined to
minimum
tolerances. All bevels shall be cleaned to bright metal finish.
Repairs shall not be made on weld preparation of pipes or fittings without written
permission from
the Superintendent.
Repairs to weld preparations shall only be carried out using repair procedures which
have been
reviewed and approved by the Superintendent. Repair procedures must be submitted in
writing for
the Superintendents review and approval.
END PREPARATION
4.6.1 General
Surfaces to be welded shall be ground free of rust. Grinding is to extend 10mm past the
toe of the
weld preparation and is to be done immediately prior to welding.
Page 4 of 5
Document No.:
Rev. No.
Procedure for Weld Identification and Weld Traceability
Page 5 of 5
Document No.:
Rev. No.