Sie sind auf Seite 1von 8

Delivering Lean Results for Healthcare 18 July 2005

Using Virtual Building & the Last


Planner System

Presentation to
Australian Construction
Creating value
Eliminating waste
Industry Conference
Sydney, Australia
18 July 2005
Sutter Healths Challenge

Delivering Lean Results for


Healthcare Using Virtual Building
& the Last Planner System

Dean Reed
DPR Construction, Inc.
2

Sutter Health Adopts The Five Big Ideas of Lean Project


Lean Project Delivery Delivery
1. Collaborate; really collaborate,
throughout design, planning, and
execution
2. Increase relatedness among all project
participants
3. Projects are networks of commitments
4. Optimize the project not the pieces
5. Tightly couple action with learning

3 4

Collaborate; Really Collaborate


Projects as Networks of Commitment
Virtual Building and the Last Planner
System require collaboration and
strengthen the network of commitments
Will be the focus of this presentation

5 6

Dean Reed, DPR Construction, Inc.


2005 1
Delivering Lean Results for Healthcare 18 July 2005
Using Virtual Building & the Last
Planner System

The Five Big Ideas of Lean Project Delivery Translating into Action on Camino
#1 Collaborate; really collaborate, throughout
design, planning, and execution Collaborate; Really Collaborate
Constructable, maintainable, and affordable design
requires the participation of the range of project
performers and constituencies. Since abandoning the
master-builder concept, and separating design from
construction, we have been patching a poorly
conceived design practice. Value engineering, design Share incomplete information early and often
assist, and constructability reviews mask an underlying Identify the Last Responsible Moment for taking action and
assumption that design can be successful when use the time to make the best possible decision
separated from engineering and construction. Design Form cross functional teams of Designers and Builders for
is an iterative conversation; the choice of ends affects Site, Parking Structure, MOB Shell and Core, and MOB
means, and available means affects ends. Interiors
Collaborative design and planning maximizes positive Coordinate in 3 and 4D as design evolves
iterations and reduces negative iterations.

7 8

Parking Structure & Medical Office Building The Camino Medical Center
For the Camino Medical Group (CMG)
In Mountain View, California
Site & Infrastructure development (420,790sf)
Parking structure (1,110 stalls, 420,000sf)
Medical Office Building (110 Providers,
250,000sf)
Urgent Care Center (6,000sf)
Outpatient Surgery Center (5 Suites, 20,000sf)
Pharmacy (6,000sf)
Laboratory and Diagnostics Radiology Center
(30,000sf)
$100 million in construction costs
9 10

Virtual Building is an enabling


Lean Project Delivery & Virtual Building
technology for Lean Project Delivery
Lean Project Delivery
A process
Lean Project Delivery System
Eliminate waste by designing product (the
building) and process (building the building) Purposes
Design
Concepts
Product
Design
Fabrication
& Logistics
Testing &
Turnover

simultaneously
Design Process Detailed
Installation

Virtual Building
Criteria Design Engineering

A technology and process


Virtual Building
3D object model of the product
Clash detection of multiple 3D object models Project
Definition
Lean
Design
Lean
Supply
Lean
Assembly

4D visualization of construction Production Control


Work Structuring

Post-Occupancy
Evaluation
11 12

Dean Reed, DPR Construction, Inc.


2005 2
Delivering Lean Results for Healthcare 18 July 2005
Using Virtual Building & the Last
Planner System

Why & How Does Virtual Building 3D Solids / Parametric Objects


Enable Lean on the Camino Project? Not CAD Drafting - Not Surfaces
Design Concepts Product Design Object Model
3D visualization has allowed stakeholders to understand design 3D solid / parametric
Process Design objects with attributes
Construction sequence animated in 4D
Detailed Engineering
HVAC, plumbing, fire protection and electrical coordination and
shop drawings in 3D
Fabrication
HVAC will fabricate from 3D shop drawings
Plumbing and electrical will pre-fab from 3D shops
Logistics and Sequence
Trade installations within areas will be sequenced in 3/4D Surface Model
2D polygons into 3D
object with limited
attributes
13 14

Modeling Raises Questions about How Multiple 3D Object Models Created


Things Fit Together (Much Earlier) by AE & Specialty Contractors

Objects from libraries Architectural Model


of predefined parts

Objects assembled
just like the real thing

15 16

Multiple 3D Object Models Created Multiple 3D Object Models Created


by AE & Specialty Contractors by AE & Specialty Contractors

HVAC Model
Electrical Model

17 18

Dean Reed, DPR Construction, Inc.


2005 3
Delivering Lean Results for Healthcare 18 July 2005
Using Virtual Building & the Last
Planner System

3D Process Lessons Learned from Previous


Integration of Multiple Models in 3 & 4D Projects
Modeling is early learning
Model incomplete work early
Integrated Model Start with blocks in schematics and develop
detail as design progresses
Model to shop drawing level and below
Integrate models created with different tools
Model in field to solve coordination problems
Surround team with 3D images
Structure work in 4D with subcontractors
Progress 4D models to use in lookahead
planning
DPR Portland Office
19 20

Sutter Healths Expectation The Vision


Facility Assembled in Computer Before Its Built Onsite

Sutter Health agreed to invest money in early All important design decisions are made during
collaboration and virtual building design phase:
DRR hired during Conceptual Design
MEP/FP, Skin and Steel subcontractors brought on in No misunderstanding
Schematic Design No conflict of systems
Architectural and construction budgets increased to No change orders
pay for additional expense of 3 / 4D modeling and
coordination
Construction costs will be reduced overall
Changes take
RFIs will be significantly reduced place during the
Change orders due to coordination conflicts will be design phase
eliminated not during
construction

21 22

Lean Virtual Building Guidelines

Lean Virtual Building Guidelines 1. Architects & Structural Engineer


Created 3D Object Models
1. Determine authors of architectural and structural 3D
object models
2. Define the Virtual - Lean Design Collaboration process
3. Pre-qualify A/Es and subcontractors for Virtual Building
capability
4. Determine collaboration and modeling responsibilities
5. Agree on protocol for sharing drawings and models
6. Agree on coordination and conflict resolution process
7. Pull design coordination from construction
8. Sequence trades through interactive construction of 4D
models

23 24

Dean Reed, DPR Construction, Inc.


2005 4
Delivering Lean Results for Healthcare 18 July 2005
Using Virtual Building & the Last
Planner System

Lean Virtual Building Guidelines


Lean Virtual Building Guidelines
2. Camino Design Collaboration Process 3. Subcontractors Pre-qualified for
Contractor
Input to Design
Criteria & Equip
Virtual Building Capability
Contractor Selection, Sizing,
Input to Design Routing &
Alternatives Coordination

SD SD DD
50% Collaboration 100% 50% Collaboration

Engineer Object Modeling


Engineering & Engineer
Design in 2D Design in 2D Detailed design will be done in CAD 3D object modeling software,
which can create objects having the following characteristics:
Each object in the model has a unique name or object identifier, and
Contractor
can have attributes attached to it, i.e., geometry info, weight, cost,
Detailed Design & schedule, procurement info, etc.
Coordination in 3D
These objects are either 3D solids or true parametric objects. They
Engr
DD Bldg CD are not 2D polygons that are combined to create a 3D object, as is the
Collaboration Stamps Permit
100% Drwgs Dept Set 100% case in a surface model.
The object model is assembled from libraries of predefined parts
Engineer
Design Review & representing a constructible component or assembly of components.
RFIs = Drawing Author
Documentaion in Build
2D
25 26

Lean Virtual Building Guidelines


Lean Virtual Building Guidelines
4. Modeling Responsibilities 5. Protocols Agreed for Sharing
Drawings & Models
Scope Design Phase 3D File naming conventions
Model Created Reference point for 3D models
Architect Schematic Design
Protocol for sharing files using FTP site
Structural Engineer Design Development
Protocol for updating the drawing files
Mechanical Engineer No 3D
Electrical Engineer No 3D CAD backgrounds, colors and layer
HVAC Contractor Construction Documents
management for the drawings / models
Plumbing Contractor Construction Documents Protocol for combining drawings in a
Electrical Contractor Construction Documents single NavisWorks model for coordination
Fire Protection Contractor Construction Documents
27 28

Lean Virtual Building Guidelines Lean Virtual Building Guidelines

6. Coordination & Conflict Resolution 7. 3D Coordination Drawings Pulled


Process Established from Construction Schedule

29 30

Dean Reed, DPR Construction, Inc.


2005 5
Delivering Lean Results for Healthcare 18 July 2005
Using Virtual Building & the Last
Planner System

Lean Virtual Building Guidelines


8. Trades Will Be Sequenced through The Five Big Ideas of Lean Project Delivery
Interactive Development of 4D Models #3 Projects are networks of commitments
Projects are not processes. They are not value
streams. The work of management in project
environments is the ongoing articulation and
activation of unique networks of commitment.
The work of leaders is bringing coherence to
the network of commitments in the face of the
uncertain future and co-creating the future with
project participants. This contrasts with the
commonsense understanding that planning is
predicting, managing is controlling, and
leadership is setting direction.

31 32

Translating into Action on Camino


Projects as Networks of Commitments Camino Organization Was Typical

Negotiate deliverables rather than issuing commands


Be willing to say and hear No
Ask for and make honest commitments
Declare complete when youre done to release work to the
next performer

33 34

Silos & Big Batches The Black Box of Design

Architects and engineers worked and Architects developed a summary level


communicated in their own silos, apart work plan to deliver the big batches
from builders
Customer inputs and deliverables within
A/Es used to working in large batches the design team and to contractors not
Schematic Design
planned
Design Development
Construction Documents Difficult to get architect to agree to delivery
A/Es traditional practice was to throw the dates for design packages
batches over the wall for cost and No Success in pulling a design phase
construct-ability review schedule from deliverable dates
35 36

Dean Reed, DPR Construction, Inc.


2005 6
Delivering Lean Results for Healthcare 18 July 2005
Using Virtual Building & the Last
Planner System

Seeing Inside the Black Box Commitment Manager

Project team came to understand Tracks commitments and related actions


importance of making requests and between people
keeping promises Maintains status of commitment
Commitment Manager software reviewed Manages commitments reminds and escalates
and selected by project team as a tool for Provides visualization of commitment status
strengthen the network of commitments Provides metrics as a byproduct of tracking the
Team members could make requests and actions
respond from their workplaces Runs on a Web or Microsoft Outlook server
Requesters, performers and observers
could see status of requested actions
37 38

Commitment Manager in Place of RFIs


During Design

Commitment Manager should be used for the following:


Documenting all design collaboration queries between the
project team prior to the permit being issued for the
particular scope of work.
Documenting of all cost impact issues shall be entered by
the subcontractors in the Commitment Manager as a
request of Scott Sass. The requests will then be committed
by Scott Sass and the DPR team in the cost impact log.

39 40

Making a Request Commitment Status Report

41 42

Dean Reed, DPR Construction, Inc.


2005 7
Delivering Lean Results for Healthcare 18 July 2005
Using Virtual Building & the Last
Planner System

Applying the Last Planner System in


Using the Weekly Work Plan
Design
Not able to create a pull Design Phase Requests for information and offers to
schedule provide answers are recorded in a MEP
Not able to look ahead and do constraints Weekly Work Plan
analysis WWP developed on screen in the meeting
DPR worked with Sutter Health to make Commitments by A/Es, the GC and
the Weekly Work Plan the focus of the subcontractors are scored and charted
weekly project meeting each week
Meeting minutes are kept to record WWP is distributed to all participants after
discussion, not used to run the meeting the meeting
43 44

Mechanical & Electrical Weekly Work Cost Benefits Study

Plan & Pareto Charts Collaboration Results So Far

Cost Avoidance: $5,356,980

45 50

Presentation to
Australian Construction
Creating value
Industry Conference
Eliminating waste Sydney, Australia
18 July 2005

Questions & Answers

Dean Reed, DPR Construction, Inc.


2005 8

Das könnte Ihnen auch gefallen