Sie sind auf Seite 1von 6

The use of cylindro-conical settlers for the

clarification of underground water


by E. C. HUNTER- (Associate)
G. T. C. EMERE-, B.A. (Hons.) (Keele) (Visitor)
SYNOPSIS
This paper analyses the performance of conical settlers on Harmony Gold Mine from 1959 to the present time,
and describes the investigation that was undertaken to substantiate and improve the use of conical settlers for a
new pump chamber in another part of the mine.
SAM EVATTI NG
Hierdie verhandeling ontleed die verrigtinge van die kegelvormige setlaars op Harmony Goudmyn vanaf 1959
tot datum en beskryf verdere ondersoek wat onderneem is om te bevestig en te verbeter op die gebruik van die
kegelvormige setlaars vir 'n nuwe pompkamer in 'n ander deel van die myn.

Introduction stream at 20 m and 10 m respectively from the first


settler. The rate of water inflow to each conical settler
The removal of water from mines is a problem as
is controlled by manual adjustment of a gate that slides
old as mining itself, and, if full use is to be made of the
over an inverted vertical 10 V-notch. This V-notch
high-lift centrifugal pumps now installed, efficient
ensures that, as the flow in the drain feeding the settlers
settling of mud and grit from the water is essential.
increases and the level rises, the first settlers in the line
When Harmony Gold Mine was planned, it was decided
are not overloaded. A fibre-glass launder then delivers
to use conical settlers from the outset!.
into a stilling box as seen in Fig. 3. The clear water
Fig. 1 shows No. 3 Shaft at Harmony with the settlers,
flows over the lip launder into storage dams, and settled
clear-water sumps, and pump chamber relative to the
mud is drawn off the bottom of each settler into a mud
shaft pillar, and Fig. 2 shows an isometric view of the
dam every twenty minutes.
layout.
Initially, the settler adjacent to the shaft operated
Flow Pattern in a Conical Settler
as a grit settler, and all the water was routed to this
settler until recently, when it was decided that the Although the stilling box terminates 1830 mm below
coarse-solids fraction arriving at the pump chamber the new flow level, the water velocity continues down-
was not large enough to justify presettling. This has wards, eventually fanning upwards towards the peri-
not resulted in abnormal problems with the mud pumps pheral overflow lip. Particles settle out against a rising
and saves the nuisance of transferring the product from current induced by the overflowing water; hence, the
the grit settler to the shaft loading boxes. action within the settler is that of countercurrent
The remaining ten settlers operate as previously settling.
describedl, the only change being in the materials used This was verified by samples taken from various
for the feed launder, stilling box, and peripheral V. points in a working settler using a long pipe with a
notches. These are now manufactured from fibre glass stoppered end. When the pipe was in the desired position
instead of sheet metal and have an estimated indefinite for a sample to be taken, the stopper was pushed out
working life, but cost twice as much to install. with a stiff piece of wire attached to the stopper through
the bore of the pipe, thus allowing water to enter the
Operation of the Settler pipe. The depth and position of the sample were re-
Raw water at a pH of 6,8 is treated with milk of lime, corded, the stopper was pulled back, and the sample
which is pumped underground from a slaker situated was removed for analysis.
in the Reduction Plant. The pH value is increased to From these samples, the flow and settling patterns in
approximately 8,5 to reduce corrosion caused by the the settler were plotted (Fig. 4).
chlorides in the water and to increase flocculation.
Since the flocculent used forms a gelatinous substance Settling Tests at Harmony
in water that is difficult to dissolve, batches of 0,9 kg The use of flocculent became essential when the
of flocculent powder are mixed by air agitation with quantity of water handled by each settler increased
182 litres of water in a tank. Small notched launders owing to an expansion of mining operations and the
then distribute the mixed flocculent evenly across the closure of a pump station at an adjacent shaft. The
raw-water stream at an average rate of 0,57 kg per experiment detailed below indicates the advantage to
megalitre of water.
be gained from the use of flocculents.
The lime and flocculent are fed into the water up-
A test apparatus holding three samples of water was
set up in 700 mm high beakers to observe the settling
*Harmony Gold Mining Company Limited, Welkom, O.F.B. characteristics. The first sample was raw water contain-

JOURNAL OF THE SOUTH AFRICAN 'N$T'TI,IT~ OF MINING AND METAI-LURGY MAY 1971 201
Fig. I-Plan of No. 3 Shaft pillar, showing the location-of the settlers

202 MAY1977 JOURNAL OF THE SOUTH AFRICAN INSTITUTE OF MINING AND METALLURGY
'. CQ\lICAL CLEAR OVERFLOW
2\1

FLOC
BLANKET

SLUDGE.

NUMBER THREE SHAF T


17 LEVEL

Fig. 2-lsometric view of the pump chamber, clear water Fig. 4-Flow pattern in a conical settler (the solids analyses
dams, and conical settlers are given in pop.m.)

OVERFLOW
LIP

~ 10
8 MEGALITRE

.,\~ ~
If)
w
ex:
RAW WATER ~
Ww
455 CHANNEL ~.J ---~~
jj ",'.' ~'~'~'~~""
~If) ""'" '",

CLEAR WATER ~
1(9
>-9
,1

RAW WATER
l \
\ " '.
\

\\
"
".
COLUMN
95 ,01
UJ
\
\
\ '.
> ,
,
I
~
:J
I
I
I
I
1=
m 001 10 100 1000 10000 100000
TIME - SECONDS ON LOG SCALE

Fig. 3-Cross-section Df a conical settler Fig. S-Settllng velocity versus time

JOURNAL OF THE SOUTH AFRICAN INSTITUTE OF MINING AND METALLURGY MAY 1977 203
10000
RM Wt>.TER
FEED
~
~
~1000
9

6 100
:::;
..J
~ ~17,5
Cl:
W
Cl.
10 -'I 1___-
PRESENT
~ O~TNG
~ PONT
~
cl
If)
I
0 2 3~ 4 6 8 10
FEED RATE -
tv1EGALlTRESPER Dt-y
Fig. 6-Feed rate to conical settler versus clarity of overflow water

ing 50464 p.p.m. of solids, with lime added but no Eleven different flow rates were forced onto a settler,
flocculent. The second sample had lime and half the and samples of the overflow were taken at various
regular dosage of flocculent, and the last sample had points round the periphery of the settler for each flow
lime and the regular flocculent dosage of 0,57 kgjM!. rate.
After the first 100 seconds, the sample of water fully Flow rates of up to 9,5 MIjd were achieved during this
loaded with flocculent had approximately 4,5 times the test, but the settling at this flow rate was unsatisfactory.
clarity Qf the unflocculated sample (i.e., 2000 p.p.m. The test indicated that flows in the region of 8 MIjd
as against 9000 p.p.m.). However, the final products per conical settler could be achieved with moderate
over a prolonged period of 2,7 hours were very similar. results, provided that the settled mud was drawn off
Flocculent greatly increased the speed of settling of regularly.
clear water to the mud interface - from 0,25 mmjs for To ensure that there would be no build-up of mud in
raw water with no flocculent to 1 mmjs, as shown in the settlers, a study was made of the drawing off of
Fig. 5. mud with the intention of making this a continuous
process. Various sizes of orifice were fixed to the bottom
Performance Tests of the settler in an attempt to find the right balance
As previously indicated!, the original layout was between a small orifice that would become choked and a
designed to treat a daily maximum of 4,59 MI of raw large orifice that would discharge so much that water
water per conical settler, with a norma.! daily rate instead of mud would be transferred to the mud dam.
of 1,636 MIld. However, the inlet-flow control plate has No satisfactory condition was attained, and it was
since been enlarged and the average throughput increased concluded that 150 mm valves opened at regular inter-
to 3,4 MIjd for a total of 27 MIjd (eight units). About 45 vals are still the best solution (Fig. 6).
per cent of the treated water is pumped to surface, while
the balance is recirculated for drilling and mining purposes. Daily Operating Costs
A series of tests was conducted to indicate the maxi- Labour (including benefits):
mum quantity of water that could be treated in an Part-time supervision R52,50
emergency, the maximum quantity being governed by Operators, 4 per shift 12,50
the quality of water acceptable for re-use as machine Lime R24,00jt at 10 tjmonth=0,33 tjd 8,00
water. Flocculent, 14 kgjd at R2,45fkg 34,30
For these tests, a variable-inlet (flow-control) gate Maintenance and repairs 5,00
was manufactured so that the flows could be in excess
of the 3,4 MIld being treated at present. Downstream Total daily operating cost R112,30
from this gate a rectangular weir was installed to measure
flow. The cost based on 27 MI settled per day is therefore
It was found that, owing to 'channelling' of the R4,15fMl.
overflow, i.e., overflow concentrated in certain sections
of the overflow lip, the maximum quantity that could New Settlers and Pump Chamber
be treated efficiently occurred when the water level in
the conical settler rose to a point just below the top of Excavation work is in progress for a new pump
the V-notches round the periphery of the settler. chamber, conical settlers, and clear water sumps that

204 MAY 1977 JOURNAL OF THE SOUTH AFRICAN INSTITUTE OF MINING AND METALLURGY
CLEAR WATER
DAMS

CONICAL
SETTLERS

FI,. 7-Layout of new pump chamber, clear water dams, and conical
settlers

are to be situated in overstoped ground. The layout is zontal settlers, both because they cut across planes in
shown in Fig. 7. the geological succession and also because stress distribu-
The capital cost ofthis project, without any mechanic- tion round circular openings is more uniform. Further,
al or electrical equipment, is estimated to be R219 000. with suitably designed and installed support, any rock
The following are the rea.sons for the establishment of failure and eventual slabbing can be effectively
this new pumping complex. restrained. The conical settlers have a shape closely
(I) Because of the extensive ground movement in approaching that of a vertical cylinder.
No. 2 Shaft pillar, the settling and pumping arrange- The application of smooth-wall blasting techniques
ments at this shaft were abandoned in 1971. The is very much more effective in circular excavations,
present settling and pumping facilities are confuied particularly when they cut sharply across the geological
to No. 3 Shaft and will have to be abandoned when strata and when the excavation has a vertical orientation.
the mining of No. 3 Shaft pillar takes place at some
future date. Practical considerations
(2) The existing layout of No. 3 Shaft is being subjected
Analytical,- a.s well as analogue- and digital-computer,
to high rock pressures, which are affecting the pump
techniques clearly demonstrate that induced compress-
alignment and pipe connections in the pump
ive-stress concentrations and deformation magnitude
chamber, together with caving of the tunnels
increase rapidly towards the~ perimeter of a shaft pillar.
connecting the settlers and the water dams. Ex-
Factors determining the stress field within the pillars
penditure on rock support became necessary in
include depth below surface, excavated stoping width,
1972 and has risen rapidly as conditions deteriorate.
and extent of stoping radially away from the pillar.
As a result of (I) and (2), it was decided to excavate
and install new pumping and settling arrangements in Theoretical and practical analysis of complex hori-
overstoped ground. The pumping capacity of this ]Jump zontal layouts shows that circular excavations should
station will be increased from the present capacity of not be sited closer together than three times the maxi-
34,5 MIld to cope with any emergency flooding condition. mum dimension of the excavation, while rectangular or
square excavations should never be sited closer than
Rock Mechanics Aspects six times the maximum dimension.
Ideally, vital excavations such as dams, settlers, and
Theoretical Considerations pump chambers should be sited outside the shaft
Vertical excavations with circular profiles are structur- protection pillar and overstoped as expeditiously as
ally stronger than the profiles typically used for hori- possible. However, extra expense during the initial

JOURNAL OF THE SOU'fH'AFRICAN INSTITUTE OF MINtNG AND METALLURGY MAY 1977 205
establishment of operatIons at shafts has generaUy been mony have proved to be very successful both from a.
against the adoption of such a policy. Because of their rock mechanics point of view and from the point of view
superior strength, conical settlers can be placed closer of efficient operation.
together and therefore occupy less space. Space is at a
premium because of the gold values contained in shaft AcknowledgeDlent
pillars.
The theoretical strength of conical settlers has been The authors thank the Management of Rand Mines
borne out in practice. Actual observation shows less Limited for permission to publish this paper.
side-wall and genera.! deterioration, and therefore less
initial support cost and less subsequent support involve- Reference
ment.
1. THIEL, E. W. Use of cylindro conical settlers for under-
SuDlDlary ground water clarification on Harmony Gold Mining Corn.
pany Limited. Association of Mine Managers of South
From experience, conical settlers as installed at Har- Africa, 1959.

Company Affiliates
The following members have been fraser & Chalmers S.A. (Pty) limited. R. J. Spargo Limited
admitted to the Institute as Com- Gardner-Denver Co. Africa (Pty) Ltd. Rooiberg Minerals Development Co.
pany Affiliates. Goldfields of S.A. Limited. LImited.
The Grootvlel (Pty) Mines limited. Rustenburg Platinum Mines limited
Harmony Gold Mining Co. limited. (Union Section).
AE & Cl limited. Hartebeesfontein G.M. Co. limited. Rustenburg Platinum Mines LImited
AfroxjDowson and Dobson limited. (Rustenburg Section).
Hlghveld Steel and Vanadium Corpo-
Amalgamated Collieries ofS.A. LImit- ration Limited. St. Helena Gold Mines LImited.
ed. Hubert Davles Heavy Equipment Shaft Sinkers (Pty) Limited.
Apex Mines limited. (Pty) Ltd S.A. Land Exploration Co. limited.
Associated Manganese Mines of S.A. Impala Platinum limited. Stllfontein G.M. Co. LImited.
limited. Ingersoll Rand Co. S.A. (Pty) Ltd. The Griqualand Exploration and Fi-
Bllllton Exploration S.A. (Pty) Johannesburg Consolidated Invest- nance Co. LImited.
limited. ment Corp. Ltd. The Messina (Transvaal) Develop-
Blackwood Hodge (S.A.) limited. Klnross Mines Limited. ment Co. limited.
Blyvoorultzlcht G.M. Co. Ltd. Kloof Gold Mining Co. limited. The Randfonteln Estates Gold Mining
Boart International LImited Lennlngs Holdings Limited. Co.Witwatersrand Ltd.
Bracken Mines LImited. Leslie G.M. LImited. The Robbins Co. (Africa) (Pty) Ltd.
Buffelsfonteln G.M. Co. limited. The Steel Engineering Co. Ltd.
Llbanon G.M. Co. LImited.
Trans-Natal Coal Corporation LimIt-
Cape Asbestos South Africa (Pty) Ltd. Lonrho S.A. limited.
ed.
Compair S.A. (Pty) limited. Loraine Gold Mines limited.
Tvl Cons. Land & Exploration Co.
Consolidated Murchlson (Tvl) Gold- Marlevale Consolidated Mines LImited Tsumeb Corporation Limited.
fields & Development Co. limited. Matte Smelters (Pty) Limited. Union Corporation Limited.
Deelkraal Gold Mining Co. Ltd. Natal Cambrian Collieries limited. Vaal Reefs Exploration & Mining Co.
Delfos & Atlas Copco (Pty) Limited. Northern LIme Co. LImited. Limited.
O'oklep Copper Company LImited. Venters post G.M. Co. Limited.
Doornfonteln G.M. Co. limited.
Otjlhase Mining Co. (Pty) LImited. Vergenoeg Mining Co. (Pty) Limited.
Durban Roodepoort Deep ~imited. Palabara Mining Co. limited. Vlakfonteln G.M. Co. Limited.
East Drlefontein G.M. Co. limited. Photometric Sorters. Welkom Gold Mining Co. Limited.
East Rand Prop. Mines LImited. President Stern G.M. Co. limited. West Drlefonteln G.M. Co. LImited.
Engineering Management Services Pretoria Portland Cement Co. limit- Western Areas Gold Mining Co. Ltd.
(Pty) Ltd. ed. Western Deep Levels Limited.
Envlrotech (Pty) Ltd. Prleska Copper Mines (Pty) limited. Western Holdings limited.
Free State Saalplaas G.M. Co. limited. Rand Mines limited. Wlnkelhaak Mines Limited.

208 MAY 1977 JOURNAL OF THE SOUTH AFRICAN INSTITUTE OF MINING AND METALLURGY

Das könnte Ihnen auch gefallen