Beruflich Dokumente
Kultur Dokumente
thus far)
EAC is calculated as BAC/CPI (in this case, $10,000/0.80). It is now
known that the project will cost more than the original estimate of
$10,000. The project has been getting only 80 cents worth of work done
for every dollar spent (CPI), and this information has been used to
forecast total project costs. This approach assumes that performance for
the remainder of the project will also be based on a CPI of 0.80.
[Monitoring and Controlling]
PMI, PMBOK Guide, 2013, 224
6. d. Cost baseline
Cost baseline is an output from the determine budget process.
[Monitoring and Controlling]
PMI, PMBOK Guide, 2013, 212213Project Cost Management 125
7. d. Electricity
Direct costs are incurred for the exclusive benefit of a project (for
example, salary of the project manager, materials used by the project,
and subcontractor expenses). Indirect costs, also called overhead costs,
are allocated to a project by its performing organization as a cost of
doing business. These costs cannot be traced to a specific project and
are accumulated and allocated equitably over multiple projects (for
example, security guards, fringe benefits, and electricity). [Planning]
PMI, PMBOK Guide, 2013, 202
9. c. Identify and estimate the cost for each work package or activity
Bottom-up estimating is derived by first estimating the cost of the
projects elemental tasks at the lower levels of the WBS or for an
activity and then aggregating those estimates at successively higher
levels of the WBS for subsequent reporting and tracking purposes.
[Planning]
PMI, PMBOK Guide, 2013, 205126 PMP Exam Practice Test and Study
Guide
10. b. Determine the cost performance needed to complete the remaining work
within managements financial goal for the project
The TCPI takes the value of work remaining and divides it by the value
of funds remaining to obtain the cost performance factor needed to
complete all remaining work according to a financial goal set by
management. [Monitoring and Controlling]
PMI, PMBOK Guide, 2013, 224
11. c. $350
CV is calculated by EV AC, or $1,500(2/3) $1,350 = $350.
[Monitoring and Controlling]
PMI, PMBOK Guide, 2013, 224
17. c. Order-of-magnitude
An order-of-magnitude estimate, which is referred to also as a ballpark
estimate, has an accuracy range of 25% to 75% and is made without
detailed data. [Planning]
PMI, PMBOK Guide, 2013, 201; Ward 2008, 295
27. c. CVs
Cumulative cost curves, or S-curves, enable the project manager to
monitor cost variances at a glance. The difference in height between the
planned-expenditure curve and the actual-expenditure curve represents
the monetary value of variances at any given time. [Monitoring and
Controlling]
PMI, PMBOK Guide, 2013, 219
28. d. Represent the basic level at which project performance is measured and
reported
Control accounts represent a management control point where scope,
budget (resource plans), actual costs, and schedule are integrated and
compared to earned value for performance measurement. [Planning]
PMI, PMBOK Guide, 2013, 132, 199, and 533132 PMP Exam Practice
Test and Study Guide
29. c. Time reporting systems
Variance analysis focuses on cost and schedule to help explain the
cause, issue, and corrective action. Trend analysis examines project
performance over time to determine performance status. Earned value
performance compares the performance measurement baseline to
actual schedule and cost performance. [Monitoring and Controlling]
PMI, PMBOK Guide, 2013, 222223
31. c. Unit costs decrease in a regular pattern as more units are produced
Learning curve theory indicates that human performance usually
improves when a task is repeated. Specifically, each time output
doubles, worker hours per unit decrease by a fixed percentage. This
percentageis called the learning rate. [Planning]
Meredith and Mantel 2012, 301303Project Cost Management 133
32. c. Current variances are viewed as typical of future variances
Past performance is indicative of future performance; therefore, EAC =
BAC/CPI. [Monitoring and Controlling]
PMI, PMBOK Guide, 2013, 201