Sie sind auf Seite 1von 48

LEND LEASE BUILDING PTY LIMITED | ABN 97 000 098 162

R8000 NEW AIR COMBAT CAPABILITY


(NACC) FACILITIES PROJECT,
RAAF BASE WILLIAMTOWN
MANAGEMENT PLAN ASBESTOS AND
HAZARDOUS BUILDING MATERIALS
27/11/2015 | Revision No: 6
Plan Revision Status

Revision
Date Purpose and Summary of Amendments Reviewed by Approved by
(in numbers)
18/09/2014 1 Initial Draft

15/10/2014 2 For Construction

25/03/2015 3 Quarterly review. Updated risks after


asbestos found in ground.
06/07/15 4 Quarterly review. Updated asbestos
management procedures in line with Dept. of
Defence requirements.
1/09/2015 5 Quarterly review- no change

27/11/2015 6 Quarterly review- update to reflect Defence


requirements and Approved Project AMP

*Note that all printed paper/hard copies of this document and related procedures are uncontrolled. The controlled copy of this document is
found either in Project Web, within the Project Management Plan section, or other project specific database/server approved by the
Regional EHS Manager.

PAGE 2
ASBESTOS (& HAZARDOUS BUILDING MATERIAL) MANAGEMENT PLAN

This Asbestos & Hazardous Building Material Management Plan details prevention and management measures for Asbestos & Hazardous Building Material issues associated with
construction works at the NACC Facilities Project, Williamtown. It defines mitigation measures to be implemented during relevant construction activities in the event that asbestos is
Scope:
located, or potentially affected areas are identified; a monitoring program that enables assessment of the impacts of construction activities on potentially affected areas; and contingency
measures that may be implemented if exceedances are measured.
To identify any asbestos or hazardous building materials in site buildings or structures to be demolished
To properly manage and remove any asbestos or hazardous building materials in encountered during excavation works on site including bulk earthworks, topsoil strip and
trenching / excavation for future services such as stormwater, sewerage, water mains, in ground power and communications.
Objective: To properly store, transport and dispose of all potential asbestos and hazardous building materials to an approved licensed waste facility.
To prevent any impact to air quality or site work areas and adjoining properties via inappropriate handling, removal or disposal of asbestos or other hazardous building materials.
Assess Williamtown Base Hazardous Substance Register to identify potential for exposure to hazardous materials during construction activities.

Historic waste management practices on the Base included burial and covering of a range of waste from construction / demolition materials to surplus military hardware and chemical
drums, as such Unexpected Finds of various types of waste including hazardous materials can be expected across the project footprint.
Given the age and condition of structures be demolished, there is potential for hazardous building materials to exist within the buildings. As the proposed redevelopment will include the
demolition of these buildings and disposal of materials, safe work measures need to be implemented to ensure that environmental (PCBs and lead) and human health risks are
appropriately minimised and managed during this process.

Asbestos
Asbestos was commonly used as an acoustic insulator, brake pads (i.e. lifts), thermal insulation (i.e. pipes and cables), fire proofing (i.e. steel beams) and in building materials such as
ceiling tiles or wall panels, pipes, floor tiles, linoleum and mastic. Asbestos is made up of microscopic bundles of fibres that may become airborne when distributed. These fibres may
become inhaled into the lungs with significant potential risks to human health.
Risks:
Other key hazardous building products
These include fluorescent light fittings with capacitors containing PCBs and building materials coated with lead-based paints. Both of these materials pose significant potential risks to the
environment and human health if removed, handled and/or disposed inappropriately.

See Appendix B for the Hazardous Materials Register

Hazardous Material risks Identified in the buildings to be demolished by the NACC Project include:
A Hazardous materials inspection of the 12 Explosive Ordinance preparations buildings are to be demolished identified:
Asbestos Containing Material (ACM) within the following structures, Buildings 307, 304, 300, 317, 287, 305, 308, 319, 320
Lead Paint found in Structures 474, 473

MANAGEMENT PLAN ASBESTOS AND HAZARDOUS Page 3 of 20


BUILDING MATERIALS
REV DATE: 27/11/2015 REV: 6 DOC ISSUE: 15OCT14 Rev DOC # R8000-WLM-00-MP-MN-00-103
Unexpected Finds to date include
Asbestos in Soil , including asbestos fibres in soil have been encountered at the SE runway and in the NACC Precinct area. There is potential to uncover more buried
asbestos waste materials during excavation activities across the whole project site.
Coal Tar drums encountered adjacent to the BOM pad area

The implementation of the Asbestos & Hazardous Building Material Management Implementation Plan is intended as mitigation measures to prevent the following risks from occurring.
Exposure of site workers, site personnel or adjacent land users to asbestos or other Hazardous Building Materials such as lead dust during demolition
Inappropriate disposal of asbestos or other Hazardous Building Materials / contaminated waste
National :
WHS ACT 2011
WHS REGS 2011
SWA NOHSC Publication: Code of Practice for the Safe Removal of Asbestos 2nd Edition [NOHSC:2002(2005)
SWA NOHSC Publication: Guidance Note on the Membrane Filter Method for Estimating Airborne Asbestos Fibres 2nd Edition [NOHSC:3003(2005)
SWA NOHSC Publication: Guidance Note on the Membrane Filter Method for the Estimation of Airborne Synthetic Mineral Fibres [NOHSC:3006 (1989)
SWA NOHSC Publication: List of Designated Hazardous Substances [NOHSC:10005 (1999)
Globally Harmonised System of Classification and Labelling of Chemicals (GHS)
Dept. of Defence, DSRG: Management and control of asbestos in defence infrastructure and estates infrastructure division procedure. Sept 2014
Key Legislation /
Standards / State:
Guidance While state legislation does not apply to Defence activities, Defence aims to be good environmental stewards and comply with State government legislation and policies to the extent that
these do not conflict with Commonwealth legislative obligations or compromise operational objectives or capability.
NOTE: State Legislation does apply to Activities carried out outside of Defence land.
Protection of the Environment Operations Act 1997;
Contaminated Land Management Act 1997
NSW EPA Waste Classification Guidelines 2014
Guidelines and Standards:
AS 4964-2004: Method for the qualitative identification of asbestos in bulk samples

A Hazardous Materials Building Survey will be conducted to identify all Hazardous building materials to assist in the management of removal, handling, storage and disposal of such
materials.
Site Control
Measures: From this survey a Hazardous Materials Building Register is to be prepared for the site prior to the demolition, disturbance or removal of any site buildings and structures to identify the
presence, location and type of hazardous building materials present on or within the proposed structures to be demolished (See Appendix B).

MANAGEMENT PLAN ASBESTOS AND HAZARDOUS Page 4 of 20


BUILDING MATERIALS
REV DATE: 27/11/2015 REV: 6 DOC ISSUE: 15OCT14 Rev DOC # R8000-WLM-00-MP-MN-00-103
Unexpected find protocol
If suspected toxic or hazardous materials are discovered / exposed during construction/demolition activities in an area of the site believed to be free of clean of hazardous materials, the
following protocol must be followed:
1. Cease work and evacuate the area of work immediately.
2. Contact a LLB representative (EHS coordinator, General Foreman, Construction Manager)
3. Erect barricades to isolate the immediate areas, with 10m between the suspect material and the erected barrier if possible.
4. The appropriate regulatory authorities including the Clients Contract Administrator should be notified as soon as possible if applicable.
5. No person shall enter the barricaded area unless expressly permitted by the qualified environmental specialist. A clearance certificate or approval should be given in
writing prior to entry.
6. Sampling of the suspect material is to be carried out by an appropriately qualified environmental specialist / occupational hygienist (usually a consultant) as advised by the
LLB construction manager. Air monitoring to be carried out by the Hygienist during sampling.
7. The nominated Environmental Specialist (in liaison with LLB senior site personnel and/or relevant authorities) will produce an Asbestos Management Plan (AMP) for the
asbestos material, describing proposed remedial actions, based on the sample test results and will nominate appropriate treatment / handling or disposal options and
procedures,
8. All permits to carry out remedial work are to be obtained, and required notifications made, prior to the commencement of any new works and the nominated Environmental
Specialist must provide written clearance approval.
9. The barricade may then be removed and work activities may resume under the direction of the LLB Construction Manager.
All controls are to comply to the LL Physical GMR 8.6

Control Measures Timing Methodology Responsibility Monitoring and Reporting Performance Measure
Planning / General
Identification of Hazardous Building Materials
Preparation of a Hazardous Building All Hazardous Building Materials
A Hazardous Materials Building Survey to be Prior to demolition survey with a Hazardous Materials listed in Register. All Hazardous
As developed by the specialised
undertaken to identify all Hazardous Materials works CM Register included. Building Materials tagged.
environmental consultant
Building commencing Appropriate Safety Data Sheet
present in file.
Hazardous Building Materials Register developed SM / Sub- Inspections prior, during and after Register is current.
At all times Incorporate information in Registers.
and maintained. contractor materials removal.
Overall site plan with elements notated and Diagram Map prepared & containing
A HS&DG Diagram will be prepared for the site that maintained as required. Review of Diagram prior works all relevant details. The diagram will
details the designated storage locations for all Prior to works CM/SM/ Sub- commencing.
May be incorporated into contractors Erosion also include a list of key buildings or
dangerous goods on the site including key areas commencing contractor
and Sediment Control Plans, or Environmental structures noted to contain
where these materials are used.
Control Plans. Hazardous Building materials.

MANAGEMENT PLAN ASBESTOS AND HAZARDOUS Page 5 of 20


BUILDING MATERIALS
REV DATE: 27/11/2015 REV: 6 DOC ISSUE: 15OCT14 Rev DOC # R8000-WLM-00-MP-MN-00-103
Control Measures Timing Methodology Responsibility Monitoring and Reporting Performance Measure
Demolition / Refurbishment
Asbestos Management Plan, specific to the
location and nature of asbestos to be removed
and incorporating Defence requirements, is to
be developed by suitably qualified and As required.
EM / SM / No asbestos dust particulates
Removal of asbestos and related building products experienced contamination specialist (See Inspection by Occupational Hygiene
Environmental detected during monitoring.
during demolition/refurbishment is to be undertaken At all times Appendix A). Surveyor for clearance.
Consultant / Correct SWMS followed.
by a licensed asbestos contractor. This plan will be reviewed by Defence prior to Clearance report
Hygienist Appropriate PPE worn.
commencing asbestos removal works on the Air monitoring report
Project.
Continuous air monitoring to be conducted
during asbestos removal.
No damaged light fittings during the
Removal of PCBs in any light fittings during As required. removal process.
Removal procedures in contractor SWMS. By
demolition/refurbishment is to be undertaken by an At all times SM Inspection by Occupational Hygiene
an approved contractor Correct SWMS followed.
approved contractor. Surveyor for clearance.
Appropriate PPE worn.
Minimal disturbance to paint / other
Removal of timber / metal / brick structures Removal procedures in contractor SWMS (i.e. hazardous substances in materials
As required.
containing lead-based paints or other hazardous sprays to stabilise paints /dust). achieved.
At all times SM Inspection by Occupational Hygiene
substances during demolition/refurbishment is to be
Air monitoring may need to be performed. Surveyor for clearance. Correct SWMS followed.
undertaken by a licensed contractor.
Appropriate PPE worn.
Excavation of contaminated material by
mechanical means
Asbestos Management Plan, specific to the
location and nature of asbestos to be removed
and incorporating Defence requirements, is to
be developed by suitably qualified and
experienced contamination specialist (See EM / SM / Correct SWMS followed.
Excavation of asbestos containing material (ACM) is
Appendix A). Environmental No non-compliance detected by the
to be supervised by of an asbestos licensed removal At all times Daily inspections
Consultant / asbestos licensed removal
contractor, or occupational hygienist. This plan will be reviewed by Defence prior to
Hygienist contractor.
commencing asbestos removal works on the
Project.
Continuous air monitoring to be conducted
during asbestos removal.
Excavator being utilised to excavate ACM must have Appropriate controls to be developed by
any enclosed cabin for the operator AMP and SWMS requirements
At all times suitably qualified and experienced SM/ Foreman Daily inspections
followed.
Excavator operator is to remain inside the cab of the contamination specialist consistent with

MANAGEMENT PLAN ASBESTOS AND HAZARDOUS Page 6 of 20


BUILDING MATERIALS
REV DATE: 27/11/2015 REV: 6 DOC ISSUE: 15OCT14 Rev DOC # R8000-WLM-00-MP-MN-00-103
Control Measures Timing Methodology Responsibility Monitoring and Reporting Performance Measure
excavator for the duration of works with the reverse legislative requirements.
cycle air conditioning running. Excavation subcontractor is responsible for
implementation of nominated controls under
supervision of the occupational hygienist
Continuous air monitoring to be conducted
during asbestos removal
Ensure water is made available onsite for dust Removal procedures in contractor SWMS (i.e.
suppression for the duration of excavation works. sprays to stabilise paints /dust), and AMP AMP and SWMS requirements
Ensure erosion and sediment controls are in place At all times SM/ Foreman Daily inspections
Continuous air monitoring to be conducted followed.
prior to works commencing particularly on highly
erodible soils. during asbestos removal.

Occupational hygienist will inspect the A clearance certificate will be issued


SM/
Occupational hygienist to provide clearance/ surfaces of the excavated area or ground following a satisfactory result during
As required Occupational Inspections to all areas as required
acceptance of affected areas. surfaces to confirm there is no visually the occupational hygienists
hygienist
identifiable asbestos. inspection.
Asbestos impacted soil excavated to be
loaded into a truck or bin lined with 200m
thick polythene totally covered and sealed.
AMP and SWMS requirements
Stockpiled potentially asbestos contaminated followed.
The asbestos impacted soil excavated to have material will be placed on, and covered with Daily inspections.
At all times SM/ Foreman Waste classification reports
dedicated containment / transport procedures. 200 m polythene prior to testing and disposal Tracking of trucks or bins leaving site
Waste tracking dockets from licensed
All asbestos contaminated material to be
landfill
waste classified in accordance with authority
requirements prior to disposal at an
appropriately licenced facility.
A geo-textile fabric layer will be laid along the
walls and base of the trench as well as the
ground surfaces to provide an indicator layer
between clean fill and asbestos impacted
soils. Certified clean fill such as crushed
All trenches excavated in asbestos impacted soils for concrete or pebble layer should be laid at the Correct SWMS followed.
At all times as base of the trench for the new services to sit
new service are to be backfilled with asbestos free SM Inspections to all areas as required Certified documentation for clean fill
required on. Clean fill material will be used to the fill
clean material. used.
and encapsulate the trench.
The occupational hygienist will inspect
surfaces of the backfilled trench and the
ground surfaces to ensure the encapsulation
of the asbestos impacted soils with geo-fabric.

MANAGEMENT PLAN ASBESTOS AND HAZARDOUS Page 7 of 20


BUILDING MATERIALS
REV DATE: 27/11/2015 REV: 6 DOC ISSUE: 15OCT14 Rev DOC # R8000-WLM-00-MP-MN-00-103
Control Measures Timing Methodology Responsibility Monitoring and Reporting Performance Measure
Excavation of contaminated materials by non -
mechanical means
Asbestos Management Plan, specific to the
location and nature of asbestos to be removed
and incorporating Defence requirements, is to
be developed by suitably qualified and
experienced contamination specialist (See Correct SWMS followed.
Excavation asbestos containing material (ACM is to
be supervised by an asbestos licensed removal At all times Appendix A). SM/ Foreman Daily inspections No non-compliance detected by the
contractor or occupational hygienist. This plan will be reviewed by Defence prior to asbestos licensed removal
commencing asbestos removal works on the contractor.
Project.
Continuous air monitoring to be conducted
during asbestos removal.
Asbestos debris removed via a combination of
emu picking (placing asbestos items into a
Asbestos debris material located on the exposed Correct SWMS followed.
200m thick polythene bag) and raking to be
surfaces of excavated ground surfaces should be
placed into the 200m thick polythene bags it No non-compliance detected by the
dedicated asbestos contaminated zones and At all times SM/ Foreman Daily inspections
should not be more than 50% full. When the asbestos licensed removal
removed via a combination of emu picking and
200m thick polythene bag is 50% full it contractor.
raking.
should be double bagged and sealed air-tight
with industrial tape.
Occupational hygienist will inspect the A clearance certificate will be issued
SM/
Occupational hygienist to provide clearance/ surfaces of the excavated area or ground following a satisfactory result during
As required Occupational Inspections to all areas as required
acceptance of affected areas. surfaces to confirm there is no visually the occupational hygienists
hygienist
identifiable asbestos. inspection.
A geo-textile fabric layer will be laid along the
walls and base of the trench as well as the
ground surfaces to provide an indicative layer
clean fill and asbestos impacted soils.
Certified clean fill such as crushed concrete or
All trenches excavated in asbestos impacted soils for pebble layer should be laid at the base of the Correct SWMS followed.
At all times as trench for the new services to sit on. Clean
new service are to be backfilled with certified clean SM Inspections to all areas as required Certified documentation for clean fill
required validated fill material will be used to the fill and
fill. used.
encapsulate the trench.
The occupational hygienist will inspect
surfaces of the backfilled trench and the
ground surfaces to ensure the encapsulation
of the asbestos impacted soils with geo-fabric.
Asbestos air monitoring and clearance

MANAGEMENT PLAN ASBESTOS AND HAZARDOUS Page 8 of 20


BUILDING MATERIALS
REV DATE: 27/11/2015 REV: 6 DOC ISSUE: 15OCT14 Rev DOC # R8000-WLM-00-MP-MN-00-103
Control Measures Timing Methodology Responsibility Monitoring and Reporting Performance Measure
A hygienist will be required on site to carry out
perimeter and clearance air monitoring and
The hygienist will be required to carry out a full
inspections in accordance with the AMP. The Prior to work Monitoring conducted during all work
visual inspection of the work area prior to the During all asbestos removal works work
hygienist will be required to carry out a full visual commencing. in progress.
commencement of any hazardous materials CM / SM in progress air monitoring should be
inspection of the work area prior to the Ongoing Results available and posted on site.
removal works to ensure containment undertaken
commencement of any hazardous materials removal
measures are satisfactory.
works to ensure containment measures are
satisfactory.
For 2 hours at
initial asbestos
find sampling and Conducted at the perimeter of a nominated
Results to be reported to the Client and Monitoring conducted during all work
Continuous asbestos fibre monitoring will be continuously area as advised by the Environmental
SM made available to relevant sub- in progress.
conducted by a NATA accredited hygienist. during any Consultants and described in the Asbestos
contractors
asbestos removal Management Plan
works

If removal works are not to the


Following the completion of the hazardous materials satisfaction of the hygienist, removal
removal works the hygienist will undertake a At completion of Visual inspection of the asbestos contractors will be required to re- enter
CM / SM satisfactory clearance inspection
thorough visual inspection of the work area and removal work contaminated zone the work area and rectify any issues
transit route. arising from the inspection.

Temporary storage & Disposal


A waste classification of the material will be
undertaken to allow the licensed waste facility to
accept the waste Undertaken by a specialised environmental Results of the waste classification shall be
At all times CM / SM Acceptance by licensed waste facility
consultant provided in a separate document

All asbestos impacted fill leaving site will be


transported in a leak proof covered vehicle
and disposed of at a licensed facility in
accordance with Waste Classification
Materials excavated from the site should be tracked Guidelines
from cradle to grave, in order to provide detailed For any truck leaving the site, the following Daily inspections. No non-conformances from
and accurate information about the location and At all times information would be recorded: CM / SM inspections or rejections of loads
quantity of all materials both on and offsite from the Tracking of trucks or bins leaving site from licensed facility.
time of their excavation until their disposal. Origin of material.
Material type.
Approximate volume.
Truck registration number.

MANAGEMENT PLAN ASBESTOS AND HAZARDOUS Page 9 of 20


BUILDING MATERIALS
REV DATE: 27/11/2015 REV: 6 DOC ISSUE: 15OCT14 Rev DOC # R8000-WLM-00-MP-MN-00-103
Control Measures Timing Methodology Responsibility Monitoring and Reporting Performance Measure

All associated materials including polythene,


Daily inspections. No non-conformances from
At completion of works all asbestos related materials coveralls, geo-fabric and rags must be double
At all times SM inspections or rejections of loads
must be disposed to a licensed facility. wrapped and sealed for disposal as asbestos Tracking of materials or bins leaving site from licensed facility
contaminated waste.
Waste disposal bins provided and marked and
Storage of asbestos, PCBs, Lead-based paints and Waste correctly stored in marked
are lined and sealed prior to removal for
other hazardous building materials must be in At all times SM Weekly inspections bins.
disposal.
dedicated waste disposal bins. No cross contamination of wastes.
SWMS supplied.
Specific procedures for the transport of asbestos,
asbestos, PCBs, Lead-based paints and other Prior to Periodic inspections of transport All transport vehicles covered with
Approved licensed waste transporter used. SM
hazardous building materials must be supplied to LL transportation containers appropriate signage and permits.
Building
Periodic inspections of waste disposal
Specific procedures for the disposal of asbestos,
documentation. Landfill waste dockets provided.
PCBs, Lead-based paints and other hazardous
building materials must be supplied to LL Building Prior to disposal. Approved licensed landfill facility used. SM Suggested verification method of Landfill dockets correspond to
following trucks to the nominated licensed remove waste volumes/types.
.
facility.
Personal decontamination
When leaving the work area all site personnel
must make their way to the nominated
decontamination area, remove their coveralls
and clean their masks and boots using the wet
Personal decontamination must be undertaken each rags. Respirator must remain on during
decontamination and must only be removed The hygienist will be required to carry
time workers leave the asbestos work zone and at
on completion of decontamination. out a full visual inspection of the work
the completion of the asbestos removal work. As detailed in the SWMS
All equipment that is to leave the work area area prior to the commencement of
Personal decontamination should be done within the At all times SM Detailed work method statement to be
must also be decontaminated in the any hazardous materials removal
asbestos work area where re-contamination cannot prepared by sub-contractor
decontamination area with the use of wet works to ensure containment
occur.
rags. measures are satisfactory.
At completion of works all asbestos related
materials including polythene, coveralls, geo-
fabric and rags must be double wrapped and
sealed for disposal as asbestos contaminated
waste.
Plant decontamination
All plant used for the removal of asbestos At competition of At the conclusion of the works the As detailed in the SWMS Landfill waste dockets provided.
contaminated or other hazardous materials must be works or if moved excavators/trucks shall be parked within a SM Detailed work method statement to be Landfill dockets correspond to
decontaminated. off site. designated washing area. Decontamination prepared by sub-contractor remove waste volumes/types.

MANAGEMENT PLAN ASBESTOS AND HAZARDOUS Page 10 of 20


BUILDING MATERIALS
REV DATE: 27/11/2015 REV: 6 DOC ISSUE: 15OCT14 Rev DOC # R8000-WLM-00-MP-MN-00-103
Control Measures Timing Methodology Responsibility Monitoring and Reporting Performance Measure
should include removing all soil from tracks
the body and bucket as far as reasonably
Practicable. The waste soil and water within
the wash area should be removed and
deposited in a truck parked outside the
asbestos zone and disposed of in accordance
with Waste Classification Guidelines

A Project Asbestos Management Plan (AMP) has been developed by the Projects Environmental Consultants, Environmental Earth Science for testing and removal of asbestos in soils, see Appendix A.
This Project AMP has been reviewed and approved for use by Defence.

MANAGEMENT PLAN ASBESTOS AND HAZARDOUS Page 11 of 20


BUILDING MATERIALS
REV DATE: 27/11/2015 REV: 6 DOC ISSUE: 15OCT14 Rev DOC # R8000-WLM-00-MP-MN-00-103
Appendix A
Approved Project Asbestos Management Plan For Asbestos Containing Material in soil

MANAGEMENT PLAN ASBESTOS AND HAZARDOUS Page 12 of 20


BUILDING MATERIALS
REV DATE: 27/11/2015 REV: 6 DOC ISSUE: 15OCT14 Rev DOC # R8000-WLM-00-MP-MN-00-103
REPORT NO. 115042_AMP_Sitewide

ASBESTOS MANAGEMENT PLAN NEW AIR COMBAT


CAPABILITY, RAAF WILLIAMTOWN, NSW

ENVIRONMENTAL EARTH SCIENCES NSW


REPORT TO LEND LEASE
11 AUGUST 2015
VERSION 1
EXECUTIVE SUMMARY
Lend Lease has engaged Environmental Earth Sciences NSW to prepare an asbestos
management plan (AMP) to provide guidance on the control and management of asbestos
containing materials (ACMs) identified on the surface or within soils associated with the New
Air Combat Capability (NACC) construction works, at RAAF Williamtown, NSW (the site).
Please note that this does not relate to asbestos containing materials within structures and
buildings at the site. A plan detailing the site location is presented on Figure 1.

Previous investigations with regard to asbestos have identified some non-friable fibre cement
sheeting and in some instances soils beneath the identified fibre cement sheeting was
sampled and found to contain asbestos considered to be friable.

The scope of the AMP is to address the appropriate handling of asbestos that may exist on
the soil surface or within soil at shallow depths (considered to be up to approximately 3
metres below ground level (mbgl)).

Please note: If any material is encountered that is deemed friable asbestos a contractor with
a friable asbestos removal licence (Class A) will be required. Comcare and WorkCover NSW
notification is mandatory for the removal of any quantity of friable asbestos material. All
relevant permits (including from WorkCover) must be obtained by the licensed removalist
prior to work commencing.

It should be noted that in the event that additional finds of a similar nature are found in the
immediate vicinity and common sense dictates that the material is identical to that which has
already been identified, the material should be managed under this AMP in accordance with
the previous asbestos find.

This AMP has been prepared in general accordance with the following relevant legislation,
codes of practice and guidelines:
National Environment Protection Council (NEPC) (1999) National Environment
Protection (Assessment of Site Contamination) Measure (Amended 2013);
DSRG (2014) Asbestos Management Plan for Defence Estate 2014;
DS-NNSW (2013) Regional Asbestos Management Plan v1.1;
Management and Control of asbestos in Defence Infrastructure and Estate
Infrastructure Division Procedure (V1.0 September 2014);
Safe Work Australia (2011) How to Manage and Control Asbestos in the Workplace;
Safe Work Australia (2011) How to Safely Remove Asbestos Code of Practice;
WorkCover NSW (2014) Managing Asbestos in or on Soil;
NSW Work Health and Safety Act, 2011; and
NSW Work Health and Safety Regulation, 2011.

This AMP details the known existing conditions at the site, guidance for management
measures/procedures, roles and responsibilities and emergency procedures in the event of
unexpected finds.

115042_Sitewide_AMP V1
On behalf of
Environmental Earth Sciences NSW

Project Manager

Senior Environmental Scientist

Project Director

Senior Geologist
115042_Sitewide_AMP

115042_Sitewide_AMP V1
TABLE OF CONTENTS

1 INTRODUCTION & OBJECTIVE ................................................................................. 1

2 FRAMEWORK ............................................................................................................. 1

3 DEFINITIONS .............................................................................................................. 2

4 EXISTING CONDITIONS ............................................................................................. 2

5 FURTHER DELINEATION OF ASBESTOS IN SOIL ................................................... 3

6 MANAGEMENT MEASURES/PROCEDURES ............................................................ 3


6.1 PERSONAL PROTECTIVE EQUIPMENT 4
6.2 EXCLUSION ZONE 5
6.2.1 Plant and machinery 5
6.2.2 Other activities lunch/phone calls 6
6.3 EXCAVATED SOILS, STOCKPILING AND DISPOSAL 6
6.4 MATERIAL MIXED WITH OTHER CONTAMINANTS 6
6.5 SUPERVISION OF EXCAVATIONS 7
6.6 DUST GENERATION 7
6.7 AIR MONITORING 7
6.8 ASBESTOS CLEARANCE INSPECTIONS 8
6.8.1 Friable 8
6.8.2 Non-friable 8
6.9 ACCIDENTS/ INCIDENTS/ NEAR MISS REPORTS 8
6.10 EMERGENCY RESPONSE PLAN 8
6.11 RESIDUAL RISK MANAGEMENT 9

7 REPORTING REQUIREMENTS .................................................................................10

8 ROLES AND RESPONSIBILITIES .............................................................................10


8.1 SITE REPRESENTATIVE 10
8.2 SITE OCCUPANTS 10
8.3 SUBCONTRACTORS 11

9 TRAINING/INDUCTION ..............................................................................................11

10 UNEXPECTED FINDS PROTOCOL ...........................................................................12

11 REVIEW OF AMP .......................................................................................................13

12 CONCLUSION ............................................................................................................13

13 LIMITATIONS .............................................................................................................13

14 REFERENCES............................................................................................................14

FIGURES

115042_Sitewide_AMP V1
1 INTRODUCTION & OBJECTIVE
The purpose of this asbestos management plan (AMP) is to provide guidance on the control
and management of asbestos containing materials (ACMs) identified on the surface or within
soils associated with the New Air Combat Capability (NACC) construction works, at RAAF
Williamtown, NSW (the site). A plan detailing the site location is presented on Figure 1.

The scope of the AMP is to address the appropriate handling of any identified asbestos or
suspected asbestos that may exist on the soil surface or within soil at shallow depths
(considered to be up to approximately 3 metres below ground level (mbgl). It is understood
that asbestos containing materials (ACMs) have been observed intermittently across the
NACC development area (Figure 2), and these have been documented in previous
unexpected findings reports and AMPs (Section 4). In brief, ACMs identified to date have
included non-friable fragments and in some instances friable material within soils. It should
be noted that the degradation of non-friable forms of asbestos is likely to have led to friable
asbestos forms detected within soils.

A copy of the AMP should be provided to site workers or occupants who may disturb the site
during future site activities.

This plan may need to be reviewed, potentially revised and re-issued as changes to the site
conditions occur. This ensures the AMP remains relevant to the site and provides assurance
to all stakeholders and the community that all asbestos issues are addressed adequately.

The objective of the AMP will be to ensure safety of site occupants, workers and the public.

2 FRAMEWORK
The following are relevant legislation, codes of practice and guidelines that have been used
in the preparation of this document:
National Environment Protection Council (NEPC) (1999) National Environment
Protection (Assessment of Site Contamination) Measure (Amended 2013);
DSRG (2014) Asbestos Management Plan for Defence Estate 2014;
DS-NNSW (2013) Regional Asbestos Management Plan v1.1;
Management and Control of asbestos in Defence Infrastructure and Estate
Infrastructure Division Procedure (V1.0 September 2014);
Safe Work Australia (2011) How to Manage and Control Asbestos in the Workplace;
Safe Work Australia (2011) How to Safely Remove Asbestos Code of Practice;
WorkCover NSW (2014) Managing Asbestos in or on Soil;
NSW Work Health and Safety Act, 2011; and
NSW Work Health and Safety Regulation, 2011.

115042_Sitewide_AMP V1 1
3 DEFINITIONS
Asbestos is the term given for a number of naturally occurring fibrous silicate minerals
(SafeWork, 2011). The condition of asbestos is subdivided into two groups;
bonded/ non-friable asbestos (bonded ACM [NEPC, 2013]0; and
Non-bonded/ friable (fibrous and asbestos fines [NEPC, 2013]).

Non- friable asbestos has been defined as any material that contains asbestos in a bonded
matrix (SafeWork, 2011a).

Friable asbestos has been defined as any material that contains asbestos and is in the form
of a powder, or can be crumbled, pulverised or reduced to a powder by hand pressure when
dry (SafeWork, 2011a).

4 EXISTING CONDITIONS
Previous asbestos assessments across the site have identified asbestos containing material
in soils in non-friable and friable forms. Fragments of non-friable asbestos have also been
identified on the soil surface around the site.

The areas of identified ACMs at the time of this document are illustrated on Figure 2. Please
refer to the following documents for further information:
Environmental Earth Sciences (2015) Asbestos Material Inspection Report for a Portion
of the NACC Precinct, RAAF, Williamtown, NSW (ref: 115042_Lt1_EMS letter);
Environmental Earth Sciences (2015a) Asbestos Management Plan Excavation
Works in Vicinity of Previous Asbestos Find - Delta 3, RAAF Williamtown, NSW (ref:
115042_AMP_Delta3);
Environmental Earth Sciences (2015b) NACC Williamtown UFP1 Asbestos
Management Procedures (ref: 115042 UFP1 Letter);
Environmental Earth Sciences (2015c) Asbestos Management Plan Construction
Works South East Runway Works, RAAF Williamtown, NSW (ref:
115042_AMP_SErunway_V3);
Environmental Earth Sciences (2015d) Asbestos Management Plan Excavation
Works Between Buildings 471 and 479, Services Installation Trench, RAAF
Williamtown, NSW (115042_AMP_ATC3);
Environmental Earth Sciences (2015e) Asbestos Management Plan Construction
Works North-West of Control Tower, Services Installation Trench, RAAF Williamtown,
NSW (115042_AMP_trench_V1);
Environmental Earth Sciences (2015f) Asbestos Management Plan Construction
Works at UFP2, Services Installation Trench for New BOM Facilities, RAAF
Williamtown, NSW (ref: 115042_AMP_UFP2);

Based on these reports, the following scenarios for occurrence of asbestos have been
developed and are applicable under this AMP;
friable asbestos in soils;

115042_Sitewide_AMP V1 2
non- friable asbestos in soils; and
non-friable asbestos fragments identified on the soil surface.

5 FURTHER DELINEATION OF ASBESTOS IN SOIL


When asbestos in soil is found to impact an area it may be appropriate to consider
undertaking further assessment in the vicinity of the asbestos find to determine actual
asbestos extent to apply the appropriate management measures. Dependent on specific
information of a particular find such as extent and severity, this will dictate the appropriate
and suitable level of assessment which should be considered. Further assessments which
could be undertaken include:
a detailed site investigation in accordance with NEPC (2013); and
Limited assessment such as a surface inspection in combination with surface soil
sampling.

Please note: If any material is encountered that is deemed friable asbestos a contractor with
a friable asbestos removal licence (Class A) will be required. Comcare and WorkCover NSW
notification is mandatory for the removal of any quantity of friable asbestos material. All
relevant permits (including from WorkCover) must be obtained by the licensed removalist
prior to work commencing.

6 MANAGEMENT MEASURES/PROCEDURES
Based on previous identification of asbestos upon the soil surface or within soils the following
management procedure has been established:
potential ACM identified;
unexpected findings protocol implemented; and
follow Table 1.

115042_Sitewide_AMP V1 3
TABLE 1 MANAGEMENT MEASURES

Non-friable ACM
Non friable fragments
Measures Friable fibres in soil Observed on the
in soil
surface

PPE As per 6.1 - Stage 3 As per 6.1 - Stage 2 As per 6.1 - Stage 1

Exclusion Zone As per 6.2 As per 6.2 N/A

Excavated soils As per 6.3 As per 6.3 As per 6.3

Supervision of
As per 6.4 As per 6.4 As per 6.4
excavations

Dust generation As per 6.5 As per 6.5 N/A

Air monitoring As per 6.6 As per 6.6 As per 6.6

Asbestos clearance
As per 6.7 As per 6.7 As per 6.7
inspections

Accidents/incidents/near
As per 6.8 As per 6.8 As per 6.8
miss reports

Emergency response
As per 6.9 As per 6.9 As per 6.9
plan

Residual risk
As per 5.10 if applicable As per 5.10 if applicable As per 5.10 if applicable
management

6.1 Personal protective equipment


In general, along with standard measures of PPE required for working on defence sites, the
following Stage 1, 2 and 3 PPE measures will be applicable with regard to asbestos.

Any personnel within asbestos work removal areas are to be equipped with adequate
personal protective equipment (PPE). For this site, protective clothing will include but not be
limited to the following:
steel capped boots;
hard-hat;
high visibility vest;
safety glasses;
gloves; and
hearing protection.

Stage 1 PPE Measures


the items listed above plus P2 filter mask.

Stage 2 PPE Measures


the items listed above plus P2 filter mask;

115042_Sitewide_AMP V1 4
disposable gloves; and
disposable coveralls (type 5/6) suitable for asbestos removal or similar to be used as
required.

It is noted that all PPE must also meet Lend Lease and RAAF requirements.

If, after a suitable period of time, the occupational hygienist or environmental consultant is
satisfied that the risk of encountering asbestos materials during the works has been
sufficiently reduced (based on visual observations) the need for Stage 2 PPE measures may
be reconsidered.

Stage 3 PPE Measures


the items listed above as within Stage 1 and 2 PPE measures;
disposable gloves;
half face respirator;
boot covers;
disposable coveralls; and
wet decontamination.

If, after a suitable period of time, the occupational hygienist or environmental consultant is
satisfied that the risk of encountering friable asbestos materials during the works has been
sufficiently reduced (based on visual observations and validation testing) the need for stage
3 PPE measures may be reconsidered.

Suitable decontamination procedures should be employed for individuals to decontaminate


prior to exiting the work area under Stage 3 PPE measures.

6.2 Exclusion zone


In areas where Stage 2 and 3 PPE measures require implementation, an exclusion zone is to
be set up (via temporary fencing) surrounding the works area. This is considered to be
responsibility of the licensed contractor. The exclusion zone should encompass a clearly
delineated area to prevent unauthorised access to the area with appropriate signage erected.

The exclusion zone should contain an access point. Adjacent or near this entry point
suitable disposal bins will be established such that personal protective equipment can be
disposed prior to exiting the exclusion zone. Under stage 3 PPE measures, a
decontamination station should also be set up adjacent or near the entry point.

6.2.1 Plant and machinery


When machinery is utilised for excavation of soil within the exclusion zone, suitable
protection such as filters for cab are required. Detail on specific friable asbestos removal
controls is required to be included within an asbestos removal control plan prepared by the
asbestos removal contractor. It may be necessary to consider a machinery parking area
within the exclusion zone.

Plant or machinery exiting the exclusion zone will be decontaminated prior to exit.

115042_Sitewide_AMP V1 5
6.2.2 Other activities lunch/phone calls
With regard to consideration of other activities such as taking of phone calls or consumption
of food, personnel must exit the exclusion zone adhering to decontamination activities prior
to undertaking the activity.

6.3 Excavated soils, stockpiling and disposal


Potential asbestos contaminated soil upon excavation will be segregated into four categories:
large fragments (>1 cm2) of non-friable asbestos, e.g. fibre cement sheeting;
soil in contact with friable asbestos;
soil in contact with the non-friable asbestos; and
soil observed to be free of asbestos.

Large fragments of non-friable asbestos material such as fibre cement sheeting should be
handpicked, placed within storage bags and double bagged such that ACM is suitably stored.
It should be noted where >10 m2 of non-friable asbestos (i.e. fibres bound in a matrix) is to
be removed then the work must be undertaken by a contractor licensed by WorkCover NSW
to remove non-friable asbestos (Class A or Class B). An application to WorkCover NSW is
also required for the removal of >10 m2 of non-friable asbestos material.

Soil material observed to be in contact with either non-friable or friable asbestos fragments
will be stockpiled and covered, to minimise cross contamination and environmental impacts
on other soil. The stockpile should be covered with HDPE plastic, geofabric or similar type
material to prevent dust blow-off. For soil material underlying the stockpiled material. a
scrape of the stockpile footprint will be required. NOTE: Any covering must be strongly
secured in accordance with specific site protocols.

Soil observed to be free of asbestos can be placed into stockpiles as per normal practice.
The number of stockpiles should be minimised such that trip/fall hazards are minimised, and
do not generate excessive dust.

Following completion of works, all stockpiles may require soil sampling for asbestos and
other potential chemicals of concern to determine appropriate waste classification for off-site
disposal purposes.

6.4 Material mixed with other contaminants


Other identified chemicals of concern have been identified at the site and these are listed in
Environmental Earth Sciences NSW (2015g). Of particular note in relation to this AMP is the
presence of perfluorinated compounds (PFCs), namely perfluorooctane sulfonate (PFOS)
and perfluorooctanoic acid (PFOA). These have been encountered in low concentrations
within soils tested (i.e. below adopted site criteria).

Any material found to be containing these compounds cannot be taken offsite without prior
approval by Lend Lease and the Department of Defence as waste classification guidelines
do not include disposal threshold for these.

115042_Sitewide_AMP V1 6
6.5 Supervision of excavations
During asbestos removal works a competent and appropriately experienced environmental
consultant and/or occupational hygienist should be appointed to oversee the works. This will
include the identification of potential ACM and advice for separating the excavated materials
appropriately.

During asbestos removal works if validation sampling is required (such as under a friable
asbestos removal scenario) an environmental consultant should be engaged to undertake
the validation sampling.

When engagement of a Class A Asbestos Removalist licensed by WorkCover is necessary,


upon engagement, a scope of works should be determined and the removal contractor is to
prepare an asbestos removal control plan. The licensed asbestos removalist must ensure
that the nominated supervisor is present at the site for the removal of any friable asbestos.
The works should be supervised by the licensed contractor in accordance with this Asbestos
Management Plan and their own asbestos removal control plan. All staff involved in the
removal must be suitably qualified to undertake removal works.

6.6 Dust generation


During asbestos removal works within soils, to minimise the potential for fibres to be liberated
from the soil, the soil surface must be wetted down or suitably covered. This includes during
excavation works and for generated stockpiles. During excavation a water-cart or similar
may be used to suppress dust. Over periods of weekends it is envisaged stockpiled material
could be covered with geofabric or similar material.

The use of a vacuum truck may be viable in certain scenarios (non-friable ACM in soil) where
the risk of friable fibre generation is deemed minimal. In any case, consideration of
appropriate waste disposal needs to be undertaken.

6.7 Air monitoring


An occupational hygienist will be appointed during asbestos removal works to carry out
regular air monitoring of the workplace and surrounding areas in accordance with the
Guidance Note on the Membrane Filter Method for Estimating Airborne Asbestos Dust
[NOHSC:3003(2005)] 2nd Edition including but not limited to:
air monitoring at the commencement of work involving excavation and handling of
potentially asbestos contaminated soil on the site;
air monitoring continuously in areas related to asbestos removal works; and
air monitoring for clearance following removal of asbestos or ACM.

Air-monitoring results are to remain below the control levels in designated areas and
monitored by an occupational hygienist. The designated control levels to be adopted are
outlined in the table below. Results are to be reported within 24 hours of sampling and made
available to the site workers undertaking this work.

115042_Sitewide_AMP V1 7
TABLE 2 CONTROL LEVELS FOR AIRBORNE ASBESTOS FIBRES

Control level (airborne fibres/ml) Control action required


<0.01 Continue with control measures
>0.01 Review control measures
Stop removal works, notify WorkCover and identify
>0.02
cause

Under current national and state regulations, the licensed asbestos removalist must notify
WorkCover NSW immediately when and if any respirable asbestos fibres are recorded at an
asbestos removal area that are more than 0.02 fibres/ml.

An area is cleared when the level of airborne asbestos fibres is measured as being below
0.01 fibres/ml.

6.8 Asbestos Clearance Inspections


6.8.1 Friable
Following friable asbestos removal works, an occupational hygienist will undertake a visual
inspection of the site area and undertake clearance air monitoring for the area comprising the
asbestos removal.

6.8.2 Non-friable
Following non-friable asbestos removal, provided air monitoring undertaken during asbestos
removal works has resulted in detections below the accepted level, the asbestos clearance
can be limited to a visual inspection only.

A brief letter documenting the clearance inspection should be provided detailing the results of
air monitoring and/or soil sampling as a record of that the area being cleared.

6.9 Accidents/ incidents/ near miss reports


All accidents, incidents and near misses must be reported to the Site Representative, who
will inform Lend Lease and the Department of Defence (DoD), where appropriate. Every
incident must be investigated and measures implemented to ensure similar situations do not
occur again.

A WorkCover incident notification form must be completed where there is an incident that
results in death or serious injury or any other serious incident that had the potential to cause
serious injury or death.

Failure to notify WorkCover may result in prosecution.

6.10 Emergency response plan


Emergency procedures cover the actions of staff and sub-contractors on site when major
events occur. This should be covered in the asbestos control plan.

115042_Sitewide_AMP V1 8
A major event may include release of asbestos fibres into the air during excavation works.
This may occur through the breaking of asbestos cement sheeting.

It is noted that other emergency events may occur during works, such as fuel spills, fires,
explosions, vehicle/ plant accidents and damage to services. It is outside the scope of this
AMP to outline emergency procedures for these, however it is prudent to consider all
potential emergencies when undertaking excavation works. These should be outlined in
specific safe work method statements.

The first priority must always be the safety of any persons either workers or others involved
in the event. A plan providing clear directions to the nearest hospital with accident and
emergency facilities must be displayed on site along with the numbers and contact names for
the following:
Fire, Police, Ambulance;
Local Fire Brigade;
WorkCover;
Site Representative;
Works Manager;
Environmental Scientist/Occupational Hygienist;
First Aid Officers;
Gas, Water, Electricity;
Poisons;
Doctor; and
Hospital (address details and directions).

Specific emergency procedures for dealing with asbestos should be developed in an


asbestos control plan and should include (but not be limited to):
identifying the emergency and safely raising the alarm;
implementing evacuation procedures as necessary;
minimise the risk of exposure of workers in the vicinity of the emergency;
providing written notification to WorkCover NSW immediately after the emergency and
prior to further work being undertaken.

6.11 Residual risk management


Where potential asbestos containing material is left in place the following management
practices will be required to control residual risk:
the asbestos location will be recorded in the Base Contaminated Site Register (CSR),
enabling further works in this area to be informed of the potential for asbestos
contamination;
it is understood where soil can remain in place and be encapsulated this represents the
most suitable management option as affected soil is at no time presenting a risk of fibre
generation. A risk assessment may be required to ensure encapsulation protects site
occupants and the public; and,

115042_Sitewide_AMP V1 9
develop a management plan for the area in accordance with DSRG Asbestos
management Plan.

7 REPORTING REQUIREMENTS
In the event of asbestos finds which are managed under this AMP, a letter or other
documentation is required to detail the results of air monitoring and/or soil sampling works
associated with the find.

Where an asbestos removal is undertaken a letter may also be required to detail results of
validation sampling which may be necessary to document asbestos removal works.

8 ROLES AND RESPONSIBILITIES

8.1 Site representative


The site representative has the following particular responsibilities under this AMP:
implementation of this AMP by the following measures:
o acknowledge that the AMP is an important document in the management of
potentially contaminated soil and in the reduction of risk to potential site beneficial
users;
o provide this AMP to site visitors and/or sub-contractors;
o review construction plans and method statements as required, to check that
adequate asbestos management measures are incorporated into the planning of
particular construction processes;
ensure that this AMP remains relevant to the site including:
o regular auditing of this AMP as required; and
o maintenance of the document so that it continues to reflect the site conditions,
best practice workplace health and safety recommendations and any changes to
the regulatory framework.

8.2 Site occupants


Site occupants have the following particular responsibilities under this AMP:
notify the site representative of any situation which they consider may represent a
potential health risk (such as unexpected finds);
respond to the directions of the site owner, project manager or other person with
delegated authority with respect to matters relating to potential asbestos contamination;
and
not undertake any works (without the permission of the site representative) which may
cause potential asbestos contamination to be disturbed.

115042_Sitewide_AMP V1 10
8.3 Subcontractors
All subcontractors and suppliers will be required to attend inductions where specific
environmental issues are addressed if deemed appropriate. They will be made aware of
their requirements to adhere to the AMP in the induction program.

All staff involved in the removal must be suitably qualified to undertake removal works.

9 TRAINING/INDUCTION
Prior to commencement of any works in the vicinity of the site relevant parties will be
required to undergo induction for the site. During the induction the AMP should be provided
such that the existence and awareness is noted, along with location it is kept at the site for
future reference. Once provided, a training log should be maintained detailing
individuals/subcontractors working under the AMP.

A copy of a training register is provided in Appendix A.

115042_Sitewide_AMP V1 11
10 UNEXPECTED FINDS PROTOCOL
In the event of an emergency such as significant disturbance or unexpected find of significant
quantity of ACM and/or other contamination, the following procedure should be undertaken.
A copy of the UFP record sheet is provided in Appendix B.

Immediately stop site works

Contact Lend Lease


representative

Construct temporary
barricading to prevent
worker access

Engage environmental
consultant/occupational
hygienist for inspection -
undertake sampling if required

If found to not be If found to present


presenting unacceptable unacceptable human
human health risk: health risk:

Remove Supervise
barricades/controls remediation/removal
undertake validation
if necessary

Remove
barricades/controls

Submit validation
clearance to Lend
Lease representative

115042_Sitewide_AMP V1 12
Contact details for relevant staff are included below.

TABLE 3 EMERGENCY CONTACT NUMBERS

Name/ Role Organisation Contact number


Environmental
Lend Lease
Manager
Project Environmental Earth Sciences
Manager NSW
Occupational
Environmental Monitoring Services
Hygienist

11 REVIEW OF AMP
This AMP must be reviewed as follows (in accordance with WorkCover NSW, 2011):
when there is a change in the control measures;
if asbestos is removed or disturbed;
if a health and safety representative requests a review; and
every five years or less.

12 CONCLUSION
Lend Lease has engaged Environmental Earth Sciences NSW to prepare an asbestos
management plan (AMP) to provide guidance on the control and management of asbestos
containing materials (ACMs) identified on the surface or within soils associated with the New
Air Combat Capability (NACC) construction works, at RAAF Williamtown, NSW (the site).

This AMP details the known existing conditions at the site, management
measures/procedures, roles and responsibilities and emergency procedures in the event of
unexpected finds. It must be read and understood by all workers involved in the
management and removal of asbestos and referred to as needed.

13 LIMITATIONS
This report has been prepared by Environmental Earth Sciences NSW ABN 109 404 006 in
response to and subject to the following limitations:
1. The specific instructions received from Lend Lease Building Pty Ltd;
2. The specific scope of works set out in tender no: 251130-13-18 and PO115059 issued by
Environmental Earth Sciences NSW;
3. May not be relied upon by any third party not named in this report for any purpose except
with the prior written consent of Environmental Earth Sciences NSW (which consent may
or may not be given at the discretion of Environmental Earth Sciences NSW);

115042_Sitewide_AMP V1 13
4. This report comprises the formal report, documentation sections, tables, figures and
appendices as referred to in the index to this report and must not be released to any third
party or copied in part without all the material included in this report for any reason;
5. The report only relates to the site referred to in the scope of works being located at south
east runway extension construction works area, RAAF Williamtown, NSW (the site);
6. The report relates to the site as at the date of the report as conditions may change
thereafter due to natural processes and/or site activities;
7. No warranty or guarantee is made in regard to any other use than as specified in the
scope of works and only applies to the depth tested and reported in this report;
8. Fill, soil, groundwater and rock to the depth tested on the site may be fit for the use
specified in this report. Unless it is expressly stated in this report, the fill, soil and/or rock
may not be suitable for classification as clean fill if deposited off site; and
9. This report is not a geotechnical or planning report suitable for planning or zoning
purposes; and
10. Our General Limitations set out at the back of the body of this report.

14 REFERENCES

Defence Support Operations DS-NNSW Regional Asbestos Management Plan (2012) v1.2
Environmental Earth Sciences (2015) Asbestos Material Inspection Report for a Portion of
the NACC Precinct, RAAF, Williamtown, NSW (ref: 115042_Lt1_EMS letter);
Environmental Earth Sciences (2015a) Asbestos Management Plan Excavation Works in
Vicinity of Previous Asbestos Find - Delta 3, RAAF Williamtown, NSW (ref:
115042_AMP_Delta3);
Environmental Earth Sciences (2015b) NACC Williamtown UFP1 Asbestos Management
Procedures (ref: 115042 UFP1 Letter);
Environmental Earth Sciences (2015c) Asbestos Management Plan Construction Works
South East Runway Works, RAAF Williamtown, NSW (ref:
115042_AMP_SErunway_V3);
Environmental Earth Sciences (2015d) Asbestos Management Plan Excavation Works
Between Buildings 471 and 479, Services Installation Trench, RAAF Williamtown, NSW
(115042_AMP_ATC3);
Environmental Earth Sciences (2015e) Asbestos Management Plan Construction Works
North-West of Control Tower, Services Installation Trench, RAAF Williamtown, NSW
(115042_AMP_trench_V1);
Environmental Earth Sciences (2015f) Asbestos Management Plan Construction Works at
UFP2, Services Installation Trench for New BOM Facilities, RAAF Williamtown, NSW
(ref: 115042_AMP_UFP2);
Environmental Earth Sciences NSW (2015g) Draft: Data review, conceptual site model and
data gaps for redevelopment areas at the New Air Combat Capability (NACC) Facility,
RAAF, Williamtown, NSW (ref: 115042_CSM_draft);
National Environment Protection Council (NEPC) (1999) National Environment Protection
(Assessment of Site Contamination) Measure (Amended 2013)

115042_Sitewide_AMP V1 14
NSW Work Health and Safety Act, 2011
NSW Work Health and Safety Regulation, 2011
National Occupational Health and Safety Commission (NOHSC. 2005) Guidance Note on the
Membrane Filter Method for Estimating Airborne Asbestos Dust [NOHSC:3003(2005)]
2nd Edition
Safe Work Australia (2011a) How to Manage and Control Asbestos in the Workplace
Safe Work Australia (2011b) How to Safely Remove Asbestos Code of Practice
WorkCover NSW (2014) Managing Asbestos in or on Soil
WorkCover NSW (2011) How to manage and control asbestos in the workplace

115042_Sitewide_AMP V1 15
ENVIRONMENTAL EARTH SCIENCES GENERAL
LIMITATIONS
Scope of services
The work presented in this report is Environmental Earth Sciences response to the specific scope of works
requested by, planned with and approved by the client. It cannot be relied on by any other third party for any
purpose except with our prior written consent. Client may distribute this report to other parties and in doing so
warrants that the report is suitable for the purpose it was intended for. However, any party wishing to rely on this
report should contact us to determine the suitability of this report for their specific purpose.

Data should not be separated from the report


A report is provided inclusive of all documentation sections, limitations, tables, figures and appendices and should
not be provided or copied in part without all supporting documentation for any reason, because misinterpretation
may occur.

Subsurface conditions change


Understanding an environmental study will reduce exposure to the risk of the presence of contaminated soil and
or groundwater. However, contaminants may be present in areas that were not investigated, or may migrate to
other areas. Analysis cannot cover every type of contaminant that could possibly be present. When combined
with field observations, field measurements and professional judgement, this approach increases the probability
of identifying contaminated soil and or groundwater. Under no circumstances can it be considered that these
findings represent the actual condition of the site at all points.

Environmental studies identify actual sub-surface conditions only at those points where samples are taken, when
they are taken. Actual conditions between sampling locations differ from those inferred because no professional,
no matter how qualified, and no sub-surface exploration program, no matter how comprehensive, can reveal what
is hidden below the ground surface. The actual interface between materials may be far more gradual or abrupt
than an assessment indicates. Actual conditions in areas not sampled may differ from that predicted. Nothing
can be done to prevent the unanticipated. However, steps can be taken to help minimize the impact. For this
reason, site owners should retain our services.

Problems with interpretation by others


Advice and interpretation is provided on the basis that subsequent work will be undertaken by Environmental
Earth Sciences NSW. This will identify variances, maintain consistency in how data is interpreted, conduct
additional tests that may be necessary and recommend solutions to problems encountered on site. Other parties
may misinterpret our work and we cannot be responsible for how the information in this report is used. If further
data is collected or comes to light we reserve the right to alter their conclusions.

Obtain regulatory approval


The investigation and remediation of contaminated sites is a field in which legislation and interpretation of
legislation is changing rapidly. Our interpretation of the investigation findings should not be taken to be that of
any other party. When approval from a statutory authority is required for a project, that approval should be
directly sought by the client.

Limit of liability
This study has been carried out to a particular scope of works at a specified site and should not be used for any
other purpose. This report is provided on the condition that Environmental Earth Sciences NSW disclaims all
liability to any person or entity other than the client in respect of anything done or omitted to be done and of the
consequence of anything done or omitted to be done by any such person in reliance, whether in whole or in part,
on the contents of this report. Furthermore, Environmental Earth Sciences NSW disclaims all liability in respect of
anything done or omitted to be done and of the consequence of anything done or omitted to be done by the client,
or any such person in reliance, whether in whole or any part of the contents of this report of all matters not stated
in the brief outlined in Environmental Earth Sciences NSWs proposal number and according to Environmental
Earth Sciences general terms and conditions and special terms and conditions for contaminated sites.

To the maximum extent permitted by law, we exclude all liability of whatever nature, whether in contract, tort or
otherwise, for the acts, omissions or default, whether negligent or otherwise for any loss or damage whatsoever
that may arise in any way in connection with the supply of services. Under circumstances where liability cannot
be excluded, such liability is limited to the value of the purchased service.

General Limitations 6 April 2009 Page 1 of 1


FIGURES

115042_Sitewide_AMP V1
Title: Site location

Location: RAAF, Williamtown,


NSW
Client: Lend Lease Job No: 115042
Drawn By: MR Scale: As Shown Source: As shown
Proj Man: MR Date:23 July 2015 Figure 1
Asbestos Material Inspection Report for a Portion
of the NACC Precinct, RAAF, Williamtown, NSW
(Environmental Earth Sciences, 2015)
Non-friable ACM present

NACC Williamtown UFP1 Asbestos Asbestos Management Plan Excavation Works


Management Procedures (Environmental in Vicinity of Previous Asbestos Find - Delta 3,
Earth Sciences NSW, 2015a) RAAF Williamtown, NSW (Environmental Earth
Sciences, 2015a)
Friable and non-friable ACM present
Non-friable ACM present

Asbestos Management Plan Excavation Works


Between Buildings 471 and 479, Services
Installation Trench, RAAF Williamtown, NSW
(Environmental Earth Sciences NSW, 2015d)
Non-friable ACM present

Asbestos Management Plan


Construction Works North-West of
Control Tower, Services Installation
Trench, RAAF Williamtown, NSW
(Environmental Earth Sciences, 2015e)
Non-friable ACM present Asbestos Management Plan Construction
Works South East Runway Works, RAAF
Williamtown, NSW (Environmental Earth
Sciences NSW, 2015c)
Friable and non-friable ACM present
Asbestos Management Plan Construction Works at
UFP2, Services Installation Trench for New BOM
Facilities, RAAF Williamtown, NSW (Environmental
Earth Sciences, 2015f)
Non-friable ACM present

Legend:
Title: Asbestos Findings
Areas tested positive for presence of
asbestos
Location: RAAF, Williamtown,
Site Boundary NSW
0 200 400 Client: Lend Lease Job No: 115042
Note: Locations are approximate Drawn By: AR Scale: As Shown Source: Google
Scale in Metres
Proj Man: MR Date: August 2015 Figure 2
APPENDIX A TRAINING REGISTER

115042_Sitewide_AMP V1
TABLE 1 TRAINING REGISTER

Name of Trainee Date of Course Course Name Description of Course

115042_AMP_SERunway Training Register


APPENDIX B UFP FORM

115042_Sitewide_AMP V1
Unexpected Findings Protocol Form

Site: NACC, RAAF, Williamtown, NSW Job No: 115042 UFP No: ___________

Personnel Onsite: __________________________________________ Date: ___________

Daily Summary
1. Suspect material encountered during daily activities ________________________________
(if yes compete 2 - 8).
2. Environmental Earth Sciences NSW contacted:_________________________________________
3. Record location of foreign material (label occurrences sequentially 1, 2, 3, etc).

Description of material encountered:


4. Asbestos or suspected asbestos containing material present (Yes/No):_____________________
5. If No to 4 is there an obvious odour present (Note: Do Not sniff soil) (Yes/No):______________
6. Visible staining (Yes/No): _______________________________________________
7. Brief written description:

8. Material quarantined (Yes/No): ________________________________

9. Location of contaminated material: _________________________


10. Attach photographs taken _________ _

Signature: ________________________________________________________________________________

115042 UFP Form Template 1


Insert Photograph or Draw Sketch

115042 UFP Form Template 2


Appendix B Hazardous Materials Register

MANAGEMENT PLAN ASBESTOS AND HAZARDOUS Page 13 of 20


BUILDING MATERIALS
REV DATE: 27/11/2015 REV: 6 DOC ISSUE: 15OCT14 Rev DOC # R8000-WLM-00-MP-MN-00-103
MANAGEMENT PLAN ASBESTOS AND HAZARDOUS Page 14 of 20
BUILDING MATERIALS
REV DATE: 27/11/2015 REV: 6 DOC ISSUE: 15OCT14 Rev DOC # R8000-WLM-00-MP-MN-00-103
MANAGEMENT PLAN ASBESTOS AND HAZARDOUS Page 15 of 20
BUILDING MATERIALS
REV DATE: 27/11/2015 REV: 6 DOC ISSUE: 15OCT14 Rev DOC # R8000-WLM-00-MP-MN-00-103
MANAGEMENT PLAN ASBESTOS AND HAZARDOUS Page 16 of 20
BUILDING MATERIALS
REV DATE: 27/11/2015 REV: 6 DOC ISSUE: 15OCT14 Rev DOC # R8000-WLM-00-MP-MN-00-103
MANAGEMENT PLAN ASBESTOS AND HAZARDOUS Page 17 of 20
BUILDING MATERIALS
REV DATE: 27/11/2015 REV: 6 DOC ISSUE: 15OCT14 Rev DOC # R8000-WLM-00-MP-MN-00-103
MANAGEMENT PLAN ASBESTOS AND HAZARDOUS Page 18 of 20
BUILDING MATERIALS
REV DATE: 27/11/2015 REV: 6 DOC ISSUE: 15OCT14 Rev DOC # R8000-WLM-00-MP-MN-00-103
MANAGEMENT PLAN ASBESTOS AND HAZARDOUS Page 19 of 20
BUILDING MATERIALS
REV DATE: 27/11/2015 REV: 6 DOC ISSUE: 15OCT14 Rev DOC # R8000-WLM-00-MP-MN-00-103
MANAGEMENT PLAN ASBESTOS AND HAZARDOUS Page 20 of 20
BUILDING MATERIALS
REV DATE: 27/11/2015 REV: 6 DOC ISSUE: 15OCT14 Rev DOC # R8000-WLM-00-MP-MN-00-103

Das könnte Ihnen auch gefallen