Beruflich Dokumente
Kultur Dokumente
Rigid pavements are generally used in constructing airports and major highways, such as
those in the interstate highway system. In addition, they commonly serve as heavy-duty
industrial floor slabs, port and harbor yard pavements, and heavy-vehicle park or terminal
pavements. Like flexible pavements, rigid highway pavements are designed as all-
weather, long-lasting structures to serve modern day high-speed traffic. Offering high
quality riding surfaces for safe vehicular travel, they function as structural layers to
distribute vehicular wheel loads in such a manner that the induced stresses transmitted to
the subgrade soil are of acceptable magnitudes.
Portland cement concrete (PCC) is the most common material used in the construction of
rigid pavement slabs. The reason for its popularity is due to its availability and the
economy. Rigid pavements must be designed to endure frequently repeated traffic
loadings. The typical designed service life of a rigid pavement is between 30 and 40
years, lasting about twice as long as a flexible pavement.
One major design consideration of rigid pavements is reducing fatigue failure due to the
repeated stresses of traffic. Fatigue failure is common among major roads because a
typical highway will experience millions of wheel passes throughout its service life. In
addition to design criteria such as traffic loadings, tensile stresses due to thermal energy
must also be taken into consideration. As pavement design has progressed, many highway
engineers have noted that thermally induced stresses in rigid pavements can be just as
intense as those imposed by wheel loadings. Due to the relatively low tensile strength of
concrete, thermal stresses are extremely important to the design considerations of rigid
pavements.
Rigid pavements are generally constructed in three layers - a prepared subgrade, base or
subbase, and a concrete slab. The concrete slab is constructed according to a designed
choice of plan dimensions for the slab panels, directly influencing the intensity of thermal
stresses occurring within the pavement. In addition to the slab panels, temperature
1
reinforcements must be designed to control cracking behavior in the slab. Joint spacing is
determined by the slab panel dimensions.
Three main types of concrete pavements commonly used are Jointed plain concrete
pavement (JPCP), jointed reinforced concrete pavement (JRCP), and continuously
reinforced concrete pavements (CRCP). JPCPs are constructed with contraction joints
which direct the natural cracking of the pavement. These pavements do not use any
reinforcing steel. JRCPs are constructed with both contraction joints and reinforcing
steel to control the cracking of the pavement. High temperatures and moisture stresses
within the pavement creates cracking, which the reinforcing steel holds tightly together.
At transverse joints, dowel bars are typically placed to assist with transferring the load of
the vehicle across the cracking. CRCPs solely rely on continuous reinforcing steel to
hold the pavements natural transverse cracks together. Prestressed concrete pavements
have also been used in the construction of highways; however, they are not as common as
the other three. Prestressed pavements allow for a thinner slab thickness by partly or
wholly neutralizing thermally induced stresses or loadings.
2
Elements of a Typical Rigid Pavement
i) Subgrade
Subgrade is the in situ soil over which the pavement structure is supported.
o Stiffness of the subgrade is measured by modulus of subgrade reaction
(K).
o K is determined with the assumption that the slab is resting on dense fluid
and thus the reactive pressure of soil on pavement is linearly proportional
to the deflection of the slab.
o Value of K is widely dependant upon the soil type, soil density, and
moisture content.
o K is determined by plate bearing test.
ii) Sub-Base
Sub-base is the layer of selected granular materials placed on the subgrade soil
and immediately below the concrete pavement
o It is provided for the following purposes
o To provide an uniform and reasonable firm pavement support.
o To prevent mud pumping.
o To provide levelling course on undulated and distorted subgrade.
o To act as capillary cut off.
It is not a part of the rigid pavement structure as it is not provided to impart
strength to the pavement structure.
Construction of subbase is generally done by
3
o Granular material like natural gravel, crushed slag, crushed concrete, brick
metal, laterite, soil aggregate etc.
o Granular construction like WBM or WMM
o Stabilized soil
o Semi rigid material like Lime clay Puzzolana Concrete, Lime Flyash
Concrete, Dry Lean Concrete.
4
RIGID PAVEMENTS
Rigid pavements have sufficient flexural strength to transmit the wheel load stresses to a
wider area below. A typical cross section of the rigid pavement is shown in Figure 1.
Compared to flexible pavement, rigid pavements are placed either directly on the
prepared sub-grade or on a single layer of granular or stabilized material. Since there is
only one layer of material between the concrete and the sub-grade, this layer can be
called as base or sub-base course.
In rigid pavement, load is distributed by the slab action, and the pavement behaves like
an elastic plate resting on a viscous medium (Figure 2). Rigid pavements are constructed
by Portland cement concrete (PCC) and should be analyzed by plate theory instead of
layer theory, assuming an elastic plate resting on viscous foundation. Plate theory is a
simplified version of layer theory that assumes the concrete slab as a medium thick plate
which is plane before loading and to remain plane after loading. Bending of the slab due
to wheel load and temperature variation and the resulting tensile and flexural stress.
5
Figure 3: Deflection on concrete pavement
6
1. Jointed Plain Concrete Pavement:
Jointed plain concrete pavement (JPCP) uses contraction joints to control cracking and
does not use any reinforcing steel. Transverse joint spacing is selected such that
temperature and moisture stresses do not produce intermediate cracking between joints.
This typically results in a spacing no longer than about 6.1 m (20 ft.). Dowel bars are
typically used at transverse joints to assist in load transfer. Tie bars are typically used at
longitudinal joints.
Jointed Plain Concrete Pavement (JPCP) are plain cement concrete pavements
constructed with closely spaced contraction joints. Dowel bars or aggregate interlocks are
normally used for load transfer across joints. They normally has a joint spacing of 5 to
10m.
7
Properties
Crack Control
Contraction joints, both transverse and longitudinal
Joint Spacing
Typically between 3.7 m (12 ft.) and 6.1 m (20 ft.). Due to the nature of concrete, slabs
longer than about 6.1 m (20 ft.) will usually crack in the middle. Depending upon
environment and materials slabs shorter than this may also crack in the middle.
Reinforcing Steel
None.
Load Transfer
Aggregate interlock and dowel bars. For low-volume roads aggregate interlock is often
adequate. However, high-volume roads generally require dowel bars in each transverse
joint to prevent excessive faulting.
Other Info
A majority of U.S. State DOTs build JPCP because of its simplicity and proven
performance.
8
2. Jointed Reinforced Concrete Pavement:
Although reinforcements do not improve the structural capacity significantly, they can
drastically increase the joint spacing to 10 to 30m. Dowel bars are required for load
transfer. Reinforcements help to keep the slab together even after cracks.
Properties
Crack Control
Contraction joints as well as reinforcing steel.
9
Joint Spacing
Longer than JPCP and up to a maximum of about 15 m (50 ft.). Due to the nature of
concrete, the longer slabs associated with JRCP will crack.
Reinforcing Steel
A minimal amount is included mid-slab to hold cracks tightly together. This can be in the
form of deformed reinforcing bars or a thick wire mesh.
Load Transfer
Dowel bars and reinforcing steel. Dowel bars assist in load transfer across transverse
joints while reinforcing steel assists in load transfer across mid-panel cracks.
Other Info
During construction of the interstate system, most agencies in the Eastern and
Midwestern U.S. built JRCP. Today only a handful of agencies employ this design
(ACPA, 2001[1]).
In general, JRCP has fallen out of favor because of inferior performance when compared
to JPCP and CRCP.
10
3. Continuous Reinforced Concrete Pavement:
During the 1970s and early 1980s, CRCP design thickness was typically about 80
percent of the thickness of JPCP. However, a substantial number of these thinner
pavements developed distress sooner than anticipated and as a consequence, the current
trend is to make CRCP the same thickness as JPCP (FHWA, June 1990[2]). The
reinforcing steel is assumed to only handle nonload-related stresses and any structural
contribution to resisting loads is ignored.
11
4. Jointed Reinforced Concrete Pavement (JRCP)
12
5. Roller-compacted concrete (RCC) pavement
Roller-compacted concrete (RCC) pavements are a type of concrete pavement that do not
include embedded steel or load transfer devices and typically is not jointed due to its
method of placement. Load transfer is provided in an RCC pavement by way of enhanced
aggregate interlock developed due to the compaction of the fresh RCC in addition to an
optimized aggregate gradation that includes a higher percentage of fine aggregates
relative to conventional paving concrete. The strength development is much quicker
relative to conventional paving concrete (see figure to the right) due to the enhanced
aggregate interlock provided by a dense, well-graded aggregate gradation. The dry nature
of RCC, along with its dense aggregate gradation, allows the pavement to be compacted
using vibratory rollers. It is typically specified that within 45-60 minutes of mixing, final
compaction should be completed.
Additionally, RCC is unlike the other concrete pavement types because it is placed using
a paver (which could be a high density paver or a typical paver used for asphalt paving)
and compacted with rollers similar to the process of asphalt paving.
13
Failure Criteria of Rigid Pavements
Traditionally fatigue cracking has been considered as the major, or only criterion for rigid
pavement design. The allowable number of load repetitions to cause fatigue cracking
depends on the stress ratio between flexural tensile stress and concrete modulus of
rupture. Of late, pumping is identified as an important failure criterion. Pumping is the
ejection of soil slurry through the joints and cracks of cement concrete pavement, caused
during the downward movement of slab under the heavy wheel loads. Other major types
of distress in rigid pavements include faulting, spalling, and deterioration.
14
Problems
1. The thin layer of bitumen coating between an existing bituminous layer and a new
bituminous layer is:
a. Seal coat
b. Intermediate coat
c. Tack coat
d. Prime coat
2. Rigid pavements are designed by
a. Rigid plate theory
b. Elastic plate theory
c. Infinite layer theory
d. Interlocking of aggregates
15
Solutions
1. The thin layer of bitumen coating between an existing
bituminous layer and a new bituminous layer is:
a. Seal coat Intermediate coat
b. Tack coat
c. Prime coat
e. Rigid pavements are designed by
a. Rigid plate theory
b. Elastic plate theory
c. Infinite layer theory
d. Interlocking of aggregates
16
Westergaard Analysis
H. M. Westergaard is considered to be pioneer person in rigid pavement design.
The basic assumptions in Westergaard (1925) analysis for computation of stresses
are
o Concrete slab acts as a homogenous, isotropic, and elastic solid in
equilibrium.
o The reaction of subgrade are vertical only and they are proportional to the
deflection of the slab. This reaction of subgrade per unit area at any given
point is equal to a constant K multiplied by the deflection at that point.
o The thickness of the slab is uniform.
o The load at the interior and at the corner of the slab is distributed
uniformly over a circular area of contact.
o For corner loading the circumference of the area of contact is tangential to
the edge of the slab.
o For the load at the edge of the slab is uniformly distributed over a semi
circular area contact. The diameter of the semicircle is with the edge of
the slab.
17
Figure 8: Critical Stress Locations
18
The resistance to deformation depends on the stiffness of the supporting medium
as well as on the flexural stiffness the slab.
This pressure deformation characteristics of rigid pavement lead Westergaard to
define the term radius of relative stiffness (l). l in cm is given by
19
Critical Combination of Stresses
The rigid pavement slab is deliberately divided into blocks of appropriate sizes in
order to take care the effects of temperature friction stress or stresses due to
moisture variation.
These deliberate planes of weaknesses in the slab are known as joints. A good
joint should have the following functional requirements:
Must be waterproof [proper sealing to be provided]
Riding quality should not be deteriorated
Should not make any structural weakness [for example staggered joints should be
avoided]
20
Joints in Rigid Pavement
21
Overview
As the name implies, rigid pavements are rigid i.e, they do not
22
taken as 0.125 cm and is the pressure sustained by the rigid
(1)
grade reaction.
23
Critical load positions
Since the pavement slab has finite length and width, either the
(2)
24
Wheel load stresses -
Westergaard's stress
equation
(3)
(4)
25
(5)
resisting section in cm
Temperature stresses
26
overall change in the slab temperature. The former results in
Warping stress
equation - .
(6)
(7)
(8)
27
where is the modulus of elasticity of concrete in kg/cm (3
Frictional stresses
(9)
28
Combination of stresses
given by
Design of joints
Expansion joints
29
design involves finding the joint spacing for a given
IRC)
Contraction joints
(10)
30
where, is the allowable stress in tension in cement
taken as 1.5.
Dowel bars
between two concrete slabs and to keep the two slabs in same
31
Mild steel rounded bars,
Bradbury's analysis
(11)
(12)
(13)
32
Design procedure
(14)
(15)
stiffness.
33
Assume a linear variation of capacity factor of 1.0 under
load to 0 at .
capacity factor.
Example
100 respectively.
34
Solution:
Given, , , , ,
, and ; and
assume diameter.
35
, So, provide long and
. Therefore .
Actual capacity is
36
Therefore assume spacing and now the actual capacity is
center to center.
Tie bars
devices, but serve as a means to tie two slabs. Hence tie bars
longitudinal joints.
37
Step Diameter and spacing: The diameter and the spacing is
total tensile stress for a unit length (one meter). Hence the
(16)
the design.
Step Length of the tie bar: Length of the tie bar is twice the
38
(17)
and .
Example
. Step 1: diameter
39
Assume . Therefore spacing is
from
Summary
40
design, a combination of load stress, frictional stress and
Problems
2. Design the length and spacing of tie bars given that the
41
working tensile stress in steel is 1750 , and bond
Solutions
1. Given, , , , ,
, and ;
42
Solving for by trial and error, it is =39.5cm Minimum
equation)
43
Step-3 : Find the required spacing: Effective distance of
spacing,
Actual capacity is
44
So we should consider 2.52>2.335 as it is greater and
. Step 1:
bar:
45
[Ans] Use tie bars of length of
Example
Design a new rigid pavement for a major interstate highway using the following
46
Investigate three levels: R = 90%, R = 95%, R = 99%. This
Interstate highways.
o: 0.40
Drainage coefficient
1.0 (usually assumed if no better data exist)
(Cd):
Loss of support: 1.0
Single unit trucks (assume 0.34 ESALs per truck) = 1872/day
Solution
By looking at several different design periods and reliability levels this example gives an
idea of the relative influence of these inputs. Work can be verified by using the Rigid
This step involves converting the daily traffic volume into an annual ESAL amount.
Pavements are typically designed for the critical lane or design lane, which accounts
47
Total = 887,878 ESALs/yr
Rounded total = 890,000 ESALs/yr
Design ESALs
This calculation is a multi-step process In the 1993 AASHTO Guide for Design of
48
1. Determine the roadbed resilient modulus and the subbase elastic modulus and use
2. Modify this k: to account for the effects of a rigid foundation near the surface. The
idea here is that the subgrade will offer greater support if a rigid foundation (such
month.
4. Using a projected slab thickness and a modulus of subgrade reaction that has been
modified to account for the effects of a rigid foundation near the surface, use a
graph to determine the relative influence the various k-values throughout the year
are potentially more damaging than higher values of k, indicating more support.
weighted average.
5. Correct the weighted average k-value to account for the potential loss of support
arising from subbase erosion. Subbase materials that are more prone to eroding
The 1993 AASHTO Guide for Design of Pavement Structures and its associated graphs
are needed to carry out this procedure because most steps involve graphical solutions.
Although these graphs are not reproduced here, a summary results table is shown below.
49
Relative Damage
Month MR Subbase MR Composite k
(ur)
86 MPa (12,500 3,447 MPa (500,000
January 950 95
psi) psi)
86 MPa (12,500 3,447 MPa (500,000
February 950 95
psi) psi)
86 MPa (12,500 3,447 MPa (500,000
March 950 95
psi) psi)
86 MPa (12,500 3,447 MPa (500,000
April 1,000 92
psi) psi)
103 MPa (15,000 3,447 MPa (500,000
May 1,000 92
psi) psi)
103 MPa (15,000 3,447 MPa (500,000
June 1,000 92
psi) psi)
103 MPa (15,000 3,447 MPa (500,000
July 1,000 92
psi) psi)
103 MPa (15,000 3,447 MPa (500,000
August 1,000 92
psi) psi)
103 MPa (15,000 3,447 MPa (500,000
September 1,000 92
psi) psi)
103 MPa (15,000 3,447 MPa (500,000
October 950 92
psi) psi)
86 MPa (12,500 3,447 MPa (500,000
November 950 95
psi) psi)
86 MPa (12,500 3,447 MPa (500,000
December 950 95
psi) psi)
50
average relative damage =
Based on Figure 3.5 in the 1993 AASHTO Guide for Design of Pavement Structures, k
980.
Based on Figure 3.6 in the 1993 AASHTO Guide for Design of Pavement Structures a
Using the previously calculated ESAL results and the 1993 AASHTO empirical rigid
pavement design equation the following pavement thickness designs can be calculated:
Layer Thickness
Design Design Period Pavement
Reliability = Reliability = Reliability =
Period ESALs Layer
90% 95% 99%
PCC Surface 280 mm 305 mm 330 mm
51
Course (4 inches) (4 inches) (4 inches)
Crushed Stone 135 mm 135 mm 135 mm
In this particular example, which only shows one set of possible solutions, the HMA base
course and crushed stone subbase course layer depths were kept constant and the PCC
surface course depth was varied depending upon requirements. Notice that a change in
reliability level from 90% to 99% results in a PCC slab thickness increase of about 50
mm (2 inches). The 380 mm (15 inch) thick slab shown for the 40-year design (99%
reliability) is probably near the maximum practical slab thickness for highway
pavements.
52
CONSTRUCTION OF RIGID PAVEMENT
7.0 INTRODUCTION
Cement concrete roads are very high standard. They are costliest than all
other types of roads. These roads provide excellent riding surface and pleasing
appearance. They are called rigid pavements because they do not allow any
flexibility.
their long span of life, excellent riding surface and negligible maintenance cost,
they prove cheaper than bitumen roads. Moreover engineers have more
confidence in cement concrete material and they also like to construct these
roads.
concrete roads:
Advantages
53
a. They provide excellent smooth surface for driving.
f. Even after their span of life, they can be used as base course and
i. Working with cement concrete is much easier and safer than with
bituminous materials.
resistance.
k. In high class cement concrete roads heavy rollers are not required
for compaction.
grades.
Disadvantages
54
b. Lots of joints are to provide which prove additional places of
weakness.
opened to traffic.
roads.
Cement concrete roads can be of following types. Out of all these types,
cement concrete slab roads, are most commonly used, and hence construction
e. Crete-ways.
55
a. Cement Concrete Slab Pavements.
base and consolidated with the help of vibrators or tamper and surface
finished smooth.
reconditioned to correct grade and profile and a loose layer of road metal
about 10 cm. Minimum size of coarse aggregate should not be less than
layer.
56
Cement and sand are taken in ration of about 1:2 and grout is
having one bag cement, requires about 35 liters water to form a fluid
lightly rolled macadam layer and allowed to seep into the voids
to smoothen the top finished surface and also to help rolling so that grout
for trueness, camber and profile. The surface is lastly cured as usual.
which is laid on the prepared sub grade of sub base and rolled with light
roller just like Water Bound Macadam Road construction. Rolling operation
should be finished before the final setting time of the cement. Curing has
57
d. Cement Bound Macadam Sandwich Type
stabilized soil base are used as foundation or base. The base layer is
about 5 cm. Cement and sand are taken ratio of 1:2 and a stiff mortar is
layer. Now lay an other layer of coarse aggregate of the same size and
After spreading the second layer of coarse aggregate over stiff mortar
layer, rolling is done using heavy roller about 12 ton. By rolling, the mortar
(one layer above and another below mortar layer) and about 10 cm thick
the surface. After rolling, the surfacing is finished and checked for camber
58
exhibit rough texture on the surface and hence are useful in hilly areas,
where gradients are steep and other types of roads become slippery and
e. Crete-ways
Crete ways are track ways made with the help of cement concrete.
thought that if only that portion of the road is treated with concrete where
wheels of cart are to move lot of savings can be affected because width of
1.5 meters are constructed. The space between strips is left untreated or
may be treated with very inferior type of material. Thickness of strip may
Crete ways strips may be pre cast and then laid on the prepared
site, just in the same way as ordinary cement concrete roads. Crete ways
so get down crete way strips. Getting down and coming up, the
59
crete way is very difficult, since space between strips and out
side the strips is soft and bullock carts get entrenched in it.
c. In dry weather, loose soil from kutcha space is blown off and a
central part of the road is made from asphalt or bitumen surfacing, for use
of motor traffic, and on both of its sides there may be crete ways for
carrying bullock carts traffic. Such road in which some width is made from
60
STRUCTURAL PARTS OF CEMENT CONCRETE
ROADS AND CONSTRUCTION
Cement concrete
pavement
Sub grade
Figure 8.1
Sub grade is concerned its most important property is not the actual
strength but uniformity of support. Sub base course of concrete road may be
made of Water Bound Macadam, granular material, or stabilized soil. In the case
of Water Bound Macadam base, thickness should be at least 15 cm and any new
layer of sub base should have been under traffic for some days to get properly
compacted.
61
a. Alternate bay system
b. Continuous construction.
one lane, full width is adopted as one longitudinal strip, but in the case of
more than one lane width, each lane is adopted as one longitudinal strip.
In short, the road surface is divided into panels. After this cement
so. After a lapse of about one weak, remaining left out bays are also filled
draw backs:
62
i. A large number of joints are developed which
easily constructed. Figure 8.2 shows formation of bays on the surface of the
road. A, B, C bays are filled first and A, B, C bays subsequently after a laps of
63
Longitudinal Joint Transverse Joint
A B C
C
A B C
Figure 8.2
b. Continuous Construction
constructed without any break. Width of the strip is generally kept one
lane. This method also helps in marking the traffic lanes after completion,
since longitudinal joints will demarcate the limit of each lane. The
construction joints are provided at the end of the days work. This method
64
be adopted for construction at a time and remaining
diversion.
Slab to be laid
PAVEMENTS.
c. Fixing of farm.
65
i. Curing.
directly be laid over the prepared sub grade. The top 15 cm layer of the
3 m length. Sub grade should be prepared and checked at least two days
paper then even concrete can be laid directly over the soil sub grade.
sub grade.
concrete slab.
66
v. If water proof paper is to be laid directly over the sub
the pavement is very heavy, a 15 cm thick sub base layer may be used
over the prepared sub grade before lying of cement concrete slab. The
Bound Macadam.
67
From i to v, all the points are for new constructions and can be
adopted as per design requirements. But vi and vii points are for existing
Concrete should not be laid on black topped surfaces having soft spots
rutted badly under traffic. In such cases entire surfacing material should
c. Fixing Of Forms.
68
Forms may be made from mild steel channel sections or wooden
planks. Depth of the forms should be equal to the thickness of the slab to
forms should be dress on one side and should have a minimum base
aggregates are batched in weigh batching plant and put into the hopper of
counted after all the materials have been put into the mixer.
69
Channel
Spike of
Needles
A A
PLAN
Prepared Sub-
grade
Section at A-A
slab. While being placed, the concrete should be rodded so that the
should be particularly well placed and tapped against the forms and along
70
f. Compaction And Finishing
done using tampers. Hand tamper is also known as hand tamping beam. It
tamping beam should be equal to the width of the slab plus 30 cm. A steel
plate is fixed at the under side of this beam. Tamper is used by placing it
on the side forms. Tampers are lifted and dropped to affect compaction.
float is worked longitudinally with sawing motion from one edge of the
pavement to the other edge. After this operation, excess water gets
disappeared but while concrete is still plastic; the surface of the slab
71
h. Belting and Edging
wide and at least 1 m longer than the width of the slab. The belt is worked
strokes.
surface, the pavement is given a broomed finish with an approved steel or fiber
broom not less than 45 cm wide. The broom should be pulled gently over the
surface of the pavement from edge with each stroke slightly over lapping the
adjacent one.
After belting and brooming and before the concrete has taken initial
set, the edges of the slab should be carefully finished with an edger of 6
mm radius.
25 CM
ELEVATION
10 CM
PLAN
72
i. Curing
concrete should be covered against rapid drying with wetted burlap, cotton
or jute mat. Covering operation with wet burlap is known as initial curing.
Burlap curing is carried out for at least two days. After this, wet burlaps are
removed and surface is covered either with damp saturated sand or with
immediately after finishing of the surface and before the set of the cement
has taken place. If the pavement is first covered with burlap it may be
applied upon removal of the burlap. This method of curing can be adopted
This check is done after curing period when curing sand has been
removed from the surface. Undulations in the surface should not exceed 6
mm in length of 3 m.
73
Forms should be removed after a lapse of about 12 hours from
After curing period, and before the pavement is opened to traffic, all
74
7.5 JOINTS IN CEMENT CONCRETE ROADS
of the cement concrete roads. Tie bars and dowel bars are provided to maintain
the strength of the pavement at the joints and also to act as load transfer
headings:
a. Expansion joints
b. Contraction joints
Expansion joints provide space into which pavement can expand. These
75
Warping joints relieve stresses due to warping effect develops in the slab.
These joints are commonly used for longitudinal joints dividing the pavement into
lanes. Warping tendencies are set up in the concrete slab due to temperature
difference between top and bottom of the slab. At 12 noon the temperature at the
top surface of the slab will be higher than that at the bottom. This causes top
fibres of the slab to expand by larger amount than the bottom fibres and slab
warps down wards at the edges. Similarly at 12 night, the temperature of the
bottom of the slab is higher than the temperature at the top of the slab and slab
warps upwards at the edges. Weight of the slab tries to prevent this warping of
the slab and thus warping stresses are set up. Intensity of warping stress is
perpendicular to the alignment of the road are termed as transverse joints. Joints
a. Tranverse Joints
skew. All these arrangements are shown in figure below. Out of these
Cracks
Tie Bars
sympathetic cracks are developed in the adjoining longitudinal strip just in front of
77
transverse joints already provided skew arrangement should not be adopted
because in this case acute corners generally get crushed away. Transverse joints
i. expansion joints
b. Longitudinal Joints.
have been used for all the process involved in concreting and at the time,
steel T-iron to the depth varying from 1/3 to 1/6 of the depth of the slab.
These joints may be plain butt type or butt with tie bars in them. Tie bars
should be bonded in the slabs across longitudinal joints and whilst casting
the first slabs thay may be bent so that one end of them lies along the
forms. After removal of the forms, bars should be straightened so that they
may extend into the concrete placed on the other side of the joint.
78
Tongued and grooved joints are also sometimes used as the longotidinal
joints.
Joints are place where continuity of the concrete slabs is broken. These
joints if not filled with proper material and allowed to remain open, grit may be
filled in them and subsequently during hot day, the slab may be pushed apart due
to expansion in the slab. Expansion not being allow at the joint due to muck filled
in it. During rains, water will infiltrate through joints into the soil sub grade thus
damaging it. This also results in mud pumping, specially where sub-grade is
Due to above mentioned difficulties; the joints must be filled with such a
material which is compressible, elastic and durable. A material, which is used for
filling the joints, is known as fillers. Some depth at the top of the joints is filled
with a material which could seal the joints completely against the entrance of
water. The material which is used for sealing the joint is known as sealer.
79
a. cork or cork bound with bitumen
b. soft wood
original thickness after three cycles of applying and removing the load. Also when
compressed to 50 % thickness, the free edge of the filler should not extrude by
more than 6.5 mm, when all other three edges are restrained.
compound. Rubber bitumen compound, air blown bitumens etc. can also be
used.
Sealer
3. During cold night, the edges of
the pavements move back due
80 gap will
to contraction and open
formed.
Joint Filler Sealer
Oughing Out
Sealer
Broken
Similarly, due to increase gap, sealing film will become thin. If sealer
poor, it may crack as shown above. So, if defective materials have been used as
fillers and sealers, the difficulty shown above may arise and render the joint
permeable, through which water or other foreign matter may enter the gap and
ACTIVITY 7
TEST YOUR UNDERSTANDING BEFORE YOU CONTINUE WITH THE NEXT
INPUT
Question
81
1. State three types of cement concrete roads.
a. _____________________________
b. _____________________________
c. _____________________________
FEEDBACK ON
ACTIVITY 7
82
Answer
1.
stages:
c. Fixing of farm.
i. Curing.
83
84
Question
85
Answer
the slab. These joints are commonly used for longitudinal joints
the slab will be higher than that at the bottom. This causes top
fibres of the slab to expand by larger amount than the bottom fibres
and slab warps down wards at the edges. Similarly at 12 night, the
86
temperature of the bottom of the slab is higher than the
temperature at the top of the slab and slab warps upwards at the
edges. Weight of the slab tries to prevent this warping of the slab
and thus warping stresses are set up. Intensity of warping stress is
directly be laid over the prepared sub grade. The top 15 cm layer of
laid directly over the soil sub grade. Prepared sub grade should
sub grade.
concrete slab.
87
vii. Minimum modulus of sub grade reaction obtained with
88
ADVANTAGES OF RIGID PAVEMENT
89
DISADVANTAGES OF RIGID PAVEMENT
90
CONCLUSION
Rigid pavements are generally used in constructing airports and major highways, such as
those in the interstate highway system. In addition, they commonly serve as heavy-duty
industrial floor slabs, port and harbor yard pavements, and heavy-vehicle park or terminal
pavements. Like flexible pavements, rigid highway pavements are designed as all-
weather, long-lasting structures to serve modern day high-speed traffic. Offering high
quality riding surfaces for safe vehicular travel, they function as structural layers to
distribute vehicular wheel loads in such a manner that the induced stresses transmitted to
the subgrade soil are of acceptable magnitudes.
91
REFERENCES
Websites:
www.wikipedia.com
www.scribd.com
www.seminarprojects.com
92